CN105239562A - Hole-forming pouring pile - Google Patents

Hole-forming pouring pile Download PDF

Info

Publication number
CN105239562A
CN105239562A CN201510618589.6A CN201510618589A CN105239562A CN 105239562 A CN105239562 A CN 105239562A CN 201510618589 A CN201510618589 A CN 201510618589A CN 105239562 A CN105239562 A CN 105239562A
Authority
CN
China
Prior art keywords
pile
concrete
prefabricated concrete
stake
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510618589.6A
Other languages
Chinese (zh)
Other versions
CN105239562B (en
Inventor
黄国庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510618589.6A priority Critical patent/CN105239562B/en
Publication of CN105239562A publication Critical patent/CN105239562A/en
Application granted granted Critical
Publication of CN105239562B publication Critical patent/CN105239562B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

Disclosed is a hole-forming pouring pile. The hole-forming pouring pile comprises a pile body; a prefabricated concrete pile wall is arranged on the periphery of the pile body and formed by concrete pipes assembled by a plurality of prefabricated concrete pieces or mixed concrete pipes and prefabricated concrete pipes assembled by the multiple prefabricated concrete pieces and serves as a wall protecting system for pile holes during pile forming; concrete expanded bodies are arranged on the outer side of the pile or at the bottom of the pile or on the outer side and at the bottom of the pile; the concrete expanded bodies of the outer side of the pile are prefabricated concrete building blocks; the concrete expanded bodies of the bottom of the pile are formed after finishing hole bottom dry operation which is performed in the pile holes of the prefabricated concrete wall protecting system of the hole walls of the pile body. By means of the hole-forming pouring pile, the problem that pile forming is hard to achieve or can not be achieved in terms of existing dry operation hole-forming pouring piles in soft soil layers, quick sand soil layers and water-contained soil layers can be solved, the pile body bearing capacity and the pile body stability are improved to the maximum degree, and the pile foundation cost can be reduced extremely.

Description

A kind of pore-creating filling pile
Technical field
The present invention relates to a kind of pore-creating filling pile in pile foundation.
Background technology
Existing pore-creating filling pile (non-Squeezing Soil Pile) mainly contains dry operation pore-creating filling pile, mud off pore-creating filling pile, casing pipeholing casting stake.Dry operation pore-creating filling pile has the pore-creating filling piles such as manually digging hole, length or short spiral, mechanically drived luoyang shovel, and the concrete piles quality of dry operation pore-creating filling pile controls well, can make full use of bearing capacity of foundation slab, and without mud construction, environment is good; Mud off pore-creating filling pile has diving boring, just or the mud off such as reverse circulation drilling, spiral-digging pore pore-creating filling pile, handles underwater concrete pouring after sediment well, wide adaptability; Casing pipeholing casting stake has Benoto castinplace pile (percussive grabbing boring), SaperTop engineering method, short screw-feed boring castinplace pile etc., and general anhydrous perfusion concrete (also having underwater grouting), wide adaptability, quality better controls.
The deficiency of existing pore-creating filling pile: the expanding body of concrete that mud off pore-creating filling pile and casing pipeholing casting stake are not generally formed in stake side, the expanding body of concrete at the bottom of stake at the bottom of expanding formation stake is also more difficult; Existing dry operation pore-creating filling pile is difficult to or cannot pile in soft soil layer, quicksand formation and water bearing ground, and compliance has great limitation; Dry operation manually digging hole pore-creating filling pile except weak soil, quicksand and water bearing ground adapt in stratum, formed pile lining with Cast-in-place concrete retaining wall cylinder, generally also there is no the expanding body of the concrete of a side, and speed of application be slow.
Summary of the invention
Technical problem to be solved by this invention is: provide a kind of pore-creating filling pile, this can solve existing dry operation pore-creating filling pile and to be difficult at soft soil layer, quicksand formation and water bearing ground or cannot the problem of pile, and has increased substantially bearing capacity and the pile body stability of pore-creating filling pile.
The technology used in the present invention solution is: a kind of pore-creating filling pile, comprise pile body, the outer of described pile body is arranged with Prefabricated Concrete pile lining, described Prefabricated Concrete pile lining is made up of the assembled concrete pipe of some Prefabricated Concrete sheets or mixed by the assembled concrete pipe of some Prefabricated Concrete sheets and Prefabricated Concrete pipe, this Prefabricated Concrete pile lining is a part for pile body, is the retaining wall protection system of stake holes when pile operation; Be provided with the expanding body of concrete outside described stake or at the bottom of stake or outside stake He at the bottom of stake, the expanding body of the concrete outside described stake is Prefabricated Concrete contract block, and Prefabricated Concrete contract block is corresponding with Prefabricated Concrete sheet to be arranged, and is longitudinally pressed in foundation soil outside stake, with fixing mounted concrete sheet; The expanding body of concrete at the bottom of described stake is completing the expanding body of concrete done operation at the bottom of the hole of carrying out in the stake holes of pile body hole wall Prefabricated Concrete retaining wall system and formed.
The further technical scheme of the present invention is: 1, have grouting layer outside Prefabricated Concrete pile lining, and grouting layer is with can the cement paste of rapid solidification be formed slip casting outside Prefabricated Concrete pile lining, with fixing mounted concrete sheet and sealing.2, at the bottom of stake, boulder and cobble bearing stratum has injecting cement paste, and this injecting cement paste is when drilling construction is close to boulder and cobble bearing stratum, adopts slim hole drilling to arrive bearing stratum, carries out slip casting to boulder and cobble bearing stratum, can shutoff underground water and the supporting capacity improving bearing stratum.
Beneficial effect of the present invention: 1, this can solve existing dry operation pore-creating filling pile and to be difficult at soft soil layer, quicksand formation and water bearing ground or cannot the problem of pile; The expanding body of concrete piles of expanding formation at the bottom of the expanding or stake in the stake side of carrying out in the stake holes 2, under Prefabricated Concrete retaining wall system protection, also slip casting can be carried out according to Different Strata situation, make full use of foundation soil condition, at utmost improve pile body bearing capacity, pile body stability and reduce pile foundation cost; 3, bearing capacity of single pile is high, can the intensity utilizing concrete piles of higher degree, is convenient to design and lays out pile, can accomplish that one pile for one column saves laying out pile of cushion cap expense, particularly core shell part in soft foundation; 4, pour into concrete under anhydrous condition, concrete piles quality provides execution conditions to ensure; 5, without mud and construction noise little, environmental protection condition is good, has saved environmental protection disposal costs; 6, the assembled formation supporting of concrete sheet because adopting batch production prefabricated, can adopt do mechanization operation, speed of application is fast.Mixed economy and social benefit remarkable.
Below in conjunction with the drawings and the specific embodiments, the invention will be further described.
Accompanying drawing explanation
Fig. 1 is an embodiment of the present invention pile body schematic diagram.
Fig. 2 is the sectional view of a kind of embodiment of concrete pipe.
Fig. 3 is the stereogram of a kind of embodiment of Prefabricated Concrete sheet.
Detailed description of the invention
As shown in Figure 1, Figure 2, Figure 3 shows; the pore-creating filling pile that the present embodiment provides; the outer of its pile body is arranged with Prefabricated Concrete pile lining 1; Prefabricated Concrete pile lining 1 is made up of the assembled concrete pipe 7 of some Prefabricated Concrete sheets 8 or mixed by the assembled concrete pipe of some Prefabricated Concrete sheets and Prefabricated Concrete pipe; this Prefabricated Concrete pile lining is a part for pile body; it is the retaining wall protection system of stake holes when pile operation; the present embodiment adopts by the assembled annular concrete pipe of some Prefabricated Concrete sheets, and annular concrete pipe can adopt the Prefabricated Concrete sheet of same size or different size assembled (as shown in Figure 2).The expanding body of concrete is provided with outside described stake or at the bottom of stake or outside stake He at the bottom of stake, the expanding body of concrete in stake outside is Prefabricated Concrete contract block 3, Prefabricated Concrete contract block 3 is corresponding with concrete pipe 7 to be arranged, longitudinally be pressed in foundation soil outside stake, with fixing mounted concrete sheet 8, and improve pile body frictional force and pile body stability (raising slenderness ratio).The expanding body of concrete 6 at the stake end is completing the expanding body of concrete (this is expanding condition at the bottom of the incomparable stake of existing most of stake) done operation at the bottom of the hole of carrying out in the stake holes of pile body hole wall Prefabricated Concrete retaining wall system and formed, to make full use of foundation soil condition, at utmost improve bearing capacity of single pile and reduce pile foundation cost.Have grouting layer 4 outside Prefabricated Concrete pile lining 1, grouting layer 4, with can the cement paste of rapid solidification be formed slip casting outside Prefabricated Concrete pile lining 1, with fixing mounted concrete sheet 8 and sealing, improves the bearing capacity of stake simultaneously.Stake end boulder and cobble bearing stratum has injecting cement paste 5, and this injecting cement paste 5 is when drilling construction is close to boulder and cobble bearing stratum, adopts slim hole drilling to arrive bearing stratum, carries out slip casting to boulder and cobble bearing stratum, can shutoff underground water and the supporting capacity improving bearing stratum.
The construction method brief description of the present embodiment pore-creating filling pile is as follows: combine casing in pore-forming job step with dismantled and assembled steel (or steel concrete) and carry out advance support, drilling tool is selected to carry out creeping into and fetching earth, in weak soil, soft plastic clay or quicksand formation, advance support surmounts and creeps into the section of fetching earth, the concrete pipe of the assembled formation stake holes of batch production Prefabricated Concrete sheet is used in pore-forming job step rear end under advance support protection, as the concrete dado system of stake holes; In hole, removable annular hydraulic systems force advance support system is advanced, and middlely to be hammered into by the Prefabricated Concrete contract block preset in a side foundation soil or with the cement paste of rapid solidification carrying out the slip casting of concrete dado lateral wall to fix mounted concrete pipe concrete pipe is assembled; At drilling construction close in boulder and cobble bearing stratum, adopt slim hole drilling to arrive bearing stratum, slip casting is carried out to boulder and cobble bearing stratum, can shutoff underground water and improve the supporting capacity of bearing stratum; In the stake holes of existing concrete dado, carry out expanding body at the bottom of expanding formation stake at the bottom of hole, improve the bearing capacity of stake; Reinforcing cage is finally installed and pours into concrete pile in anhydrous conditions.

Claims (3)

1. a pore-creating filling pile, comprise pile body, it is characterized in that: the outer of described pile body is arranged with Prefabricated Concrete pile lining, described Prefabricated Concrete pile lining is made up of the assembled concrete pipe of some Prefabricated Concrete sheets or mixed by the assembled concrete pipe of some Prefabricated Concrete sheets and Prefabricated Concrete pipe, this Prefabricated Concrete pile lining is a part for pile body, is the retaining wall protection system of stake holes when pile operation; Be provided with the expanding body of concrete outside described stake or at the bottom of stake or outside stake He at the bottom of stake, the expanding body of the concrete outside described stake is Prefabricated Concrete contract block, and Prefabricated Concrete contract block is corresponding with Prefabricated Concrete sheet to be arranged, and is longitudinally pressed in foundation soil outside stake, with fixing mounted concrete sheet; The expanding body of concrete at the bottom of described stake is completing the expanding body of concrete done operation at the bottom of the hole of carrying out in the stake holes of pile body hole wall Prefabricated Concrete retaining wall system and formed.
2. pore-creating filling pile according to claim 1, is characterized in that: have grouting layer outside Prefabricated Concrete pile lining, and grouting layer is with can the cement paste of rapid solidification be formed slip casting outside Prefabricated Concrete pile lining, with fixing mounted concrete sheet and sealing.
3. pore-creating filling pile according to claim 1 and 2, is characterized in that: at the bottom of stake, boulder and cobble bearing stratum has injecting cement paste.
CN201510618589.6A 2015-09-25 2015-09-25 A kind of pore-creating filling pile Active CN105239562B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510618589.6A CN105239562B (en) 2015-09-25 2015-09-25 A kind of pore-creating filling pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510618589.6A CN105239562B (en) 2015-09-25 2015-09-25 A kind of pore-creating filling pile

Publications (2)

Publication Number Publication Date
CN105239562A true CN105239562A (en) 2016-01-13
CN105239562B CN105239562B (en) 2017-09-08

Family

ID=55037361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510618589.6A Active CN105239562B (en) 2015-09-25 2015-09-25 A kind of pore-creating filling pile

Country Status (1)

Country Link
CN (1) CN105239562B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523200A (en) * 2020-12-18 2021-03-19 郑州大学综合设计研究院有限公司 Integrated tubular pile

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08209689A (en) * 1993-02-26 1996-08-13 Nippon Concrete Ind Co Ltd Construction work method for pile
CN2387145Y (en) * 1999-09-02 2000-07-12 阎慧奎 Mounting concrete precast dado for hole digging pile
CN104120716A (en) * 2013-04-28 2014-10-29 杨哲 Slurry wall protection construction method for bored pile
CN204940257U (en) * 2015-09-25 2016-01-06 黄国庆 A kind of pore-creating filling pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08209689A (en) * 1993-02-26 1996-08-13 Nippon Concrete Ind Co Ltd Construction work method for pile
CN2387145Y (en) * 1999-09-02 2000-07-12 阎慧奎 Mounting concrete precast dado for hole digging pile
CN104120716A (en) * 2013-04-28 2014-10-29 杨哲 Slurry wall protection construction method for bored pile
CN204940257U (en) * 2015-09-25 2016-01-06 黄国庆 A kind of pore-creating filling pile

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
徐湘生等: "人工挖孔扩底灌注桩在复杂地质条件下的施工", 《建筑技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523200A (en) * 2020-12-18 2021-03-19 郑州大学综合设计研究院有限公司 Integrated tubular pile

Also Published As

Publication number Publication date
CN105239562B (en) 2017-09-08

Similar Documents

Publication Publication Date Title
CN103321244B (en) Sand foundation existing building sets up the construction method of basement
CN101139839B (en) Setting arrangement for high artesian area ultra-deep foundation pit
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN104988907A (en) Construction method of concrete pile
CN105464074B (en) A kind of artificial digging pile high polymer grouting safeguard structure and its construction method
CN103882881A (en) Underwater construction method for bearing platform deeply embedded in rock
CN105649012A (en) Construction method for bored pile of subway station enclosure structure of upper-soft lower-hard ground
CN104963346A (en) Support construction method for deep foundation pit in complex geological condition
CN111705786A (en) Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile
CN203213101U (en) Embedding grouting combined pile
CN106677166A (en) Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode
CN104074197B (en) The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure
CN102235152A (en) Hole-forming construction method for bored pile on high-strength stabilized soil layer
CN107100160A (en) A kind of construction technology for lower storage reservoir check dam vibro-replacement stone column
CN102418348B (en) Construction technology of using occlusive pile to form underground continuous wall
CN206752454U (en) One kind perfusion embedded pile
CN204940257U (en) A kind of pore-creating filling pile
CN102535462A (en) Method for constructing anchor cable on sand layer
CN105239562B (en) A kind of pore-creating filling pile
CN207109804U (en) A kind of quick spreading structure configuration of soft soil foundation bored concrete pile
CN107012792B (en) A kind of construction method of bridge substructure
CN212405174U (en) Supporting structure and building of soft rock foundation pit at lower part of upper soil layer
CN107476293A (en) A kind of quick spreading structure of soft soil foundation bored concrete pile configures and its spreading method
JPH08184058A (en) Landslide protection construction
CN102220760B (en) Method for casting deep inverted T-shaped pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant