KR101303870B1 - PFP execution method for grating facilities of offshore platform - Google Patents

PFP execution method for grating facilities of offshore platform Download PDF

Info

Publication number
KR101303870B1
KR101303870B1 KR1020110106919A KR20110106919A KR101303870B1 KR 101303870 B1 KR101303870 B1 KR 101303870B1 KR 1020110106919 A KR1020110106919 A KR 1020110106919A KR 20110106919 A KR20110106919 A KR 20110106919A KR 101303870 B1 KR101303870 B1 KR 101303870B1
Authority
KR
South Korea
Prior art keywords
pfp
grating
construction
main support
layer
Prior art date
Application number
KR1020110106919A
Other languages
Korean (ko)
Other versions
KR20130042815A (en
Inventor
주종일
Original Assignee
현대중공업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현대중공업 주식회사 filed Critical 현대중공업 주식회사
Priority to KR1020110106919A priority Critical patent/KR101303870B1/en
Publication of KR20130042815A publication Critical patent/KR20130042815A/en
Application granted granted Critical
Publication of KR101303870B1 publication Critical patent/KR101303870B1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B3/00Hulls characterised by their structure or component parts
    • B63B3/14Hull parts
    • B63B3/66Gratings
    • AHUMAN NECESSITIES
    • A62LIFE-SAVING; FIRE-FIGHTING
    • A62CFIRE-FIGHTING
    • A62C3/00Fire prevention, containment or extinguishing specially adapted for particular objects or places
    • A62C3/07Fire prevention, containment or extinguishing specially adapted for particular objects or places in vehicles, e.g. in road vehicles
    • A62C3/10Fire prevention, containment or extinguishing specially adapted for particular objects or places in vehicles, e.g. in road vehicles in ships
    • CCHEMISTRY; METALLURGY
    • C09DYES; PAINTS; POLISHES; NATURAL RESINS; ADHESIVES; COMPOSITIONS NOT OTHERWISE PROVIDED FOR; APPLICATIONS OF MATERIALS NOT OTHERWISE PROVIDED FOR
    • C09KMATERIALS FOR MISCELLANEOUS APPLICATIONS, NOT PROVIDED FOR ELSEWHERE
    • C09K21/00Fireproofing materials

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Ocean & Marine Engineering (AREA)
  • Organic Chemistry (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Materials Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Revetment (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 해양 또는 육상구조물의 그레이팅 시설에 대한 PFP 시공방법에 관한 것으로서, 더욱 상세하게는 그레이팅을 지지하는 메인지지대의 상면에 그레이팅의 통공이 배치되도록 시공하여 PFP물질에 대한 도포가 상기 통공을 통해 메인지지대의 상면에 도포되도록 함으로써 PFP 시공에 대한 편의성을 증대하고 메인지지대의 상면에 도포된 PFP층의 높이와 그레이팅의 높이가 간편하게 맞춰질 수 있도록 한 해양구조물의 그레이팅 시설에 대한 PFP 시공방법에 관한 것이다.
이를 위해, 해양구조물의 그레이팅 시설에 대한 PFP 시공방법에 있어서, 메인지지대의 상면에 그레이팅의 통공이 배치되도록 시공하고, PFP 물질을 그레이팅에 형성된 통공에 채워넣음으로써 PFP 시공이 완료되도록 한 것을 특징으로 하는 해양구조물의 그레이팅 시설에 대한 PFP 시공방법을 제공한다.
한편, 본 발명은 해양구조물 뿐만 아니라 비슷한 형태의 육상구조물(onshore)에도 적용이 가능하다.
The present invention relates to a method for constructing a PFP for a grating facility of an offshore or onshore structure, and more particularly, the construction of the grating to be disposed on the upper surface of the main support for supporting the grating to apply the coating to the PFP material through the through-hole. The present invention relates to a PFP construction method for a grating facility of an offshore structure in which the convenience of PFP construction is increased by being applied to the upper surface of the main support, and the height of the PFP layer applied on the upper surface of the main support and the grating height can be easily adjusted. .
To this end, in the PFP construction method for the grating facility of the offshore structure, the construction so that the through hole of the grating is disposed on the upper surface of the main support, and the PFP construction is completed by filling the through hole formed in the grating material PFP material It provides a PFP construction method for the grating facility of offshore structures.
On the other hand, the present invention can be applied not only to offshore structures, but also onshore structures of a similar type.

Description

해양구조물의 그레이팅 시설에 대한 PFP 시공방법.{PFP execution method for grating facilities of offshore platform}PFP execution method for grating facilities of offshore platform

본 발명은 해양구조물의 그레이팅 시설에 대한 PFP 시공방법에 관한 것으로서, 더욱 상세하게는 그레이팅 시설에 대한 PFP 시공이 간편하게 이루어질 수 있도록 한 해양구조물의 그레이팅 시설에 대한 PFP 시공방법에 관한 것이다.The present invention relates to a PFP construction method for a grating facility of an offshore structure, and more particularly, to a PFP construction method for a grating facility of an offshore structure to facilitate the construction of the PFP for the grating facility.

일반적으로 그레이팅이라 하면 도로, 주거단지, 지하철, 항만, 해양구조물, 선박 및 각종 플랜트 등에 계단, 보도, 환기통의 집배수 및 횡단용 뚜껑으로 널리 사용하는 건설자재로서 스틸 그레이팅은 재질을 스틸 및 갈바코팅으로 하여 강도가 요구되는 부분에 주로 쓰인다. Generally, grating is widely used as construction material for drainage and crossing of stairs, sidewalks, ventilation troughs, etc. in roads, residential complexes, subway, harbors, offshore structures, ships and various plants. Steel gratings are made of steel and galvanized It is mainly used in areas where strength is required as a coating.

상기 스틸 그레이팅은 해양구조물의 데크에 설치되어, 상방에서는 발판으로 사용되며, 그레이팅이 설치된 하방의 공간에서는 가스 등의 기체가 그레이팅을 통해 배출되도록 하는 역할을 하게 된다.The steel grating is installed on a deck of an offshore structure and is used as a footrest in an upper part. In the lower space where the grating is installed, the steel grating serves to discharge gas such as gas through the grating.

이때, 그레이팅에 대한 설치구조를 도 1을 통해 간략하게 살펴보면 다음과 같다.Here, the installation structure for the grating will be briefly described with reference to FIG.

도 1에 도시된 바와 같이, 메인지지대(10)가 설치되고, 상기 메인지지대(10)를 사이에 두고 그레이팅(20)이 설치된다.As shown in FIG. 1, a main support 10 is installed, and a grating 20 is installed with the main support 10 interposed therebetween.

이때, 그레이팅(20)과 그레이팅(20) 사이에는 상기 그레이팅(20)을 지지하는 서브지지대(30)가 설치되고, 그레이팅(20)과 메인지지대(10)가 만나는 그레이팅(20)의 단부에는 상기 그레이팅(20)의 단부를 지지하는 별도의 보강재(40)가 설치된다.At this time, a sub support 30 for supporting the grating 20 is provided between the grating 20 and the grating 20. At an end of the grating 20 where the grating 20 and the main support 10 meet, A separate stiffener 40 is provided to support the end of the grating 20.

이때, 상기 보강재(40)는 후술하는 PFP(Passive Fire Protection) 시공을 위한 지지대 역할을 하게 되는데, 만약 보강재(40)가 설치되지 않으면 그레이팅(20)의 단부를 지지하는 구조물이 없게 되므로 그레이팅(20)을 딛고 PFP 시공을 하기가 어려워지게 된다.At this time, the stiffener 40 serves as a support for the passive fire protection (PFP) construction described later. If the stiffener 40 is not provided, there is no structure for supporting the end of the grating 20, ) And it becomes difficult to construct the PFP.

한편, 상기한 PFP 시공은 해양 및 육상구조물의 화재 발생시 주요 구조물의 급격한 강도 저하를 방지하고, 대피시간의 확보, 화재의 확산 저지 및 인명과 재산을 보호하기 위한 시공이다.Meanwhile, the above-mentioned PFP construction is a construction for preventing sudden decrease in strength of main structure in case of fire of marine or land structure, securing of evacuation time, prevention of fire spread, protection of life and property.

상기 PFP 시공은 화염이 직접적으로 전달되는 것을 일정시간 유보시키기 위한 시공으로서, 전체 구조물에 시공되기보다는 해양구조물의 주요구조물에만 시공된다.The PFP construction is a construction for keeping the direct delivery of the flame for a certain period of time, and it is applied only to the main structure of the offshore structure rather than the whole structure.

이때, 그레이팅(20)이 설치된 구조물에도 PFP 시공이 이루어지는데, 도 1에 도시된 바와 같이 메인지지대(10)에만 PFP 시공이 이루어지게 된다.At this time, the PFP construction is also performed on the structure in which the grating 20 is installed. As shown in FIG. 1, the PFP construction is performed only on the main support stand 10.

즉, 해양구조물의 주요 구조물인 메인지지대(10)에 PFP 시공이 이루어지도록 하여, 화재가 발생하더라도 메인지지대(10)에 대한 지지력이 일정 기간 확보되도록 함으로써 해양구조물이 단시간 내에 화염에 의해 급격히 무너지지 않도록 한 것이다.That is, the PFP construction is performed on the main support 10, which is a main structure of the offshore structure, so that even if a fire occurs, the support force against the main support 10 can be secured for a certain period so that the offshore structure is not rapidly collapsed by the flame in a short time It is.

이때, PFP 물질은 메인지지대(10)의 외측면을 따라 시공이 된다.At this time, the PFP material is applied along the outer surface of the main support 10.

하지만, 상기한 바와 같이 종래의 그레이팅 구조는 PFP 시공하는데 있어서, 여러가지 문제가 있었다.However, as described above, the conventional grating structure has various problems in PFP construction.

첫째, 해양 구조물 바닥이 플레이트 형태로 구성된 구조는, 구조가 단순하여 저면만 PFP 시공하기 때문에 별문제는 없었으나, 그레이팅 바닥을 PFP 시공하는 경우에는 구조가 복잡하여 추가 보강재가 소요되므로 시공이 어려운 문제가 있었다.First, the structure of the bottom of the marine structure in the form of a plate, because the simple structure, only the bottom of the PFP construction was not a problem, but when the grating flooring PFP construction is difficult because the construction is complicated and additional reinforcement is required there was.

둘째, 바닥을 그레이팅과 PFP 시공을 동시에 하기 위해서는 도 1에 도시된 바와 같이 메인지지대(10)의 양측에 보강재(40)를 별도로 설치하여 그레이팅(20)과 PFP층을 분리해야할 뿐만 아니라, 시공된 PFP층의 높이와 그레이팅(20)의 높이가 동일하도록 시공이 이루어져야 하는바, 이러한 PFP 작업은 수작업으로 이루어지기 때문에 시공의 어려움이 있었다.Second, in order to simultaneously grating the floor and PFP construction, as shown in FIG. 1, the reinforcing material 40 must be separately installed on both sides of the main support 10 to separate the grating 20 and the PFP layer. Construction should be made so that the height of the PFP layer and the height of the grating 20 is the same, there was a difficulty in construction because such a PFP work is made by hand.

특히, 시공된 PFP층의 높이와 그레이팅(20)의 높이를 동일하게 시공하는 것은 매우 어려운 문제였다.In particular, it was very difficult to construct the same height of the constructed PFP layer and the height of the grating 20.

왜냐하면, PFP 시공을 하기 위해서는 미장을 통해 마감해야 하는바, 상기 미장작업을 통해 시공된 PFP 코팅층과 그레이팅(20)의 높이를 정확하게 맞추기 어려웠던 것이다.Because, in order to PFP construction should be finished through the plastering, it was difficult to accurately match the height of the PFP coating layer and the grating 20 constructed through the plastering work.

이와 같이, PFP 코팅층과 그레이팅(20)의 높이가 동일하지 않을 경우, 그레이팅(20)을 지나다니는 장비의 간섭 및 충격에 의해 PFP 코팅층이 손상되는 문제가 발생하게 된다.As such, when the heights of the PFP coating layer and the grating 20 are not the same, a problem occurs that the PFP coating layer is damaged by the interference and impact of the equipment passing through the grating 20.

셋째, 메인지지대(10)의 상부 측면(플랜지)과 그레이팅(20) 및 보강재(40) 사이의 간격(T:대략 20mm정도))이 좁아 상기 메인지지대(10)의 플랜지 부위는 PFP 시공하기가 매우 어려운 문제가 있었다.Third, the gap between the upper side (flange) of the main support 10 and the grating 20 and the reinforcing material 40 (T: about 20mm) is narrow, so that the flange portion of the main support 10 is PFP construction There was a very difficult problem.

본 발명은 상기한 문제점을 해결하기 위하여 안출된 것으로서, 본 발명의 목적은 메인지지대의 상면에 그레이팅을 설치하여 그레이팅의 통공에 PFP 물질을 채워넣는 시공이 이루어지도록 함으로써 메인지지대에 대한 PFP 시공의 편의성을 증대하고, 시공된 PFP층의 높이와 그레이팅의 높이가 용이하게 맞춰질 수 있도록 한 해양구조물 그레이팅의 PFP 시공방법을 제공하고자 한 것이다.The present invention has been made to solve the above problems, the object of the present invention is to install the grating on the upper surface of the main support to make the construction of filling the PFP material in the through hole of the grating by the convenience of PFP construction for the main support It is to provide a method of constructing the PFP of offshore structure grating to increase the height of the constructed PFP layer and easy to match the grating height.

본 발명은 상기한 목적을 달성하기 위하여, 해양구조물의 그레이팅 시설에 대한 PFP 시공방법에 있어서, 메인지지대의 상면에 그레이팅의 통공이 배치되도록 시공하고, PFP 물질을 그레이팅에 형성된 통공에 채워넣음으로써 PFP 시공이 완료되도록 하되, 상기 PFP 시공방법은, 메인지지대의 표면에 블라스팅 처리하는 블라스팅 단계;메인지지대의 상면을 제외한 표면에 코팅하는 코팅단계;메인지지대의 상면을 제외한 표면에 PFP물질을 도포하는 1차 도포단계;PFP물질이 도포된 PFP 물질을 미장하는 미장단계;1차 도포된 PFP층에 메시(mesh)를 설치하는 메시 설치 단계;1차 도포된 PFP층을 건조하는 건조단계;메인지지대의 상면을 제외한 표면에 PFP물질을 도포하는 2차 도포단계;2차 도포된 PFP층을 건조하는 건조단계;상기와 같이 PFP 시공된 메인지지대의 상면에 그레이팅의 통공이 배치되도록 시공하는 그레이팅 시공단계;PFP 물질을 그레이팅의 통공을 향해 분사하여, PFP물질이 메인지지대의 상면에 도포되도록 한 PFP 도포단계;그레이팅의 상면에 도포된 PFP 물질을 미장하여 PFP층의 높이와 그레이팅의 높이를 동일하게 맞추는 미장단계:를 포함하여 구성된 해양구조물의 그레이팅 시설에 대한 PFP 시공방법을 제공한다.In order to achieve the above object, the present invention, in the construction method of the PFP for the grating facility of the offshore structure, the construction so that the through hole of the grating is disposed on the upper surface of the main support, by filling the through hole formed in the grating PFP material PFP The construction is completed, but the PFP construction method, the blasting step of blasting on the surface of the main support; coating step of coating on the surface except the upper surface of the main support; 1 to apply a PFP material on the surface except the upper surface of the main support Primary coating step; Plastering step of plastering the PFP material coated PFP material; Mesh installation step of installing a mesh (mesh) on the first applied PFP layer; Drying step of drying the first applied PFP layer; Secondary coating step of applying a PFP material to the surface other than the upper surface; Drying step of drying the second applied PFP layer; As shown above on the upper surface of the main support A grating construction step for constructing the through-hole of the rating; PFP coating step of spraying the PFP material toward the hole of the grating, to apply the PFP material to the upper surface of the main support; Provides a method of constructing PFP for a grating facility consisting of offshore structures, including: Plastering stages, where the height of the layer is equal to the height of the grating.

삭제delete

이때, 상기 2차 도포된 PFP층을 건조하는 건조단계 후에, 스티플 스프레이(stipple spray)를 도포하여 외관 균일 작업을 수행하는 외관 균일 작업단계를 수행하는 것이 바람직하다.At this time, after the drying step of drying the second applied PFP layer, it is preferable to perform an appearance uniform work step of applying a stipple spray to perform an appearance uniform work.

본 발명에 따른 해양구조물의 그레이팅 시설에 대한 PFP 시공방법은 다음과 같은 효과가 있다.PFP construction method for the grating facility of the offshore structure according to the present invention has the following effects.

첫째, PFP 시공을 하기 위한 별도의 보강재를 설치할 필요가 없기 때문에, 그레이팅의 설치구조가 간편해지므로, 시공작업이 간편해지는 효과가 있다.First, since there is no need to install a separate reinforcing material for the PFP construction, since the installation structure of the grating is simplified, there is an effect that the construction work is simplified.

즉, 메인지지대가 그레이팅을 지지하고 있는 구조이기 때문에, 그레이팅을 지지하기 위한 별도의 보강재는 필요없게 되는 것이다.That is, since the main support is a structure supporting the grating, a separate reinforcement for supporting the grating is not necessary.

둘째, 메인지지대의 상부에 그레이팅이 설치된 상태에서, PFP 시공을 위한 물질을 그레이팅의 통공에 채워넣기만 하면 되므로, PFP 시공이 간편해지는 효과가 있다.Second, in the state in which the grating is installed on the upper portion of the main support, it is only necessary to fill the through hole of the grating material for the PFP construction, there is an effect that the PFP construction is easy.

나아가, 공기가 단축되므로 작업 생산성이 높아지는 효과가 있다.Furthermore, since the air is shortened, the work productivity is increased.

셋째, 메인지지대의 상면을 제외한 표면이 외부에 노출되어 있으므로, 메인지지대의 표면에 대한 PFP 시공 역시 안정성 및 편의성이 증대되는 효과가 있다. Third, since the surface except the upper surface of the main support is exposed to the outside, PFP construction on the surface of the main support also has the effect of increasing stability and convenience.

도 1은 종래의 그레이팅 구조를 나타낸 측단면도
도 2는 본 발명의 바람직한 실시예에 따른 해양구조물의 그레이팅 시설에 대한 PFP 시공방법을 나타낸 순서도
도 3은 본 발명의 바람직한 실시예에 따른 그레이팅 구조를 나타낸 측단면도
도 4는 본 발명의 바람직한 실시예에 따른 해양구조물의 그레이팅 시설에 대한 PFP 시공방법을 통해 형성된 코팅층을 나타낸 단면도.
Figure 1 is a side cross-sectional view showing a conventional grating structure
Figure 2 is a flow chart showing a PFP construction method for the grating facility of the offshore structure according to a preferred embodiment of the present invention
Figure 3 is a side cross-sectional view showing a grating structure according to a preferred embodiment of the present invention
Figure 4 is a cross-sectional view showing a coating layer formed through the PFP construction method for the grating facility of the offshore structure according to an embodiment of the present invention.

본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정 해석되지 아니하며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.It is to be understood that the words or words used in the present specification and claims are not to be construed in a conventional or dictionary sense and that the inventor can properly define the concept of a term in order to describe its invention in the best possible way And should be construed in light of the meanings and concepts consistent with the technical idea of the present invention.

이하, 첨부된 도 2 내지 도 4를 참조하여 본 발명의 바람직한 실시예에 따른 해양구조물의 그레이팅 시설에 대한 PFP 시공방법(이하, 'PFP 시공방법'이라 함)에 대하여 설명하도록 한다.Hereinafter, a PFP construction method (hereinafter, referred to as a 'PFP construction method') for a grating facility of an offshore structure according to a preferred embodiment of the present invention will be described with reference to FIGS. 2 to 4.

PFP 시공방법은 해양구조물에 화재 발생시, 화염에 의한 주요 구조물의 급격한 강도 저하를 방지하기 위한 PFP 시공에 대한 편의성을 증대하고, 주요 구조물에 시공된 PFP 코팅층의 높이와 그레이팅의 높이를 용이하게 맞출 수 있도록 한 기술적 특징이 있다.PFP construction method can increase convenience for PFP construction to prevent sudden drop in strength of main structures due to flames in case of fire in offshore structures, and can easily match the height of grating with the height of PFP coating layer installed in main structures. There is one technical feature.

이하, 도 2를 참조하여 본 발명의 바람직한 실시예에 따른 PFP 시공방법에 대하여 설명하도록 한다Hereinafter, a PFP construction method according to a preferred embodiment of the present invention will be described with reference to FIG. 2.

먼저, 메인지지대(10)의 표면(이때에는 메인지지대의 상면도 포함)을 블라스팅(blasting) 처리한다.(S10)First, the surface of the main support 10 (in this case, including the upper surface of the main support) is blasted. (S10)

이는 녹을 제거하여 후술하는 PFP 물질의 흡착이 효율적으로 이루어질 수 있도록 하기 위함이다.This is to remove the rust so that the adsorption of the PFP material to be described later can be made efficiently.

다음으로, 블라스팅 처리된 메인지지대(10)의 표면에 2회에 걸쳐 코팅(도장)작업을 수행한다.(S11)Next, the coating (painting) is performed twice on the surface of the blasted main support 10. (S11)

이때, 코팅층의 두께는 DFT(코팅두께 측정기) 110㎛ 이하인 것이 바람직하다.At this time, the thickness of the coating layer is preferably DFT (coating thickness meter) 110㎛ or less.

다음으로, 메인지지대(10)의 표면을 크리닝한 후에, PFP 시공을 하지 않는 다른 부위에 PFP 물질이 튀지 않도록 마스킹 작업을 실시한다.(S12)Next, after cleaning the surface of the main support 10, the masking operation is performed to prevent the PFP material from splashing on other portions where the PFP is not constructed. (S12)

다음으로, 메인지지대(10)의 표면에 PFP 물질을 스프레이로 도포하는 작업을 1차로 수행한다.(S13)Next, the operation of spraying the PFP material on the surface of the main support 10 with a spray is primarily performed. (S13)

이때, PFP 물질은 에폭시 팽창제품, 시멘트 type, 미네랄 울 등으로 제공될 수 있다.In this case, the PFP material may be provided as an epoxy expanded product, cement type, mineral wool, or the like.

한편, PFP 시공시 작업 환경으로는 작업장(도장 shop)의 대기온도는 10℃이상임이 바람직하며, 대기습도는 85% 이하임이 바람직하다.On the other hand, in the work environment at the time of PFP construction, the air temperature of the workplace (painting shop) is preferably 10 ℃ or more, the atmospheric humidity is preferably 85% or less.

또한, 작업할 부위의 철판온도는 이슬점보다 3℃ 이상인 것이 바람직하다.Moreover, it is preferable that the iron plate temperature of the site | part to be worked is 3 degreeC or more than dew point.

다음으로, 상기한 바와 같이 PFP 물질에 대한 1차 도포 작업이 완료되면, 작업자는 흙손을 이용하여 메인지지대(10)에 도포된 PFP 물질에 대하여 미장작업을 실시한다.(S14)Next, as described above, when the primary coating operation on the PFP material is completed, the operator performs a plastering operation on the PFP material applied to the main support 10 using a trowel.

이는, 메인지지대(10)의 표면에 도포된 PFP 물질이 상기 메인지지대(10)의 표면에 고르고 균일하게 흡착되도록 하기 위함이다.This is to allow the PFP material applied on the surface of the main support 10 to be evenly and uniformly adsorbed on the surface of the main support 10.

다음으로, PFP 물질이 1차로 도포되어 형성된 1차 PFP층에 메시(mesh)를 설치한다.(S15)Next, a mesh is installed on the primary PFP layer formed by applying the PFP material first. (S15)

이는, 해양 구조물에 화재가 발생되어 화염이 PFP층에 전달되더라도, 고온에 의한 PFP층(숯:charcoal)이 일그러지는 것을 방지하기 위함이다.This is to prevent the PFP layer (charcoal) from being distorted due to high temperature even when a fire occurs in the marine structure and the flame is transferred to the PFP layer.

즉, 메시는 PFP층(숯:charcoal)이 일그러지지 않도록 뼈대 역할을 하는 것이다.In other words, the mesh serves as a skeleton so that the PFP layer (charcoal) is not distorted.

다음으로, 롤러 작업을 통해 1차로 도포된 PFP층에 메시에 대한 흡착을 극대화한다.(S16)Next, to maximize the adsorption of the mesh to the PFP layer applied primarily through the roller operation. (S16)

즉, PFP층과 메시 간에 틈이 발생하지 않도록 하여 메시의 역할을 극대화하기 위한 것이다.In other words, the gap is not maximized between the PFP layer and the mesh to maximize the role of the mesh.

다음으로, 1차로 도포된 PFP층을 상온 또는 겨울철에는 히터를 이용하여 약 1일간 건조시키는 과정을 수행한다.(S17)Next, a process of drying the first applied PFP layer at room temperature or in winter using a heater is performed for about one day. (S17)

다음으로, 1차로 도포된 PFP층의 건조가 완료되면, 1차 PFP층 위에 2차로 PFP 물질을 스프레이로 도포시킨다.(S18) Next, when the drying of the first applied PFP layer is completed, the PFP material is sprayed on the primary PFP layer by spraying (S18).

다음으로, PFP 물질에 대한 2차 도포 작업이 완료되면, 작업자는 1차 도포 작업때와 마찬가지로 흙손을 이용하여 1차 PFP층에 도포된 2차 PFP 물질에 대하여 미장작업을 실시한다.(S19)Next, when the secondary coating operation on the PFP material is completed, the operator performs a plastering operation on the secondary PFP material applied to the primary PFP layer using a trowel as in the first application operation.

다음으로, 2차로 도포된 PFP층을 상온 또는 겨울철에는 히터를 이용하여 약 1일간 건조시키는 과정을 수행한다.Next, the process of drying the second applied PFP layer at room temperature or winter using a heater for about one day.

다음으로, 2차 PFP층의 건조가 완료되면, PFP층의 외관이 고르게 보이도록 외관 균일 작업을 실시한다.(S20)Next, when drying of the secondary PFP layer is completed, the appearance uniformity operation is performed so that the appearance of the PFP layer is evenly seen. (S20)

이는, 숙련공이라 하더라도 미장작업에 의한 PFP층의 표면은 완벽하게 고르고 균일하게 제공되기 어려운바, 스티플 스프레이(stipple spray)를 도포하여 시각적으로 PFP층의 외관이 균일하게 보이도록 한 것이다.This means that even a skilled worker can hardly provide a uniform and uniform surface of the PFP layer by a plastering operation, so that the appearance of the PFP layer can be visually seen by applying a stipple spray.

상기 스티플 스프레이는 도포액이 2차 PFP층에 도트(dot) 형태로 분사되도록 하여, 시각적으로 2차 PFP층의 표면이 고르게 보이도록 하기 위함이다.The stifle spray is to spray the coating liquid in the form of a dot (dot) to the secondary PFP layer, so that the surface of the secondary PFP layer visually looks even.

다음으로, 주변 구조물에 붙인 마스킹을 제거하는 작업을 실시한다.(S21)Next, to remove the masking attached to the surrounding structure is carried out (S21).

다음으로, PFP층에 대한 시공이 잘 마무리가 되었는지 최종 검사를 수행한다.(S22)Next, a final inspection is performed to see if the construction of the PFP layer is well finished (S22).

다음으로, 주변의 구조물과 동일 색상으로 어우러질 수 있도록 탑 코팅을 수행한다.(S23)Next, the top coating is performed so that the structures can be combined with the same color. (S23)

이때, 탑 코팅은 2회에 걸쳐 수행되며, 도 4에 도시된 바와 같이 에폭시층과 우레탄층으로 코팅이 이루어지게 된다.At this time, the top coating is performed twice, and the coating is made of an epoxy layer and a urethane layer as shown in FIG. 4.

다음으로, 상기와 같이 메인지지대(10)의 상면을 제외한 표면의 PFP 시공이 완료되면, 메인지지대(10)를 도장 작업장으로부터 인출하여 그레이팅 시공을 수행한다.Next, when the PFP construction of the surface except the upper surface of the main support 10 is completed as described above, the main support 10 is taken out from the painting workshop to perform the grating construction.

이때, 메인지지대(10)는 도 2에 도시된 바와 같이, 지면에 대하여 수직으로 설치되고, 상기 메인지지대(10)의 상부에는 그레이팅(20)이 설치된다.At this time, as shown in Figure 2, the main support 10 is installed perpendicular to the ground, the grating 20 is installed on the upper portion of the main support (10).

이때, 그레이팅 고정은 전동드릴에 의한 고정 또는 부분용접에 의해 고정된다.At this time, the grating fixed is fixed by a fixed or partial welding by a power drill.

이에 따라, 그레이팅(20)에 형성되어 있는 복수의 통공(21)을 통해 메인지지대의 상면은 외부로 노출된 상태가 된다.Accordingly, the upper surface of the main support is exposed to the outside through the plurality of through holes 21 formed in the grating 20.

이때, 메인지지대(10)의 상부에 설치된 그레이팅(20)의 좌,우측 방향으로 복수의 그레이팅(20)이 연이어 설치되며, 연이어 설치된 그레이팅(20)의 하부에는 서브지지대(30)가 설치되어 상기 그레이팅(20)을 지지하게 된다.At this time, a plurality of gratings 20 are successively installed in the left and right directions of the grating 20 installed on the upper part of the main support 10, and the sub supporters 30 are installed at the lower parts of the gratings 20 which are successively installed. The grating 20 is supported.

이와 같은 구조는 전술한 종래 기술과는 다르게, 별도의 보강재가 설치되어 있지 않음을 알 수 있다.This structure is different from the above-described prior art, it can be seen that no separate reinforcement is installed.

이와 같이 그레이팅에 대한 시공이 완료되면, PFP 시공이 이루어지지 않은 메인지지대(10)의 상면에 대한 PFP 시공을 실시한다.When the construction for the grating is completed as described above, the PFP construction is performed on the upper surface of the main support 10 on which the PFP construction is not made.

이를 위해 먼저, 스프레이를 이용해 PFP 물질을 메인지지대(10)의 상면을 향해 도포한다.(S25) To this end, first spray the PFP material toward the upper surface of the main support 10 using a spray (S25).

이때, PFP 물질은 그레이팅(20)에 형성된 통공(21)을 통해 메인지지대(10)의 상면에 도포되며, 상기 PFP물질은 그레이팅(20) 통공(21)에 채워지게 된다.At this time, the PFP material is applied to the upper surface of the main support 10 through the through hole 21 formed in the grating 20, the PFP material is filled in the grating 20 through the hole (21).

다음으로, 작업자는 흙손을 이용하여 도포된 PFP 물질에 대한 미장작업을 실시한다.(S26)Next, the operator performs a plastering operation on the applied PFP material using a trowel. (S26)

이때, PFP 물질은 그레이팅(20)의 통공(21)을 구획하는 격벽에 의해 가이드됨에 따라, PFP층의 높이와 그레이팅의 높이가 용이하게 맞추어 지므로 시공이 간편해질 수 있다.At this time, as the PFP material is guided by the partition wall partitioning the through hole 21 of the grating 20, the construction can be simplified because the height of the PFP layer and the height of the grating are easily matched.

이때, PFP층과 그레이팅(20)의 높이가 동일하게 유지됨에 따라, 그레이팅(20)을 지나는 장비와의 충격 및 간섭이 발생하지 않음으로써 PFP층이 손상되는 일은 발생하지 않게 된다.At this time, as the heights of the PFP layer and the grating 20 are kept the same, the PFP layer is not damaged by the impact and the interference with the equipment passing through the grating 20 does not occur.

이후, 건조 과정 및 탑 코팅 과정을 통해, 메인지지대의 상면에 대한 PFP 시공이 완료된다.Then, through the drying process and the top coating process, the PFP construction on the upper surface of the main support is completed.

지금까지 설명한 바와 같이, 본 발명에 따른 PFP 시공방법은 해양구조물의 주요구조물에 대한 PFP 시공을 하는 것에 있어서, 그레이팅이 시공된 메인지지대의 상면에 대한 PFP 시공이 간편하게 이루어질 수 있으며, PFP층의 수명을 오랫동안 유지할 수 있는 기술적 특징이 있다.As described so far, in the PFP construction method according to the present invention, in the PFP construction of the main structure of the offshore structure, the PFP construction on the upper surface of the main support grafting can be made easily, the lifetime of the PFP layer There is a technical characteristic that can maintain a long time.

이상에서 본 발명은 기재된 구체예에 대하여 상세히 설명되었지만 본 발명의 기술사상 범위 내에서 다양한 변형 및 수정이 가능함은 당업자에게 있어서 명백한 것이며, 이러한 변형 및 수정은 첨부된 특허 청구범위에 속함은 당연한 것이다.While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is evident that many alternatives, modifications and variations will be apparent to those skilled in the art.

10 : 메인지지대 20 : 그레이팅
21 : 통공 30 : 서브 지지대
40 : 보강재
10: main support 20: grating
21: through hole 30: sub support
40: reinforcement

Claims (3)

삭제delete 해양구조물의 그레이팅 시설에 대한 PFP 시공방법에 있어서, 메인지지대의 상면에 그레이팅의 통공이 배치되도록 시공하고, PFP 물질을 그레이팅에 형성된 통공에 채워넣음으로써 PFP 시공이 완료되도록 하되, 상기 PFP 시공방법은,
메인지지대의 표면에 블라스팅 처리하는 블라스팅 단계;
메인지지대의 상면을 제외한 표면에 코팅하는 코팅단계;
메인지지대의 상면을 제외한 표면에 PFP물질을 도포하는 1차 도포단계;
PFP물질이 도포된 PFP 물질을 미장하는 미장단계;
1차 도포된 PFP층에 메시(mesh)를 설치하는 메시 설치 단계;
1차 도포된 PFP층을 건조하는 건조단계;
메인지지대의 상면을 제외한 표면에 PFP물질을 도포하는 2차 도포단계;
2차 도포된 PFP층을 건조하는 건조단계;
상기와 같이 PFP 시공된 메인지지대의 상면에 그레이팅의 통공이 배치되도록 시공하는 그레이팅 시공단계;
PFP 물질을 그레이팅의 통공을 향해 분사하여, PFP물질이 메인지지대의 상면에 도포되도록 한 PFP 도포단계;
그레이팅의 상면에 도포된 PFP 물질을 미장하여 PFP층의 높이와 그레이팅의 높이를 동일하게 맞추는 미장단계:를 포함하여 구성된 해양구조물의 그레이팅 시설에 대한 PFP 시공방법.
In the PFP construction method for the grating facility of the offshore structure, the construction so that the through hole of the grating is disposed on the upper surface of the main support, and filling the through hole formed in the grating PFP construction to complete the PFP construction method, ,
A blasting step of blasting the surface of the main support;
Coating step of coating on the surface except the upper surface of the main support;
A first application step of applying the PFP material to the surface except the upper surface of the main support;
A plastering step of plastering the PFP material to which the PFP material is applied;
A mesh installation step of installing a mesh on the first applied PFP layer;
Drying step of drying the first applied PFP layer;
A second coating step of applying the PFP material to the surface except the upper surface of the main support;
Drying step of drying the second applied PFP layer;
A grating construction step of constructing the through-hole of the grating on the upper surface of the main support plate which has been constructed as described above;
PFP application step of spraying the PFP material toward the through hole of the grating, so that the PFP material is applied to the upper surface of the main support;
Plastering step of plastering the PFP material applied on the upper surface of the grating to match the height of the PFP layer and the grating height: PFP construction method for the grating facility of the marine structure consisting of.
제 2항에 있어서,
상기 2차 도포된 PFP층을 건조하는 건조단계 후에, 스티플 스프레이(stipple spray)를 도포하여 외관 균일 작업을 수행하는 외관 균일 작업단계를 수행하는 것을 특징으로 하는 해양구조물의 그레이팅 시설에 대한 PFP 시공방법.
The method of claim 2,
After the drying step of drying the second applied PFP layer, PFP construction for the grating facility of the offshore structure, characterized in that to perform a uniform appearance step of applying a stipple spray to perform the uniform appearance operation Way.
KR1020110106919A 2011-10-19 2011-10-19 PFP execution method for grating facilities of offshore platform KR101303870B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110106919A KR101303870B1 (en) 2011-10-19 2011-10-19 PFP execution method for grating facilities of offshore platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110106919A KR101303870B1 (en) 2011-10-19 2011-10-19 PFP execution method for grating facilities of offshore platform

Publications (2)

Publication Number Publication Date
KR20130042815A KR20130042815A (en) 2013-04-29
KR101303870B1 true KR101303870B1 (en) 2013-09-04

Family

ID=48441297

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110106919A KR101303870B1 (en) 2011-10-19 2011-10-19 PFP execution method for grating facilities of offshore platform

Country Status (1)

Country Link
KR (1) KR101303870B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200137597A (en) 2019-05-31 2020-12-09 삼성중공업 주식회사 Heat resisting support and support installing method
KR20210071178A (en) 2019-12-05 2021-06-16 삼성중공업 주식회사 Grating facilities of offshore platform

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101601930B1 (en) 2014-06-05 2016-03-10 삼성중공업 주식회사 Apparatus for painted surface treatment
GB2554075B (en) * 2016-09-15 2021-05-19 Equinor Energy As Optimising fire protection for an offshore platform
GB2554077B (en) 2016-09-15 2021-05-19 Equinor Energy As Handling of hydrocarbons on an offshore platform
GB2560378B (en) 2017-03-10 2022-05-18 Equinor Energy As Power supply system for an offshore platform

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6285790A (en) * 1985-10-09 1987-04-20 Ishikawajima Harima Heavy Ind Co Ltd Transport ship for purified petroleum product
JPH02103415A (en) * 1988-10-12 1990-04-16 Mitsutoyo Corp Photoelectric displacement detector
KR20030006599A (en) * 2001-07-13 2003-01-23 주식회사 해광 The process of producing and production for conduction grate panel
KR20100020824A (en) * 2008-08-13 2010-02-23 삼성중공업 주식회사 Manufacturing method of fireproof panel for ship and firewall construction method for ship
KR20120134350A (en) * 2011-06-02 2012-12-12 삼성중공업 주식회사 Marine structure including grating

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6285790A (en) * 1985-10-09 1987-04-20 Ishikawajima Harima Heavy Ind Co Ltd Transport ship for purified petroleum product
JPH02103415A (en) * 1988-10-12 1990-04-16 Mitsutoyo Corp Photoelectric displacement detector
KR20030006599A (en) * 2001-07-13 2003-01-23 주식회사 해광 The process of producing and production for conduction grate panel
KR20100020824A (en) * 2008-08-13 2010-02-23 삼성중공업 주식회사 Manufacturing method of fireproof panel for ship and firewall construction method for ship
KR20120134350A (en) * 2011-06-02 2012-12-12 삼성중공업 주식회사 Marine structure including grating

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200137597A (en) 2019-05-31 2020-12-09 삼성중공업 주식회사 Heat resisting support and support installing method
KR20210071178A (en) 2019-12-05 2021-06-16 삼성중공업 주식회사 Grating facilities of offshore platform

Also Published As

Publication number Publication date
KR20130042815A (en) 2013-04-29

Similar Documents

Publication Publication Date Title
KR101303870B1 (en) PFP execution method for grating facilities of offshore platform
TWI673418B (en) External wall cantilever construction platform and its assembly method
CN111042573A (en) Construction method and structure for additionally arranging lift apartment sandwich floor without dehumidification operation
JPWO2007023656A1 (en) Treatment method and reinforcement method of slate surface, reinforcement slate, construction method of surface treatment or reinforcement work, and roof work column
CN103276840A (en) Nuclear power plant composite floor slab module and construction method thereof
JP6282066B2 (en) Protective net fence for building and construction method of protective net fence for building
JP6768286B2 (en) Fireproof coating structure and fireproof coating method
TWM529726U (en) High tech factory return air floor template
JP2012112151A (en) Seismic strengthening method for roof
JP6368538B2 (en) Fireproof frame structure
CN205857443U (en) A kind of shaped steel fireproof construction of steel building
FI127264B (en) Staircase elements and procedure for building stairwells
JP3728661B2 (en) Peripheral curing device and peripheral curing method for building attached structures
JP2010024811A (en) Steel construction improving fire-resistive performance
CN107165478A (en) A kind of reusable assembling type enclosing shield unit
KR100903151B1 (en) Cover element for fireproof process
CN206859841U (en) A kind of reusable assembling type enclosing shield unit
JP7122080B2 (en) temporary scaffolding
KR102145286B1 (en) Soundproof wall with polyurea-coated column and repairing method thereof
JP2011084932A (en) Method of repairing existing steel stairway
KR101034190B1 (en) Water tank storage of sts pannel and a support, joint uses inorganic coated layer having high hardness
JP2012127106A (en) Curing facility of lower equipment present near high-rise structure and construction method of curing facility of lower equipment
JP6993904B2 (en) How to coat the refractory coating material on the steel column
JP2018168662A (en) Construction method of building
CN105220878A (en) Movable Scaffold is utilized to carry out combining maintenance storehouse finishing and pipeline construction method of installation

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160728

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170801

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee