KR101826094B1 - Construction method for transfer mat and transfer mat using the same - Google Patents

Construction method for transfer mat and transfer mat using the same Download PDF

Info

Publication number
KR101826094B1
KR101826094B1 KR1020150091210A KR20150091210A KR101826094B1 KR 101826094 B1 KR101826094 B1 KR 101826094B1 KR 1020150091210 A KR1020150091210 A KR 1020150091210A KR 20150091210 A KR20150091210 A KR 20150091210A KR 101826094 B1 KR101826094 B1 KR 101826094B1
Authority
KR
South Korea
Prior art keywords
slab
temporary
transfer mat
gantry
main body
Prior art date
Application number
KR1020150091210A
Other languages
Korean (ko)
Other versions
KR20170001351A (en
Inventor
최익준
김용남
전진수
전병갑
황상철
Original Assignee
삼성물산 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 삼성물산 주식회사 filed Critical 삼성물산 주식회사
Priority to KR1020150091210A priority Critical patent/KR101826094B1/en
Publication of KR20170001351A publication Critical patent/KR20170001351A/en
Application granted granted Critical
Publication of KR101826094B1 publication Critical patent/KR101826094B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/30Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts being composed of two or more materials; Composite steel and concrete constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • E04B5/40Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element with metal form-slabs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/29Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
    • E04C3/293Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

According to an aspect of the present invention, there is provided a method of constructing a transfer mat to be placed between a columnar structure (1) and a wall structure (2), comprising the steps of: placing a temporary slab (200) (S100); And a second step (S200) of placing a main body slab (300) on the upper side of the temporary slab (200) to synthesize the temporary slab (200) and the main body slab (300) A method of constructing a mat is provided.
According to the present invention, since it is not required to install the installation materials such as a trowel, it is possible to reduce the difficulty of site construction and shorten the construction period.

Description

BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a transfer mat,

BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to a construction masonry field, and more particularly, to a transfer mason construction method applied between a columnar structure and a wall structure of a building, and a transfer mat constructed using the same.

The transfer mat (transfer girder) is used for residential and commercial buildings and apartments. The basement floor of the residential complex and the upper floor of the ground floor are the column structure (Residential part) is a wall structure with no pillars, which is a wall structure, and the layer that changes from the column structure to the wall structure is a transition layer (one ground layer), and is installed on both columns of the transition layer, It is the transfer mat to transfer the transmitted load to the lower column constantly.

The transfer mat can be applied not only to the residential complex but also to the lobbying of the general apartment, in which case the transition layer is formed on the ground.

Since the upper part of the transition layer is composed of a plurality of walls, it is necessary to transfer the load from the upper side to the column constantly at the transition layer part by the plurality of walls. From such a wall structure, What is needed to transmit the force is a transfer mat, not a common girder.

The transition layer is a part where the shape and position change when the concrete is poured in the building, so if you install this part quickly, it will bring forward the whole air.

However, the actual transfer mats weigh about 20 to 30 tons and are about 8 to 15 meters in length (these figures are dependent on the size of the transfer girders used). In this case, it is necessary to use large-sized heavy equipment, and there is a problem that it can not be transferred to the construction site due to problems such as road conditions.

Therefore, in the case of a large-sized concrete structure such as the transfer girder, most of the structures are constructed with cast-in-place concrete. In the construction method in which the concrete is laid in the field, the concrete is placed on the site, And a lot of temporary construction materials such as a trowel for supporting the formwork should be installed in a large number, so that a lot of specialized personnel must be mobilized for the production of formwork and provisional construction materials, and a lot of time and manpower is required for concrete casting and curing .

SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems of the conventional transfer mat construction method, and it is an object of the present invention to provide a transfer mat which can reduce the difficulty of site construction and shorten the construction period, And a transfer mat that is constructed using the same.

Another object of the present invention is to provide a transfer mat which does not require a separate mold for transfer mat using only a gantry used in the formation of a reference layer and a permanent form permanently bonded to the lower part of the transfer mat, And a transfer mat which is constructed using the same.

It is a further object of the present invention to provide a transfer mat construction method capable of enhancing the structural stability and efficiency of construction by adopting a system in which a lower portion of a transfer mat is pierced to form a temporary slab and a main slab is supported by a temporary slab, And to provide a transfer mat that is constructed using the same.

According to an aspect of the present invention, there is provided a method of constructing a transfer mat to be placed between a columnar structure (1) and a wall structure (2), comprising the steps of: placing a temporary slab (200) (S100); And a second step (S200) of placing a main body slab (300) on the upper side of the temporary slab (200) to synthesize the temporary slab (200) and the main body slab (300) A method of constructing a mat is provided.

In this case, the substructure 100 includes a column 110; A steel composite beam 120 having both ends connected to the column 110; And a deck plate (130) mounted on the steel composite sheet (120).

Also, the steel composite beam 120 includes a lower steel plate 121; A first angle 122 coupled to an upper surface of the lower steel plate 121; A second angle (123) coupled to the upper portion of the first angle (122); And a reticle (124) connecting the first angle (122) and the second angle (123) to each other.

In addition, the temporary slab 200 in the first step S100 may be installed lower than the upper surface of the second angle 123 and the deck plate 130 .

In addition, the lower structure 100 includes an upper side 131 coupled to an upper surface of the deck plate 130; And a cast iron muscle 400 coupled to an upper portion of the upper surface 131 and passing through the gap between the reticle members 124. [

Also, the cast iron 400 may be buried in the main body slab 300.

The bottom surface of the main slab 300 and the bottom surface of the main slab 300 may be formed to be in contact with the deck plate 130 and the bottom plate 121 And a side surface of the main slab (300) is formed by using the gantry (500).

The transfer mat may be installed on the upper surface of the temporary slab 200 in order to fix the gantry 500.

The deck plate 130 and the stopper 510 coupled to the gantry 500 may be fixed to fix the position of the gantry 500 in the formation of the temporary slab 200 and the body slab 300. [ Wherein the stopper 510 and the gantry 500 are bolted to each other.

According to another aspect of the present invention, there is provided a transfer mat applied by a method of applying a transfer mat.

According to the present invention, since it is not required to install the installation materials such as a trowel, it is possible to reduce the difficulty of site construction and shorten the construction period.

According to the present invention, there is an effect that it is not required to use a mold which is used for forming the reference layer as a side mold and a permanent mold which is permanently combined with the lower part of the transfer mat, as a mold, and a separate mold for the transfer mat alone.

According to the present invention, there is an effect that the structural stability and efficiency of the construction can be improved by adopting a system in which a lower portion of the transfer mat is laid in a line to form a temporary slab and the body slab is supported by a temporary slab.

BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a view for defining a transfer mat placed between a columnar structure and a wall structure of a building; FIG.
2 is a plan view of a lower structure of a transfer mat according to an embodiment of the present invention;
3 is a perspective view of a steel composite beam according to one embodiment of the present invention.
FIG. 4 is a side view of a substructure having a built-in slab according to an embodiment of the present invention; FIG.
5 is a side view of a substructure in which a body slab and a temporary slab are combined according to an embodiment of the present invention.
6 is a side view showing the structure of gang foam according to one embodiment of the present invention.

A method of constructing a transfer mat according to the present invention and an embodiment of a transfer mat constructed using the same will be described in detail with reference to the accompanying drawings. In the following description with reference to the accompanying drawings, And the description thereof will be omitted.

It is also to be understood that the terms first, second, etc. used hereinafter are merely reference numerals for distinguishing between identical or corresponding components, and the same or corresponding components are defined by terms such as first, second, no.

In addition, the term " coupled " is used not only in the case of direct physical contact between the respective constituent elements in the contact relation between the constituent elements, but also means that other constituent elements are interposed between the constituent elements, Use them as a concept to cover each contact.

The present invention relates to a transfer mat which is placed between a columnar structure (1) and a wall structure (2) and distributes the load transferred by the wall structure (2) to the columnar structure (1).

Since the conventional transfer mat construction has been carried out in the whole installation method in the field, it has been required to install a large number of temporary members and form assembly for casting a transfer mat having a large volume.

The construction of the transfer mat takes a long period of time because of the construction of the temporary structure and the assembly of the mold in the field, and the construction period of the entire building is prolonged and the construction cost is excessively spent.

Accordingly, the present invention allows a transfer mat to be installed in a manner that a supporting structure is formed by partially piling a part of slabs constituting a transfer mat and then the remaining slabs are synthesized, In addition, the side surface of the slab is formed by using the gantry used for the construction of the reference layer having the upper wall structure 2 of the transfer mat, and the lower surface of the slab is formed by utilizing the deck plate as the permanent form, The construction time can be shortened, and a structurally stable transfer mat can be constructed.

DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the structure and effects of the present invention will be described with reference to specific examples.

A method of constructing a transfer mat according to an embodiment of the present invention includes a first step S100 of placing a temporary slab 200 on a lower structure 100 and a main slab 300 on an upper portion of a temporary slab 200 And a second step S200 of combining the temporary slab 200 and the main body slab 300 by placing the slabs 300 (Figs. 4 and 5).

That is, instead of placing the entire slab at a time, the temporary slab 200 and the main body slab are separately laid so that the temporary slab 200 is utilized as a supporting structure for installing the main body slab 300.

Hereinafter, reference is made to the thickness of the pavement of the pavement slab 200 and the construction necessary for the structurally stable composition of the pavement slab 200 and the body slab 300.

A part of the structure of the lower structure 100 is formed into a composite structure for the structurally stable synthesis of the temporary slab 200 and the main body slab 300.

That is, the lower structure 100 includes a column 110, a steel composite member 120 having both ends connected to the column 110, and a deck plate 130 mounted on the steel composite member 120 (FIG. 4) The steel composite beam 120 includes a lower steel plate 121, a first angle 122 coupled to the upper surface of the lower steel plate 121, a second angle 123 coupled to the upper portion of the first angle 122, And a reticle member 124 connecting the first angle 122 and the second angle 123 (FIG. 3).

In this case, it is preferable that the temporary slab 200 in the first step S100 is installed lower than the upper surface of the second angle 123 and the deck plate 130.

The lower or entire portions of the lower steel plate 121, the first angle 122 and the resty member 124 of the steel composite member 120 are embedded in the temporary slab 200, The upper portion of the first slab 124 and the second angle 123 are embedded in the main body slab 300.

Therefore, the steel composite beam 120 serves as a composite member of the temporary slab 200 and the main body slab 300.

The lower structure 100 according to an embodiment of the present invention is coupled to an upper portion of the upper side 131 and an upper portion of the upper portion 131 coupled to the upper surface of the deck plate 130, And may further include a cast iron rope 400 (Fig. 4). It is preferable that the cast iron 400 is embedded in the main body slab 300.

In this case, the structural stability of the transfer mat can be ensured and the composite force of the slab 200 and the main body slab 300 can be increased.

The lower surface of the temporary slab 200 and the lower surface of the main body slab 300 in the formation of the temporary slab 200 and the main body slab 300 according to an embodiment of the present invention may include a deck plate 130 and a lower steel plate 121 And the side surfaces of the temporary slab 200 and the main body slab 300 are formed by using the gantry 500. In this case,

That is, the temporary slab 200 and the main body slab 300 are formed by using the gantry 500 used for the reference layer construction, without using a separate form to form the transfer mat.

As a result, it is possible to eliminate the use of a separate member, thereby reducing the cost of the member, lowering the difficulty of site construction, and quickly performing the construction progress.

According to the present invention, since the gantry 500 can be directly applied to the reference layer construction of the wall-like structure 2 formed on the transfer mat after completion of the construction of the transfer mat, the efficiency of the work performance can be obtained .

In addition, it is also possible to install the deck plate 130 vertically to replace the gantry 500.

According to an embodiment of the present invention, in forming the side surfaces of the temporary slab 200 and the main body slab 300 using the gantry 500, the gantry fixing portion 600 may be provided to fix the position of the gantry 500, Can be formed on the upper surface of the temporary slab 200.

More specifically, when the temporary slab 200 is installed and cured, a ring-shaped fixed gantry 600 is installed on the upper surface of the temporary slab 200 at a predetermined distance from a position where the gantry is to be installed, After the curing is completed, it is possible to fix the gantry 500 to the correct position by connecting and fixing the gantry 500 and the gantry fixing part 600 using a wire member.

According to one embodiment of the present invention, in the formation of the temporary slab 200 and the main body slab 300, the deck plate 130 and the stopper (not shown) coupled to the gantry 500 510) (Fig. 6).

The stopper 510 is coupled along the direction of the gang 500 and the deck plate 130 and is bent at an angle depending on the angle formed by the gang 500 and the deck plate 130, .

In this case, the stopper 510 and the gantry 500 are bolted to each other to release the bolt connection after the curing of the temporary slab 200 and the main body slab 300 so that the gantry 500 can be separated desirable.

It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.

100: Substructure
200: hypothetical slab
300: Body slab
400: Cast iron rods
500: Modified
600:

Claims (10)

In a method of constructing a transfer mat to be placed between a columnar structure (1) and a wall structure (2)
A first step (S100) of laying the slab (200) on the substructure (100); And
And a second step S200 of placing a main body slab 300 on the upper side of the temporary slab 200 to synthesize the temporary slab 200 and the main body slab 300,
The lower structure (100)
A column 110;
A steel composite beam 120 having both ends connected to the column 110; And
And a deck plate (130) mounted on the steel composite member (120)
The steel composite beam (120)
A lower iron plate 121;
A first angle 122 coupled to an upper surface of the lower steel plate 121;
A second angle (123) coupled to the upper portion of the first angle (122); And
And a reticle (124) connecting the first angle (122) and the second angle (123)
Wherein the pivotal slab (200) in the first step (S100) is lower than the upper surface of the second angle (123) and the deck plate (130).
delete delete delete The method according to claim 1,
The lower structure (100)
An upper surface 131 coupled to an upper surface of the deck plate 130; And
A main iron core 400 coupled to an upper portion of the upper surface 131 and passing through the reticle member 124;
Further comprising the steps of:
6. The method of claim 5,
Wherein the main rail (400) is embedded in the main body slab (300).
The method according to claim 6,
In forming the temporary slab 200 and the body slab 300,
The lower surfaces of the temporary slab 200 and the main body slab 300 are formed by using the deck plate 130 and the lower steel plate 121 as permanent molds,
Wherein the side surfaces of the temporary slab (200) and the main body slab (300) are formed using a gantry (500).
8. The method of claim 7,
Wherein a fixed gantry 600 for fixing the gantry 500 is installed on the upper surface of the temporary slab 200.
9. The method of claim 8,
In forming the temporary slab 200 and the body slab 300,
And a stopper 510 coupled to the deck plate 130 and the gantry 500 to fix the position of the gantry 500,
Wherein the stopper (510) and the gantry (500) are bolted to each other.
A transfer mat constructed by the method of constructing the transfer mat of any one of claims 1 and 5 to 9.
KR1020150091210A 2015-06-26 2015-06-26 Construction method for transfer mat and transfer mat using the same KR101826094B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150091210A KR101826094B1 (en) 2015-06-26 2015-06-26 Construction method for transfer mat and transfer mat using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150091210A KR101826094B1 (en) 2015-06-26 2015-06-26 Construction method for transfer mat and transfer mat using the same

Publications (2)

Publication Number Publication Date
KR20170001351A KR20170001351A (en) 2017-01-04
KR101826094B1 true KR101826094B1 (en) 2018-03-22

Family

ID=57831749

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150091210A KR101826094B1 (en) 2015-06-26 2015-06-26 Construction method for transfer mat and transfer mat using the same

Country Status (1)

Country Link
KR (1) KR101826094B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200075600A (en) 2018-12-18 2020-06-26 삼표피앤씨 주식회사 Method for constructing transfer layer of building using precast concrete slab

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102149661B1 (en) * 2018-12-18 2020-08-31 삼표피앤씨(주) Method for constructing overground transfer layer of building using precast concrete
KR102111883B1 (en) * 2019-04-23 2020-05-18 현대건설주식회사 Construction Method of Transfer girder

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200075600A (en) 2018-12-18 2020-06-26 삼표피앤씨 주식회사 Method for constructing transfer layer of building using precast concrete slab

Also Published As

Publication number Publication date
KR20170001351A (en) 2017-01-04

Similar Documents

Publication Publication Date Title
CN105317137B (en) Precast wall body, wallboard and its construction method and prefabricated panel production method
KR101379305B1 (en) Wall structure manufacturing method using precast front wall panel and precast back wall panel
AU2017304226B2 (en) Precast concrete formwork, floor system and a method of construction
CN103388357B (en) Shatter-proof, prefabricated steel tube shear Temperature Variation In Buildings of Mixed Structures thing
CN103590602B (en) The construction method of cast-in-place concrete hollow building roof
KR101457077B1 (en) Reformed concrete filled tube column structure
CN103806656A (en) Construction method of cast-in-place concrete flat slab built-in thin-wall hollow box body
KR102182536B1 (en) Combined structure of precast columns and beams for construction of warehouse, precast beams used for the same
JP5405337B2 (en) Construction method of railway RC ramen structure viaduct
KR101826094B1 (en) Construction method for transfer mat and transfer mat using the same
CN103410269A (en) Unbonded prestress cast-in-place reinforced concrete hollow slab construction structure and method
CN111576236A (en) Method for mounting integral type prefabricated bridge deck auxiliary structure
KR101334071B1 (en) The needless filling structure in the junction of pc beam and vertical member
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
KR101658929B1 (en) Precast box structure and construction method thereof
CN107237448A (en) A kind of prefabricated interior fill concrete wallboard and its manufacture method
GB2495319A (en) Beam and slab floor construction
KR101345672B1 (en) Unsupported the detachable bracket
KR101118508B1 (en) Construction method and structure of anchored slabstone on concrete
CN203475599U (en) Shock-proof prefabricated building of steel tube shearing wall composite structure
CN104234432B (en) Shed deckhead construction method
KR102222834B1 (en) Slim transfer mat structure and construction method with reverse drop panel
KR101482523B1 (en) Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof
KR101315946B1 (en) Rc construction method for concrete lining in parallel
KR101346671B1 (en) The pin connection structure using the spacer in the junction of pc beam and vertical member

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right