CN105442453A - 悬索桥桥塔横梁组合支架施工方法 - Google Patents

悬索桥桥塔横梁组合支架施工方法 Download PDF

Info

Publication number
CN105442453A
CN105442453A CN201510855625.0A CN201510855625A CN105442453A CN 105442453 A CN105442453 A CN 105442453A CN 201510855625 A CN201510855625 A CN 201510855625A CN 105442453 A CN105442453 A CN 105442453A
Authority
CN
China
Prior art keywords
bracket
connector
tower
construction
crossbeam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510855625.0A
Other languages
English (en)
Inventor
单晓东
孟祥源
王志强
钱育强
吴琼明
杨浩
梁紫艳
张金翠
强龙维
庞庆
刘帅帅
冯雄飞
胡茳
蔡悬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co Ltd
CCCC Fourth Highway Engineering Co Ltd
Original Assignee
Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co Ltd
CCCC Fourth Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co Ltd, CCCC Fourth Highway Engineering Co Ltd filed Critical Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co Ltd
Priority to CN201510855625.0A priority Critical patent/CN105442453A/zh
Publication of CN105442453A publication Critical patent/CN105442453A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/02Suspension bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种悬索桥桥塔横梁组合支架施工方法,在桥塔左右塔枝施工到一定高度时,在两塔枝相对的一侧塔身内对称预埋牛腿连接件,在牛腿连接件上方预埋贝雷片连接件,牛腿连接件与牛腿焊接;在牛腿上方安装沙筒,所述沙筒、承重梁;利用贝雷片连接件安装贝雷片,贝雷片上安装模板分配梁;在分配梁上安装模板、绑扎钢筋,进行横梁混凝土浇筑;横梁浇筑完成后,利用塔吊依次拆除模板、分配梁、贝雷片、承重梁、沙筒、牛腿,完成横梁施工。

Description

悬索桥桥塔横梁组合支架施工方法
技术领域
本发明属于桥梁施工技术领域,具体涉及一种悬索桥桥塔横梁的施工方法。
背景技术
在公路交通等基础建设中,作为跨越能力最强的悬索桥,常作为跨越江河湖海、高山峡谷的首选桥型。桥塔作为悬索桥中的重要受力构件,为满足主缆线形的需求,通常塔身都很高,为保持桥塔的强度和稳定,桥塔左右塔枝之间通常设数道横梁,使两塔枝连成整体。目前,悬索桥桥塔横梁施工普遍采用落地支架的施工方式。落地支架通常采用钢管等型材从基础位置一直搭建到横梁位置,支架横向需设数道横联与塔身连接,以增强支架的稳定性。如果横梁设计的很高,必然导致支架也很高,所需的耗材和人工都会很多,因此采用落地支架在施工周期、施工安全、施工成本上存在诸多缺陷:
1、支架搭设耗用时间长,影响施工周期;
2、支架占用桥塔下方空间,对材料堆放转运不利,对需要从塔底通行的临时交通需求不能满足;
3、支架施工周期长,高空作业时间久,安全隐患高;
4、支架需要大量施工耗材,成本投入大。
针对落地支架存在的上述诸多问题,迫切需要一种不需要落地支架的施工方法。
发明内容
悬索桥桥塔横梁采用落地支架施工时,在施工周期、施工安全、施工成本上存在诸多缺陷,针对诸多缺陷迫切需要一种不需要落地支架的施工方法,用以缩短施工周期、降低施工耗材、保障施工安全。
为解决上述技术问题,本发明采用如下技术方案:
一种悬索桥桥塔横梁组合支架施工方法,其特征在于包括以下步骤:
(1)在桥塔左右塔枝施工到一定高度时,在两塔枝相对的一侧塔身内对称预埋牛腿连接件,在牛腿连接件上方预埋贝雷片连接件;
(2)所述的牛腿连接件预埋好后,将牛腿连接件与牛腿焊接;
(3)所述牛腿安装完毕后,在牛腿上方安装用于调平及卸落支架所用的沙筒,所述沙筒调平后,其上安装用于支撑贝雷片的承重梁;
(4)将贝雷片在地面成榀拼装好后,利用塔吊整体吊放到所述承重梁顶面,所述贝雷片利用连接杆与所述贝雷片连接件连接;
(5)所述贝雷片安装完毕后,在其上方安装模板分配梁;
(6)在分配梁上安装底模板,绑扎横梁底板钢筋及部分腹板钢筋,安装底截面预应力管道、外侧模板和内模板,浇筑底板混凝土及部分腹板混凝土;绑扎剩余腹板钢筋和顶板钢筋,安装顶截面预应力管道及内模顶板,浇筑混凝土;
(7)横梁张拉、压浆;
(8)利用塔吊依次拆除内模板、侧模板、底模板、分配梁、贝雷片、承重梁、沙筒、牛腿,完成横梁施工。
本发明通过在桥塔塔身预埋连接件来固定牛腿,通过牛腿支撑贝雷片、承重梁、分配梁组拼成的横梁支架体系,以达到桥塔横梁无落地支架施工的目的。本发明相比目前普遍采用的落地支架施工方法,具有以下有益效果:
(1)节约成本:牛腿与贝雷片组合支架***所用材料相对落地支架耗材大大减少。
(2)缩短工期:利用贝雷片作为支架横梁,从牛腿安装到贝雷片安装完成形成施工平台***,其作业时间短,可节约大量工时。贝雷片拼装速度快,无需切割焊接等工序,相对落地支架所用型钢需要切割下料、杆件焊接等工序,施工效率较高。
(3)施工安全性高:落地支架高空作业时间较长,另外落地支架教高时,其自身的结构稳定性及安全性都会受到影响,另外施工过程交叉作业较多,也加大了安全风险。
附图说明
图1是本发明的施工方法流程图;
图2是塔身预埋牛腿及贝雷片连接件示意图;
图3是安装牛腿示意图;
图4是牛腿上设置沙筒及承重梁示意图;
图5是安装贝雷片及分配梁示意图;
图6是分配梁设置平面图;
图7是横梁浇筑施工示意图;
图8是横梁施工完成的状态示意图。
具体实施方式
图1所示为本发明的施工方法流程图。以下结合附图对本发明的具体实施方式进行说明。
如图2所示,在桥塔塔柱1施工过程中,在桥塔左右塔枝施工到一定高度时,在两塔枝相对的一侧塔身内对称预埋牛腿连接件2,在牛腿连接件上方预埋贝雷片连接件3。
所述的牛腿连接件2包括牛腿上连接件、牛腿下连接件,所述贝雷片连接件3包括贝雷上榫头连接件、贝雷下榫头连接件。所述牛腿连接件及贝雷片连接件预埋位置依据施工设计方案确定。
如图3所示,牛腿连接件2预埋好后,将其与牛腿4焊接,所述牛腿可采用型钢焊接而成。
如图4所示,所述牛腿4安装完毕后,在牛腿上方安装用于调平及卸落支架所用的沙筒5,所述沙筒5调平后,其上安装用于支撑贝雷片的承重梁6。
如图5所示,将贝雷片7在地面成榀拼装好后,利用塔吊整体吊放到所述承重梁6上,所述贝雷片7利用连接杆与所述贝雷片连接件3连接。所述贝雷片7安装完毕后,在其上方安装模板分配梁8。
如图6所示,安装分配梁时,使分配梁8长度大于要施工的横梁的宽度,悬出部分作为施工操作平台。
如7所示,分配梁8设置完成后,在分配梁上安装底模板,绑扎横梁底板钢筋及部分腹板钢筋,安装底截面预应力管道、外侧模板和内模板,浇筑底板混凝土及部分腹板混凝土;绑扎剩余腹板钢筋和顶板钢筋,安装顶截面预应力管道及内模顶板,浇筑混凝土。
混凝土达到设计强度后,进行横梁张拉、压浆,完成横梁9浇筑施工。
最后,利用塔吊依次拆除内模板、侧模板、底模板、分配梁、贝雷片、承重梁、沙筒、牛腿,完成横梁施工。横梁9施工完成后的状态如图8所示。

Claims (4)

1.一种悬索桥桥塔横梁组合支架施工方法,其特征在于包括以下步骤:
(1)在桥塔左右塔枝施工到一定高度时,在两塔枝相对的一侧塔身内对称预埋牛腿连接件,在牛腿连接件上方预埋贝雷片连接件;
(2)所述的牛腿连接件预埋好后,将牛腿连接件与牛腿焊接;
(3)所述牛腿安装完毕后,在牛腿上方安装用于调平及卸落支架所用的沙筒,所述沙筒调平后,其上安装用于支撑贝雷片的承重梁;
(4)将贝雷片在地面成榀拼装好后,利用塔吊整体吊放到所述承重梁顶面,所述贝雷片利用连接杆与所述贝雷片连接件连接;
(5)所述贝雷片安装完毕后,在其上方安装模板分配梁;
(6)在分配梁上安装底模板,绑扎横梁底板钢筋及部分腹板钢筋,安装底截面预应力管道、外侧模板和内模板,浇筑底板混凝土及部分腹板混凝土;绑扎剩余腹板钢筋和顶板钢筋,安装顶截面预应力管道及内模顶板,浇筑混凝土;
(7)横梁张拉、压浆;
(8)利用塔吊依次拆除内模板、侧模板、底模板、分配梁、贝雷片、承重梁、沙筒、牛腿,完成横梁施工。
2.根据权利要求1所述的悬索桥桥塔横梁组合支架施工方法,其特征在于:所述的牛腿连接件包括牛腿上连接件、牛腿下连接件,所述贝雷片连接件包括贝雷上榫头连接件、贝雷下榫头连接件。
3.根据权利要求1所述的悬索桥桥塔横梁组合支架施工方法,其特征在于:所述牛腿为型钢组拼焊接而成。
4.根据权利要求1所述的悬索桥桥塔横梁组合支架施工方法,其特征在于:所述分配梁长度大于横梁宽度,利用悬出部分作为施工操作平台。
CN201510855625.0A 2015-11-30 2015-11-30 悬索桥桥塔横梁组合支架施工方法 Pending CN105442453A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510855625.0A CN105442453A (zh) 2015-11-30 2015-11-30 悬索桥桥塔横梁组合支架施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510855625.0A CN105442453A (zh) 2015-11-30 2015-11-30 悬索桥桥塔横梁组合支架施工方法

Publications (1)

Publication Number Publication Date
CN105442453A true CN105442453A (zh) 2016-03-30

Family

ID=55553050

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510855625.0A Pending CN105442453A (zh) 2015-11-30 2015-11-30 悬索桥桥塔横梁组合支架施工方法

Country Status (1)

Country Link
CN (1) CN105442453A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035741A (zh) * 2018-02-05 2018-05-15 三门峡市水利勘测设计有限责任公司 一种顶模台车
CN113417372A (zh) * 2021-07-01 2021-09-21 中铁大桥局第七工程有限公司 一种混凝土塔柱预埋牛腿***及安装方法
CN114057114A (zh) * 2020-08-02 2022-02-18 中交第四公路工程局有限公司 一种缆索吊机缆塔快速安装方法
CN114086478A (zh) * 2021-11-25 2022-02-25 中铁广州工程局集团桥梁工程有限公司 一种牛腿兼做临时支撑的主塔下横梁施工体系及方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19607952C2 (de) * 1996-03-01 2000-09-07 Roland Kehl Traggerüst zur Stützung von Massivbauwerken
CN101210418A (zh) * 2007-12-25 2008-07-02 赵志茹 悬索桥塔架横梁无落地支架施工方法
ES2352023A1 (es) * 2008-04-03 2011-02-15 Structural Research, S.L. Procedimiento de montaje de dinteles prefabricados de hormigón.
CN103352428A (zh) * 2013-07-06 2013-10-16 中交路桥建设有限公司 悬索桥索塔横梁无支架施工方法
CN104109999A (zh) * 2014-06-26 2014-10-22 中铁大桥局股份有限公司 桥塔横梁的施工方法
CN104532749A (zh) * 2014-12-18 2015-04-22 中铁建设集团有限公司 一种用于悬索桥主塔上横梁施工的支架

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19607952C2 (de) * 1996-03-01 2000-09-07 Roland Kehl Traggerüst zur Stützung von Massivbauwerken
CN101210418A (zh) * 2007-12-25 2008-07-02 赵志茹 悬索桥塔架横梁无落地支架施工方法
ES2352023A1 (es) * 2008-04-03 2011-02-15 Structural Research, S.L. Procedimiento de montaje de dinteles prefabricados de hormigón.
CN103352428A (zh) * 2013-07-06 2013-10-16 中交路桥建设有限公司 悬索桥索塔横梁无支架施工方法
CN104109999A (zh) * 2014-06-26 2014-10-22 中铁大桥局股份有限公司 桥塔横梁的施工方法
CN104532749A (zh) * 2014-12-18 2015-04-22 中铁建设集团有限公司 一种用于悬索桥主塔上横梁施工的支架

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
钟建锋,房金钱,王保君: "悬索桥桥塔横梁施工新技术", 《公路与汽运》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035741A (zh) * 2018-02-05 2018-05-15 三门峡市水利勘测设计有限责任公司 一种顶模台车
CN114057114A (zh) * 2020-08-02 2022-02-18 中交第四公路工程局有限公司 一种缆索吊机缆塔快速安装方法
CN113417372A (zh) * 2021-07-01 2021-09-21 中铁大桥局第七工程有限公司 一种混凝土塔柱预埋牛腿***及安装方法
CN113417372B (zh) * 2021-07-01 2023-02-28 中铁大桥局第七工程有限公司 一种混凝土塔柱预埋牛腿***及安装方法
CN114086478A (zh) * 2021-11-25 2022-02-25 中铁广州工程局集团桥梁工程有限公司 一种牛腿兼做临时支撑的主塔下横梁施工体系及方法
CN114086478B (zh) * 2021-11-25 2023-09-08 中铁广州工程局集团桥梁工程有限公司 一种牛腿兼做临时支撑的主塔下横梁施工体系及方法

Similar Documents

Publication Publication Date Title
CN105386778A (zh) 隧道暗挖衬砌施工台车及隧道暗挖衬砌施工方法
CN101781878B (zh) 独塔无背索斜拉桥主塔整体提升模板及其提升施工方法
CN105350454B (zh) 一种用于钢桁拱桥梁的钢拱肋外包混凝土施工方法
CN105839536A (zh) 一种斜拉桥索塔的施工方法
CN101560752A (zh) 浮托顶推架设钢桁梁施工方法
CN104109999A (zh) 桥塔横梁的施工方法
CN104594204B (zh) 城市轻轨高架桥山型u梁施工支撑体系及施工方法
CN101158146A (zh) 斜拉桥主梁滑动模架***及施工方法
CN203668833U (zh) 钢腹板定位装置
CN105442453A (zh) 悬索桥桥塔横梁组合支架施工方法
CN103938533A (zh) 简支变连续结构及其施工方法
CN105401679A (zh) 大坡度现浇混凝土斜屋面施工方法
CN102134832B (zh) 活动支架辅助不变幅架梁吊机架设钢箱梁方法及活动支架
CN105568854A (zh) 水上曲线形鱼腹式现浇钢筋混凝土箱梁施工方法
CN103321155B (zh) 高架桥桥墩施工平台体系及搭建该体系并浇注桥墩的方法
CN105649213A (zh) 一种密集布筋区大型钢结构预埋件的施工方法
CN104314009B (zh) 大节段提升机构及使用方法
CN103952979B (zh) 一种钢砼叠合梁顶板无支架施工装置及施工方法
CN109881587B (zh) 一种大风环境下主塔上横梁支架整体安装方法
CN103233426A (zh) 一种软基中无支墩的贝雷梁支架及其支护方法
CN204475184U (zh) 城市轻轨高架桥山型u梁施工支撑体系
CN102936953B (zh) “大”字型劲钢结构模板施工方法
CN103061568B (zh) 倒锥壳保温水塔水柜采用锥形悬架高位现浇施工方法
CN205116025U (zh) 自平衡式砼箱梁及t梁桥悬臂翼缘二次浇筑吊架装置
CN103835238A (zh) 一种高墩斜拉桥0号块无支架施工方法及施工中的结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160330

WD01 Invention patent application deemed withdrawn after publication