CN104929648B - A kind of tunnel branch base tunnel construction method - Google Patents

A kind of tunnel branch base tunnel construction method Download PDF

Info

Publication number
CN104929648B
CN104929648B CN201510299337.1A CN201510299337A CN104929648B CN 104929648 B CN104929648 B CN 104929648B CN 201510299337 A CN201510299337 A CN 201510299337A CN 104929648 B CN104929648 B CN 104929648B
Authority
CN
China
Prior art keywords
arch
construction
tunnel
excavation
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510299337.1A
Other languages
Chinese (zh)
Other versions
CN104929648A (en
Inventor
舒志乐
刘保县
周少波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xihua University
Original Assignee
Xihua University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xihua University filed Critical Xihua University
Priority to CN201510299337.1A priority Critical patent/CN104929648B/en
Publication of CN104929648A publication Critical patent/CN104929648A/en
Application granted granted Critical
Publication of CN104929648B publication Critical patent/CN104929648B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of tunnel branch base tunnel construction method, comprise the following steps:(1) preparation;(2) Shed-pipe Advanced Support, ductule construction;(3) arch Ring Cutting;(4) arch preliminary bracing and gib;(5) left and right excavation with guide pit and supporting;(6) Core Soil and inverted arch excavate;(7) tunnel bottom preliminary bracing;(8) inverted arch pours, fills;(9) secondary lining.Present invention advantage compared with prior art is:Using the construction method of the present invention, can prevent arch from caving in across shallow tunnel the big of rock crusher, its construction overall process is in safe and stable, quick controllable state;Quality project rate can reach more than 95% it is ensured that no industrial accident occurs.

Description

A kind of tunnel branch base tunnel construction method
Technical field
The present invention relates to construction method, a kind of more particularly, to tunnel branch base tunnel construction method.
Background technology
China is vast in territory, and surface relief is big, and 75% about territory is mountain region or weight mound, and the height above sea level discrepancy in elevation reaches 5000m, The highway built for 30 years after the founding of the state mostly winding detour or cut slope deep-cut, heavy damage ecological environment, cause soil erosion and Landslide landslide, or even some Formation of Revived Fossil Landslides, the fifties, China only has the vcehicular tunnel more than 30 of 2500 meters of overall length, " 95 " ~Tenth Five-Year Plan Period, for adapting to reform and opening-up and movement of population, expressway construction has obtained fast development, and the enforcement period of the ninth five-year plan is new Built tunnel 27.8 ten thousand linear meter(lin.m.), has also built up many spy's major long tunnel, such as Zhongliang Hill tunnel, Mount Jinyun tunnel and two Lang Shan tunnels Deng with Chinese society economic development, the deep expansion of strategy to develop western regions and the input further pulling domestic demand, on ground Shape, landforms and engineering geological condition are complicated, but tunnel of more growing up will be built in the west area of aboundresources, traffic reticular density Road engineering.Enter 21 century, China's urbanization, motorization process are constantly accelerated, and the urbanization rate of China in 2000 is only 36.2%, reached 47.5% to urbanization rate in 2010, cities and towns personnel by 4.6 hundred million poly- increase to 6.4 hundred million, to 2015 at the end of, with " ten Two or five " requirement planned is up to 51.5%, and China's automobile pollution is only 3,630,000 within 1986, and in the end of the year 2012, China is motor-driven Car recoverable amount has reached 2.4 hundred million, and the sharp increase of vehicle makes original road can't bear the heavy load, and has a strong impact on the trip of people and daily Life, become the bottleneck of socio-economic development, in order to ensure reasonable, the fast deployment of resource, will certainly build more three lanes, Highway tunnel with four lanes, due to the constraint of landform, geology, programme path etc., for meeting separate tunnel clear distance requirement, often needs by force Pull open linear and lead to adjacent segments to have some setbacks, project occupation of land is wider, Bridge-wire fusing time location can not effectively take into account bridge arrangement will Ask, small interval and multiple-arch tunnel are arisen at the historic moment with its unique advantage, multiple-arch tunnel structure construction and construction are complicated, quick to deforming Sense, and small-clear-distance tunnel can make full use of the bearing capacity of rock column in-between, substantially, many scholars are once in this side for economical and technical benefit Face is made that fruitful research.But because its section flat ratio is big, clear distance is little, and excavated section is big, than typically unidirectional pair of car Big 1.5~2.0 times of road tunnel cross-section, adjacent tunnel influences each other in work progress it is clear that traditional construction method can not Adapt to the requirement of across small interval greatly road construction completely, particularly in import and export section, complex geologic conditions, rock crusher, buried depth Shallow, therefore, the big construction method across small-clear-distance tunnel is studied, the practice of abundant highway in China constructing tunnel is had important Engineering significance and economic worth.
In China, the common method of tunneling typically has full section method, benching tunnelling method, and Ring Cutting stays core local method, hands over Fork median septum method (CRD method), two side-wall pilot tunnel etc..Usually, at the preferable situation of wall rock geology (I-III level country rock), On the premise of meeting tunnel safety quality, preferentially should adopt full section method and benching tunneling method, in the situation that wall rock geology is poor (IV-V level country rock), it is considered to the safe construction in tunnel, the especially tunnel mountain ridge geological conditions complicated when entering hole, should preferentially be adopted With two side-wall pilot tunnel and intersection median septum method.
Two side-wall pilot tunnel is all to arrange base tunnel in the both sides of tunnel excavation section, and all it is arranged with interim initial support The partial excavation method of side wall member, also known as glasses method it is adaptable to IV, V level country rock, when tunnel, span is very big for two side-wall pilot tunnel, Subsidence requires strictly, and wall rock condition row is not poor, when single side heading method is difficult to control to surrouding rock deformation, can be led using double side wall Hole method, field measurement shows, the ground settlement caused by two side-wall pilot tunnel is only about the 1/2 of short benching tunnelling method, this method one As section is divided into left and right sides base tunnel, top Core Soil and get out of a predicament or an embarrassing situation four pieces, the determination principle of size of heading and single side wall drift Method is identical, but width is no more than the 1/3 of section maximum span, and shape should be bordering on elliptical section, and left and right side base tunnel staggers Distance, should will not involve opposite side according to the impact excavating the redistribution of the surrouding rock stress caused by the base tunnel of side and become will base tunnel Principle determine, the transverse section that two side-wall pilot tunnel excavates is illustrated as shown in figure 1, vertical section is illustrated as shown in Fig. 2 construction operation Order is as follows:(1) left (right) excavation with guide pit;(2) left (right) base tunnel preliminary bracing;(3) right (left) excavation with guide pit;(4) right (left) Base tunnel preliminary bracing;(5) top bar is excavated;(6) top bar preliminary bracing, base tunnel next door are removed;(7) get out of a predicament or an embarrassing situation excavation;(8) face upward Arch preliminary bracing;(9) inverted arch pours in advance;(10) tunneling boring secondary lining.Shortcoming using two side-wall pilot tunnel is:1st, for Shallow-buried Large-span Tunnel, particularly country rock, compared with Area cracked, easily make tunnel arch scope country rock collapse using two side-wall pilot tunnel construction Collapse, roof fall the problems such as, construction safety risk is big;2nd, for unsymmetrial loading tunnel, horizontal displacement is larger;3rd, mutual shadow between each operation Ring, speed of application is slow.
Content of the invention
The present invention is to solve above-mentioned deficiency, there is provided a kind of tunnel branch base tunnel construction method.
The above-mentioned purpose of the present invention is realized by following technical scheme:A kind of tunnel branch base tunnel construction method, its It is characterised by:Comprise the following steps:
(1) preparation:Carry out drawing joint examination and work of confiding a technological secret before construction first, carry out live hole place simultaneously Smooth, equipment and materials preparation;And the centrage in measuring tunnel and sideline, some cross-sectional views are painted to light and shade interface segment, according to Massif side slope line and the plane relation in tunnel, determine shield arch position;
(2) Shed-pipe Advanced Support, ductule construction:
1., before pipe roof construction, first carry out 2m cased arch construction, embedded 5 Pin I18 I-steel in set arch, and by pipe canopy guide pipe Φ 127 × 4mm aperture sealing of tube is accurately fixed on I18 I-steel, and inclination angle becomes 5 °~10 ° angles with tunnel longitudinal gradient, in case pipe canopy Invade in tunnel excavation section because drilling rod deadweight is sunk during boring, thus hindering the excavation construction in tunnel, shield arch concrete placings Good aperture after mouth pipe is numbered;
2. pipe canopy adopts hot rolled seamless steel tube Φ 108mm, wall thickness 6mm, saves long 3m or 6m, pipe is away from the uniform cloth of 40cm spacing Hole;Inclination angle, parallel to gradient incline, is oriented parallel to route center line, and steel pipe construction error is radially not more than 20cm;
3. pipe canopy adopts blast drill carriage in crawler type SKM130, levelling of the land before boring, accurately determines hole position, in drilling process In do not shift and tilt, boring alternately, is often drilled hole jacking steel pipe immediately, in pipe, total length sets exhaustor, and stretches Outlet spout, at steel pipe and aperture gap closure closely knit it is ensured that during slip casting serosity do not spill over;
4. adopt GZJB type double-fluid grouting machine after installing steel pipe, serosity is by TBW250/15 type mixing hollander mixing;Slip casting material Material:Two fluid grouting;Cement mortar and waterglass volume ratio 1: 0.5, the cement mortar ratio of mud 1: 1, waterglass 40 Baume degrees, waterglass mould Number is 2.4;First pressing 0.5-1.0MPa, final pressure 2.5MPa, stop slip casting after holding pressure 15min;Grouting amount should meet the requirement of design, If grouting amount transfinites, not up to pressure requirements when, concentration of slurry should be adjusted and continue slip casting it is ensured that boring surrounding rock body and steel pipe week Enclose pore filling full;" single " number hole, Reperfu- sion " double " number hole is first irrigated during slip casting;After pressure reaches 2.5MPa, voltage stabilizing is very Zhong Hou, and enter to starch proportion identical with pulp proportion when stop slip casting;Special messenger will be had during slip casting to carry out filling in of slip casting log, real Border records the plasma volume of the every 5min of slip casting;
5. be first accurately positioned installation one Pin steel arch-shelf entering hole face, outside steel arch-shelf along the line by design document requirement Apply advanced tubule in the range of 130 ° of tunnel arch, ductule adopts YT28 type air drill perforate, opening diameter is 50mm, and With the blowpipe that blast is 0.5~0.6MPa, sandstone is blown out, drilling depth is not less than design hole depth;Pointed cone is made in ductule front end Shape, afterbody welding φ 8mm reinforcing bar is put more energy into hoop, every 30cm blossom type jewel hole on tube wall, eyelet a diameter of φ 8mm, tail length 100cm is as the only slurry section do not holed;After pore-forming, inspection declaration is verified, qualified after by ductule press design requirement with band impact YT28 type air drill heads into ductule in hole, expose 10-20cm convenient install to stop starch flexible pipe, after the completion of slip casting by ductule with Steelframe welding collectively constitutes pre support system;
(3) arch Ring Cutting:For the V level country rock that geological conditions is poor, because surrounding rock stability is poor, should in construction Follow the basic principle of " managing advanced, tight slip casting, short excavation, strong supporting, diligent measurement, early closing ", V level country rock should first advance support After excavate, Portal Section pre support adopt " pipe canopy+slip casting ", other sections of barrel adopt " ductule+slip casting " pre support, excavate adopt Human assisted mining machine excavates, and is directly transported to outside hole with loader, is transported with dumper.Often excavating cyclic advance is 1.0m, by Survey crew control direction and elevation, and release excavation contour line, left and right sides excavation with guide pit radius 6.252m, remainder is arch Portion's excavation width, excavates along excavation contour line during construction, excavation face should be as smoother as possible, to reduce stress concentration, strictly by applying Work Authority Contro1 out break.After the completion of excavation, preliminary bracing should be carried out in time;
(4) arch preliminary bracing and gib:
1. carry out immediately after excavating just spraying, to close country rock exposure as early as possible;Should carry out clearly to by spray scar before just spraying Reason, first sprays 4-6cm thickness concrete enclosing scar after the completion of cleaning;
2. just after spray concrete, I18 steelframe spacing 50cm is installed in time, is fixed with connecting reinforcing bar using lock foot anchoring stock, lock foot anchor Bar adopts the long Φ of 4m 22 grouting rock bolt, longitudinally adopts Φ 22 reinforcement welding of spacing 75cm firmly, makes bow member be linked to be entirety;
3. reinforced mesh is directly erected on steel arch-shelf, and is connected firmly with steel arch-shelf and anchor pole;Using A8 sizing reinforcing bar 20cm × 20cm welded mesh, the lap of splice is 20cm;
4. system anchor bolt drilling first should draw the bolthole point position needing construction and installation on scar, straight using YT28 type air drill Connect and pierce, connect GZJB type grouting pump and supporting filling adaptor carries out slip casting, blast controls in 0.4~0.6Mpa, gets into and sets Borehole cleaning behind meter position, it is to avoid blocking injected hole, during slip casting, Stress control is in 1~1.5Mpa;Anchor pole spacing 0.5 × 1.0m length in length and breadth Degree 4.0m is in that blossom type is arranged;System anchor bolt should be squeezed into vertical scar, its afterbody and steel arch-shelf firm welding;Injecting paste material adopts Neat slurry, cement mortar concentration 0.5: 1.5~1: 1.5, grouting pressure 0.6~1.0MPa, during slip casting, initial grouting pressure 0.3mpa to be maintained at, when reaching design pressure 1.0, after air vent pulp, stops slip casting, starches flexible pipe closed orifices with stopping;
5., after system anchor bolt construction, first spray scar is carried out clearing up it is sprayed onto design thickness again;Reality must be sprayed in bow member behind, no Must there is cavity;
6. by design and code requirement combine on-site actual situations, embedded monitoring measurement observation station, grasp construction in time During occur various situations, the generation of Accident prevention, for the later stage remove temporary support provide accurate metric data;
7. arch temporary support adopts the fan-shaped support of I22 I-steel, at interval of 1 Pin steel arch-shelf setting together, longitudinal pitch 1.0m, fan-shaped support bottom void slag is cleaned out and uses concrete levelling, then is welded integral with I22 I-steel, and sector supports middle Use Φ 22 bar connecting again;Suspend area surface construction after the excavation supporting circulation 10m of arch;
(5) left and right excavation with guide pit and supporting:
1. after the completion for the treatment of arch excavation supporting, and fall behind arch face 10m, carry out side base tunnel advanced tubule and apply Work;
2., after the completion of advanced tubule construction, side excavation with guide pit, preliminary bracing and gib are carried out;The side wall initial stage props up Shield steel arch-shelf should be connected firmly with arch steel arch-shelf, and side wall drift preliminary bracing construction method is identical with arch;
3., formerly after construction side excavation with guide pit 5-8m, opposite side excavation with guide pit, preliminary bracing and gib are carried out;
4. bury monitoring measurement observation station, the various situations occurring in grasp work progress in time, the generation of Accident prevention, Removing temporary support for the later stage provides accurate metric data;
5. after the completion of both sides excavation with guide pit, preliminary bracing and gib construction, according to monitoring and measurement data, determine arch After portion is stable, remove arch temporary support;
6., after removing arch temporary support, arch, double -side approach construction circulation are carried out;
(6) Core Soil and inverted arch excavate:
1. according to metrology data, after determining that double side wall is stable, remove double side wall gib, in demolishing process, two side should Stagger, prevent stress mutation from causing preliminary bracing to deform;
2., after removing double side wall gib, carry out Core Soil excavation and inverted arch excavates;
(7) tunnel bottom preliminary bracing:
1. carry out immediately after excavating just spraying, to close country rock exposure as early as possible, jetting cement is thick to be required according to design drawing Carry out;
2. press design requirement and set up steel arch-shelf, be connected with side wall steel arch-shelf, make overall steel arch-shelf closing cyclization;
(8) inverted arch pours, fills:
1. by design drawing requirement laying inverted arch reinforcing bar, carry out inverted arch concreting again;
2. lay after drain pipe by design drawing requirement, then carry out inverted arch filling and pour;
(9) secondary lining:
1. deform basicly stable in country rock and preliminary bracing, displacement convergence substantially slows down, produced items displacement Under conditions of meeting design requirement, carry out Second Lining Construction, in order to ensure two lining concrete qualities, template adopts the hydraulic pressure of 9m Integral movable type steel formwork trolley, is uniformly distributed 12 form vibrators on trolley formwork;Concrete blending station outside hole Centralized mixing, 9m3Concrete tank transports, and delivery pump is pumped into mould;Must be symmetrical before pouring, in case chassis displacement and mould Plate deforms, and should be continuously finished a mould concreting, and mode of vibration is shaken using poker vibrator cooperation attached vibrator Smash;
2. striking time:Not load-carrying members form removal when two lining concrete strengths reach 2.5Mpa, load-carrying members are secondary Lining concrete intensity reaches form removal during design strength 70%;
3. two lining concrete arrange special messenger periodically to carry out maintenance of sprinkling water after form removal.
The present invention improves working environment, ensures construction safety, improves efficiency of construction;And for shallow embedding, broken tunnel it is ensured that Arch scope country rock will not cave in, roof fall the problems such as, reduce construction risk;Also environmental protection simultaneously:Tunnel scheme typically requires Face-upward slope is carried out brush slope, change original topography and geomorphology, digging process pole causes face-upward slope unstability, and base tunnel partial excavation method can Realize the construction technology that " zero excavation " enters hole, realize engineering and environment and join in a common effort one.
Present invention advantage compared with prior art is:Using the construction method of the present invention, to rock crusher big across shallow Bury tunnel, can prevent arch from caving in, its construction overall process is in safe and stable, quick controllable state;Quality project rate More than 95% can be reached it is ensured that no industrial accident occurs.
Brief description
The schematic cross-sectional view that the traditional two side-wall pilot tunnel of Fig. 1 excavates.
The schematic longitudinal section that the traditional two side-wall pilot tunnel of Fig. 2 excavates.
Schematic cross-sectional view is excavated in Fig. 3 construction method of the present invention.
Schematic longitudinal section is excavated in Fig. 4 construction method of the present invention.
In Fig. 5 construction method of the present invention, branch's pilot tunnel method excavates perspective view.
The construction method flow chart of Fig. 6 present invention.
The schematic diagram of arch Ring Cutting in Fig. 7 construction method of the present invention.
The schematic diagram of left and right excavation with guide pit in Fig. 8 construction method of the present invention.
The schematic diagram of Core Soil and inverted arch excavation in Fig. 9 construction method of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawings the present invention is described in further detail.
Branch of the present invention pilot tunnel method technological principle:Based on rock mass mechanics theory, summed up point using New Austrian Tunneling Method principle Portion's pilot tunnel method construction method, will be divided into annular arch, left and right side base tunnel, central core four parts of soil by cavern excavation section. The determination principle of size of heading can be according to on-site actual situations flexible arrangement, and annular arch size is advisable with convenient construction operation, General height is 2m, and no more than the 1/3 of section maximum span, shape should be bordering on elliptical section to left and right base tunnel width, The distance that left and right side base tunnel staggers, should will not ripple according to the impact excavating the redistribution of the surrouding rock stress caused by side base tunnel And opposite side has become the principle of will base tunnel to determine, the reasonable distance between each base tunnel is 1.0B, to ensure that multiple operation circulates Line production, it is to avoid construction interferes, improves efficiency of construction.Concrete construction method is first arch Ring Cutting supporting, stable Arch, separated by a distance with annular arch after, left (right) excavation with guide pit supporting, then undertake mid portion country rock with side wall supporting Gravity, make excavated surface form preferable stability, shorten excavated section preliminary bracing closure the cyclization time it is ensured that Construction safety, its scope of application master be top rock country rock more open it is impossible to form the section of Load -carring arch.Fig. 3 is branch Pilot tunnel method excavates schematic cross-sectional view, and Fig. 4 is schematic longitudinal section, and Fig. 5 is to excavate perspective view.Construction operation order is as follows:
(1) annular arch is excavated;
(2) annular arch preliminary bracing;
(3) left (right) excavation with guide pit;
(4) left (right) base tunnel preliminary bracing;
(5) right (left) excavation with guide pit top bar is excavated;
(6) right (left) base tunnel preliminary bracing top bar preliminary bracing;
(7) central core soil excavates, base tunnel next door is removed;
(8) inverted arch preliminary bracing;
(9) inverted arch pours in advance;
(10) tunneling boring secondary lining.
For small-clear-distance tunnel due between adjacent two tunnels excavation can produce and influence each other, and cause rock column in-between Repeatedly disturbance, if construction spacing in row hole closely can have a strong impact on very much the stability of rock column in-between one after another, far can extend work very much again Phase, during construction, desirable 1.5B is to excavate spacing, to ensure to apply safety.
For the Large span tunnel in Shallow-buried location, when excavating using branch's pilot tunnel method, first excavate shallow embedding side tunnel, when When vertical stress is maximum principal stress, first excavates the base tunnel by rock column in-between and to surrounding rock stability and control deformation advantageously, When horizontal crustal stress be maximum principal stress when, first excavate away from rock column in-between base tunnel advantageously.Work progress should weigh Point reinforces arch springing and rock column in-between, and should perform inverted arch in time, strengthens country rock stability in the large, prevents pucking phenomenon.
As shown in fig. 6, the comprising the following steps that of a kind of tunnel branch base tunnel construction method of the present invention:
(1) preparation:Carry out drawing joint examination and work of confiding a technological secret before construction first, carry out live hole place simultaneously Smooth, equipment and materials preparation;And the centrage in measuring tunnel and sideline, some cross-sectional views are painted to light and shade interface segment, according to Massif side slope line and the plane relation in tunnel, determine shield arch position;
(2) Shed-pipe Advanced Support, ductule construction:
1., before pipe roof construction, first carry out 2m cased arch construction, embedded 5 Pin I18 I-steel in set arch, and by pipe canopy guide pipe Φ 127 × 4mm aperture sealing of tube is accurately fixed on I18 I-steel, and inclination angle becomes 5 °~10 ° angles with tunnel longitudinal gradient, in case pipe canopy Invade in tunnel excavation section because drilling rod deadweight is sunk during boring, thus hindering the excavation construction in tunnel, shield arch concrete placings Good aperture after mouth pipe is numbered;
2. pipe canopy adopts hot rolled seamless steel tube Φ 108mm, wall thickness 6mm, saves long 3m or 6m, pipe is away from the uniform cloth of 40cm spacing Hole;Inclination angle, parallel to gradient incline, is oriented parallel to route center line, and steel pipe construction error is radially not more than 20cm;
3. pipe canopy adopts blast drill carriage in crawler type SKM130, levelling of the land before boring, accurately determines hole position, in drilling process In do not shift and tilt, boring alternately, is often drilled hole jacking steel pipe immediately, in pipe, total length sets exhaustor, and stretches Outlet spout, at steel pipe and aperture gap closure closely knit it is ensured that during slip casting serosity do not spill over;
4. adopt GZJB type double-fluid grouting machine after installing steel pipe, serosity is by TBW250/15 type mixing hollander mixing;Slip casting material Material:Two fluid grouting;Cement mortar and waterglass volume ratio 1: 0.5, the cement mortar ratio of mud 1: 1, waterglass 40 Baume degrees, waterglass mould Number is 2.4;First pressing 0.5-1.0MPa, final pressure 2.5MPa, stop slip casting after holding pressure 15min;Grouting amount should meet the requirement of design, If grouting amount transfinites, not up to pressure requirements when, concentration of slurry should be adjusted and continue slip casting it is ensured that boring surrounding rock body and steel pipe week Enclose pore filling full;" single " number hole, Reperfu- sion " double " number hole is first irrigated during slip casting;After pressure reaches 2.5MPa, voltage stabilizing is very Zhong Hou, and enter to starch proportion identical with pulp proportion when stop slip casting;Special messenger will be had during slip casting to carry out filling in of slip casting log, real Border records the plasma volume of the every 5min of slip casting;
5. be first accurately positioned installation one Pin steel arch-shelf entering hole face, outside steel arch-shelf along the line by design document requirement Apply advanced tubule in the range of 130 ° of tunnel arch, ductule adopts YT28 type air drill perforate, opening diameter is 50mm, and With the blowpipe that blast is 0.5~0.6MPa, sandstone is blown out, drilling depth is not less than design hole depth;Pointed cone is made in ductule front end Shape, afterbody welding φ 8mm reinforcing bar is put more energy into hoop, every 30cm blossom type jewel hole on tube wall, eyelet a diameter of φ 8mm, tail length 100cm is as the only slurry section do not holed;After pore-forming, inspection declaration is verified, qualified after by ductule press design requirement with band impact YT28 type air drill heads into ductule in hole, expose 10-20cm convenient install to stop starch flexible pipe, after the completion of slip casting by ductule with Steelframe welding collectively constitutes pre support system;
(3) arch Ring Cutting:As shown in fig. 7, for the poor V level country rock of geological conditions, because surrounding rock stability is relatively Difference, should follow the basic principle of " advanced, the tight slip casting of pipe, short excavation, strong supporting, duty measure, early close ", V level country rock in construction Should excavate after first advance support, Portal Section pre support adopts " pipe canopy+slip casting ", and other sections of barrel are pre- using " ductule+slip casting " Supporting, is excavated and is excavated using human assisted mining machine, be directly transported to outside hole with loader, transported with dumper.Often excavate circulation Drilling depth is 1.0m, by survey crew control direction and elevation, and releases excavation contour line, left and right sides excavation with guide pit radius 6.252m, remainder is arch excavation width, excavates along excavation contour line, excavation face should be as smoother as possible, to subtract during construction Few stress concentration, strictly presses job specfication and controls out break.After the completion of excavation, preliminary bracing should be carried out in time;
(4) arch preliminary bracing and gib:
1. carry out immediately after excavating just spraying, to close country rock exposure as early as possible;Should carry out clearly to by spray scar before just spraying Reason, first sprays 4-6cm thickness concrete enclosing scar after the completion of cleaning;
2. just after spray concrete, I18 steelframe spacing 50cm is installed in time, is fixed with connecting reinforcing bar using lock foot anchoring stock, lock foot anchor Bar adopts the long Φ of 4m 22 grouting rock bolt, longitudinally adopts Φ 22 reinforcement welding of spacing 75cm firmly, makes bow member be linked to be entirety;
3. reinforced mesh is directly erected on steel arch-shelf, and is connected firmly with steel arch-shelf and anchor pole;Using A8 sizing reinforcing bar 20cm × 20cm welded mesh, the lap of splice is 20cm;
4. system anchor bolt drilling first should draw the bolthole point position needing construction and installation on scar, straight using YT28 type air drill Connect and pierce, connect GZJB type grouting pump and supporting filling adaptor carries out slip casting, blast controls in 0.4~0.6Mpa, gets into and sets Borehole cleaning behind meter position, it is to avoid blocking injected hole, during slip casting, Stress control is in 1~1.5Mpa;Anchor pole spacing 0.5 × 1.0m length in length and breadth Degree 4.0m is in that blossom type is arranged;System anchor bolt should be squeezed into vertical scar, its afterbody and steel arch-shelf firm welding;Injecting paste material adopts Neat slurry, cement mortar concentration 0.5: 1.5~1: 1.5, grouting pressure 0.6~1.0MPa, during slip casting, initial grouting pressure 0.3mpa to be maintained at, when reaching design pressure 1.0, after air vent pulp, stops slip casting, starches flexible pipe closed orifices with stopping;
5., after system anchor bolt construction, first spray scar is carried out clearing up it is sprayed onto design thickness again;Reality must be sprayed in bow member behind, no Must there is cavity;
6. by design and code requirement combine on-site actual situations, embedded monitoring measurement observation station, grasp construction in time During occur various situations, the generation of Accident prevention, for the later stage remove temporary support provide accurate metric data;
7. arch temporary support adopts the fan-shaped support of I22 I-steel, at interval of 1 Pin steel arch-shelf setting together, longitudinal pitch 1.0m, fan-shaped support bottom void slag is cleaned out and uses concrete levelling, then is welded integral with I22 I-steel, and sector supports middle Use Φ 22 bar connecting again;Suspend area surface construction after the excavation supporting circulation 10m of arch;
(5) left and right excavation with guide pit and supporting:Left and right excavation with guide pit as shown in figure 8,
1. after the completion for the treatment of arch excavation supporting, and fall behind arch face 10m, carry out side base tunnel advanced tubule and apply Work;
2., after the completion of advanced tubule construction, side excavation with guide pit, preliminary bracing and gib are carried out;The side wall initial stage props up Shield steel arch-shelf should be connected firmly with arch steel arch-shelf, and side wall drift preliminary bracing construction method is identical with arch;
3., formerly after construction side excavation with guide pit 5-8m, opposite side excavation with guide pit, preliminary bracing and gib are carried out;
4. bury monitoring measurement observation station, the various situations occurring in grasp work progress in time, the generation of Accident prevention, Removing temporary support for the later stage provides accurate metric data;
5. after the completion of both sides excavation with guide pit, preliminary bracing and gib construction, according to monitoring and measurement data, determine arch After portion is stable, remove arch temporary support;
6., after removing arch temporary support, arch, double -side approach construction circulation are carried out;
(6) Core Soil and inverted arch excavate:As shown in figure 9,
1. according to metrology data, after determining that double side wall is stable, remove double side wall gib, in demolishing process, two side should Stagger, prevent stress mutation from causing preliminary bracing to deform;
2., after removing double side wall gib, carry out Core Soil excavation and inverted arch excavates;
(7) tunnel bottom preliminary bracing:
1. carry out immediately after excavating just spraying, to close country rock exposure as early as possible, jetting cement is thick to be required according to design drawing Carry out;
2. press design requirement and set up steel arch-shelf, be connected with side wall steel arch-shelf, make overall steel arch-shelf closing cyclization;
(8) inverted arch pours, fills:
1. by design drawing requirement laying inverted arch reinforcing bar, carry out inverted arch concreting again;
2. lay after drain pipe by design drawing requirement, then carry out inverted arch filling and pour;
(9) secondary lining:
1. deform basicly stable in country rock and preliminary bracing, displacement convergence substantially slows down, produced items displacement Under conditions of meeting design requirement, carry out Second Lining Construction, in order to ensure two lining concrete qualities, template adopts the hydraulic pressure of 9m Integral movable type steel formwork trolley, is uniformly distributed 12 form vibrators on trolley formwork;Concrete blending station outside hole Centralized mixing, 9m3Concrete tank transports, and delivery pump is pumped into mould;Must be symmetrical before pouring, in case chassis displacement and mould Plate deforms, and should be continuously finished a mould concreting, and mode of vibration is shaken using poker vibrator cooperation attached vibrator Smash;
2. striking time:Not load-carrying members form removal when two lining concrete strengths reach 2.5Mpa, load-carrying members are secondary Lining concrete intensity reaches form removal during design strength 70%;
3. two lining concrete arrange special messenger periodically to carry out maintenance of sprinkling water after form removal.
Example:Lishui City 50 provincial highway lotus all section road improvenment the 4th contract section road gulf Tunnel Engineering total prices 5469.9 ten thousand Unit, is separate tunnel, class of loading:Highway-I level, Tunnel Design speed per hour 60km/h.Left hole starting point mileage K4+040, terminal Mileage K4+703, length of tunnel is 663m.Portal Section (K4+040-K4+115) ground mulching is entered in left tunnel hole the residual of 6-9m thickness Slope accumulation body, surface vegetation is developed, and this section is shallow embedding, bias location, joints development, and country rock is weak, and subsoil water is relatively developed, and belongs to V level country rock, surrounding rock stability is poor, when arch and side wall non-support, can produce and caves in, falls the problems such as block, slump.50 provincial highway lotuses are all Section road improvenment road gulf left tunnel hole Shallow-buried section starts to construct using this engineering method on March 26th, 2013,2013 , on August completed to construct for 8, and averagely daily progress is 0.55m.Using after this engineering method, construction overall process is in safe and stable, fast The controllable state of speed.Quality project rate reaches more than 95%, and no industrial accident occurs, and has obtained the good of various circles of society Comment.
The foregoing is only embodiments of the invention, not thereby limit the present invention the scope of the claims, every using this Equivalent structure or equivalent flow conversion that bright description is made, or directly or indirectly it is used in other related technology necks Domain, is included within the scope of the present invention.

Claims (1)

1. a kind of tunnel branch base tunnel construction method it is characterised in that:Comprise the following steps:
(1) preparation:Carry out drawing joint examination and work of confiding a technological secret before construction first, carry out live hole place simultaneously and put down Whole, equipment and materials preparation;And the centrage in measuring tunnel and sideline, some cross-sectional views are painted to light and shade interface segment, according to mountain Body side slope line and the plane relation in tunnel, determine shield arch position;
(2) Shed-pipe Advanced Support, ductule construction:
1., before pipe roof construction, first carry out 2m cased arch construction, embedded 5 Pin I18 I-steel in set arch, and by pipe canopy guide pipe Φ 127 × 4mm aperture sealing of tube is accurately fixed on I18 I-steel, and inclination angle becomes 5 °~10 ° angles with tunnel longitudinal gradient, in case the boring of pipe canopy When, invade in tunnel excavation section because drilling rod deadweight is sunk, thus hindering the excavation construction in tunnel, after shield arch concrete placings are good Orifice tube is numbered;
2. pipe canopy adopts hot rolled seamless steel tube Φ 108mm, wall thickness 6mm, saves long 3m or 6m, pipe is away from the uniform cloth hole of 40cm spacing;Incline Angle, parallel to gradient incline, is oriented parallel to route center line, and steel pipe construction error is radially not more than 20cm;
3. pipe canopy adopts blast drill carriage in crawler type SKM130, levelling of the land before boring, accurately determines hole position, in drilling process not Shift and tilt, boring alternately, is often drilled hole jacking steel pipe immediately, in pipe, total length sets exhaustor, and protruded tube Mouthful, at steel pipe and aperture gap block closely knit it is ensured that during slip casting serosity do not spill over;
4. adopt GZJB type double-fluid grouting machine after installing steel pipe, serosity is by TBW250/15 type mixing hollander mixing;Injecting paste material: Two fluid grouting;Cement mortar and waterglass volume ratio 1: 0.5, the cement mortar ratio of mud 1: 1, waterglass 40 Baume degrees, modulus of water glass For 2.4;First pressing 0.5-1.0MPa, final pressure 2.5MPa, stop slip casting after holding pressure 15min;Grouting amount meets the requirement of design, if note Slurry amount transfinites, not up to pressure requirements when, adjustment concentration of slurry continue slip casting it is ensured that boring surrounding rock body and steel pipe around hole Filling is full;" single " number hole, Reperfu- sion " double " number hole is first irrigated during slip casting;After voltage stabilizing ten minutes after pressure reaches 2.5MPa, And enter to starch proportion identical with pulp proportion when stop slip casting;Special messenger to be had during slip casting to carry out filling in of slip casting log, actual note The plasma volume of the record every 5min of slip casting;
5. be first accurately positioned installation one Pin steel arch-shelf entering hole face, outside steel arch-shelf along the line by design document requirement in tunnel Advanced tubule is applied, ductule adopts YT28 type air drill perforate, opening diameter is 50mm, and uses wind in the range of 130 ° of road arch The blowpipe for 0.5~0.6MPa is pressed to blow out sandstone, drilling depth is not less than design hole depth;Sharp cone distal is made in ductule front end, Afterbody welding φ 8mm reinforcing bar is put more energy into hoop, every 30cm blossom type jewel hole on tube wall, eyelet a diameter of φ 8mm, and tail length 100cm is as the only slurry section do not holed;After pore-forming, inspection declaration is verified, qualified after by ductule press design requirement with band impact YT28 type air drill heads into ductule in hole, expose 10-20cm convenient install to stop starch flexible pipe, after the completion of slip casting by ductule with Steelframe welding collectively constitutes pre support system;
(3) arch Ring Cutting:For the V level country rock that geological conditions is poor, because surrounding rock stability is poor, follow in construction The basic principle of " managing advanced, tight slip casting, short excavation, strong supporting, diligent measurement, early closing ", opens after V level country rock elder generation advance support Dig, Portal Section pre support adopts " pipe canopy+slip casting ", other sections of barrel adopt " ductule+slip casting " pre support, excavate using artificial Assisted mining machine excavates, and is directly transported to outside hole with loader, is transported with dumper, and often excavating cyclic advance is 1.0m, by measuring Personnel control direction and elevation, and release excavation contour line, left and right sides excavation with guide pit radius 6.252m, remainder is arch Excavation width, excavates along excavation contour line during construction, and excavation face is as smoother as possible, to reduce stress concentration, strictly presses construction rule Model controls out break, after the completion of excavation, carries out preliminary bracing in time;
(4) arch preliminary bracing and gib:
1. carry out immediately after excavating just spraying, to close country rock exposure as early as possible;Clear up to by spray scar before just spraying, cleaning After the completion of first spray 4-6cm thickness concrete enclosing scar;
2. just after spray concrete, I18 steelframe spacing 50cm is installed in time, is fixed with connecting reinforcing bar using lock foot anchoring stock, lock foot anchoring stock is adopted With the long Φ of 4m 22 grouting rock bolt, longitudinally adopt Φ 22 reinforcement welding of spacing 75cm firmly, make bow member be linked to be entirety;
3. reinforced mesh is directly erected on steel arch-shelf, and is connected firmly with steel arch-shelf and anchor pole;Using A8 sizing reinforcing bar 20cm × 20cm welded mesh, the lap of splice is 20cm;
4. system anchor bolt drilling first draws the bolthole point position needing construction and installation on scar, is directly bored using YT28 type air drill Enter, connect GZJB type grouting pump and supporting filling adaptor carries out slip casting, blast controls in 0.4~0.6Mpa, get into design position Postpone borehole cleaning, it is to avoid blocking injected hole, during slip casting, Stress control is in 1~1.5Mpa;Anchor pole spacing 0.5 × 1.0m length in length and breadth 4.0m is in that blossom type is arranged;The vertical scar of system anchor bolt is squeezed into, its afterbody and steel arch-shelf firm welding;Injecting paste material adopts pure water Mud, cement mortar concentration 0.5: 1.5~1: 1.5, grouting pressure 0.6~1.0MPa, during slip casting, initial grouting pressure will be protected Hold in 0.3mpa, when reaching design pressure 1.0, after air vent pulp, stop slip casting, starch flexible pipe closed orifices with stopping;
5., after system anchor bolt construction, first spray scar is carried out clearing up it is sprayed onto design thickness again;Reality must be sprayed in bow member behind, must not have Cavity;
6. by design and code requirement combine on-site actual situations, embedded monitoring measurement observation station, grasp work progress in time The various situations of middle appearance, the generation of Accident prevention, removing temporary support for the later stage provides accurate metric data;
7. arch temporary support adopts the fan-shaped support of I22 I-steel, at interval of 1 Pin steel arch-shelf setting together, longitudinal pitch 1.0m, Sector supports bottom void slag to clean out and use concrete levelling, then is welded integral with I22 I-steel, uses Φ again in the middle of fan-shaped support 22 bar connecting;Suspend area surface construction after the excavation supporting circulation 10m of arch;
(5) left and right excavation with guide pit and supporting:
1. after the completion for the treatment of arch excavation supporting, and fall behind arch face 10m, carry out side base tunnel advanced tubule construction;
2., after the completion of advanced tubule construction, side excavation with guide pit, preliminary bracing and gib are carried out;Side wall preliminary bracing steel Bow member is connected firmly with arch steel arch-shelf, and side wall drift preliminary bracing construction method is identical with arch;
3., formerly after construction side excavation with guide pit 5-8m, opposite side excavation with guide pit, preliminary bracing and gib are carried out;
4. bury monitoring measurement observation station, grasp the various situations occurring in work progress in time, the generation of Accident prevention, after being Phase removes temporary support and provides accurate metric data;
5., after the completion of both sides excavation with guide pit, preliminary bracing and gib construction, according to monitoring and measurement data, determine that arch is steady After fixed, remove arch temporary support;
6., after removing arch temporary support, arch, double -side approach construction circulation are carried out;
(6) Core Soil and inverted arch excavate:
1. according to metrology data, after determining that double side wall is stable, remove double side wall gib, in demolishing process, stagger in two side, Prevent stress mutation from causing preliminary bracing to deform;
2., after removing double side wall gib, carry out Core Soil excavation and inverted arch excavates;
(7) tunnel bottom preliminary bracing:
1. carry out immediately after excavating just spraying, to close country rock exposure as early as possible, jetting cement is thick to be required to carry out according to design drawing;
2. press design requirement and set up steel arch-shelf, be connected with side wall steel arch-shelf, make overall steel arch-shelf closing cyclization;
(8) inverted arch pours, fills:
1. by design drawing requirement laying inverted arch reinforcing bar, carry out inverted arch concreting again;
2. lay after drain pipe by design drawing requirement, then carry out inverted arch filling and pour;
(9) secondary lining:
1. deform basicly stable in country rock and preliminary bracing, displacement convergence substantially slows down, produced items displacement meets Under conditions of design requirement, carry out Second Lining Construction, in order to ensure two lining concrete qualities, template adopts the hydraulic pressure of 9m overall Mobile steel formwork jumbo, is uniformly distributed 12 form vibrators on trolley formwork;Concrete blending station outside hole is concentrated Mixing, 9m3Concrete tank transports, and delivery pump is pumped into mould;Must be symmetrical before pouring, in case chassis displacement and template become Shape, and it is continuously finished a mould concreting, mode of vibration is vibrated using poker vibrator cooperation attached vibrator;
2. striking time:Not load-carrying members form removal when two lining concrete strengths reach 2.5Mpa, load-carrying members are in secondary lining Concrete strength reaches form removal during design strength 70%;
3. two lining concrete arrange special messenger periodically to carry out maintenance of sprinkling water after form removal.
CN201510299337.1A 2015-06-03 2015-06-03 A kind of tunnel branch base tunnel construction method Expired - Fee Related CN104929648B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510299337.1A CN104929648B (en) 2015-06-03 2015-06-03 A kind of tunnel branch base tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510299337.1A CN104929648B (en) 2015-06-03 2015-06-03 A kind of tunnel branch base tunnel construction method

Publications (2)

Publication Number Publication Date
CN104929648A CN104929648A (en) 2015-09-23
CN104929648B true CN104929648B (en) 2017-03-01

Family

ID=54117041

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510299337.1A Expired - Fee Related CN104929648B (en) 2015-06-03 2015-06-03 A kind of tunnel branch base tunnel construction method

Country Status (1)

Country Link
CN (1) CN104929648B (en)

Families Citing this family (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863648B (en) * 2016-04-06 2018-04-10 中铁二十三局集团第二工程有限公司 A kind of tunneling is shallow to cover large-section tunnel construction method
CN107013220A (en) * 2017-05-16 2017-08-04 深圳市瑞利源工程技术有限公司 A kind of tunnel deep hole grouting method, pipe canopy and retrusive Grouting Pipe
CN107060778B (en) * 2017-06-15 2019-03-05 中铁十一局集团第五工程有限公司 Pass through super high-rise building group back filled region method for tunnel construction
CN107704675B (en) * 2017-09-28 2021-07-16 中南大学 Design method and model of advanced pipe shed-steel arch frame-foot locking anchor rod integrated mechanical model
CN107605509A (en) * 2017-11-08 2018-01-19 中铁十局集团有限公司 Sand-pebble layer small curve radius shallow tunnel subsurface excavation method advanced supporting construction method
CN108487911A (en) * 2018-03-28 2018-09-04 中铁二院工程集团有限责任公司 The compound crossing method construction method of longspan tunnel bilateral wall under complex geological condition
CN108643925A (en) * 2018-05-17 2018-10-12 中铁十二局集团有限公司 Intersect the cycle construction method of the tunneling section under mid-board engineering method
CN109026029A (en) * 2018-10-09 2018-12-18 中建地下空间有限公司 A kind of construction method suitable for breaking surrounding rock tunnel excavation support
CN109667603A (en) * 2018-12-28 2019-04-23 中铁第四勘察设计院集团有限公司 A kind of super shallow-buried tunnel structure and construction method
CN109518722A (en) * 2019-01-22 2019-03-26 云南省建设投资控股集团有限公司 The short underpass structure and its construction method of newly-built basement and existing subway station
CN109779641B (en) * 2019-03-13 2023-12-15 大连理工大学 Composite submarine tunnel structure based on hydraulic self-supporting characteristic and construction method
CN109915178B (en) * 2019-03-29 2020-06-12 中国水利水电第三工程局有限公司 Steel structure assisted jacking flow-reducing tunnel water plugging method
CN110230497A (en) * 2019-06-24 2019-09-13 中铁隧道局集团有限公司 A kind of positive barrel double -side approach construction method in threaded list road
CN110630282B (en) * 2019-09-02 2021-07-06 中铁十八局集团有限公司 Double-track railway tunnel weak surrounding rock advanced reinforcement simple pipe shed room
CN110578536A (en) * 2019-10-15 2019-12-17 中铁十二局集团有限公司 Excavation support reinforcing method for underground excavation section of subway to penetrate existing street crossing channel
CN111706352A (en) * 2020-05-21 2020-09-25 中国水利水电第十四工程局有限公司 Method for entering arch into hole by using bias tunnel arch sleeve
CN111502715B (en) * 2020-05-29 2021-07-20 中铁第六勘察设计院集团有限公司 Method for comprehensively constructing fractured rock mass in oversized underground cavern crossing stage
CN111828048B (en) * 2020-07-28 2022-09-06 中建七局安装工程有限公司 Method for preventing powder soil from caving at top of shallow-buried underground-excavated tunnel construction tunnel
CN112302662B (en) * 2020-10-29 2022-10-14 中铁上海工程局集团有限公司 Construction method of artificial backfill shallow-buried tunnel passing through highway
CN112902933A (en) * 2021-01-21 2021-06-04 河北建设勘察研究院有限公司 Tunnel structure deformation monitoring device and monitoring method
CN113236259B (en) * 2021-06-02 2023-12-05 崔旭雄 Special construction process for excavating and supporting bulk-junction tunnel
CN113401586B (en) * 2021-06-26 2022-05-10 山东省公路桥梁建设集团有限公司 Tunnel excavation method
CN113389566B (en) * 2021-07-30 2022-04-08 中铁十二局集团有限公司 Construction method for rapid expanding excavation and conversion by CRD (China railway track) normal double-side-wall pit guiding method
CN113404517B (en) * 2021-08-03 2023-09-22 福建工程学院 Construction method for tunnel mud bursting and water flushing
CN114109436A (en) * 2021-12-01 2022-03-01 中铁二局集团有限公司 Large-span underground excavation construction method for subway station

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3266257A (en) * 1963-05-31 1966-08-16 Robbins & Assoc James S Shield tunneling method and mechanism
CN101737061B (en) * 2009-12-24 2011-11-16 中国水电顾问集团华东勘测设计研究院 Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel
CN101858220B (en) * 2010-05-28 2012-02-22 深圳市建设(集团)有限公司 Tunnel double upper sidewall heading construction method
CN102182466B (en) * 2011-04-08 2013-05-01 中铁上海设计院集团有限公司 Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel
CN102587924A (en) * 2012-03-26 2012-07-18 中铁十三局集团第四工程有限公司 Construction method for shallow-buried high-water-content clayed soil tunnel
CN102720504A (en) * 2012-06-13 2012-10-10 北京市公路桥梁建设集团有限公司 Double-side-wall-pilot-hole subsection bench cut method construction method
CN104405399B (en) * 2014-09-18 2017-05-31 中铁建大桥工程局集团第二工程有限公司 One kind passes through drift sand stratum tunnel excavation support body engineering method

Also Published As

Publication number Publication date
CN104929648A (en) 2015-09-23

Similar Documents

Publication Publication Date Title
CN104929648B (en) A kind of tunnel branch base tunnel construction method
CN104612698B (en) A kind of shallow-depth-excavation tunnel top bar interval wall construction method
CN106337686B (en) Three layers of subway station canopy structure of rocky stratum tunneling and construction method
CN102606162B (en) Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel
CN104500077B (en) A kind of shallow-depth-excavation tunnel passes through cottage area construction method
CN105443132B (en) Shallow buried covered excavation cross stull method for tunnel construction
CN102226403B (en) Construction method of large-span subway station main body by using arched cover method and station main body structure
CN101440708B (en) PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN104564128B (en) A kind of shallow-depth-excavation tunnel construction deformation monitoring method
CN104453921B (en) A kind of Soft Rock Tunnel Excavation construction technology
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN107542470B (en) Existing railway Business Line construction method is worn under the shallow tunnel of karst broken region
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN202707075U (en) Long-span subway station main structure constructed based on column and arch method
CN110700841B (en) Double-side-wall guide pit type excavation method for tunnel excavation
CN205977229U (en) Arcading tunnel non - flushes entrance to a cave structure suitable for bias voltage condition
CN110130927A (en) A kind of carbonaceous slate serious deformation control construction method
CN105587320B (en) Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN109538246A (en) Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN106979021A (en) Large-section loess tunnel is excavated and preliminary bracing quick closure looping technique
CN110374657A (en) The Mining Method Subway Tunnel ventilating shaft and its construction method of " well after first shield "
CN111794774A (en) Rapid entering protection structure of half cut single-pressure open cut tunnel and construction method
CN100513705C (en) Underground Beam-Pile Frame Structure for Slope Reinforcement

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170301

Termination date: 20170603

CF01 Termination of patent right due to non-payment of annual fee