CN109505416A - A kind of mountable double-deck column lifting bracing means - Google Patents

A kind of mountable double-deck column lifting bracing means Download PDF

Info

Publication number
CN109505416A
CN109505416A CN201811366950.0A CN201811366950A CN109505416A CN 109505416 A CN109505416 A CN 109505416A CN 201811366950 A CN201811366950 A CN 201811366950A CN 109505416 A CN109505416 A CN 109505416A
Authority
CN
China
Prior art keywords
fixed
angle plate
deck column
mountable double
fixed angle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811366950.0A
Other languages
Chinese (zh)
Other versions
CN109505416B (en
Inventor
刘威
武涛
黄永胜
裴少帅
郭昌奇
马蕙昂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201811366950.0A priority Critical patent/CN109505416B/en
Publication of CN109505416A publication Critical patent/CN109505416A/en
Application granted granted Critical
Publication of CN109505416B publication Critical patent/CN109505416B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/30Safety or protective measures preventing damage to building parts or finishing work during construction against mechanical damage or dirt, e.g. guard covers of stairs

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of mountable double-deck column lifting bracing means, including the fixed angle plate to be removably fixedly connected with the corner of mountable double-deck column respectively, it is equipped with multiple fixed supported slabs between adjacent fixed angle plate, is removably fixedly connected between fixed supported slab and fixed angle plate.Using mountable double-deck column provided by the invention lifting bracing means, in the corner of mountable double-deck column, fixed angle plate is set, and fixed supported slab is set between adjacent fixed angle plate and is supported, it is removably fixedly connected between fixed angle plate and mountable double-deck intercolumniation, adjacent fixed angle plate.It realizes quickly fixed, it is convenient to dismantle and can be recycled, it is often big, easily-deformable with fixing tool disassembly difficulty that the device overcomes mountable double-deck column component, the problems such as lead to not can be recycled, it is realized that the later period of mountable double-deck column installs and reinforces, it is easy to produce without pre-buried in Prefabrication link.

Description

A kind of mountable double-deck column lifting bracing means
Technical field
The present invention relates to construction engineering technical fields, reinforce more specifically to a kind of lifting of mountable double-deck column Device.
Background technique
Process of Housing Industrialization is carried forward vigorously in country and place in recent years.Wherein, Shanghai City requires the outer ring from 2016 Civil buildings are created within line should be all using assembled architecture, and Section of Outer Ring Line is in addition more than 50%;Section of Outer Ring Line is external from 2017 Increase year by year on the basis of 50%.Meanwhile to using concrete structural system build assembled architecture monomer pre-emulsion assembly rate into It has gone and respective specified and has stepped up, since 2016, monomer pre-emulsion rate was not less than 40%.
With assembled architecture development and widely popularize, there is various technical problem, existing assembled skill The related way of art just seems awkward, the serious development for restricting assembled architecture technology.
Such as the production of electronic workshop industrial project, construction in practice, are frequently encountered mountable double-deck column, but this Prefabricated bilayer column easily distorts in processes interior joint area reinforcing bars such as lifting installations, or even destroys and influence to use, existing Some ways are to increase using reinforcing tooling or in prefabricated post reinforcing bar, but there are serious wastes and inconvenience substantially, such as: Node area reinforcing bar increase make troubles to production, node construction is complicated, stirrup binding inconvenience etc..
Summary of the invention
In view of this, the purpose of the present invention is to provide a kind of mountable double-deck column lifting bracing means, it is existing to solve There is the prefabricated double-deck column the problems such as processes interior joint area reinforcing bars such as lifting installation easily distort.
In order to achieve the above object, the invention provides the following technical scheme:
A kind of mountable double-deck column lifting bracing means, comprising:
To the fixed angle plate being removably fixedly connected with the corner of mountable double-deck column respectively, the adjacent fixed angles It is equipped with multiple fixed supported slabs between plate, is removably fixedly connected between the fixed supported slab and the fixed angle plate.
Preferably, the fixed supported slab is included in horizontally disposed first fixed supported slab between the adjacent fixed angle plate, institute State the both ends that the first fixed supported slab is respectively arranged at the length direction of the fixed angle plate.
Preferably, the fixed supported slab further include the second fixed supported slab arranged in a crossed manner between the adjacent fixed angle plate and Third fixed supported slab.
Preferably, the fixed angle plate is equipped with for the bolt hole with the cooperation of the corner of mountable double-deck column, the spiral shell The number of keyhole is multiple.
Preferably, the fixed angle plate is specially angle steel.
Preferably, the fixed supported slab is specially steel plate.
Mountable double-deck column provided by the invention lifting bracing means, including to the angle respectively with mountable double-deck column The fixed angle plate that portion is removably fixedly connected is equipped with multiple fixed supported slabs, fixed supported slab and fixed angles between adjacent fixed angle plate It is removably fixedly connected between plate.
Using mountable double-deck column provided by the invention lifting bracing means, in the corner of mountable double-deck column, setting is solid Angle fixing plate, and fixed supported slab is set between adjacent fixed angle plate and is supported, it is fixed angle plate and mountable double-deck intercolumniation, adjacent solid It is removably fixedly connected between angle fixing plate.It realizes and quickly fixes that convenient to dismantle and can be recycled, which overcomes assembly Formula bilayer column component is often big, easily-deformable with fixing tool disassembly difficulty, the problems such as leads to not can be recycled, realizes assembled The later period of the double-deck column, which installs, reinforces, easy to produce without pre-buried in Prefabrication link.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is the mounting structure signal that a kind of mountable double-deck column provided in an embodiment of the present invention lifts bracing means Figure;
Fig. 2 is the cross-sectional structure schematic diagram of Fig. 1;
Fig. 3 is partial enlargement structural representation at the A of Fig. 2;
Fig. 4 is the mounting structure schematic diagram of bolt provided in an embodiment of the present invention.
It is marked in attached drawing as follows:
Mountable double-deck column 1, fixed angle plate 2, the first fixed supported slab 3, the second fixed supported slab 4, bolt 5, bolt hole 6.
Specific embodiment
The embodiment of the invention discloses a kind of mountable double-deck column lifting bracing means, to solve the existing prefabricated double-deck column The problems such as the processes interior joint area reinforcing bars such as lifting installation easily distort.
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Fig. 1-Fig. 4 is please referred to, Fig. 1 is that a kind of mountable double-deck column provided in an embodiment of the present invention lifts bracing means Mounting structure schematic diagram;Fig. 2 is the cross-sectional structure schematic diagram of Fig. 1;Fig. 3 is partial enlargement structural representation at the A of Fig. 2;Fig. 4 For the mounting structure schematic diagram of bolt provided in an embodiment of the present invention.
In a kind of specific embodiment, mountable double-deck column 1 provided by the invention lifting bracing means, including with It is equipped with the fixed angle plate 2 being removably fixedly connected with the corner of mountable double-deck column 1 respectively, between adjacent fixed angle plate 2 more A fixed supported slab is removably fixedly connected between fixed supported slab and fixed angle plate 2.
Formwork and bolt hole 6 are reserved by predeterminated position in mountable double-deck column 1, it can be solid by bolt hole 6 and fixed angle plate 2 Fixed, fixed angle plate 2 is arranged along the corner of mountable double-deck column 1, and mountable double-deck column 1 is preferably cuboid.In order to guarantee device Rigidity, fixed supported slab is set between adjacent fixed angle plate 2, is preferably respectively set between any two fixed angle plate 2 solid Determine supporting plate, can also be fixed by bolt 5 between fixed supported slab and fixed angle plate 2, or consolidated by other screw elements It is fixed.
Using mountable double-deck column 1 provided by the invention lifting bracing means, it is arranged in the corner of mountable double-deck column 1 Fixed angle plate 2, and fixed supported slab is set between adjacent fixed angle plate 2 and is supported, between fixed angle plate 2 and mountable double-deck column 1, It is removably fixedly connected between adjacent fixed angle plate 2.It is realized and quickly fixes, convenient to dismantle and can be recycled, the device gram It is often big, easily-deformable with fixing tool disassembly difficulty to have taken 1 component of mountable double-deck column, the problems such as has led to not can be recycled, It realizes that the later period of mountable double-deck column 1 installs to reinforce, it is easy to produce without pre-buried in Prefabrication link.
Specifically, fixed supported slab is included in horizontally disposed first fixed supported slab 3 between adjacent fixed angle plate 2, first is fixed Supporting plate 3 is respectively arranged at the both ends of the length direction of fixed angle plate 2.It is horizontally disposed between adjacent fixed angle plate 2 solid there are two first Determine supporting plate 3, certainly, in other embodiments, according to the length of fixed angle plate 2, multiple first fixed supported slabs 3 also can be set, M type etc. can also be set by the first fixed supported slab 3, can be configured according to actual needs.
Further, fixed supported slab further includes the second fixed supported slab 4 and third arranged in a crossed manner between adjacent fixed angle plate 2 Fixed supported slab.In order to guarantee the rigidity of device, second fixed supported slab 4 arranged in a crossed manner and third are fixed between adjacent fixed angle plate 2 Supporting plate, the second fixed supported slab 4 and third fixed supported slab may be provided on the first fixed supported slab 3, be distinguished by the same bolt hole 6 First fixed supported slab 3, the second fixed supported slab 4 and third fixed supported slab and fixed angle plate 2 is fixed, certainly, in other embodiments In, directly the second fixed supported slab 4 and third fixed supported slab can also be arranged on fixed angle plate 2, in protection of the invention In range.
In one embodiment, fixed angle plate 2 is equipped with for the bolt hole 6 with the cooperation of the corner of mountable double-deck column 1, The number of bolt hole 6 is multiple.Bolt hole 6 is uniformly arranged along the length direction of fixed angle plate 2, is thus arranged, to meet not With 1 component of mountable double-deck column of size, multifunctional use is realized, to reach standardization, fast construct and energy-saving and environment-friendly Purpose.Further, the aperture of multiple bolts hole 6 is differed, to meet different assembly demands.
Specifically, fixed angle plate 2 is specially angle steel, angle steel includes the branch being arranged in a mutually vertical manner, and is set respectively in each branch It is equipped with bolt hole 6, to realize the connection with mountable double-deck column 1 and fixed supported slab.Fixed supported slab is specially steel plate, of steel plate Number is 16 pieces, and four sides of mountable double-deck column 1 are respectively set four, is horizontally disposed with two, two arranged in a crossed manner.
In a kind of specific embodiment, specific installation steps are as follows:
On 1 component of mountable double-deck column, opsition dependent reserves formwork and installation present apparatus bolt hole 6;
The vertical angle steel of L75 × 6 in four, prefabricated post corner is produced, then according to drawing, in corresponding position prepared screw-bolt hole 6;
Production outside four sides laterally, 16 pieces of 4 × 60 steel plate oblique, four pieces of each side of prefabricated post, laterally and oblique each 2 Block, then according to drawing, in corresponding position prepared screw-bolt hole 6;
By manufactured 2 vertical angle steel and 4 blocks of side steel plates, connected with bolt 5 it is integral, that is, complete lifting plus It is fixedly mounted with the one side set to assemble, lifting bracing means and the prefabricated double-deck column are installed before fixing, and two sides is first assembled;
By assembled two sides footing device by the bolt hole 6 reserved on the prefabricated double-deck column, fixed installation is finished, Then 8 pieces of steel plate groups of other two side are installed to complete, the i.e. assemblings of the whole lifting bracing means of completion;
After the prefabricated double-deck column completes all lifting bracing means programs, installation, disassembly etc. can be lifted by crane, in case circulation makes With;
The lifting bracing means disassembled is checked, is handled, storage is stand-by in order.
By, by the bolt hole 6 that practical different prefabricated column sections are reserved, a lifting may be implemented on lifting bracing means Bracing means is suitable for all different size of 1 components of mountable double-deck column.It is normal that the device overcomes 1 component of mountable double-deck column It is big, easily-deformable with fixing tool disassembly difficulty, the problems such as lead to not can be recycled, multifunctional use is realized, to reach mark Standardization, rapid and convenient construction, energy conservation and environmental protection.Simultaneously as lifting bracing means sheet is as an entirety, not only rigidity is not easy greatly Deformation, disassembly & recycling are also more convenient.
The device is that later period installation is reinforced, easy to produce without pre-buried in Prefabrication link;Self-assembles, disassembly letter It is single quick;Stiffness by itself is big, is not easy to deform in lifting installation process, can be recycled;Pacify between the prefabricated double-deck column component Fill fixed simple and fast, it is only necessary to which the bolt 5 of eight diameter 14mm is installed;Eight bolts hole 6 of installation utilize the prefabricated double-deck column certainly Reserved construction formwork bolt hole 6 with it is not necessarily to extra openings.
Finally, it is to be noted that, herein, relational terms such as first and second and the like be used merely to by One entity or operation are distinguished with another entity or operation, without necessarily requiring or implying these entities or operation Between there are any actual relationship or orders.Moreover, the terms "include", "comprise" or its any other variant meaning Covering non-exclusive inclusion, so that the process, method, article or equipment for including a series of elements not only includes that A little elements, but also including other elements that are not explicitly listed, or further include for this process, method, article or The intrinsic element of equipment.In the absence of more restrictions, the element limited by sentence "including a ...", is not arranged Except there is also other identical elements in the process, method, article or apparatus that includes the element.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other The difference of embodiment, the same or similar parts in each embodiment may refer to each other.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (6)

1. a kind of mountable double-deck column lifting bracing means characterized by comprising
To the fixed angle plate being removably fixedly connected with the corner of mountable double-deck column respectively, between the adjacent fixed angle plate Equipped with multiple fixed supported slabs, removably it is fixedly connected between the fixed supported slab and the fixed angle plate.
2. mountable double-deck column according to claim 1 lifting bracing means, which is characterized in that the fixed supported slab packet Horizontally disposed first fixed supported slab between the adjacent fixed angle plate is included, first fixed supported slab is respectively arranged at described solid The both ends of the length direction of angle fixing plate.
3. mountable double-deck column according to claim 2 lifting bracing means, which is characterized in that the fixed supported slab is also Including the second fixed supported slab and third fixed supported slab arranged in a crossed manner between the adjacent fixed angle plate.
4. mountable double-deck column according to claim 3 lifting bracing means, which is characterized in that on the fixed angle plate It is multiple equipped with the number for the bolt hole with the cooperation of the corner of mountable double-deck column, the bolt hole.
5. mountable double-deck column according to claim 4 lifting bracing means, which is characterized in that the fixed angle plate tool Body is angle steel.
6. mountable double-deck column according to claim 5 lifting bracing means, which is characterized in that the fixed supported slab tool Body is steel plate.
CN201811366950.0A 2018-11-16 2018-11-16 Assembled double-deck for post hoist and mount reinforcing apparatus Active CN109505416B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811366950.0A CN109505416B (en) 2018-11-16 2018-11-16 Assembled double-deck for post hoist and mount reinforcing apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811366950.0A CN109505416B (en) 2018-11-16 2018-11-16 Assembled double-deck for post hoist and mount reinforcing apparatus

Publications (2)

Publication Number Publication Date
CN109505416A true CN109505416A (en) 2019-03-22
CN109505416B CN109505416B (en) 2020-07-17

Family

ID=65748794

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811366950.0A Active CN109505416B (en) 2018-11-16 2018-11-16 Assembled double-deck for post hoist and mount reinforcing apparatus

Country Status (1)

Country Link
CN (1) CN109505416B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2009000437A1 (en) * 2007-06-22 2008-12-31 Ludwig Juergen Plaster connecting strip for the reveal of windows and doors
AT506771B1 (en) * 2008-05-08 2010-02-15 Peter Kassmannhuber TWO-PIECE CONNECTION PROFILE FOR COMPONENTS TO BE ADJUSTED TO PUTZ
CN103255841A (en) * 2013-05-31 2013-08-21 江苏科技大学 Assembly-type concrete column-steel beam overhanging end plate type node connecting device
CN204899255U (en) * 2015-07-31 2015-12-23 中国十七冶集团有限公司 Detachable concrete column's post angle protection device
CN206681413U (en) * 2017-05-09 2017-11-28 闫欢欢 A kind of civil engineering angle steel outer packed strengthening device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2009000437A1 (en) * 2007-06-22 2008-12-31 Ludwig Juergen Plaster connecting strip for the reveal of windows and doors
AT506771B1 (en) * 2008-05-08 2010-02-15 Peter Kassmannhuber TWO-PIECE CONNECTION PROFILE FOR COMPONENTS TO BE ADJUSTED TO PUTZ
CN103255841A (en) * 2013-05-31 2013-08-21 江苏科技大学 Assembly-type concrete column-steel beam overhanging end plate type node connecting device
CN204899255U (en) * 2015-07-31 2015-12-23 中国十七冶集团有限公司 Detachable concrete column's post angle protection device
CN206681413U (en) * 2017-05-09 2017-11-28 闫欢欢 A kind of civil engineering angle steel outer packed strengthening device

Also Published As

Publication number Publication date
CN109505416B (en) 2020-07-17

Similar Documents

Publication Publication Date Title
CN109869028B (en) Assembled reinforced concrete silo and manufacturing method thereof
CN109457798B (en) Mixed assembly node of precast concrete column and concrete beam plate and construction method
CN106149866A (en) Steel reinforced concrete assembled energy-saving residential building system
CN112323985A (en) Prefabricated reinforced concrete column and composite board node and construction process
CN109083401B (en) Template erection method and template structure for joint of cylindrical beam and frame beam
CN104895221B (en) Assembled shaped steel confined concrete shear wall structure
CN113323189A (en) Assembled heat-preservation energy-saving shear wall based on channel steel connecting piece and implementation method
CN212636080U (en) Prefabricated coincide floor mould of accurate adjustable length
CN109518950B (en) Support-free tool-based template system applied to assembled cast-in-place section and use method thereof
CN109505416A (en) A kind of mountable double-deck column lifting bracing means
CN107675871A (en) One kind is building rise long-span outrigger wall-connecting piece construction method
CN208776198U (en) A kind of steel reinforcement cage Universal hanger
CN108086523B (en) Light steel concrete block composite wall and construction method thereof
CN206942191U (en) A kind of temporary support of telescopic in height regulation reinforces combination steel construction
CN216075217U (en) Accurate pre-buried device of complicated basic column base bolt of steel construction
CN215166524U (en) Steel structure combined column and beam joint
CN212984626U (en) Prefabricated assembled formwork system
CN110206347B (en) Side span structure of assembled electronic factory building and construction method thereof
CN210827936U (en) Assembled modularization lightweight steel construction wall body
CN102433961A (en) Prefabricated beam structure construction member
CN202787485U (en) Open structure packaging combined type building
CN221089420U (en) Device for preventing prefabricated box girder inner die from floating upwards
CN219825647U (en) Shock-resistant steel beam and concrete column rigid joint point
CN210032628U (en) Supporting beam structure for building construction
CN206625569U (en) A kind of locating part for movement joint shear wall formwork

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant