KR101826094B1 - Construction method for transfer mat and transfer mat using the same - Google Patents
Construction method for transfer mat and transfer mat using the same Download PDFInfo
- Publication number
- KR101826094B1 KR101826094B1 KR1020150091210A KR20150091210A KR101826094B1 KR 101826094 B1 KR101826094 B1 KR 101826094B1 KR 1020150091210 A KR1020150091210 A KR 1020150091210A KR 20150091210 A KR20150091210 A KR 20150091210A KR 101826094 B1 KR101826094 B1 KR 101826094B1
- Authority
- KR
- South Korea
- Prior art keywords
- slab
- temporary
- transfer mat
- gantry
- main body
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/30—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts being composed of two or more materials; Composite steel and concrete constructions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
- E04B5/36—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
- E04B5/38—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
- E04B5/40—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element with metal form-slabs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/29—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
- E04C3/293—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
According to an aspect of the present invention, there is provided a method of constructing a transfer mat to be placed between a columnar structure (1) and a wall structure (2), comprising the steps of: placing a temporary slab (200) (S100); And a second step (S200) of placing a main body slab (300) on the upper side of the temporary slab (200) to synthesize the temporary slab (200) and the main body slab (300) A method of constructing a mat is provided.
According to the present invention, since it is not required to install the installation materials such as a trowel, it is possible to reduce the difficulty of site construction and shorten the construction period.
Description
BACKGROUND OF THE
The transfer mat (transfer girder) is used for residential and commercial buildings and apartments. The basement floor of the residential complex and the upper floor of the ground floor are the column structure (Residential part) is a wall structure with no pillars, which is a wall structure, and the layer that changes from the column structure to the wall structure is a transition layer (one ground layer), and is installed on both columns of the transition layer, It is the transfer mat to transfer the transmitted load to the lower column constantly.
The transfer mat can be applied not only to the residential complex but also to the lobbying of the general apartment, in which case the transition layer is formed on the ground.
Since the upper part of the transition layer is composed of a plurality of walls, it is necessary to transfer the load from the upper side to the column constantly at the transition layer part by the plurality of walls. From such a wall structure, What is needed to transmit the force is a transfer mat, not a common girder.
The transition layer is a part where the shape and position change when the concrete is poured in the building, so if you install this part quickly, it will bring forward the whole air.
However, the actual transfer mats weigh about 20 to 30 tons and are about 8 to 15 meters in length (these figures are dependent on the size of the transfer girders used). In this case, it is necessary to use large-sized heavy equipment, and there is a problem that it can not be transferred to the construction site due to problems such as road conditions.
Therefore, in the case of a large-sized concrete structure such as the transfer girder, most of the structures are constructed with cast-in-place concrete. In the construction method in which the concrete is laid in the field, the concrete is placed on the site, And a lot of temporary construction materials such as a trowel for supporting the formwork should be installed in a large number, so that a lot of specialized personnel must be mobilized for the production of formwork and provisional construction materials, and a lot of time and manpower is required for concrete casting and curing .
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems of the conventional transfer mat construction method, and it is an object of the present invention to provide a transfer mat which can reduce the difficulty of site construction and shorten the construction period, And a transfer mat that is constructed using the same.
Another object of the present invention is to provide a transfer mat which does not require a separate mold for transfer mat using only a gantry used in the formation of a reference layer and a permanent form permanently bonded to the lower part of the transfer mat, And a transfer mat which is constructed using the same.
It is a further object of the present invention to provide a transfer mat construction method capable of enhancing the structural stability and efficiency of construction by adopting a system in which a lower portion of a transfer mat is pierced to form a temporary slab and a main slab is supported by a temporary slab, And to provide a transfer mat that is constructed using the same.
According to an aspect of the present invention, there is provided a method of constructing a transfer mat to be placed between a columnar structure (1) and a wall structure (2), comprising the steps of: placing a temporary slab (200) (S100); And a second step (S200) of placing a main body slab (300) on the upper side of the temporary slab (200) to synthesize the temporary slab (200) and the main body slab (300) A method of constructing a mat is provided.
In this case, the
Also, the
In addition, the
In addition, the
Also, the cast iron 400 may be buried in the
The bottom surface of the
The transfer mat may be installed on the upper surface of the
The
According to another aspect of the present invention, there is provided a transfer mat applied by a method of applying a transfer mat.
According to the present invention, since it is not required to install the installation materials such as a trowel, it is possible to reduce the difficulty of site construction and shorten the construction period.
According to the present invention, there is an effect that it is not required to use a mold which is used for forming the reference layer as a side mold and a permanent mold which is permanently combined with the lower part of the transfer mat, as a mold, and a separate mold for the transfer mat alone.
According to the present invention, there is an effect that the structural stability and efficiency of the construction can be improved by adopting a system in which a lower portion of the transfer mat is laid in a line to form a temporary slab and the body slab is supported by a temporary slab.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a view for defining a transfer mat placed between a columnar structure and a wall structure of a building; FIG.
2 is a plan view of a lower structure of a transfer mat according to an embodiment of the present invention;
3 is a perspective view of a steel composite beam according to one embodiment of the present invention.
FIG. 4 is a side view of a substructure having a built-in slab according to an embodiment of the present invention; FIG.
5 is a side view of a substructure in which a body slab and a temporary slab are combined according to an embodiment of the present invention.
6 is a side view showing the structure of gang foam according to one embodiment of the present invention.
A method of constructing a transfer mat according to the present invention and an embodiment of a transfer mat constructed using the same will be described in detail with reference to the accompanying drawings. In the following description with reference to the accompanying drawings, And the description thereof will be omitted.
It is also to be understood that the terms first, second, etc. used hereinafter are merely reference numerals for distinguishing between identical or corresponding components, and the same or corresponding components are defined by terms such as first, second, no.
In addition, the term " coupled " is used not only in the case of direct physical contact between the respective constituent elements in the contact relation between the constituent elements, but also means that other constituent elements are interposed between the constituent elements, Use them as a concept to cover each contact.
The present invention relates to a transfer mat which is placed between a columnar structure (1) and a wall structure (2) and distributes the load transferred by the wall structure (2) to the columnar structure (1).
Since the conventional transfer mat construction has been carried out in the whole installation method in the field, it has been required to install a large number of temporary members and form assembly for casting a transfer mat having a large volume.
The construction of the transfer mat takes a long period of time because of the construction of the temporary structure and the assembly of the mold in the field, and the construction period of the entire building is prolonged and the construction cost is excessively spent.
Accordingly, the present invention allows a transfer mat to be installed in a manner that a supporting structure is formed by partially piling a part of slabs constituting a transfer mat and then the remaining slabs are synthesized, In addition, the side surface of the slab is formed by using the gantry used for the construction of the reference layer having the
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the structure and effects of the present invention will be described with reference to specific examples.
A method of constructing a transfer mat according to an embodiment of the present invention includes a first step S100 of placing a
That is, instead of placing the entire slab at a time, the
Hereinafter, reference is made to the thickness of the pavement of the
A part of the structure of the
That is, the
In this case, it is preferable that the
The lower or entire portions of the
Therefore, the
The
In this case, the structural stability of the transfer mat can be ensured and the composite force of the
The lower surface of the
That is, the
As a result, it is possible to eliminate the use of a separate member, thereby reducing the cost of the member, lowering the difficulty of site construction, and quickly performing the construction progress.
According to the present invention, since the
In addition, it is also possible to install the
According to an embodiment of the present invention, in forming the side surfaces of the
More specifically, when the
According to one embodiment of the present invention, in the formation of the
The
In this case, the
It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.
100: Substructure
200: hypothetical slab
300: Body slab
400: Cast iron rods
500: Modified
600:
Claims (10)
A first step (S100) of laying the slab (200) on the substructure (100); And
And a second step S200 of placing a main body slab 300 on the upper side of the temporary slab 200 to synthesize the temporary slab 200 and the main body slab 300,
The lower structure (100)
A column 110;
A steel composite beam 120 having both ends connected to the column 110; And
And a deck plate (130) mounted on the steel composite member (120)
The steel composite beam (120)
A lower iron plate 121;
A first angle 122 coupled to an upper surface of the lower steel plate 121;
A second angle (123) coupled to the upper portion of the first angle (122); And
And a reticle (124) connecting the first angle (122) and the second angle (123)
Wherein the pivotal slab (200) in the first step (S100) is lower than the upper surface of the second angle (123) and the deck plate (130).
The lower structure (100)
An upper surface 131 coupled to an upper surface of the deck plate 130; And
A main iron core 400 coupled to an upper portion of the upper surface 131 and passing through the reticle member 124;
Further comprising the steps of:
Wherein the main rail (400) is embedded in the main body slab (300).
In forming the temporary slab 200 and the body slab 300,
The lower surfaces of the temporary slab 200 and the main body slab 300 are formed by using the deck plate 130 and the lower steel plate 121 as permanent molds,
Wherein the side surfaces of the temporary slab (200) and the main body slab (300) are formed using a gantry (500).
Wherein a fixed gantry 600 for fixing the gantry 500 is installed on the upper surface of the temporary slab 200.
In forming the temporary slab 200 and the body slab 300,
And a stopper 510 coupled to the deck plate 130 and the gantry 500 to fix the position of the gantry 500,
Wherein the stopper (510) and the gantry (500) are bolted to each other.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150091210A KR101826094B1 (en) | 2015-06-26 | 2015-06-26 | Construction method for transfer mat and transfer mat using the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150091210A KR101826094B1 (en) | 2015-06-26 | 2015-06-26 | Construction method for transfer mat and transfer mat using the same |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20170001351A KR20170001351A (en) | 2017-01-04 |
KR101826094B1 true KR101826094B1 (en) | 2018-03-22 |
Family
ID=57831749
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150091210A KR101826094B1 (en) | 2015-06-26 | 2015-06-26 | Construction method for transfer mat and transfer mat using the same |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101826094B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20200075600A (en) | 2018-12-18 | 2020-06-26 | 삼표피앤씨 주식회사 | Method for constructing transfer layer of building using precast concrete slab |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102149661B1 (en) * | 2018-12-18 | 2020-08-31 | 삼표피앤씨(주) | Method for constructing overground transfer layer of building using precast concrete |
KR102111883B1 (en) * | 2019-04-23 | 2020-05-18 | 현대건설주식회사 | Construction Method of Transfer girder |
-
2015
- 2015-06-26 KR KR1020150091210A patent/KR101826094B1/en active IP Right Grant
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20200075600A (en) | 2018-12-18 | 2020-06-26 | 삼표피앤씨 주식회사 | Method for constructing transfer layer of building using precast concrete slab |
Also Published As
Publication number | Publication date |
---|---|
KR20170001351A (en) | 2017-01-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105317137B (en) | Precast wall body, wallboard and its construction method and prefabricated panel production method | |
KR101379305B1 (en) | Wall structure manufacturing method using precast front wall panel and precast back wall panel | |
AU2017304226B2 (en) | Precast concrete formwork, floor system and a method of construction | |
CN103388357B (en) | Shatter-proof, prefabricated steel tube shear Temperature Variation In Buildings of Mixed Structures thing | |
CN103590602B (en) | The construction method of cast-in-place concrete hollow building roof | |
KR101457077B1 (en) | Reformed concrete filled tube column structure | |
CN103806656A (en) | Construction method of cast-in-place concrete flat slab built-in thin-wall hollow box body | |
KR102182536B1 (en) | Combined structure of precast columns and beams for construction of warehouse, precast beams used for the same | |
JP5405337B2 (en) | Construction method of railway RC ramen structure viaduct | |
KR101826094B1 (en) | Construction method for transfer mat and transfer mat using the same | |
CN103410269A (en) | Unbonded prestress cast-in-place reinforced concrete hollow slab construction structure and method | |
CN111576236A (en) | Method for mounting integral type prefabricated bridge deck auxiliary structure | |
KR101334071B1 (en) | The needless filling structure in the junction of pc beam and vertical member | |
CN207110214U (en) | A kind of prefabricated interior fill concrete wallboard | |
KR101658929B1 (en) | Precast box structure and construction method thereof | |
CN107237448A (en) | A kind of prefabricated interior fill concrete wallboard and its manufacture method | |
GB2495319A (en) | Beam and slab floor construction | |
KR101345672B1 (en) | Unsupported the detachable bracket | |
KR101118508B1 (en) | Construction method and structure of anchored slabstone on concrete | |
CN203475599U (en) | Shock-proof prefabricated building of steel tube shearing wall composite structure | |
CN104234432B (en) | Shed deckhead construction method | |
KR102222834B1 (en) | Slim transfer mat structure and construction method with reverse drop panel | |
KR101482523B1 (en) | Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof | |
KR101315946B1 (en) | Rc construction method for concrete lining in parallel | |
KR101346671B1 (en) | The pin connection structure using the spacer in the junction of pc beam and vertical member |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
N231 | Notification of change of applicant | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right |