CN109461290A - A kind of monitoring management system and equipment of civil construction - Google Patents

A kind of monitoring management system and equipment of civil construction Download PDF

Info

Publication number
CN109461290A
CN109461290A CN201811346803.7A CN201811346803A CN109461290A CN 109461290 A CN109461290 A CN 109461290A CN 201811346803 A CN201811346803 A CN 201811346803A CN 109461290 A CN109461290 A CN 109461290A
Authority
CN
China
Prior art keywords
target
control instruction
construction
equipment
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811346803.7A
Other languages
Chinese (zh)
Inventor
刘莹
丁金听
王小伟
杨飞
王文亮
王作飞
葛警军
陈磊
冯卫闯
齐萌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SIPPR Engineering Group Co Ltd
Original Assignee
SIPPR Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SIPPR Engineering Group Co Ltd filed Critical SIPPR Engineering Group Co Ltd
Priority to CN201811346803.7A priority Critical patent/CN109461290A/en
Publication of CN109461290A publication Critical patent/CN109461290A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B21/00Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
    • G08B21/18Status alarms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Alarm Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of monitoring management system of civil construction and equipment, which includes construction equipment monitoring device, for acquiring the running state information of target construction equipment;Material monitoring device, for acquiring the location information of target material;Data processing equipment is analyzed for the running state information to target construction equipment, and generates the first control instruction when target construction equipment is operating abnormally;The location information of target material is analyzed, and generates the second control instruction when the malposition of target material;Warning device, for generating the first alarm prompt according to the first control instruction;The second alarm prompt is generated according to the second alarm command.The application can trigger warning device in the status information exception of construction equipment or material and alarm, so that relevant staff takes corresponding treatment measures according to corresponding alarm prompt in time, the workload for alleviating staff improves the supervision timeliness and supervisory efficiency of civil construction.

Description

A kind of monitoring management system and equipment of civil construction
Technical field
The present embodiments relate to construction engineering technical fields, more particularly to a kind of monitoring management system of civil construction And equipment.
Background technique
Building trade is one of important departments engaged in material production and pillar industry of Chinese national economy.It is continuous with technology How development, utilize technology of Internet of things and the field management of artificial intelligence technology standard construction, reduction accident in Construction stage Occurrence frequency prevents various violation operations and uncivil construction, improves construction engineering quality, is a weight of people in the industry's research Want direction.
The project amount of building trade civil construction is usually larger, and including multiple construction links, in the construction process may be used Various abnormal conditions can be will appear, currently, the abnormal conditions in the building trade civil construction stage are mainly by peace The inspection of crew can be found, not only need a large amount of manpower, but also response timeliness is poor, is unfavorable for applying entire civil engineering The supervision of work.
In consideration of it, how to provide a kind of monitoring management system of the civil construction of solution above-mentioned technical problem and equipment becomes Those skilled in the art's problem to be solved.
Summary of the invention
The purpose of the embodiment of the present invention is that providing the monitoring management system and equipment of a kind of civil construction, in use The workload that can reduce staff improves the supervision timeliness and supervisory efficiency of civil construction.
In order to solve the above technical problems, the embodiment of the invention provides a kind of monitoring management systems of civil construction, comprising:
Construction equipment monitoring device, for acquiring the running state information of target construction equipment;
Material monitoring device, for acquiring the location information of target material;
Data processing equipment is analyzed for the running state information to the target construction equipment, and works as the mesh Mark construction equipment generates the first control instruction when being operating abnormally;The location information of the target material is analyzed, and works as institute The second control instruction is generated when stating the malposition of target material;
Warning device, for generating the first alarm prompt according to first control instruction;Refer to according to second alarm It enables and generates the second alarm prompt.
It optionally, further include emergency treatment device, for obtaining constructing with the target according to first control instruction The corresponding abnormal rank of equipment and Exception Type, and execute corresponding emergency operation.
Optionally, the construction equipment monitoring device is also used to acquire the location information of the target construction equipment;
The data processing equipment is also used to carry out discriminance analysis to the location information of the target construction equipment, and works as The target construction equipment generates third control instruction not in corresponding target location;
The warning device is also used to generate third alarm prompt according to the third control instruction.
Optionally, the material monitoring device, is also used to acquire the identification code information of the target material;
The data processing equipment is also used to identify the target material according to the identification code information of the target material Quality information, and determine whether the target material is qualified according to the quality information, it is raw when the target material is unqualified At the 4th control instruction;
The warning device is also used to generate the 4th alarm prompt according to the 4th control instruction.
Optionally, further includes:
Personnel positioning apparatus, for acquiring the location information of all kinds of staff;
The data processing equipment is also used to analyze the location information of all kinds of staff, determines position The type of the staff of Information abnormity is set, and generates the 5th control instruction;
The warning device is also used to generate the 5th alarm prompt according to the 5th control instruction.
Optionally, further includes:
Described image acquisition device, for acquiring the image information of construction site;
The data processing equipment is also used to carry out discriminance analysis to described image information, and judgement is currently with the presence or absence of pre- If emergency situations, and if it exists, then according to the location information and type information of the default emergency situations and all kinds of work people The location information of member generates emergency flight control instruction;
The emergency treatment device is also used to instruct sending emergency plan voice broadcast according to the emergency flight control.
Optionally, further includes:
Environment monitoring device, for acquiring the environmental parameter of construction site;
The data processing equipment is also used to analyze the environmental parameter, and when the environmental parameter exception Generate the 5th control instruction;
The warning device is also used to generate the 5th alarm prompt according to the 5th control instruction.
Optionally, the environmental parameter includes one of temperature, humidity, noise or fugitive dust degree or a variety of combinations.
Optionally, the warning device includes buzzer.
The embodiment of the invention also provides a kind of managing apparatus of civil construction, apply including civil engineering as described above The monitoring management system of work.
The embodiment of the invention provides a kind of monitoring management system of civil construction and equipment, which includes: construction machine Has monitoring device, for acquiring the running state information of target construction equipment;Material monitoring device, for acquiring target material Location information;Data processing equipment is analyzed for the running state information to target construction equipment, and works as target construction machine Tool generates the first control instruction when being operating abnormally;The location information of target material is analyzed, and works as the position of target material The second control instruction is generated when abnormal;Warning device, for generating the first alarm prompt according to the first control instruction;According to second Alarm command generates the second alarm prompt.
As it can be seen that the application can be by construction equipment monitoring device and material monitoring device to the construction machine in construction site Tool and material are monitored, and by data processing equipment to collected running state information corresponding with target construction equipment It is analyzed with location information corresponding with target material, the triggering alarm dress when the status information exception of construction equipment or material It sets and alarms, so that relevant staff takes corresponding treatment measures according to corresponding alarm prompt in time, alleviate work The workload for making personnel improves the supervision timeliness and supervisory efficiency of civil construction.
Detailed description of the invention
It to describe the technical solutions in the embodiments of the present invention more clearly, below will be to institute in the prior art and embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is a kind of structural schematic diagram of the monitoring management system of civil construction provided in an embodiment of the present invention;
Fig. 2 is the structural schematic diagram of the monitoring management system of another civil construction provided in an embodiment of the present invention.
Specific embodiment
The embodiment of the invention provides a kind of monitoring management system of civil construction and equipment, can subtract in use The light workload of staff, improves the supervision timeliness and supervisory efficiency of civil construction.
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art Every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
Fig. 1 is please referred to, Fig. 1 is a kind of structural representation of the monitoring management system of civil construction provided in an embodiment of the present invention Figure.
The monitoring management system, comprising:
Construction equipment monitoring device 11, for acquiring the running state information of target construction equipment;
Material monitoring device 12, for acquiring the location information of target material;
Data processing equipment 13 is analyzed for the running state information to target construction equipment, and when target is constructed Equipment generates the first control instruction when being operating abnormally;The location information of target material is analyzed, and works as the position of target material The second control instruction is generated when setting exception;
Warning device 14, for generating the first alarm prompt according to the first control instruction;It is generated according to the second alarm command Second alarm prompt.
It should be noted that since each construction equipment for participating in construction is likely to occur abnormal conditions in the process of running, So can be using each construction equipment for participating in constructing as target construction equipment in the application, it can be to each target construction machine Corresponding construction equipment monitoring device 11 is arranged in tool, and the application is described in detail by taking a target construction equipment as an example.Wherein, It may include sensor in the construction equipment monitoring device 11, and believed by the operating status that sensor acquires target construction equipment Breath, sensor can have multiple, so as to acquire the various running state informations in target construction equipment, and will be collected Running state information be sent to data processing equipment 13, data processor 13 can be received according to the connection pre-established To running state information corresponding with target construction equipment be analyzed and processed, when running state information exception, then generate Corresponding first control instruction, and warning device 14 is triggered, warning device 14, will be according to this after receiving the first control instruction First control instruction generates the first alarm prompt, wherein first alarm prompt can be light prompt, auditory tone cues or short breath Letter prompt etc..Specifically, data processing equipment 13 can be to every when the collected running state information of institute includes multiple types The running state information of a type is analyzed, and when certain class running state information occurs abnormal, generates corresponding first Control instruction, wherein the type information of operating status is carried in first control instruction, warning device 14 can be according to first Type information in control instruction determines the type of abnormality and issues corresponding first alarm prompt, so as to staff The current position for exception occur can be locked in time according to first alarm prompt, to take corresponding treatment measures.
It should also be noted that, may not have after materials arrival since the material for needing to use in work progress is very more There is transport to corresponding installed position, if can not find that construction speed can be had an impact in time, so the application In further include material monitoring device 12, the location information of target material is monitored by the material monitoring device 12, data 13 pairs of processing unit the location information of collected target material be analyzed and processed, can specifically pass through the mark of target material Know code and matches correct position corresponding with the target material from database, location information and correct position when the target material It sets when not being inconsistent, then illustrates that the installation position of the target material is not right, the second control instruction can be generated at this time, second control instruction In can carry identification code corresponding with target material, warning device 14 can generate corresponding the according to second control instruction Two alarm prompts, so that staff can accurately determine that mistake occurs for current location information according to second alarm prompt Target material, to take corresponding treatment measures.
As it can be seen that the application can be by construction equipment monitoring device and material monitoring device to the construction machine in construction site Tool and material are monitored, and by data processing equipment to collected running state information corresponding with target construction equipment It is analyzed with location information corresponding with target material, the triggering alarm dress when the status information exception of construction equipment or material It sets and alarms, so that relevant staff takes corresponding treatment measures according to corresponding alarm prompt in time, alleviate work The workload for making personnel improves the supervision timeliness and supervisory efficiency of civil construction.
On the basis of the above embodiments, the embodiment of the present invention makes further optimization and explanation to technical solution, asks Referring to Fig. 2, the system is specific as follows:
Further, which further includes emergency treatment device 15, for obtaining applying with target according to the first control instruction The corresponding abnormal rank of work equipment and Exception Type, and execute corresponding emergency operation.
Specifically, in order to which corresponding emergency can be taken to arrange in time in the operating status exception of target construction equipment It applies, to ensure that construction speed and construction safety, the application are also provided with emergency treatment device 15, wherein data processing equipment 13 can also be sent to the first control instruction of generation emergency treatment device 15, emergency treatment device 15 receive this first After control instruction, obtained and target construction equipment according to the information (abnormal position and Exception Type) that first control instruction carries Corresponding Exception Type, then abnormal position and Exception Type according to the pre-stored data corresponding relationship corresponding with abnormal rank are true Abnormal rank corresponding with target construction equipment is made, and the behaviour needed to be implemented is determined according to the exception rank and Exception Type Make, the operation is then executed, for example, it is desired to which controlling target construction equipment is automatically closed or cuts off the emergency operations such as construction power supply. Wherein, different Exception Types may correspond to different abnormal ranks, and also various abnormal conditions can be classified in advance, And partition of the level is carried out to the abnormal conditions of each type, and can be preset corresponding with Exception Type and abnormal rank Emergency operation information, emergency treatment device 15 determine that corresponding emergency operation is believed according to different Exception Types and abnormal rank After breath, corresponding operation is executed according to the emergency operation information.
Further, construction equipment monitoring device 11 is also used to acquire the location information of target construction equipment;
Data processing equipment 13 is also used to carry out discriminance analysis to the location information of target construction equipment, and when target is applied Work equipment generates third control instruction not in corresponding target location;
Warning device 14 is also used to generate third alarm prompt according to third control instruction.
It should be noted that target construction equipment needs to carry out constructing operation to specified place in the construction process, this Construction equipment monitoring device 11 in application can also collect the location information of target construction equipment, pass through location information reality Now to the positioning of target construction equipment, data processing equipment 13 can determine the target according to the location information of the mark construction equipment Construction equipment whether in preset target location, if the target construction equipment not in corresponding target location, then It needs to control warning device 4 and issues corresponding third alarm prompt, so that staff can send out in time according to the prompt information The malposition situation of existing target construction equipment, and the position of target construction equipment is adjusted, it is advantageously ensured that construct into Degree and construction quality.Wherein, it may include GPS positioning device in the construction equipment monitoring device 11, which can be filled It sets and is mounted on target construction equipment, to realize the positioning to target construction equipment.
Further, material monitoring device 12 is also used to acquire the identification code information of target material;
Data processing equipment 13 is also used to the quality information of the identification code information identification target material according to target material, And determine whether target material is qualified according to quality information, the 4th control instruction is generated when target material is unqualified;
Warning device 14 is also used to generate the 4th alarm prompt according to the 4th control instruction.
It is understood that may have the matter of respective material due to various aspects for the material that construction is prepared Measure unqualified, and each material can be previously provided with corresponding identification code information, according to the identification code information from material Parameter information corresponding with the material can be obtained by being matched in database, which includes quality information, so When being monitored to material, material monitoring device 12 can also obtain the identification code information of material, and data processing equipment 13 Corresponding quality information can be matched from database according to the identification code information, when the target material is unqualified, then controlled Warning device 14 issues corresponding alarm prompt, so that relevant staff is notified, so that staff can have found in time Underproof material, and material is replaced, it is advantageously ensured that construction quality.Wherein, identification code information can pass through scanning Two dimensional code corresponding with each material obtains.
Further, the system further include:
Personnel positioning apparatus 16, for acquiring the location information of all kinds of staff;
Data processing equipment 13 is also used to analyze the location information of all kinds of staff, determines location information The type of abnormal staff, and generate the 5th control instruction;
Warning device 14 is also used to generate the 5th alarm prompt according to the 5th control instruction.
It should be noted that then needing all kinds of work for the link that must have staff's participation in work progress Personnel work on respective operating position, if there is staff be fitted without requirement to hilllock or not in corresponding position It sets, deviates work position, being normally carried out for construction may be will affect, wherein all kinds of staff for example may include quality inspection Member, security official, builder etc., because different types of staff needs to wear different types of safety cap, it is possible to logical The position positioning that corresponding positioning device realization is set on safety cap to all kinds of staff is crossed, to obtain corresponding position Information, since arrangement and method for construction can be arranged before construction, the corresponding position of all kinds of staff can be pre-set, so data Processing unit 13 can according to the data information prestored in database to collected all kinds of staff location information into Row analysis so that it is determined that going out which kind of staff not in target location, and is capable of determining which specific position goes out Exception is showed, corresponding alarm prompt has been issued to generate corresponding 5th control instruction to control warning device 14, so as to phase The staff answered can note abnormalities in time, and as early as possible to going to execute corresponding work on corresponding target position.To really Protect construction speed.In addition, the application can also include display device, and can be collected according to 16 institute of personnel positioning apparatus All kinds of staff are that child's information shows the position distribution of each staff, so as to corresponding administrative staff into Row is checked, wherein different types of staff can be shown by the icon of different color or shape, to distinguish The type of staff.
Further, further includes:
Image collecting device 17, for acquiring the image information of construction site;
Data processing equipment 13 is also used to carry out image information discriminance analysis, and judgement is currently with the presence or absence of default burst Situation, and if it exists, then raw according to the location information and type information and the location information of all kinds of staff for presetting emergency situations It is instructed at emergency flight control;
Emergency treatment device 15 is also used to instruct sending emergency plan voice broadcast according to emergency flight control.
It should also be noted that, since construction site is also possible that the burst feelings such as burst accident, such as fire, landslide Condition, so image collecting device 17 can also further be arranged in the application, by the image collecting device 17 to construction site It Image Acquisition is carried out, obtains the image information of construction site each region, data carding apparatus 13 can be according to pre-establishing Database carries out discriminance analysis to these image informations, so that it is determined that whether go out has default emergency case, and if it exists, then know Not Chu emergency situations occur position and type corresponding with default emergency case, and according to default emergency situations occur position Confidence breath and the location information of the collected all kinds of staff of personnel positioning apparatus 16 can determine corresponding emergency measure, And emergency flight control instruction is issued, emergency treatment device 15 can instruct according to emergency flight control and issue emergency plan voice broadcast.Example Such as, if it is current happens is that fire, arrives the work in the position pre-determined distance by determining that fire location is available Make the information of personnel (for example including 1 team of security official and 2 teams and 1 team of builder and 2 teams), and formulates these staff that put up a notice The emergency plan put out a fire to fire spot, and corresponding emergency flight control is generated according to the emergency plan and is instructed, at emergency The voice broadcast information that reason device 15 instructs the relevant work personnel that give notice to be succoured to destination according to the emergency flight control, To notify the implementation of these staff to the flash appeal of fire, in order to avoid delaying rescue, lead to more serious consequence.This Application can find emergency situations in time, and make corresponding emergency plan as the case may be, then pass through voice broadcast Mode notify relevant staff, so that relevant staff can take in time suitable scheme to cope with, make to apply Safety during work is higher.
Further, the system further include:
Environment monitoring device 18, for acquiring the environmental parameter of construction site;
Data processing equipment 13 is also used to analyze environmental parameter, and the 5th control is generated when environmental parameter exception System instruction;
Warning device 14 is also used to generate the 5th alarm prompt according to the 5th control instruction.
Specifically, environmental parameter is also to influence a key factor of construction speed, so can also pass through in the application Environment monitoring device 18 is monitored the environment of construction site, obtains corresponding environmental parameter, such as humidity, temperature, fugitive dust And the environmental parameters such as noise, after data processing equipment 13 analyzes these environmental parameters, when some environment therein is joined When number is beyond preset index, then it can control warning device 4 and issue corresponding alarm prompt.In addition, if necessary can be with Control emergency treatment device 15 controls water pump or water-tank lorry unlatching carries out construction site the work such as to spray.
Specifically, the warning device 14 in the application may include buzzer, it also may include the devices such as warning light, specifically Do not do particular determination.
On the basis of the above embodiments, the embodiment of the invention also provides a kind of managing apparatus of civil construction, Monitoring management system including such as above-mentioned civil construction.
It should be noted that the managing apparatus of civil construction provided in the present embodiment has and above-described embodiment In civil construction the identical beneficial effect of monitoring management apparatus, to the prison of civil construction involved in this present embodiment The specific introduction of control management device please refers to above-described embodiment, and the application repeats no more.
It should also be noted that, in the present specification, relational terms such as first and second and the like be used merely to by One entity or operation are distinguished with another entity or operation, without necessarily requiring or implying these entities or operation Between there are any actual relationship or orders.Moreover, the terms "include", "comprise" or its any other variant meaning Covering non-exclusive inclusion, so that the process, method, article or equipment for including a series of elements not only includes that A little elements, but also including other elements that are not explicitly listed, or further include for this process, method, article or The intrinsic element of equipment.In the absence of more restrictions, the element limited by sentence "including a ...", is not arranged Except there is also other identical elements in the process, method, article or apparatus that includes the element.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (10)

1. a kind of monitoring management system of civil construction characterized by comprising
Construction equipment monitoring device, for acquiring the running state information of target construction equipment;
Material monitoring device, for acquiring the location information of target material;
Data processing equipment is analyzed for the running state information to the target construction equipment, and when the target is applied Work equipment generates the first control instruction when being operating abnormally;The location information of the target material is analyzed, and works as the mesh The second control instruction is generated when marking the malposition of material;
Warning device, for generating the first alarm prompt according to first control instruction;It is produced according to second alarm command Raw second alarm prompt.
2. the monitoring management system of civil construction according to claim 1, which is characterized in that further include emergency processing dress It sets, for obtaining abnormal rank corresponding with the target construction equipment and Exception Type according to first control instruction, and Execute corresponding emergency operation.
3. the monitoring management system of civil construction according to claim 2, which is characterized in that the construction equipment monitoring dress It sets, is also used to acquire the location information of the target construction equipment;
The data processing equipment is also used to carry out discriminance analysis to the location information of the target construction equipment, and when described Target construction equipment generates third control instruction not in corresponding target location;
The warning device is also used to generate third alarm prompt according to the third control instruction.
4. the monitoring management system of civil construction according to claim 2, which is characterized in that the material monitoring device, It is also used to acquire the identification code information of the target material;
The data processing equipment is also used to identify the quality of the target material according to the identification code information of the target material Information, and determine whether the target material is qualified according to the quality information, is generated when the target material is unqualified Four control instructions;
The warning device is also used to generate the 4th alarm prompt according to the 4th control instruction.
5. the monitoring management system of civil construction according to claim 2, which is characterized in that further include:
Personnel positioning apparatus, for acquiring the location information of all kinds of staff;
The data processing equipment is also used to analyze the location information of all kinds of staff, determines that out position is believed The type of abnormal staff is ceased, and generates the 5th control instruction;
The warning device is also used to generate the 5th alarm prompt according to the 5th control instruction.
6. the monitoring management system of civil construction according to claim 5, which is characterized in that further include:
Described image acquisition device, for acquiring the image information of construction site;
The data processing equipment is also used to carry out described image information discriminance analysis, and judgement is currently with the presence or absence of default prominent Hair-like condition, and if it exists, then according to the location information and type information of the default emergency situations and all kinds of staff Location information generates emergency flight control instruction;
The emergency treatment device is also used to instruct sending emergency plan voice broadcast according to the emergency flight control.
7. the monitoring management system of civil construction according to claim 2, which is characterized in that further include:
Environment monitoring device, for acquiring the environmental parameter of construction site;
The data processing equipment is also used to analyze the environmental parameter, and generates when the environmental parameter exception 5th control instruction;
The warning device is also used to generate the 5th alarm prompt according to the 5th control instruction.
8. the monitoring management system of civil construction according to claim 7, which is characterized in that the environmental parameter includes temperature One of degree, humidity, noise or fugitive dust degree or a variety of combinations.
9. the monitoring management system of civil construction according to claim 1, which is characterized in that the warning device includes bee Ring device.
10. a kind of managing apparatus of civil construction, which is characterized in that including as described in any one of claims 1-9 The monitoring management system of civil construction.
CN201811346803.7A 2018-11-13 2018-11-13 A kind of monitoring management system and equipment of civil construction Pending CN109461290A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811346803.7A CN109461290A (en) 2018-11-13 2018-11-13 A kind of monitoring management system and equipment of civil construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811346803.7A CN109461290A (en) 2018-11-13 2018-11-13 A kind of monitoring management system and equipment of civil construction

Publications (1)

Publication Number Publication Date
CN109461290A true CN109461290A (en) 2019-03-12

Family

ID=65610299

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811346803.7A Pending CN109461290A (en) 2018-11-13 2018-11-13 A kind of monitoring management system and equipment of civil construction

Country Status (1)

Country Link
CN (1) CN109461290A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111754601A (en) * 2020-05-08 2020-10-09 国网浙江省电力有限公司 On-site operation management and control method based on intelligent safety helmet
CN112036755A (en) * 2020-09-02 2020-12-04 张海军 Supervision method and system for building engineering quality detection
CN113359645A (en) * 2021-06-30 2021-09-07 四川交达预应力工程检测科技有限公司 Prestressed construction monitoring and early warning system and method based on engineering Internet of things
CN116340394A (en) * 2023-05-23 2023-06-27 中交二公局东萌工程有限公司 Digital processing system based on enterprise security management

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010073031A (en) * 2008-09-19 2010-04-02 Hitachi Constr Mach Co Ltd Execution management system
CN107330664A (en) * 2016-05-12 2017-11-07 上海点贸信息技术有限公司 A kind of intelligence based on Internet of Things builds management system
CN107527155A (en) * 2017-09-06 2017-12-29 北京北控建设发展有限公司 Construction project supervisory systems
CN107948245A (en) * 2017-10-31 2018-04-20 重庆工程职业技术学院 Project Management System based on BIM

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010073031A (en) * 2008-09-19 2010-04-02 Hitachi Constr Mach Co Ltd Execution management system
CN107330664A (en) * 2016-05-12 2017-11-07 上海点贸信息技术有限公司 A kind of intelligence based on Internet of Things builds management system
CN107527155A (en) * 2017-09-06 2017-12-29 北京北控建设发展有限公司 Construction project supervisory systems
CN107948245A (en) * 2017-10-31 2018-04-20 重庆工程职业技术学院 Project Management System based on BIM

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111754601A (en) * 2020-05-08 2020-10-09 国网浙江省电力有限公司 On-site operation management and control method based on intelligent safety helmet
CN112036755A (en) * 2020-09-02 2020-12-04 张海军 Supervision method and system for building engineering quality detection
CN112036755B (en) * 2020-09-02 2023-09-26 深圳比目鱼平方科技有限公司 Supervision method and system for quality detection of building engineering
CN113359645A (en) * 2021-06-30 2021-09-07 四川交达预应力工程检测科技有限公司 Prestressed construction monitoring and early warning system and method based on engineering Internet of things
CN113359645B (en) * 2021-06-30 2023-04-21 四川交达预应力工程检测科技有限公司 Prestress construction monitoring and early warning system and method based on engineering Internet of things
CN116340394A (en) * 2023-05-23 2023-06-27 中交二公局东萌工程有限公司 Digital processing system based on enterprise security management

Similar Documents

Publication Publication Date Title
CN109461290A (en) A kind of monitoring management system and equipment of civil construction
KR101645139B1 (en) Management System at a work in place and Drive Method of the Same
CN108615204A (en) A kind of building based on BIM and UWB faces side hole safety management system and method
KR101675733B1 (en) Nuclear power plant accident integrated action system
US11935391B2 (en) Methods and systems for commission, inspection, and maintenance of a connected fire alarm system
CN108111342B (en) Visualization-based threat alarm display method
CN111178828A (en) Method and system for building fire safety early warning
US20190318170A1 (en) Artificial intelligence and image processing-based work force safety
CN111667597A (en) Constructor monitoring system based on big data and task presetting
CN109583772A (en) Method for managing and monitoring, device, system and the readable storage medium storing program for executing of construction site
KR20080070543A (en) Early warning method for estimating inferiority in automatic production line
CN107204105A (en) Dangerous monitoring and early warning method and device
CN113988328A (en) Early warning event interaction method and device based on large visual screen
CN105976116A (en) IoT based fire safety dynamic evaluation method and system
CN108389008A (en) Power distribution network resource management system
CN110533307A (en) A kind of building safety monitoring system and emergency processing method based on BIM
CN112819374A (en) System and method for risk management of railway bridge constructors
JP2019067217A (en) Safety integrity determination program, safety integrity determination method and safety integrity determination device
CN111667598A (en) Constructor monitoring system based on big data and grouping task presetting
CN104570977A (en) Safety production supervision system for initiating explosive devices
KR20180112951A (en) Inspection system and method
CN110219472A (en) A kind of construction worker's safety protection equipment and method
CN111553061A (en) Nuclear power plant typhoon emergency response and early warning device and construction method thereof
CN116523492A (en) Hydropower station supervision method and system, electronic equipment and storage medium
CN115587709A (en) Enterprise safety production management method, system and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190312

RJ01 Rejection of invention patent application after publication