CN104110035A - Perpendicularity correcting device for concrete-filled steel tube columns constructed by top-down process and construction method implemented by perpendicularity correcting device - Google Patents

Perpendicularity correcting device for concrete-filled steel tube columns constructed by top-down process and construction method implemented by perpendicularity correcting device Download PDF

Info

Publication number
CN104110035A
CN104110035A CN201310131150.1A CN201310131150A CN104110035A CN 104110035 A CN104110035 A CN 104110035A CN 201310131150 A CN201310131150 A CN 201310131150A CN 104110035 A CN104110035 A CN 104110035A
Authority
CN
China
Prior art keywords
verticality
steel
steel pipe
perpendicularity
correcting device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310131150.1A
Other languages
Chinese (zh)
Inventor
白秉英
赵建立
岳齐贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
CMTCC Shanghai Shisanye Construction Co Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
CMTCC Shanghai Shisanye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd, CMTCC Shanghai Shisanye Construction Co Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201310131150.1A priority Critical patent/CN104110035A/en
Publication of CN104110035A publication Critical patent/CN104110035A/en
Pending legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention relates to the field of pile foundation construction of foundation pit engineering, and discloses a perpendicularity correcting device for concrete-filled steel tube columns constructed by a top-down process. The perpendicularity correcting device comprises a steel casing, and is characterized by further comprising four steel supports, a crossed adjusting frame, two perpendicularity detecting rods, four perpendicularity adjusting jacks and four fine adjustment jacks; the crossed adjusting frame is arranged on the tops of the steel supports, the bottom of the crossed adjusting frame is firmly linked with the top of a to-be-detected steel tube, the four perpendicularity adjusting jacks are respectively arranged on the lower sides of four end points of the crossed adjusting frame, the four fine adjustment jacks are horizontally arranged on the outer wall of the to-be-detected steel tube, and the perpendicularity detecting rods are respectively perpendicularly and firmly connected to the top of the to-be-detected steel tube. The invention further discloses a construction method implemented by the perpendicularity correcting device. The perpendicularity correcting device and the construction method have the advantages that the perpendicularity correcting device and the construction method are mainly applied to construction operation on the column-pile steel tube columns constructed by the top-down process; the perpendicularity correcting device and the construction method are high in universality, the perpendicularity correcting device is simple in manufacture, and the perpendicularity of the column-pile steel tube columns constructed by the top-down process can be controlled at a low cost; the perpendicularity correcting device is simple in structure, easy to manufacture and convenient to operate.

Description

Contrary sequence method steel core concrete column perpendicularity correction equipment and construction method thereof
Technical field
The present invention relates to base pit engineering pile foundation construction field, relate in particular to base pit engineering pile foundation area of maintenance.
Background technology
Pit top-down construction was used more and more in recent years.Pit top-down construction, first along building basement sideline or foundation ditch surrounding construction diaphragm wall, engineering pile and the stand column pile of construction foundation pit inside simultaneously, the basement roof of then constructing is as cross binding, downward earth excavation and build each layer of underground structure successively subsequently, until base plate back cover.It is little that reverse construction has space enclosing structure deflection, little on the impact of adjacent building, takies construction space little, shortens the advantages such as engineering time.
During foundation ditch adverse construction method, by stand column pile, bear beam and slab structure deadweight and working load.These loads transmit by inserting the support post of stand column pile inside.This vertical supporting mode is also referred to as a post.Support post adopts steel core concrete column or shaped steel lattice column conventionally.For steel core concrete column, except as vertical applied force member during adverse construction method, toward contact, as permanent structure post, use.Therefore, national regulation has strict control requirement to the verticality of steel core concrete column.In < < underground structrue engineering contrary sequence method technical specification > > JGJ165-2010,6.4.1 money regulation: monolayer steel pipe concrete column verticality allowable variation is not more than 1/1000 and be not more than 25.0mm.
Through prior art literature search is found, steel core concrete column verticality is controlled a variety of construction methods, but all very complicated, is unfavorable for operation, is also unfavorable for promoting.As Shao Kaiping adopts two point control methods in application > > mono-literary composition of an one post construction " verticality two point control methods " of < < contrary sequence method, but must excavate active well, operating personnel's operation in active well during adjustment, complex procedures, operating efficiency is low.
Summary of the invention
The object of the invention is to, provide means for correcting that one of a kind of contrary sequence method foundation pit construction post steel core concrete column installs verticality its there is the advantages such as simple structure, easy to operate, floor space is little.
In order to achieve the above object, the present invention is achieved in that
A contrary sequence method steel core concrete column perpendicularity correction equipment, it comprises a steel casing, it is characterized in that: also comprise four steel supports, a cross adjustment rack, two verticality test rods, four verticality adjustment jack and four fine-adjustment jacks, every two of described steel support is one group, square crossing is arranged mutually, cross adjustment rack is arranged at two groups of steel support end faces and its bottom firmly links with steel pipe end face to be measured, four verticality are adjusted jack and are located at respectively the below of four end points of cross adjustment rack and are positioned in same level, four fine-adjustment jacks are horizontally placed on outer wall of steel pipe to be measured and adjust jack in same fore-and-aft plane with four verticality respectively, two verticality test rods are vertically firmly connected in respectively steel pipe top to be measured, and respectively with two mutually perpendicular end points of cross adjustment rack in same fore-and-aft plane.
A kind of construction method of means for correcting claimed in claim 1; It is characterized in that: it comprises the steps:
Step 1, plain concrete cure process is carried out in the region of the non-stake of steel core concrete column periphery hole site;
Step 2, after plain concrete is hardened to design strength, pre-buried one section of steel casing in stake hole site, and with stake a machine carry out pore-forming operation;
Step 3, stake are after a pore-forming completes, and land clearing is clean, at the axis of steel casing top measuring steel pipe column to be installed, and centered by the axis of steel pipe column to be installed, four steel supports fixing are installed mutually intersecting on vertical both direction;
Step 4, in steel casing, lay steel pipe column, steel pipe column should vertically slowly be put into, and reach absolute altitude, planar central meets designing requirement;
Step 5, cross adjustment rack and steel pipe column top are welded to connect;
Step 6, four end points of cross adjustment rack are supported on respectively on four steel supports, and meanwhile, four end points belows of cross adjustment rack are laid respectively a verticality and adjusted jack;
Step 7, at steel pipe column outer wall, be horizontally disposed with four fine-adjustment jacks, described four fine-adjustment jacks are adjusted jack in same fore-and-aft plane with four verticality respectively;
Step 8, at steel pipe column end face, weld respectively two verticality test rods, two verticality test rods respectively with two mutually perpendicular end points of cross adjustment rack in same fore-and-aft plane;
Step 9, with two transits, by two verticality test rods, observe vertical axis and the plan-position of steel pipe column;
Step 10, according to the observational record of verticality test rod, by corresponding four verticality of jacking, adjust any one in jack, reach the corresponding cross adjustment rack of jacking, thereby adjust steel pipe column verticality and absolute altitude to meeting code requirement, and jack is fixed;
After step 11, steel pipe column top are fixed, in steel casing, with four fine-adjustment jacks, steel pipe column is carried out to verticality fine setting fixing.
The present invention adopts said apparatus and construction method, and it is mainly for the construction operation of inverse method one-column one-pile steel pipe column; Meanwhile, highly versatile, makes simply the control that has solved inverse method one-column one-pile steel pipe column verticality with lower cost.Simple structure, makes easily, easy to operate.
Accompanying drawing explanation
Fig. 1 is top view of the present invention.
Fig. 2 is left view of the present invention.
The specific embodiment
By specific embodiment, further illustrate the present invention below.
As shown in Figure 1 and Figure 2, a kind of contrary sequence method steel core concrete column perpendicularity correction equipment, it comprises a steel casing 2, also comprises that four steel supports 7, cross adjustment rack 4, two verticality test rods 3, four verticality adjust jack 6 and four fine-adjustment jacks 5, every two of described steel support 7 is one group, square crossing is arranged mutually, cross adjustment rack 4 is arranged at two groups of steel support 7 end faces and its bottom firmly links with steel pipe 1 end face to be measured, four verticality are adjusted jack 6 and are located at respectively the below of 4 four end points of cross adjustment rack and are positioned in same level, four fine-adjustment jack water 5 is flat to be arranged at steel pipe 1 outer wall to be measured and to adjust very heavy 6 tops in same fore-and-aft plane with four verticality respectively, two verticality test rods 3 are vertically firmly connected in respectively steel pipe to be measured 1 top, and respectively with 4 two mutually perpendicular end points of cross adjustment rack in same fore-and-aft plane.
The construction method of described means for correcting; It comprises the steps:
Step 1, plain concrete cure process is carried out in the region of the non-stake of steel core concrete column periphery hole site;
Step 2, after plain concrete is hardened to design strength, the long steel casing 2 of pre-buried one section of 1.5m in stake hole site, and carry out pore-forming operation with a machine;
Step 3, stake are after a pore-forming completes, and land clearing is clean, at the axis of steel casing 2 top measuring steel pipe column 1 to be installed, and centered by the axis of steel pipe column 1 to be installed, four steel supports 7 fixing are installed mutually intersecting on vertical both direction;
Step 4, in steel casing 2, lay steel pipe column 1, steel pipe column 1 should vertically slowly be put into, and reach absolute altitude, planar central meets designing requirement;
Step 5, cross adjustment rack 4 is connected with steel pipe column 1 welded top;
Step 6,4 four end points of cross adjustment rack are supported on respectively on four steel supports 7, and meanwhile, 4 four end points belows of cross adjustment rack are laid respectively a verticality and adjusted jack 6;
Step 7, at steel pipe column 1 outer wall, from steel casing 2 tops, down 1 meter of is horizontally disposed with four fine-adjustment jacks 5, described four fine-adjustment jacks 5 are adjusted very heavy 6 tops in same fore-and-aft plane with four verticality respectively;
Step 8, steel pipe column 1 end face weld respectively 3, two verticality test rods 3 of two verticality test rods respectively with 4 two mutually perpendicular end points of cross adjustment rack in same fore-and-aft plane;
Step 9, with two transits, by two verticality test rods 3, observe vertical axis and the plan-position of steel pipe column 1;
Step 10, according to the observational record of verticality test rod 3, by corresponding four verticality of jacking, adjust any one in jack 6, reach the corresponding cross adjustment rack 4 of jacking, thereby adjust steel pipe column 1 verticality and absolute altitude to meeting code requirement, and jack is fixed;
After step 11, steel pipe column 1 top are fixed, at four fine-adjustment jacks 5 of the interior use of steel casing 2, steel pipe column 1 is carried out to verticality fine setting fixing.
The present invention adopts said apparatus and construction method, and it is mainly for the construction operation of inverse method one-column one-pile steel pipe column; Meanwhile, highly versatile, makes simply the control that has solved inverse method one-column one-pile steel pipe column verticality with lower cost.Simple structure, makes easily, easy to operate.

Claims (2)

1. a contrary sequence method steel core concrete column perpendicularity correction equipment, it comprises a steel casing, it is characterized in that: also comprise that four steel supports, a cross adjustment rack, two verticality test rods, four verticality adjust jack and four fine-adjustment jacks, every two of described steel support is one group, square crossing is arranged mutually, cross adjustment rack is arranged at two groups of steel support end faces and its bottom firmly links with steel pipe end face to be measured, four verticality are adjusted jack and are located at respectively the below of four end points of cross adjustment rack and are positioned in same level, four fine-adjustment jacks are horizontally placed on outer wall of steel pipe to be measured and adjust jack in same fore-and-aft plane with four verticality respectively, two verticality test rods are vertically firmly connected in respectively steel pipe top to be measured, and respectively with two mutually perpendicular end points of cross adjustment rack in same fore-and-aft plane.
2. the construction method of a means for correcting claimed in claim 1; It is characterized in that: it comprises the steps:
Step 1, plain concrete cure process is carried out in the region of the non-stake of steel core concrete column periphery hole site;
Step 2, after plain concrete is hardened to design strength, pre-buried one section of steel casing in stake hole site, and with stake a machine carry out pore-forming operation;
Step 3, stake are after a pore-forming completes, and land clearing is clean, at the axis of steel casing top measuring steel pipe column to be installed, and centered by the axis of steel pipe column to be installed, four steel supports fixing are installed mutually intersecting on vertical both direction;
Step 4, in steel casing, lay steel pipe column, steel pipe column should vertically slowly be put into, and reach absolute altitude, planar central meets designing requirement;
Step 5, cross adjustment rack and steel pipe column top are welded to connect;
Step 6, four end points of cross adjustment rack are supported on respectively on four steel supports, and meanwhile, four end points belows of cross adjustment rack are laid respectively a verticality and adjusted jack;
Step 7, at steel pipe column outer wall, be horizontally disposed with four fine-adjustment jacks, described four fine-adjustment jacks are adjusted jack in same fore-and-aft plane with four verticality respectively;
Step 8, at steel pipe column end face, weld respectively two verticality test rods, two verticality test rods respectively with two mutually perpendicular end points of cross adjustment rack in same fore-and-aft plane;
Step 9, with two transits, by two verticality test rods, observe vertical axis and the plan-position of steel pipe column;
Step 10, according to the observational record of verticality test rod, by corresponding four verticality of jacking, adjust any one in jack, reach the corresponding cross adjustment rack of jacking, thereby adjust steel pipe column verticality and absolute altitude to meeting code requirement, and jack is fixed;
After step 11, steel pipe column top are fixed, in steel casing, with four fine-adjustment jacks, steel pipe column is carried out to verticality fine setting fixing.
CN201310131150.1A 2013-04-16 2013-04-16 Perpendicularity correcting device for concrete-filled steel tube columns constructed by top-down process and construction method implemented by perpendicularity correcting device Pending CN104110035A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310131150.1A CN104110035A (en) 2013-04-16 2013-04-16 Perpendicularity correcting device for concrete-filled steel tube columns constructed by top-down process and construction method implemented by perpendicularity correcting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310131150.1A CN104110035A (en) 2013-04-16 2013-04-16 Perpendicularity correcting device for concrete-filled steel tube columns constructed by top-down process and construction method implemented by perpendicularity correcting device

Publications (1)

Publication Number Publication Date
CN104110035A true CN104110035A (en) 2014-10-22

Family

ID=51707013

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310131150.1A Pending CN104110035A (en) 2013-04-16 2013-04-16 Perpendicularity correcting device for concrete-filled steel tube columns constructed by top-down process and construction method implemented by perpendicularity correcting device

Country Status (1)

Country Link
CN (1) CN104110035A (en)

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104389313A (en) * 2014-11-13 2015-03-04 中国电建集团铁路建设有限公司 Positioning perpendicularity adjusting device and method of dual-spliced I-shaped steel latticed column
CN104532843A (en) * 2014-12-26 2015-04-22 中国一冶集团有限公司 Method for positioning and straightening steel stand column of stand column pile
CN105672314A (en) * 2016-01-19 2016-06-15 中建八局第三建设有限公司 Method for constructing steel pipe upright pile through semi-reversed-construction method
CN106013206A (en) * 2016-06-03 2016-10-12 广东省源天工程有限公司 Steel pipe column positioning device and steel pipe concrete column and pile foundation connecting structure
CN106436743A (en) * 2016-10-21 2017-02-22 开普天(上海)国际贸易有限公司 Guide pipe for steel stand column guide insertion construction
CN106555401A (en) * 2016-10-21 2017-04-05 开普天(上海)国际贸易有限公司 For the stand of guide pipe top positioning
CN106958244A (en) * 2017-04-27 2017-07-18 中铁隧道集团四处有限公司 The installation and locating method of ultra-deep and large diameter steel pipe column
CN107013046A (en) * 2017-06-19 2017-08-04 中冶建工集团有限公司 A kind of antidote of heavy in section concrete filled steel tube coupled column
CN108240887A (en) * 2017-12-27 2018-07-03 安徽金大仪器有限公司 A kind of radio data pressure meter with installation auxiliary device
CN108374418A (en) * 2018-03-26 2018-08-07 中铁五局集团有限公司 Steel pipe column precise positioning Fast Installation construction technology in a kind of sheltered reverse excavation
CN109025328A (en) * 2018-08-21 2018-12-18 中国十七冶集团有限公司 A kind of degree control method in lattice column work progress
CN109487822A (en) * 2018-12-05 2019-03-19 昆明捷程桩工有限责任公司 Reverse construction erection of steel pipe column method of adjustment and control device
CN109629555A (en) * 2018-06-21 2019-04-16 中铁十局集团第六工程有限公司 Improve the positioning device of empty stake interpolation steel pipe column and the method for pile integrated construction
CN110016914A (en) * 2019-05-06 2019-07-16 福建省九龙建设集团有限公司 Contrary sequence method steel pipe column perpendicularity correction equipment and steel pipe column construction method
CN110106881A (en) * 2019-05-30 2019-08-09 中国电建市政建设集团有限公司 A kind of steel-pipe pile construction guidance locating rack and construction method
CN110219326A (en) * 2019-05-23 2019-09-10 海天建设集团有限公司 The underwater vertical adjustment construction technology of inverse method one-column one-pile
CN110629756A (en) * 2018-06-21 2019-12-31 北京东地岩土工程有限公司 Anchor cable removing method
CN110836019A (en) * 2019-12-04 2020-02-25 中建二局第一建筑工程有限公司 Novel lattice column verticality positioner
CN111441349A (en) * 2020-04-03 2020-07-24 中铁大桥局集团第五工程有限公司 Construction method for accurately positioning steel pipe column of urban bridge and subway co-constructed pile foundation
CN111622224A (en) * 2020-06-06 2020-09-04 江西中恒地下空间科技有限公司 Construction method of connected column pile in reverse construction method
CN112267467A (en) * 2020-11-05 2021-01-26 中国建筑第四工程局有限公司 Adjustable support for accurate positioning of permanent double-steel-pipe column
CN112942367A (en) * 2021-02-03 2021-06-11 中铁十五局集团第五工程有限公司 Steel pipe column of HPE hydraulic pressure inserted bored concrete pile
CN112982828A (en) * 2021-02-05 2021-06-18 中铁广州工程局集团深圳工程有限公司 Steel pipe column and reinforcement cage integrated structure and construction method thereof
CN114108624A (en) * 2021-12-21 2022-03-01 中建八局第三建设有限公司 Two-adjustment one-control type perpendicularity control construction method for one-column one-pile steel pipe column
CN114108630A (en) * 2021-12-31 2022-03-01 张忠良 Civil engineering building foundation pile construction equipment
CN114622556A (en) * 2022-03-24 2022-06-14 中国电建市政建设集团有限公司 AI image recognition-based CFG pile intelligent deviation rectifying method and device
CN115492403A (en) * 2022-10-09 2022-12-20 浙江省一建建设集团有限公司 Combined type precise positioning construction device for tower footing steel latticed column

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000001854A (en) * 1998-06-15 2000-01-07 Shimizu Corp Structural stud erection device and structural stud erection method
CN201258496Y (en) * 2008-08-11 2009-06-17 上海市机械施工有限公司 One-column and one-pile correcting device
CN101824919A (en) * 2010-03-26 2010-09-08 中铁隧道集团有限公司 Deep hole underwater installation and locating method of steel pipe column in weak watery stratum
CN102767182A (en) * 2012-07-18 2012-11-07 上海建工二建集团有限公司 Verticality adjustment system for lattice column correcting mount and construction method thereof
CN203256744U (en) * 2013-04-16 2013-10-30 中冶天工上海十三冶建设有限公司 Device for correcting perpendicularity of concrete-filled steel tubular column through reverse construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000001854A (en) * 1998-06-15 2000-01-07 Shimizu Corp Structural stud erection device and structural stud erection method
CN201258496Y (en) * 2008-08-11 2009-06-17 上海市机械施工有限公司 One-column and one-pile correcting device
CN101824919A (en) * 2010-03-26 2010-09-08 中铁隧道集团有限公司 Deep hole underwater installation and locating method of steel pipe column in weak watery stratum
CN102767182A (en) * 2012-07-18 2012-11-07 上海建工二建集团有限公司 Verticality adjustment system for lattice column correcting mount and construction method thereof
CN203256744U (en) * 2013-04-16 2013-10-30 中冶天工上海十三冶建设有限公司 Device for correcting perpendicularity of concrete-filled steel tubular column through reverse construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
中国市政工程协会等: "《2011中国城市地下空间开发高峰论坛论文集》", 30 November 2011, 武汉:武汉理工大学出版社 *

Cited By (36)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104389313B (en) * 2014-11-13 2016-04-20 中国电建集团铁路建设有限公司 The positioning and plumbing device of Two bors d's oeuveres type i iron lattice column and positioning and plumbing method thereof
CN104389313A (en) * 2014-11-13 2015-03-04 中国电建集团铁路建设有限公司 Positioning perpendicularity adjusting device and method of dual-spliced I-shaped steel latticed column
CN104532843A (en) * 2014-12-26 2015-04-22 中国一冶集团有限公司 Method for positioning and straightening steel stand column of stand column pile
CN104532843B (en) * 2014-12-26 2016-08-24 中国一冶集团有限公司 A kind of steel column location straightening method of stand column pile
CN105672314A (en) * 2016-01-19 2016-06-15 中建八局第三建设有限公司 Method for constructing steel pipe upright pile through semi-reversed-construction method
CN105672314B (en) * 2016-01-19 2017-10-10 中建八局第三建设有限公司 A kind of semi-inverse method steel pipe post pile construction method
CN106013206A (en) * 2016-06-03 2016-10-12 广东省源天工程有限公司 Steel pipe column positioning device and steel pipe concrete column and pile foundation connecting structure
CN106013206B (en) * 2016-06-03 2017-12-29 广东省源天工程有限公司 Steel pipe column positioning device, steel core concrete column and pile foundation attachment structure
CN106436743B (en) * 2016-10-21 2019-10-01 开普天(上海)国际贸易有限公司 The guide pipe of insertion construction is oriented to for steel column
CN106436743A (en) * 2016-10-21 2017-02-22 开普天(上海)国际贸易有限公司 Guide pipe for steel stand column guide insertion construction
CN106555401A (en) * 2016-10-21 2017-04-05 开普天(上海)国际贸易有限公司 For the stand of guide pipe top positioning
CN106555401B (en) * 2016-10-21 2019-10-01 开普天(上海)国际贸易有限公司 Rack for the positioning of guide pipe top
CN106958244A (en) * 2017-04-27 2017-07-18 中铁隧道集团四处有限公司 The installation and locating method of ultra-deep and large diameter steel pipe column
CN106958244B (en) * 2017-04-27 2019-01-29 中铁隧道集团四处有限公司 The installation and locating method of ultra-deep and large diameter steel pipe column
CN107013046A (en) * 2017-06-19 2017-08-04 中冶建工集团有限公司 A kind of antidote of heavy in section concrete filled steel tube coupled column
CN107013046B (en) * 2017-06-19 2019-04-05 中冶建工集团有限公司 A kind of antidote of big section steel pipe concrete combination column
CN108240887A (en) * 2017-12-27 2018-07-03 安徽金大仪器有限公司 A kind of radio data pressure meter with installation auxiliary device
CN108374418A (en) * 2018-03-26 2018-08-07 中铁五局集团有限公司 Steel pipe column precise positioning Fast Installation construction technology in a kind of sheltered reverse excavation
CN109629555A (en) * 2018-06-21 2019-04-16 中铁十局集团第六工程有限公司 Improve the positioning device of empty stake interpolation steel pipe column and the method for pile integrated construction
CN110629756A (en) * 2018-06-21 2019-12-31 北京东地岩土工程有限公司 Anchor cable removing method
CN109025328A (en) * 2018-08-21 2018-12-18 中国十七冶集团有限公司 A kind of degree control method in lattice column work progress
CN109487822A (en) * 2018-12-05 2019-03-19 昆明捷程桩工有限责任公司 Reverse construction erection of steel pipe column method of adjustment and control device
CN110016914A (en) * 2019-05-06 2019-07-16 福建省九龙建设集团有限公司 Contrary sequence method steel pipe column perpendicularity correction equipment and steel pipe column construction method
CN110219326A (en) * 2019-05-23 2019-09-10 海天建设集团有限公司 The underwater vertical adjustment construction technology of inverse method one-column one-pile
CN110106881A (en) * 2019-05-30 2019-08-09 中国电建市政建设集团有限公司 A kind of steel-pipe pile construction guidance locating rack and construction method
CN110836019A (en) * 2019-12-04 2020-02-25 中建二局第一建筑工程有限公司 Novel lattice column verticality positioner
CN111441349A (en) * 2020-04-03 2020-07-24 中铁大桥局集团第五工程有限公司 Construction method for accurately positioning steel pipe column of urban bridge and subway co-constructed pile foundation
CN111622224A (en) * 2020-06-06 2020-09-04 江西中恒地下空间科技有限公司 Construction method of connected column pile in reverse construction method
CN112267467A (en) * 2020-11-05 2021-01-26 中国建筑第四工程局有限公司 Adjustable support for accurate positioning of permanent double-steel-pipe column
CN112942367A (en) * 2021-02-03 2021-06-11 中铁十五局集团第五工程有限公司 Steel pipe column of HPE hydraulic pressure inserted bored concrete pile
CN112982828A (en) * 2021-02-05 2021-06-18 中铁广州工程局集团深圳工程有限公司 Steel pipe column and reinforcement cage integrated structure and construction method thereof
CN114108624A (en) * 2021-12-21 2022-03-01 中建八局第三建设有限公司 Two-adjustment one-control type perpendicularity control construction method for one-column one-pile steel pipe column
CN114108630A (en) * 2021-12-31 2022-03-01 张忠良 Civil engineering building foundation pile construction equipment
CN114622556A (en) * 2022-03-24 2022-06-14 中国电建市政建设集团有限公司 AI image recognition-based CFG pile intelligent deviation rectifying method and device
CN114622556B (en) * 2022-03-24 2023-08-08 中国电建市政建设集团有限公司 Intelligent correction method and correction device for CFG pile based on AI image recognition
CN115492403A (en) * 2022-10-09 2022-12-20 浙江省一建建设集团有限公司 Combined type precise positioning construction device for tower footing steel latticed column

Similar Documents

Publication Publication Date Title
CN104110035A (en) Perpendicularity correcting device for concrete-filled steel tube columns constructed by top-down process and construction method implemented by perpendicularity correcting device
CN205296874U (en) Information -based construction monitor positioning device of stake integration
CN105887811B (en) Ultra-deep weak soil pile integral construction method is monitored based on precise informationization
CN104264902B (en) Structure for connecting concrete filled steel tubular column with pile foundation
CN202658909U (en) Steel column positioning rack based on reverse-building method
CN108265618B (en) Underground reverse storey-adding construction method for viaduct pier foundation
CN102888865A (en) Method and device for correcting perpendicularity of steel structural member in process of constructing vertical column pile
CN102587648A (en) Gate-type steel pipe and fastener-type steel pipe fabricated formwork support device and construction method
KR20120033683A (en) Device for constructing an underground structure and method thereof
CN106013206A (en) Steel pipe column positioning device and steel pipe concrete column and pile foundation connecting structure
CN104878786B (en) Tiltedly orthogonal is for group&#39;s Pile-soil-structure Interaction experimental model
CN112878354A (en) Beam-slab assembled prestressed concrete foundation for onshore wind turbine generator
KR101567628B1 (en) The jackup device for the extension and floor increase
CN103061454A (en) Locating method of installing concrete filled steel tubular column in underground deep hole
CN105297731A (en) Reverse construction method steel stand column positioning device and positioning method
CN102966254A (en) Measuring tower used for construction of stub matching method and arrangement thereof
CN111119260B (en) Deviation rectifying method applying dynamic monitoring and dynamic reinforcement
CN204753656U (en) A clump of piles - soil - structure interact experimental model directly replaces to one side
CN203256744U (en) Device for correcting perpendicularity of concrete-filled steel tubular column through reverse construction method
TWM510942U (en) Precasted concrete foundation for upright shape steel post
CN104652445A (en) Pile and column steel latticed column location device for deep foundation pits and construction method for location device
CN104153374A (en) Combined foundation pit supporting structure with inclined strut and pull anchor
CN210002459U (en) Underpinning system for repairing tunnel and passing through existing building for active underpinning
CN104568573A (en) Bracket device for hydrostatic test of in-service spherical tank and regulating method
CN108755669B (en) Construction method for cross-tunnel steel reinforced concrete cast-in-place pile and transfer beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20141022

RJ01 Rejection of invention patent application after publication