CN107508245A - Foldable cable bearer - Google Patents

Foldable cable bearer Download PDF

Info

Publication number
CN107508245A
CN107508245A CN201710805431.9A CN201710805431A CN107508245A CN 107508245 A CN107508245 A CN 107508245A CN 201710805431 A CN201710805431 A CN 201710805431A CN 107508245 A CN107508245 A CN 107508245A
Authority
CN
China
Prior art keywords
cable
support bar
cable support
limited block
conduit line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710805431.9A
Other languages
Chinese (zh)
Other versions
CN107508245B (en
Inventor
刘立阳
董博超
高军
姜凯
赵传让
王超
杨伟
王所钺
潘富杰
孙宇斌
徐晓涛
李松
谢志平
孙晔
谭林斌
王友琳
张涛
王利
王肖亚
毕凯
郑朝
李国成
苏海勇
张华珍
张沈阳
贾希剑
徐伟
尹文杰
孙凯
徐天锡
刘新鑫
张强
王春勇
王小青
孙奉杰
王岩
曲克强
李同全
刘持军
商爱民
王光通
孙奉林
宋鹏
黄新良
王鑫泽
刘恺
韩涛
王勇
孙丰进
隋中东
乔宏业
孔淑
李雪媛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710805431.9A priority Critical patent/CN107508245B/en
Publication of CN107508245A publication Critical patent/CN107508245A/en
Application granted granted Critical
Publication of CN107508245B publication Critical patent/CN107508245B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/06Installations of electric cables or lines in or on the ground or water in underground tubes or conduits; Tubes or conduits therefor
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/08Installations of electric cables or lines in or on the ground or water in tunnels

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The invention belongs to the laying technology facility field of power cable in cable duct, it is related to a kind of foldable cable bearer, it is installed in conduit line, including cable bearer body, cable bearer body is fixed with the connecting rod parallel with conduit line wall, connecting rod is provided with limited block by the rotating shaft connection cable support bar vertical with conduit line wall, the cable support bar top at the non-cantilever end of rotating shaft side, and limited block is fixed on cable bearer body;The face that cable bearer body is fixed with conduit line wall is provided with bracket fixing bolt.The present invention is reasonable in design, it is folding by the fixed horizontal cable support Design of script, the cable support bar of level can be rotated up being retracted to before cable laying or during cable fault maintenance perpendicular to the ground, the activity space in conduit line is extended to greatest extent, is provided convenience for the entrance of movement and repair apparatus of the maintainer in raceway groove.

Description

Foldable cable bearer
Technical field
The present invention relates to a kind of foldable cable bearer, belong to the laying technology facility field of power cable in cable duct.
Background technology
Cable tunnel and the main thoroughfare that cable duct is urban electricity supply, for a long time, set up cable and made using angle bar Cable bearer.Angle iron bracket is typically welded angle bar section bar or fastener link or is spliced.Cable bearer preferably with ditch Wall built-in fitting welds, and weld anti-corrosion, firmly installs, and smooth vertical and horizontal, the same layer stull of each support should be in same level, its Vertical deviation≤5mm, the cable bearer installed in acclive cable duct or on building, should have and cable duct or building The identical gradient.The cable bearer the superiors and orlop should meet to ditch top, floor or bottom of trench, the distance on ground《Electric device Installing engineering cable run is constructed and acceptance specification》The regulation of (GB 50168).
Before cable laying, cable duct inner cable support has been installed fixation and finished so that in originally narrow cable duct Remaining space is narrower, and movement of the further laying to cable in place with personnel in ditch brings obstacle and inconvenience.It is existing There is the technical difficulty that the problem of cable bearer adds cable laying, add unnecessary man-hour;Moreover, enter in cable duct During row cable fault rush repair, due to the limitation in space so that some malfunction elimination equipment are difficult to enter conduit line;It is narrow and small Space limit translational speed of the maintainer in raceway groove, this all extends the investigation of cable fault and repair time, entered And electric power feeding time is extended, unnecessary economic loss is brought to electricity consumption enterprise and client.
The content of the invention
It is an object of the invention to propose a kind of foldable cable bearer, water that the foldable cable bearer will be originally fixed Flat cable support Design is folding, can be upward by the cable support bar of level before cable laying or during cable fault maintenance Rotation is retracted to perpendicular to the ground, extends the activity space in conduit line to greatest extent, is maintainer in raceway groove Movement and the entrance of repair apparatus provide convenience.
Foldable cable bearer of the present invention, is installed in conduit line, including cable bearer body, cable bearer Body is fixed with the connecting rod parallel with conduit line wall, and connecting rod passes through the rotating shaft connection cable vertical with conduit line wall Support bar, the cable support bar top at the non-cantilever end of rotating shaft side are provided with limited block, and limited block is fixed on cable bearer body; The face that cable bearer body is fixed with conduit line wall is provided with bracket fixing bolt.
Cable bearer body is fixed on conduit line inwall by bracket fixing bolt, during working condition, cable support Bar is in horizontality, and now the cable support bar at the non-cantilever end of rotating shaft side is limited by limited block, makes cable support Bar keep level, cable are placed in above cable support bar;When maintenance or other reasonses need larger space, by cable support Bar is rotated up around rotating shaft, and the upper surface of transposition cable support bar contacts with limited block, i.e., cable support bar upwards turn 90 ° with Ground plumbness.And under the restriction effect of limited block, cable support bar has at most been merely able to rotation in 90 °.
Preferably, described cable bearer body is provided with 2 layers or more than 2 layers of cable support bar, next layer of cable support The connection pole length of bar connection is more than the total of the width for connecting pole length and cable support bar of last layer cable support bar connection With, and the relevant position above every layer of cable support bar is equipped with limited block.Generally, same cable raceway groove domestic demand is transported Defeated multigroup cable, it is therefore desirable to which multi-layer cable support bar undertakes support translocation.The connection of next layer of cable support bar connection Pole length is more than the summation of the connection pole length of last layer cable support bar connection and the width of cable support bar, can effectively prevent Interfered when only every layer of cable support bar rotates up folding, so as to so that cable support bar rotates up and is folded to maximum Angle, it is to greatest extent conduit line Free up Memory.
Preferably, the cable support bar upper surface setting neck below described limited block, neck shape and limited block Shape is engaged, and the upper end of limited block is higher than cable support bar upper surface.The bottom of limited block is entrenched in neck, and The upper end of limited block is higher than cable support bar upper surface, and limited block can be made to play more preferable position-limiting action.
Preferably, depression is in concave surface downwards for the stage casing part of described cable support bar, facilitates the placement of cable, Ke Yiyou Effect prevents cable from sliding.
Preferably, the concave part of described cable support bar is provided with through hole, and rainwater etc. can be made to drain in time, also increased Gas permeability, advantageously radiated in cable.
Preferably, strut angle, the bearing of trend of strut angle and connection are set below described cable support bar Bar is parallel, and effective supporting role is played to cable support bar.
Rotating shaft has certain damping, and when only external force acts on, cable support bar can just surround axis of rotation, therefore, When cable support bar goes to perpendicular to the ground, oneself will not be gone to if no external force acts on cable support bar horizontal State.
The possessed compared with prior art beneficial effect of the present invention is:
(1) present invention enhances security for the laying work of power cable in conduit line.In traditional cable raceway groove Support is inwardly stretched out by furrow bank, when maintainer moves in raceway groove, is easy to be scratched by overhanging cable bearer.At this specially In profit, when necessary, support can be packed up fully upward, so as to drastically increase peace when maintainer moves in raceway groove Quan Xing;
(2) operating efficiency is improved, has saved man-hour.First, space improves inspection in the larger ditch after support is packed up Translational speed of the personnel in raceway groove is repaiied, meanwhile, after enough spaces are possessed, originally because volume reason can not enter raceway groove Interior repair apparatus can be moved and used in conduit line, further increase the operating efficiency of operation in conduit line;
(3) there is certain economic benefit.The raising of maintenance construction operation efficiency necessarily causes the preparation of power transmission in cable Time is reduced, and accelerates power transmission speed, reduces electricity consumption enterprise because the economic loss that delay power transmission is brought.
Brief description of the drawings
Fig. 1, foldable cable bearer front view;
Fig. 2, foldable cable bearer left view;
Fig. 3, foldable cable bearer top view.
In figure:1st, cable bearer body;2nd, limited block;3rd, rotating shaft;4th, cable support bar;5th, bracket fixing bolt;6th, even Extension bar;7th, through hole;8th, strut angle;9th, neck;10th, concave surface.
Embodiment
The present invention is described further below in conjunction with the accompanying drawings:
Such as Fig. 1-Fig. 3, foldable cable bearer of the present invention, it is installed in conduit line, including cable bearer sheet Body 1, cable bearer body 1 are fixed with the connecting rod 6 parallel with conduit line wall, and connecting rod 6 is connected by rotating shaft 3 and cable The vertical cable support bar 4 of channel walls, the top of cable support bar 4 at the non-cantilever end of the side of rotating shaft 3 is provided with limited block 2, spacing Block 2 is fixed on cable bearer body 1;The face that cable bearer body 1 is fixed with conduit line wall is provided with bracket fixing bolt 5.
In the present embodiment:Cable bearer body 1 is provided with 2 layers or more than 2 layers of cable support bar 4, next layer of cable support The length of connecting rod 6 that bar 4 connects is more than the length of connecting rod 6 of the connection of last layer cable support bar 4 and the width of cable support bar 4 Summation, and the relevant position of the top of every layer of cable support bar 4 is equipped with limited block 2, what next layer of cable support bar 4 connected The length of connecting rod 6 is more than the length of connecting rod 6 of the connection of last layer cable support bar 4 and the summation of the width of cable support bar 4, can To be interfered when effectively preventing every layer of cable support bar 4 from rotating up folding, so as to so that cable support bar 4 rotates up Maximum angle is folded to, is to greatest extent conduit line Free up Memory;The upper surface of cable support bar 4 of the lower section of limited block 2 is set Neck 9 is put, the shape of neck 9 is engaged with the shape of limited block 2, and the upper end of limited block 2 is higher than the upper table of cable support bar 4 Face, the bottom of limited block 2 are entrenched in neck 9, and the upper end of limited block 2 is higher than the upper surface of cable support bar 4, can make limit Position block 2 plays more preferable position-limiting action;Depression is in concave surface 10 downwards for the stage casing part of cable support bar 4, facilitates the placement of cable, Effectively it can prevent cable from sliding;The part of concave surface 10 of cable support bar 4 is provided with through hole 7, and rainwater etc. can be made to drain in time, also Gas permeability is added, is advantageously radiated in cable;The lower section of cable support bar 4 sets strut angle 8, strut angle 8 Bearing of trend is parallel with connecting rod 6, and effective supporting role is played to cable support bar 4;Rotating shaft 3 has certain damping, only outer Masterpiece used time, cable support bar 4 can just rotate around rotating shaft 3, therefore, when cable support bar 4 goes to perpendicular to the ground, such as Fruit does not have external force effect cable support bar 4 then oneself will not go to horizontality.
Cable bearer body 1 is fixed on conduit line inwall by bracket fixing bolt 5, during working condition, cable branch Strut 4 is in horizontality, and the cable support bar 4 at the non-cantilever end of the side of now rotating shaft 3 is limited by limited block 2, makes electricity The keep level of cable support bar 4, cable are placed in the top of cable support bar 4;, will when maintenance or other reasonses need larger space The cable support bar 4 of each layer is rotated up around rotating shaft 3, and the upper surface of transposition cable support bar 4 contacts with limited block 2, i.e., electric Cable support bar 4 turns 90 ° of states perpendicular to the ground upwards.And under the restriction effect of limited block 2, cable support bar 4 is at most only Being capable of complete rotation in 90 °.When cable support bar 4 upwards turn 90 ° it is perpendicular to the ground when, extend to greatest extent in conduit line Activity space, provided convenience for the entrance of movement and repair apparatus of the maintainer in raceway groove.

Claims (6)

1. a kind of foldable cable bearer, is installed in conduit line, it is characterised in that:Including cable bearer body (1), cable Rack body (1) is fixed with the connecting rod parallel with conduit line wall (6), and connecting rod (6) is connected by rotating shaft (3) and cable The vertical cable support bar (4) of channel walls, cable support bar (4) top at the non-cantilever end of rotating shaft (3) side are provided with limited block (2), limited block (2) is fixed on cable bearer body (1);Cable bearer body (1) is provided with branch with the face that conduit line wall is fixed Frame fixing bolt (5).
2. foldable cable bearer according to claim 1, it is characterised in that:Cable bearer body (1) is provided with 2 layers or 2 Cable support bar (4) more than layer, connecting rod (6) length of next layer of cable support bar (4) connection are more than last layer cable branch The summation of connecting rod (6) length of strut (4) connection and the width of cable support bar (4), and on every layer of cable support bar (4) The relevant position of side is equipped with limited block (2).
3. foldable cable bearer according to claim 1 or 2, it is characterised in that:Cable support below limited block (2) Bar (4) upper surface sets neck (9), and neck (9) shape is engaged with the shape of limited block (2), and the upper end of limited block (2) Higher than cable support bar (4) upper surface.
4. foldable cable bearer according to claim 1, it is characterised in that:The stage casing part of cable support bar (4) to Lower recess is in concave surface (10).
5. foldable cable bearer according to claim 4, it is characterised in that:Concave surface (10) portion of cable support bar (4) It is arranged with through hole (7).
6. foldable cable bearer according to claim 1, it is characterised in that:Support is set below cable support bar (4) Angle iron (8), the bearing of trend of strut angle (8) are parallel with connecting rod (6).
CN201710805431.9A 2017-09-08 2017-09-08 Foldable cable support Active CN107508245B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710805431.9A CN107508245B (en) 2017-09-08 2017-09-08 Foldable cable support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710805431.9A CN107508245B (en) 2017-09-08 2017-09-08 Foldable cable support

Publications (2)

Publication Number Publication Date
CN107508245A true CN107508245A (en) 2017-12-22
CN107508245B CN107508245B (en) 2020-03-17

Family

ID=60695855

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710805431.9A Active CN107508245B (en) 2017-09-08 2017-09-08 Foldable cable support

Country Status (1)

Country Link
CN (1) CN107508245B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108808584A (en) * 2018-05-21 2018-11-13 江苏亚特电缆有限公司 A kind of cable gathering anchor and fixing means
CN109038411A (en) * 2018-09-12 2018-12-18 镇江朝阳机电科技有限公司 Multi-purpose type tooth form opening Wiring trough
CN110601121A (en) * 2019-09-25 2019-12-20 国网山东省电力公司经济技术研究院 Double-layer visual fireproof cable trench
CN111009872A (en) * 2019-12-31 2020-04-14 华南理工大学 Pre-buried cable support and construction method of cable trench
CN111969542A (en) * 2020-08-12 2020-11-20 陕西鼎固建筑工程有限公司 Electric power tunnel cable frame
CN112054440A (en) * 2020-08-21 2020-12-08 国网山东省电力公司昌邑市供电公司 Cable head machining table

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2615923A1 (en) * 1987-05-26 1988-12-02 Seine Const Elect IMPROVEMENTS ON METAL CONSOLES
CN2150419Y (en) * 1993-02-09 1993-12-22 王进蓬 Support for wire in underground ditch
CN201219187Y (en) * 2008-06-21 2009-04-08 宜昌供电公司变电修试部 Novel cable coil unwinding holder
JP4411638B2 (en) * 2005-06-08 2010-02-10 未来工業株式会社 Box fixture
CN201629542U (en) * 2010-03-11 2010-11-10 郑庆华 Composite cable bearer with flow guide strips
CN201742063U (en) * 2010-07-15 2011-02-09 东莞市深通实业有限公司 Combination cable bracket
CN205026215U (en) * 2015-09-30 2016-02-10 国网山东省电力公司经济技术研究院 Collapsible flexible cable support
CN206268614U (en) * 2016-12-19 2017-06-20 广州市井力建材有限公司 A kind of Combined cable support

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2615923A1 (en) * 1987-05-26 1988-12-02 Seine Const Elect IMPROVEMENTS ON METAL CONSOLES
CN2150419Y (en) * 1993-02-09 1993-12-22 王进蓬 Support for wire in underground ditch
JP4411638B2 (en) * 2005-06-08 2010-02-10 未来工業株式会社 Box fixture
CN201219187Y (en) * 2008-06-21 2009-04-08 宜昌供电公司变电修试部 Novel cable coil unwinding holder
CN201629542U (en) * 2010-03-11 2010-11-10 郑庆华 Composite cable bearer with flow guide strips
CN201742063U (en) * 2010-07-15 2011-02-09 东莞市深通实业有限公司 Combination cable bracket
CN205026215U (en) * 2015-09-30 2016-02-10 国网山东省电力公司经济技术研究院 Collapsible flexible cable support
CN206268614U (en) * 2016-12-19 2017-06-20 广州市井力建材有限公司 A kind of Combined cable support

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108808584A (en) * 2018-05-21 2018-11-13 江苏亚特电缆有限公司 A kind of cable gathering anchor and fixing means
CN108808584B (en) * 2018-05-21 2023-09-22 江苏亚特电缆有限公司 Cable assembly anchoring device and fixing method
CN109038411A (en) * 2018-09-12 2018-12-18 镇江朝阳机电科技有限公司 Multi-purpose type tooth form opening Wiring trough
CN110601121A (en) * 2019-09-25 2019-12-20 国网山东省电力公司经济技术研究院 Double-layer visual fireproof cable trench
CN111009872A (en) * 2019-12-31 2020-04-14 华南理工大学 Pre-buried cable support and construction method of cable trench
CN112202135A (en) * 2019-12-31 2021-01-08 华南理工大学 Pre-buried cable support and construction method of cable trench
CN111969542A (en) * 2020-08-12 2020-11-20 陕西鼎固建筑工程有限公司 Electric power tunnel cable frame
CN112054440A (en) * 2020-08-21 2020-12-08 国网山东省电力公司昌邑市供电公司 Cable head machining table

Also Published As

Publication number Publication date
CN107508245B (en) 2020-03-17

Similar Documents

Publication Publication Date Title
CN107508245A (en) Foldable cable bearer
CN206480986U (en) A kind of wellhead cable, which turns to lay, uses guiding trestle
CN110107972A (en) Cabin-type refrigerating plant room and its construction method
RU2312187C1 (en) Method for underground passage and tunnel forming and underground passage or tunnel section
CN207260193U (en) A kind of pipe gallery system with fire-extinguishing function concurrently
CN210985463U (en) Auxiliary device is laid to cable
EP3743587B1 (en) Smart skidding system for land operations
CN107143699A (en) A kind of pipe line steel flexible anti-shock support
KR100751573B1 (en) Reinforcement apparatus of water pipe in weakness ground
KR100917395B1 (en) Shelf apparatus in power hole enabling both sides folding and height adjusting for installing power distributing cable
CN105971012B (en) A kind of prefabricated piping lane
CN115417232A (en) Multifunctional cable laying device
CN103556837A (en) Method for installing steel column on podium building
CN104631496B (en) Temporary access road above a kind of ballast water tank water and the installation method of this passage
CN106803653A (en) A kind of fixing means of distribution line
CN216290075U (en) Distribution network engineering pre-installation cable trench
CN112502188A (en) Power communication comprehensive pipe rack in easy-to-slide area and construction method thereof
CN205689897U (en) A kind of detachable cable support
CN106760566B (en) Construction method of height-variable feeding and discharging platform
CN207234231U (en) A kind of buried electricity box of overhead type
CN207568252U (en) A kind of underground machine room
CN203783066U (en) Indoor pipeline integrated mounting structure
CN205935796U (en) Sled formula components of a whole that can function independently pump house
CN201396068Y (en) Folding tube trunking moving along with drilling machine
CN205894350U (en) Prefabricated formula wall connection structure and utilize this connection structure's prefabricated formula housing construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant