CN106884427A - Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water - Google Patents

Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water Download PDF

Info

Publication number
CN106884427A
CN106884427A CN201710200234.4A CN201710200234A CN106884427A CN 106884427 A CN106884427 A CN 106884427A CN 201710200234 A CN201710200234 A CN 201710200234A CN 106884427 A CN106884427 A CN 106884427A
Authority
CN
China
Prior art keywords
under water
immersed tube
tube tunnel
soft soil
compaction pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710200234.4A
Other languages
Chinese (zh)
Inventor
卢永昌
梁桁
林佑高
李建宇
何洪涛
王征亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC FHDI Engineering Co Ltd
Original Assignee
CCCC FHDI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC FHDI Engineering Co Ltd filed Critical CCCC FHDI Engineering Co Ltd
Priority to CN201710200234.4A priority Critical patent/CN106884427A/en
Publication of CN106884427A publication Critical patent/CN106884427A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/08Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Sciences (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a kind of immersed tube tunnel under water, including the Soft Soil Layer under water reinforced with sand compaction pile, and the block stone bed course and blotter being laid on successively on the Soft Soil Layer under water;The immersed tube tunnel laid above blotter, immersed tube tunnel top and both sides are backfill block stone structures;Height of the laying level height of the immersed tube tunnel less than Soft Soil Layer under water;The transverse width of the transverse width more than immersed tube tunnel of the described Soft Soil Layer under water, block stone bed course and blotter reinforced with sand compaction pile.The present invention sets horizontal block stone bed course form compound foundation using sand compaction pile displacement, compacted weak soil, can effectively improve foundation bearing capacity, reduce residual settlement after work, reaches the purpose of reinforcing soft ground.The method has that foundation stabilization effect is good, economic and environment-friendly, depth is big for treatment, the manageable advantage of construction quality.

Description

Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water
Technical field
The present invention relates to foundation treatment technology, more particularly to one kind immersed tube tunnel changeover portion soft soil foundation and its reinforcing under water Method, belongs to bridge tunnel engineering construction technical field.
Background technology
In recent years, Transportation Infrastructure Construction quickly grows, and large quantities of bridge spanning the seas and passage start to build, more and more Tunnel in sea, bridge, man-made island engineering construction on complicated offshore soft foundation.Under water immersed tube tunnel itself load compared with It is small, mainly based on anti-floating power, need not generally carry out basement process, but immersed tube tunnel changeover portion under water, i.e. water The joining place of lower immersed tube tunnel and man-made island, immersed tube tunnel is gradually transferred under water by waterborne, soft soil foundation buried depth thickness change compared with Greatly, physico-mechanical properties is poor, if being easy to larger relative settlement without basement process immersed tube tunnel, ground holds Power is carried also to be difficult to reach design requirement.Using excavation cushion, normal sands more than the method for processing foundation of immersed tube tunnel soft soil foundation Well draining concretion method, slip casting method, pile foundation method etc..
Excavate cushion pass through to excavate, the soft layer below replacing base bottom surface, then returned with the preferable material of property Fill out and be compacted, good artificial foundation can be formed.But underwater excavation changes and fills out that not only quantities is big, involves great expense, and substantial amounts of Silt leakage will cause tremendous influence to marine environment.
Common sand drain draining concretion method typically uses piling prepressing, with reference to common sand drain as vertical drainage passage to weak soil Ground is improved.By the precompressed of certain hour, weak soil intensity gradually increases, and most of sedimentation can be completed in the precompressed phase, most Eventually design requirement is can reach after unloading.But draining concretion method process time is long, work efficiency is low, residual settlement is larger after work.
Slip casting method carries out slip casting to immersed tube tunnel base foundation by Grouting Pipe, forms injecting cement paste, it is adaptable to soft foundation, Sedimentation can be reduced, foundation bearing capacity is improved, sand liquefaction can be also prevented.But slurry injection technique difficulty of construction is larger, the cycle is long, and deposits In environmental protection, construction detection and quality Control.
Pile foundation method is more universal in Western European countries' application, it is adaptable to soft soil foundation, but immersed tube tunnel axis direction substrate soil Soft or hard uneven, pile foundation is rigid structure, and immersed tube is more easy to the problem that differential settlement occurs.Additionally, pile cover installation under water is tired It is difficult.
The pars infrasegmentalis of immersed tube tunnel transition under water generally there are the mud or silt soil strata of thickness change, and reinforcing this layer of soil is The key of basement process, how to seek it is a kind of can it is economic and environment-friendly and meanwhile again can effectively reinforcing soft soil layer method it is most important.
The content of the invention
It is an object of the invention to overcome, difficulty of construction existing for Soft Soil Subgrade Treatment Techniques in the prior art is big, cost It is high, long in time limit, the problems such as ambient influnence is big or deficiency, there is provided a kind of soft soil foundation reinforcing method.It is particularly a kind of to be applied to water Lower immersed tube tunnel transition section soft soil foundation reinforcing method.The soft soil foundation reinforcing method significantly reduces underwater excavation and changes the amount of filling out simultaneously Cost is reduced, the Soft Soil Layer of different buried depth can be effectively reinforced, is a kind of economic and environment-friendly ground while avoiding pile body age problem Processing method.
In order to realize foregoing invention purpose, the invention provides following technical scheme:
A kind of immersed tube tunnel under water, including the Soft Soil Layer under water reinforced with sand compaction pile, and the weak soil under water is laid on successively Block stone bed course and blotter on layer, the immersed tube tunnel laid above blotter, immersed tube tunnel top and both sides are Backfill block stone structure.Less than the height of Soft Soil Layer under water, i.e., Soft Soil Layer passes through the laying level height of the immersed tube tunnel under water Excavation treatment so that the Soft Soil Layer under water and block stone bed course thereon of sand compaction pile reinforcing, the aggregate level of blotter are highly Less than the level height of the Soft Soil Layer under water of surrounding.Soft Soil Layer under water that described sand compaction pile is reinforced, block stone bed course and broken The transverse width of stone bed course is more than the transverse width of immersed tube tunnel, to realize for the preferable supporting function of immersed tube tunnel.It is best It is that the transverse width of the Soft Soil Layer under water that blotter, block stone bed course and sand compaction pile are reinforced increases successively, realizes trapezium structure Supporting surface, the pressure for bearing immersed tube tunnel that can more stablize of supporting construction so that the stability of immersed tube tunnel is more preferable.
Wherein, described Soft Soil Layer under water is the conventional address of this area, is primarily referred to as subsea floor structure and excavates mud The later structure of soft clay layer of layer.Described backfill block stone structure realizes other each faces in addition to lower surface to immersed tube tunnel Protection is surrounded, the current scour effect under being acted on especially for undercurrent under water keeps out effect with good, can be good at Keep the long-time stability of immersed tube tunnel.
Described, immersed tube tunnel includes the appendage of immersed tube tunnel and its laying structure under water, the body of immersed tube tunnel and The accessory structures such as ground constitute the submerged tunnel of stabilization.Immersed tube tunnel under water of the present invention is the whole of composition immersed tube tunnel Body laying structure, is the global concept of submerged tunnel.
Further, 1.2 ~ 2.0m of the underwater sand compaction pile diameter.The layout density of sand compaction pile is moderate, lays compacted sand Preferably, the construction volume of sand compaction pile is also minimum for the structural stability of Soft Soil Layer under water of stake.Preferably, the replacement rate of sand compaction pile is 40%-70%。
Further, described block stone bed course is laid by the blocks of natural stone of 10 ~ 100kg or cast stone.Block stone Volume and weight is larger, under water with good stability, the stone material layer of effect closing soft soil foundation.Preferably, it is described Block stone bed course thickness be 1.0 ~ 3.0m.
It is existing to solve it is a further object of the present invention to provide a kind of soft soil foundation layer reinforcement means of above-mentioned immersed tube tunnel under water The immersed tube tunnel under water having soft soil foundation layer job specfication, and immersed tube tunnel construction quality guarantee.
A kind of immersed tube tunnel changeover portion soft soil foundation reinforcing method under water, comprises the following steps:
(1)Peel off soft soil foundation(That is Soft Soil Layer under water)The mud layer on surface.
(2)To Soft Soil Layer under water(That is soft soil foundation)Lay underwater sand compaction pile.
(3)Smart digging treatment is carried out to the Soft Soil Layer under water that sand compaction pile is reinforced, block stone bed course is then laid thereon.In block Blotter is laid on stone bed course.
The soft soil foundation of method of the present invention consolidation process, peels off the mud layer for removing soft soil foundation surface first so that The surface of Soft Soil Layer has preliminary intensity under water, is difficult occur large-scale mud interference in work progress, and suitably Foundation strength.Then, using sand compaction pile will reinforced soft soil ground under water, pre- depthkeeping is caused by the immersed tube bored sandstone of high pressure The soft soil foundation densification of degree, forms the composite foundation of immersed tube tunnel sand compaction pile under water, prevents building for soft soil foundation under water If after the completion of many decades in occur sedimentation variation.
Further, based on above-mentioned " soft soil foundation reinforcing method " the derivative laying of immersed tube tunnel under water engineering method:In step (3)Reinforce on the soft soil foundation for completing and lay the construction that immersed tube tunnel under water is immersed tube tunnel under water.Laying accordingly Immersed tube tunnel both sides and top spread backfill block stone closing, you can complete the laying work of immersed tube tunnel under water.
Soft soil foundation reinforcing method of the invention is particularly well-suited at the reinforced soft soil ground of immersed tube tunnel changeover portion under water Reason, can effectively reduce the work difficulty of the treatment of reinforced soft soil ground under water, improve the efficiency reinforced, and after ensureing to reinforce Soft soil foundation can carry submerged tunnel immersed tube after enough bracing forces be provided, it is ensured that the long time stability in tunnel Property.
By the treatment of sand compaction pile, Soft Soil Layer density basic forming, now still retains Soft Soil Layer under water and sand under water The easy impact mobility of stone mar.The corresponding upper block stone bed course of laying, block stone bed course is laid using block stone, and block stone is 10 ~ The blocks of natural stone of 100kg or cast stone, block stone volume and weight are larger, under water with good stability, effect envelope Close the stone material layer of soft soil foundation.Then metalling is equipped with block stone bed course, blotter is the rubble paving of some fritters Into rock layers, rubble can fill up the hole of block stone bed course, convenient to lay immersed tube tunnel thereon, fixed, and immersed tube tunnel Position adjustment.
Specifically after the laying of soft soil foundation reinforcing method under water immersed tube tunnel of the invention, the underwater cross section in tunnel Form schematic diagram should be horizontal bed course on sand compaction pile as shown in figure 1, bottom is sand compaction pile, and horizontal bed course includes Blotter 4 on block stone bed course 3 and block stone layer.Last immersed tube tunnel 5(Immersed tunnel structure)Positioning is routed on horizontal bed course, Connect multiple immersed tube tunnels sections after adjustment positioning, and in immersed tube tunnel upper berth last time fill block stone 6, just complete the paving of submerged tunnel If work.
Compared with prior art, beneficial effects of the present invention:
1. a kind of immersed tube tunnel changeover portion soft soil foundation reinforcing method under water that the present invention is provided, simple structure is reasonable in design, It is easy to promote.
2. soft soil foundation reinforcing method under water of the invention, by the sand compacted under water for laying major diameter, replacement rate high Stake, replaces and compacted Soft Soil Layer form compound foundation, is allowed to increase the foundation bearing capacity of upper load, and settlement after construction significantly subtracts It is small.
3. soft soil foundation reinforcing method under water of the invention, by setting the block stone bed course rammed after putting down, can be obviously reduced stake Native load share ratio, has played stake with native respective stress to a greater degree.
4. the inventive method environmental protection and economy, convenient and quick construction, depth is big, quality controllable for treatment, cost is relatively low, have Good economic and social benefit.
Brief description of the drawings:
Fig. 1 is the structural representation of immersed tube tunnel changeover portion soft soil foundation reinforcing method under water of the invention.
In figure:1- Soft Soil Layers, 2- sand compaction piles, 3- block stone bed courses, 4- blotters, 5- immersed tunnel structures, 6- is locked and returned Fill block stone, A1- slightly digs face, A2- essences digging face.
Specific embodiment
It is attached in specific implementation process, soft soil foundation reinforcing method of the invention is described as follows, at reinforcing Foundation structure after reason is divided into:Soft Soil Layer, sand compaction pile and block stone bed course, the compound ground of sand compaction pile that above three is collectively forming Base.The Soft Soil Layer is the natural weakness uniform ground of clay, and the sand compaction pile is uniform in length and breadth along immersed tube tunnel bearing of trend The underwater sand compaction pile of laying, described piece of stone bed course is by ramming the flat level being placed on Soft Soil Layer and sand compaction pile under water Bed course.
Further, the underwater sand compaction pile is along the laying of immersed tube under water direction parallel arrangement.Obviously it is of the invention to squeeze under water Close sand pile is multiple, and the compacted weak soil of sand compaction pile and corresponding part together constitutes compacted Soft Soil Layer, used as main gravity Bearing part, sand compaction pile is arranged along the laying direction of immersed tube tunnel, effectively immersed tube tunnel is provided a supporting role.
Further, the underwater sand compaction pile is the underwater sand compaction pile uniformly laid along immersed tube tunnel bearing of trend.Most It is well simultaneously uniform on direction in length and breadth laying, it is ensured that the uniformity of sand compaction pile.In work progress, sand compaction pile be usually earlier than The laying work of immersed tube tunnel, it is certain it is noted that controlling the laying direction of sand compaction pile so that structural integrity is more preferable.
Further, 1.2 ~ 2.0m of the underwater sand compaction pile diameter, replacement rate is 40% ~ 70%, through Soft Soil Layer.Control The diameter and replacement rate of sand compaction pile can be very good to control after the packing of sand compaction pile and sand compaction pile shaping most Whole support force, it is ensured that the stability of structure has important help.
The present invention sets horizontal block stone bed course form compound foundation using sand compaction pile displacement, compacted weak soil, can be effective Improve foundation bearing capacity, reduce work after residual settlement, reach the purpose of reinforcing soft ground, with foundation stabilization effect it is good, warp Ji is environmentally friendly, treatment depth is big, the manageable advantage of construction quality.
Further, during the sand compaction pile material is preferably, coarse sand, its clay content should be equal to or less than 5%, can be mixed in sand material Have a small amount of(Equal to or less than 10%)The gravel material of 5 ~ 20mm of particle diameter.During the sand compaction pile material is preferably, coarse sand, its clay content≤ 5%, gravel material≤10% of 5 ~ 20mm of particle diameter in sand material.
Further, the Soft Soil Layer is the natural weakness uniform ground of clay.
Further, step(1)Described in peel off the mud layer on soft soil foundation surface, be to excavate foundation trench for the first time, for the first time The cutting depth of foundation trench is more than 3m.The mud layer on soft soil foundation surface is peeled off, primarily with respect to the soft soil foundation knot of underwater complex The surface of structure layer is excavated, and removes the interference effect of mud layer, improves the consolidation effect of soft soil foundation layer.
Preferably, while forming thick face of digging after controlling to excavate for the first time foundation trench in design foundation trench bottom absolute altitude above 3.0m.Base Groove is slightly dug after completion, and sand compaction pile consolidation process is carried out to soft soil foundation.Then the Soft Soil Layer that sand compaction pile is reinforced is carried out Smart digging treatment(Second foundation trench is excavated), smart digging face is just constituted, as the bottom surface of design foundation trench.It is last to lay thereon accordingly Horizontal bed course, both block stone bed course and blotter.
Construction of foundation ditch process can form thick digging face and smart digging face, and more than foundation trench bottom absolute altitude is being designed about in the thick digging face 3.0m, the smart digging face is design foundation trench bottom absolute altitude.It is attached in embodiments of the invention 1, respective figure can be with easier This technology main points are understood, wherein the thick digging face A1 and essence digging face A2 of the excavation foundation trench for controlling, have corresponded to first time foundation trench and opened respectively Dig and second foundation trench is excavated.
Further, described piece of stone bed course is by ramming the flat level pad being placed on Soft Soil Layer and sand compaction pile under water Layer.I.e. block stone bed course is by ramming the flat horizontal bed course being placed on the Soft Soil Layer that sand compaction pile is reinforced under water.Block stone bed course It is main enclosed construction, by ramming flat treatment under water, the sealing process of block stone bed course more preferably, preferably maintains sand compaction pile Structural stability.
Further, described piece of stone bed course is by throwing waterborne and through ramming flat shape under water into 1.0 ~ 3.0m of thickness is placed in weak soil On layer and sand compaction pile.The thickness control of block stone bed course can well ensure the Stability Analysis of Structures of block stone bed course in 1.0 ~ 3.0m Property and for the sealing process of sand compaction pile foundation structure below.
Further, the block stone material that described piece of stone bed course is used is 10 ~ 100kg building stones for monolithic quality, and building stones are in water Intensity after being impregnated with is not less than 50MPa.Block stone bed course is the building stones being directly enclosed on the soft soil foundation layer of sand compaction pile solidification, Its monolithic quality and intensity should keep higher, because needing to keep its structure under the pressure of the immersed tube tunnel for bearing afterwards Integrality, to realize effective supporting role of immersed tube tunnel.
Further, block stone bed course rams flat under water using hydraulic vibration driver.Hydraulic vibration driver rams flat strength greatly under water, rams flat Effect is good, and cost is extremely low.
Parameters of construction technology in above-mentioned specific embodiment can also lay directly as immersed tube tunnel under water The restriction explanation of structure, might not be limited in above-mentioned engineering method, because the special parameter in construction inherently can be direct Remain into the middle of corresponding construction results.
With reference to test example and specific embodiment, the present invention is described in further detail.But this should not be understood For the scope of above-mentioned theme of the invention is only limitted to following embodiment, all technologies realized based on present invention belong to this The scope of invention.
Embodiment 1
As shown in figure 1, the schematic cross-section of seabed immersed tube tunnel, Soft Soil Layer 1 is excavated the thick digging face A2 of formation, in thick groove face Bottom Soft Soil Layer is reinforced by sand compaction pile 2, forms sand compaction pile portion.Essence is carried out to the Soft Soil Layer that sand compaction pile is reinforced and digs treatment shape Into smart digging face A1.It is block stone bed course 3 above sand compaction pile portion, is blotter 4 in the top of block stone bed course 3.Immersed tube knot Structure 5 is laid on the top of blotter 4, and is filled with locking and backfilling block stone 6.
The sand compaction pile composite foundation that Soft Soil Layer 1, sand compaction pile 2 and block stone bed course 3 are formed, the Soft Soil Layer 1 is day The right weakness uniform ground of clay, the sand compaction pile 2 is the sand compacted under water uniformly laid in length and breadth along immersed tube tunnel bearing of trend Stake, described piece of stone bed course 3 is by ramming the flat horizontal bed course being placed on Soft Soil Layer and sand compaction pile under water.Blotter 4 On block stone bed course 3, immersed tunnel structure 5 is located on blotter 4, is finally locked and is backfilled block stone 6 and be located at immersed tunnel structure 5 Around.Both it had been the overall structure of seabed immersed tube tunnel of the invention.
Further, construction method of the invention is illustrated with reference to specific construction note.
Immersed tube tunnel changeover portion reinforced soft soil ground under water, with reference to shown in Fig. 1, its specific work process is:
S1, immersed tube tunnel basic engineering, using sand compaction pile composite foundation, after determining immersed tube tunnel design foundation bearing capacity, work Residual settlement and relative settlement requirement, reinforcing scope, reinforcement depth and replacement rate(It is determined that stake footpath and stake spacing).
S2, immersed tube tunnel foundation trench slightly dig, and form thick digging face A1.
Wherein, the thick face A1 that digs is in design foundation trench bottom absolute altitude above 3.0m.
S3, in Soft Soil Layer 1 using construction process of underwater sand compaction pile formed sand compaction pile 2.
Wherein, 2 1.2 ~ 2.0m of footpath of sand compaction pile, replacement rate is 40% ~ 70%, and big replacement rate sand compaction pile composite foundation can Meet the design requirement of immersed tube tunnel foundation bearing capacity, residual settlement and relative settlement;The stake top absolute altitude of sand compaction pile 2 should not be low More than the absolute altitude of design foundation trench bottom at one times of sand compaction pile stake footpath;The stake bottom absolute altitude of sand compaction pile 2 preferably penetrates Soft Soil Layer 1, and Into the hard stratum of lower sleeping certain depth;When stake bottom absolute altitude reaches design stake bottom absolute altitude, if the injection speed of sand pile sleeve pipe Occur continuing 10s being not more than 1.0m/min, and sand pile set ttom of pipe absolute altitude with design stake bottom absolute altitude difference when being not more than 3.0m, can stop Only sand pile sleeve pipe injection and in this, as stake bottom absolute altitude.
S4, immersed tube tunnel foundation trench essence are dug, and form essence digging face A2.
Wherein, smart digging face A2 is design foundation trench bottom absolute altitude;Foundation trench essence is dug and should remove underwater sand compaction pile work progress hogging The mud for rising, it is ensured that subsequent block stone bed course is free of sludge interlayer 3 times.
S5, fill block stone throwing are gone forward side by side and ram under water-filling flat, form block stone bed course 3.
Wherein, 1.0 ~ 3.0m of throwing thickness, 10 ~ 100kg block stones, should be according to design requirement, construction ability, tidal level and wave shadow Ring, it is determined that layering and section construction order;The block stone bed course for ramming after putting down under water should meet correlated quality acceptance criteria and specification will Ask.
Also include before step S4 after embodiment of the present invention step S3:
Pile body compactness inspection should be carried out after the completion of step S3', sand compaction pile construction, to determine or readjust design foundation trench bottom Absolute altitude;When the SPT blow count for detecting the design foundation trench bottom following pile body of absolute altitude is less than standard value(Average SPT blow count is not less than 20 Hit, average SPT blow count hits not less than 12 in the range of stake top 2.0m)When, should supplement and set sand compaction pile;When detecting design base The SPT blow count of the following pile body of bottom land absolute altitude is more than or equal to standard value(Average SPT blow count hits not less than 20, stake top 2.0m models Interior average SPT blow count is enclosed to be hit not less than 12)Shi Jinhang steps S4.
Embodiments of the invention are illustrated with reference to Fig. 1, wherein the surface excavated for the first time reaches A1 faces, by weak soil ground Mud layer on base is to stripping so that mud interference discharge under water, because mud is unformed cannot also to reinforce qualitative, directly Connect to be peeled off and expose soft soil foundation layer.It is full soft soil foundation layer under A1 faces, now the soft soil foundation layer to A1 faces squeezes into water Lower sand compaction pile, you can realize the basic solidification for the bottom of laying immersed tube tunnel later.By the solidification of sand compaction pile The Soft Soil Layer ground of immersed tube tunnel has obtained sufficient solidification under water, soft soil foundation essence is dug again then and reaches A2 faces.At smart digging The packing that reason is primarily due to sand compaction pile sand compaction pile of soft soil foundation surface portion in construction is relatively low, and essence is excavated soft The part of soil primary surface, the actual packing of the further soft soil foundation layer for improving sand compaction pile treatment.Now in A2 faces The upper block stone bed course of last time laying and blotter are used as closing so that the base fixed reliability of immersed tube tunnel laying.Such as Fig. 1 institutes Show, after immersed tube tunnel has laid, immersed tube tunnel 5 is closed, the immersed tube tunnel cross section structure of formation shows, immersed tube The various pieces in tunnel are all closed well, belong to half embedded structure, and it is good to wash away resistance for ocean current under water.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, on the premise of the technology of the present invention principle is not departed from, some improvement and replacement can also be made, these improve and replace Also should be regarded as protection scope of the present invention.

Claims (10)

1. one kind immersed tube tunnel under water, including the Soft Soil Layer under water reinforced with sand compaction pile, and be laid on successively described soft under water Block stone bed course and blotter on soil layer;
The immersed tube tunnel laid above blotter, immersed tube tunnel top and both sides are backfill block stone structures;
Height of the laying level height of the immersed tube tunnel less than Soft Soil Layer under water;
The transverse width of the described Soft Soil Layer under water, block stone bed course and blotter reinforced with sand compaction pile is more than immersed tube tunnel Transverse width.
2. immersed tube tunnel under water as claimed in claim 1, it is characterised in that blotter, block stone bed course and sand compaction pile are reinforced The transverse width of Soft Soil Layer under water increase successively.
3. immersed tube tunnel under water as claimed in claim 1, it is characterised in that 1.2 ~ 2.0m of the underwater sand compaction pile diameter.
4. immersed tube tunnel under water as claimed in claim 1, it is characterised in that described block stone bed course is by the natural of 10 ~ 100kg What stone or cast stone laid.
5. immersed tube tunnel under water as claimed in claim 1, it is characterised in that the thickness of described block stone bed course is 1.0 ~ 3.0m.
6. one kind immersed tube tunnel changeover portion soft soil foundation reinforcing method under water, comprises the following steps:
(1)Peel off the mud layer on soft soil foundation surface;
(2)Underwater sand compaction pile is laid to Soft Soil Layer under water;
(3)Smart digging treatment is carried out to the Soft Soil Layer under water that sand compaction pile is reinforced, block stone bed course is then laid thereon;In block stone pad Blotter is laid on layer.
7. immersed tube tunnel changeover portion soft soil foundation reinforcing method under water as claimed in claim 6, it is characterised in that described to squeeze under water Close sand pile is the underwater sand compaction pile uniformly laid along immersed tube tunnel bearing of trend.
8. immersed tube tunnel changeover portion soft soil foundation reinforcing method under water as claimed in claim 6, it is characterised in that described to squeeze under water 1.2 ~ 2.0m of close sand pile diameter, replacement rate is 40% ~ 70%.
9. immersed tube tunnel changeover portion soft soil foundation reinforcing method under water as claimed in claim 6, it is characterised in that the compacted sand During pile material is preferably, coarse sand, its clay content≤5%, gravel material≤10% of 5 ~ 20mm of particle diameter in sand material.
10. immersed tube tunnel changeover portion soft soil foundation reinforcing method under water as claimed in claim 6, it is characterised in that based on above-mentioned " soft soil foundation reinforcing method " the derivative laying of immersed tube tunnel under water engineering method:In claim 6 step(3)Reinforce the soft of completion The construction that immersed tube tunnel under water is immersed tube tunnel under water is laid on soil base;Accordingly in the both sides of the immersed tube tunnel for laying And the stone closing of backfill block is spread at top, you can complete the laying work of immersed tube tunnel under water.
CN201710200234.4A 2017-03-30 2017-03-30 Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water Pending CN106884427A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710200234.4A CN106884427A (en) 2017-03-30 2017-03-30 Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710200234.4A CN106884427A (en) 2017-03-30 2017-03-30 Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water

Publications (1)

Publication Number Publication Date
CN106884427A true CN106884427A (en) 2017-06-23

Family

ID=59181323

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710200234.4A Pending CN106884427A (en) 2017-03-30 2017-03-30 Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water

Country Status (1)

Country Link
CN (1) CN106884427A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107663865A (en) * 2017-11-14 2018-02-06 山东大学 A kind of cable-stayed type immersed tube tunnel structure and method
CN108086348A (en) * 2018-02-01 2018-05-29 中交第四航务工程勘察设计院有限公司 A kind of immersed tube tunnel combined foundation and setting method
CN108343088A (en) * 2018-05-16 2018-07-31 上海市城市建设设计研究总院(集团)有限公司 Without earthing along river open trench tunnel structure
CN111472359A (en) * 2020-03-19 2020-07-31 中国二十冶集团有限公司 Method for replacing and filling peat soil soft foundation box culvert foundation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62260919A (en) * 1986-05-07 1987-11-13 Tokyu Constr Co Ltd Small pile for reinforcing foundation ground to earthquake
CN200985497Y (en) * 2006-12-15 2007-12-05 中国神华能源股份有限公司 Dam
CN101718091A (en) * 2009-11-05 2010-06-02 东南大学 Method for treating foundation consisting of liquid soil layer and soft soil mutual layer
CN104947708A (en) * 2015-04-24 2015-09-30 中国交通建设股份有限公司 Combined foundation bed for immersed tube tunnels and construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62260919A (en) * 1986-05-07 1987-11-13 Tokyu Constr Co Ltd Small pile for reinforcing foundation ground to earthquake
CN200985497Y (en) * 2006-12-15 2007-12-05 中国神华能源股份有限公司 Dam
CN101718091A (en) * 2009-11-05 2010-06-02 东南大学 Method for treating foundation consisting of liquid soil layer and soft soil mutual layer
CN104947708A (en) * 2015-04-24 2015-09-30 中国交通建设股份有限公司 Combined foundation bed for immersed tube tunnels and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
林鸣等: "海上挤密砂桩工法及其在港珠澳大桥岛遂工程的应用", 《中国港湾建设》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107663865A (en) * 2017-11-14 2018-02-06 山东大学 A kind of cable-stayed type immersed tube tunnel structure and method
CN107663865B (en) * 2017-11-14 2024-03-05 山东大学 Inclined-pulling immersed tube tunnel structure and method
CN108086348A (en) * 2018-02-01 2018-05-29 中交第四航务工程勘察设计院有限公司 A kind of immersed tube tunnel combined foundation and setting method
CN108343088A (en) * 2018-05-16 2018-07-31 上海市城市建设设计研究总院(集团)有限公司 Without earthing along river open trench tunnel structure
CN108343088B (en) * 2018-05-16 2023-07-04 上海市城市建设设计研究总院(集团)有限公司 Non-earthing open cut tunnel structure along river
CN111472359A (en) * 2020-03-19 2020-07-31 中国二十冶集团有限公司 Method for replacing and filling peat soil soft foundation box culvert foundation

Similar Documents

Publication Publication Date Title
CN108468325B (en) Large-area coastal beach sea mud rapid curing construction method
CN101265701A (en) Soft soil foundation reinforcing means
CN103233454A (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN104131575A (en) Plugging and drainage method for dam foundation on karst highly developed stratum
CN106884427A (en) Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water
CN111851505A (en) Construction method and structure of pouring type impervious core earth-rock dam
CN104711967A (en) Method for carrying out combined vacuum preloading treatment on soft foundation by gravel piles
CN106759223A (en) Controllable rigid pile+displacement hull+reinforcement cushion combined composite foundation
CN103374900B (en) Build the gravity type quay on muddy foundation and construction method thereof
CN106759133A (en) The mixing structure of dam type and construction method of a kind of homogeneous earth and rockfill dam and rock
CN107859062A (en) The earth-filling method of underground pipe gallery
CN106498959A (en) Gutter for deep overburden
CN107190709B (en) Method for building river channel in newly dredged soil reclamation land-enclosed area
CN111335263B (en) Method for building artificial island
CN103276717B (en) The method of composite earthwork synthetic materials reinforcement cushion soft soil foundation
CN105804045A (en) Equipment for strengthening deep soft soil foundation by vacuum preloading of filter well and method
CN202626934U (en) Gravity wharf built on silty foundation
CN110804994B (en) Reservoir dam construction method
CN205776282U (en) A kind of immersed tube tunnel rebuilds cofferdam structure
CN110144871A (en) A kind of dark creek processing construction method
CN213143069U (en) Pouring type impervious core earth-rock dam structure
CN111197300B (en) Earth-rock cofferdam back slope type seepage-proofing dam and reverse construction method
CN108570979A (en) A kind of construction method for building antiseepage composite foundation on dolomite stratigraph
CN111335290B (en) Offshore artificial island structure suitable for silt foundation and construction method
CN204608701U (en) A kind of gravity type quay being applicable to roadbed of alluvial silt

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170623