CH359270A - Method of constructing a reinforced concrete floor by means of temporary slab supports and device for implementing the method - Google Patents

Method of constructing a reinforced concrete floor by means of temporary slab supports and device for implementing the method

Info

Publication number
CH359270A
CH359270A CH359270DA CH359270A CH 359270 A CH359270 A CH 359270A CH 359270D A CH359270D A CH 359270DA CH 359270 A CH359270 A CH 359270A
Authority
CH
Switzerland
Prior art keywords
plank
slabs
support
floor
extension
Prior art date
Application number
Other languages
French (fr)
Inventor
Alziari Louis
Original Assignee
Alziari Louis
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Alziari Louis filed Critical Alziari Louis
Publication of CH359270A publication Critical patent/CH359270A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/50Girders, beams, or the like as supporting members for forms
    • E04G11/54Girders, beams, or the like as supporting members for forms of extensible type, with or without adjustable supporting shoes, fishplates, or the like
    • E04G11/56Girders, beams, or the like as supporting members for forms of extensible type, with or without adjustable supporting shoes, fishplates, or the like of telescopic type
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/40Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings for coffered or ribbed ceilings
    • E04G11/46Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings for coffered or ribbed ceilings of hat-like or trough-like shape encasing a rib or the section between two ribs or encasing one rib and its adjacent flat floor or ceiling section

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Moulds, Cores, Or Mandrels (AREA)

Description

  

  Procédé de     construction    d'un plancher en béton armé  au moyen de supports provisoires de hourdis  et dispositif pour la mise en     #uvre    du procédé    Le présent breveta pour objet un     procédé    de  construction d'un plancher en béton armé au moyen  de supports provisoires de hourdis et un dispositif  pour la mise en     #uvre    du procédé.  



  Pour la construction de planchers en béton  armé, on se sert généralement de coffrages entière  ment en bois. La mise en place correcte du coffrage  et de ses nombreux étais pour obtenir que toutes  les parties de la surface restent bien dans un même  plan horizontal demande de multiples ajustements et  constitue une opération longue et délicate. Pour évi  ter ces difficultés, on utilise actuellement des pou  trelles métalliques, constituées par un     corps        unique     ou par un corps     principal    avec une ou deux rallon  ges coulissant     télescopiquement    dans le     corps    prin  cipal.

   Les semelles supérieures de ces poutrelles rec  tilignes, accrochées sur les planches de rive     accolées     aux murs et autres appuis des travées, constituent  les supports du     coffrage    ou des hourdis préfabriqués  en réalisant ainsi, par le fait même de la rigidité de  la poutrelle, la planéité du plancher.  



  Ce     dispositif    présente cependant un grand incon  vénient du fait que les poutrelles, devant résister sans  flexion sensible à la charge due au poids du plancher  en ne reposant qu'à leurs extrémités, sont     forcément     lourdes et coûteuses.

   Or, alors que le béton fait prise  en quelques jours et pourrait aussitôt être décoffré  si le plancher, qui n'a pas     encore    la     solidité    néces  saire,     restait    soutenu entre ses appuis,     il    est impos  sible de retirer les poutrelles qui le soutiennent avant  le complet     durcissement    du béton et la solidification  totale du plancher,     ce    qui demande un long délai.  



  La longue     immobilisation    des poutrelles à cha  que plancher en construction impose donc à l'entre-    preneur, quia plusieurs chantiers en exploitation,  l'obligation d'avoir en stock un grand nombre de ces  poutrelles,     ce    qui représente une mise de fonds  importante, de telle sorte que l'emploi de telles pou  trelles,     malgré    leurs     avantages,    est prohibitif pour  les entrepreneurs comme étant trop onéreux et, par  suite, peu intéressant.  



  Le présent brevet, qui vise à obvier à     ces    incon  vénients, a pour objet un     procédé    de     construction     d'un plancher en béton armé au moyen de supports  provisoires de     hourdis,    caractérisé par le fait que,  après avoir aménagé dans la longueur d'au moins  deux poutrelles.

       parallèles    au moins une interruption  de leur semelle supérieure respective     formant    le plan  de support des hourdis, ladite     interruption    étant  constituée par un     décrochement    vers le bas de ladite  semelle, on engage dans     l'espace    libre     ainsi    créé un  madrier     transversal    sous le plan de     support    des  hourdis, ledit madrier, soutenu par des     étais    de cha  que côté desdites     poutrelles;

      étant destiné à suppor  ter une partie du coffrage ou des hourdis, et qu'on  enlève d'abord les poutrelles dès la prise du béton,  le plancher     restant    soutenu par le madrier, puis on  enlève le madrier après la     solidification        complète    du  plancher.  



  Le brevet     concerne    également un dispositif     pour     la     mise    en     #uvre    de     ce        procédé.     



  Le dessin annexé représente une forme     d7exécu-          tion    et une variante du dispositif pour la mise en       #uvre    du procédé,     données    à titre d'exemple.  



  Les     fig.    1 à 3 représentent une poutrelle com  posée d'un corps principal et d'une rallonge de  moindre hauteur coulissant     télescopiquement    dans le  corps principal à l'intérieur des     extrémités    de celui-      ci, la fié. 1 étant une vue en élévation de la pou  trelle ; la     fig.    2, une coupe suivant la ligne     II-II    de  la fi-. 1, et la     fig.    3 une coupe suivant la ligne     III-          III    de la     fig.    1, montrant des     poutrelles    supportant  un plancher composé de corps creux de hourdis.  



  La     fig.    4, à une plus petite échelle, est une vue  en élévation, partiellement en coupe, dans une  variante de la forme     d'exécution    représentée aux  fi-. 1 à 3, d'une poutrelle composée de deux     corps     reliés par une rallonge, ou élément de liaison inter  médiaire, de hauteur plus petite.

      Le     dispositif,    dans la forme     d'exécution    repré  sentée aux     fig.    1 à 3, comprend une poutrelle P,  comportant à au moins l'une de -ses     extrémités    une  solution de     continuité,    de manière à former une glis  sière de guidage pour une rallonge R, de moindre  hauteur, l'une ou l'autre des     parties    de la poutrelle,  ou les deux, étant pourvue de boulons ou d'autres  moyens de serrage     destinés    à assurer leur     solidarisa-          tion.    A     cet    effet, la poutrelle P, par exemple,

       com-          porte,    entre sa semelle inférieure 1, à     section    en  forme de U, sa semelle supérieure 5 et les montants  ou diagonales     répartis    en deux jeux     2a-2b    placés  latéralement, un     vide    central     formant    glissière lon  gitudinale, dans lequel est susceptible d'être engagée  et de coulisser la rallonge R, constituée simplement  par deux semelles 3, 3', en T, et par un treillis cen  tral 4.

   La semelle supérieure 5 de la     poutrelle,    com  portant un profil     tubulaire    à face supérieure plane  pour porter le     coffrage    ou les hourdis, est pourvue  en plusieurs points de sa longueur de boulons 6  destinés à être vissés dans la semelle elle-même ou,  de     préférence,    dans des écrous 6", soudés sur les  bords de trous percés     dans    la paroi     inférieure    de la  semelle pour laisser passer     librement    les tiges des       boulons.    Les têtes 6' des boulons 6 sont     destinées     à assurer leur     manoeuvre    et à venir,

   par le dévis  sage des     boulons,    se serrer contre la semelle supé  rieure 3' de la rallonge R pour la mettre en aligne  ment avec la poutrelle et bloquer ensemble les deux       pièces.    La semelle supérieure 5 de la poutrelle P  présente une     solution    de     continuité    au voisinage du  milieu de sa longueur ou, si la poutrelle est assez  longue, en des     points        convenablement    espacés.

   Cette  solution de continuité est     destinée    à aménager un  intervalle vide au-dessus d'une     portion    p, de moin  dre hauteur, de la poutrelle P, de     manière    à pouvoir  introduire     dans    cet intervalle un madrier transver  sal M, reposant sur la partie     abaissée    p et affleurant  au niveau des faces supérieures des semelles 5,  comme représenté à la     fig.    1.

   Le madrier M est  ensuite     étayé,    latéralement à la poutrelle P, par un       support    E avant d'entreprendre l'enlèvement de la  dite poutrelle, le madrier restant étayé jusqu'à la       solidification    complète du plancher. La     différence     de niveau entre le plan de coffrage et la rallonge R,  suspendue par un fer coudé T à la planche de rive  correspondante, est susceptible d'être rattrapée éga  lement par des madriers.    La     fig.    3 montre la disposition d'ensemble de  corps creux de     hourdis    portés par une série de pou  trelles P et un madrier transversal M étayé en E.  



  Dans une variante à la     forme    d'exécution décrite.  la poutrelle P, dans le cas de grandes     portées,    est  composée de plusieurs éléments, à savoir deux corps  principaux P1, P2     (fig.    4) réunis entre eux et     ajus-          tables    en longueur par une rallonge L intermé  diaire, semblable ou analogue à la rallonge R décrite  ci-dessus. Les deux corps principaux Pl et P2 pré  sentent dans toute leur longueur, ou au voisinage de  leurs extrémités, des organes formant des glissières  longitudinales.

   La hauteur de la rallonge L de liaison  est plus     petite    que celle des corps P1 et P2, de  manière à ménager un espace vide     au-dessus    de la  dite rallonge lorsqu'elle est engagée dans les glissiè  res des corps P1 et P2, ledit espace vide étant des  tiné au passage d'un madrier M' transversal de sou  tien, reposant sur la semelle supérieure de la ral  longe L.  



  Dans le cas où l'intervalle entre les deux     corps     principaux P1 et P2 est supérieur à la largeur du  madrier M', on dispose à côté de     celui-ci    un ou deux       madriers    supplémentaires, tels que les madriers m  et      i    , qu'on enlève en même temps que les corps  P1 et P2, dès la prise du béton.



  Method of constructing a reinforced concrete floor by means of provisional slab supports and device for implementing the process The present patent relates to a method of constructing a reinforced concrete floor by means of temporary slab supports and a device for carrying out the method.



  For the construction of reinforced concrete floors, all-wooden formwork is generally used. The correct positioning of the formwork and its numerous props to obtain that all the parts of the surface remain in the same horizontal plane requires multiple adjustments and is a long and delicate operation. To avoid these difficulties, metal bins are currently used, consisting of a single body or of a main body with one or two extensions sliding telescopically in the main body.

   The upper flanges of these rec tilinear joists, hung on the edge boards attached to the walls and other supports of the spans, constitute the supports of the formwork or the prefabricated slabs thus achieving, by the very fact of the rigidity of the joist, the flatness from the floor.



  However, this device has a major drawback owing to the fact that the beams, having to resist without significant bending to the load due to the weight of the floor by resting only at their ends, are necessarily heavy and expensive.

   However, while the concrete sets in a few days and could immediately be stripped if the floor, which does not yet have the necessary solidity, remained supported between its supports, it is impossible to remove the joists which support it before complete hardening of the concrete and total solidification of the floor, which takes a long time.



  The long immobilization of the joists on each floor under construction therefore imposes on the contractor, who has several sites in operation, the obligation to have a large number of these joists in stock, which represents a significant capital outlay, so that the use of such waste bins, despite their advantages, is prohibitive for contractors as being too expensive and, consequently, unattractive.



  The present patent, which aims to obviate these drawbacks, relates to a method of constructing a reinforced concrete floor by means of temporary slab supports, characterized in that, after having arranged in the length of at minus two joists.

       parallel at least one interruption of their respective upper flange forming the support plane of the slabs, said interruption being constituted by a recess towards the bottom of said sole, a transverse plank is engaged in the free space thus created under the support plane of the slabs, said plank, supported by props on each side of said joists;

      being intended to support part of the formwork or slabs, and that first the joists are removed as soon as the concrete sets, the floor remaining supported by the plank, then the plank is removed after the complete solidification of the floor.



  The patent also relates to a device for carrying out this process.



  The accompanying drawing shows an embodiment and a variant of the device for carrying out the method, given by way of example.



  Figs. 1 to 3 show a beam com posed of a main body and an extension of lesser height sliding telescopically in the main body inside the ends thereof, the fié. 1 being an elevational view of the bin; fig. 2, a section along the line II-II of the fi. 1, and fig. 3 a section along the line III-III of FIG. 1, showing joists supporting a floor made up of hollow slabs.



  Fig. 4, on a smaller scale, is an elevational view, partially in section, in a variant of the embodiment shown in FIGS. 1 to 3, a beam composed of two bodies connected by an extension, or intermediate connecting element, of smaller height.

      The device, in the embodiment shown in FIGS. 1 to 3, comprises a beam P, comprising at least one of its ends a solution of continuity, so as to form a guide slide for an extension R, of less height, one or the other parts of the beam, or both, being provided with bolts or other tightening means intended to secure their connection. For this purpose, the beam P, for example,

       has, between its lower sole 1, with a U-shaped section, its upper sole 5 and the uprights or diagonals distributed in two sets 2a-2b placed laterally, a central void forming a longitudinal slide, in which is capable of be engaged and slide the extension R, consisting simply of two flanges 3, 3 ', T, and a central trellis 4.

   The upper flange 5 of the beam, comprising a tubular profile with a flat upper face to support the formwork or the slabs, is provided at several points along its length with bolts 6 intended to be screwed into the flange itself or, preferably , in 6 "nuts, welded to the edges of holes drilled in the bottom wall of the sole to allow the bolt shanks to pass freely. The heads 6 'of the bolts 6 are intended to ensure their operation and to come,

   by carefully unscrewing the bolts, tighten against the upper flange 3 'of the extension R to align it with the joist and lock the two parts together. The upper flange 5 of the beam P has a solution of continuity in the vicinity of the middle of its length or, if the beam is long enough, at suitably spaced points.

   This solution of continuity is intended to create an empty gap above a portion p, of less height, of the beam P, so as to be able to introduce into this gap a transverse plank M, resting on the lowered part p and flush with the upper faces of the flanges 5, as shown in FIG. 1.

   The beam M is then supported, laterally to the beam P, by a support E before starting to remove the said beam, the beam remaining supported until the complete solidification of the floor. The difference in level between the formwork plane and the extension R, suspended by an angled iron T to the corresponding edge board, can also be taken up by planks. Fig. 3 shows the overall arrangement of hollow slab bodies carried by a series of P trellis and a transverse plank M supported at E.



  In a variant of the embodiment described. the beam P, in the case of large spans, is made up of several elements, namely two main bodies P1, P2 (fig. 4) joined together and adjustable in length by an intermediate extension L, similar or similar to the extension R described above. The two main bodies P1 and P2 present throughout their length, or in the vicinity of their ends, members forming longitudinal slides.

   The height of the connecting extension L is smaller than that of the bodies P1 and P2, so as to leave an empty space above said extension when it is engaged in the slides of the bodies P1 and P2, said space empty being tined by the passage of a transverse support plank M ', resting on the upper flange of the lanyard L.



  In the event that the interval between the two main bodies P1 and P2 is greater than the width of the plank M ', one or two additional planks, such as the planks m and i, are placed next to it. removes at the same time as the bodies P1 and P2, as soon as the concrete sets.

 

Claims (1)

REVENDICATIONS 1. Procédé de construction d'un plancher en béton armé au moyen de supports provisoires de hourdis, caractérisé par le fait que, après avoir aménagé dans la longueur d'au moins deux poutrel les parallèles au moins une interruption de leur semelle supérieure respective formant le plan de sup port des hourdis, ladite interruption étant constituée par un décrochement vers le bas de ladite semelle, on engage dans l'espace libre ainsi créé un madrier transversal sous le plan de support des hourdis, ledit madrier, soutenu par des étais de chaque côté des- dites poutrelles, CLAIMS 1. A method of constructing a reinforced concrete floor by means of temporary slab supports, characterized in that, after having arranged in the length of at least two joists the parallels at least one interruption of their respective upper flange forming the supporting plane of the slabs, said interruption being constituted by a recess towards the bottom of said sole, a transverse plank is engaged in the free space thus created under the supporting plane of the slabs, said plank, supported by props on each side of said beams, étant destiné à supporter une partie du coffrage ou des hourdis, et qu'on enlève d'abord les poutrelles dès la prise du béton, le plancher res tant soutenu par le madrier, puis on enlève le madrier après la solidification complète du plancher. Il. Dispositif pour la mise en oeuvre du procédé selon la revendication I, caractérisé par le fait qu'il comprend une poutrelle de support provisoire dont la partie supérieure est interrompue, l'espace vide ainsi formé sous le plan de support des hourdis étant destiné à loger au moins un madrier transversal, ledit madrier étant étayé par au moins un support sur le côté de la poutrelle. SOUS-REVENDICATIONS 1. being intended to support part of the formwork or slabs, and that first the joists are removed as soon as the concrete sets, the floor being supported by the plank, then the plank is removed after the complete solidification of the floor. He. Device for carrying out the method according to Claim I, characterized in that it comprises a temporary support beam, the upper part of which is interrupted, the empty space thus formed under the support plane of the slabs being intended to accommodate at least one transverse plank, said plank being supported by at least one support on the side of the joist. SUB-CLAIMS 1. Dispositif selon la revendication II, caractérisé par le fait que la poutrelle destinée à former le sup port provisoire du coffrage ou des hourdis comporte au moins un décrochement vers le bas, ledit décro chement étant obtenu par l'interruption de la mem brure supérieure de la poutrelle au niveau du plan de support, un espace vide étant ménagé au-dessous dudit niveau pour le passage d'au moins un madrier transversal. 2. Device according to Claim II, characterized in that the beam intended to form the temporary support of the shuttering or slabs comprises at least one downward step, said step being obtained by interrupting the upper member of the beam. joist at the level of the support plane, an empty space being provided below said level for the passage of at least one transverse plank. 2. Dispositif selon la revendication 11, caractérisé par le fait qu'il comprend deux corps principaux de poutrelles et une rallonge intermédiaire de liaison, ladite rallonge présentant une hauteur plus petite que celle desdits corps, ces trois éléments étant blo qués ensemble par un moyen de fixation, l'espace vide étant ménagé entre les deux corps principaux et au-dessus de la rallonge intermédiaire pour le passage d'au moins un madrier transversal. Device according to Claim 11, characterized in that it comprises two main bodies of beams and an intermediate connecting extension, said extension having a height smaller than that of said bodies, these three elements being blocked together by a fixing means , the empty space being provided between the two main bodies and above the intermediate extension for the passage of at least one transverse plank.
CH359270D 1959-02-13 1960-04-09 Method of constructing a reinforced concrete floor by means of temporary slab supports and device for implementing the method CH359270A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FR6394A FR1216705A (en) 1959-02-13 1959-02-13 Improvements to metal joists serving as formwork in the construction of reinforced concrete floors, and methods for their use

Publications (1)

Publication Number Publication Date
CH359270A true CH359270A (en) 1961-12-31

Family

ID=8571473

Family Applications (1)

Application Number Title Priority Date Filing Date
CH359270D CH359270A (en) 1959-02-13 1960-04-09 Method of constructing a reinforced concrete floor by means of temporary slab supports and device for implementing the method

Country Status (7)

Country Link
AT (1) AT245767B (en)
BE (1) BE587599A (en)
CH (1) CH359270A (en)
ES (1) ES255727A1 (en)
FR (2) FR1216705A (en)
GB (1) GB941801A (en)
MC (1) MC196A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112342930B (en) * 2020-12-11 2022-03-11 山西建筑工程集团有限公司 PC component superimposed sheet bailey frame braced system device

Also Published As

Publication number Publication date
GB941801A (en) 1963-11-13
BE587599A (en) 1960-05-30
AT245767B (en) 1966-03-10
ES255727A1 (en) 1960-10-01
MC196A1 (en) 1960-09-08
FR1216705A (en) 1960-04-27
FR75612E (en) 1961-11-27

Similar Documents

Publication Publication Date Title
CA2017930A1 (en) Prefabricated concrete form units and wall building process
CH616197A5 (en)
FR2664319A1 (en) Shuttering device comprising panels, and connection pieces for assembling these panels
FR2962143A1 (en) PREFABRICATED STAIRCASE IN CONCRETE WITH MODULAR RACK
EP0511921A1 (en) Modular supporting system for floor forms; method and form using this system
FR2620153A1 (en) CONSTRUCTION PANEL, ESPECIALLY CLADDING PANEL, WITH INTEGRATED THERMAL INSULATION
CH359270A (en) Method of constructing a reinforced concrete floor by means of temporary slab supports and device for implementing the method
FR2542030A1 (en) Method for reinforcing roof framings having trusses in the creation of habitable roof spaces
FR2760482A1 (en) Shuttering for the formation of concrete slabs or floors using a modular, load bearing system
EP0165856A1 (en) Set of building elements for the erection of walls by post-tensioning
FR2900672A1 (en) Dwelling module for forming e.g. prefabricated single-family house, has base constituted of reinforced concrete slab, where slab has lower surface including connection beams extending from one side to another side of retaining beam
FR2621340A1 (en) Metal frame
CH678440A5 (en) Concrete floor laying system - using steel G-shaped clips and reinforcing rods to engage laid concrete with timber floor beams
BE843363A (en) PROCEDURE AND DEVICE FOR THE RENOVATION OF BUILDINGS BY CASTING CONCRETE SLABS ON EXISTING FLOORS
FR2567182A1 (en) Method for converting a truss and means for implementing this method
OA19773A (en) Early release formwork system for solid slabs.
BE497281A (en)
CH132238A (en) Cement concrete floor-ceiling, and method of carrying it out.
EP3467224A1 (en) Calliper formed by two half-callipers provided with nestable male and female arms
BE843882R (en) PROCESS FOR CONSTRUCTION OF A BRIDGE WITH A MIXED STEEL AND CONCRETE STRUCTURE DECK
FR2616827A1 (en) Shuttering system for concrete floors
BE502215A (en)
BE510147A (en)
FR2568297A1 (en) METAL FORMWORK AND METHOD FOR CASTING A LARGE CONCRETE RESERVOIR USING SUCH FORMWORK
CH409342A (en) Scaffolding