CN108915702B - Shield receiving method in circular small-section tunnel - Google Patents

Shield receiving method in circular small-section tunnel Download PDF

Info

Publication number
CN108915702B
CN108915702B CN201810600751.5A CN201810600751A CN108915702B CN 108915702 B CN108915702 B CN 108915702B CN 201810600751 A CN201810600751 A CN 201810600751A CN 108915702 B CN108915702 B CN 108915702B
Authority
CN
China
Prior art keywords
steel
grouting
shield
tunnel
arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810600751.5A
Other languages
Chinese (zh)
Other versions
CN108915702A (en
Inventor
陈德国
经莲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd
Rail Transit Engineering Co Ltd of China Railway 21St Bureau Group Co Ltd
Original Assignee
Rail Transit Engineering Co Ltd of China Railway 21St Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rail Transit Engineering Co Ltd of China Railway 21St Bureau Group Co Ltd filed Critical Rail Transit Engineering Co Ltd of China Railway 21St Bureau Group Co Ltd
Priority to CN201810600751.5A priority Critical patent/CN108915702B/en
Publication of CN108915702A publication Critical patent/CN108915702A/en
Application granted granted Critical
Publication of CN108915702B publication Critical patent/CN108915702B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A shield receiving method in a circular small-section tunnel comprises the following steps: s1, advance support of the tunnel; s2, primary support; s3, radial grouting and reinforcing of the preliminary bracing arch back; s4, blocking and reinforcing the front soil body by the tunnel face; s5, secondary lining of the tunnel; s6, advance support of a shield tunneling section; s7, backfilling mortar; s8, installing a guide table; s9, precipitation; s10, receiving by a shield; the invention has the advantages of no need of installing a rubber water-stopping curtain, simplicity, convenience, safe construction and the like, and can be popularized and applied to the field of receiving construction of the shield tunneling machine.

Description

Shield receiving method in circular small-section tunnel
Technical Field
The invention belongs to the field of shield machine receiving construction, and particularly relates to a shield receiving construction method of an urban subway in a water-rich sandy gravel circular tunnel.
Background
In the shield construction of urban subways, a shield machine generally adopts a mode of directly receiving on a receiving bracket or an arc guide table, in an urban shallow-buried underground tunnel, a 'CD' method, a 'CRD' method or a double-side wall method is generally adopted, a temporary middle partition wall is adopted in a supporting section or a temporary inverted arch is arranged in the middle of the section, and a temporary support needs to be cut off during shield receiving construction. In the project, the tunnel penetrating stratum is mainly a sandy gravel stratum, the underground water level is high, the diameter of a shield cutterhead is 6280mm, the inner diameter of the lining section of the round tunnel in the mining method is 6400mm, in addition, the decomposition mileage of the tunnel in the mining method is positioned at the lower part of the footing of the foundation of a 12-storey building, and the construction safety is difficult to guarantee by simply adopting a conventional method to receive construction.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide a shield receiving method in a circular small-section tunnel, which does not need to install a rubber water-stopping curtain, is simple and convenient and is safe to construct.
The technical scheme for solving the technical problems comprises the following steps:
s1, advance support of the tunnel: adopting a mode of pre-grouting reinforcement for a large pipe shed and a self-advancing anchor rod in advance;
s2, primary support: the whole ring is provided with a steel arch frame;
s3, radial grouting reinforcement of the preliminary bracing arch back: pre-embedding a steel perforated pipe as a grouting pipe within 120 degrees of the vault during primary support construction, and performing grouting reinforcement;
s4, blocking and reinforcing the front soil body by the tunnel face: when the mine method tunnel is excavated to the position of a plug wall, C25 concrete is sprayed in time to close the tunnel face and pipe shed guide pipes are pre-buried;
s5, secondary lining of the tunnel: constructing a secondary lining with the thickness of 200m under the condition of not dismantling the support;
s6, shield tunneling section advance support: after finishing secondary lining, drilling an advanced large pipe shed within 120 degrees of the vault of the end head;
s7, mortar backfilling: after finishing secondary lining and end large pipe shed construction, removing the temporary steel support and backfilling and sealing a 9m interval by adopting plain cement slurry doped with a proper amount of expanding agent;
s8, installing a guide table: pouring a C20 fine-stone concrete guide table at the bottom of the circular tunnel, and embedding and installing a steel plate and a guide rail;
s9, precipitation: a tunnel construction dewatering well is utilized to dewater before shield receiving;
s10, shield receiving: the shield is directly tunneled and received on the guide table through a 9m backfill section, and the backfill section is formed by splicing shield segments.
Step S1 of the present invention includes: the large pipe shed is made of P110 steel flower pipes with the diameter of 146mm and the wall thickness of 9mm, the arch crown is constructed within 120 degrees, the circumferential center distance is 300mm, the external insertion angle is 1-2 degrees, the number of the steel flower pipes per cycle is 31, the steel flower pipes are lapped according to 3m, the large pipe shed is grouted by cement single slurry with the water-cement ratio of 0.5-1.0, the grouting pressure is 0.5-1.2 MPa, the grouting sequence is from bottom to top, the two sides are arranged first and then the center are symmetrically grouted, and the grouting pressure is gradually increased from small to small; the self-advancing anchor rod is made of a hot-rolled seamless steel tube with the diameter of 32mm, the wall thickness is 4mm, the length is 2.2m, the arch back is arranged within 120 degrees, the circumferential distance is 0.3m multiplied by the longitudinal distance of 1.0m, the external insertion angle is 10-15 degrees, the tail end of the steel tube is arranged on the belly of the steel arch frame, cement paste with the water-cement ratio of 0.5-1.0 is adopted for grouting, and the grouting pressure is 0.3-0.5 MPa.
Step S2 of the present invention includes: the steel arch is arranged in a full ring, the interval between I20a steel arches is 0.5m, double-layer steel bar meshes with the diameter of 8mm form a grid of 150mm multiplied by 150mm, and the full ring is arranged in double layers and is respectively arranged on the inner side and the outer side of the steel arch; longitudinal connecting ribs with the diameter of 22mm are arranged on the inner side and the outer side, and the circumferential distance between the longitudinal connecting ribs is 1.0 m; the sprayed concrete is C25P6 early strength concrete, the sprayed and mixed thickness is 300mm, the full-section support is realized, and the thickness of the middle partition plate and the temporary inverted arch support is 250 mm; the foot locking anchor rod adopts an R32S self-drilling foot locking anchor pipe, the length of the foot locking anchor pipe is 3.0m, the foot locking anchor rod is arranged at the position of a circumferential joint of a primary support steel arch frame and the position of a guide pit corner part of a sub-excavation, the longitudinal distance is the same as the longitudinal distance of the steel arch frame, grouting pipes are embedded in the arch crown 120-degree range, the circumferential distance is 2.0m multiplied by 2.0m in the longitudinal direction and are arranged in a quincunx mode, the grouting pipes adopt steel pipes with the diameter of 32mm and the wall thickness of 3.5mm, and the.
Step S3 of the present invention includes: the diameter of the steel perforated pipe is 42mm, the wall thickness is 3.5mm, the length is the primary support thickness +0.5m, the distance between grouting pipes is 2.0m in the circumferential direction and 2.0m in the longitudinal direction, the steel perforated pipe is arranged in a quincunx manner, after the primary support is closed into a ring with the length of 50m, cement paste is injected to the back of the primary support arch in a pressing mode, the water-cement ratio of the cement paste is 0.5-1.0, and the grouting pressure is 0.1-0.3 MPa.
Step S4 of the present invention includes: the sprayed C25 concrete seals the tunnel face, the thickness of the sprayed concrete is 300mm, a 150mm multiplied by 150mm grid is formed by double layers of glass fiber reinforcements with the diameter of 12mm in the concrete and is connected with a primary support grid, and grouting holes are reserved during construction of the plug wall.
Step S6 of the present invention includes: the large pipe shed adopts P110 steel flower pipes with the diameter of 146mm and the wall thickness of 9mm, the circular center interval of 300mm is beaten on the arch back, the outer inserting angle is 1-2 degrees, the length of the large pipe shed is 20m, the large pipe shed adopts cement paste single liquid cement paste with the water cement ratio of 0.5-1.0, and the grouting pressure is 0.5-1.2 MPa.
Compared with the prior art, the invention has the following advantages:
1. the method can be used for shield launching and receiving construction without ground reinforcing conditions, and is convenient to construct and operate;
2. the risk of stratum settlement and collapse is reduced, and shield receiving construction is safer and quicker.
Drawings
Figure 1 is a longitudinal cross-sectional view of a shield of the present invention.
Figure 2 is a plan view of a shield receiving of the present invention.
Figure 3 is a cross-sectional view of the shield reception of the present invention.
In the figure: 1. primary support; 2. grouting a water stop ring at the arch back; 3. secondary lining of the tunnel; 4. thirdly, lining the tunnel; 5. a shield segment; 6. a bulkhead wall; 7. a large pipe shed; 8. shielding; 9. and (6) backfilling the mortar.
Detailed Description
The present invention will be described in further detail with reference to the following drawings and examples, but the present invention is not limited to these examples.
Example 1
In fig. 1 to 3, the invention relates to a method for receiving a shield in a circular small-section tunnel, which comprises the following steps:
s1, advance support of the tunnel: adopting a mode of pre-grouting reinforcement for a large pipe shed and a self-advancing anchor rod in advance; the large pipe shed 7 is made of P110 steel perforated pipes with the diameter of 146mm and the wall thickness of 9mm, the pipe is constructed within 120 degrees of the arch crown, the circumferential center spacing is 300mm, the external insertion angle is 1-2 degrees, the number of pipes per cycle is 31, the pipes are lapped according to 3 meters, the grouting of the large pipe shed 7 is made of cement slurry single-liquid slurry with the water-cement ratio of 0.5-1.0, the grouting pressure is 0.5-1.2 MPa, the grouting sequence is from bottom to top, symmetrical grouting is performed after two sides and the center, the grouting pressure is gradually increased from small to small, the final pressure, the grouting speed and the final pressure holding time of the grouting are well controlled in the grouting process, the grouting pressure is observed at any time in the grouting process, the grouting condition is analyzed, the blockage and the slurry leakage are prevented, and the grouting record is made so as to analyze the grouting effect; the self-advancing anchor rod is made of a hot-rolled seamless steel pipe with the diameter of 32mm, the wall thickness is 4mm, the length is 2.2m, the arch crown is arranged within 120 degrees, the interval is 0.3m in the circumferential direction and 1.0m in the longitudinal direction, the outer inserting angle is 10-15 degrees, the tail end of the steel pipe is arranged on the belly of the steel arch frame, cement paste with the water-cement ratio of 0.5-1.0 is used for grouting, and the grouting pressure is 0.3-0.5 MPa.
S2, primary support: the whole ring is provided with a steel arch frame; i20a steel arch frames are arranged at a distance of 0.5m, double-layer steel bar meshes with the diameter of 8mm form a grid of 150mm multiplied by 150mm, and the steel arch frames are arranged in a full-ring double-layer mode and are respectively arranged on the inner side and the outer side of each steel arch frame; longitudinal connecting ribs with the diameter of 22mm are arranged on the inner side and the outer side, and the circumferential distance between the longitudinal connecting ribs is 1.0 m; the sprayed concrete is C25P6 early strength concrete, the sprayed and mixed thickness is 300mm, the full-section support is realized, and the thickness of the middle partition plate and the temporary inverted arch support is 250 mm; the foot locking anchor rod adopts an R32S self-drilling foot locking anchor pipe, the length of the foot locking anchor pipe is 3.0m, the foot locking anchor rod is arranged at the position of a circumferential joint and a branch excavation pilot hole corner of a primary support 1 steel arch, the longitudinal distance is the same as the longitudinal distance of the steel arch, grouting pipes are embedded in the arch crown range of 120 degrees, the circumferential distance is 2.0m multiplied by 2.0m in the longitudinal direction and are arranged in a quincunx shape, the grouting pipes adopt steel pipes with the diameter of 32mm and the wall thickness of 3.5mm, and the length of the grouting pipes is 0.8.
S3, radial grouting reinforcement of the preliminary bracing arch back: pre-embedding a steel perforated pipe as a grouting pipe within 120 degrees of the vault during primary support construction, and performing grouting reinforcement; the diameter of the steel perforated pipe is 42mm, the wall thickness is 3.5mm, the length is 1 +0.5m of the primary support, the interval between grouting pipes is annularly 2.0m multiplied by longitudinal 2.0m, the arrangement is in a quincunx shape, after the primary support is closed to form a ring with the length of 50m, cement paste is injected to the 1 arch back of the primary support in a pressing mode, the water cement ratio of the cement paste is 0.5-1.0, the grouting pressure is 0.1-0.3 Mpa, the site is determined according to geological condition tests, after excavation, more sections of underground water are exposed, and the sections with water leakage are still left after backfilling and grouting of the primary support, and grouting is carried out on deeper surrounding rocks behind the lining according to specific conditions.
S4, blocking and reinforcing the front soil body by the tunnel face: when the mine method tunnel is excavated to the position of a plug wall, C25 concrete is sprayed in time to close the tunnel face and pipe shed guide pipes are pre-buried; the thickness of the sprayed concrete is 300mm, a 150mm multiplied by 150mm grid is formed by double-layer glass fiber ribs with the diameter of 12mm and is connected with a primary support 1 grid, grouting holes are reserved in the construction of the plug wall 6, soil in front of the plug wall 6 is subjected to grouting reinforcement and water stop by the grouting holes, and reinforcing measures and materials adopted by grouting reinforcement cannot influence the passing of a shield, and single-liquid slurry can be adopted.
S5, secondary lining of the tunnel: constructing a secondary lining with the thickness of 200m under the condition of not dismantling the support;
s6, shield tunneling section advance support: after finishing secondary lining, drilling an advanced large pipe shed within 120 degrees of the vault of the end head; the large pipe shed adopts P110 steel flower pipes with the diameter of 146mm and the wall thickness of 9mm, the circular center interval of 300mm is beaten on the arch back, the outer inserting angle is 1-2 degrees, the length of the large pipe shed is 20m, the large pipe shed adopts cement paste single liquid cement paste with the water cement ratio of 0.5-1.0, and the grouting pressure is 0.5-1.2 MPa.
S7, mortar backfilling: after finishing secondary lining and end large pipe shed construction, removing the temporary steel support and backfilling and sealing a 9m interval by adopting plain cement slurry doped with a proper amount of expanding agent;
s8, installing a guide table: pouring a C20 fine-stone concrete guide table at the bottom of the circular tunnel, and embedding and installing a steel plate and a guide rail;
s9, precipitation: a tunnel construction dewatering well is utilized to dewater before shield receiving;
s10, shield receiving: the shield is directly tunneled and received on the guide table through a 9m backfill section, and the backfill section is formed by splicing shield segments.

Claims (5)

1. A shield receiving method in a circular small-section tunnel is characterized by comprising the following steps:
s1, advance support of the tunnel: adopting a mode of pre-grouting reinforcement for a large pipe shed and a self-advancing anchor rod in advance; the step S1 includes: the large pipe shed is made of P110 steel flower pipes with the diameter of 146mm and the wall thickness of 9mm, the arch crown is constructed within 120 degrees, the circumferential center distance is 300mm, the external insertion angle is 1-2 degrees, the number of the steel flower pipes per cycle is 31, the steel flower pipes are lapped according to 3m, the large pipe shed is grouted by cement single slurry with the water-cement ratio of 0.5-1.0, the grouting pressure is 0.5-1.2 MPa, the grouting sequence is from bottom to top, the two sides are arranged first and then the center are symmetrically grouted, and the grouting pressure is gradually increased from small to small; the self-advancing anchor rod is made of a hot-rolled seamless steel pipe with the diameter of 32mm, the wall thickness is 4mm, the length is 2.2m, the arch back is arranged within 120 degrees, the circumferential distance is 0.3m multiplied by 1.0m in the longitudinal direction, the external insertion angle is 10-15 degrees, the tail end of the steel pipe is arranged on the belly of the steel arch frame, cement paste with the water-cement ratio of 0.5-1.0 is adopted for grouting, and the grouting pressure is 0.3-0.5 MPa;
s2, primary support: the whole ring is provided with a steel arch frame;
s3, radial grouting reinforcement of the preliminary bracing arch back: pre-embedding a steel perforated pipe as a grouting pipe within 120 degrees of the vault during primary support construction, and performing grouting reinforcement;
s4, blocking and reinforcing the front soil body by the tunnel face: when the mine method tunnel is excavated to the position of a plug wall, C25 concrete is sprayed in time to close the tunnel face and pipe shed guide pipes are pre-buried;
s5, secondary lining of the tunnel: constructing a secondary lining with the thickness of 200mm under the condition of not dismantling the support;
s6, shield tunneling section advance support: after finishing secondary lining, drilling an advanced large pipe shed within 120 degrees of the vault of the end head;
s7, mortar backfilling: after finishing secondary lining and end large pipe shed construction, removing the temporary steel support and backfilling and sealing a 9m interval by adopting plain cement slurry doped with a proper amount of expanding agent;
s8, installing a guide table: pouring a C20 fine-stone concrete guide table at the bottom of the circular tunnel, and embedding and installing a steel plate and a guide rail;
s9, precipitation: a tunnel construction dewatering well is utilized to dewater before shield receiving;
s10, shield receiving: the shield is directly tunneled and received on the guide table through a 9m backfill section, and the backfill section is formed by splicing shield segments.
2. The method for receiving the shield in the circular small-section tunnel according to claim 1, wherein: the step S2 includes: the steel arch is arranged in a full ring, the interval between I20a steel arches is 0.5m, double-layer steel bar meshes with the diameter of 8mm form a grid of 150mm multiplied by 150mm, and the full ring is arranged in double layers and is respectively arranged on the inner side and the outer side of the steel arch; longitudinal connecting ribs with the diameter of 22mm are arranged on the inner side and the outer side, and the circumferential distance between the longitudinal connecting ribs is 1.0 m; the sprayed concrete is C25P6 early strength concrete, the sprayed and mixed thickness is 300mm, the full-section support is realized, and the thickness of the middle partition plate and the temporary inverted arch support is 250 mm; the foot locking anchor rod adopts an R32S self-drilling foot locking anchor pipe, the length of the foot locking anchor pipe is 3.0m, the foot locking anchor rod is arranged at the position of a circumferential joint of a primary support steel arch frame and the position of a guide pit corner part of a sub-excavation, the longitudinal distance is the same as the longitudinal distance of the steel arch frame, grouting pipes are embedded in the arch crown 120-degree range, the circumferential distance is 2.0m multiplied by 2.0m in the longitudinal direction and are arranged in a quincunx mode, the grouting pipes adopt steel pipes with the diameter of 32mm and the wall thickness of 3.5mm, and the.
3. The method for receiving the shield in the circular small-section tunnel according to claim 1, wherein: the step S3 includes: the diameter of the steel perforated pipe is 42mm, the wall thickness is 3.5mm, the length is the primary support thickness +0.5m, the distance between grouting pipes is 2.0m in the circumferential direction and 2.0m in the longitudinal direction, the steel perforated pipe is arranged in a quincunx manner, after the primary support is closed into a ring with the length of 50m, cement paste is injected to the back of the primary support arch in a pressing mode, the water-cement ratio of the cement paste is 0.5-1.0, and the grouting pressure is 0.1-0.3 MPa.
4. The method for receiving the shield in the circular small-section tunnel according to claim 1, wherein: the step S4 includes: the sprayed C25 concrete seals the tunnel face, the thickness of the sprayed concrete is 300mm, a 150mm multiplied by 150mm grid is formed by double layers of glass fiber reinforcements with the diameter of 12mm in the concrete and is connected with a primary support grid, and grouting holes are reserved during construction of the plug wall.
5. The method for receiving the shield in the circular small-section tunnel according to claim 1, wherein: the step S6 includes: the large pipe shed adopts P110 steel flower pipes with the diameter of 146mm and the wall thickness of 9mm, the circular center interval of 300mm is beaten on the arch back, the outer inserting angle is 1-2 degrees, the length of the large pipe shed is 20m, the large pipe shed adopts cement paste single liquid cement paste with the water cement ratio of 0.5-1.0, and the grouting pressure is 0.5-1.2 MPa.
CN201810600751.5A 2018-06-12 2018-06-12 Shield receiving method in circular small-section tunnel Active CN108915702B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810600751.5A CN108915702B (en) 2018-06-12 2018-06-12 Shield receiving method in circular small-section tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810600751.5A CN108915702B (en) 2018-06-12 2018-06-12 Shield receiving method in circular small-section tunnel

Publications (2)

Publication Number Publication Date
CN108915702A CN108915702A (en) 2018-11-30
CN108915702B true CN108915702B (en) 2020-09-22

Family

ID=64410827

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810600751.5A Active CN108915702B (en) 2018-06-12 2018-06-12 Shield receiving method in circular small-section tunnel

Country Status (1)

Country Link
CN (1) CN108915702B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110792457A (en) * 2019-10-12 2020-02-14 成都建工路桥建设有限公司 Tunnel portal structure installation method for shield tunneling through mine tunnel
CN110985016B (en) * 2019-12-16 2021-02-09 中铁一局集团有限公司 Quick receiving method of shield machine suitable for hard rock stratum in mine tunnel
CN114135318A (en) * 2021-12-06 2022-03-04 江西丰强科技发展有限公司 Closely-adhered underpass tunnel lining structure and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11247585A (en) * 1998-12-10 1999-09-14 Mitsui Constr Co Ltd Shield backfilling equipment
CN103953355A (en) * 2014-04-23 2014-07-30 中铁十五局集团有限公司 Method of acceptance construction in slurry shield tunnel
CN104790959A (en) * 2015-04-03 2015-07-22 核工业井巷建设公司 Shallowly buried small-spacing rock soil tunnel construction method
CN104790971A (en) * 2015-04-03 2015-07-22 核工业井巷建设公司 Large pipe shed advanced pre-reinforcement method for shallow buried small-spacing rock soil tunnel construction
CN106437726A (en) * 2016-11-02 2017-02-22 中铁二十局集团第五工程有限公司 Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN107091101A (en) * 2017-03-27 2017-08-25 中铁隧道勘测设计院有限公司 Mine shield handing-over tunnel folded type joint design and construction method in the middle part of marine site

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11247585A (en) * 1998-12-10 1999-09-14 Mitsui Constr Co Ltd Shield backfilling equipment
CN103953355A (en) * 2014-04-23 2014-07-30 中铁十五局集团有限公司 Method of acceptance construction in slurry shield tunnel
CN104790959A (en) * 2015-04-03 2015-07-22 核工业井巷建设公司 Shallowly buried small-spacing rock soil tunnel construction method
CN104790971A (en) * 2015-04-03 2015-07-22 核工业井巷建设公司 Large pipe shed advanced pre-reinforcement method for shallow buried small-spacing rock soil tunnel construction
CN106437726A (en) * 2016-11-02 2017-02-22 中铁二十局集团第五工程有限公司 Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN107091101A (en) * 2017-03-27 2017-08-25 中铁隧道勘测设计院有限公司 Mine shield handing-over tunnel folded type joint design and construction method in the middle part of marine site

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
跨海超长地铁隧道设计与施工关键技术研究;汤浩杰;《交通世界》;20160430(第11期);第72-75页 *

Also Published As

Publication number Publication date
CN108915702A (en) 2018-11-30

Similar Documents

Publication Publication Date Title
CN103306687B (en) Soft rock tunnel long cantilever horizontal jet grouting Deformation control construction method
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN109404005B (en) Pre-reinforcing system for small hole and large hole of underground tunnel and construction method
CN105041325A (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN101709651A (en) Grouting water blocking method for undersea tunnel
CN110735653A (en) deep-hole retreating type grouting water plugging construction method for igneous rock water-rich fault
CN110056369A (en) A kind of construction method at tunnel's entrance and exit hole
CN110878696B (en) Method for reinforcing surrounding rock of tunnel section at junction of upper soft and lower hard stratum shield method and mine method
CN202117686U (en) Surrounding rock advanced support structure for railway tunnel at deep-buried watery and weak stratums
CN102606168B (en) Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN108915702B (en) Shield receiving method in circular small-section tunnel
CN107091101A (en) Mine shield handing-over tunnel folded type joint design and construction method in the middle part of marine site
CN113073983B (en) Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
CN107165661A (en) A kind of high-ground stress weak surrounding rock large deformation tunnel overlength enlarged footing anchor cable construction method
CN107503755A (en) A kind of construction method for exempting from button arch flat-top cavern-pile method construction subway station
CN111396067A (en) Comprehensive shield steel sleeve receiving construction method in complex environment
CN208965598U (en) The Anti-seeping technology structure of grout curtain and underground chamber intersection area
CN104612696A (en) Construction method for underground excavated large-section subway station to pass through viaduct in fine sand layer based on pioneer heading-column method
CN112963156A (en) Composite reinforcing method and composite reinforcing structure for shallow tunnel in soil-rock composite stratum
CN114412475A (en) Reverse tunnel exit construction method for shallow-buried broken surrounding rock
CN108661652B (en) Reinforcing device and method for shield starting and receiving ends in mine tunnel
CN207406345U (en) Rich water sand-pebble layer shield tunnel end horizontal grouting ruggedized construction
CN104863613B (en) Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method
CN110735641B (en) Construction method of transfer passage of underpass pipeline
CN105840209B (en) Construction method for controlling deformation of anchor pile in tunnel body section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210125

Address after: 18-21 / F, Xiyuan building, intersection of Shun'an road and Yantai Road, Jinan west railway station, Shandong Province

Patentee after: CHINA RAILWAY 21 BUREAU GROUP RAIL TRANSIT ENGINEERING Co.,Ltd.

Patentee after: THE 2ND ENGINEERING CO., LTD. OF CHINA RAILWAY 22ND BUREAU Group

Address before: 18-21 / F, Xiyuan building, intersection of Shun'an road and Yantai Road, Jinan west railway station, Shandong Province

Patentee before: CHINA RAILWAY 21 BUREAU GROUP RAIL TRANSIT ENGINEERING Co.,Ltd.