CN107700503B - A kind of dry packet sandbag construction method based on hydraulic reclamation reef sand cofferdam - Google Patents
A kind of dry packet sandbag construction method based on hydraulic reclamation reef sand cofferdam Download PDFInfo
- Publication number
- CN107700503B CN107700503B CN201710639810.5A CN201710639810A CN107700503B CN 107700503 B CN107700503 B CN 107700503B CN 201710639810 A CN201710639810 A CN 201710639810A CN 107700503 B CN107700503 B CN 107700503B
- Authority
- CN
- China
- Prior art keywords
- sandbag
- dry packet
- sand
- construction
- cofferdam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/02—Restraining of open water
- E02D19/04—Restraining of open water by coffer-dams, e.g. made of sheet piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/18—Making embankments, e.g. dikes, dams
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
Abstract
, construction survey and setting-out, the processing of geotextile bag body the present invention relates to a kind of dry packet sandbag construction methods based on hydraulic reclamation reef sand cofferdam, characterized by the following steps: (1);(2), foundation trench excavates;(3), geotextile is laid with bag body;(4), cofferdam bag body is constructed, the dry packet sandbag filling of bottom, the dry packet sandbag filling in middle layer, the dry packet sandbag filling in upper layer;(5), after the completion of the body of weir, protection geotextiles is laid with and is laid with sun-proof geotextiles in time after the completion of the bath of top layer sand pocket is closely knit, wraps up entire sand pocket cofferdam.The present invention solves the problems, such as to gather materials on the spot in material shortage, the transportation cost regional hydraulic reclamation cofferdam construction such as higher, easy for construction, it is loose to packing material Particle size requirements, cofferdam can be quickly formed, the advantages that greatly reducing construction cost, accelerate construction speed.The method sufficiently demonstrates its exploitativeness and economical by engineering construction example.
Description
Technical field
The invention belongs to dredging and reclamation cofferdam construction technical fields, more particularly to a kind of dry based on hydraulic reclamation reef sand cofferdam
Packet sandbag construction method.
Background technique
In some special regions, engineering material extremely lacks, and transportation cost is higher.Using well-known technique and traditional construction
Technique, not only construction cost is higher, and material supply is also difficult to ensure construction needs.The present invention takes full advantage of the hydraulic reclamation of dredger
Main material of the material as engineering, had both met the needs of construction, ensure that construction speed, and engineering cost is greatly saved.
Summary of the invention
The present invention provides one kind to solve technical problem present in well-known technique, and cost is relatively low, simple process, construction
Fast, strong operability, solve the problems, such as the regional hydraulic reclamation cofferdam construction such as poor, transport difficult of material based on hydraulic reclamation
The dry packet sandbag construction method in reef sand cofferdam.
The technical scheme adopted by the present invention to solve the technical problems existing in the known art is that
A kind of dry packet sandbag construction method based on hydraulic reclamation reef sand cofferdam, characterized by the following steps: (1), apply
Work measurement and setting-out, the processing of geotextile bag body, go out axis and set steel on the face Yuan Jiao 1 before constructing using measuring instrument measuring
Pipe is identified, and is suitably encrypted in arc section and dog-ear section;Geotextiles are cut by geotextile bag body computational length
Several, then the protection geotextiles cut are sewed into code requirement according to geotextiles along its length, it sews up into needed for cloth bag
Width;
(2), foundation trench excavates: hydraulic reclamation was taken at the land stage and first blew back wall early period, was directly filled out backfill reef sand blast by dredger
To cofferdam construction region, foundation trench is dug on the spot with excavator, foundation trench width determines that grooving length is bigger by the dry packet sandbag width of bottom
In cofferdam construction length, foundation trench excavates the nearest other side of reef sand in foundation trench two sides, use when backfilling;
It after land-based area takes on a certain scale, takes and first encloses after-blow, soil construction is first returned with dump truck by hydraulic reclamation region
It fills out to form work surface, backfill section width is determined according to builder's road and weir bottom width degree;
(3), geotextile is laid with bag body, and the bottom of the dry packet sandbag body of bottom is fixed using the steel pipe set in advance;
(4), cofferdam bag body is constructed, the dry packet sandbag filling of bottom: surveying and locating first, using steel pipe the dry packet sandbag of bottom
The bottom of body is fixed, and then in excavator back-up sand to the dry packet sandbag body of bottom, bottom is done with portable sewing machine after sand is full
Packet sandbag body is sewed it up, and is finally washed by water closely knit;When thickness is insufficient or local eminence, artificial stop-off high-pressure water pipe should be flattened or used in time
Water-filling leveling;
The dry packet sandbag filling in middle layer: the dry packet sandbag in middle layer is laid with above the dry packet sandbag body of bottom;Equally, excavator is utilized
In back-up sand to the dry packet sandbag body in middle layer, the dry packet sandbag body in middle layer is sewed it up with portable sewing machine after sand is full, is finally washed by water close
It is real;It, should artificial stop-off leveling in time or with the leveling of high-pressure water pipe water-filling when thickness is insufficient or local eminence;
The dry packet sandbag filling in upper layer: the dry packet sandbag in upper layer is laid with above the dry packet sandbag body in middle layer;Equally, it is filled out using excavator
In sand to the dry packet sandbag body in upper layer, the dry packet sandbag body in upper layer is sewed it up with portable sewing machine after sand is full, is finally washed by water closely knit;
It, should artificial stop-off leveling in time or with the leveling of high-pressure water pipe water-filling when thickness is insufficient or local eminence;
(5), after the completion of the body of weir, protection geotextiles is laid with and are laid with sun-proof geotechnique in time after the completion of the bath of top layer sand pocket is closely knit
Cloth wraps up entire sand pocket cofferdam.
The advantages and positive effects of the present invention are: the present invention efficiently solve it is higher in material shortage, transportation cost
Deng the problem of regional hydraulic reclamation cofferdam construction, can gather materials on the spot, it is easy for construction, it is loose to packing material Particle size requirements, it can quick shape
At cofferdam, the advantages that greatly reducing construction cost, accelerate construction speed.The method is sufficiently demonstrated by engineering construction example
Its exploitativeness and economical.
Detailed description of the invention
Fig. 1, backfill work surface schematic diagram;
Fig. 2, foundation trench excavated section schematic diagram;
Fig. 3, dry packet sandbag cofferdam schematic diagram;
In figure: 1, the face Yuan Jiao;2, reef sand is backfilled;3, foundation trench excavates reef sand;4, foundation trench;5, the dry packet sandbag of bottom;6, middle layer
Dry packet sandbag;7, the dry packet sandbag in upper layer;8, geotextiles are protected.
Specific embodiment
In order to further understand the content, features and effects of the present invention, the following examples are hereby given, and cooperate attached drawing
Detailed description are as follows:
It please refers to Fig.1 to Fig.3, a kind of dry packet sandbag construction method based on hydraulic reclamation reef sand cofferdam includes the following steps:
(1), construction survey and setting-out, the processing of geotextile bag body, go out axis and on the face Yuan Jiao 1 using measuring instrument measuring before constructing
It sets steel pipe to be identified, suitably be encrypted in arc section and dog-ear section;Geotextiles are pressed into geotextile bag body computational length
Several are cut into, then the protection geotextiles cut are sewed into code requirement according to geotextiles along its length, sews up into cloth bag
Required width;
(2), foundation trench excavates: hydraulic reclamation was taken at the land stage and first blew back wall early period, was directly blown backfill reef sand 2 by dredger
It is filled to cofferdam construction region, digs foundation trench 4 on the spot with excavator, foundation trench width is determined by the dry packet sandbag width of bottom, grooving length
Slightly larger than cofferdam construction length, foundation trench excavates the nearest other side of reef sand 3 in foundation trench two sides, use when backfilling;
It after land-based area takes on a certain scale, takes and first encloses after-blow, soil construction is first returned with dump truck by hydraulic reclamation region
It fills out to form work surface, backfill section width is determined according to builder's road and weir bottom width degree;
(3), geotextile is laid with bag body, and the bottom of the dry packet sandbag body of bottom is fixed using the steel pipe set in advance;
(4), cofferdam bag body is constructed: the dry packet sandbag filling of bottom: surveying and locating first, using steel pipe the dry packet sandbag of bottom
The bottom of body 6 is fixed, and then in excavator back-up sand to the dry packet sandbag body of bottom, bottom is done with portable sewing machine after sand is full
Packet sandbag body is sewed it up, and is finally washed by water closely knit;When thickness is insufficient or local eminence, artificial stop-off high-pressure water pipe should be flattened or used in time
Water-filling leveling;
The dry packet sandbag filling in middle layer: the dry packet sandbag in middle layer is laid with above the dry packet sandbag body of bottom;Equally, excavator is utilized
In back-up sand to the dry packet sandbag body 7 in middle layer, the dry packet sandbag body in middle layer is sewed it up with portable sewing machine after sand is full, is finally washed by water close
It is real;It, should artificial stop-off leveling in time or with the leveling of high-pressure water pipe water-filling when thickness is insufficient or local eminence;
The dry packet sandbag filling in upper layer: the dry packet sandbag in upper layer is laid with above the dry packet sandbag body in middle layer;Equally, it is filled out using excavator
In sand to the dry packet sandbag body 8 in upper layer, the dry packet sandbag body in upper layer is sewed it up with portable sewing machine after sand is full, is finally washed by water close
It is real;It, should artificial stop-off leveling in time or with the leveling of high-pressure water pipe water-filling when thickness is insufficient or local eminence;
(5), after the completion of the body of weir, protection geotextiles is laid with and are laid with sun-proof geotechnique in time after the completion of the bath of top layer sand pocket is closely knit
Cloth wraps up entire sand pocket cofferdam.
In conclusion this construction method simple process, easy for construction, efficiently solve material shortage, transportation cost compared with
The problem of high area hydraulic reclamation cofferdam construction, can gather materials on the spot, loose to packing material Particle size requirements, can quickly form cofferdam,
The advantages that greatly reducing construction cost, accelerating construction speed.The method is sufficiently demonstrated implementable by engineering construction example
Property and economical.
The above is only the preferred embodiments of the present invention, and is not intended to limit the present invention in any form,
Any simple modification made to the above embodiment according to the technical essence of the invention, equivalent variations and modification, belong to
In the range of technical solution of the present invention.
Claims (1)
1. a kind of dry packet sandbag construction method based on hydraulic reclamation reef sand cofferdam, characterized by the following steps:
(1), construction survey and setting-out, the processing of geotextile bag body, go out axis and in Yuan Jiao using measuring instrument measuring before constructing
Steel pipe is set on face (1) to be identified, and is suitably encrypted in arc section and dog-ear section;By geotextiles based on geotextile bag body
It calculates length and is cut into several, then the protection geotextiles cut are sewed into code requirement according to geotextiles along its length, sew up
At width needed for cloth bag;
(2), foundation trench excavates: hydraulic reclamation was taken at the land stage and first blew back wall early period, is directly filled to backfill reef sand blast by dredger and encloses
Weir construction area digs foundation trench with excavator on the spot, and foundation trench width is determined by the dry packet sandbag width of bottom, and grooving length, which is slightly larger than, encloses
Weir construction length, foundation trench excavate the nearest other side of reef sand in foundation trench two sides, use when backfilling;
It after land-based area takes on a certain scale, takes and first encloses after-blow, soil construction first backfills shape with dump truck by hydraulic reclamation region
At work surface, backfills section width and determined according to builder's road and weir bottom width degree;
(3), geotextile is laid with bag body, and the bottom of the dry packet sandbag body of bottom is fixed using the steel pipe set in advance;
(4), cofferdam bag body is constructed, the dry packet sandbag filling of bottom: surveying and locating first, using steel pipe the dry packet sandbag body of bottom
Bottom is fixed, and then in excavator back-up sand to the dry packet sandbag body of bottom, bottom is done Bao Sha with portable sewing machine after sand is full
Bag body is sewed it up, and is finally washed by water closely knit;It, should artificial stop-off leveling in time or with high-pressure water pipe water-filling when thickness is insufficient or local eminence
Leveling;
The dry packet sandbag filling in middle layer: the dry packet sandbag in middle layer is laid with above the dry packet sandbag body of bottom;Equally, excavator back-up sand is utilized
To the dry packet sandbag body in middle layer, the dry packet sandbag body in middle layer is sewed it up with portable sewing machine after sand is full, is finally washed by water closely knit;It is thick
It, should artificial stop-off leveling in time or with the leveling of high-pressure water pipe water-filling when degree is insufficient or local eminence;
The dry packet sandbag filling in upper layer: the dry packet sandbag in upper layer is laid with above the dry packet sandbag body in middle layer;Equally, extremely using excavator back-up sand
In the dry packet sandbag body in upper layer, the dry packet sandbag body in upper layer is sewed it up with portable sewing machine after sand is full, is finally washed by water closely knit;Thickness
It, should artificial stop-off leveling in time or with the leveling of high-pressure water pipe water-filling when insufficient or local eminence;
(5), after the completion of the body of weir, protection geotextiles is laid with and are laid with sun-proof geotextiles in time after the completion of the bath of top layer sand pocket is closely knit,
Wrap up entire sand pocket cofferdam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710639810.5A CN107700503B (en) | 2017-07-31 | 2017-07-31 | A kind of dry packet sandbag construction method based on hydraulic reclamation reef sand cofferdam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710639810.5A CN107700503B (en) | 2017-07-31 | 2017-07-31 | A kind of dry packet sandbag construction method based on hydraulic reclamation reef sand cofferdam |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107700503A CN107700503A (en) | 2018-02-16 |
CN107700503B true CN107700503B (en) | 2019-07-09 |
Family
ID=61170794
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710639810.5A Active CN107700503B (en) | 2017-07-31 | 2017-07-31 | A kind of dry packet sandbag construction method based on hydraulic reclamation reef sand cofferdam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107700503B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108625417A (en) * | 2018-05-22 | 2018-10-09 | 四川城凯特建设工程有限公司 | A kind of channel cleanout method and its device |
CN110284393A (en) * | 2019-06-28 | 2019-09-27 | 中国二十冶集团有限公司 | The method of peat soil soft base build sidewalk |
CN110924364A (en) * | 2019-12-10 | 2020-03-27 | 安庆市水利水电规划设计院 | River-blocking weir gate anti-impact deep tooth wall and construction method thereof |
CN112900357A (en) * | 2021-03-03 | 2021-06-04 | 中交上海航道勘察设计研究院有限公司 | Degradable geotextile filling bag |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11256588A (en) * | 1998-03-12 | 1999-09-21 | Kajima Corp | Underwater strut constructing method |
CN201891104U (en) * | 2010-11-11 | 2011-07-06 | 上海勘测设计研究院 | Combination bag outer prism structure for tidal flat reclamation |
CN105178245A (en) * | 2015-08-18 | 2015-12-23 | 水利部交通运输部国家能源局南京水利科学研究院 | Large filling bag ecological embankment and revetment building method for river lake channel |
-
2017
- 2017-07-31 CN CN201710639810.5A patent/CN107700503B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11256588A (en) * | 1998-03-12 | 1999-09-21 | Kajima Corp | Underwater strut constructing method |
CN201891104U (en) * | 2010-11-11 | 2011-07-06 | 上海勘测设计研究院 | Combination bag outer prism structure for tidal flat reclamation |
CN105178245A (en) * | 2015-08-18 | 2015-12-23 | 水利部交通运输部国家能源局南京水利科学研究院 | Large filling bag ecological embankment and revetment building method for river lake channel |
Also Published As
Publication number | Publication date |
---|---|
CN107700503A (en) | 2018-02-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107700503B (en) | A kind of dry packet sandbag construction method based on hydraulic reclamation reef sand cofferdam | |
CN105201518B (en) | Disassembling method is received in a kind of major diameter slurry balance shield hole | |
CN103225267B (en) | Construction method of deep and thick soft soil foundation bed bridge abutment | |
CN2911010Y (en) | Fast reinforcing apparatus for blowing-filling sludge ground | |
CN107254878B (en) | A kind of excavation method of hydroelectric project dam abutment high gradient slope control dust | |
CN203668885U (en) | Novel hydraulic reclamation mould bag | |
CN208965598U (en) | The Anti-seeping technology structure of grout curtain and underground chamber intersection area | |
CN105781556A (en) | Construction method for shield to penetrate through shallow-covered urban landscape lake downwards | |
CN103255762B (en) | Method of leading Yellow River silt to fill reclamation coal mining subsidence land | |
CN107859062A (en) | The earth-filling method of underground pipe gallery | |
CN104652409B (en) | A kind of forced-ventilated water continuously combines the close soft foundation processing technology method of rammer | |
CN107816050A (en) | A kind of concrete cofferdam and earth rock cofferdam combined cofferdam and its construction method | |
CN105971638A (en) | Application of WSS construction method in shield tool changing reinforcement of water-rich sand layer | |
US2757514A (en) | Method of forming an impermeable wall in the terrain | |
CN103276717B (en) | The method of composite earthwork synthetic materials reinforcement cushion soft soil foundation | |
CN106884427A (en) | Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water | |
CN107190709B (en) | Method for building river channel in newly dredged soil reclamation land-enclosed area | |
CN101481913A (en) | Construction method of rock-socketed underground continuous wall punching slot section | |
CN106761914B (en) | A kind of routed water water damage prevention and controls of shallow buried coal seam mine raceway groove flood | |
CN107881987A (en) | Deep covering layer top panel Rockfill Dam based moisture barrier structure | |
CN103422467B (en) | Mucky soil filling bag embankment method | |
CN106120827A (en) | Freeze to make end water-bound and method inside a kind of sensitizing range, city tunneling foundation ditch | |
CN107859040A (en) | A kind of excavation method of foundation ditch large area soft soil horizon | |
CN111197300B (en) | Earth-rock cofferdam back slope type seepage-proofing dam and reverse construction method | |
CN102182867B (en) | Method for laying ore pulp pipelines in quicksand bed section |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |