CN102926544A - 一种框架柱内拉墙筋的施工方法及构造 - Google Patents

一种框架柱内拉墙筋的施工方法及构造 Download PDF

Info

Publication number
CN102926544A
CN102926544A CN2011102285238A CN201110228523A CN102926544A CN 102926544 A CN102926544 A CN 102926544A CN 2011102285238 A CN2011102285238 A CN 2011102285238A CN 201110228523 A CN201110228523 A CN 201110228523A CN 102926544 A CN102926544 A CN 102926544A
Authority
CN
China
Prior art keywords
frame column
steel bars
pulling steel
wall pulling
wall bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011102285238A
Other languages
English (en)
Inventor
蹇广珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN2011102285238A priority Critical patent/CN102926544A/zh
Publication of CN102926544A publication Critical patent/CN102926544A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种框架柱内拉墙筋的施工方法及构造,其方法是在框架柱浇筑时预埋套管,待框架柱浇筑完毕拆模后,在预埋的套管中穿入拉墙筋,将拉墙筋固定连接在框架柱上。其构造是在框架柱内设置套管,在套管内设置拉墙筋,拉墙筋固定连接在框架柱上。由于采用了上述技术方案,本发明将拉墙筋固定在已成型的框架柱上,有效地避免了拉墙筋位置的移动,确保了设计的实施;并且消除了在浇筑后剥离拉墙筋易造成预制混凝土柱表面外观损伤的缺陷。而且,本发明的施工方法及构造简单,能在不影响钢筋混凝土柱强度的前提下,加快施工速度,降低成本。本发明还可利用预埋的套管固定框架柱浇筑时模板的位置,用于保证框架柱的外形尺寸。

Description

一种框架柱内拉墙筋的施工方法及构造
技术领域
本发明涉及建筑结构领域,特别是一种框架柱内拉墙筋的施工方法及构造。
背景技术
在工业与民用建筑中有许许多多的框架结构,对于这种框架柱内拉墙筋的施工通常是采用浇筑框架柱时直接预埋拉墙筋的方法,或在框架柱浇筑完后采用植筋的方法。采用直接预埋拉墙筋的方法时,由于在浇筑振捣中易使拉墙筋移位,使得框架柱浇筑凝固后拉墙筋的位置与设计相比有偏差;并且由于拉墙筋容易被包裹在混凝土中,剥离拉墙筋时预制混凝土柱表面常被损坏,影响其外观。采用植筋的方法有两个方面的缺陷,一是施工周期较长,其次造价较高。
发明内容
本发明要解决的技术问题是:提供一种能避免拉墙筋移位、避免柱面外观受损、减少施工周期、降低成本的框架柱内拉墙筋的施工方法及构造,以克服现有技术的不足。
本发明的框架柱内拉墙筋的施工方法是这样实现的:首先在框架柱浇筑时预埋套管;其次,待框架柱浇筑完毕拆模后,在预埋的套管中穿入拉墙筋;最后,将拉墙筋固定连接在框架柱上。
本发明的框架柱内拉墙筋的构造是这样构成的:它包括框架柱,在框架柱内设有套管,在套管内设有拉墙筋,拉墙筋固定连接在框架柱上。
上述的框架柱内拉墙筋的构造中,套管是塑料管
前述的框架柱内拉墙筋的构造中,拉墙筋3是通过螺母或钢片固定连接在框架柱上。
由于采用了上述技术方案,与现有技术比较,本发明将拉墙筋固定在已定型的框架柱上,有效地避免了拉墙筋位置的移动,确保了设计的实施;并且消除了在浇筑后剥离拉墙筋易造成预制混凝土柱表面外观损伤的缺陷。而且,本发明的施工方法及构造简单,能在不影响钢筋混凝土柱强度的前提下,加快施工速度,降低成本。不仅如此,本发明可利用预埋的套管固定框架柱浇筑时模板的位置,用于保证框架柱的外形尺寸。
附图说明:
图1是本发明构造的示意图;
图2是本发明砌筑成墙后的示意图;
附图的标记为:1-框架柱,2-套管,3-拉墙筋,4-螺母或钢片,5-围护墙体。
具体实施方式:
本发明的实施例:框架柱内拉墙筋的施工方法:首先在框架柱1浇筑时预埋套管2;其次,待框架柱1浇筑完毕拆模后,在预埋的套管2中穿入拉墙筋3;最后,将拉墙筋3固定连接在框架柱1上。
采用上述方法的框架柱内拉墙筋的构造如图1所示,它包括现有的框架柱1,在框架柱1内放置套管2(套管2在浇筑框架柱1时根据实际施工要求放置),待框架柱1浇筑完毕拆模后,将拉墙筋3穿入套管2,再将拉墙筋3固定连接在框架柱1上。为了降低成本,套管2可以采用塑料管。为了实用方便,可在拉墙筋3两侧安装螺母来固定;或者将钢片4穿套在拉墙筋3上,再将钢片4焊接在框架柱1上。完成墙筋3的安装固定后即可其上砌筑围护墙体5(如图2所示)。

Claims (4)

1.一种框架柱内拉墙筋的施工方法,其特征在于:首先在框架柱(1)浇筑时预埋套管(2);其次,待框架柱(1)浇筑完毕拆模后,在预埋的套管(2)中穿入拉墙筋(3);最后,将拉墙筋(3)固定连接在框架柱(1)上。
2.一种框架柱内拉墙筋的构造,它包括框架柱(1),其特征在于:在框架柱(1)内设有套管(2),在套管(2)内设有拉墙筋(3),拉墙筋(3)固定连接在框架柱(1)上。
3.根据权利要求2所述的框架柱内拉墙筋的构造,其特征在于:套管(2)是塑料管。
4.根据权利要求2所述的框架柱内拉墙筋的构造,其特征在于:拉墙筋(3)是通过螺母或钢片(4)固定连接在框架柱(1)上。
CN2011102285238A 2011-08-10 2011-08-10 一种框架柱内拉墙筋的施工方法及构造 Pending CN102926544A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011102285238A CN102926544A (zh) 2011-08-10 2011-08-10 一种框架柱内拉墙筋的施工方法及构造

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011102285238A CN102926544A (zh) 2011-08-10 2011-08-10 一种框架柱内拉墙筋的施工方法及构造

Publications (1)

Publication Number Publication Date
CN102926544A true CN102926544A (zh) 2013-02-13

Family

ID=47641460

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011102285238A Pending CN102926544A (zh) 2011-08-10 2011-08-10 一种框架柱内拉墙筋的施工方法及构造

Country Status (1)

Country Link
CN (1) CN102926544A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103104099A (zh) * 2011-11-09 2013-05-15 贵阳铝镁设计研究院有限公司 一种框架柱内拉墙筋的施工方法及构造
CN106168068A (zh) * 2016-08-04 2016-11-30 中国十七冶集团有限公司 一种构造柱插筋、拉结筋插筋定位安装方法
CN107654021A (zh) * 2017-10-25 2018-02-02 程丹松 一种可装配式预制钢筋混凝土柱及装配式混合框架建筑体系

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3869530A (en) * 1974-02-19 1975-03-04 Chester I Williams Method of constructing a prestressed concrete circular wall
JP2002089043A (ja) * 2000-09-19 2002-03-27 Maeda Corp 鉄筋コンクリート構造物及び鉄骨鉄筋コンクリート構造物の構築工法
KR20030025471A (ko) * 2001-09-21 2003-03-29 이광명 고강도 콘크리트 또는 모르타르와 강재를 이용한프리캐스트 프리스트레스트 보강재 및 이를 이용한철근콘크리트 구조물
JP2004316322A (ja) * 2003-04-18 2004-11-11 Takenaka Komuten Co Ltd プレキャストコンクリート部材による柱梁躯体構築工法
CN2784490Y (zh) * 2005-04-22 2006-05-31 北京工业大学 装配式混凝土框架结构梁柱的预应力连接节点

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3869530A (en) * 1974-02-19 1975-03-04 Chester I Williams Method of constructing a prestressed concrete circular wall
GB1470471A (en) * 1974-02-19 1977-04-14 Williams C Method of constructing a pre-stressed concrete circular wall
JP2002089043A (ja) * 2000-09-19 2002-03-27 Maeda Corp 鉄筋コンクリート構造物及び鉄骨鉄筋コンクリート構造物の構築工法
KR20030025471A (ko) * 2001-09-21 2003-03-29 이광명 고강도 콘크리트 또는 모르타르와 강재를 이용한프리캐스트 프리스트레스트 보강재 및 이를 이용한철근콘크리트 구조물
JP2004316322A (ja) * 2003-04-18 2004-11-11 Takenaka Komuten Co Ltd プレキャストコンクリート部材による柱梁躯体構築工法
CN2784490Y (zh) * 2005-04-22 2006-05-31 北京工业大学 装配式混凝土框架结构梁柱的预应力连接节点

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103104099A (zh) * 2011-11-09 2013-05-15 贵阳铝镁设计研究院有限公司 一种框架柱内拉墙筋的施工方法及构造
CN106168068A (zh) * 2016-08-04 2016-11-30 中国十七冶集团有限公司 一种构造柱插筋、拉结筋插筋定位安装方法
CN107654021A (zh) * 2017-10-25 2018-02-02 程丹松 一种可装配式预制钢筋混凝土柱及装配式混合框架建筑体系

Similar Documents

Publication Publication Date Title
CN104989102B (zh) 一种改进的混凝土墙、柱施工方法
CN203022024U (zh) 一种管廊现浇施工整体移动式模架
CN104631512A (zh) 吊模法后浇带梁板施工方法
CN104631706A (zh) 一种免拆模混凝土柱及其施工方法
CN104453224A (zh) 一种地下室外墙的模板支护结构及其施工方法
CN103556819B (zh) 一种在梁板上预留构造柱孔洞的施工方法
CN104278840A (zh) 装饰清水混凝土施工方法及所用对拉螺栓孔模具
CN104047419A (zh) 一种脚手架的连墙方法及所用连墙件
CN102926544A (zh) 一种框架柱内拉墙筋的施工方法及构造
CN103104099A (zh) 一种框架柱内拉墙筋的施工方法及构造
CN104805960A (zh) 一种免拆模混凝土梁及其施工方法
CN104153573A (zh) V型圆柱混凝土的浇筑模具及施工方法
CN102912977A (zh) 一种用于浇筑定型楼梯的模具
CN105696796A (zh) 一种悬挑脚手架钢梁锚固方法
CN202882438U (zh) 现浇混凝土斜墙斜柱串筒
CN210976630U (zh) 一种可重复使用并免剔凿的构造柱喇叭口砼浇筑装置
CN204299162U (zh) 悬挑工字钢梁锚固结构
CN204590584U (zh) 建筑模板结构
CN105604339B (zh) 二次结构构造柱加固方法
CN104453235B (zh) 换流站防火墙施工工艺
CN203097290U (zh) 装配式对拉螺栓
CN104499712A (zh) 建筑模板拉杆
CN202202405U (zh) 一种框架柱内拉墙筋的构造
CN205135109U (zh) 一种新型施工专用围栏
CN201043329Y (zh) 现浇钢筋砼内模固定装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130213