JP2000001854A - Structural stud erection device and structural stud erection method - Google Patents

Structural stud erection device and structural stud erection method

Info

Publication number
JP2000001854A
JP2000001854A JP10167409A JP16740998A JP2000001854A JP 2000001854 A JP2000001854 A JP 2000001854A JP 10167409 A JP10167409 A JP 10167409A JP 16740998 A JP16740998 A JP 16740998A JP 2000001854 A JP2000001854 A JP 2000001854A
Authority
JP
Japan
Prior art keywords
level
guide pipe
gantry
pillar
straight
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10167409A
Other languages
Japanese (ja)
Other versions
JP3750042B2 (en
Inventor
Yasuo Kajioka
保夫 梶岡
Toshiya Nomichi
利哉 野路
Shoichi Mochida
正一 持田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP16740998A priority Critical patent/JP3750042B2/en
Publication of JP2000001854A publication Critical patent/JP2000001854A/en
Application granted granted Critical
Publication of JP3750042B2 publication Critical patent/JP3750042B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a permanent substructural column erection device and a permanent substructural column erection method capable of facilitating the erection of a structural stud and the correction, etc., in the case of ground subsidence, etc. SOLUTION: A permanent substructural column erection device 1 is constituted of a guide pipe 4 and a base holder 5, and the base holder 5 is equipped with a rising and falling jack 11 for adjusting a slope level of the base holder and a level indicator 30 for indicating the slope level. The layout of the guide pipe 4 is once made in a state to set the base holder 5 and guide pipe 4 in a unit, the slope level of the base holder 5 indicated by the level indicator 30 is then recorded, and then, in the case the layout of the guide pipe 4 is required to be made again, the level adjustment of the base holder 5 is made in accordance with the slope level kept in a record.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地盤に形成した掘
削孔内に構真柱を高精度で建入れるときに用いて好適な
構真柱建入れ装置および構真柱建入れ工法に関するもの
である。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a trussed pillar installation apparatus and a trussed pillar erection method suitable for use when laying a trussed pillar with high precision in an excavation hole formed in the ground. is there.

【0002】[0002]

【従来の技術】従来、例えば、逆打ち工法で高層ビルの
地下部や地下構造物を構築するに際しては、地盤に掘削
孔を形成して構真柱(本設の鉄骨柱)を所定精度で建て
入れた後に、バックホー等を用いて掘削孔を土砂で埋め
戻し、その後、施工の進捗に伴って地盤を根切りしなが
ら、上方から下方に向けて本設の鉄骨梁を前記構真柱に
順次取り付けるようにしている。
2. Description of the Related Art Conventionally, for example, when constructing an underground part or an underground structure of a high-rise building by a reverse striking method, an excavation hole is formed in the ground and a straight column (a permanent steel column) is formed with a predetermined accuracy. After erection, the excavation hole was backfilled with earth and sand using a backhoe, etc., and then, while cutting off the ground as the construction progressed, the steel beam of the main construction was installed from the top to the bottom to the straight pillar. They are to be installed sequentially.

【0003】このような構真柱の建入れは、その平面上
の位置(通り芯位置)と鉛直度および上下レベルを精度
良く維持した状態で、構真柱の少なくとも下端部をコン
クリートで固める必要がある。そのため、例えば掘削孔
の周縁部に筒状のスタンドパイプを略鉛直にセットし、
構真柱の側面にジャッキ等を取り付けてこれを水平方向
に伸縮させ、その反力をスタンドパイプに取ることによ
って構真柱の鉛直度の調整を行う工法等が開発されてい
る。
In order to install such a straight pillar, it is necessary to solidify at least the lower end of the straight pillar with concrete while maintaining the position on the plane (position of the center line), the verticality and the vertical level accurately. There is. Therefore, for example, a cylindrical stand pipe is set substantially vertically on the periphery of the drilling hole,
A method has been developed in which a jack or the like is attached to the side surface of a timber shaft, which is expanded and contracted in the horizontal direction, and the vertical force of the timber shaft is adjusted by taking the reaction force of the stand pipe.

【0004】ところで、構真柱を建入れるに際しては、
掘削孔内に構真柱を建入れた後にコンクリートを後打ち
するコンクリート後打ち式と、掘削孔内にコンクリート
を先打ちした後に構真柱を建入れるコンクリート先打ち
式とがある。このうち、コンクリート後打ち式では、構
真柱を挿入した後の狭い空間にコンクリート打設用のト
レミー管等を挿入しなければならず、作業に手間が掛か
るものとなっている。一方、コンクリート先打ち式では
このような問題は生じないものの、当然のことながら先
打ちしたコンクリートが硬化するまでの間に構真柱の建
入れ調整を完了する必要がある。ところが、前記工法で
は、ジャッキ等を用いて構真柱の鉛直度の調整を行って
いたのでは時間が掛かるため、コンクリート先打ち方式
に適していない。
[0004] By the way, when building a tall pillar,
There is a concrete post-casting type in which concrete is post-installed in a drill hole and a concrete post-casting type in which concrete is pre-cast in an excavation hole and a concrete post-installed type. Of these, in the concrete post-casting method, it is necessary to insert a tremy pipe or the like for concrete casting in a narrow space after the timber pillar is inserted, and the work is troublesome. On the other hand, although such a problem does not occur in the concrete pre-casting method, it is, of course, necessary to complete the adjustment of the straight pillars before the pre-cast concrete hardens. However, in the above-described method, it is not suitable for the concrete pre-casting method because it takes time to adjust the verticality of the straight pillar using a jack or the like.

【0005】しかも、前記工法では、建入れる構真柱の
サイズに合わせてジャッキを取り付けるためのブラケッ
ト等を用意しなければならず、これにも手間とコストが
かかるという問題がある。
In addition, in the above-mentioned construction method, it is necessary to prepare a bracket or the like for attaching a jack in accordance with the size of the framed pillar to be built, and this also has a problem that it is troublesome and costly.

【0006】この問題を解決するため、本出願人は、内
周面にガイドレールを備えたガイドパイプを予め鉛直に
建て込み、構真柱をガイドレールに沿って掘削孔内に挿
入することによって鉛直に建て入れる装置および工法を
既に出願している(特願平8−163511号)。
[0006] In order to solve this problem, the present applicant has previously built a guide pipe having a guide rail on the inner peripheral surface in a vertical direction, and inserted a straight pillar into the excavation hole along the guide rail. We have already filed an application for a device to be built vertically and a construction method (Japanese Patent Application No. 8-163511).

【0007】[0007]

【発明が解決しようとする課題】しかしながら、上述し
たような本出願人が提案した技術においても、以下に示
すような問題が残されている。ガイドパイプやこれを支
持する架台は切削等の機械加工によって製作されるわけ
ではなく、それ自体に高い精度を要求することができな
い。したがって掘削孔の周縁部に架台を設置した状態で
架台の水平を出したとしても、その後ガイドパイプをセ
ットしたときに鉛直が出るとは限らず、このため、架台
にガイドパイプをセットした状態でガイドパイプの鉛直
出しを行わなければならない。また、他の位置に構真柱
を建入れるため、ガイドパイプと架台を移動させた場合
にも、その度にガイドパイプの位置出しを行う必要があ
る。そして、ガイドパイプの鉛直出しにはレーザ管等の
機器を用いなければならず、その準備や測定に手間が掛
かり、さらなる改善の余地がある。
However, the above-mentioned technique proposed by the present applicant still has the following problems. The guide pipe and the gantry for supporting the guide pipe are not manufactured by machining such as cutting, and cannot themselves require high precision. Therefore, even if the gantry is leveled out with the gantry installed at the periphery of the excavation hole, the vertical does not always come out when the guide pipe is set, and for this reason, with the guide pipe set on the gantry The guide pipe must be vertically extended. Further, in order to set up a timber pillar at another position, it is necessary to position the guide pipe each time the guide pipe and the gantry are moved. Then, a device such as a laser tube must be used for vertically projecting the guide pipe, and preparation and measurement thereof are troublesome, and there is room for further improvement.

【0008】しかも、地盤沈下等によりガイドパイプの
レベルがズレた場合、その位置修正に再度手間がかかる
のはいうまでもなく、またガイドパイプの通り芯位置が
ずれると、ガイドパイプの位置を水平方向に修正する手
段がないため、その修正は非常に困難である。
In addition, when the level of the guide pipe shifts due to land subsidence or the like, it is needless to say that it takes time and effort to correct the position of the guide pipe. The correction is very difficult because there is no means to correct in the direction.

【0009】本発明は、以上のような点を考慮してなさ
れたもので、構真柱の建入れおよび地盤沈下時等の修正
等を容易に行うことのできる構真柱建入れ装置および構
真柱建入れ工法を提供することを課題とする。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned points, and has a structure and an apparatus for directly installing a straight pole, which can easily perform the correction of land subsidence and the like. It is an object to provide a method of building a pillar.

【0010】[0010]

【課題を解決するための手段】請求項1に係る発明は、
地盤中に形成された掘削孔内に構真柱を建て入れる装置
であって、前記構真柱を建入れるときにこれをガイドす
る筒状のガイドパイプと、前記掘削孔の周縁の地表面に
設置されて前記ガイドパイプを支持する架台と、を備え
て構成され、前記架台には、該架台の水平面に対する傾
斜レベルを調整するレベル調整手段と、前記架台の傾斜
レベルを示すレベル表示手段とが備えられていることを
特徴としている。
The invention according to claim 1 is
A device for erection of a trussed pillar in an excavation hole formed in the ground, and a tubular guide pipe for guiding the erected pillar when the erection pillar is erected, A pedestal that is installed and supports the guide pipe, and the pedestal includes a level adjustment unit that adjusts a tilt level of the gantry with respect to a horizontal plane, and a level display unit that indicates a tilt level of the gantry. It is characterized by being provided.

【0011】これにより、ガイドパイプの位置出しを一
度行い、そのときレベル表示手段によって示される架台
の傾斜レベルを記録しておき、再度位置出しをする場合
には、記録した傾斜レベルに合わせてレベル調整手段で
架台の傾斜レベルを調整すればよい。このようにして、
一度位置出しを行えば、ガイドパイプの位置がずれたり
しても、レーザ管等を用いることなく、レベル表示手段
によって示される傾斜レベルにあわせるのみでガイドパ
イプの位置出しを行うことができる。なお、一回目に位
置出しを行うとき、および再度位置出しするときには、
いずれも架台の傾斜レベルを水平に合わせるのではな
く、あくまでもガイドパイプが鉛直となるようにする。
したがって、レベル表示手段で表示される傾斜レベル
は、ガイドパイプが鉛直となった状態での架台の傾斜レ
ベルを表示する。
Thus, once the guide pipe is positioned, the inclination level of the gantry indicated by the level display means is recorded at that time, and when re-positioning, the level is adjusted in accordance with the recorded inclination level. What is necessary is just to adjust the inclination level of a gantry by adjusting means. In this way,
Once the positioning is performed, even if the position of the guide pipe is shifted, the positioning of the guide pipe can be performed only by adjusting to the inclination level indicated by the level display means without using a laser tube or the like. When performing positioning for the first time and when positioning again,
In each case, instead of adjusting the tilt level of the gantry to horizontal, the guide pipe must be vertical.
Therefore, the tilt level displayed by the level display means indicates the tilt level of the gantry when the guide pipe is vertical.

【0012】請求項2に係る発明は、請求項1記載の構
真柱建入れ装置であって、前記レベル表示手段が、前記
架台の複数箇所にそれぞれ設置されたレベル測定器と、
これらのレベル測定器間に設けられて前記各レベル測定
器で傾斜レベルを測定するための液体等の媒体を互いに
連通させる連通管と、前記各レベル測定器での測定レベ
ルを表示する表示器とを備えて構成されていることを特
徴としている。
According to a second aspect of the present invention, there is provided the vertical-column building apparatus according to the first aspect, wherein the level display means includes a level measuring device installed at each of a plurality of positions of the gantry.
A communication pipe that is provided between these level measuring devices and communicates a medium such as a liquid for measuring a slope level with each of the level measuring devices, and a display that displays a measurement level of each of the level measuring devices. It is characterized by comprising.

【0013】これにより、各レベル測定器においては、
媒体の液面レベルが等しくなり、すなわち同一水平面に
対する複数箇所のレベルを知ることができる。また、こ
のようなレベル表示手段は、従来使用していたレーザ管
等に比較して非常に簡易な構成となっている。
Thus, in each level measuring device,
The liquid level of the medium becomes equal, that is, it is possible to know the levels at a plurality of points on the same horizontal plane. Further, such a level display means has a very simple configuration as compared with a conventionally used laser tube or the like.

【0014】請求項3に係る発明は、請求項1または2
記載の構真柱建入れ装置であって、前記架台が三本の脚
部によって立脚した構成となっていることを特徴として
いる。
The invention according to claim 3 is the invention according to claim 1 or 2
The erected pillar installation device according to claim 1, wherein the gantry is configured to be erected by three legs.

【0015】これにより、脚部を四本以上備えた場合に
対し、ガタつきが生じたりすることもなく、また各脚部
で分担する荷重も均一となる。また、三本脚なので、レ
ベル出しも容易である。
As a result, in comparison with a case where four or more legs are provided, rattling does not occur, and the load shared by each leg is also uniform. Also, because it has three legs, leveling is easy.

【0016】請求項4に係る発明は、請求項3記載の構
真柱建入れ装置であって、前記脚部の下端部が、略球面
状をなしていることを特徴としている。
According to a fourth aspect of the present invention, there is provided the vertical-column building apparatus according to the third aspect, wherein a lower end of the leg has a substantially spherical shape.

【0017】これにより、脚部の下端部とこの架台の設
置面とが点接触することとなり、ガタつき等が防止でき
る。
As a result, the lower end of the leg portion comes into point contact with the installation surface of the gantry, and rattling or the like can be prevented.

【0018】請求項5に係る発明は、請求項1から4の
いずれかに記載の構真柱建入れ装置であって、前記ガイ
ドパイプと前記架台との間には、前記ガイドパイプの水
平面内における通り芯位置を調整する芯調整手段が備え
られていることを特徴としている。
According to a fifth aspect of the present invention, there is provided the straight-column installation device according to any one of the first to fourth aspects, wherein a space between the guide pipe and the gantry is within a horizontal plane of the guide pipe. Is provided with a core adjusting means for adjusting the center line position in.

【0019】これにより、ガイドパイプの通り芯位置が
ずれた場合にも、芯調整手段で調整することができる。
Thus, even when the center position of the guide pipe is displaced, it can be adjusted by the core adjusting means.

【0020】請求項6に係る発明は、地盤中に形成され
た掘削孔内に構真柱を建て入れる工法であって、地盤に
掘削孔を略鉛直に形成し、前記掘削孔の周縁の地表面に
架台を設置するとともに、前記構真柱を建入れるときに
これをガイドする筒状のガイドパイプを前記架台にセッ
トし、この状態で、前記ガイドパイプを前記構真柱の通
り芯位置に合わせて位置出しし、このときの前記架台の
複数箇所における傾斜レベルを記録し、しかる後に、前
記ガイドパイプを再度位置出しするときには、前記記録
した傾斜レベルに合わせてレベル調整手段で前記架台を
レベル調整することを特徴としている。
According to a sixth aspect of the present invention, there is provided a method for erection of a straight pillar in a digging hole formed in the ground, wherein the digging hole is formed substantially vertically in the ground, and a ground around the periphery of the digging hole is formed. Along with installing a gantry on the surface, a cylindrical guide pipe that guides the trussed pillar when setting it is set on the gantry, and in this state, the guide pipe is placed at the center of the trussed pillar. In addition, when the guide pipe is repositioned afterwards, when the guide pipe is repositioned, the mount is leveled by level adjusting means in accordance with the recorded tilt level. It is characterized by adjustment.

【0021】このようにして、ガイドパイプの位置出し
を一度行い、そのときのレベル表示手段によって示され
る架台の傾斜レベルを記録しておくことによって、再度
位置修正をする場合等には、記録した傾斜レベルに合わ
せてレベル調整手段で架台の傾斜レベルを調整すればよ
い。しかも、このとき、レーザ管等を用いることなく、
レベル表示手段によって示される傾斜レベルにあわせる
のみで良く、作業を容易に行える。
In this way, when the position of the guide pipe is determined once and the inclination level of the gantry indicated by the level display means at that time is recorded, the position is recorded when the position is corrected again. What is necessary is just to adjust the inclination level of the gantry by the level adjusting means in accordance with the inclination level. Moreover, at this time, without using a laser tube or the like,
It is only necessary to match the inclination level indicated by the level display means, and the work can be easily performed.

【0022】[0022]

【発明の実施の形態】以下、本発明に係る構真柱建入れ
装置および構真柱建入れ工法の実施の形態の一例を、図
1ないし図6を参照して説明する。これらの図におい
て、符号Cは構真柱、Gは地盤、Hは構真柱Cを建て込
むため地盤Gに形成された掘削孔、1は構真柱Cを所定
の精度で建入れるための構真柱建入れ装置、2は周囲の
地盤Gの崩壊を防ぐため掘削孔Hの上部に設けられた円
筒状の鋼管からなるスタンドパイプ、をそれぞれ示して
いる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a timber-column construction apparatus and a timber-column construction method according to the present invention will be described below with reference to FIGS. In these figures, reference numeral C denotes a shaft, G denotes the ground, H denotes an excavation hole formed in the ground G for installing the shaft C, and 1 denotes a hole for installing the shaft C with predetermined accuracy. The vertical column building device 2 is a stand pipe made of a cylindrical steel pipe provided above the excavation hole H in order to prevent the collapse of the surrounding ground G.

【0023】図1に示すように、構真柱建入れ装置1
は、スタンドパイプ2内に挿入されて所定の通り芯位置
Lに鉛直に位置出し保持されることで後から挿入される
構真柱Cを通り芯位置Lに鉛直に直接ガイドするガイド
パイプ4と、掘削孔Hの周縁の地表面に設置されてガイ
ドパイプ4を支持するベース架台5とを備えて構成され
ている。
As shown in FIG.
And a guide pipe 4 which is inserted into the stand pipe 2 and is vertically positioned and held at a predetermined core position L to directly guide the vertical position to the core position L through a straight pillar C inserted later. , A base frame 5 installed on the ground surface at the periphery of the excavation hole H and supporting the guide pipe 4.

【0024】図1および図2に示すように、ベース架台
5は、地表面に敷設された敷鉄板6上に設置される下部
架台7と、下部架台7上に設置される上部架台(架台)
8とから構成されている。
As shown in FIGS. 1 and 2, the base frame 5 is composed of a lower frame 7 installed on an iron plate 6 laid on the ground surface, and an upper frame (frame) installed on the lower frame 7.
And 8.

【0025】下部架台7はスタンドパイプ2を囲むよう
平面視ロ字状に形成されており、その上面には三つの受
け台9が略正三角形の位置関係をなすよう配置されてい
る。
The lower pedestal 7 is formed in a rectangular shape in plan view so as to surround the stand pipe 2, and three receiving pedestals 9 are arranged on the upper surface thereof so as to form a substantially equilateral triangular positional relationship.

【0026】上部架台8は、下部架台7と同様に平面視
ロ字状をなしており、その下面には、各受け台9上に立
脚する三つの脚部10が略正三角形の位置関係をなすよ
う備えられている。三つのうち、二つの脚部10には、
上下方向に伸縮駆動される昇降ジャッキ(レベル調整手
段)11が備えられている。そして、各脚部10の上端
部はフランジ継手12を介して上部架台8に連結されて
いる。また、各脚部10の下端部10aは球面状に形成
され、一方、受け台9側もその受け面が球面状に形成さ
れて、互いにボールジョイントされるようになってい
る。さらに、上部架台8の上面には、その四隅にそれぞ
れ二カ所ずつ、ジャッキベース14が備えられている。
The upper gantry 8 has a rectangular shape in plan view like the lower gantry 7, and its lower surface has three legs 10 erected on each pedestal 9 in a substantially equilateral triangular positional relationship. It is equipped to do. Of the three, two legs 10
An elevating jack (level adjusting means) 11 that is driven to expand and contract in the vertical direction is provided. The upper end of each leg 10 is connected to the upper gantry 8 via a flange joint 12. The lower end 10a of each leg 10 is formed in a spherical shape, and the receiving surface of the receiving stand 9 is also formed in a spherical shape, so that they are ball-joined to each other. Further, on the upper surface of the upper gantry 8, two jack bases 14 are provided at four corners thereof.

【0027】このような上部架台8は、二つの脚部10
に備えられた昇降ジャッキ11を昇降駆動させることに
よって、上部架台8の水平面に対する傾斜レベルを調整
できるようになっている。しかもこのとき、各脚部10
の下端部10aは球面状であるので、上部架台8が傾斜
しても下部架台7の受け台9上に点接触して確実に接地
し、ガタつき等が発生しないようになっている。
The upper pedestal 8 has two legs 10
By driving the lifting jack 11 provided at the upper and lower sides, the inclination level of the upper gantry 8 with respect to the horizontal plane can be adjusted. Moreover, at this time, each leg 10
Since the lower end portion 10a is spherical, even if the upper gantry 8 is inclined, the lower gantry 8 is in point contact with the receiving pedestal 9 of the lower gantry 7 to be surely grounded, so that rattling or the like does not occur.

【0028】図1および図3に示すように、上部架台8
上には、平面視ロ字状のピン架台15がセットされるよ
うになっており、ピン架台15の各辺の中央部には、板
状のピン取付ベース16が備えられている。図1および
図4に示すように、各ピン取付ベース16には上方に向
けて突出する位置決めピン17が着脱自在に取り付けら
れるようになっている。なおこの位置決めピン17は、
基端部から先端部に向けてその径寸法が漸次小さくなる
テーパ形状とされている。
As shown in FIG. 1 and FIG.
A pin base 15 having a rectangular shape in a plan view is set on the top, and a plate-shaped pin mounting base 16 is provided at the center of each side of the pin base 15. As shown in FIGS. 1 and 4, a positioning pin 17 projecting upward is detachably attached to each pin attachment base 16. In addition, this positioning pin 17
It has a tapered shape whose diameter gradually decreases from the base end to the tip.

【0029】このピン架台15は、上部架台8の上面の
各脚部10付近に備えられた板状の受けブラケット(図
示なし)の上面に、摩擦低減材(図示なし)を介してセ
ットされている。摩擦低減材としては、例えばテフロン
板や、ステンレススチールあるいは銅板等にグリース材
を塗布したもの等が用いられる。これにより、ピン架台
15は、上部架台8上で略水平方向に移動自在にセット
されている。
The pin mount 15 is set via a friction reducing material (not shown) on the upper surface of a plate-shaped receiving bracket (not shown) provided near each leg 10 on the upper surface of the upper mount 8. I have. As the friction reducing material, for example, a Teflon plate, a material obtained by applying a grease material to a stainless steel or copper plate, or the like is used. Thus, the pin base 15 is set on the upper base 8 so as to be movable in a substantially horizontal direction.

【0030】そして、ピン架台15と上部架台8との間
には、前記各ジャッキベース14にセットされた水平ジ
ャッキ(芯調整手段)19が介装されている。これら計
8本の水平ジャッキ19を伸長状態とすることによって
ピン架台15は上部架台8に一体に固定され、またこれ
ら水平ジャッキ19を伸縮駆動させることによってピン
架台15は水平方向に移動可能となっている。
A horizontal jack (core adjusting means) 19 set on each jack base 14 is interposed between the pin base 15 and the upper base 8. By extending these eight horizontal jacks 19 in an extended state, the pin rack 15 is fixed to the upper rack 8 integrally, and by moving these horizontal jacks 19 in and out, the pin rack 15 can be moved in the horizontal direction. ing.

【0031】図1に示したように、上記ベース架台5に
支持されるガイドパイプ4は、スタンドパイプ2よりも
所定寸法小径の円筒状の鋼管からなり、その上端部の外
周面には、ピン架台15よりも所定寸法大きな外形寸法
を有した平面視矩形の受けプレート20が一体に設けら
れている。受けプレート20には、位置決めピン17に
対応した所定位置にピン穴22が形成されている。各ピ
ン穴22はガイドパイプ4の径方向に長い長穴とされ、
その幅(短径)は、位置決めピン17の外径と略同寸に
設定されている。そして、受けプレート20の各ピン穴
22に位置決めピン17を挿入することによって、受け
プレート20がピン架台15に対して水平面内で一体に
固定されるようになっている。また、ピン17を通り芯
軸上に配置することにより、ガイドパイプ4の位置を通
り芯に適合させることができるようになっている。
As shown in FIG. 1, the guide pipe 4 supported by the base frame 5 is formed of a cylindrical steel pipe having a smaller diameter than the stand pipe 2 by a predetermined dimension. A receiving plate 20 having a rectangular shape in plan view and having an outer dimension larger than the gantry 15 by a predetermined dimension is integrally provided. A pin hole 22 is formed in the receiving plate 20 at a predetermined position corresponding to the positioning pin 17. Each pin hole 22 is a long hole that is long in the radial direction of the guide pipe 4,
The width (short diameter) is set to be substantially the same as the outer diameter of the positioning pin 17. By inserting the positioning pins 17 into the respective pin holes 22 of the receiving plate 20, the receiving plate 20 is integrally fixed to the pin base 15 in a horizontal plane. Further, by arranging the pin 17 on the core axis, the position of the guide pipe 4 can be adapted to the core.

【0032】このようにして、ガイドパイプ4は、ベー
ス架台5にその全荷重が支持され、さらにベース架台5
の昇降ジャッキ11を駆動させると上部架台8と一体に
動いて鉛直度が調整され、また水平ジャッキ19を駆動
させるとピン架台15と一体に移動して水平面内での位
置、つまり通り芯位置Lの調整がなされるようになって
いる。
As described above, the guide pipe 4 is supported by the base gantry 5 at its full load, and
When the lifting jack 11 is driven, it moves together with the upper gantry 8 to adjust the verticality, and when the horizontal jack 19 is driven, it moves integrally with the pin gantry 15 and moves in the horizontal plane, that is, the center line position L Adjustments are made.

【0033】さらに、上記ベース架台5には、自身の水
平面に対する傾斜レベルを表示するレベル表示装置(レ
ベル表示手段)30が備えられている。図5に示すよう
に、レベル表示装置30は、例えば上部架台8の各脚部
10(図1参照)の上端部近傍に備えられた計3台のレ
ベル測定器31と、これらレベル測定器31を互いに連
通する連通管32と、監視盤(表示器)33とから構成
されている。これらレベル測定器31には、水W等の計
測用媒体が所定量注入されており、水Wの水面レベルが
例えば超音波等によって計測されるようになっている。
そして、各レベル測定器31で計測された水面レベルは
信号出力され、監視盤33において各レベル測定器31
での水面レベルがインジケータ34に一括して表示され
るようになっている。
Further, the base pedestal 5 is provided with a level display device (level display means) 30 for displaying an inclination level with respect to its own horizontal plane. As shown in FIG. 5, the level display device 30 includes, for example, a total of three level measuring devices 31 provided near the upper end of each leg 10 (see FIG. 1) of the upper gantry 8, and these level measuring devices 31. And a monitoring panel (display) 33 that communicates with each other. A predetermined amount of a measuring medium such as water W is injected into these level measuring devices 31, and the water surface level of the water W is measured by, for example, ultrasonic waves.
Then, the water surface level measured by each level measuring device 31 is output as a signal, and the monitoring panel 33 outputs each level measuring device 31.
Is displayed on the indicator 34 in a lump.

【0034】このレベル表示装置30では、連通管32
によって3台のレベル測定器31が互いに連通している
ので、監視盤33で表示される各レベル測定器31にお
ける水面レベルは、同一水平面に位置することとなる。
つまり、レベル表示装置30では、同一水平面に対する
各部(レベル測定器31を備えた3カ所)のレベルを表
示するのであって、このときベース架台5自体は水平で
あるとは限らない。
In the level display device 30, the communication pipe 32
Since the three level measuring devices 31 communicate with each other, the water surface levels of the respective level measuring devices 31 displayed on the monitoring panel 33 are located on the same horizontal plane.
That is, the level display device 30 displays the level of each part (three locations provided with the level measuring device 31) on the same horizontal plane, and at this time, the base mount 5 itself is not necessarily horizontal.

【0035】また、図1に示したように、前記ガイドパ
イプ4の内周面には、上下方向に所定長延在する二本一
対のガイドレール35が一体に形成されている。これら
ガイドレール35に沿って、建入れるべき構真柱Cの上
端部に着脱自在に取り付けられたガイド部材36が走行
するようになっており、これによって構真柱Cがガイド
パイプ4の通り芯位置Lに沿って建入れられるようにな
っている。
As shown in FIG. 1, a pair of two guide rails 35 extending a predetermined length in the vertical direction are integrally formed on the inner peripheral surface of the guide pipe 4. Along the guide rails 35, a guide member 36 removably attached to the upper end of the framed pillar C to be built runs so that the shafted pillar C is aligned with the core of the guide pipe 4. It can be built along the position L.

【0036】次に、上記構成からなる構真柱建入れ装置
1を用いた構真柱Cの建入れ工法について説明する。ま
ず、図6に示すように、地盤Gに、地盤Gの崩落を防止
する目的としたスタンドパイプ2を建て込み、次いで掘
削孔Hを略鉛直に削坑する。
Next, a method of installing a vertical column C using the vertical column building apparatus 1 having the above-described configuration will be described. First, as shown in FIG. 6, a stand pipe 2 for preventing the collapse of the ground G is erected in the ground G, and then the excavation hole H is cut substantially vertically.

【0037】そして、図2に示したように、掘削孔Hの
周縁部にベース架台5を構成する下部架台7を敷鉄板6
上に設置し、さらにその上に上部架台8をセットする。
Then, as shown in FIG. 2, a lower gantry 7 constituting the base gantry 5 is placed around
It is set on the top, and the upper gantry 8 is set thereon.

【0038】続いて、図3に示したように、上部架台8
上にピン架台15を載せた後、上部架台8の各ジャッキ
ベース14に水平ジャッキ19をセットし、これら水平
ジャッキ19を伸ばしてピン架台15の位置を固定す
る。
Subsequently, as shown in FIG.
After the pin gantry 15 is placed thereon, the horizontal jacks 19 are set on the jack bases 14 of the upper gantry 8, and the horizontal jacks 19 are extended to fix the position of the pin gantry 15.

【0039】この状態で、図4に示したように、トラン
シット等でピン架台15の水平方向の位置を視準し、各
ピン取付ベース16上に、位置決めピン17をそれぞれ
通り芯位置L上に位置するようボルト等で取り付ける。
In this state, as shown in FIG. 4, the horizontal position of the pin base 15 is collimated with a transit or the like, and the positioning pins 17 are respectively positioned on the pin mounting bases 16 and on the center positions L. Attach it with bolts so that it is positioned.

【0040】この後、図1に示したように、ガイドパイ
プ4を吊り込み、これを掘削孔H内に下ろしていき、そ
の上端部に形成されている受けプレート20の各ピン穴
22に、位置決めピン17を挿入させて嵌合させる。こ
のときに、各位置決めピン17がテーパ状とされている
ので、各ピン穴22への挿入を容易かつ確実に行うこと
ができるようになっている。これによりガイドパイプ4
が通り芯位置Lに位置合わせされた状態となる。
Thereafter, as shown in FIG. 1, the guide pipe 4 is suspended and lowered into the excavation hole H, and is inserted into each pin hole 22 of the receiving plate 20 formed at the upper end thereof. The positioning pins 17 are inserted and fitted. At this time, since each positioning pin 17 is tapered, insertion into each pin hole 22 can be performed easily and reliably. With this, the guide pipe 4
Are aligned with the center line position L.

【0041】次いで、ガイドパイプ4の鉛直度を、例え
ばレーザ管(図示なし)等で計測し、傾斜している場合
には、上部架台8の脚部10の昇降ジャッキ11を伸縮
駆動させることによってガイドパイプ4を上部架台8と
一体に傾動させ、ガイドパイプ4の鉛直を出す。そし
て、各位置決めピン17の位置が通り芯位置L上に位置
しているか、再度トランシットで視準し、もしガイドパ
イプ4の傾動にともなって通り芯位置Lから水平方向に
ズレたときには、水平ジャッキ19を操作してピン架台
15を位置修正する。
Next, the verticality of the guide pipe 4 is measured by, for example, a laser tube (not shown) or the like, and if the guide pipe 4 is inclined, the vertical jack 11 of the leg 10 of the upper base 8 is driven to expand and contract. The guide pipe 4 is tilted integrally with the upper gantry 8 so that the guide pipe 4 extends vertically. Then, the position of each positioning pin 17 is positioned on the center line position L and collimated again by transit. If the guide pin 4 is tilted and shifted from the center line position L in the horizontal direction, the horizontal jack is used. By operating 19, the position of the pin base 15 is corrected.

【0042】これにより、ガイドパイプ4が、鉛直に、
かつ通り芯位置L上に位置出しされた状態となるので、
このときのベース架台5の傾斜レベルを前記レベル表示
装置30で計測し、監視盤33に表示される各レベル測
定器31の水面レベルを、ベース架台5の初期設定レベ
ルとして記録、または初期設定レベルの状態を水平レベ
ルとなるようレベル計を設定しておく。なお、このとき
のベース架台5の傾斜レベルは、あくまでもガイドパイ
プ4が鉛直状態であるときの傾斜レベルであるので、水
平であるとは限らない。
Thus, the guide pipe 4 is vertically
And it will be in the state of being positioned on the center line position L,
At this time, the inclination level of the base gantry 5 is measured by the level display device 30, and the water level of each level measuring device 31 displayed on the monitoring panel 33 is recorded as the initial setting level of the base gantry 5, or the initial setting level The level meter is set so that the state becomes the horizontal level. Note that the inclination level of the base gantry 5 at this time is not necessarily horizontal because the inclination level is only when the guide pipe 4 is in the vertical state.

【0043】しかる後には、例えばコンクリート先打ち
式を採用する場合、コンクリートを掘削孔Hの底部にト
レミー管等で所定レベルまで打設した後、直ちに、建て
込むべき構真柱Cを吊り込んでガイドパイプ4内に挿入
する。このとき、構真柱Cの上部と下部にはガイド部材
36を取り付けておき、これをガイドパイプ4のガイド
レール35でガイドさせることによって、構真柱Cが通
り芯位置L通りに挿入されることとなる。
Thereafter, in the case of adopting a concrete pre-casting method, for example, concrete is poured into the bottom of the excavation hole H to a predetermined level with a tremy tube or the like, and immediately after that, the concrete pillar C to be built is suspended. Insert into the guide pipe 4. At this time, guide members 36 are attached to the upper and lower parts of the straight pillars C, and the guide members 36 are guided by the guide rails 35 of the guide pipes 4, so that the straight pillars C are inserted at the center positions L. It will be.

【0044】このようにして構真柱Cを鉛直に建て込ん
でいき、その下端部がコンクリート中に挿入され、かつ
天端が所定レベルに到達した時点で、この構真柱Cを図
示しないジャーナルジャッキ等の仮受け材で保持する。
この状態で、構真柱Cは、鉛直に、かつ所定のレベルで
建て込まれた状態となっている。
In this manner, the trussed pillar C is erected vertically, and when the lower end is inserted into the concrete and the top end reaches a predetermined level, the trussed pillar C is not shown in the journal. Hold with a temporary receiving material such as a jack.
In this state, the timber pillar C is erected vertically and at a predetermined level.

【0045】コンクリートが硬化して所定の強度が発現
したら、ガイドパイプ4を吊り上げて引き抜き、ベース
架台5を撤去し、構真柱Cの頭部をスタンドパイプ2に
仮固定した後、掘削孔Hを埋め戻し、その後スタンドパ
イプ2を引き抜いて撤去することによって構真柱Cの建
入れ作業が完了する。
When the concrete hardens and exhibits a predetermined strength, the guide pipe 4 is lifted and pulled out, the base pedestal 5 is removed, and the head of the trussed column C is temporarily fixed to the stand pipe 2. And then the stand pipe 2 is pulled out and removed, thereby completing the work of erection of the straight pillar C.

【0046】なお、ガイドパイプ4を鉛直かつ通り芯位
置L上に位置出ししてベース架台5の初期設定レベルを
記録したよりも以降において、例えば吊り込んだ構真柱
Cの荷重によって地盤沈下等が生じ、ガイドパイプ4が
ズレたときには、ベース架台5の脚部10の昇降ジャッ
キ11を操作して上部架台8を傾動させ、レベル表示装
置30で表示される各レベル測定器31のレベルが、前
記初期設定レベルに合うよう調整する。この調整によっ
て、ガイドパイプ4が鉛直かつ通り芯位置L上に位置修
正される。
After the guide pipe 4 is positioned vertically and on the center line position L and the initial setting level of the base gantry 5 is recorded, for example, land subsidence caused by the load of the suspended vertical column C When the guide pipe 4 is displaced, the upper pedestal 8 is tilted by operating the lifting jack 11 of the leg 10 of the base pedestal 5, and the level of each level measuring device 31 displayed on the level display device 30 becomes Adjust to match the default level. By this adjustment, the position of the guide pipe 4 is corrected vertically and on the center line position L.

【0047】また、引き続き、他の位置に構真柱Cを建
入れるときには、上記と同様にガイドパイプ4の位置出
しを行う必要がある。このときには、ベース架台5の傾
斜レベルを、レベル表示装置30での表示レベルが前記
初期設定レベルに合うよう昇降ジャッキ11で調整する
とともに、位置決めピン17の位置を通り芯位置L上に
位置するようピン架台15の位置を水平ジャッキ19で
調整すればよく、ガイドパイプ4の鉛直出しをレーザー
管で行う必要はない。もちろん、このときには、ガイド
パイプ4とベース架台5のセット方向を統一しておく必
要がある。
Further, when the vertical pillar C is to be erected at another position, it is necessary to position the guide pipe 4 in the same manner as described above. At this time, the tilt level of the base pedestal 5 is adjusted by the lifting jack 11 so that the display level on the level display device 30 matches the above-mentioned initial setting level, and is positioned on the core position L through the position of the positioning pin 17. The position of the pin base 15 may be adjusted with the horizontal jack 19, and the guide pipe 4 does not need to be vertically extended with a laser tube. Of course, at this time, it is necessary to unify the setting directions of the guide pipe 4 and the base stand 5.

【0048】上述した構真柱建入れ装置1および構真柱
Cの建入れ工法では、構真柱建入れ装置1がガイドパイ
プ4とベース架台5とを備えて構成され、ベース架台5
には、その傾斜レベルを調整する昇降ジャッキ11と、
傾斜レベルを示すレベル表示装置30とが備えられた構
成となっている。そして、ベース架台5とガイドパイプ
4とを一体にセットした状態でガイドパイプ4の位置出
しを一回行い、このときレベル表示装置30で表示され
るベース架台5の傾斜レベルを記録しておき、しかる後
に、ズレや他の位置への移動によってガイドパイプ4を
再度位置出しする必要が生じたときには、記録した初期
設定レベルに合わせてベース架台5をレベル調整する構
成となっている。したがって、最初の一回を除き、レー
ザ管等を用いることなくガイドパイプ4の位置出しを容
易かつ確実に行うことができ、施工の迅速化を図ること
が可能となる。しかもガイドパイプ4をベース架台5に
セットした状態で位置出しおよび初期設定レベルの記録
を行うので、ガイドパイプ4,ベース架台5自体に高い
精度が要求されることもなく、これらを低コストで製作
することが可能となる。
In the above-described construction method of the trussed column setting device 1 and the trussed column C, the trussed column setting device 1 is provided with the guide pipe 4 and the base pedestal 5.
Has a lifting jack 11 for adjusting its inclination level,
A level display device 30 indicating the inclination level is provided. Then, the guide pipe 4 is positioned once with the base gantry 5 and the guide pipe 4 being set integrally, and at this time, the inclination level of the base gantry 5 displayed on the level display device 30 is recorded, Thereafter, when it is necessary to reposition the guide pipe 4 due to displacement or movement to another position, the level of the base frame 5 is adjusted in accordance with the recorded initial setting level. Therefore, except for the first time, the positioning of the guide pipe 4 can be easily and reliably performed without using a laser tube or the like, and the construction can be speeded up. In addition, since the positioning and recording of the initial setting level are performed while the guide pipe 4 is set on the base gantry 5, the guide pipe 4 and the base gantry 5 are not required to have high accuracy, and are manufactured at low cost. It is possible to do.

【0049】また、レベル表示装置30が、複数のレベ
ル測定器31と、これらを互いに連通させる連通管32
と、各レベル測定器31での測定レベルを表示する監視
盤33とを備えた構成となっている。このようにレベル
表示装置30は、従来使用していたレーザ管等に比較し
て非常に簡易な構成となっている。したがって、その準
備等の作業を容易に行うことができ、より一層の施工の
迅速化を図ることができ、加えて機材コストも削減する
ことができる。
The level display device 30 includes a plurality of level measuring devices 31 and a communication pipe 32 for communicating these devices with each other.
And a monitoring panel 33 for displaying the measurement level of each level measuring device 31. As described above, the level display device 30 has a very simple configuration as compared with a conventionally used laser tube or the like. Therefore, the work such as the preparation can be easily performed, the construction can be further speeded up, and the equipment cost can be reduced.

【0050】さらに、上部架台8が三本の脚部10によ
って立脚した構成となっている。これにより、四本以上
の脚部を備えた場合に比較して、ガタつきが生じたりす
ることもなく、また各脚部10で分担する荷重も均一と
なる。したがって、ガイドパイプ4の鉛直出しをより高
精度で行うことができる。加えて、荷重のばらつきによ
る周囲地盤の沈下等も防止できるので、ガイドパイプ4
の位置ズレ等も抑制することができる。また、レベル出
しを短時間で容易に行うことが可能となる。
Further, the upper gantry 8 is configured to stand on three legs 10. As a result, compared to the case where four or more legs are provided, rattling does not occur, and the load shared by each leg 10 is also uniform. Therefore, the guide pipe 4 can be vertically extended with higher accuracy. In addition, the settlement of the surrounding ground due to the variation of the load can be prevented.
Can be suppressed. Further, leveling can be easily performed in a short time.

【0051】しかも、各脚部10の下端部10aが略球
面状をなした構成となっている。これによって上部架台
8が昇降ジャッキ11の駆動により傾動したときにも、
なめらかな動きを実現できる。
Further, the lower end 10a of each leg 10 has a substantially spherical shape. Accordingly, even when the upper gantry 8 is tilted by the driving of the lifting jack 11,
Smooth movement can be realized.

【0052】また、ピン架台15と上部架台8との間、
つまりガイドパイプ4とベース架台5との間に、水平ジ
ャッキ19が備えられた構成となっている。これによ
り、ガイドパイプ4の通り芯位置Lがずれた場合にも調
整することが可能となり、ガイドパイプ4をより容易か
つ正確に位置出しすることが可能となる。
Further, between the pin mount 15 and the upper mount 8,
That is, the horizontal jack 19 is provided between the guide pipe 4 and the base frame 5. Thereby, it is possible to adjust even when the center position L of the guide pipe 4 is shifted, and it is possible to position the guide pipe 4 more easily and accurately.

【0053】加えて、ガイドパイプ4にはその内周面に
二本一対のガイドレール35,35を形成しておき、構
真柱Cにはガイドレール35,35によってガイドされ
るガイド部材36,36を着脱自在に装着する構成とな
っている。このようにして、鉛直に建て込んだガイドパ
イプ4のガイドレール35,35をガイドとして構真柱
Cを建入れることにより、構真柱Cをスムーズに挿入す
ることができ、また従来手間がかかっていた建入れ調整
作業を廃して、先打ちしたコンクリートが凝結するまで
の間に構真柱Cを容易かつ迅速に高精度で建入れること
ができる。しかも、ガイド部材36が着脱可能な構成と
なっているので、このガイド部材36を転用することに
より、コストダウンを図ることができる。
In addition, a pair of two guide rails 35 are formed on the inner peripheral surface of the guide pipe 4, and guide members 36, guided by the guide rails 35, 35 are formed on the straight pillar C. 36 is detachably mounted. In this way, the vertical pillar C can be inserted smoothly by using the guide rails 35, 35 of the guide pipe 4 which is vertically installed as a guide, so that the vertical pillar C can be inserted smoothly, and it takes time and effort conventionally. It is possible to easily and quickly erection the timber pillar C with high accuracy before the pre-cast concrete solidifies, by abolishing the installation adjustment work that has been performed. Moreover, since the guide member 36 is configured to be detachable, the cost can be reduced by diverting the guide member 36.

【0054】なお、上記実施の形態において、レベル表
示装置30の構成については上記したもの以外であって
も良い。例えば監視盤33で各レベル測定器31の測定
レベルを一括して表示する構成としたが、もちろん、各
レベル測定器31で表示するようにしても良い。また、
用いるレベル測定器31の種類も何ら限定するものでは
ない。
In the above embodiment, the configuration of the level display device 30 may be other than that described above. For example, although the monitoring panel 33 is configured to collectively display the measurement levels of the respective level measuring devices 31, it is needless to say that the monitoring levels may be displayed by the respective level measuring devices 31. Also,
The type of the level measuring device 31 to be used is not limited at all.

【0055】また、昇降ジャッキ11や水平ジャッキ1
9を設置する場所も、上記実施の形態で示したものに限
らず、他の箇所であっても良い。
The lifting jack 11 and the horizontal jack 1
The place where 9 is installed is not limited to that described in the above embodiment, but may be another place.

【0056】さらに、上記実施の形態において、構真柱
Cを建入れるに際してコンクリートを先打ちする構成と
したが、もちろん、コンクリートを後打ちする場合にお
いても適用可能である。この場合には、ガイドパイプ4
を建入れ、これに沿って構真柱Cを所定レベルまで挿入
し、これを仮受け材等で保持した後、ガイドパイプ4内
の所定位置にトレミー管等を建て込んで、コンクリート
の打設を行えばよい。また、本発明に係る構真柱建入れ
装置および構真柱建入れ工法は、例えばこれを充填鋼管
コンクリート構造とする場合には、前記に引き続いてガ
イドパイプ4内にコンクリートを打ち上げればよい。
Further, in the above-described embodiment, the concrete is pre-punched when the trussed pillar C is erected. However, it is needless to say that the present invention can be applied to the case where the concrete is post-punched. In this case, the guide pipe 4
After that, the straight pillar C is inserted to a predetermined level along with this, and this is held by a temporary receiving material or the like, and then a tremy pipe or the like is installed at a predetermined position in the guide pipe 4, and concrete is poured. Should be performed. In addition, in the case of the straight-column construction device and the straight-column construction method according to the present invention, for example, when this is to be a filled steel pipe concrete structure, concrete may be launched into the guide pipe 4 subsequently to the above.

【0057】また、上記実施の形態では、ベース架台5
を下部架台7と上部架台8とから構成し、上部架台8で
ピン架台15を設置し、このピン架台15でガイドパイ
プ4を支持する構成としたが、ガイドパイプ4を所定の
位置に位置決めすることができるのであれば、その構造
については何ら限定するものではなく、構真柱建入れ装
置1に他の構造を採用しても良い。
In the above embodiment, the base frame 5
Is composed of a lower pedestal 7 and an upper pedestal 8, a pin pedestal 15 is installed on the upper pedestal 8, and the guide pipe 4 is supported by the pin pedestal 15, but the guide pipe 4 is positioned at a predetermined position. If possible, the structure is not limited in any way, and another structure may be adopted for the vertical column building device 1.

【0058】加えて、ガイドパイプ4で構真柱Cをガイ
ドする構造について、ガイドレール35およびガイド部
材36を用いる構成としたが、その具体的な構成につい
ては、本出願人が先に出願した特願平8−163511
号の技術等を適宜採用すれば良く、もちろんこれ以外に
も、他の構造を適宜用いることができる。
In addition, for the structure in which the guide pipe 4 guides the straight pillar C, the guide rail 35 and the guide member 36 are used, but the specific structure has been previously filed by the present applicant. Japanese Patent Application No. 8-163511
It is only necessary to appropriately adopt the technology described in (1), and of course, other structures can be used as appropriate.

【0059】これ以外にも、本発明の主旨を逸脱しない
範囲内であれば、いかなる構成を採用しても良く、また
上記したような構成を適宜選択的に組み合わせたものと
しても良いのは言うまでもない。
Other than this, any configuration may be adopted as long as it does not depart from the gist of the present invention, and it is needless to say that the above-described configurations may be selectively combined as appropriate. No.

【0060】[0060]

【発明の効果】以上説明したように、請求項1に係る構
真柱建入れ装置によれば、ガイドパイプと、ガイドパイ
プを支持する架台とを備えて構成され、架台には、その
傾斜レベルを調整するレベル調整手段と、傾斜レベルを
示すレベル表示手段とが備えられた構成となっている。
これにより、ガイドパイプの位置出しを一度行って、そ
のときレベル表示手段によって示される架台の傾斜レベ
ルを記録しておけば、再度位置修正をする場合、あるい
は別の位置に構真柱建入れ装置を設置する場合に、記録
した傾斜レベルに合わせてレベル調整手段で架台の傾斜
レベルを調整すればよい。このように、レーザ管等を用
いることなく、ガイドパイプの位置出しを容易かつ確実
に行うことができるので、施工の迅速化を図ることが可
能となる。しかもガイドパイプを架台にセットした状態
で位置出しおよび初期設定レベルの記録を行うので、ガ
イドパイプおよび架台に高い精度が要求されることもな
く、これらを低コストで製作することが可能となる。
As described above, according to the straight-column construction device according to the first aspect, a guide pipe and a gantry for supporting the guide pipe are provided, and the gantry has an inclination level. And level display means for indicating the inclination level.
Thus, once the guide pipe is located, and the inclination level of the gantry indicated by the level display means is recorded at that time, if the position is to be corrected again, or the vertical column building device is to be placed at another position. Is installed, the inclination level of the gantry may be adjusted by the level adjusting means in accordance with the recorded inclination level. As described above, since the positioning of the guide pipe can be easily and reliably performed without using a laser tube or the like, it is possible to speed up the construction. In addition, since the positioning and the recording of the initial setting level are performed with the guide pipe set on the gantry, high precision is not required for the guide pipe and the gantry, and these can be manufactured at low cost.

【0061】請求項2に係る構真柱建入れ装置によれ
ば、レベル表示手段が、複数のレベル測定器と、各レベ
ル測定器どうしで測定用の媒体を連通させる連通管と、
各レベル測定器での測定レベルを表示する表示器とを備
えた構成となっている。これにより、レベル表示手段
が、従来使用していたレーザ管等に比較して非常に簡易
な構成となっており、その準備等の作業を容易に行え、
請求項1に係る効果をより顕著なものとすることができ
るばかりか、工費を削減することも可能となる。
According to the second aspect of the present invention, the level display means includes a plurality of level measuring devices, a communication pipe for communicating a measuring medium between the level measuring devices,
And a display for displaying the measurement level of each level measuring device. As a result, the level display means has a very simple configuration as compared with a laser tube or the like which has been conventionally used, so that operations such as preparation can be easily performed.
Not only can the effect according to claim 1 be made more remarkable, but also the construction cost can be reduced.

【0062】請求項3に係る構真柱建入れ装置によれ
ば、架台が三本の脚部によって立脚した構成となってい
る。これにより、脚部を四本以上備えた場合に対し、ガ
タつきが生じたりすることもなく、また各脚部で分担す
る荷重も均一となる。したがって、ガイドパイプの鉛直
出しをより高速高精度で行うことができ、しかも荷重の
ばらつきによる周囲地盤の沈下等も防止できる。
According to the third aspect of the present invention, the gantry has a configuration in which the gantry is erected by three legs. As a result, in comparison with a case where four or more legs are provided, no rattling occurs, and the load shared by each leg is also uniform. Accordingly, the guide pipe can be vertically extended with higher speed and higher accuracy, and the settlement of the surrounding ground due to the variation in load can be prevented.

【0063】請求項4に係る構真柱建入れ装置によれ
ば、脚部の下端部が略球面状をなした構成となってい
る。これにより、脚部の下端部とこの架台の設置面とが
点接触することとなり、レベル調整手段によって架台が
傾動したときにも、スムーズな調整レベル出しを実現で
きる。
According to the straight pillar installation device of the fourth aspect, the lower end of the leg portion has a substantially spherical shape. As a result, the lower end of the leg portion comes into point contact with the installation surface of the gantry, and even when the gantry is tilted by the level adjusting means, a smooth adjustment level can be achieved.

【0064】請求項5に係る構真柱建入れ装置によれ
ば、ガイドパイプと架台との間に、ガイドパイプの通り
芯位置を調整する芯調整手段が備えられた構成となって
いる。これにより、ガイドパイプの通り芯位置がずれた
場合にも、芯調整手段で調整することができ、ガイドパ
イプをより容易かつ正確に位置出しすることが可能とな
る。
In accordance with the fifth aspect of the present invention, there is provided a structure for providing a straight pillar, wherein a core adjusting means for adjusting the center position of the guide pipe is provided between the guide pipe and the gantry. Thus, even when the center position of the guide pipe is shifted, the position can be adjusted by the center adjusting means, and the guide pipe can be positioned more easily and accurately.

【0065】請求項6に係る構真柱建入れ工法によれ
ば、架台とガイドパイプをセットし、この状態でガイド
パイプを位置出しし、このときの架台の複数箇所におけ
る傾斜レベルを記録し、しかる後に、ガイドパイプを再
度位置出しするときには、記録した傾斜レベルに合わせ
て架台をレベル調整する構成となっている。このように
して、ズレや移動等によって再度ガイドパイプを位置出
しする必要が生じたときには、記録した傾斜レベルに合
わせてレベル調整手段で架台の傾斜レベルを調整すれば
よい。したがって、レーザ管等を用いることなく、ガイ
ドパイプの位置出しを容易かつ確実に行うことができ、
施工の迅速化を図ることが可能となる。しかもガイドパ
イプを架台にセットした状態で位置出しおよび初期設定
レベルの記録を行うので、ガイドパイプおよび架台自体
に高い精度が要求されることもなく、これらを低コスト
で製作することが可能となる。
According to the straight pillar construction method according to claim 6, the gantry and the guide pipe are set, the guide pipe is positioned in this state, and the inclination levels at a plurality of positions of the gantry at this time are recorded. Thereafter, when the guide pipe is repositioned, the gantry is adjusted in level according to the recorded inclination level. In this way, when it is necessary to position the guide pipe again due to displacement, movement, or the like, the inclination level of the gantry may be adjusted by the level adjusting means in accordance with the recorded inclination level. Therefore, the position of the guide pipe can be easily and reliably determined without using a laser tube or the like.
It is possible to speed up the construction. In addition, since the positioning and recording of the initial setting level are performed with the guide pipe set on the gantry, high precision is not required for the guide pipe and the gantry itself, and these can be manufactured at low cost. .

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明に係る構真柱建入れ装置および構真柱
建入れ工法の一例を示す平面図および立断面図(半断面
図)である。
FIG. 1 is a plan view and an elevational sectional view (half sectional view) showing an example of a tall-column construction device and a tall-column construction method according to the present invention.

【図2】 前記構真柱建入れ工法において、架台をセッ
トした状態を示す平面図および立断面図(半断面図)で
ある。
FIG. 2 is a plan view and a vertical sectional view (half sectional view) showing a state in which a gantry is set in the vertical column construction method.

【図3】 同、架台上にピン架台をセットした状態を示
す平面図および立断面図(半断面図)である。
FIG. 3 is a plan view and a vertical sectional view (half sectional view) showing a state where a pin platform is set on the platform.

【図4】 同、ピン架台上に位置決めピンをセットした
状態を示す平面図および立断面図(半断面図)である。
FIG. 4 is a plan view and a vertical sectional view (half sectional view) showing a state where a positioning pin is set on a pin base.

【図5】 同、用いるレベル表示手段の構成を示す図で
ある。
FIG. 5 is a diagram showing a configuration of a level display means used in the embodiment.

【図6】 同、スタンドパイプを設置した状態を示す平
面図および立断面図(半断面図)である。
FIG. 6 is a plan view and a vertical sectional view (half sectional view) showing a state where the stand pipe is installed.

【符号の説明】[Explanation of symbols]

1 構真柱建入れ装置 4 ガイドパイプ 8 上部架台(架台) 10 脚部 11 昇降ジャッキ(レベル調整手段) 19 水平ジャッキ(芯調整手段) 30 レベル表示装置(レベル表示手段) 31 レベル測定器 32 連通管 33 監視盤(表示器) C 構真柱 H 掘削孔 L 通り芯位置 DESCRIPTION OF REFERENCE NUMERALS 1 Construction device for building a straight pillar 4 Guide pipe 8 Upper pedestal (mount) 10 Leg 11 Elevating jack (level adjustment means) 19 Horizontal jack (core adjustment means) 30 Level display device (level display means) 31 Level measuring device 32 Communication Pipe 33 Monitoring panel (indicator) C Pillar of straight structure H Drilling hole L Center line position

───────────────────────────────────────────────────── フロントページの続き (72)発明者 持田 正一 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 Fターム(参考) 2D050 AA13 EE03 EE12 EE19  ────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Shoichi Mochida 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation F-term (reference) 2D050 AA13 EE03 EE12 EE19

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 地盤中に形成された掘削孔内に構真柱を
建て入れる装置であって、 前記構真柱を建入れるときにこれをガイドする筒状のガ
イドパイプと、 前記掘削孔の周縁の地表面に設置されて前記ガイドパイ
プを支持する架台と、を備えて構成され、 前記架台には、該架台の水平面に対する傾斜レベルを調
整するレベル調整手段と、前記架台の傾斜レベルを示す
レベル表示手段とが備えられていることを特徴とする構
真柱建入れ装置。
An apparatus for erection of a trussed pillar in an excavation hole formed in the ground, comprising: a tubular guide pipe for guiding the erection pillar when the erection pillar is installed; A pedestal installed on a peripheral ground surface to support the guide pipe, wherein the pedestal indicates a level adjusting means for adjusting an inclination level of the pedestal with respect to a horizontal plane, and an inclination level of the pedestal. A erected pole installation device comprising a level display means.
【請求項2】 請求項1記載の構真柱建入れ装置であっ
て、前記レベル表示手段が、前記架台の複数箇所にそれ
ぞれ設置されたレベル測定器と、これらのレベル測定器
間に設けられて前記各レベル測定器で傾斜レベルを測定
するための液体等の媒体を互いに連通させる連通管と、
前記各レベル測定器での測定レベルを表示する表示器と
を備えて構成されていることを特徴とする構真柱建入れ
装置。
2. The vertical column setting device according to claim 1, wherein said level display means is provided between a level measuring device installed at each of a plurality of positions of said mount and said level measuring devices. A communication pipe for communicating a medium such as a liquid for measuring an inclination level with each of the level measuring devices,
And a display for displaying a measurement level of each of the level measuring devices.
【請求項3】 請求項1または2記載の構真柱建入れ装
置であって、前記架台が三本の脚部によって立脚した構
成となっていることを特徴とする構真柱建入れ装置。
3. The straight pole installation device according to claim 1, wherein the gantry is configured to be erected by three legs.
【請求項4】 請求項3記載の構真柱建入れ装置であっ
て、前記脚部の下端部が、略球面状をなしていることを
特徴とする構真柱建入れ装置。
4. The vertical column setting device according to claim 3, wherein a lower end of the leg has a substantially spherical shape.
【請求項5】 請求項1から4のいずれかに記載の構真
柱建入れ装置であって、前記ガイドパイプと前記架台と
の間には、前記ガイドパイプの水平面内における通り芯
位置を調整する芯調整手段が備えられていることを特徴
とする構真柱建入れ装置。
5. The straight-column installation device according to claim 1, wherein a position of a center of the guide pipe in a horizontal plane is adjusted between the guide pipe and the gantry. A straight pillar installation device, comprising:
【請求項6】 地盤中に形成された掘削孔内に構真柱を
建て入れる工法であって、 地盤に掘削孔を略鉛直に形成し、前記掘削孔の周縁の地
表面に架台を設置するとともに、前記構真柱を建入れる
ときにこれをガイドする筒状のガイドパイプを前記架台
にセットし、 この状態で、前記ガイドパイプを前記構真柱の通り芯位
置に合わせて位置出しし、このときの前記架台の複数箇
所における傾斜レベルを記録し、 しかる後に、前記ガイドパイプを再度位置出しするとき
には、前記記録した傾斜レベルに合わせてレベル調整手
段で前記架台をレベル調整することを特徴とする構真柱
建入れ工法。
6. A construction method for erection of a straight pillar in an excavation hole formed in the ground, wherein the excavation hole is formed substantially vertically in the ground, and a gantry is installed on the ground surface around the periphery of the excavation hole. Along with this, the tubular guide pipe that guides the straight pillar when it is built is set on the gantry, and in this state, the guide pipe is positioned according to the center position of the straight pillar, At this time, the inclination levels at a plurality of positions of the gantry are recorded, and thereafter, when the guide pipe is repositioned, the gantry is level-adjusted by level adjusting means in accordance with the recorded inclination level. The construction method of building a pillar.
JP16740998A 1998-06-15 1998-06-15 Construction pillar erection device Expired - Fee Related JP3750042B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16740998A JP3750042B2 (en) 1998-06-15 1998-06-15 Construction pillar erection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16740998A JP3750042B2 (en) 1998-06-15 1998-06-15 Construction pillar erection device

Publications (2)

Publication Number Publication Date
JP2000001854A true JP2000001854A (en) 2000-01-07
JP3750042B2 JP3750042B2 (en) 2006-03-01

Family

ID=15849169

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16740998A Expired - Fee Related JP3750042B2 (en) 1998-06-15 1998-06-15 Construction pillar erection device

Country Status (1)

Country Link
JP (1) JP3750042B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008509545A (en) * 2004-08-06 2008-03-27 オーストリアマイクロシステムズ アクチエンゲゼルシャフト High voltage NMOS transistor and manufacturing method
CN102767182A (en) * 2012-07-18 2012-11-07 上海建工二建集团有限公司 Verticality adjustment system for lattice column correcting mount and construction method thereof
CN104110035A (en) * 2013-04-16 2014-10-22 中冶天工上海十三冶建设有限公司 Perpendicularity correcting device for concrete-filled steel tube columns constructed by top-down process and construction method implemented by perpendicularity correcting device
JP2020090839A (en) * 2018-12-05 2020-06-11 株式会社フジタ Inverted post positioning jig
CN114319439A (en) * 2022-02-16 2022-04-12 广西珠委南宁勘测设计院有限公司 Geotechnical engineering positioning and supporting device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62133255A (en) * 1985-12-03 1987-06-16 清水建設株式会社 Method and apparatus for building steel bar pillar
JPH07109733A (en) * 1993-10-14 1995-04-25 Takenaka Komuten Co Ltd Center positioning jig for erecting permanent substructural column
JPH08209718A (en) * 1995-02-01 1996-08-13 Nittoc Constr Co Ltd Erection and adjustment device for structural center column
JPH09125391A (en) * 1995-11-02 1997-05-13 Shimizu Corp Built-in method for construction center column and jig used therefor
JPH09291535A (en) * 1996-04-25 1997-11-11 Nagano Yuki Kk Device for burying cylindrical casing in ground

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62133255A (en) * 1985-12-03 1987-06-16 清水建設株式会社 Method and apparatus for building steel bar pillar
JPH07109733A (en) * 1993-10-14 1995-04-25 Takenaka Komuten Co Ltd Center positioning jig for erecting permanent substructural column
JPH08209718A (en) * 1995-02-01 1996-08-13 Nittoc Constr Co Ltd Erection and adjustment device for structural center column
JPH09125391A (en) * 1995-11-02 1997-05-13 Shimizu Corp Built-in method for construction center column and jig used therefor
JPH09291535A (en) * 1996-04-25 1997-11-11 Nagano Yuki Kk Device for burying cylindrical casing in ground

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008509545A (en) * 2004-08-06 2008-03-27 オーストリアマイクロシステムズ アクチエンゲゼルシャフト High voltage NMOS transistor and manufacturing method
CN102767182A (en) * 2012-07-18 2012-11-07 上海建工二建集团有限公司 Verticality adjustment system for lattice column correcting mount and construction method thereof
CN104110035A (en) * 2013-04-16 2014-10-22 中冶天工上海十三冶建设有限公司 Perpendicularity correcting device for concrete-filled steel tube columns constructed by top-down process and construction method implemented by perpendicularity correcting device
JP2020090839A (en) * 2018-12-05 2020-06-11 株式会社フジタ Inverted post positioning jig
JP7181069B2 (en) 2018-12-05 2022-11-30 株式会社フジタ Reversed strut positioning jig
CN114319439A (en) * 2022-02-16 2022-04-12 广西珠委南宁勘测设计院有限公司 Geotechnical engineering positioning and supporting device
CN114319439B (en) * 2022-02-16 2023-12-22 广西珠委南宁勘测设计院有限公司 Geotechnical engineering positioning and supporting device

Also Published As

Publication number Publication date
JP3750042B2 (en) 2006-03-01

Similar Documents

Publication Publication Date Title
US20130091801A1 (en) Power line tower alignment method
US7530176B2 (en) Method and apparatus for monitoring element alignment
CN114277803B (en) Post-insertion method positioning construction method for reverse construction method steel pipe structural column
CN109252511A (en) A kind of installation of steel reinforcement cage and concrete casting platform
JP2000001854A (en) Structural stud erection device and structural stud erection method
US7484913B2 (en) Placing elements in piles
JPH08120673A (en) Accurate erection method and equipment for steel frame column under ground surface of reverse construction method
JPH03295931A (en) Construction method for frame straight pillar
JP3616895B2 (en) Construction pillar erection device
JP3030377B2 (en) Construction and repair equipment for trussed pillars
JP4504126B2 (en) Jacket support height adjustment stand
JPH0657763A (en) Construction of vertical shaft with center column by solidification of mud slurry
JPS62133255A (en) Method and apparatus for building steel bar pillar
CN216194782U (en) Steel pipe column positioning system
JPH04281916A (en) Base device for construction of main post
JP3062976B2 (en) Supporting steel frame mounting base
JP3030374B2 (en) Construction method and equipment for trussed pillar
CN114277802B (en) Post-insertion method positioning construction structure for reverse construction method steel pipe structural column
JP3305128B2 (en) Settlement generator for soil structures
CN219910059U (en) Steel stand fixing device
CN113832966B (en) Accurate positioning device for large-diameter ultra-long steel casing and accurate installation method thereof
CN110004993B (en) Ultra-thick bottom plate measuring paying-off construction method and paying-off platform
JP3320691B2 (en) Pipe burial method
CN117266241A (en) Construction method of reverse construction method lattice column
JPH10299019A (en) Joining method for permanent sub-structural column and main steel in inverted construction method

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050705

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050815

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051101

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051122

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111216

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees