KR100797185B1 - Construction method and the apparatus of a ground retaining structures or walls - Google Patents

Construction method and the apparatus of a ground retaining structures or walls Download PDF

Info

Publication number
KR100797185B1
KR100797185B1 KR1020070090103A KR20070090103A KR100797185B1 KR 100797185 B1 KR100797185 B1 KR 100797185B1 KR 1020070090103 A KR1020070090103 A KR 1020070090103A KR 20070090103 A KR20070090103 A KR 20070090103A KR 100797185 B1 KR100797185 B1 KR 100797185B1
Authority
KR
South Korea
Prior art keywords
steel
pile
steel pile
piles
steel piles
Prior art date
Application number
KR1020070090103A
Other languages
Korean (ko)
Inventor
배명제
윤가호
임해식
이광호
장해동
Original Assignee
대한주택공사
(주)만선지오쓰
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대한주택공사, (주)만선지오쓰 filed Critical 대한주택공사
Application granted granted Critical
Publication of KR100797185B1 publication Critical patent/KR100797185B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0216Cribbing walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083Shoring struts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

An apparatus and a method for constructing a soil retaining wall are provided to prevent accidents by installing prefabricated steel piles to a soil retaining wall dually and supporting the soil retaining wall strongly, thereby preventing a soil retaining wall or a steel pile from being broken or pushed by earth pressure, and to secure the recycling efficiency of construction equipment, the safety of a building and work efficiency by removing the dually constructed steel piles simply after the construction of a building. An apparatus for constructing a soil retaining wall comprises many first steel piles(11) equipped with soil retaining plate grooves at two sides in the shape of an H-beam and installed on the ground at the soil surface at regular intervals, many second steel piles(12) equipped with soil retaining plate grooves at two sides in the shape of an H-beam and supporting the first steel piles respectively, many soil retaining plates(20) fitted to the soil retaining plate grooves of the first steel piles or the second steel piles in a horizontal direction, many first pile assemblies assembling the second steel piles to the first steel piles, and many steel pile stiffeners(60) installed perpendicular to the second steel piles to connect and support the second steel piles. A method for constructing a soil retaining wall comprises the steps of: reinforcing a soil retaining wall primarily by driving many first steel piles to the ground at the soil surface and fastening many soil retaining plates to soil retaining plate grooves of the first steel piles in a horizontal direction; reinforcing the soil retaining wall dually by placing second steel piles correspondingly to the first steel piles and assembling the first steel piles and the second steel piles using first pile assemblies; keeping the distance between second steel piles and reinforcing the soil retaining wall by inserting many soil retaining plates between the second steel piles in a horizontal direction; installing a soil nail(50) to the dually reinforced soil retaining wall by the first pile assemblies; and connecting and supporting the second steel piles by installing many steel pile stiffeners perpendicular to the second steel piles.

Description

옹벽용 또는 흙막이용 토류벽 조성장치 및 방법{Construction method and the apparatus of a ground retaining structures or walls}Construction method and the apparatus of a ground retaining structures or walls}

본 발명은 옹벽용 또는 흙막이용 토류벽을 이중으로 보강하는 장치 및 방법에 관한 것으로서, 더욱 상세하게는 건축물의 기초 터파기 후 절토면 또는 성토면의 측벽에 구축되어 경사면을 안정화시키는 토류벽에 이중 강재말뚝을 조립하여 토류벽이 토압에 의해 붕괴되거나 밀리는 것을 방지할 수 있도록 하여 인명사고 등을 효과적으로 예방하고 또한 건축물 시공 후 필요시 이중 강재말뚝을 간단하게 분해하여 제거할 수 있도록 함으로써 건축물의 안전성 확보 및 작업 효율성을 향상시킬 수 있는 옹벽용 또는 흙막이용 토류벽 조성장치 및 방법에 관한 것이다. The present invention relates to a device and a method for reinforcing a double earth wall for retaining wall or retaining wall. More specifically, a double steel pile is installed on the earth wall for stabilizing the slope by being built on the cut surface or the side wall of the earth surface after foundation destruction of the building. By assembling to prevent the earth wall from collapsing or being pushed by earth pressure, it can effectively prevent human accidents, and it is possible to simply disassemble and remove the double steel pile when necessary after construction to secure the safety of the building and work efficiency. The present invention relates to an earth wall forming apparatus and method for a retaining wall or a retaining wall which can be improved.

일반적으로 산비탈이나 언덕에 콘크리트구조물의 축조를 위한 지반 굴착공사 실시하거나 또는 새로운 토지를 조성하거나 또는 도로 및 철도를 개설하거나 또는 자연 재해 등에 의한 경사면의 훼손 등이 발생되는 경우, 토지의 굴착면 또는 조성면 또는 절개면의 토사붕괴, 침하방지, 변위억제를 위해서는 해당 지역의 경사면에 보강구조를 설치하여 인접지반의 안정성을 유지할 수 있게 된다.In general, when excavation works such as ground excavation works for construction of concrete structures on hillsides or hills, new lands, roads and railroads, or damage to slopes due to natural disasters occur, Or in order to maintain the stability of the adjacent ground by installing a reinforcement structure on the inclined surface of the area in order to prevent soil disintegration, settlement, and displacement of the cut surface.

도 1은 종래 토류벽 공법에 의한 보강구조의 한 예를 도시한 것으로서, 도면 에 도시된 바와 같이, 양측에 토류판 요입부(10a)가 구비된 "H"형의 강재말뚝(10)을 일정간격으로 이격시켜 지반에 타설한 후 상기 다수의 강재말뚝(10)사이에 다수 개의 토류판(20)을 횡방향으로 설치하여, 강재말뚝(10)과 토류판(20)으로 구성되는 토류벽을 형성함으로써 이러한 토류벽 보강구조에 의해 토사의 붕괴를 막아줄 수 있도록 구성되어 있다.1 shows an example of a reinforcing structure by the conventional earth wall method, and as shown in the drawing, the steel pile 10 of the “H” type provided with the earth plate recesses 10a on both sides at regular intervals. After placing in the ground by spaced apart between the plurality of steel piles (10) by installing a plurality of earth plate 20 in the transverse direction, by forming the earth wall consisting of the steel pile 10 and the earth plate 20 to reinforce such earth wall It is structured to prevent the collapse of soil by the structure.

그러나, 상기 보강구조는 다수개의 토류판(20)이 별도의 지지구조 없이 단순히 강재말뚝(10)의 토류판 요입부(10a)에 끼워져 고정되는 형태로서, 토류판(20) 자체의 강성만으로 토압에 견디도록 한 것이기 때문에 토압이 작용하게 되면 토류판(20)의 자체 강성만으로는 이를 견디지 못하여 그대로 절단되면서 대형 참사로 이어지는 사고가 발생하게 되는 등의 문제점이 있었으며, 특히 지반이 약하거나 지하수 유출이 많은 지역에서는 이러한 현상이 더욱 가중된다.However, the reinforcing structure is a form in which a plurality of earth plate 20 is simply fitted into the earth plate recessed portion 10a of the steel pile 10 without a separate support structure, so as to withstand earth pressure with only the rigidity of the earth plate 20 itself. Because of this, when the earth pressure is applied, there is a problem such that the stiffness of the earth plate 20 alone cannot endure it and is cut as it is, resulting in an accident leading to a large disaster, especially in areas with weak ground or high groundwater leakage. This is further weighted.

도 2는 토류판의 강성 보강을 위해 개선된 종래 토류벽 공법에 의한 보강구조의 다른 예를 도시한 것으로서, 양단에 토류판 요입부(10a)가 구비된 "H"형의 강재말뚝(10)을 일정간격으로 이격시켜 지반에 타설한 후 상기 다수의 강재말뚝(10) 사이에 제1, 제2 토류판(21,22)이 안팎으로 겹쳐지도록 하여 횡방향으로 설치하고, 상기 겹쳐진 두 토류판(21,22) 사이에 의해 형성되는 공간에 콘크리트(30)를 타설하여 토류벽 보강구조를 형성함으로써 토사의 붕괴를 보다 확실하게 막아줄 수 있도록 구성되어 있다.Figure 2 shows another example of the reinforcement structure by the conventional earth wall method improved for the rigid reinforcement of the earth plate, the "H" type steel pile 10 is provided with the earth plate recessed portion (10a) at both ends a predetermined interval After placing in the ground spaced apart by the first and second earth plate (21, 22) between the plurality of steel piles (10) installed in the transverse direction so as to overlap in and out, the two earth plate (21, 22) The concrete 30 is poured into the space formed by the space, and the earth wall reinforcement structure is formed to prevent the earth and sand from collapsing more reliably.

그러나 상기의 토류벽 공법에 의한 보강구조는 건축공사가 끝나게 되면 제거하거나 그대로 매입하는 것인데, 토류벽을 제거작업이 매우 복잡할 뿐만 아니라 또 한 토류벽을 제거한다 하더라도 토류벽이 설치되었던 자리를 메꿔주어야 하나 되메우기 작업이 완벽하게 이루어지지 않게 되면, 건축물에 누수현상이 발생되거나 또는 토사가 흘러내리는 등의 문제점 발생 원인이 되는 것이다.However, the reinforcing structure by the earth wall method is to remove or purchase it as it is after construction work. The earth wall removal process is very complicated, and even if the earth wall is removed, the place where the earth wall was installed should be refilled. If this is not done completely, it will be the cause of problems such as water leakage in the building or landslides.

따라서 본 발명은 상기의 문제점을 해결하기 위하여 안출한 것으로서 본 발명의 목적은 건축물의 기초 터파기 후 절토면 또는 성토면 등의 토사면에 구축되어 사면을 안정화시키는 토류벽에 조립식 강재말뚝을 이중으로 간단하게 설치하여 토류벽을 견고하게 지지할 수 있도록 함으로써 토류벽이나 강재말뚝이 토압에 의해 붕괴되거나 밀리는 것을 방지하여 안전사고를 예방하고, 건축물 시공 후 이중 설치된 조립식 강재말뚝을 간단하게 분해하여 제거함으로써 시공설비의 재활용성 및 건축물의 안전성 확보는 물론 작업 효율성을 향상시킬 수 있는 옹벽용 또는 흙막이용 토류벽의 조성장치 및 방법을 제공함에 있다.Therefore, the present invention has been made in order to solve the above problems, an object of the present invention is to simply build a prefabricated steel pile on the earth wall to stabilize the slope is built on the soil surface, such as cut surface or embankment surface after foundation destruction of the building By installing it so that the earth wall can be firmly supported, it prevents the earth wall or the steel pile from collapsing or being pushed by the earth pressure to prevent safety accidents. And it provides a composition and method of the earth wall for retaining wall or retaining wall that can ensure the safety of the building as well as improve the work efficiency.

상기의 목적을 달성하기 위한 본 발명 장치의 제 1특징은, 토류벽을 형성하기 위한 토사면에 다수 개가 직접 설치되는 제 1강재말뚝; 상기 제 1강재말뚝에 각각 대응되는 개수로 구비되며, 상기 각 제 1강재말뚝을 토사면의 반대방향에서 토사면 측으로 지지할 수 있도록 상기 제 1강재말뚝과 지면에 대하여 기울어진 상태로 지반에 타설되는 다수 개의 제 2강재말뚝; 상기 제 1강재말뚝과 제 2강재말뚝을 조립 또는 분리하며, 각도 조절이 가능하게 힌지 결합된 두개의 말뚝캡에 의해 상 기 제 1강재말뚝과 제 2강재말뚝을 각도 조절 가능하게 하나의 쌍으로 결합시키는 다수 개의 제 1말뚝 조립체; 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝에 수직하게 다수 개 설치되는 강재말뚝 보강재를 포함하는 옹벽용 또는 흙막이용 토류벽의 조성장치이다.A first feature of the device of the present invention for achieving the above object, the first steel pile is directly installed on a plurality of soil surface for forming the earth wall; It is provided in the number corresponding to each of the first steel pile, and placed on the ground in an inclined state with respect to the first steel pile and the ground so as to support each of the first steel pile to the soil surface side in the opposite direction of the soil surface A plurality of second steel piles; Assembling or separating the first steel pile and the second steel pile, and the first steel pile and the second steel pile by a pair of hinge caps hinged to enable the angle adjustment in a pair to enable angle adjustment. A plurality of first pile assemblies to couple; It is a composition device for a retaining wall or earth retaining wall including a steel pile reinforcement is installed in a plurality of vertically perpendicular to the plurality of second steel piles to support the plurality of second steel piles.

상기의 목적을 달성하기 위한 본 발명 장치의 제 2특징은, 토류벽을 형성하기 위한 토사면에 다수 개가 직접 설치되는 제 1강재말뚝; 상기 제 1강재말뚝에 각각 대응되는 개수로 구비되며, 상기 제 1강재말뚝과 이격되어 토사면의 반대방향에서 상기 각 제 1강재말뚝과 나란하거나 또는 경사지게 지반에 타설되는 다수 개의 제 3강재말뚝; 상기 제 1강재말뚝 및 제 3강재말뚝에 각각 대응되는 개수로 구비되며, 지면으로부터 이격되어 상기 제 1강재말뚝과 제 3강재말뚝의 상단부에 거치되는 형태로 양단부가 조립 또는 분리되는 조립빔; 각도 조절이 가능하게 힌지 결합된 두 개의 말뚝캡에 의해 상기 제 1강재말뚝과 조립빔 및 제 3강재말뚝과 조립빔을 각도 조절 가능하게 하나의 쌍으로 결합시키는 다수 개의 제 1말뚝 조립체; 상기 다수 개의 제 3강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 3강재말뚝에 수직하게 다수 개 설치되는 강재말뚝 보강재를 포함하는 옹벽용 또는 흙막이용 토류벽의 조성장치이다.A second feature of the device of the present invention for achieving the above object, the first steel pile is directly installed on a plurality of soil surface for forming the earth wall; A plurality of third steel piles provided in a number corresponding to each of the first steel piles and spaced apart from the first steel piles and placed on the ground in parallel to or inclined with the first steel piles in opposite directions of the soil surface; An assembly beam provided with a number corresponding to each of the first steel pile and the third steel pile, the both ends being assembled or separated from each other by being spaced apart from the ground and mounted on the upper ends of the first steel pile and the third steel pile; A plurality of first pile assemblies configured to couple the first steel pile and the assembly beam and the third steel pile and the assembly beam by one pair so that angle adjustment is possible by two pile caps hinged to each other; It is a composition device for a retaining wall or earth retaining wall including a steel pile reinforcement is installed in a plurality of vertically perpendicular to the plurality of third steel piles to support the plurality of third steel piles.

상기 본 발명의 각 실시예에 의한 옹벽용 또는 흙막이용 토류벽 조성장치에서, 상기 제 1말뚝 조립체는, 두 개의 말뚝캡에 상기 각 강재말뚝이 삽입될 수 있도록 내부 공간이 각각 형성되어 상기 제 1강재말뚝과 제 2강재말뚝, 또는 제1강재말뚝과 조립빔, 또는 제3강재말뚝과 조립빔의 단부에 말뚝캡이 씌워져 조립되는 것 이 바람직하다.In the retaining wall or earth retaining wall wall forming apparatus according to each embodiment of the present invention, the first pile assembly, the inner space is formed so that each steel pile is inserted into the two pile caps, respectively, the first steel pile It is preferable that the pile cap is covered with the end of the second steel pile, or the first steel pile and the assembly beam, or the third steel pile and the assembly beam.

상기의 목적을 달성하기 위한 본 발명 장치의 제 3특징은, 토류벽을 형성하기 위한 토사면에 다수 개가 직접 설치되며 상단부에 적어도 하나의 케이블 삽입홈을 형성한 제 1강재말뚝; 상기 제 1강재말뚝에 각각 대응되는 개수로 구비되며, 상기 제 1강재말뚝과 이격되어 토사면의 반대방향에서 상기 각 제 1강재말뚝과 나란하거나 또는 경사지게 지반에 타설되고, 상단부에 적어도 하나의 케이블 삽입홈을 형성한 제 3강재말뚝; 상기 제 1강재말뚝 및 제 3강재말뚝에 각각 대응되는 개수로 구비되며, 지면으로부터 이격되어 상기 제 1강재말뚝과 제 3강재말뚝 상단부의 케이블 삽입홈을 통해 각 강재말뚝의 외측으로 양단부가 고정되되 상기 제 1강재말뚝과 제 3강재말뚝을 신축 가능하게 하나의 쌍으로 결합시키는 조립 케이블; 상기 다수 개의 제 3강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 3강재말뚝에 수직하게 다수 개 설치되는 강재말뚝 보강재를 포함하는 옹벽용 또는 흙막이용 토류벽의 조성장치이다.A third feature of the apparatus of the present invention for achieving the above object, the first steel pile is a plurality of directly installed on the soil surface for forming the earth wall and formed at least one cable insertion groove in the upper end; It is provided in a number corresponding to each of the first steel piles, spaced apart from the first steel piles are placed on the ground parallel to or inclined with each of the first steel piles in the opposite direction of the soil surface, at least one cable at the upper end A third steel pile having an insertion groove; It is provided with a number corresponding to the first steel pile and the third steel pile, respectively, and is spaced apart from the ground and both ends are fixed to the outside of each steel pile through the cable insertion groove of the upper end of the first steel pile and the third steel pile. An assembly cable configured to elastically couple the first steel pile and the third steel pile into one pair; It is a composition device for a retaining wall or earth retaining wall including a steel pile reinforcement is installed in a plurality of vertically perpendicular to the plurality of third steel piles to support the plurality of third steel piles.

상기 목적을 달성하기 위한 본 발명 장치의 제 4특징은, 토사면의 지반에 설치되는 다수 개의 제 2강재말뚝; 상기 각각의 제 2강재말뚝 사이에 제 2강재말뚝과 교대로 설치되되, 제 2강재말뚝에 대하여 엇갈리게 토사면의 지반에 타설되는 다수 개의 제 4강재말뚝; 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝에 수직하게 다층으로 결합되는 다수 개의 강재말뚝 보강재; 상기 다수 개의 강재말뚝 보강재 중에서 최상층에 위치하는 강재말뚝 보강재에 고정 설치되며, 각도 조절이 가능하게 힌지 결합된 말뚝캡을 구비하여 상 기 말뚝캡에 의해 최상층의 강재말뚝 보강재에 상기 제 4강재말뚝의 상단부를 각도 조절 가능하게 결합하는 다수 개의 제 2말뚝조립체;를 포함하는 옹벽용 또는 흙막이용 토류벽 조성장치이다.A fourth feature of the present invention device for achieving the above object, a plurality of second steel pile is installed on the ground of the soil surface; A plurality of fourth steel piles which are alternately installed with the second steel piles between the second steel piles and alternately placed on the ground of the soil slope with respect to the second steel piles; A plurality of steel pile stiffeners coupled to the plurality of second steel piles in a vertical manner so as to be connected to each other to support the plurality of second steel piles; Of the plurality of steel pile reinforcement is fixed to the steel pile reinforcement located on the top floor, and provided with a hinge cap coupled to the angle adjustable to the steel pile reinforcement of the top layer by the pile cap of the fourth steel pile It is a earth wall earthing device for retaining wall or retaining wall comprising a; a plurality of second pile assembly for coupling the upper end to the angle adjustable.

상기 제 2말뚝조립체는, 힌지축과, 상기 힌지축 일측에 형성되며, 상기 강재말뚝 보강재의 후면에 고정되는 브라켓 부재와, 상기 힌지축의 다른 일측에 상기 브라켓 부재에 대향하여 일체로 형성되되, 상기 힌지축을 중심으로 회전 가능하게 형성되며, 일측 단부가 개방되어 그 개방부의 내부로 상기 제 4강재말뚝의 상단부가 삽입될 수 있는 내부 공간을 형성한 말뚝캡;을 포함하여 구성되는 것이 바람직하다.The second pile assembly is formed on the hinge shaft, one side of the hinge shaft, the bracket member is fixed to the rear of the steel pile reinforcement, and formed integrally opposite the bracket member on the other side of the hinge shaft, It is formed to be rotatable about a hinge axis, and one end is open, the pile cap formed an inner space in which the upper end of the fourth steel pile can be inserted into the opening portion; preferably comprises a.

상기의 목적을 달성하기 위한 본 발명 방법의 제 1특징은, 토사면의 지반에 다수의 제 1강재말뚝을 타설하여 토류벽을 조성하는 방법에 있어서, (a) 토사면의 반대방향에서 상기 제 1강재말뚝을 각각 지지할 수 있도록 상기 제 1강재말뚝에 대응되는 개수의 제 2강재말뚝을 상기 제 1강재말뚝 측으로 기울어지게 지반에 타설하는 제 1단계; (b) 각도조절 가능하게 힌지 결합된 제 1말뚝 조립체의 제 1강재말뚝캡와 제 2강재말뚝캡의 각도를 상기 제 1강재말뚝과 그에 대응되게 타설된 제 2강재말뚝이 이루는 각도에 대응되게 조절하고, 상기 각도 조절된 제 1말뚝 조립체를 이용하여 상기 제 1강재말뚝 각각에 제 2강재말뚝을 각각 쌍으로 조립하여 토류벽을 이중 보강하는 제 2단계; (c) 상기 제 1말뚝 조립체에 의해 이중 보강된 토류벽에 쏘일 네일 설치 작업을 실시하는 제 3단계; (d) 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝에 수직하게 다 수 개의 강재말뚝 보강재를 설치하는 제 4단계;로 이루어지는 옹벽용 또는 흙막이용 토류벽의 조성방법이다.A first feature of the method of the present invention for achieving the above object is a method of forming a earth wall by pouring a plurality of first steel piles in the ground of the soil surface, (a) the first in the opposite direction of the soil surface A first step of placing the second steel piles corresponding to the first steel piles on the ground so as to be inclined toward the first steel piles so as to support the steel piles; (b) adjusting the angle of the first steel pile cap and the second steel pile cap of the first pile assembly hingedly coupled to the angle so as to correspond to the angle formed by the first steel pile and the second steel pile which is correspondingly placed; A second step of double reinforcing the earth wall by assembling a pair of second steel piles to each of the first steel piles using the angle-adjusted first pile assembly; (c) a third step of performing nail installation work on the earth wall doublely reinforced by the first pile assembly; (d) a fourth step of installing a plurality of steel pile stiffeners perpendicular to the plurality of second steel piles so as to connect and support the plurality of second steel piles to each other; The composition method of.

상기의 목적을 달성하기 위한 본 발명 방법의 제 2특징은, 토사면의 지반에 다수의 강재말뚝을 타설하여 토류벽을 조성하는 방법에 있어서, 토사면의 지반에 제 2강재말뚝을 타설하는 단계; 상기 각각의 제 2강재말뚝 사이에 제 2강재말뚝과 교대로 엇갈리게 다수 개의 제 4강재말뚝을 토사면의 지반에 타설하는 단계; 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝에 수직하게 다층으로 다수 개의 강재말뚝 보강재를 결합하는 단계; 상기 다수 개의 강재말뚝 보강재 중에서 최상층에 위치하는 강재말뚝 보강재에 각도 조절이 가능하도록 힌지 결합된 말뚝캡을 구비한 다수 개의 제 2말뚝조립체를 고정 설치한 후 상기 말뚝캡에 의해 최상층의 강재말뚝 보강재에 상기 제 4강재말뚝의 상단부를 각도 조절 가능하게 결합하는 단계; 상기 제 2말뚝 조립체에 의해 이중 보강된 토류벽에 쏘일 네일 설치 작업을 실시하는 단계;로 이루어지는 옹벽용 또는 흙막이용 토류벽 조성방법이다.According to a second aspect of the present invention, there is provided a method of forming a soil wall by laying a plurality of steel piles on a ground of a soil surface, the method comprising: pouring a second steel pile on the ground of a soil surface; Placing a plurality of fourth steel piles on the ground of the soil surface alternately alternately with the second steel piles between the respective second steel piles; Coupling a plurality of steel pile reinforcements in a multi-layer perpendicular to the plurality of second steel piles so as to support the plurality of second steel piles by connecting to each other; After fixing a plurality of second pile assemblies having a hinge cap coupled to the steel pile reinforcement located on the top layer of the plurality of steel pile reinforcement to enable angle adjustment to the steel pile reinforcement of the top layer by the pile cap Coupling an upper end of the fourth steel pile to be adjustable in angle; A method of forming a retaining wall or retaining wall for the retaining wall, comprising: performing a nail installation operation on the earth wall double reinforced by the second pile assembly.

이상의 본 발명에 의하면, 사면을 안정화시키는 토류벽에 조립식 강재말뚝을 이중으로 간단하게 설치하여 토류벽을 견고하게 지지할 수 있도록 함으로써 토류벽이나 강재말뚝이 토압에 의해 붕괴되거나 밀리는 것을 방지할 수 있도록 하여 인명 피해 등의 안전사고를 예방하고, 건축물 시공 후 이중 설치된 조립식 강재말뚝을 간단하게 분해하여 제거함으로써 시공설비의 재활용성 및 건축물의 안전성 확보는 물론 작업 효율성을 향상시킬 수 있게 되는 등의 유용함이 있다.According to the present invention, it is possible to simply install the prefabricated steel pile on the earth wall stabilizing the slope so that the earth wall can be firmly supported to prevent the earth wall or steel pile from collapsing or being pushed by the earth pressure to prevent human injury, etc. It is useful to prevent safety accidents, and to simply disassemble and remove the prefabricated steel piles installed after the construction of the building, to ensure the recyclability of the construction equipment, the safety of the building, and to improve the work efficiency.

상기 본 발명의 이들 목적과 특징 및 장점은 첨부도면 및 다음의 상세한 설명을 참조함으로써 더욱 쉽게 이해될 수 있을 것이다.These objects, features and advantages of the present invention will be more readily understood by reference to the accompanying drawings and the following detailed description.

이하, 첨부된 도면을 참조하여 본 발명의 바람직한 실시 예에 대한 구성 및 작용에 대해 상세히 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings will be described in detail the configuration and operation of the preferred embodiment of the present invention.

도 3과 도 4는 본 발명의 한 특징에 의한 옹벽용 또는 흙막이용 토류벽의 조성장치의 단면도와 정면도이고, 도 5는 본 발명에 따른 토류벽 조성장치에서 제 1말뚝 조립체를 분리하여 상세 도시한 사시도로서, H 빔 형상으로 양측에 토류판 요입부(11a)가 각각 구비되고 토사면의 지반에 토류판의 길이만큼 일정 간격 이격되게 관입 설치되는 다수의 제 1강재말뚝(11), H 빔 형상으로 양측에 토류판 요입부(12a)가 각각 구비되고 상기 제 1강재말뚝(11)을 각각 지지하는 다수 개의 제 2강재말뚝(12), 상기 제 1강재말뚝 또는 제 2강재말뚝의 토류판 요입부(11a, 12a) 에 횡방향으로 끼워지는 다수의 토류판(20) 상기 제 2강재말뚝(12)을 제 1강재말뚝(11)에 조립하는 제 1말뚝 조립체(40), 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝(12)에 수직하게 설치되는 다수 개의 강재말뚝 보강재(60)를 포함하여 구성된다.3 and 4 are a cross-sectional view and a front view of the composition of the earth wall for retaining wall or retaining wall according to an aspect of the present invention, Figure 5 is a perspective view showing in detail separated from the first pile assembly in the earth wall forming apparatus according to the present invention As a plurality of first steel piles 11, H beams are provided on both sides in the H-beam shape, respectively, and are infiltrated at predetermined intervals by the length of the earth plate. A plurality of second steel piles 12 each having a soil plate recess portion 12a and supporting the first steel pile 11, and the earth plate recess portions 11a and 12a of the first steel pile or the second steel pile, respectively. The first pile assembly 40 to assemble the second steel pile (12) to the first steel pile 11, the plurality of earth plate (20) fitted laterally to the plurality of second steel piles connected to each other To support the plurality of second steels Is configured to include a plurality of reinforcing steel pile 60 is vertically installed on the pile 12. The

상기 제 2강재말뚝(12)은 상기 제 1강재말뚝(11)에 각각 대응되는 개수로 구비되며, 상기 각 제 1강재말뚝(11)을 토사면의 반대방향에서 토사면 측으로 지지할 수 있도록 상기 제 1강재말뚝(11)과 지면에 대하여 기울어진 상태로 지반에 타설된 다. 필요에 따라 상기 제 1강재말뚝과 제 2강재말뚝을 모두 경사지게 설치하거나 제 1강재말뚝을 경사지게 설치하고 제 2강재말뚝을 수직으로 설치하여 효율을 높일 수 있다.The second steel pile 12 is provided in a number corresponding to the first steel pile 11, respectively, so as to support the first steel pile 11 to the side of the soil surface in the opposite direction of the soil surface The first steel pile (11) is placed on the ground in an inclined state with respect to the ground. If necessary, both the first steel pile and the second steel pile may be installed to be inclined or the first steel pile may be installed to be inclined and the second steel pile may be vertically installed to increase efficiency.

상기 제 1말뚝 조립체(40)는 상기 제 1강재말뚝(11)과 제 2강재말뚝(12)을 조립 또는 분리하기 위해 설치되며, 힌지축(43)을 중심으로 각도 조절이 가능하게 힌지 결합된 제 1강재말뚝캡(41)과 제 2강재말뚝캡(42)을 구비하여, 상기 제 1강재말뚝캡(41)과 제 2강재말뚝캡(42)에 의해 상기 제 1강재말뚝(11)과 제 2강재말뚝(12)을 각도 조절 가능하게 하나의 쌍으로 결합시키는 역할을 한다. 이때 제 1강재말뚝캡(41)과 제 2강재말뚝캡(42)에는 상기 각 강재말뚝이 삽입될 수 있도록 내부 공간이 형성되며, 상기 제 1강재말뚝(11)과 제 2강재말뚝(12)의 상단부에 제 1강재말뚝캡(41)과 제 2강재말뚝캡(42)의 하단부가 덮어 씌워지는 형태로 각각 조립되거나 분리된다.The first pile assembly 40 is installed to assemble or separate the first steel pile 11 and the second steel pile 12, the hinge coupled to the angle adjustable around the hinge shaft 43 And a first steel pile cap 41 and a second steel pile cap 42, the first steel pile cap 41 and the second steel pile cap 42 by the first steel pile cap The second steel pile 12 serves to couple the pair in an angle adjustable. In this case, an internal space is formed in the first steel pile cap 41 and the second steel pile cap 42 so that the steel piles can be inserted, and the first steel pile 11 and the second steel pile 12 are formed. The upper and lower ends of the first steel pile cap 41 and the second steel pile cap 42 are assembled or separated, respectively, in the form of covering.

그리고 마지막으로 상기 다수 개의 제 2강재말뚝(12)의 외부에는 그들을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝에 수직하게 다수 개의 강재말뚝 보강재(60)가 설치된다.And finally, a plurality of steel pile reinforcement 60 is installed on the outside of the plurality of second steel piles 12 perpendicular to the plurality of second steel piles so as to connect and support them.

이상과 같이 구성되는 본 발명의 토류벽 조성과정은 먼저, 토사면의 지반에 다수의 제 1강재말뚝(11)을 타설하고, 상기 제 1강재말뚝(11)의 토류판 요입부(11a)에 다수 개의 토류판(20)을 횡방향으로 체결하여 토류벽을 1차 보강하며, 상기 제 1강재말뚝(11)에 대응되도록 제 2강재말뚝(12)을 타설한 후 제 1말뚝 조립체(40)를 이용하여 상기 제 1강재말뚝(11)과 제 2강재말뚝(12)을 조립하여 고정시 킴으로써 토류벽을 이중 보강할 수 있고, 상기 제 2강재말뚝 사이에 횡방향으로 다수의 토류판(20)을 삽입하여 제 2강재말뚝의 간격 유지 및 토류벽 보강을 실시하며, 다음으로 제 1말뚝 조립체(40)에 의해 제 2강재말뚝(12)으로 이중 보강된 토류벽에 쏘일 네일(50) 설치 작업을 실시한 후 상기 다수 개의 제 2강재말뚝에 수직하게 다수 개의 강재말뚝 보강재(60)를 설치하여 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록 함으로써, 토류벽 조성작업을 완료할 수 있게 된다.In the process of forming the earth wall of the present invention constituted as described above, first, a plurality of first steel piles 11 are poured into the ground of the soil surface, and a plurality of earth plate recesses 11a of the first steel piles 11 are formed. Fastening the earth plate 20 laterally by fastening the earth plate 20 laterally, after pouring the second steel pile 12 so as to correspond to the first steel pile (11) by using the first pile assembly (40) By assembling and fixing the first steel pile (11) and the second steel pile (12), it is possible to double reinforce the earth wall, and insert a plurality of earth plate (20) in the transverse direction between the second steel pile. After maintaining the spacing of the two steel piles and reinforcing the earth wall, and after the installation of the nail (50) to be installed on the soil wall double reinforced by the second steel pile 12 by the first pile assembly (40) By installing a plurality of steel pile reinforcement (60) perpendicular to the second steel pile By making it possible to support a plurality of second groups of steel piles connected with each other, it is possible to complete the operation toryubyeok composition.

즉, 상기 1차 보강된 토류벽에 토사면의 반대방향에서 상기 제 1강재말뚝(11)을 각각 지지할 수 있도록 상기 제 1강재말뚝(11)에 대응되는 개수로 제 2강재말뚝(12)을 설치한다. 이때 상기 제 2강재말뚝(12)은 상기 제 1강재말뚝(11) 측으로 기울어지게 하여 상기 제 1강재말뚝(11)과 같은 간격으로 이격되게 지반에 타설한다.That is, the second steel pile 12 in a number corresponding to the first steel pile 11 so as to support the first steel pile 11 in the opposite direction of the soil surface to the primary reinforced earth wall. Install. At this time, the second steel pile 12 is inclined toward the first steel pile 11 to be placed on the ground spaced at the same interval as the first steel pile (11).

이어서 각도조절 가능하게 힌지 결합된 제 1말뚝 조립체(40)의 제 1강재말뚝캡(41)과 제 2강재말뚝캡(42)의 각도를 상기 제 1강재말뚝(11)과 그에 대응되게 타설된 제 2강재말뚝(12)이 이루는 각도에 대응되게 조절하고, 상기 각도 조절된 제 1말뚝 조립체(40)의 제 1강재말뚝캡(41)과 제 2강재말뚝캡(42)의 내부로 상기 제 1강재말뚝(11)과 제 2강재말뚝(12)을 삽입하여 각각 쌍으로 조립함으로써 상기 토류벽을 이중으로 보강할 수 있게 된다.Subsequently, the angles of the first steel pile cap 41 and the second steel pile cap 42 of the first pile assembly 40 hinged to be adjustable in angle are placed in correspondence with the first steel pile 11. The second steel pile 12 is adjusted to correspond to the angle formed, and the first steel pile cap 41 and the second steel pile cap 42 of the angle-controlled first pile assembly 40 into the first By inserting the first steel pile (11) and the second steel pile (12) and assembled in pairs, respectively, the earth wall can be doublely reinforced.

다음으로 상기 제 1말뚝 조립체(40)에 의해 이중 보강된 토류벽에 쏘일 네일(50) 설치 작업을 실시하고, 상기 다수 개의 제 2강재말뚝(12)을 강재말뚝 보강재(60)에 의해 지면에 대하여 수평하게 서로 연결하여 지지함으로써 건축물 기초 흙막이용 토류벽 설치공정을 완료할 수 있게 된다.Next, the nail nail 50 is installed on the earth wall doublely reinforced by the first pile assembly 40, and the plurality of second steel piles 12 are connected to the ground by the steel pile reinforcement 60. By connecting and supporting each other horizontally, it is possible to complete the earth wall installation process for building foundation mudstone.

이후 공사가 완료된 이후 필요에 따라 상기 이중 보강된 토류벽의 제 1말뚝 조립체(40)를 제거함으로써 상기 제 1강재말뚝(11)과 제2강재말뚝(12) 및 강재말뚝보강재(60)가 분리되며, 따라서 상기 이중 보강재로 사용된 제 2강재말뚝(12) 및 강재말뚝 보강재(60)를 제 1강재말뚝(11)으로부터 분리시켜 재활용 가능하게 된다.After the construction is completed, the first steel pile 11 and the second steel pile 12 and the steel pile stiffener 60 is separated by removing the first pile assembly 40 of the double reinforced earth wall as necessary. Therefore, the second steel pile 12 and the steel pile reinforcing material 60 used as the double reinforcing material is separated from the first steel pile 11 to be recyclable.

도 6은 본 발명의 다른 특징에 의한 옹벽용 또는 흙막이용 토류벽의 조성장치의 단면도로서, 토류벽을 형성하기 위한 토사면에 다수 개가 직접 설치되는 제 1강재말뚝(11)과, 상기 제 1강재말뚝에 각각 대응되는 개수로 구비되며, 상기 제 1강재말뚝과 이격되어 토사면의 반대방향에 설치되되 상기 각 제 1강재말뚝에 나란하거나 또는 경사지게 지반에 타설되는 다수 개의 제 3강재말뚝(13)과, 상기 제 1강재말뚝 및 제 3강재말뚝에 각각 대응되는 개수로 구비되며, 지면으로부터 이격되어 상기 제 1강재말뚝과 제 3강재말뚝의 상단부에 거치되는 형태로 양단부가 조립 또는 분리되는 조립빔(70)과, 각도 조절이 가능하게 힌지 결합된 두 개의 말뚝캡(41,42)에 의해 상기 제 1강재말뚝(11)과 조립빔(70) 및 제 3강재말뚝(13)과 조립빔(70)을 각도 조절 가능하게 하나의 쌍으로 결합시키는 다수 개의 제 1말뚝 조립체(40)를 포함하여 구성된다. 여기서 상기 도 6에는 도시되지 않았으나, 상기 다수 개의 제 3강재말뚝을 서로 연결하여 지지할 수 있도록, 도 5의 실시예에서와 같이 상기 다수 개의 제 3강재말뚝(13)에는 그에 수직하게 다수 개의 강재말뚝 보강재(60)가 더 조립될 수 있음은 물론이다.Figure 6 is a cross-sectional view of the composition of the earth wall for retaining wall or retaining wall according to another feature of the present invention, a plurality of first steel pile 11 is directly installed on the soil surface for forming the earth wall, and the first steel pile And a plurality of third steel piles 13 which are provided in a number corresponding to each other and are spaced apart from the first steel piles and installed in opposite directions of the soil surface, and are placed on the ground side by side or inclined to each of the first steel piles. Assembled beams are provided in a number corresponding to the first steel pile and the third steel pile, respectively, and are assembled or separated at both ends in a form spaced from the ground and mounted on the upper ends of the first steel pile and the third steel pile ( 70 and the first steel pile 11 and the assembly beam 70 and the third steel pile 13 and the assembly beam 70 by two pile caps 41 and 42 hinged to allow the angle adjustment. ) One angle adjustable It is configured to include a plurality of first pile assembly 40 for coupling to. Although not shown in FIG. 6, the plurality of third steel piles 13, as shown in the embodiment of FIG. 5, may be connected to each other to support the plurality of third steel piles. Of course, the pile reinforcement 60 can be further assembled.

이로써 지반 면적에 여유가 있는 토사 지반의 경우 상기 도 6에 도시된 바와 같이 제 1강재말뚝(11)을 지반에 타설하고, 제 3강재말뚝(13)을 상기 제 1강재말뚝(11)과 나란하게 또는 경사지게 타설한 후, 다수 개의 제 1말뚝 조립체(40)을 매개체로 하여 상기 제 1강재말뚝(11)과 제 3강재말뚝(13)의 상단부에 조립빔(70)의 양단부를 연결하여 지지함으로써 건축물 기초 흙막이용 토류벽 설치공정을 완료할 수 있게 된다.As a result, in the case of earth and sand having a sufficient ground area, as shown in FIG. 6, the first steel pile 11 is placed on the ground, and the third steel pile 13 is aligned with the first steel pile 11. After pouring or inclinedly, the both ends of the assembly beam 70 are connected to the upper ends of the first steel pile 11 and the third steel pile 13 by using a plurality of first pile assemblies 40 as a medium. By doing so, it is possible to complete the earth wall installation process for building foundation mudstone.

이상의 설치 공정이 완료된 이후, 공사가 모두 완료되면 필요에 따라 상기 이중 보강된 토류벽의 제 1말뚝 조립체(40)를 분리시켜 제거함으로써 상기 제 1강재말뚝(11)과 제 3강재말뚝(13)이 분리될 수 있으며, 따라서 상기 이중 보강재로 사용된 제 3강재말뚝(13) 및 강재말뚝 보강재(60)를 제 1강재말뚝(11)으로부터 분리시켜 재활용 가능하게 된다.After the above installation process is completed, when the construction is completed, the first steel pile 11 and the third steel pile 13 by separating and removing the first pile assembly 40 of the double reinforced earth wall as necessary. It can be separated, and thus can be recycled by separating the third steel pile 13 and the steel pile reinforcement 60 used as the double reinforcement from the first steel pile (11).

도 7과 도 8은 본 발명의 또 다른 특징에 의한 옹벽용 또는 흙막이용 토류벽 조성장치의 단면도로서, 도 7은 조립 케이블이 와이어 로프(82)와 장력 조절부재(81)가 조립되어 구성된 예를 도시하고 있으며, 도 8은 조립 케이블이 타이 케이블(85)로 구성된 예를 도시하고 있다.7 and 8 are cross-sectional views of the earth wall for earth retaining wall or earth retaining device according to another feature of the present invention, Figure 7 is an example of the assembly of the wire rope 82 and the tension adjusting member 81 is assembled 8 shows an example in which the assembly cable consists of a tie cable 85.

상기 도 7에 도시된 바와 같이, 본 발명의 또 다른 실시예는, 토류벽을 형성하기 위한 토사면의 지반에 다수 개가 직접 설치되며 상단부에 적어도 하나의 케이블 삽입홈(도면에는 미도시됨)을 형성한 제 1강재말뚝(11)과, 상기 제 1강재말뚝에 각각 대응되는 개수로 구비되며, 상기 제 1강재말뚝과 이격되어 토사면의 반대방향에 설치되되 상기 각 제 1강재말뚝에 나란하거나 또는 경사지게 지반에 타설되고, 상단부에 적어도 하나의 케이블 삽입홈을 형성한 제 3강재말뚝(13)과, 상기 제 1강 재말뚝(11) 및 제 3강재말뚝(13)에 각각 대응되는 개수로 구비되며, 지면으로부터 이격되어 상기 제 1강재말뚝과 제 3강재말뚝 상단부의 케이블 삽입홈을 통해 각 강재말뚝의 외측으로 양단부가 고정되되 케이블의 일부를 장력 조절부재(81)로 구성하여 상기 제 1강재말뚝(11)과 제 3강재말뚝(13)을 신축 가능하게 하나의 쌍으로 결합시키는 조립 케이블(80)을 포함하여 구성한다. 여기서 상기 장력 조절부재(81)는 턴 버클 등과 같이 줄의 장력을 조절할 수 있는 부재 중의 어느 하나를 선택적으로 사용할 수 있을 것이며, 예를 들어 턴 버클이 적용되는 경우 버클 하우징을 중심으로 양편에 서로 반대 방향으로 조립된 수나사를 돌려, 그 양쪽에 이어지는 와이어 로프(82)를 당기거나 풀 수 있도록 구성될 것이다. As shown in FIG. 7, according to another embodiment of the present invention, a plurality of directly installed on the ground of the soil surface for forming the earth wall and at least one cable insertion groove (not shown in the figure) formed at the upper end It is provided with a number corresponding to each of the first steel pile (11) and the first steel pile, spaced apart from the first steel pile is installed in the opposite direction of the earth surface, or parallel to each of the first steel pile or It is provided on the ground to be inclined, and provided in the number corresponding to each of the third steel pile 13 and the first steel ash pile 11 and the third steel pile 13 formed at least one cable insertion groove in the upper end Both ends are fixed to the outside of each steel pile through the cable insertion grooves of the first steel pile and the third steel pile, spaced apart from the ground, and a part of the cable is composed of a tension adjusting member 81 to form the first steel. Pile (1 It comprises a 1) and the assembly cable 80 for coupling the third steel pile 13 in a stretchable pair. Here, the tension adjusting member 81 may selectively use any one of the members capable of adjusting the tension of the cord, such as a turn buckle, and, for example, when the turn buckle is applied, opposite to each other around the buckle housing. It will be configured to turn or loosen the assembled male screw in the direction so as to pull or loosen the wire rope 82 connected to both sides.

상기 조립 케이블(80)은 도 7에 도시된 바와 같이, 필요에 따라 케이블의 장력을 조절할 수 있는 장력 조절부재(81)와, 상기 장력 조절부재(81)를 상기 제 1강재말뚝(11) 및 제 3강재말뚝(13)에 각각 연결하는 와이어 로프(82)로 구성된다. 여기서 상기 와이어 로프(82)의 양단부에는 고리가 형성되며 상기 제1 강재말뚝(11)과 제 3강재말둑(13)의 케이블 삽입홈을 통해 각 강재말뚝의 외측에 부착된 띠장 빔(83)에 걸어 고정할 수 있도록 구성한다. 이를 위하여 상기 제 1강재말뚝(11)과 제 3강재말뚝(13)의 외측에는 지반으로부터 수평으로 이격되게 띠장 빔(83)이 부착되며, 상기 띠장 빔(83)을 지지하기 위한 브라켓(84)이 설치된다.As shown in FIG. 7, the assembly cable 80 includes a tension adjusting member 81 capable of adjusting the tension of the cable as necessary, and the tension adjusting member 81 of the first steel pile 11 and The wire rope 82 is connected to the third steel pile 13, respectively. Here, a ring is formed at both ends of the wire rope 82 and is connected to the strip beam 83 attached to the outside of each steel pile through the cable insertion grooves of the first steel pile 11 and the third steel pile 13. It is configured to be fixed by hanging. To this end, a belt beam 83 is attached to the outside of the first steel pile 11 and the third steel pile 13 so as to be horizontally spaced from the ground, and a bracket 84 for supporting the belt beam 83 is provided. This is installed.

도 8은 상기 조립 케이블이 타이 케이블(85)로 구성된 예로서, 도 8에 도시된 바와 같이, 타이 케이블(85)은 양단부에 너트 결합을 위한 나사산이 형성되며, 상기 제 1강재말뚝(11) 및 제 3강재말뚝(13)의 케이블 삽입홈을 통해 각 말뚝의 외 측으로 그 양단부가 돌출되어, 너트 조립 위치에 따라 케이블의 길이를 조절할 수 있도록 너트부재(86)에 의해 각 말뚝의 외측에서 양단부가 조립된다. 이 실시예에서도 상기 타이 케이블(85)의 양단부를 상부와 하부에서 각각 지지할 수 있도록, 상기 제 1강재말뚝(11)과 제 3강재말뚝(13)의 외측에는 지반으로부터 수평으로 이격되게 띠장 빔(83a,83b)이 부착되며, 상기 띠장 빔(83a,83b)을 지지하기 위한 브라켓(84)이 설치된다.8 is an example in which the assembly cable consists of a tie cable 85, as shown in FIG. 8, the tie cable 85 is formed with a thread for nut coupling at both ends, and the first steel pile 11 And both ends protrude from the outside of each pile through the cable insertion groove of the third steel pile 13, and both ends from the outside of each pile by the nut member 86 to adjust the length of the cable according to the nut assembly position. Is assembled. Also in this embodiment, the outer side of the first steel pile 11 and the third steel pile (13) horizontally spaced from the ground so as to support both ends of the tie cable (85) from the top and bottom, respectively 83a and 83b are attached, and a bracket 84 for supporting the strip beams 83a and 83b is provided.

도 7 및 도 8에는 도시되지 않았으나, 상기 각 실시예에서도 상기 다수 개의 제 3강재말뚝을 서로 연결하여 지지할 수 있도록, 도 5의 실시예에서와 같이 상기 다수 개의 제 3강재말뚝(13)에는 그에 수직하게 다수 개의 강재말뚝 보강재(60)가 더 조립될 수 있음은 물론이며, 상기 제 1강재말뚝과 제 3강재말뚝은 각각 H 빔 형상으로 구성되고 양측에 토류판 요입부가 각각 구비되고 토사면의 지반에 토류판의 길이만큼 일정 간격 이격되게 관입 설치되는 것으로, 상기 도 3 및 도 4에 도시된 제 1강재말뚝 및 제 2강재말뚝과 동일하므로 그 상세한 설명은 생락하기로 한다.Although not illustrated in FIGS. 7 and 8, the plurality of third steel piles 13 may be formed as shown in the embodiment of FIG. 5 so that the plurality of third steel piles may be connected to and supported by each other. Of course, a plurality of steel pile reinforcement material 60 may be further assembled vertically, and the first steel pile and the third steel pile are each configured in an H-beam shape, and earth plate recesses are provided at both sides of the soil slope, respectively. Since it is installed in the ground spaced apart by a predetermined length of the earth plate, the same as the first steel pile and the second steel pile shown in Figures 3 and 4 will be omitted in detail.

이로써 지반 면적에 여유가 있는 토사 지반의 경우 도면에 도시된 바와 같이 제 1강재말뚝 및 제 3강재말뚝을 나란하거나 또는 경사지게 지반에 타설하고, 장력 조절부재(81)와 와이어 로프(82)를 이용한 조립 케이블의 장력 조절, 또는 타이 케이블(85)과 너트(86)를 이용한 케이블의 길이 조절에 의해 상기 제 1강재말뚝(11)과 제 3강재말뚝(13)의 상단부를 신축 가능하게 조립할 수 있게 되며, 상기 조립 케이블(80)에 의해 두 강재 말뚝을 연결 및 지지함으로써 건축물 기초 흙막이용 토류벽 설치공정을 완료할 수 있게 된다.As a result, in the case of earth and sand ground having a sufficient ground area, the first steel pile and the third steel pile are placed side by side or inclined as shown in the drawing, and the tension adjusting member 81 and the wire rope 82 are used. By adjusting the tension of the assembly cable or by adjusting the length of the cable using the tie cable 85 and the nut 86, the upper ends of the first steel pile 11 and the third steel pile 13 can be flexibly assembled. By connecting and supporting the two steel piles by the assembly cable 80, it is possible to complete the earth wall installation process for building foundation mud.

도 9는 본 발명의 제5실시예에 의한 옹벽용 또는 흙막이용 토류벽 조성장치의 배면 일부를 발췌하여 예시한 사시도로서, 토사면의 지반에 설치되는 다수 개의 제 2강재말뚝(12)과, 제 2강재말뚝 사이에 제 2강재말뚝과 교대로 설치되는 다수 개의 제4강재말뚝(14)과, 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝에 수직하게 다층으로 볼트 또는 용접에 의해 결합되는 다수 개의 강재말뚝 보강재(60)와, 상기 다수 개의 강재말뚝 보강재 중에서 최상층에 위치하는 강재말뚝 보강재에 고정 설치되는 다수 개의 제2말뚝 조립체(90)를 포함하여 구성된다.FIG. 9 is a perspective view illustrating a portion of the rear surface of the retaining wall or earth retaining earth wall forming apparatus according to the fifth embodiment of the present invention, and includes a plurality of second steel piles 12 installed on the ground of the earth and sand; Vertically perpendicular to the plurality of second steel piles so that the plurality of fourth steel piles 14 alternately installed with the second steel piles between the two steel piles and the plurality of second steel piles can be connected and supported. Including a plurality of steel pile reinforcement 60 is coupled to the multi-layer by a bolt or welding, and a plurality of second pile assembly 90 is fixed to the steel pile reinforcement located on the top layer of the plurality of steel pile reinforcement It is composed.

여기서 상기 배면 강재말뚝인 제 4강재말뚝(14)은 상기 도 9에 도시된 바와 같이 토사면에 대하여 기울어지게 또는 수직하게 지반에 설치되되, 상기 제 2강재말뚝에 대하여 엇갈리게 타설되는 것이 바람직하다. 또한 상기 다수 개의 제 2말뚝 조립체(90)는 각도 조절이 가능하게 힌지 결합된 말뚝캡(93)을 구비하여 상기 말뚝캡에 의해 최상층의 강재말뚝 보강재(60)에 상기 제 4강재말뚝의 상단부를 각도 조절 가능하게 결합할 수 있게 된다. 상기 도 9에서는 다수 개의 강재말뚝 보강재(60)와 제 4강재말뚝(14)간의 연결부(100)가 볼트에 의해 결합된 경우를 예시하고 있으나, 용접에 의해서도 결합될 수 있음은 물론이다.Here, the fourth steel pile 14, which is the rear steel pile, is installed on the ground inclined or vertically with respect to the soil surface as shown in FIG. 9, but is preferably placed alternately with respect to the second steel pile. In addition, the plurality of second pile assembly 90 has a pile cap 93 hinged to enable the angle adjustment to the upper end of the fourth steel pile to the steel pile reinforcement 60 of the uppermost layer by the pile cap Can be combined to adjust the angle. In FIG. 9, the connection part 100 between the plurality of steel pile reinforcement 60 and the fourth steel pile 14 is illustrated by a bolt, but may be coupled by welding.

도 10은 도 9의 제5실시예에서 강재말뚝 보강재와 제2강재말뚝간의 결합부 상세도로서, 상기 제 2말뚝조립체(90)는, 힌지축(92)과, 상기 힌지축 일측에 축방향으로 형성되며 상기 강재말뚝 보강재의 후면에 볼트결합에 의해 고정되는 브라켓 부재(91)와, 상기 힌지축의 다른 일측에 상기 브라켓 부재에 대향하여 일체로 형성 되되 상기 힌지축을 중심으로 회전 가능하게 설치되고 일측 단부가 개방되어 그 개방부의 내부로 상기 제 4강재말뚝(14)의 상단부가 삽입될 수 있는 내부 공간을 형성한 말뚝캡(93)을 포함하여 구성된다.FIG. 10 is a detailed view of the coupling portion between the steel pile reinforcement and the second steel pile in the fifth embodiment of FIG. And a bracket member 91 fixed to the rear of the steel pile reinforcement by bolt coupling and formed integrally with the bracket member on the other side of the hinge shaft, and rotatably installed around the hinge shaft. It is configured to include a pile cap 93, the end of which is formed an inner space into which the upper end of the fourth steel pile 14 can be inserted into the opening.

이와 같은 실시예에서, 토사면의 지반에 다수의 강재말뚝을 타설하여 토류벽을 조성하는 방법을 보면, 우선 토사면의 전면에서 후면측으로 지면에 대하여 기울어지게 또는 수직하게 제 2강재말뚝(12)을 지반에 타설하고, 상기 각각의 제 2강재말뚝(12) 사이에 제 2강재말뚝과 교대로 엇갈리게 다수 개의 제 4강재말뚝(14)을 타설한다. 그리고 다수 개의 제 2강재말뚝에 수직하게 다층으로 다수 개의 강재말뚝 보강재(60)를 용접에 의해 또는 볼트부재를 사용하여 결합함으로써, 상기 다수 개의 제 2강재말뚝(12)을 서로 연결하여 지지될 수 있게 한다. In this embodiment, the method of forming the earth wall by placing a plurality of steel piles on the ground of the soil surface, first the second steel pile 12 inclined or perpendicular to the ground from the front surface of the soil surface to the rear side A plurality of fourth steel piles 14 are alternately alternated with the second steel piles between the respective second steel piles 12. And by joining the plurality of steel pile reinforcement 60 in a multi-layer perpendicular to the plurality of second steel piles by welding or by using a bolt member, the plurality of second steel piles 12 can be supported by connecting to each other. To be.

다음으로 각도 조절이 가능하도록 힌지 결합된 말뚝캡(93)을 구비한 다수 개의 제 2말뚝조립체(90)를 상기 다수 개의 강재말뚝 보강재 중에서 최상층에 위치하는 강재말뚝 보강재(60)에 볼트 결합에 의해 고정 설치한 후, 상기 말뚝캡(93)의 내부 공간에 상기 제 4강재말뚝(14)의 상단부를 끼워 넣음으로써, 제2 말뚝 조립체를 매개체로 하여 최상층의 강재말뚝 보강재(60)에 제 4강재말뚝(14)을 조립한다.Next, a plurality of second pile assemblies having a pile cap 93 hinged to enable angle adjustment may be bolted to the steel pile stiffener 60 located at the top layer of the plurality of steel pile stiffeners. After the fixed installation, by inserting the upper end of the fourth steel pile 14 in the inner space of the pile cap 93, the fourth steel material to the steel pile reinforcement 60 of the uppermost layer using the second pile assembly as a medium Assemble the pile (14).

이로써 상기 최상층의 강재 말뚝 보강재(60)에는 전면 강재말뚝인 제 2강재말뚝(12)과 후면 강재말뚝인 제 4강재말뚝(14)이 상기 제 2말뚝 조립체(90)에 의해 교대로 엇갈리게 조립되어, 이중으로 보강된 토류벽을 형성할 수 있게 되며, 이후는 상기 제 2말뚝 조립체에 의해 이중 보강된 토류벽에 쏘일 네일 설치 작업을 실시함으로써 토류벽 시공을 완료할 수 있게 된다.As a result, the steel pile reinforcement 60 of the uppermost layer is alternately assembled with the second steel pile 12, which is the front steel pile, and the fourth steel pile 14, which is the rear steel pile, alternately by the second pile assembly 90. It is possible to form a double reinforced earth wall, and after that, the installation of the soil nail can be completed on the earth wall double reinforced by the second pile assembly to complete the earth wall construction.

이상과 같이 본 발명의 바람직한 실시 예를 설명하였으나 본 발명은 다양한 변화와 변경 및 균등물을 사용할 수가 있으며, 상기 실시 예를 적절히 변형하여 동일하게 응용할 수 있음이 명확하다. 따라서 상기 기재 내용은 하기 특허청구범위의 한계에 의해 정해지는 본 발명의 범위를 한정하는 것은 아니다.As described above, the preferred embodiment of the present invention has been described, but the present invention may use various changes, modifications, and equivalents. Therefore, the above description does not limit the scope of the invention defined by the limitations of the following claims.

도 1은 종래의 토류벽 공법에 의한 보강구조의 예시도,1 is an exemplary view of a reinforcing structure by a conventional earth wall method;

도 2는 토류판의 강성 보강을 위해 개선된 종래의 토류벽 공법에 의한 보강구조의 다른 예시도,Figure 2 is another illustration of the reinforcement structure by the conventional earth wall method improved for the rigid reinforcement of the earth plate,

도 3과 도 4는 본 발명의 제1실시예에 의한 옹벽용 또는 흙막이용 토류벽 조성장치의 단면도와 정면도,3 and 4 are a cross-sectional view and a front view of the earth wall earthing device for retaining wall or retaining wall according to the first embodiment of the present invention,

도 5는 도 3의 제1실시예에서 제 1말뚝 조립체를 분리하여 도시한 상세도,FIG. 5 is a detailed view of the first pile assembly separated from the first embodiment of FIG. 3;

도 6 내지 도 8은 본 발명의 제2실시예 내지 제4실시예에 의한 옹벽용 또는 흙막이용 토류벽의 조성장치의 단면도,6 to 8 are cross-sectional views of the composition of the earth wall for retaining wall or retaining wall according to the second to fourth embodiments of the present invention,

도 9는 본 발명의 제5실시예에 의한 옹벽용 또는 흙막이용 토류벽 조성장치의 배면 일부를 발췌하여 예시한 사시도이고,FIG. 9 is a perspective view illustrating a portion of the rear surface of the retaining wall forming apparatus for the retaining wall or the retaining wall according to the fifth embodiment of the present invention;

도 10은 도 9의 제5실시예에서 강재말뚝 보강재와 제4강재말뚝 간의 결합부 상세도이다.10 is a detailed view of the coupling portion between the steel pile reinforcing material and the fourth steel pile in the fifth embodiment of FIG.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

11,12,13,14 : 강재말뚝 11a,12a : 토류판 요입부11, 12, 13, 14: steel pile 11a, 12a: earth plate recess

20,21,22 : 토류판 30 : 콘크리트 40,90 : 말뚝 조립체20, 21, 22: earth plate 30: concrete 40, 90: pile assembly

41,42 : 강재말뚝캡 43 : 힌지축 50 : 쏘일 네일41,42: Steel pile cap 43: Hinge shaft 50: Soil nail

60 : 강재말뚝보강재 70 : 조립빔 80 : 조립 케이블60: steel pile reinforcement 70: assembly beam 80: assembly cable

81 : 장력조절부재 82 : 와이어 로프 83 : 띠장 빔81: tension adjusting member 82: wire rope 83: strip beam

84 : 브라켓 85 : 타이케이블 86 : 너트부재84: bracket 85: tie cable 86: nut member

91 : 브라켓 부재 92 : 힌지축 93 : 말뚝캡91: bracket member 92: hinge axis 93: pile cap

100 : 연결부100: connection

Claims (13)

토류벽을 형성하기 위한 토사면에 다수 개가 직접 설치되는 제 1강재말뚝;A first steel pile having a plurality of directly installed on the soil slope for forming the earth wall; 상기 제 1강재말뚝에 대응되는 개수로 각각 구비되며, 토사면의 전면에서 토사면의 후면측으로 상기 각각의 제 1강재말뚝을 지지할 수 있도록 상기 제 1강재말뚝과 지면에 대하여 기울어진 상태로 지반에 타설되는 다수 개의 제 2강재말뚝;The first steel piles are provided in a number corresponding to the first steel piles, and are inclined with respect to the first steel piles and the ground so as to support the respective first steel piles from the front surface of the soil surface to the rear side of the soil surface. A plurality of second steel piles to be poured into; 상기 제 1강재말뚝과 제 2강재말뚝을 조립 또는 분리하며, 각도 조절이 가능하게 힌지 결합된 제 1강재말뚝캡와 제 2강재말뚝캡에 의해 상기 제 1강재말뚝과 제 2강재말뚝을 각도 조절 가능하게 하나의 쌍으로 결합시키는 다수 개의 제 1말뚝 조립체;Assembling or separating the first steel pile and the second steel pile, and the angle of the first steel pile and the second steel pile by the hinged first steel pile cap and the second steel pile cap capable of adjusting the angle can be adjusted. A plurality of first pile assemblies to be coupled in a pair; 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝에 수직하게 결합되는 다수 개의 강재말뚝 보강재를 포함하는 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽 조성장치. Retaining wall or earthwall building device comprising a plurality of steel pile reinforcement coupled to the plurality of second steel piles vertically so as to support the plurality of second steel piles connected to each other. 제 1항에 있어서, 상기 제 1말뚝 조립체는,The method of claim 1, wherein the first pile assembly, 제 1강재말뚝캡와 제 2강재말뚝캡에 상기 각 강재말뚝이 끼워져 삽입될 수 있도록, 상기 각각의 강재말뚝캡에 내부 공간이 각각 형성되는 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽 조성장치.Retaining wall or earthwall construction device for the retaining wall or mudstone, characterized in that the inner space is formed in each of the steel pile cap, so that each steel pile is inserted into the first steel pile cap and the second steel pile cap. 제 1항에 있어서, 상기 제 1말뚝 조립체는,The method of claim 1, wherein the first pile assembly, 상기 제 1강재말뚝과 제 2강재말뚝의 상단부에 제 1강재말뚝캡와 제 2강재말뚝캡의 하단부가 각각 조립되는 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽 조성장치.Retaining wall or earthwall composition for retaining wall, characterized in that the lower end of the first steel pile cap and the second steel pile cap is assembled on the upper end of the first steel pile and the second steel pile. 토사면의 지반에 다수의 강재말뚝을 타설하여 토류벽을 조성하는 방법에 있어서, In the method of forming a earth wall by pouring a plurality of steel piles on the ground of the soil slope, (a) 토사면의 반대방향에서 제 1강재말뚝을 각각 지지할 수 있도록 상기 제 1강재말뚝에 대응되는 개수의 제 2강재말뚝을 상기 제 1강재말뚝 측으로 기울어지게 지반에 타설하는 제 1단계;(a) a first step of placing the second steel piles corresponding to the first steel piles on the ground so as to be inclined toward the first steel piles so as to support the first steel piles in opposite directions of the soil surface; (b) 각도조절 가능하게 힌지 결합된 제 1말뚝 조립체의 제 1강재말뚝캡와 제 2강재말뚝캡의 각도를 상기 제 1강재말뚝과 그에 대응되게 타설된 제 2강재말뚝이 이루는 각도에 대응되게 조절하고, 상기 각도 조절된 제 1말뚝 조립체를 이용하여 상기 제 1강재말뚝 각각에 제 2강재말뚝을 각각 쌍으로 조립하여 토류벽을 이중 보강하는 제 2단계;(b) adjusting the angle of the first steel pile cap and the second steel pile cap of the first pile assembly hingedly coupled to the angle so as to correspond to the angle formed by the first steel pile and the second steel pile which is correspondingly placed; A second step of double reinforcing the earth wall by assembling a pair of second steel piles to each of the first steel piles using the angle-adjusted first pile assembly; (c) 상기 제 1말뚝 조립체에 의해 이중 보강된 토류벽에 쏘일 네일 설치 작업을 실시하는 제 3단계;(c) a third step of performing nail installation work on the earth wall doublely reinforced by the first pile assembly; (d) 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝에 수직하게 다수 개의 강재말뚝 보강재를 설치하는 제 4단계;로 이루어지는 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽 조성방법.(d) a fourth step of installing a plurality of steel pile reinforcement vertically to the plurality of second steel piles so as to support the plurality of second steel piles to be connected to each other; Earth wall construction method 제 4항에 있어서, 상기 제 2단계는,The method of claim 4, wherein the second step, 제 1말뚝 조립체의 제 1강재말뚝캡와 제 2강재말뚝캡 내부에 형성된 공간에 상기 제 1강재말뚝과 제 2강재말뚝의 상단부가 삽입되어 조립되는 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽 조성방법.A method for forming a retaining wall or earthwall for a retaining wall, wherein the upper end of the first steel pile and the second steel pile is inserted into a space formed in the first steel pile cap and the second steel pile cap of the first pile assembly. 토사면의 지반에 설치되는 다수 개의 제 2강재말뚝;A plurality of second steel piles installed on the ground of the soil slope; 상기 각각의 제 2강재말뚝 사이에 제 2강재말뚝과 교대로 설치되되, 제 2강재말뚝에 대하여 엇갈리게 토사면의 지반에 타설되는 다수 개의 제 4강재말뚝;A plurality of fourth steel piles which are alternately installed with the second steel piles between the second steel piles and alternately placed on the ground of the soil slope with respect to the second steel piles; 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝에 수직하게 다층으로 결합되는 다수 개의 강재말뚝 보강재;A plurality of steel pile stiffeners coupled to the plurality of second steel piles in a vertical manner so as to be connected to each other to support the plurality of second steel piles; 상기 다수 개의 강재말뚝 보강재 중에서 최상층에 위치하는 강재말뚝 보강재에 고정 설치되며, 각도 조절이 가능하게 힌지 결합된 말뚝캡을 구비하여 상기 말뚝캡에 의해 최상층의 강재말뚝 보강재에 상기 제 4강재말뚝의 상단부를 각도 조절 가능하게 결합하는 다수 개의 제 2말뚝조립체;를 포함하는 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽 조성장치.The upper end of the fourth steel pile to the steel pile reinforcement of the uppermost layer by the pile cap having a pile cap fixed to the steel pile reinforcement located on the uppermost layer of the plurality of steel pile reinforcement, the hinge can be adjusted to the angle A retaining wall or earthwall composition for a retaining wall comprising a; a plurality of second pile assembly for coupling the angle adjustable. 제 6항에 있어서, 상기 제 2말뚝조립체는,The method of claim 6, wherein the second pile assembly, 힌지축과,Hinge axis, 상기 힌지축 일측에 형성되며, 상기 강재말뚝 보강재의 후면에 고정되는 브라켓 부재와,A bracket member formed at one side of the hinge shaft and fixed to a rear surface of the steel pile reinforcement member; 상기 힌지축의 다른 일측에 상기 브라켓 부재에 대향하여 일체로 형성되되, 상기 힌지축을 중심으로 회전 가능하게 형성되며, 일측 단부가 개방되어 그 개방부의 내부로 상기 제 4강재말뚝의 상단부가 삽입될 수 있는 내부 공간을 형성한 말뚝캡;을 포함하여 구성되는 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽 조성장치.It is formed integrally opposite the bracket member on the other side of the hinge shaft, rotatably formed around the hinge shaft, the one end is open so that the upper end of the fourth steel pile can be inserted into the opening portion A pile wall forming device for a retaining wall or a retaining wall, comprising: a pile cap forming an inner space. 토사면의 지반에 다수의 강재말뚝을 타설하여 토류벽을 조성하는 방법에 있어서, In the method of forming a earth wall by pouring a plurality of steel piles on the ground of the soil slope, 토사면의 지반에 제 2강재말뚝을 타설하는 단계;Placing a second steel pile on the ground of the soil slope; 상기 각각의 제 2강재말뚝 사이에 제 2강재말뚝과 교대로 엇갈리게 다수 개의 제 4강재말뚝을 토사면의 지반에 타설하는 단계;Placing a plurality of fourth steel piles on the ground of the soil surface alternately alternately with the second steel piles between the respective second steel piles; 상기 다수 개의 제 2강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 2강재말뚝에 수직하게 다층으로 다수 개의 강재말뚝 보강재를 결합하는 단계;Coupling a plurality of steel pile reinforcements in a multi-layer perpendicular to the plurality of second steel piles so as to support the plurality of second steel piles by connecting to each other; 상기 다수 개의 강재말뚝 보강재 중에서 최상층에 위치하는 강재말뚝 보강재에 각도 조절이 가능하도록 힌지 결합된 말뚝캡을 구비한 다수 개의 제 2말뚝조립체를 고정 설치한 후 상기 말뚝캡에 의해 최상층의 강재말뚝 보강재에 상기 제 4강재말뚝의 상단부를 각도 조절 가능하게 결합하는 단계;After fixing a plurality of second pile assemblies having a hinge cap coupled to the steel pile reinforcement located on the top layer of the plurality of steel pile reinforcement to enable angle adjustment to the steel pile reinforcement of the top layer by the pile cap Coupling an upper end of the fourth steel pile to be adjustable in angle; 상기 제 2말뚝 조립체에 의해 이중 보강된 토류벽에 쏘일 네일 설치 작업을 실시하는 단계;로 이루어지는 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽 조 성방법.A method of forming a soil wall for a retaining wall or a retaining wall, comprising: performing a nail installation operation on a soil wall double reinforced by the second pile assembly. 토류벽을 형성하기 위한 토사면에 직접 설치되는 다수 개의 제 1강재말뚝;A plurality of first steel piles directly installed on the soil surface for forming the earth wall; 상기 제 1강재말뚝에 각각 대응되는 개수로 구비되며, 상기 제 1강재말뚝과 이격되어 토사면의 반대방향에서 상기 각 제 1강재말뚝에 나란하게 또는 경사지게 지반에 타설되는 다수 개의 제 3강재말뚝;A plurality of third steel piles provided in a number corresponding to each of the first steel piles and spaced apart from the first steel piles and placed on the ground side by side or inclined to the first steel piles in opposite directions of the soil surface; 상기 제 1강재말뚝 및 제 3강재말뚝에 각각 대응되는 개수로 구비되며, 지면으로부터 이격되어 상기 제 1강재말뚝과 제 3강재말뚝의 상단부에 거치되는 형태로 양단부가 조립 또는 분리되는 조립빔;An assembly beam provided with a number corresponding to each of the first steel pile and the third steel pile, the both ends being assembled or separated from each other by being spaced apart from the ground and mounted on the upper ends of the first steel pile and the third steel pile; 각도 조절이 가능하게 힌지 결합된 두 개의 말뚝캡에 의해 상기 제 1강재말뚝과 조립빔 및 제 3강재말뚝과 조립빔을 각도 조절 가능하게 하나의 쌍으로 결합시키는 다수 개의 제 1말뚝 조립체;A plurality of first pile assemblies configured to couple the first steel pile and the assembly beam and the third steel pile and the assembly beam by one pair so that angle adjustment is possible by two pile caps hinged to each other; 상기 다수 개의 제 3강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 3강재말뚝에 수직하게 다수 개 설치되는 강재말뚝 보강재를 포함하는 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽의 조성장치.Retaining device for the retaining wall or earthwall wall comprising a steel pile reinforcement is installed in a plurality of vertically perpendicular to the plurality of third steel piles to support the plurality of third steel piles. 삭제delete 토류벽을 형성하기 위한 토사면에 다수 개가 직접 설치되며 상단부에 적어도 하나의 케이블 삽입홈을 형성한 제 1강재말뚝;A first steel pile having a plurality of directly installed on the soil surface for forming the earth wall and having at least one cable insertion groove formed at an upper end thereof; 상기 제 1강재말뚝에 각각 대응되는 개수로 구비되며, 상기 제 1강재말뚝과 이격되어 토사면의 반대방향에서 상기 각 제 1강재말뚝에 나란하게 또는 경사지게 지반에 타설되고, 상단부에 적어도 하나의 케이블 삽입홈을 형성한 제 3강재말뚝;It is provided with a number corresponding to each of the first steel piles, spaced apart from the first steel piles are placed on the ground side by side or inclined to the first steel piles in the opposite direction of the soil surface, at least one cable at the upper end A third steel pile having an insertion groove; 상기 제 1강재말뚝 및 제 3강재말뚝에 각각 대응되는 개수로 구비되며, 지면으로부터 이격되어 상기 제 1강재말뚝과 제 3강재말뚝 상단부의 케이블 삽입홈을 통해 각 강재말뚝의 외측으로 양단부가 고정되되 상기 제 1강재말뚝과 제 3강재말뚝을 신축 가능하게 하나의 쌍으로 결합시키는 조립 케이블;It is provided with a number corresponding to the first steel pile and the third steel pile, respectively, and is spaced apart from the ground and both ends are fixed to the outside of each steel pile through the cable insertion groove of the upper end of the first steel pile and the third steel pile. An assembly cable configured to elastically couple the first steel pile and the third steel pile into one pair; 상기 다수 개의 제 3강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 3강재말뚝에 수직하게 다수 개 설치되는 강재말뚝 보강재를 포함하며,It includes a plurality of steel pile reinforcement is installed in the vertical to the plurality of third steel piles, so as to support the plurality of third steel piles connected to each other, 상기 조립 케이블은,The assembly cable, 케이블의 일부를 장력 조절부재로 구성한 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽의 조성장치.A device for forming a retaining wall or retaining wall for a retaining wall, wherein a part of the cable is configured as a tension adjusting member. 제 11항에 있어서, 상기 조립 케이블은,The method of claim 11, wherein the assembly cable, 상기 장력 조절부재의 양단을 상기 제 1강재말뚝 및 제 3강재말뚝에 각각 연결하는 와이어 로프를 포함하며, A wire rope connecting both ends of the tension adjusting member to the first steel pile and the third steel pile, respectively. 상기 와이어 로프의 양단부에는 고리가 형성되어 상기 제 1강재말뚝과 제 3강재말둑의 각 케이블 삽입홈을 통해 각 강재말뚝의 외측에 부착된 띠장 빔에 걸어 고정할 수 있도록 구성된 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽의 조성장치.Retaining wall is formed at both ends of the wire rope is configured to be fixed to the banding beam attached to the outside of each steel pile through each cable insertion groove of the first steel pile and the third steel pile. Or earth-moving earth wall composition device. 토류벽을 형성하기 위한 토사면에 다수 개가 직접 설치되며 상단부에 적어도 하나의 케이블 삽입홈을 형성한 제 1강재말뚝;A first steel pile having a plurality of directly installed on the soil surface for forming the earth wall and having at least one cable insertion groove formed at an upper end thereof; 상기 제 1강재말뚝에 각각 대응되는 개수로 구비되며, 상기 제 1강재말뚝과 이격되어 토사면의 반대방향에서 상기 각 제 1강재말뚝에 나란하게 또는 경사지게 지반에 타설되고, 상단부에 적어도 하나의 케이블 삽입홈을 형성한 제 3강재말뚝;It is provided with a number corresponding to each of the first steel piles, spaced apart from the first steel piles are placed on the ground side by side or inclined to the first steel piles in the opposite direction of the soil surface, at least one cable at the upper end A third steel pile having an insertion groove; 상기 제 1강재말뚝 및 제 3강재말뚝에 각각 대응되는 개수로 구비되며, 지면으로부터 이격되어 상기 제 1강재말뚝과 제 3강재말뚝 상단부의 케이블 삽입홈을 통해 각 강재말뚝의 외측으로 양단부가 고정되되 상기 제 1강재말뚝과 제 3강재말뚝을 신축 가능하게 하나의 쌍으로 결합시키는 조립 케이블;It is provided with a number corresponding to the first steel pile and the third steel pile, respectively, and is spaced apart from the ground and both ends are fixed to the outside of each steel pile through the cable insertion groove of the upper end of the first steel pile and the third steel pile. An assembly cable configured to elastically couple the first steel pile and the third steel pile into one pair; 상기 다수 개의 제 3강재말뚝을 서로 연결하여 지지할 수 있도록, 상기 다수 개의 제 3강재말뚝에 수직하게 다수 개 설치되는 강재말뚝 보강재를 포함하며,It includes a plurality of steel pile reinforcement is installed in the vertical to the plurality of third steel piles, so as to support the plurality of third steel piles connected to each other, 상기 조립 케이블은,The assembly cable, 타이 케이블로 구성되며, Consists of tie cables, 상기 타이 케이블의 양단부에는 너트 결합을 위한 나사산이 형성되어 상기 제 1강재말뚝과 제 3강재말뚝의 각 케이블 삽입홈을 통해 각 강재말뚝의 외측으로 돌출되고, 너트 조립 위치에 따라 케이블의 길이를 조절할 수 있도록 너트부재에 의해 각 강재말뚝의 외측에서 그 양단부가 조립되는 것을 특징으로 하는 옹벽용 또는 흙막이용 토류벽의 조성장치.Both ends of the tie cable are formed with threads for coupling nuts, protruding to the outside of each steel pile through the cable insertion grooves of the first steel pile and the third steel pile, and adjusting the length of the cable according to the nut assembly position. Retaining device for retaining wall or earth retaining wall, characterized in that both ends are assembled at the outside of each steel pile by a nut member.
KR1020070090103A 2007-07-23 2007-09-05 Construction method and the apparatus of a ground retaining structures or walls KR100797185B1 (en)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
KR1020070073727 2007-07-23
KR20070073727 2007-07-23
KR20070078145 2007-08-03
KR1020070078145 2007-08-03

Publications (1)

Publication Number Publication Date
KR100797185B1 true KR100797185B1 (en) 2008-01-23

Family

ID=39218974

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070090103A KR100797185B1 (en) 2007-07-23 2007-09-05 Construction method and the apparatus of a ground retaining structures or walls

Country Status (1)

Country Link
KR (1) KR100797185B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101262357B1 (en) * 2011-03-25 2013-05-08 임재욱 Inclined Earth Retaining Structure Method
KR101568982B1 (en) * 2014-03-18 2015-11-13 박정원 Shutting off water method of hole on sheet pile
KR101821342B1 (en) * 2017-02-06 2018-01-23 한창헌 Connection structure of before and after pile
CN108999196A (en) * 2018-08-15 2018-12-14 北京市政建设集团有限责任公司 In-network processing construction method for supporting between a kind of stake

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001040671A (en) 1999-05-25 2001-02-13 Bridgestone Corp Slope reinforcing unit, and filling reinforcing structure and filling reinforcing construction method using the unit
JP2004211459A (en) 2003-01-07 2004-07-29 Takenaka Komuten Co Ltd Earth retaining structure
KR20060032823A (en) * 2004-10-13 2006-04-18 코오롱건설주식회사 Soil retaining method using two rows pile

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001040671A (en) 1999-05-25 2001-02-13 Bridgestone Corp Slope reinforcing unit, and filling reinforcing structure and filling reinforcing construction method using the unit
JP2004211459A (en) 2003-01-07 2004-07-29 Takenaka Komuten Co Ltd Earth retaining structure
KR20060032823A (en) * 2004-10-13 2006-04-18 코오롱건설주식회사 Soil retaining method using two rows pile

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101262357B1 (en) * 2011-03-25 2013-05-08 임재욱 Inclined Earth Retaining Structure Method
KR101568982B1 (en) * 2014-03-18 2015-11-13 박정원 Shutting off water method of hole on sheet pile
KR101821342B1 (en) * 2017-02-06 2018-01-23 한창헌 Connection structure of before and after pile
CN108999196A (en) * 2018-08-15 2018-12-14 北京市政建设集团有限责任公司 In-network processing construction method for supporting between a kind of stake

Similar Documents

Publication Publication Date Title
CN106703045A (en) Assembled type crown beam, surrounding purlin and waist beam structure
KR20130006420A (en) Method of constructing underground structure to be newly built
KR100797185B1 (en) Construction method and the apparatus of a ground retaining structures or walls
KR101255027B1 (en) Precast rahmen type box culvert
KR101026583B1 (en) A wale system for supporting earth retaining wall
KR200409942Y1 (en) Strut supporting member for temporary soil sheathing
KR100289256B1 (en) Tunnel construction method in shallow toffee area
KR100869764B1 (en) Earth of building land-side protection wall structure
KR100657655B1 (en) Assembly pile for method of ground improvement
KR101677236B1 (en) Double-layered steel plate cutoff wall structure and construction method of cutoff wall of temporary facility using the same
JP3564669B2 (en) Reinforcement spacer and foundation pile method
KR101127475B1 (en) Device for connecting wales
JP2000328586A (en) Retaining wall
KR101545713B1 (en) Composite type cutoff wall of steel temporary facility and construction method of the same
KR100327066B1 (en) A Retaining Wall Structure for using Pipes and It&#39;s Construction Method
KR100744972B1 (en) Earth of building land-side protection wall structure
JP2973815B2 (en) Construction method of pressure-resistant wall under the building
KR101218825B1 (en) Method of land-side protection wall using bracing
KR200361098Y1 (en) Retaining wall for reinforcing road slope
KR200429236Y1 (en) Temporarily installed material capable of easy attachment and detachment
KR100417487B1 (en) Filling crushed stone type retainingwall
JP3135495B2 (en) Construction method of avalanche and rock fall protection fence and avalanche and rock fall protection fence
KR200231108Y1 (en) Tunnel Construction Structure for using Wave Profile Type Steel Plate
JP2571426B2 (en) Construction method of retaining wall
JP4319231B2 (en) Approach caisson and method for constructing tunnel approach section composed of caisson

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
G170 Publication of correction
FPAY Annual fee payment

Payment date: 20130115

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20140108

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20150116

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20160118

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20170116

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20180116

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20190116

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20200116

Year of fee payment: 13