US3226933A - Sheeting wall system and method of constructing same - Google Patents

Sheeting wall system and method of constructing same Download PDF

Info

Publication number
US3226933A
US3226933A US96980A US9698061A US3226933A US 3226933 A US3226933 A US 3226933A US 96980 A US96980 A US 96980A US 9698061 A US9698061 A US 9698061A US 3226933 A US3226933 A US 3226933A
Authority
US
United States
Prior art keywords
wall
rock
overburden
sheeting
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US96980A
Inventor
Robert E White
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Spencer White and Prentis Inc
Original Assignee
Spencer White and Prentis Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Spencer White and Prentis Inc filed Critical Spencer White and Prentis Inc
Priority to US96980A priority Critical patent/US3226933A/en
Application granted granted Critical
Publication of US3226933A publication Critical patent/US3226933A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/48Foundations inserted underneath existing buildings or constructions

Definitions

  • braces deprive the builder of complete and iinhindered access to maneuver within the excavated area.
  • The'internal braces of the prior art are exposed to certain hazards which are very real and which create safety hazards and hindrances.
  • Internal braces are often knocked out or damaged by careless operation of construction equipment or other phases of construction work such as blasting. If a brace is knocked out or damaged, a section of the sheeting wall may collapse or, at least, bulge out and create a hazardous condition.
  • equipment must be moved ice resistance of the earth along the shear plane and, thus, the present invention is more eifective than internal bracing in preventing the start of possible movement of the overburden.
  • FIGURE 1 is a front view of a portion of a sheeting wall 'in accordance with the present invention.
  • FIGURE 2 is a schematic view of the first stage in the construction of the wall
  • FIGURE 3 is a schematic View of the second stage in the construction of the wall
  • FIGURE 4 is a schematic view of the third stage in the construction of the wall
  • FIGURE 5 is a schematic view of the fourth stage in the construction of the wall
  • FIGURE 6 is a sectional view of the wall of FIGURE 1 along lines 6-6;
  • FIGURE 7 is an enlarged fragmentary front view of the wale and soldier beam arrangement of the wall shown in FIGURE l looking downwardly at a 45 angle;
  • FIGURE 8 is a fragmentary side view of a portion of the wall showing another embodiment of the soldier beam, wale and anchor head arrangement;
  • FIGURE 9 is a sectional View of the embodiment of FIGURE 8 along lines 99;
  • braces are made ofst'eel and it has a greater r tensile than compressive strength less material is required for tendons than is required for braces.
  • FIGURE 10 is a sectional view of an embodiment of an anchor head for holding a tie-back which is comprised of several wires of high tensile strength;
  • FIGURE 11 is a sectional view of a rock anchor for the'tie-backs of FIGURE 10;
  • FIGURE 12 is a sectional view of an embodiment of an anchor head for holding a tie-back which is comprised of a solid high tensile strength rod;
  • FIGURE 13 is a sectional view of an underpinning 'wall witha tie-back construction
  • FIGURE 14 is a view of the wall of FIGURE 13 along lines 14'14 of FIGURE 13;
  • FIGURE. 15a is a sectional view of a rock socket with a mechanical type of anchor therein;
  • FIGURE 15 is a View similar to FIGURE 15a with a grouted anchor
  • FIGURE is a View similar to FIGURE 15a with another type of grouted anchor.
  • FIGURE 1501 is a view similar to FIGURE 15a with stillanother type of grouted anchor.
  • the method of construction of the present invention In FIGURE 1, a complete sheeting Wall 10 is shown whichhasbeen constructed without the necessity of internal braces.
  • the soldier beams 12 are driven into the ground along the desired line of the sheeting Wall.
  • the soldier beams 12 usually are wide flange or bearing pile steel piling members having a cross-sectional area such as shown in FIGURE 9, but other suitable construction materials such as Wood or concrete may also be used. The or boring, and in the case of concrete by pouring.
  • the present invention is not limited to sheeting Walls of the type wherein wood sheeting is used as the covering material. It is also contemplated thatinterlocking sheet steel piling may be used as a combination piling and sheeting material. In addition, the present invention is also applicable to the underpinning of adjacent structures during excavation operations.
  • the soldier beams 12 are first driven to refusal and if the rocker layer R which underlies the earth overburden G is close to the surface, the beams will become seated thereon. As shown in FIGURE 2, with the soldier beams 12 in place, the overburden G is excavated to an elevation where a safe berm of earth still remains outside the line of soldier beams 12. If necessary, sheeting pieces 14 may be advantageously placed horizontally joined to adjacent soldier beams 12 at this time to insure that the unexcavated overburden holds during further operations.
  • each casing 16 being oriented at an angle of about 45 with the horizontal.
  • the casings are placed by any conventional means such as jetting, drilling, etc., until the driving end of the casing becomes seated on the rock layer R.
  • rock sockets 18 are drilled in the layer R, each socket being substantially in line and extensive from the end of the casing 16.
  • These sockets may be drilled by any suitable means, such as percussion, rotary or diamond drills which are well known in the art.
  • mechanical anchors such as cone type wedges may be used in place of the grouted anchors.
  • Such mechanical anchors are usually more expensive than the grouted type and in some cases they may take longer to place.
  • a wale 26 On which is placed anchor heads 28 for holding each tendon 22.
  • the head 28 becomes spaced from the wale 26 due to the elongation of the tendons by the applied load. This spacing of the head from the wale is maintained by means of spacer plates 30 so that the final applied load is constant.
  • the sheeting wall structure which is obtained by the method of the present invention may be best understood by a reference to FIGURES l and 6-11 and the particular structure illustrated therein.
  • the wall comprises a frame of vertically aligned soldier beams 12 driven to refusal and at least one row of wales 26 directed substantially horizontally and connected to the soldier beams 12, a series of tendons 22 in the form of tie-backs anchored beyond the line of beams 12 and maintained under a high tensile load, and sheeting 14 horizontally positioned and aflixed to the frame of soldier beams 12 and Wales.
  • the tie-backs or tendons 22 of the illustrated structure olfer no interference with work operations being conducted in the excavated area. This is particularly advantageous in a case where a building or. a similar structure is to be built on a limited plot of land in a crowded city or industrial area. If the building is to abut against existing structures care must be taken to insure that such structures are not disturbed by the excavation.
  • an existing structure 60 is adjacent to a building 62 which is to extend below the elevation of the structure 60.
  • the piers 66 are held in place during construction of the building 62 by means of a series of tendons 68.
  • Each tendon 68 is anchored in a rock socket 70 by a suitable anchor and also connected to an anchor head 72 mounted on the pier 66.
  • Each tendon 68 is elongated and posttensioned as described previously.
  • sheeting 74 is provided between the piers 66 to hold back the overburden beneath the existing structure 66; or a continuous underpinning wall may be providing eliminating the necessity of sheeting between the piers.
  • the bank driven tie-backs or tendons leave the excavated area substantially clear and no unnecessary loss of building space need occur.
  • the tie-backs or tendons 22 may be composed of a number of high tensile strength wires or a single high tensile strength rod. When a number of wires are to be used the tie-back may be of the type shown in FIG- URES l0 and 11.
  • a grout pipe 32 with an anchor 20 mounted near the end thereof is placed in the casing. Attached to the anchor 20 is a series of high tensile strength wires 34.
  • the grout pipe 32 is extended to the bottom of the rock socket 18 and the anchor 20 and wires 34 are carried along with it.
  • the grout pipe 32 may be in lengths of twenty feet, each length being connected to the preceding one as required.
  • Water is flushed through the pipe 32, which has an angularly cut end or any other suitable construction which permits ease in placing the grout, until the water runs from the top of the casing 16 in a clear condition free of dirt.
  • the supply of water is then shut off and the Water in the casing and socket is allowed to settle and seek its own level. In some cases the use of water may not be necessary and it will be sufiicient to use high pressure air which may be blown into the socket.
  • Grout 24 is then pumped through the grout pipe 32 and into the rock socket 18.
  • the amount of grout 24 used for each tie-back should be sufficient to fill the rock socket 18, the grout pipe 32 and about 3 to 7 feet of the casing 16 above the rock socket 18. By placing at least this amount of grout in the socket 18, pipe 32 and casing 16, the anchor 20 is firmly and securely held in place.
  • the grout is allowed to set until the desired minimum strength is obtained before the wires 34, which had been drawn taut before grouting, are post-tensioned.
  • the posttensioning is accomplished by jacking the wires 34 against the wale 26.
  • the wale 26 is comprised of a pair of steel channel members 36 spaced back to back to permit the wires 34 and the grout pipe 32 to be inserted between them.
  • the channels 36 are advantageously positioned so that the webs 38 are parallel to the line on which the casings 16 are driven and may serve as a guide when the casings are inserted.
  • the wales 26 may be of any desired shape, such as I-beams, wide flange members, built up sections, angles, channels and such; and they may be at an angle or horizontally directed.
  • a short bracket 40 together with a top bearing plate 42 is welded to each soldier beam 12.
  • the channels 36 are set on the plates 42 and held in place by tack welding the flange of each channel 36 to the plates.
  • the anchor head 28 In jacking the wires 34 the anchor head 28 is drawn away from the wale 26 until a load in excess of the final post-tension load is achieved. As discussed previously, this excess load is held for about ten minutes and then the load is reduced to the desired amount. At this time the anchor head 28 will be spaced from the wale since elongation of the wires 34 takes place during the loading operation.
  • spacer plates 30 are inserted between the anchor head 28 and the wale 26.
  • a spreader plate 44 may also advantageously be placed between the spacer 30 and the Wale 26 so that the load is distributed over a greater portion of the channels 36.
  • every third soldier beam 50 is a master beam comprised of two heavy channels spaced apart a short amount, sufiicient to permit the casing 16 and the solid tendon 52 to be inserted therethrough.
  • the remaining soldier beams 12 are similar to those described previously.
  • the solid tendon 52 is passed through a casing 16 and grouted in place as described previously.
  • the wale construction and anchor head are different.
  • the wale 54 is mounted by its flange directly to the flanges of the channels of the master beam 50.
  • Welded above the Wale 54 and to the master beam 50 is an anchor bearing piece 56.
  • the bearing piece 56 is comprised of a built up angle section through which the solid tendon 52 extends.
  • the upper end of the tendon 52 in the illustrated embodiment, is threaded and a heavy duty nut 58 is placed thereon. In order to posttension the tendon 52 the nut 58 is tightened against the bearing piece 56 to control means such as a torque wrench.
  • the braces are in compression while the tendons of the present invention are in tension. Since higher design stresses are permitted with tension members than with compression members, the size of the tendons is reduced compared to a brace which carries the same equivalent load as the tendon. In addition, long braces must be supported by secondary bracing or the design load must be sharply reduced. Accordingly, the, present invention not only aids the builder during construction, but it also assists the designer by allowing him greater latitude since the allowable stresses are greater.
  • FIGURES 15a-d four additional anchors are shown.
  • FIGURE 15a a mechanical anchor 76 is illustrated which is comprised of a cone and wedge combination of the expansion type.
  • the rock socket has an oversize lower section 78 which is carefully drilled.
  • the anchor 76 is afiixed to the tendon 22 and inserted into the lower section 78.
  • the anchor 76 is comprised of a cone 80 fitted into split wedges 82 which mate with the surface of the cone 80.
  • the cone 80 spreads the wedges apart and presses them into tight locking engagement with the walls of the lower socket section 78.
  • the time to drill the section 78 and the cost of the cone and wedge combination have to be carefully considered before using this type of anchor in place of a grouted anchor.
  • FIG- URES 15b Some additional grouted anchors are shown in FIG- URES 15b, 0 and d.
  • FIGURE 15b a simple Series of parallel strands 84 are shown.
  • FIGURE 15c a series of wire tendons 86 are shown which are woven under and over a series of rings 88.
  • the open structure about the rings provides very high holding power when the rock socket is filled with grout.
  • FIGURE 15d a series of wire tendons90 are shown which have been twisted together to provide additional bond surface and added holding power.
  • buttons and nut and washer combinations may also be used.
  • the tendons may also be of various kinds. Besides solid rods and wires, the tendons may be of strand, i.e. a series of wires twisted about a larger center wire, or of cable.
  • a rock anchored wall structure and an undisturbed and in place overburden which overlies a rock layer said overburden substantially compressed by the structure, said structure comprising a retaining wall, anchors set in rock sockets in the rock layer beneath the undisturbed overburden, connecting means extending from the wall downwardly at an angle through the overburden to the rock layer post-tensioned tendons inserted through the connecting means and joined to the anchors and to the wall whereby the undisturbed overburden is compressed and maintained in place without any bracing of the Wall on the side of the wall opposite the rock anchors.
  • a rock anchored Wall structure an undisturbed and in place overburden which overlies a rock layer as defined in claim 1 wherein the connecting means is comprised or a casing member.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Description

Jan. 4, 1966 E. WHITE 3,226,933
I SHEETING WALL SYSTEM AND METHOD OF CONSTRUGTING SAME Filed March 20, l96l 5 Sheets-Sheet 1 Fig.l
INVENTOR. Robert E. White F i g 3 law/vb, :QSfl/d ATTORNEYS NALL SYSTEM AND METHOD OF CONSTRUCTING SAME R. E. WHITE Jan. 4, 1966 SHEETING Filed March 20, 1961 5 Sheets-Sheet 2 il n II In Fig.7
INVENTOR. Robeq'r E. White ATTORNEYS R. E. WHITE Jan. 4, 1966 SHEETING WALL SYSTEM AND METHOD OF CONSTRUC'IING SAME 5 Sheets-Sheet 5 Filed March 20, 1961 INVENTOR.
Robert E. White F i q. 9
ATTOR NE YS R. E. WHITE Jan. 4, 1966 SHEETING WALL SYSTEM AND METHOD OF CONSTRUCTING SAME Filed March 20, 1961.
5 Sheets-Sheet 4 Fig.lO
INVENTOR. Robert E. White BY @ar/g Adair/5L, gfimf A TTOR N E YS Illlllllll R. E. WHITE Jan. 4, 1966 SHEE'I'ING WALL SYSTEM AND METHOD OF CONSTRUCTING SAME Filed March 20, 1961 5 Sheets-Sheet 5 Fig.l5b
Fig.l4
INVENTOR. Robert E. White BY Card/9' Msrni, 755146 ATTORNEYS United. States Patent 3,226,933 1 SHEETING WALL SYSTEM AND METHOD OF CONSTRUCTING SAME Robert E. White, Larchmont, N.Y., assignor to Spencer, White and Prentis, Inc., New York, N.Y., a corporation of New York Filed Mar. 20, 1961, Ser. No. 96,980 7 Claims. (Cl. 6139) This invention relates to a sheeting wall system and to a method of forming such. a wall, and particularly to a wall system foruse in retaining the banks of excavated areas. Y In the construction of large buildings and other such.
structures, it is generally necessary to excavate to a substantial depth to permit large foundations and/or the below ground level portion of the building or structure to be constructed. When excavations are made in normal types of earth such as sand,\clay, gravel or combinations of these as' is usually the case), the banks of the excavated area tend to shear off along sloping planes of rupture, the exact angle of slope being dependent upon the nature and composition of the excavated material.
Engineers have attempted to prevent'the shearing off of the excavated banks in many ways. The usual means employed heretofore has been to provide sheeting walls which are shored up by angularly or horizontally directed braces placed within the excavated area, and which will be referred to as internal bracings since they are located within the excavated area. Such internally braced walls have' many disadvantages and shortcomings. Not the least of these is the interference of the braces with the various phases of construction work in the excavated are'a. l I r I Among the phases of construction work which are interfered with are: excavation, form work, concreting, placing of reinforcing steel, waterproofing, placing of mechanical equipment and conduits, andlike operations. Also, the use of large prefabricated panel sections and r similar modular systems cannot be economically used where internal braces deprive the builder of complete and iinhindered access to maneuver within the excavated area. The'internal braces of the prior art are exposed to certain hazards which are very real and which create safety hazards and hindrances. Internal braces are often knocked out or damaged by careless operation of construction equipment or other phases of construction work such as blasting. If a brace is knocked out or damaged, a section of the sheeting wall may collapse or, at least, bulge out and create a hazardous condition. In order to avoid damaging the braces, equipment must be moved ice resistance of the earth along the shear plane and, thus, the present invention is more eifective than internal bracing in preventing the start of possible movement of the overburden.
Accordingly, it is an object of the present invention to provide a sheeting wall system which is economical to install and practical to use in actual construction operatons.
In the drawings:
FIGURE 1 is a front view of a portion of a sheeting wall 'in accordance with the present invention;
FIGURE 2 is a schematic view of the first stage in the construction of the wall;
FIGURE 3 is a schematic View of the second stage in the construction of the wall;
FIGURE 4 is a schematic view of the third stage in the construction of the wall;
FIGURE 5 is a schematic view of the fourth stage in the construction of the wall;
FIGURE 6 is a sectional view of the wall of FIGURE 1 along lines 6-6;
FIGURE 7 is an enlarged fragmentary front view of the wale and soldier beam arrangement of the wall shown in FIGURE l looking downwardly at a 45 angle;
FIGURE 8 is a fragmentary side view of a portion of the wall showing another embodiment of the soldier beam, wale and anchor head arrangement;
FIGURE 9 is a sectional View of the embodiment of FIGURE 8 along lines 99;
may best be understood by referring to the drawings.
Since most braces are made ofst'eel and it has a greater r tensile than compressive strength less material is required for tendons than is required for braces.
" The post-tensioning of the tie-backs or tendons compresses the overburden and places substantial passive pres sure on the sliding or shearing surface or plane of the earth overburden held back by the Wall. Normally the wedge of earth between the sliding planeand the wall would tend to slide into the excavation. The pressure induced by the post-tensioning mobilizes the shearing pilings may be placed by driving, drilling FIGURE 10 is a sectional view of an embodiment of an anchor head for holding a tie-back which is comprised of several wires of high tensile strength;
FIGURE 11 is a sectional view of a rock anchor for the'tie-backs of FIGURE 10;
FIGURE 12 'is a sectional view of an embodiment of an anchor head for holding a tie-back which is comprised of a solid high tensile strength rod;
FIGURE 13 is a sectional view of an underpinning 'wall witha tie-back construction;
FIGURE 14 is a view of the wall of FIGURE 13 along lines 14'14 of FIGURE 13;
FIGURE. 15a is a sectional view of a rock socket with a mechanical type of anchor therein;
FIGURE 15]) is a View similar to FIGURE 15a with a grouted anchor;
FIGURE is a View similar to FIGURE 15a with another type of grouted anchor; and
FIGURE 1501 is a view similar to FIGURE 15a with stillanother type of grouted anchor. The method of construction of the present invention In FIGURE 1, a complete sheeting Wall 10 is shown whichhasbeen constructed without the necessity of internal braces.
To construct the sheeting Wall 10 of FIGURE 1, a series of soldier beams 12 are driven into the ground along the desired line of the sheeting Wall. The soldier beams 12 usually are wide flange or bearing pile steel piling members having a cross-sectional area such as shown in FIGURE 9, but other suitable construction materials such as Wood or concrete may also be used. The or boring, and in the case of concrete by pouring.
It is to be understood that the present invention is not limited to sheeting Walls of the type wherein wood sheeting is used as the covering material. It is also contemplated thatinterlocking sheet steel piling may be used as a combination piling and sheeting material. In addition, the present invention is also applicable to the underpinning of adjacent structures during excavation operations.
Since the present invention is preferably used where there is a rock layer R not too far below ground level, the soldier beams 12 are first driven to refusal and if the rocker layer R which underlies the earth overburden G is close to the surface, the beams will become seated thereon. As shown in FIGURE 2, with the soldier beams 12 in place, the overburden G is excavated to an elevation where a safe berm of earth still remains outside the line of soldier beams 12. If necessary, sheeting pieces 14 may be advantageously placed horizontally joined to adjacent soldier beams 12 at this time to insure that the unexcavated overburden holds during further operations.
With the soldier beams 12 in place and the overburden sheeted, a series of casings or pipes 16 are then driven into the overburden G, each casing 16 being oriented at an angle of about 45 with the horizontal. The casings are placed by any conventional means such as jetting, drilling, etc., until the driving end of the casing becomes seated on the rock layer R.
With the casings 16 seated on the rock layer, rock sockets 18 are drilled in the layer R, each socket being substantially in line and extensive from the end of the casing 16. These sockets may be drilled by any suitable means, such as percussion, rotary or diamond drills which are well known in the art.
With the sockets 18 prepared anchors 20 are then placed therein with high strength tendons 22 attached thereto. Grout 24 is next introduced into the rock sockets and the anchors 20 are fixed in place. The grout 24 is permitted sufiieient time to set and harden, about three days or longer, before any considerabel load is put on the tendons 22. To insure proper anchorage, a test load substantially greater than the final load is first placed on the tendons before final post-tensioning. For example, where a load of 133,000 pounds is to be finally placed on a tendon 22, an initial load of 200,000 pounds is first applied for about ten minutes before the load is reduced to 133,000.
If desired mechanical anchors such as cone type wedges may be used in place of the grouted anchors. Such mechanical anchors are usually more expensive than the grouted type and in some cases they may take longer to place.
Horizontally mounted on the soldier beams 12 and along the line of intersection between the casings 16 and the solder beams 12 is a wale 26 on which is placed anchor heads 28 for holding each tendon 22. When the final desired load is placed on the tendons 22, the head 28 becomes spaced from the wale 26 due to the elongation of the tendons by the applied load. This spacing of the head from the wale is maintained by means of spacer plates 30 so that the final applied load is constant.
Further excavation and sheeting between the soldier beams 12 may now continue. As shown in FIGURE 1, if the depth of the excation is very great additional lines of tie-backs may be provided at lower elevations if required.
The sheeting wall structure which is obtained by the method of the present invention may be best understood by a reference to FIGURES l and 6-11 and the particular structure illustrated therein. The wall comprises a frame of vertically aligned soldier beams 12 driven to refusal and at least one row of wales 26 directed substantially horizontally and connected to the soldier beams 12, a series of tendons 22 in the form of tie-backs anchored beyond the line of beams 12 and maintained under a high tensile load, and sheeting 14 horizontally positioned and aflixed to the frame of soldier beams 12 and Wales.
The tie-backs or tendons 22 of the illustrated structure olfer no interference with work operations being conducted in the excavated area. This is particularly advantageous in a case where a building or. a similar structure is to be built on a limited plot of land in a crowded city or industrial area. If the building is to abut against existing structures care must be taken to insure that such structures are not disturbed by the excavation.
As stated previously the present invention is also applicable to underpinning adjacent structures during excavation operations. As shown in FIGURES 13 and 14 an existing structure 60 is adjacent to a building 62 which is to extend below the elevation of the structure 60. Beneath the bottom of the footings 64 of the existinng structure 60 a series of underpinning piers 66 are placed. These piers 66 rest on the rock layer R in much the same manner as the soldier beams 12.
The piers 66 are held in place during construction of the building 62 by means of a series of tendons 68. Each tendon 68 is anchored in a rock socket 70 by a suitable anchor and also connected to an anchor head 72 mounted on the pier 66. Each tendon 68 is elongated and posttensioned as described previously.
If desired, sheeting 74 is provided between the piers 66 to hold back the overburden beneath the existing structure 66; or a continuous underpinning wall may be providing eliminating the necessity of sheeting between the piers.
With the present invention the bank driven tie-backs or tendons leave the excavated area substantially clear and no unnecessary loss of building space need occur.
The tie-backs or tendons 22 may be composed of a number of high tensile strength wires or a single high tensile strength rod. When a number of wires are to be used the tie-back may be of the type shown in FIG- URES l0 and 11.
Referring to FIGURES l0 and 11, after the soldier beams 12 are driven, the casing 16 is in place and the rock socket 18 is drilled, a grout pipe 32 with an anchor 20 mounted near the end thereof is placed in the casing. Attached to the anchor 20 is a series of high tensile strength wires 34. The grout pipe 32 is extended to the bottom of the rock socket 18 and the anchor 20 and wires 34 are carried along with it. For convenience in installation, the grout pipe 32 may be in lengths of twenty feet, each length being connected to the preceding one as required.
Water is flushed through the pipe 32, which has an angularly cut end or any other suitable construction which permits ease in placing the grout, until the water runs from the top of the casing 16 in a clear condition free of dirt. The supply of water is then shut off and the Water in the casing and socket is allowed to settle and seek its own level. In some cases the use of water may not be necessary and it will be sufiicient to use high pressure air which may be blown into the socket.
Grout 24 is then pumped through the grout pipe 32 and into the rock socket 18. The amount of grout 24 used for each tie-back should be sufficient to fill the rock socket 18, the grout pipe 32 and about 3 to 7 feet of the casing 16 above the rock socket 18. By placing at least this amount of grout in the socket 18, pipe 32 and casing 16, the anchor 20 is firmly and securely held in place.
The grout is allowed to set until the desired minimum strength is obtained before the wires 34, which had been drawn taut before grouting, are post-tensioned. The posttensioning is accomplished by jacking the wires 34 against the wale 26. As shown in FIGURES 6, 7 and 10, the wale 26 is comprised of a pair of steel channel members 36 spaced back to back to permit the wires 34 and the grout pipe 32 to be inserted between them. The channels 36 are advantageously positioned so that the webs 38 are parallel to the line on which the casings 16 are driven and may serve as a guide when the casings are inserted. The wales 26 may be of any desired shape, such as I-beams, wide flange members, built up sections, angles, channels and such; and they may be at an angle or horizontally directed.
In order to maintain the channels 36 in proper position, a short bracket 40 together with a top bearing plate 42 is welded to each soldier beam 12. The channels 36 are set on the plates 42 and held in place by tack welding the flange of each channel 36 to the plates.
In jacking the wires 34 the anchor head 28 is drawn away from the wale 26 until a load in excess of the final post-tension load is achieved. As discussed previously, this excess load is held for about ten minutes and then the load is reduced to the desired amount. At this time the anchor head 28 will be spaced from the wale since elongation of the wires 34 takes place during the loading operation. In order to maintain the elongation (and the accompanying developed load on the wires 34) spacer plates 30 are inserted between the anchor head 28 and the wale 26. A spreader plate 44 may also advantageously be placed between the spacer 30 and the Wale 26 so that the load is distributed over a greater portion of the channels 36.
In FIGURES 8, 9 and 12, another embodiment of the tie-back, wale and soldier beam construction is shown. As shown therein, every third soldier beam 50 is a master beam comprised of two heavy channels spaced apart a short amount, sufiicient to permit the casing 16 and the solid tendon 52 to be inserted therethrough. The remaining soldier beams 12 are similar to those described previously.
In this embodiment the solid tendon 52 is passed through a casing 16 and grouted in place as described previously. However, the wale construction and anchor head are different. The wale 54 is mounted by its flange directly to the flanges of the channels of the master beam 50. Welded above the Wale 54 and to the master beam 50 is an anchor bearing piece 56. The bearing piece 56 is comprised of a built up angle section through which the solid tendon 52 extends. The upper end of the tendon 52, in the illustrated embodiment, is threaded and a heavy duty nut 58 is placed thereon. In order to posttension the tendon 52 the nut 58 is tightened against the bearing piece 56 to control means such as a torque wrench.
In the prior art where braces are used within the excavated area, the braces are in compression while the tendons of the present invention are in tension. Since higher design stresses are permitted with tension members than with compression members, the size of the tendons is reduced compared to a brace which carries the same equivalent load as the tendon. In addition, long braces must be supported by secondary bracing or the design load must be sharply reduced. Accordingly, the, present invention not only aids the builder during construction, but it also assists the designer by allowing him greater latitude since the allowable stresses are greater.
Various types of anchors will occur to these skilled in the art. In FIGURES 15a-d four additional anchors are shown.
In FIGURE 15a a mechanical anchor 76 is illustrated which is comprised of a cone and wedge combination of the expansion type. In this embodiment the rock socket has an oversize lower section 78 which is carefully drilled. The anchor 76 is afiixed to the tendon 22 and inserted into the lower section 78. The anchor 76 is comprised of a cone 80 fitted into split wedges 82 which mate with the surface of the cone 80. When tension is applied to the tendon 22, the cone 80 spreads the wedges apart and presses them into tight locking engagement with the walls of the lower socket section 78. The time to drill the section 78 and the cost of the cone and wedge combination have to be carefully considered before using this type of anchor in place of a grouted anchor.
Some additional grouted anchors are shown in FIG- URES 15b, 0 and d. In FIGURE 15b a simple Series of parallel strands 84 are shown.
In FIGURE 15c a series of wire tendons 86 are shown which are woven under and over a series of rings 88. The open structure about the rings provides very high holding power when the rock socket is filled with grout.
In FIGURE 15d a series of wire tendons90 are shown which have been twisted together to provide additional bond surface and added holding power.
In addition to these anchors others such as buttons and nut and washer combinations may also be used.
The tendons may also be of various kinds. Besides solid rods and wires, the tendons may be of strand, i.e. a series of wires twisted about a larger center wire, or of cable.
It is to be understood that the embodiments shown are illustrative of the present invention and are not to be a limitation thereof as other embodiments will occur to those skilled in the art which will be within the scope of the accompanying claims.
I claim:
1. A rock anchored wall structure and an undisturbed and in place overburden which overlies a rock layer said overburden substantially compressed by the structure, said structure comprising a retaining wall, anchors set in rock sockets in the rock layer beneath the undisturbed overburden, connecting means extending from the wall downwardly at an angle through the overburden to the rock layer post-tensioned tendons inserted through the connecting means and joined to the anchors and to the wall whereby the undisturbed overburden is compressed and maintained in place without any bracing of the Wall on the side of the wall opposite the rock anchors.
2. A rock anchored Wall structure an undisturbed and in place overburden which overlies a rock layer as defined in claim 1 wherein the connecting means is comprised or a casing member.
3. The method of constructing a sheeting wall structure for retaining undisturbed and in place an overburden which overlies a rock layer comprising erecting a wall framework including a series of upright pilings driven into the overburden along the line of the overburden to be retained, inserting casings downwardly into the overburden and at an angle with the pilings until said casings reach the rock layer, preparing rock sockets in the rock layer, said rock sockets set below the lower extent of the casings, inserting a tension member through each casing, anchoring said tension members in the rock sockets, tensioning the tenison members and afiixing them to said framework.
4. The method of claim 3 wherein said tension members have anchors attached thereto and said anchors are fixed in the rock sockets by grouting.
5. The method of claim 3 wherein the casings are inserted at an angle of about 45.
6. The method of claim 3 wherein the tenison members are initially temporarily tensioned to a load of two to three times the final desired load before being finally affixed to the framework.
7. The method of claim 3 wherein said upright pilings are interlocking sheet piles.
References Cited by the Examiner UNITED STATES PATENTS 1,270,659 6/1918 Ravier 6139 1,696,421 12/ 1928 Showell 61-41 1,947,151 2/1934 Caples 61-39 2,865,180 12/ 1958 Nielsen 61-49 FOREIGN PATENTS 618,328 9/ 1935 Germany. 318,381 2/ 1957 Switzerland.
CHARLES E. OCONNELL, Primary Examiner.
WILLIAM I. MUSHAKE, JACOB L. NACKENOFF,
Examiners.
T. W. FLYNN, I SHAPIRO, Assistant Examiners.

Claims (1)

1. A ROCK ANCHORED WALL STRUCTURE AND AN UNDISTURBED AND IN PLACE OVERBURDEN WHICH OVERLIES A ROCK LAYER SAID OVERBURDEN SUBSTANTIALLY COMPRESSED BY THE STRUCTURE, SAID STRUCTURE COMPRISING A RETAINING WALL, ANCHORS SET IN ROCK SOCKETS IN THE ROCK LAYER BENEATH THE UNDISTURBED OVERBURDEN, CONNECTING MEANS EXTENDING FROM THE WALL DOWNWARDLY AT AN ANGLE THROUGH THE OVERBURDEN TO THE
US96980A 1961-03-20 1961-03-20 Sheeting wall system and method of constructing same Expired - Lifetime US3226933A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US96980A US3226933A (en) 1961-03-20 1961-03-20 Sheeting wall system and method of constructing same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US96980A US3226933A (en) 1961-03-20 1961-03-20 Sheeting wall system and method of constructing same

Publications (1)

Publication Number Publication Date
US3226933A true US3226933A (en) 1966-01-04

Family

ID=22260077

Family Applications (1)

Application Number Title Priority Date Filing Date
US96980A Expired - Lifetime US3226933A (en) 1961-03-20 1961-03-20 Sheeting wall system and method of constructing same

Country Status (1)

Country Link
US (1) US3226933A (en)

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3354657A (en) * 1965-05-03 1967-11-28 Lee A Turzillo Method for installing anchoring or supporting columns in situ
US3379016A (en) * 1965-01-11 1968-04-23 Chester I. Williams Rock bolt assembly and procedure for use in conjunction with blasting operations
US3421326A (en) * 1963-03-27 1969-01-14 Vidal Henri C Constructional works
US3490242A (en) * 1968-03-07 1970-01-20 Harry Schnabel Jr Method and structure for reinforcing an earthen excavation
US3503213A (en) * 1967-08-14 1970-03-31 Rotary Oil Tool Co Method of and apparatus for installing reinforcing members in boreholes
US3507121A (en) * 1964-11-11 1970-04-21 Carl Olof Oskar Morfeldt Tie rod anchoring method and apparatus
US3530676A (en) * 1969-02-19 1970-09-29 Pomeroy & Co Inc J H Concrete wall construction with tension-loaded external reinforcing element and method
US3541798A (en) * 1969-04-18 1970-11-24 Harry Schnabel Jr Method and structure for shoring a lateral face of an excavation
US3650112A (en) * 1970-09-21 1972-03-21 Howlett Machine Works Method of shoring and apparatus therefor
US3728862A (en) * 1971-06-23 1973-04-24 Meredith Drilling Co Inc Shoring system and components therefor
US3807182A (en) * 1972-05-03 1974-04-30 H Schnabel Method of installing support tendons
US3999391A (en) * 1975-06-12 1976-12-28 Meredith Drilling Co., Inc. Tie-back anchor components and method for a shoring system
US4158519A (en) * 1976-08-06 1979-06-19 Imperial Chemical Industries Limited Rock reinforcement
US4480945A (en) * 1982-04-20 1984-11-06 Schnabel Foundation Company Method of reinforcing an existing earth supporting wall
US4715745A (en) * 1984-07-13 1987-12-29 Stump Bohr Gmbh Ground anchor system
WO1989011567A1 (en) * 1988-05-25 1989-11-30 Cenefill Pty Ltd. Methods of construction and implements therefor
US5395185A (en) * 1993-11-22 1995-03-07 Schnabel Foundation Company Method of temporarily shoring and permanently facing and excavated slope with a retaining wall
US5551810A (en) * 1994-06-08 1996-09-03 Schnabel Foundation Company Retaining wall with an outer face and method of forming the same
US5588784A (en) * 1995-06-07 1996-12-31 Schnabel Foundation Company Soil or rock nail wall with outer face and method of constructing the same
US20090071094A1 (en) * 2007-09-18 2009-03-19 Franklin Dale Boxberger Construction and design method
ES2329207A1 (en) * 2007-04-09 2009-11-23 Santiago Quesada Garcia Flexible anchoring for the attachment of an elastic zunch to a wall of tapia. (Machine-translation by Google Translate, not legally binding)
US20100166505A1 (en) * 2003-12-18 2010-07-01 R&B Leasing, Llc Self-centralizing soil nail and method of creating subsurface support
US20100166506A1 (en) * 2003-12-18 2010-07-01 R&B Leasing, Llc Composite self-drilling soil nail and method
US8376661B2 (en) 2010-05-21 2013-02-19 R&B Leasing, Llc System and method for increasing roadway width incorporating a reverse oriented retaining wall and soil nail supports
US20230183936A1 (en) * 2021-12-10 2023-06-15 Steven Robertson Pier support system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1270659A (en) * 1918-04-18 1918-06-25 Sylvain Louis Ravier Works such as retaining-walls, piers, and wharves.
US1696421A (en) * 1928-03-21 1928-12-25 Showell Sam Houston Method of and apparatus for supporting the side walls of excavations
US1947151A (en) * 1932-12-27 1934-02-13 William G Caples Sheet-metal-piling wall structure
DE618328C (en) * 1929-04-24 1935-09-11 Andre Coyne Support walls, dam walls, weir systems or similar structures
CH318381A (en) * 1954-02-10 1957-01-15 Vobag Ag Fuer Vorgespannten Be Avalanche protection facility
US2865180A (en) * 1953-12-23 1958-12-23 Great Lakes Dredge & Dock Comp Sheet piling wall structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1270659A (en) * 1918-04-18 1918-06-25 Sylvain Louis Ravier Works such as retaining-walls, piers, and wharves.
US1696421A (en) * 1928-03-21 1928-12-25 Showell Sam Houston Method of and apparatus for supporting the side walls of excavations
DE618328C (en) * 1929-04-24 1935-09-11 Andre Coyne Support walls, dam walls, weir systems or similar structures
US1947151A (en) * 1932-12-27 1934-02-13 William G Caples Sheet-metal-piling wall structure
US2865180A (en) * 1953-12-23 1958-12-23 Great Lakes Dredge & Dock Comp Sheet piling wall structure
CH318381A (en) * 1954-02-10 1957-01-15 Vobag Ag Fuer Vorgespannten Be Avalanche protection facility

Cited By (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3421326A (en) * 1963-03-27 1969-01-14 Vidal Henri C Constructional works
US3507121A (en) * 1964-11-11 1970-04-21 Carl Olof Oskar Morfeldt Tie rod anchoring method and apparatus
US3379016A (en) * 1965-01-11 1968-04-23 Chester I. Williams Rock bolt assembly and procedure for use in conjunction with blasting operations
US3354657A (en) * 1965-05-03 1967-11-28 Lee A Turzillo Method for installing anchoring or supporting columns in situ
US3503213A (en) * 1967-08-14 1970-03-31 Rotary Oil Tool Co Method of and apparatus for installing reinforcing members in boreholes
US3490242A (en) * 1968-03-07 1970-01-20 Harry Schnabel Jr Method and structure for reinforcing an earthen excavation
US3530676A (en) * 1969-02-19 1970-09-29 Pomeroy & Co Inc J H Concrete wall construction with tension-loaded external reinforcing element and method
US3541798A (en) * 1969-04-18 1970-11-24 Harry Schnabel Jr Method and structure for shoring a lateral face of an excavation
US3650112A (en) * 1970-09-21 1972-03-21 Howlett Machine Works Method of shoring and apparatus therefor
US3728862A (en) * 1971-06-23 1973-04-24 Meredith Drilling Co Inc Shoring system and components therefor
US3807182A (en) * 1972-05-03 1974-04-30 H Schnabel Method of installing support tendons
US3999391A (en) * 1975-06-12 1976-12-28 Meredith Drilling Co., Inc. Tie-back anchor components and method for a shoring system
US4158519A (en) * 1976-08-06 1979-06-19 Imperial Chemical Industries Limited Rock reinforcement
US4480945A (en) * 1982-04-20 1984-11-06 Schnabel Foundation Company Method of reinforcing an existing earth supporting wall
US4715745A (en) * 1984-07-13 1987-12-29 Stump Bohr Gmbh Ground anchor system
WO1989011567A1 (en) * 1988-05-25 1989-11-30 Cenefill Pty Ltd. Methods of construction and implements therefor
US5253959A (en) * 1988-05-25 1993-10-19 Cenefill Pty Ltd Methods of construction and implements therefor
US5395185A (en) * 1993-11-22 1995-03-07 Schnabel Foundation Company Method of temporarily shoring and permanently facing and excavated slope with a retaining wall
US5551810A (en) * 1994-06-08 1996-09-03 Schnabel Foundation Company Retaining wall with an outer face and method of forming the same
US5588784A (en) * 1995-06-07 1996-12-31 Schnabel Foundation Company Soil or rock nail wall with outer face and method of constructing the same
US20100166506A1 (en) * 2003-12-18 2010-07-01 R&B Leasing, Llc Composite self-drilling soil nail and method
US20100166505A1 (en) * 2003-12-18 2010-07-01 R&B Leasing, Llc Self-centralizing soil nail and method of creating subsurface support
US8851801B2 (en) * 2003-12-18 2014-10-07 R&B Leasing, Llc Self-centralizing soil nail and method of creating subsurface support
US9273442B2 (en) 2003-12-18 2016-03-01 R&B Leasing, Llc Composite self-drilling soil nail and method
ES2329207A1 (en) * 2007-04-09 2009-11-23 Santiago Quesada Garcia Flexible anchoring for the attachment of an elastic zunch to a wall of tapia. (Machine-translation by Google Translate, not legally binding)
US20090071094A1 (en) * 2007-09-18 2009-03-19 Franklin Dale Boxberger Construction and design method
US7828497B2 (en) 2007-09-18 2010-11-09 Franklin Dale Boxberger Construction and design method
US8376661B2 (en) 2010-05-21 2013-02-19 R&B Leasing, Llc System and method for increasing roadway width incorporating a reverse oriented retaining wall and soil nail supports
US8708597B2 (en) 2010-05-21 2014-04-29 R&B Leasing, Llc System and method for increasing roadway width incorporating a reverse oriented retaining wall and soil nail supports
US20230183936A1 (en) * 2021-12-10 2023-06-15 Steven Robertson Pier support system
US11926985B2 (en) * 2021-12-10 2024-03-12 Steven Robertson Pier support system

Similar Documents

Publication Publication Date Title
US3226933A (en) Sheeting wall system and method of constructing same
US3184893A (en) Contact foundation method
US8898996B2 (en) Method for forming a retaining wall, and corresponding retaining wall
US3490242A (en) Method and structure for reinforcing an earthen excavation
US5551810A (en) Retaining wall with an outer face and method of forming the same
US3555830A (en) Concrete wall structure and method
AU2008243212A1 (en) Earth Retention and Piling Systems
US6616380B1 (en) Subterranean structures and methods for constructing subterranean structures
CN113417300A (en) Slope support system and construction method thereof
JP2000352296A (en) Method o constructing passage just under underground structure
CN100443673C (en) Method of construction
US3299644A (en) Underpinning system and method of constructing same
JP3448629B2 (en) Seismic retrofitting method for existing structure foundation
US3091938A (en) Method and structure for underpinning
JP3002126B2 (en) Temporary receiving method for structures
US5871307A (en) Pre-cast concrete panel wall
JPH01146020A (en) Foundation structure by banking and its construction
JPH0559728A (en) Sheathing work above underground structure
JPS584094A (en) Method of constructing low road cross
JPH04115024A (en) Sheathing method
KR960016755B1 (en) Working method and working apparatus of underground structure
JPH08291529A (en) Underground floor construction method
JPH1150407A (en) Road and construction method thereof
JPH09209364A (en) Filling soil construction method
AU2012202472B2 (en) Earth Retention and Piling Systems