CN101737061B - Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel - Google Patents

Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel Download PDF

Info

Publication number
CN101737061B
CN101737061B CN2009101569076A CN200910156907A CN101737061B CN 101737061 B CN101737061 B CN 101737061B CN 2009101569076 A CN2009101569076 A CN 2009101569076A CN 200910156907 A CN200910156907 A CN 200910156907A CN 101737061 B CN101737061 B CN 101737061B
Authority
CN
China
Prior art keywords
hole
tunnel
existing single
arch
pilot tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009101569076A
Other languages
Chinese (zh)
Other versions
CN101737061A (en
Inventor
章立峰
邹金杰
吴向东
吾佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN2009101569076A priority Critical patent/CN101737061B/en
Publication of CN101737061A publication Critical patent/CN101737061A/en
Application granted granted Critical
Publication of CN101737061B publication Critical patent/CN101737061B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a method for constructing a double-arch tunnel by rebuilding and expanding an existing single-hole tunnel. The technical problem to be solved by the invention is to provide a method for constructing the double-arch tunnel by rebuilding and expanding the existing single-hole tunnel, which adopts a ' middle pilot hole, the existing tunnel and a right hole' three pilot pit construction scheme, enlarges construction face and reduce excavation face and surrounding rock disturbed zone. To solve the technical problem, the invention adopts a technical scheme that the method for constructing the double-arch tunnel by rebuilding and expanding the existing single-hole tunnel comprises the following steps: 1.1 constructing the middle pilot hole parallel to the existing single-hole tunnel on one side of the existing single-hole tunnel and completing supporting construction; 1.2, constructing a left hole by sequence and zone on the basis of the existing single-hole tunnel and communicating the left hole and the middle pilot hole; and 1.3, after excavating the left hole to a certain size, constructing the right hole by sequence and zone and communicating the right hole with the middle pilot hole. The method is mainly used in highway traffic engineering and municipal traffic engineering.

Description

The reorganization and expansion of existing single-hole tunnel is the job practices of multiple-arch tunnel
Technical field
The present invention relates to the tunnel reorganization and expansion of a kind of existing single-hole is the job practices of multiple-arch tunnel.Mainly be applicable to highway communication engineering and municipal traffic engineering.
Background technology
Along with the develop rapidly of Chinese national economy, the traffic volume is increasing day by day, and the existing road of part can not adapt to the requirement of communications and transportation, need carry out corresponding reorganization and expansion and just can reach corresponding service level.In the developed area, these problems become increasingly conspicuous, as reorganization and expansion of the big speedway in Shen, Shanghai-Hangzhou speedway etc.The continuing of highway, municipal infrastructure carries out, and construction of tunnel has obtained fast development, and the tunnel develops into the up-downgoing of two holes by single hole two way to be separated.No matter the transformation of urban road or the enlarging of each standard highway for the tunnel, as the part of highway, have run into the reorganization and expansion problem equally.The tunnel is different from earth construction, therefore should comprehensively prove in conjunction with the actual conditions of engineering for the reorganization and expansion scheme of established tunnel, seeks the most rational reorganization and expansion mode.
In hilling terrain high-grade highway tunnel, the mountain ridge, Midwest or the reorganization and expansion of major urban arterial highway list hole tunnel, construction scheme selects to be subjected to through regular meeting the restriction of various factors.According to tunnel two terminal strip spare differences, generally there are the three kinds of engineering proposals that can select: separate tunnel, small-clear-distance tunnel and multiple-arch tunnel scheme.Compare separate tunnel, small-clear-distance tunnel scheme, the big and risk of multiple-arch tunnel scheme construction technology complexity, difficulty of construction is difficult to control.The tunnel reconstruction and extension project is big because of technical sophistication, difficulty of construction, and domestic similar engineering is less relatively.Domestic design and construction technical research at the tunnel reorganization and expansion at present is less, mainly only rests on the aspect of certain single engineering construction technical Analysis.The engineering field that particularly single hole tunnel reorganization and expansion is a multiple-arch tunnel almost is blank.Yet along with the sharp increase of the traffic volume, domestic most city tunnels are more particularly built the problem that single hole tunnel of the remote past all is faced with reorganization and expansion, and single hole tunnel reorganization and expansion is that multiple-arch tunnel is an important directions of building development from now on.Therefore, successfully groping a cover existing single-hole tunnel reorganization and expansion is that the key technology of building of multiple-arch tunnel seems very urgent.
Summary of the invention
The technical problem to be solved in the present invention is: it is the job practices of multiple-arch tunnel that the problem that exists at the existing tunnel reorganization and expansion provides the tunnel reorganization and expansion of a kind of existing single-hole, adopt the construction scheme of " middle pilot tunnel+existing tunnel+right hole " three base tunnels, increase working face, reduce excavation face and disturbance country rock scope to reach, improve the purpose of working security.
The technical solution adopted in the present invention is: the reorganization and expansion of existing single-hole tunnel is the job practices of multiple-arch tunnel, it is characterized in that may further comprise the steps:
1.1 after existing single-hole tunnel one side applies parallel with it middle pilot tunnel, finishes supporting, apply mid-board, utilize existing single-hole tunnel and middle pilot tunnel that multiple-arch tunnel integral body is applied pipe canopy leading pre-supporting then;
1.2 the construction of left hole after middle pilot tunnel construction is finished, is removed the secondary lining in existing single-hole tunnel, then country rock is carried out branch and distinguishes the preface excavation, pilot tunnel temporary lining in the dismounting makes it be communicated with middle pilot tunnel, and immediate support;
1.3 the construction of right hole after left hole is excavated to certain drilling depth, divides the differentiation preface to excavate right hole at middle pilot tunnel opposite side, pilot tunnel temporary lining in the dismounting makes it be communicated with middle pilot tunnel, and immediate support.
Middle pilot tunnel construction sequence is as follows:
Carry out advance support, the safety of pilot drive and Stability Analysis of Structures in the assurance 2.1 utilize ductule to cooperate steel to support the centering pilot tunnel;
2.2 centering pilot tunnel barrel excavates and in time applies bolt-spary supports;
2.3 in middle pilot tunnel, apply the steel concrete mid-board, adopt the slabstone backfill and apply the temporary steel stull away from existing single-hole tunnel one side at mid-board then along its axis.
Hole, left side construction sequence is as follows:
3.1 adopt controlled blasting that the secondary lining in existing single-hole tunnel is removed, the dismounting cyclic advance is 1.5-3m;
3.2 (the Dan Dong hole directly is the footpath, Dan Dong hole of new built tunnel when secondary lining dismounting drilling depth reaches footpath, twice Dan Dong hole herein, in addition, described Dan Dong hole, back directly is the footpath, Dan Dong hole of new built tunnel), first section country rock of left hole is excavated, and in time carry out preliminary bracing;
3.3 second section country rock of left hole is excavated, and in time applies inverted arch, the preliminary bracing of left hole can in time be sealed;
3.4 when second section country rock excavation drilling depth of left hole reaches footpath, one times of Dan Dong hole, carry out left hole secondary lining and apply.Right hole construction sequence is as follows:
4.1 adopt booth pipe and steel bow member that right pilot tunnel is carried out advance support, after secondary lining dismounting drilling depth reaches footpath, four times of Dan Dong holes, then right pilot tunnel excavated, and in time carry out preliminary bracing;
4.2 when right pilot drive drilling depth reaches footpath, twice Dan Dong hole, first section arch country rock of right hole is excavated, and in time carries out preliminary bracing;
4.3 when first section arch country rock excavation drilling depth of right hole reaches footpath, one times of Dan Dong hole, first section core soil of right hole is excavated;
4.4 when core soil excavation drilling depth reaches footpath, one times of Dan Dong hole, second section country rock of right hole is excavated, and in time applies inverted arch, seal whole section;
4.5 when second section country rock excavation drilling depth of right hole reaches footpath, one times of Dan Dong hole, apply right hole arch wall secondary lining.
The minimum thickness of being separated by between pilot tunnel and the existing tunnel in described is 1.6-1.8m, the thickness of rock mass and existing single-hole Tunnel Second Lining between pilot tunnel and the existing tunnel during this thickness comprises.
The invention has the beneficial effects as follows: the present invention proposes the design theory of zero distance reorganization and expansion multiple-arch tunnel on existing single-hole tunnel original position, make full use of existing tunnel, adopt the construction scheme of " middle pilot tunnel+existing tunnel+right hole " three base tunnels, be about to big cavern and be decomposed into some small cavities, the little work in big hole, big with little generation, increased the construction working face, improved efficiency of construction and working security; The leading excavation of middle pilot tunnel has played the advance geologic prediction effect, and part underground water is carried out white-out, has improved the excavation condition; Under the relatively poor condition of weak surrounding rock and geological conditions, the excavation face is little, and disturbance country rock scope is little, greatly reduces the risk that rock burst takes place; Preliminary bracing and secondary lining sealing in time help construction and engineering safety; The sedimentation of vault and footing is less, and the rigidity of structure is bigger, overall security and firmness height.
Description of drawings
Fig. 1 is a sectional drawing of the present invention.
The specific embodiment
As shown in Figure 1, present embodiment considers that the multiple-arch tunnel that is two-way Four-Lane Road with the two-way two track tunnel enlargings in single hole is a background.The about 9m of existing single-hole tunnel 34 clear span, the about 5.5m of clear height, the about 3m of track clearance height.According to related specifications and technical standard, the headroom gauge in existing single-hole tunnel 34 can't meet the demands, and needs badly and carries out reorganization and expansion.Limit by tunnel two terminal strip spares, determine to make full use of the existing single-hole tunnel when drafting construction scheme as far as possible.Design proves repeatedly from aspects such as safety, economy, durations, proposed the construction scheme of " apply middle pilot tunnel+in conjunction with right hole, existing single-hole tunnel+apply " three base tunnels.Newly-built multiple-arch tunnel layout is basic parallel with existing single-hole tunnel 34, and both wire center distance between centers of tracks are controlled at 7.8~8.95m.The process characteristic of present embodiment is the excavation and the supporting of pilot tunnel 31 in carrying out earlier, connect and after mid-board 4 applies completion at middle pilot tunnel 31, carry out 32,33 front and back, hole, the left and right sides stagger the excavation and preliminary bracing, middle pilot tunnel 31 is for the support of mid-board 4 arcading intersection points is provided in advance.Concrete work progress may further comprise the steps:
1.1 applying parallel with it and width in existing single-hole tunnel 34 1 sides is that the middle pilot tunnel 31 of 6m is (in this example, in between pilot tunnel and existing tunnel about the about 1.7m of rock pillar minimum thickness, this thickness comprises the thickness of existing tunnel two linings), apply mid-board 4 after finishing supporting, utilize 31 pairs of multiple-arch tunnel integral body of existing single-hole tunnel 34 and middle pilot tunnel to apply pipe canopy leading pre-supporting 6 then, guarantee that the tunnel advances wide open safety of digging, and makes the country rock resistance to overturning not be subjected to excessive disturbance; In this example, the elevation scale between leading pre-supporting 6 and the multiple-arch tunnel axis is the 15-30 degree.
1.2 32 constructions of left hole after middle pilot tunnel 31 constructions are finished, are removed the secondary lining 7 in existing single-hole tunnel 34, then country rock are carried out branch and distinguish the preface excavation, pilot tunnel temporary lining in the dismounting makes it be communicated with middle pilot tunnel 31, and immediate support.
1.3 33 constructions of right hole after left hole 32 is excavated to certain drilling depth, divide the differentiation preface to excavate right hole 33 at middle pilot tunnel 31 opposite sides, pilot tunnel temporary lining in the dismounting makes it be communicated with middle pilot tunnel 31, and immediate support.
In must close traffic during pilot tunnel 31 excavation, and strengthen monitoring measurement to existing single-hole tunnel 34, adopt steel to support in case of necessity it reinforced, its construction sequence is as follows:
Carry out advance support 2.1 utilize the bassoon canopy to cooperate steel to support centering pilot tunnel 31, the safety and the Stability Analysis of Structures of pilot tunnel 31 excavations in the assurance;
2.2 centering pilot tunnel 31 barrels excavate and in time apply bolt-spary supports 3;
2.3 in middle pilot tunnel 31, apply steel concrete mid-board 4 along its axis, adopt the slabstone backfill and apply temporary steel stull 2 away from existing single-hole tunnel 34 1 sides at mid-board 4 then, the bias voltage that pilot tunnel 31 right sides produce in during with hole, a balance left side 32 excavations, the monolithic stability of assurance mid-board 4.
After middle pilot tunnel 31 constructions are finished, multiple-arch tunnel integral body is applied pipe canopy leading pre-supporting 6, carries out the construction in left hole 32 then:
3.1 adopt controlled blasting that the secondary lining 7 in existing single-hole tunnel 34 is removed, the dismounting cyclic advance is 1.5-3m, can carry out suitable adjustment according to field condition, during III level country rock, the dismounting drilling depth is 3m, and during IV level country rock, the dismounting drilling depth is 1.5m; The preliminary bracing of main hole must be removed work plane immediately following the secondary lining 7 in existing single-hole tunnel 34 and be applied, after promptly the secondary lining 7 in existing single-hole tunnel 34 is removed, along with the tunnel excavation preliminary bracing will be caught up with as early as possible.
3.2 (indication Dan Dong hole directly is the footpath, Dan Dong hole of new built tunnel herein when secondary lining 7 dismounting drilling depths reach footpath, twice Dan Dong hole, in addition, described Dan Dong hole, back directly is the footpath, Dan Dong hole of new built tunnel) time, left hole 32 first section country rocks 8 are excavated, and in time carry out preliminary bracing;
3.3 left hole 32 second section country rocks 10 are excavated, and in time apply inverted arch 11,32 preliminary bracings of left hole can in time be sealed, help construction and engineering safety;
3.4 when left hole 32 second section country rock 10 excavation drilling depths reach footpath, one times of Dan Dong hole, carrying out left hole secondary lining 12 applies, secondary lining is not only that structural safety is stocked, also will play bearing part load effect, so the timely sealing of secondary lining also helps the safety of engineering construction to structural safety.
Carry out 33 constructions of right hole at last, its step is as follows:
4.1 mark part as right pilot tunnel 14 on 33 right sides, right hole, and adopt booth pipe and steel bow member that right pilot tunnel 14 is carried out advance support, guarantee the safety of right pilot tunnel 14 constructions, after secondary lining 7 dismounting drilling depths reach footpath, four times of Dan Dong holes, right pilot tunnel 14 is excavated, and in time the excavation face is carried out preliminary bracing, to seal right pilot tunnel 14 as early as possible, guarantee that surrounding rock structure is stable;
4.2 when right pilot tunnel 14 excavation drilling depths reach footpath, twice Dan Dong hole, first section arch country rock 16 of right hole is excavated, and in time carries out preliminary bracing, guarantee Stability Analysis of Structures, for the excavation of reserving core soil 18 is created good execution conditions;
4.3 when first section arch country rock 16 excavation drilling depths of right hole reach footpath, one times of Dan Dong hole, first section core soil 18 of right hole is excavated;
4.4 when core soil 18 excavation drilling depths reach footpath, one times of Dan Dong hole, second section country rock 19 of right hole is excavated, and in time applies inverted arch 20,, help constructing and the safety of engineering to seal whole section as early as possible;
4.5 when second section country rock 19 excavation drilling depths of right hole reach footpath, one times of Dan Dong hole, apply right hole arch wall secondary lining 21.
Answer strictness to follow the basic principle of " pipe is leading, tight slip casting, weak explosion, short excavation, strong supporting, the diligent measurement, early sealing " in the construction; For guaranteeing construction safety and Stability Analysis of Structures, must adopt controlled blasting during tunnel excavation, and require the secondary lining in each construction sequence to apply immediately following work plane; Simultaneously, main hole (comprising Zuo Dong and You Dong) when excavation, backfill etc. should be set as cushion coat between mid-board 4 and main hole, reduce of the influence of the impact load of explosion generation to mid-board 4 as far as possible.

Claims (4)

1. job practices that the reorganization and expansion of existing single-hole tunnel is a multiple-arch tunnel is characterized in that may further comprise the steps:
1.1 (34) one sides apply parallel with it middle pilot tunnel (31) in the existing single-hole tunnel, utilize existing single-hole tunnel (34) and middle pilot tunnel (31) that multiple-arch tunnel integral body is applied pipe canopy leading pre-supporting (6) then;
1.2 left hole (32) construction after middle pilot tunnel (31) construction is finished, is removed the secondary lining in existing single-hole tunnel (34), then country rock is carried out branch and distinguish the preface excavation, pilot tunnel temporary lining in the dismounting makes existing single-hole tunnel (34) be communicated with middle pilot tunnel (31), and immediate support;
1.3 right hole (33) construction after left hole (32) are excavated to certain drilling depth, divides the differentiation preface to excavate right hole (33) at middle pilot tunnel (31) opposite side, pilot tunnel temporary lining in the dismounting makes right hole (33) be communicated with middle pilot tunnel (31), and immediate support,
The construction sequence of pilot tunnel is as follows in described:
Carry out advance support, the safety and the Stability Analysis of Structures of pilot tunnel in the assurance (31) excavation 1.4 utilize ductule to cooperate steel to support centering pilot tunnel (31);
1.5 centering pilot tunnel (31) barrel excavates and in time applies bolt-spary supports (3);
1.6 in middle pilot tunnel (31), apply steel concrete mid-board (4), adopt the slabstone backfill and apply temporary steel stull (2) away from existing single-hole tunnel (34) one sides at mid-board (4) then along its axis.
2. existing single-hole according to claim 1 tunnel reorganization and expansion is the job practices of multiple-arch tunnel, it is characterized in that left hole construction sequence is as follows:
2.1 adopt controlled blasting that the secondary lining (7) of existing single-hole tunnel (34) is removed, the dismounting cyclic advance is 1.5-3m;
2.2 when secondary lining (7) dismounting drilling depth reaches footpath, twice Dan Dong hole, left hole (32) first section country rock (8) is excavated, and in time carries out preliminary bracing;
2.3 left hole (32) second section country rock (10) is excavated, and in time applies inverted arch (11), left hole (32) preliminary bracing can in time be sealed;
2.4 when left hole (32) second section country rock (10) excavation drilling depth reaches footpath, one times of Dan Dong hole, carry out left hole secondary lining (12) and apply.
3. existing single-hole according to claim 1 tunnel reorganization and expansion is the job practices of multiple-arch tunnel, it is characterized in that right hole construction sequence is as follows:
3.1 mark part as right pilot tunnel (14) on You Dong (33) right side, and adopt booth pipe and steel bow member that right pilot tunnel (14) is carried out advance support, after secondary lining (7) dismounting drilling depth reaches footpath, four times of Dan Dong holes, right pilot tunnel (14) is excavated, and in time carry out preliminary bracing;
3.2 when right pilot tunnel (14) excavation drilling depth reaches footpath, twice Dan Dong hole, first section arch country rock (16) of right hole is excavated, and in time carries out preliminary bracing;
3.3 when first section arch country rock (16) excavation drilling depth of right hole reaches footpath, one times of Dan Dong hole, first section core soil (18) of right hole is excavated;
3.4 when core soil (18) excavation drilling depth reaches footpath, one times of Dan Dong hole, second section country rock (19) of right hole is excavated, and in time applies inverted arch (20), seal whole section;
3.5 when second section country rock (19) excavation drilling depth of right hole reaches footpath, one times of Dan Dong hole, apply right hole arch wall secondary lining (21).
4. existing single-hole according to claim 1 tunnel reorganization and expansion is the job practices of multiple-arch tunnel, it is characterized in that: the thickness of being separated by between pilot tunnel (31) and the existing tunnel in described is 1.6-1.8m.
CN2009101569076A 2009-12-24 2009-12-24 Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel Expired - Fee Related CN101737061B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101569076A CN101737061B (en) 2009-12-24 2009-12-24 Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101569076A CN101737061B (en) 2009-12-24 2009-12-24 Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel

Publications (2)

Publication Number Publication Date
CN101737061A CN101737061A (en) 2010-06-16
CN101737061B true CN101737061B (en) 2011-11-16

Family

ID=42461028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101569076A Expired - Fee Related CN101737061B (en) 2009-12-24 2009-12-24 Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel

Country Status (1)

Country Link
CN (1) CN101737061B (en)

Families Citing this family (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102121385B (en) * 2011-03-18 2012-12-05 同济大学 Tunnel excavation method for extending existing single-hole tunnel into double-arch tunnel
CN102296963B (en) * 2011-08-01 2013-10-23 湖南省交通规划勘察设计院 Construction method for ultra-long deep-buried road tunnel
CN102606167B (en) * 2012-03-16 2014-03-12 西安理工大学 Settlement control construction method for transverse grouting guide pipe of shallow underground excavation tunnel
CN102650212B (en) * 2012-05-04 2014-04-09 中国十七冶集团有限公司 Construction method for protecting partition wall in double-arch tunnel through temporary support of middle pilot tunnel
CN103628884B (en) * 2012-08-29 2016-01-27 中国水电顾问集团华东勘测设计研究院 Shared Rock of Neighborhood Tunnel reinforcement means
CN103114856B (en) * 2013-03-05 2015-04-01 福州市规划设计研究院 Construction method for in-situ broadening and remolding of existing double-arched tunnel
CN103306680B (en) * 2013-03-23 2015-09-30 中铁二院工程集团有限责任公司 Existing single-track tunnel enlarging is the construction method of multiple track tunnel
CN103256052B (en) * 2013-05-17 2015-04-15 北京国道通公路设计研究院股份有限公司 Construction method for integral straight middle wall type double-arch tunnel
CN103485791A (en) * 2013-09-27 2014-01-01 福州大学 Construction method for in-situ maintenance or extension of road tunnel
CN103821523A (en) * 2014-02-07 2014-05-28 福建省交通规划设计院 Excavating method for extending existing single-hole two-driveway tunnel into four-driveway tunnel
CN104405419B (en) * 2014-10-13 2016-05-18 中铁二院重庆勘察设计研究院有限责任公司 The parallel median septum construction method of wall multiple-arch tunnel in implicit expression
CN104929648B (en) * 2015-06-03 2017-03-01 西华大学 A kind of tunnel branch base tunnel construction method
CN104948208B (en) * 2015-06-30 2017-07-28 昆明理工大学 It is a kind of that big constructing structure and method across cavern is laterally extended based on narrow and small underpass
CN105862914B (en) * 2016-04-18 2018-03-09 西南交通大学 A kind of method separated ground additional load and influenceed on bottom proximity tunnel
CN105804760B (en) * 2016-05-17 2018-05-25 中铁十五局集团有限公司 Super-large-section tunnel drilling and blasting method extends constructing structure and construction method in situ
CN106988748B (en) * 2017-03-15 2019-10-29 中铁二院工程集团有限责任公司 High-order parallel heading construction and capacity expansion revamping are the construction method of double line tunnel
CN107060772B (en) * 2017-03-23 2019-05-17 中铁五局集团成都工程有限责任公司 Large section construction method is mutated for Line for Passenger Transportation standard section
CN108729927B (en) * 2018-05-22 2019-07-16 长安大学 A kind of existing tunnel reorganization and expansion is the mid-board construction method of multiple-arch tunnel
CN109695457A (en) * 2018-12-21 2019-04-30 中铁四局集团有限公司 The enlarging large section tunnel in situ and step construction method of hard rock
CN109882182A (en) * 2019-01-09 2019-06-14 中铁七局集团西安铁路工程有限公司 A kind of extra small clear distance construction method in tunnel
CN110185457B (en) * 2019-06-24 2020-08-04 中铁隧道局集团有限公司 TBM (Tunnel boring machine) horizontal pilot tunnel construction method
CN114086966B (en) * 2021-11-17 2023-04-25 湖南省交通规划勘察设计院有限公司 Construction method for fine vibration reduction blasting of four-arch tunnel
CN114263467B (en) * 2021-11-17 2022-09-23 湖南省交通规划勘察设计院有限公司 Excavation design construction method for four-arch tunnel
CN114086992B (en) * 2021-11-18 2024-05-03 中铁二院重庆勘察设计研究院有限责任公司 Large-span tunnel expanding and excavating construction method under complex geological conditions
CN114961739A (en) * 2022-05-16 2022-08-30 中铁五局集团有限公司 Construction method for re-excavation and expanded excavation of abandoned tunnel

Also Published As

Publication number Publication date
CN101737061A (en) 2010-06-16

Similar Documents

Publication Publication Date Title
CN101737061B (en) Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel
CN100487224C (en) Rapid-construction method for rapid change of small-section into large-section tunnel
CN106337686B (en) Three layers of subway station canopy structure of rocky stratum tunneling and construction method
CN101775988B (en) Method for constructing from inclined shaft to main tunnel in weak surrounding rock
CN202707075U (en) Long-span subway station main structure constructed based on column and arch method
CN102587922B (en) Oblique-crossing inclined shaft upper arc guide top brushing construction method for soft crushed rock layer
CN101440708B (en) PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN105888703B (en) Super Shallow Covered Metro Station construction method under lateral canopy lid is performed in micro- pilot tunnel
CN102748040B (en) Main structure for metro long-span station and pillar arching construction method thereof
CN102536273B (en) 26-meter large-span space one-step forming construction method
CN104632235A (en) Method for expanding excavation of large-diameter shield tunnel for subway station construction through pile arch wall support
CN102312672A (en) Fast large-cross-section tunnel construction method adapting to complicated and variable geological conditions
CN104165056A (en) Construction method for excavating water-rich shallow underground excavation tunnel
CN105804760B (en) Super-large-section tunnel drilling and blasting method extends constructing structure and construction method in situ
CN105443132A (en) Construction method of shallow-buried subsurface-excavated cross-shaped cross-strut tunnel
CN104929648A (en) Method for constructing branch guide pits of tunnels
CN104074524B (en) A kind of construction method of shallow embedding underpass of freeways large cross-section tunnel
CN103485790A (en) Shallow tunneling method for pipe-proof-supporting structure combined system
CN106050243A (en) Super-shallow-buried small-spacing large-section multi-tunnel concurrent construction method
CN103306680A (en) Construction method for extending single-track tunnel to multi-track tunnel
CN111206944B (en) Construction method for differential settlement control of pre-supporting excavation of deformation joint of underpass subway station
CN110017144A (en) A kind of three step construction method of loess tunnel considering bottom stab ilization processing
CN103161476A (en) Mechanical shaft-forming method of shield cutterhead maintenance shaft in tunnel and underground construction
CN105370288A (en) Construction method of shallow-buried large-span tunnels
CN109958445A (en) The frame construction method in Large Underground space is buried for an ultra shallow

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111116

Termination date: 20171224

CF01 Termination of patent right due to non-payment of annual fee