JPH11324336A - Repair works management device, repair works management method, and recording medium - Google Patents

Repair works management device, repair works management method, and recording medium

Info

Publication number
JPH11324336A
JPH11324336A JP13036398A JP13036398A JPH11324336A JP H11324336 A JPH11324336 A JP H11324336A JP 13036398 A JP13036398 A JP 13036398A JP 13036398 A JP13036398 A JP 13036398A JP H11324336 A JPH11324336 A JP H11324336A
Authority
JP
Japan
Prior art keywords
construction
information
input
work
storage means
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13036398A
Other languages
Japanese (ja)
Inventor
Kenji Hasebe
憲次 長谷部
Keiko Otani
圭子 大谷
Sachiko Shinohara
祥子 篠原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP13036398A priority Critical patent/JPH11324336A/en
Publication of JPH11324336A publication Critical patent/JPH11324336A/en
Pending legal-status Critical Current

Links

Landscapes

  • Control By Computers (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To manage by computer a series of information from request for repair works to collating. SOLUTION: This repair works management device includes a works information storage means 1 for storing works information until a fixed period of time, a works hysteresis information storage means 3 for storing information of works which has passed fixed period of time, an information input/output means 5 for conducting the processing of saving data in the works information storage means 1 and the works hysteresis information storage means 3 and the processing of retrieving the works information storage means 1 and the works hysteresis information storage means 3 for data, and plural works information register and retrieval request means 7 for making the works information register request and retrieval request for the information input/output means 5. At this time, the works information register and retrieval request means 7 is formed by an input device 9, an output device 11 and a works information retrieval and register processing means 13 for transmitting the works information register request and retrieval request input by the input device 9 to the information input/output means 5 and outputting the retrieval result from the information input/ output device 5 to the output device 11.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、発電所等のプラン
トの日常の保全修理工事(以下、保修工事という。)を
管理する管理装置および管理方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a management apparatus and a management method for managing daily maintenance and repair work (hereinafter referred to as maintenance work) of a plant such as a power plant.

【0002】[0002]

【従来の技術】発電所等のプラントの設備保守のため、
日常的に保修工事が行われており、その工事の依頼、工
事業者への指示、工事費の算出、検収など一連の作業は
全て紙伝票で運用されるのが普通である。これを効率よ
く行うために、コンピュータによる保修工事の管理が望
まれている。
2. Description of the Related Art In order to maintain facilities of plants such as power plants,
Maintenance work is performed on a daily basis, and a series of work, such as requesting construction work, instructing construction contractors, calculating construction costs, and receiving inspections, is usually performed using paper slips. In order to carry out this efficiently, it is desired to manage maintenance work using a computer.

【0003】[0003]

【発明が解決しようとする課題】ところで、日常保修工
事をコンピュータで管理するには、保修工事にかかわる
人が通常居る場所から工事情報を更新したり検索したり
できようにする必要があり、このように大勢の人が同時
に管理作業を行うことができる管理装置は得られていな
かった。
By the way, in order to manage daily maintenance work by computer, it is necessary to be able to update and search construction information from a place where people who are involved in maintenance work are usually present. As described above, a management device that allows a large number of people to perform management work at the same time has not been obtained.

【0004】本発明は、かかる点に対処してなされたも
ので、工事管理作業を複数の人が同時に実施することが
できる保修工事管理装置を提供することを目的とする。
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and it is an object of the present invention to provide a maintenance work management apparatus that allows a plurality of persons to simultaneously perform a work management operation.

【0005】また本発明は、イメージの補助情報によ
り、文字情報を補って不具合箇所の特定を確実にするこ
とができる保修工事管理装置を提供することを目的とす
る。
It is another object of the present invention to provide a maintenance work management apparatus capable of supplementing character information with image auxiliary information to reliably specify a defective portion.

【0006】また本発明は、プラント停止時に実施する
など実施時期に制限のある工事とそうでない日常工事を
区別することができる保修工事管理装置を提供すること
を目的とする。
It is another object of the present invention to provide a maintenance work management device that can distinguish between work having a limited execution time such as when the plant is shut down and daily work that is not.

【0007】また本発明は、登録された工事情報に誤り
があった場合、その情報を登録した人に戻すことができ
る保修工事管理装置を提供することを目的とする。
It is another object of the present invention to provide a maintenance work management apparatus which can return registered work information to a registered person when there is an error.

【0008】また本発明は、勘定科目ごとに工事件数や
金額を把握することができる保修工事管理装置を提供す
ることを目的とする。
Another object of the present invention is to provide a maintenance work management device capable of grasping the number of works and the amount of money for each account item.

【0009】また本発明は、統計処理して不具合の傾向
等を把握することができる保修工事管理装置を提供する
ことを目的とする。
Another object of the present invention is to provide a maintenance work management device capable of grasping the tendency of a defect by performing statistical processing.

【0010】また本発明は、工費計算の基盤となる管理
費係数や、工事単価、税率等の変更に適切に対応するこ
とができる保修工事管理装置を提供することを目的とす
る。
Another object of the present invention is to provide a maintenance work management apparatus which can appropriately cope with changes in a management cost coefficient, a construction unit price, a tax rate, and the like, which serve as a basis for calculation of construction costs.

【0011】また本発明は、工事情報に対しセキュリテ
ィーをもたせることができる保修工事管理装置を提供す
ることを目的とする。
Another object of the present invention is to provide a maintenance work management device capable of providing security to construction information.

【0012】[0012]

【課題を解決するための手段】すなわち、請求項1の発
明は、プラントの設備機器の保全修理を行う保修工事を
管理する装置において、保修工事ごとに、保修の依頼内
容を示す工事依頼情報、当該保修の作業を業者に指示す
る内容の作業指示情報、当該工事の作業実績を示す工事
実績情報、および当該工事の検収内容を示す工事検収情
報の各工事情報を工事の進捗段階に応じて順次記憶する
工事情報記憶手段と、前記工事情報記憶手段の工事情報
の登録および検索を行う情報入出力手段と、前記情報入
出力手段と伝送路を介して接続され、入力装置および出
力装置を備え、前記入力装置を介して入力された情報に
基づいて前記情報入出力手段に対して工事情報の登録要
求または検索要求を行い、前記情報入出力手段からの検
索結果を前記出力装置へ出力する、少なくとも1つの工
事情報登録・検索要求手段とを具備することを特徴とす
る。
That is, the invention of claim 1 is an apparatus for managing maintenance work for performing maintenance and repair of plant equipment and equipment, comprising: construction request information indicating the contents of a maintenance request for each maintenance work; Each piece of work information, such as work instruction information that instructs the contractor to perform the maintenance work, construction performance information that indicates the work performance of the construction, and construction acceptance information that indicates the contents of the inspection of the construction, is sequentially performed according to the progress stage of the construction. Construction information storage means for storing, information input / output means for registering and searching for construction information in the construction information storage means, connected to the information input / output means via a transmission path, comprising an input device and an output device, A construction information registration request or a search request is made to the information input / output means based on the information input via the input device, and a search result from the information input / output means is output to the information input / output means. Output to location, characterized by comprising at least one construction information registration and retrieval request unit.

【0013】請求項2の発明は、請求項1の保修工事管
理装置において、前記工事情報登録・検索要求手段が、
前記入力装置からの内容承認要求により、前記情報入出
力手段を介して前記工事情報記憶手段から該当する工事
情報を読み出して前記出力装置に出力し、前記入力装置
を介して入力された内容承認信号により前記情報入出力
手段を介して前記工事情報記憶手段の該当する工事情報
に承認情報を付加する手段を有することを特徴とする。
According to a second aspect of the present invention, in the maintenance work management device of the first aspect, the construction information registration / search requesting means includes:
According to the content approval request from the input device, the corresponding construction information is read from the construction information storage means via the information input / output means and output to the output device, and the content approval signal input via the input device Means for adding approval information to the corresponding construction information in the construction information storage means via the information input / output means.

【0014】請求項3の発明は、請求項1または2の保
修工事管理装置において、前記工事情報登録・検索要求
手段が、前記入力装置からの工事情報の入力要求によ
り、工事情報の入力を促す工事情報入力画面を前記出力
装置に出力し、前記工事情報入力画面にしたがって前記
入力装置を介して入力された情報に基づいて工事情報を
作成し、前記情報入出力手段を介して前記工事情報記憶
手段に登録する手段を有することを特徴とする。
According to a third aspect of the present invention, in the maintenance work management device according to the first or second aspect, the construction information registration / search request means prompts for the input of the construction information in response to a construction information input request from the input device. A construction information input screen is output to the output device, construction information is created based on information input through the input device according to the construction information input screen, and the construction information storage is performed through the information input / output means. It is characterized by having means for registering in means.

【0015】請求項4の発明は、請求項1または2の保
修工事管理装置において、前記工事情報登録・検索要求
手段が、前記入力装置からの工事情報の入力要求によ
り、前段階の情報まで登録された保修工事を対象工事と
して前記情報入出力手段を介して前記工事情報記憶手段
から取り出し、対象工事一覧を前記出力装置に出力する
手段と、前記対象工事一覧から前記入力装置を介して選
択された保修工事について工事情報の入力を促す工事情
報入力画面を前記出力装置に出力する手段と、前記工事
情報入力画面に従って前記入力装置を介して入力された
情報に基づいて工事情報を作成し、前記情報入出力手段
を介して前記工事情報記憶手段の当該保修工事の登録情
報に付加する手段とを有することを特徴とする。
According to a fourth aspect of the present invention, in the maintenance work management device according to the first or second aspect, the construction information registration / search requesting means registers up to information of a previous stage in response to a construction information input request from the input device. Means for taking out the maintenance work as a target work from the work information storage means via the information input / output means, outputting a target work list to the output device, and selecting the target work list from the target work list via the input device. Means for outputting a construction information input screen for prompting the input of construction information for the maintenance work to the output device, and creating construction information based on the information input via the input device according to the construction information input screen, Means for adding to the registered information of the maintenance work in the work information storage means via an information input / output means.

【0016】請求項1〜4の発明においては、工事情報
記憶手段への工事情報の出し入れを行う情報入出力手段
に伝送路を介して端末となる工事情報登録・検索要求手
段を増設可能に接続することにより、保修工事にかかわ
る、工事依頼者、作業指示者、工事請負業者、それぞれ
の上長などの多くの人が近くの端末から工事情報を管理
操作することができる。
According to the first to fourth aspects of the present invention, a construction information registration / retrieval request means serving as a terminal is connected to an information input / output means for transferring construction information to / from the construction information storage means via a transmission line so as to be extendable. By doing so, many people, such as a construction client, a work instructor, a construction contractor, and their respective superiors, involved in maintenance work can manage and operate construction information from nearby terminals.

【0017】請求項5の発明は、請求項1ないし4のい
ずれか1項の保修工事管理装置において、保修工事を補
足説明するイメージ情報を記憶するイメージ情報記憶手
段を具備し、前記情報入出力手段が、前記工事情報登録
・検索要求手段からの登録要求により、登録要求ととも
に送信されたイメージ情報および工事情報のうちイメー
ジ情報を前記イメージ情報記憶手段に格納し、前記工事
情報に前記イメージ情報との連携情報を付加して前記工
事情報記憶手段に登録する手段と、前記工事情報登録・
検索要求手段からの検索要求により、前記工事情報記憶
手段から該当する工事情報を検索し、当該工事情報に付
加された連携情報に基づいて前記イメージ情報記憶手段
から該当するイメージ情報を検索する手段とを有するこ
とを特徴とする。
According to a fifth aspect of the present invention, there is provided the maintenance work management apparatus according to any one of the first to fourth aspects, further comprising image information storage means for storing image information supplementarily describing the maintenance work, wherein the information input / output is performed. Means for storing, in the image information storage means, image information of the image information and the construction information transmitted together with the registration request in response to a registration request from the construction information registration / search requesting means, Means for adding the link information of the construction information and registering the construction information in the construction information storage means;
Means for retrieving the relevant construction information from the construction information storage means in response to a search request from the search request means, and retrieving the relevant image information from the image information storage means based on the link information added to the construction information; It is characterized by having.

【0018】請求項5の発明においては、工事情報とし
て、文字だけでなく、保修の必要な箇所や状況を示すポ
ンチ絵などのイメージ情報を併せて管理することによ
り、より的確に情報の把握や伝達を行うことができる。
According to the fifth aspect of the present invention, not only the text but also image information such as a punch picture indicating the location or situation requiring maintenance is managed as the construction information, so that the information can be grasped and transmitted more accurately. It can be performed.

【0019】請求項6の発明は、請求項1ないし5のい
ずれか1項の保修工事管理装置において、作業保留対象
の工事依頼情報を記憶する保留工事情報記憶手段を具備
し、前記工事情報登録・検索要求手段が、作業指示の段
階で、前記出力装置に出力された対象工事一覧から前記
入力装置を介して作業保留対象として選択された保修工
事について、前記情報入出力手段を介して前記工事情報
記憶手段から該当する工事情報を前記保留工事情報記憶
手段に移動する手段と、前記入力装置からの要求によ
り、前記情報入出力手段を介して前記保留工事情報記憶
手段に記憶されている作業保留対象の工事情報を読み出
し、保留工事一覧を前記出力装置に出力する手段と、前
記保留工事一覧から前記入力装置を介して選択された工
事情報を前記保留工事情報記憶手段から前記工事情報記
憶手段に移動する手段とを有することを特徴とする。
According to a sixth aspect of the present invention, there is provided the maintenance work management apparatus according to any one of the first to fifth aspects, further comprising a suspended construction information storage means for storing construction request information to be suspended. The search request means, at the stage of the work instruction, the maintenance work selected as a work suspension target via the input device from the target work list output to the output device, the work via the information input / output means Means for moving the relevant construction information from the information storage means to the reserved construction information storage means, and a work reservation stored in the reserved construction information storage means via the information input / output means in response to a request from the input device. Means for reading out the target construction information and outputting a list of the pending constructions to the output device; and transmitting the construction information selected from the list of the pending constructions via the input device to the construction Characterized in that the information storage means and means for moving the construction information storage unit.

【0020】請求項6の発明においては、工事情報が登
録された保修工事がプラント停止時にしか実施できない
ような作業保留対象工事と判断した時点で、その工事情
報を保留工事情報記憶手段に移して通常の工事情報と区
別して管理することにより、保修工事を混乱なくスムー
ズに進捗させることができる。
In the invention of claim 6, when the maintenance work in which the construction information is registered is determined to be a work to be suspended which can only be performed when the plant is stopped, the construction information is transferred to the suspended construction information storage means. The maintenance work can be smoothly progressed without confusion by managing the work separately from normal construction information.

【0021】請求項7の発明は、請求項1ないし6のい
ずれか1項の保修工事管理装置において、前記工事情報
登録・検索要求手段が、前記工事情報記憶手段から前記
出力装置に出力された工事情報について、前記入力装置
からの差し戻し要求により、前記入力装置を介して入力
された前記工事情報の不備を示す差し戻し理由を、前記
情報入出力手段を介して前記工事情報記憶手段の当該工
事情報に付加する手段と、前記入力装置からの要求によ
り、前記情報入出力手段を介して前記工事情報記憶手段
から前記差し戻し理由を付加された工事情報を修正対象
工事情報として読み出し、前記出力装置に修正対象工事
情報一覧を出力する手段と、前記修正対象工事情報一覧
から前記入力装置を介して選択された工事情報につい
て、前記入力装置を介して入力された情報に基づいて、
前記情報入出力手段を介して前記工事情報記憶手段の当
該工事情報の不備を修正しかつ前記差し戻し理由を削除
する手段とを有することを特徴とする。
According to a seventh aspect of the present invention, in the maintenance work management apparatus according to any one of the first to sixth aspects, the construction information registration / search request means is output from the construction information storage means to the output device. With regard to the construction information, a return request indicating a defect of the construction information input via the input device by the return request from the input device, the construction information of the construction information storage means via the information input / output means, Means for adding the reason for remanding from the construction information storage means via the information input / output means in response to a request from the input device, as construction information to be corrected, and corrects the output device. Means for outputting a target construction information list, and for the construction information selected from the correction target construction information list via the input device, the input device Based on the information inputted by,
Means for correcting, via the information input / output means, deficiencies of the work information in the work information storage means and deleting the reason for return.

【0022】請求項7の発明においては、工事依頼の入
力内容や工事実績の入力内容に不備があった場合には、
その保修工事の進捗段階を工事依頼の入力や工事実績の
入力段階に差し戻すことにより、その情報を入力した当
事者に、差し戻されたことを通知するとともに工事情報
の不備を正すことができる。
In the invention according to claim 7, when there is a defect in the input contents of the construction request and the input contents of the construction results,
By reverting the progress stage of the maintenance work to the input of the construction request and the input of the construction results, it is possible to notify the party who has input the information that the maintenance work has been returned and correct the deficiency of the construction information.

【0023】請求項8の発明は、請求項1ないし7のい
ずれか1項の保修工事管理装置において、経理上の工費
区分を示す勘定科目ごとに勘定科目コードを記憶する勘
定科目コード記憶手段を具備し、前記情報入出力手段
が、前記工事情報登録・検索要求手段から送信された勘
定科目コードについて前記勘定科目コード記憶手段に記
憶されているか否かを判定し、記憶されているとき前記
勘定科目コードを前記工事情報記憶手段の対応する工事
情報に付加する手段を有することを特徴とする。
According to an eighth aspect of the present invention, there is provided the maintenance work management apparatus according to any one of the first to seventh aspects, wherein the account code storage means for storing an account code for each account showing the accounting cost division. The information input / output means determines whether or not the account code transmitted from the construction information registration / search request means is stored in the account code storage means. It is characterized by having means for adding a subject code to the corresponding construction information in the construction information storage means.

【0024】請求項8の発明においては、工事情報に勘
定科目コードを付加することにより、勘定科目毎の工事
件数や工事金額を集計することができる。また、勘定科
目コードの入力時に、すべての勘定科目コードを記憶す
る勘定科目コード手段を参照して、入力したコードがあ
るか否かを判断することにより、勘定科目コードの入力
ミスを防ぐことができる。
According to the eighth aspect of the invention, by adding an account code to the construction information, the number of construction works and the construction cost for each account can be totaled. Also, when inputting an account code, it is possible to prevent an input error of the account code by determining whether or not the input code exists by referring to the account code means for storing all the account codes. it can.

【0025】請求項9の発明は、請求項1ないし8のい
ずれか1項の保修工事管理装置において、保修工事を統
計処理する観点を示す統計対象項目別に、それぞれ設定
された統計用コードを記憶する統計コード記憶手段を具
備し、前記情報入出力手段が、前記工事情報登録・検索
要求手段から送信された前記統計対象項目に対応する各
統計用コードについて前記統計コード記憶手段に記憶さ
れているか否かを判定し、記憶されているとき前記各統
計用コードを前記工事情報記憶手段の対応する工事情報
に付加する手段と、前記工事情報登録・検索要求手段か
ら送信された統計対象項目を含む検索条件に基づいて前
記工事情報記憶手段を検索し、検索結果を当該統計対象
項目によって統計処理し前記工事情報登録・検索要求手
段に送信する手段とを有することを特徴とする。
According to a ninth aspect of the present invention, in the maintenance work management apparatus according to any one of the first to eighth aspects, a statistical code set for each statistical target item indicating a viewpoint of performing statistical processing of the maintenance work is stored. Whether the information input / output means is stored in the statistical code storage means for each statistical code corresponding to the statistical target item transmitted from the construction information registration / search request means. Means for determining whether or not each of the statistical codes is stored in the corresponding construction information in the construction information storage means, and a statistical target item transmitted from the construction information registration / search request means. Means for searching the construction information storage means based on search conditions, statistically processing a search result according to the statistical target item, and transmitting the result to the construction information registration / search request means Characterized in that it has a.

【0026】請求項9の発明においては、工事情報に現
象、原因、処置、保修対象機器などの各種統計項目情報
を付加することにより、その項目をもとに統計処理を行
うことができ、不具合の傾向把握を容易にすることがで
きる。
According to the ninth aspect of the invention, by adding various statistical item information such as a phenomenon, a cause, a measure, and a device to be repaired to the construction information, statistical processing can be performed based on the items. Can be easily grasped.

【0027】請求項10の発明は、請求項1ないし9の
いずれか1項の保修工事管理装置において、工費計算に
必要なシステム管理定数をその有効開始日とともに記憶
するシステム管理定数記憶手段を具備し、前記情報入出
力手段が、前記工事情報登録・検索要求手段から送信さ
れた工事期間を示す情報に基づいて、前記システム管理
定数記憶手段から有効なシステム管理定数を取り出す手
段を有し、前記工事情報登録・検索要求手段が、前記情
報入出力手段から送信されたシステム管理定数と前記入
力装置から入力された作業実績または作業査定に基づい
て工費を算出する手段を有することを特徴とする。
According to a tenth aspect of the present invention, there is provided the maintenance work management apparatus according to any one of the first to ninth aspects, further comprising a system management constant storage means for storing a system management constant required for calculating a construction cost together with its effective start date. The information input / output means has means for extracting a valid system management constant from the system management constant storage means based on information indicating the construction period transmitted from the construction information registration / search request means, The construction information registration / search requesting means has means for calculating a construction cost based on a system management constant transmitted from the information input / output means and a work record or work evaluation input from the input device.

【0028】請求項10の発明においては、切替予定の
ある管理費率、作業員1人1日当たりの作業単価、税率
などのシステム管理定数を有効開始日とともに管理する
ことにより、その作業日を有効開始日と比較して、適切
なシステム管理定数を自動的に適用することができる。
According to the tenth aspect of the present invention, the system management constants such as the management cost rate scheduled to be switched, the work unit price per worker per day, and the tax rate are managed together with the effective start date so that the work day can be made effective. Appropriate system management constants can be automatically applied compared to the start date.

【0029】請求項11の発明は、請求項1ないし10
の保修工事管理装置において、IDごとに使用可能な機
能と使用付加の機能を示す機能制約情報を記憶する機能
制約情報記憶手段と、前記工事情報登録・検索要求手段
から送信されたIDにより、前記機能制約情報記憶手段
から対応する機能制約情報を読み出し、前記工事情報登
録・検索要求手段に送信するID照合手段とを具備する
ことを特徴とする。
The invention of claim 11 is the invention of claims 1 to 10
In the maintenance work management device of the above, the function constraint information storage means for storing function constraint information indicating the functions available for each ID and the function of additional use, and the ID transmitted from the construction information registration and search request means, ID checking means for reading out corresponding function restriction information from the function restriction information storage means and transmitting the read function restriction information to the construction information registration / search request means.

【0030】請求項11の発明においては、入力装置よ
り入力されたIDにより使用可能な機能を制限するた
め、工事情報のセキュリティーを保つことができる。
According to the eleventh aspect of the present invention, since the functions that can be used are restricted by the ID input from the input device, the security of the construction information can be maintained.

【0031】請求項12の発明は、請求項1ないし11
のいずれか1項の保修工事管理装置において、過去に完
了した保修工事の工事情報を記憶する工事履歴情報記憶
手段を具備し、前記情報入出力手段が、前記工事情報記
憶手段に工事検収情報まで登録され工事完了した保修工
事のうち所定の判定基準を満たした保修工事について前
記工事情報記憶手段から前記工事履歴情報記憶手段に工
事情報を移動する手段を有することを特徴とする。
The twelfth aspect of the present invention provides the first to eleventh aspects.
The maintenance work management device according to any one of the above, further comprising a construction history information storage means for storing construction information of maintenance work completed in the past, the information input / output means, the construction information storage means to the construction acceptance information It is characterized by having means for transferring construction information from the construction information storage means to the construction history information storage means for the maintenance work satisfying a predetermined judgment criterion among the registered and completed maintenance works.

【0032】請求項12の発明においては、過去の保修
工事についても工事履歴情報として管理することによ
り、過去に同様な保修工事があれば、その保修工事の工
事情報を有効に活用することができる。請求項13の発
明は、プラントの設備機器の保全修理を行う保修工事の
工事情報をコンピュータを用いて管理する保修工事管理
方法において、工事依頼入力機能を選択する信号の入力
により、保修工事の依頼を受け付ける工事依頼入力画面
を表示する工程と、前記工事依頼入力画面に従って入力
された情報に基づいて工事依頼情報を作成する工程と、
作成された工事依頼情報を工事情報記憶手段に登録する
工程と、工事依頼入力内容承認機能を選択する信号の入
力により、前記工事情報記憶手段から工事依頼情報まで
登録されたすべての工事を抽出し、工事依頼承認対象工
事として一覧表示する工程と、一覧表示された工事依頼
承認対象工事のいずれかを指定する信号の入力により、
指定された工事の依頼入力内容を表示する工程と、表示
された工事依頼入力内容を承認する信号の入力により、
当該工事依頼情報の内容承認情報を前記工事情報記憶手
段に登録する工程と、作業指示入力機能を選択する信号
の入力により、前記工事情報記憶手段から工事依頼情報
の内容承認情報まで登録されたすべての工事を抽出し、
作業指示対象工事として一覧表示する工程と、一覧表示
された作業指示対象工事のいずれかを指定する信号の入
力により、指定された工事の作業指示入力画面を表示す
る工程と、前記作業指示入力画面に従って入力された情
報に基づいて作業指示情報を作成する工程と、作成され
た作業指示情報を対応する工事の登録情報に付加して前
記工事情報記憶手段に登録する工程と、作業指示入力内
容承認機能を選択する信号の入力により、前記工事情報
記憶手段から作業指示情報まで登録されたすべての工事
を抽出し、作業指示承認対象工事として一覧表示する工
程と、一覧表示された作業指示承認対象工事のいずれか
を指定する信号の入力により、指定された工事の作業指
示入力内容を表示する工程と、表示された作業指示入力
内容を承認する信号の入力により、当該作業指示情報の
内容承認情報を前記工事情報記憶手段に登録する工程
と、工事実績入力機能を選択する信号の入力により、前
記工事情報記憶手段から作業指示情報の内容承認情報ま
で登録されたすべての工事を抽出し、実績入力対象工事
として一覧表示する工程と、一覧表示された実績入力対
象工事のいずれかを指定する信号の入力により、指定さ
れた工事の実績入力画面を表示する工程と、前記工事実
績入力画面に従って入力された情報に基づいて工事実績
情報を作成する工程と、作成された工事実績情報を対応
する工事の登録情報に付加して前記工事情報記憶手段に
登録する工程と、工事実績入力内容承認機能を選択する
信号の入力により、前記工事情報記憶手段から工事実績
情報まで登録されたすべての工事を抽出し、工事実績承
認対象工事として一覧表示する工程と、一覧表示された
工事実績承認対象工事のいずれかを指定する信号の入力
により、指定された工事の実績入力内容を表示する工程
と、表示された工事実績入力内容を承認する信号の入力
により、当該工事実績情報の内容承認情報を前記工事情
報記憶手段に登録する工程と、工事検収入力機能を選択
する信号の入力により、前記工事情報記憶手段から工事
実績情報の内容承認情報まで登録されたすべての工事を
抽出し、検収入力対象工事として一覧表示する工程と、
一覧表示された検収入力対象工事のいずれかを指定する
信号の入力により、指定された工事の検収入力画面を表
示する工程と、前記工事検収入力画面に従って入力され
た情報に基づいて工事検収情報を作成する工程と、作成
された工事検収情報を対応する工事の登録情報に付加し
て前記工事情報記憶手段に登録する工程と、工事検収入
力内容承認機能を選択する信号の入力により、前記工事
情報記憶手段から工事検収情報まで登録されたすべての
工事を抽出し、工事検収承認対象工事として一覧表示す
る工程と、一覧表示された工事検収承認対象工事のいず
れかを指定する信号の入力により、指定された工事の検
収入力内容を表示する工程と、表示された工事検収入力
内容を承認する信号の入力により、当該工事検収情報の
内容承認情報を前記工事情報記憶手段に登録する工程と
を含むことを特徴とする。
In the twelfth aspect of the present invention, the past maintenance work is also managed as construction history information, so that if there is a similar maintenance work in the past, the construction information of the maintenance work can be effectively utilized. . According to a thirteenth aspect of the present invention, in the maintenance work management method for managing the maintenance information of the maintenance work for performing maintenance and repair of the equipment of the plant by using a computer, the maintenance work request is input by inputting a signal for selecting the work request input function. A step of displaying a construction request input screen for receiving, and a step of creating construction request information based on information input according to the construction request input screen,
By registering the created construction request information in the construction information storage means, and by inputting a signal for selecting a construction request input content approval function, all the works registered from the construction information storage means to the construction request information are extracted. , By inputting a signal that specifies one of the listed construction request approval work,
By the process of displaying the input contents of the specified construction request and the input of the signal to approve the displayed construction request input contents,
By registering the content approval information of the construction request information in the construction information storage means, and by inputting a signal for selecting a work instruction input function, all the contents registered from the construction information storage means to the content approval information of the construction request information are registered. Extract the construction of
A step of displaying a list as the work instruction target work, a step of displaying a work instruction input screen of the designated work by inputting a signal designating any of the work instruction target work listed, and the work instruction input screen Creating work instruction information based on the information input according to the above, adding the created work instruction information to the corresponding construction registration information and registering it in the construction information storage means, and approving the work instruction input contents By inputting a signal for selecting a function, all the work registered from the work information storage means to the work instruction information is extracted, and a list is displayed as a work instruction approval target work, and a list of the work instruction approval target work is displayed. A step of displaying the input contents of the work instruction of the designated construction by inputting a signal designating any of the above, and a signal of approving the input contents of the displayed work instruction. The step of registering the content approval information of the work instruction information in the construction information storage means, and the input of a signal for selecting a construction performance input function, from the construction information storage means to the content approval information of the work instruction information A process for extracting all registered works and displaying them as a work input target work list, and inputting a signal to specify one of the work input target work listed, displays the work input screen for the specified work And a step of creating construction result information based on the information input according to the construction result input screen, and adding the created construction result information to the corresponding construction registration information and registering it in the construction information storage means. And the input of a signal for selecting the construction result input content approval function, all constructions registered from the construction information storage means to construction result information are extracted. Then, a process for displaying a list of construction work approval target works and a process for displaying a result input content of the designated construction by inputting a signal designating any of the construction work approval target construction work listed are displayed. A step of registering the content approval information of the construction result information in the construction information storage means by inputting a signal for approving the construction result input content, and a step of inputting a signal for selecting a construction acceptance input function, A process of extracting all the registered works from to the contents approval information of the construction results information and displaying them as a list of works for acceptance input,
A step of displaying an acceptance input screen for the designated construction by inputting a signal designating any of the construction input target constructions displayed in the list, and a construction acceptance information based on the information input according to the construction acceptance input screen. The step of creating, the step of adding the created construction inspection information to the registration information of the corresponding construction and registering it in the construction information storage means, and the input of a signal for selecting a construction inspection input content approval function, Extraction of all registered works from the storage means up to the work acceptance information and display as a work to be approved for work acceptance, and designation by inputting a signal to specify any of the work to be approved for work acceptance In the process of displaying the received acceptance information of the construction and the input of the signal to approve the displayed construction acceptance input, the content approval information of the construction Characterized in that it comprises a step of registering the construction information storage unit.

【0033】請求項14の発明は、請求項13の保修工
事管理方法において、工事進捗状況検索機能を選択する
信号の入力により、検索条件入力用の検索画面を表示す
る工程と、前記検索画面に従って入力された検索条件に
基づいて前記工事情報記憶手段から該当する工事の登録
情報を検索する工程と、検索された工事の登録情報によ
り工事進捗状況一覧を表示する工程とを含むことを特徴
とする。
According to a fourteenth aspect of the present invention, in the maintenance management method according to the thirteenth aspect, a step of displaying a search screen for inputting search conditions by inputting a signal for selecting a construction progress search function, and The method includes a step of searching for the registration information of the corresponding construction from the construction information storage unit based on the input search condition, and a step of displaying a list of the construction progress according to the retrieved registration information of the construction. .

【0034】請求項15の発明は、工事依頼入力機能を
選択する信号の入力により、設備機器の保全修理の依頼
を受け付ける工事依頼入力画面を表示する工程と、前記
工事依頼入力画面に従って入力された情報に基づいて工
事依頼情報を作成する工程と、作成された工事依頼情報
を工事情報記憶手段に登録する工程と、工事依頼入力内
容承認機能を選択する信号の入力により、前記工事情報
記憶手段から工事依頼情報まで登録されたすべての工事
を抽出し、工事依頼承認対象工事として一覧表示する工
程と、一覧表示された工事依頼承認対象工事のいずれか
を指定する信号の入力により、指定された工事の依頼入
力内容を表示する工程と、表示された工事依頼入力内容
を承認する信号の入力により、当該工事依頼情報の内容
承認情報を前記工事情報記憶手段に登録する工程と、作
業指示入力機能を選択する信号の入力により、前記工事
情報記憶手段から工事依頼情報の内容承認情報まで登録
されたすべての工事を抽出し、作業指示対象工事として
一覧表示する工程と、一覧表示された作業指示対象工事
のいずれかを指定する信号の入力により、指定された工
事の作業指示入力画面を表示する工程と、前記作業指示
入力画面に従って入力された情報に基づいて作業指示情
報を作成する工程と、作成された作業指示情報を対応す
る工事の登録情報に付加して前記工事情報記憶手段に登
録する工程と、作業指示入力内容承認機能を選択する信
号の入力により、前記工事情報記憶手段から作業指示情
報まで登録されたすべての工事を抽出し、作業指示承認
対象工事として一覧表示する工程と、一覧表示された作
業指示承認対象工事のいずれかを指定する信号の入力に
より、指定された工事の作業指示入力内容を表示する工
程と、表示された作業指示入力内容を承認する信号の入
力により、当該作業指示情報の内容承認情報を前記工事
情報記憶手段に登録する工程と、工事実績入力機能を選
択する信号の入力により、前記工事情報記憶手段から作
業指示情報の内容承認情報まで登録されたすべての工事
を抽出し、実績入力対象工事として一覧表示する工程
と、一覧表示された実績入力対象工事のいずれかを指定
する信号の入力により、指定された工事の実績入力画面
を表示する工程と、前記工事実績入力画面に従って入力
された情報に基づいて工事実績情報を作成する工程と、
作成された工事実績情報を対応する工事の登録情報に付
加して前記工事情報記憶手段に登録する工程と、工事実
績入力内容承認機能を選択する信号の入力により、前記
工事情報記憶手段から工事実績情報まで登録されたすべ
ての工事を抽出し、工事実績承認対象工事として一覧表
示する工程と、一覧表示された工事実績承認対象工事の
いずれかを指定する信号の入力により、指定された工事
の実績入力内容を表示する工程と、表示された工事実績
入力内容を承認する信号の入力により、当該工事実績情
報の内容承認情報を前記工事情報記憶手段に登録する工
程と、工事検収入力機能を選択する信号の入力により、
前記工事情報記憶手段から工事実績情報の内容承認情報
まで登録されたすべての工事を抽出し、検収入力対象工
事として一覧表示する工程と、一覧表示された検収入力
対象工事のいずれかを指定する信号の入力により、指定
された工事の検収入力画面を表示する工程と、前記工事
検収入力画面に従って入力された情報に基づいて工事検
収情報を作成する工程と、作成された工事検収情報を対
応する工事の登録情報に付加して前記工事情報記憶手段
に登録する工程と、工事検収入力内容承認機能を選択す
る信号の入力により、前記工事情報記憶手段から工事検
収情報まで登録されたすべての工事を抽出し、工事検収
承認対象工事として一覧表示する工程と、一覧表示され
た工事検収承認対象工事のいずれかを指定する信号の入
力により、指定された工事の検収入力内容を表示する工
程と、表示された工事検収入力内容を承認する信号の入
力により、当該工事検収情報の内容承認情報を前記工事
情報記憶手段に登録する工程とをコンピュータに実行さ
せるプログラムを記録した記録媒体である。
According to a fifteenth aspect of the present invention, there is provided a step of displaying a construction request input screen for accepting a maintenance repair request for equipment by inputting a signal for selecting a construction request input function, and inputting according to the construction request input screen. A step of creating construction request information based on the information, a step of registering the created construction request information in the construction information storage means, and a signal for selecting a construction request input content approval function, and The process of extracting all constructions registered up to the construction request information and displaying them as a list of construction requests to be approved, and inputting a signal to specify any of the listed construction requests to be approved. The content approval information of the construction request information is displayed by inputting a signal for approving the displayed construction request input content. By registering the information in the information storage means and inputting a signal for selecting a work instruction input function, all the works registered up to the content approval information of the work request information are extracted from the work information storage means, and the work instruction target work is extracted. A step of displaying a list, a step of displaying a work instruction input screen of the designated construction by inputting a signal designating any of the listed work instruction target works, and information input according to the work instruction input screen A step of creating work instruction information based on the work instruction, a step of adding the created work instruction information to corresponding construction registration information and registering the work instruction information in the construction information storage means, and a signal for selecting a work instruction input content approval function. The process of extracting all the works registered from the work information storage means to the work instruction information, and displaying the work as a work instruction approval target work in a list. By inputting a signal designating any of the listed work order approval target works, by displaying a work instruction input content of the designated work, and by inputting a signal approving the displayed work instruction input content, By registering the content approval information of the work instruction information in the construction information storage means, and by inputting a signal for selecting a construction performance input function, all of the contents registered from the construction information storage means to the content approval information of the work instruction information are registered. A process of extracting the construction of the work and displaying it as a result input target work in a list, and a process of displaying a result input screen of the designated construction by inputting a signal specifying one of the list of the result input target work, A step of creating construction result information based on the information input according to the construction result input screen,
A step of adding the created construction result information to the corresponding construction registration information and registering it in the construction information storage means, and inputting a signal for selecting a construction result input content approval function, the construction result storage means The process of extracting all works registered up to the information and displaying them as a list of works approved for construction results, and inputting a signal to specify one of the works approved for work results approved in the list, the result of the specified work A step of displaying the input contents, a step of registering the contents approval information of the work result information in the work information storage means by inputting a signal for approving the displayed work result input contents, and selecting a work acceptance input function. Depending on the signal input,
A step of extracting all constructions registered from the construction information storage means up to the content approval information of the construction performance information and displaying them in a list as work to be accepted for input, and a signal for designating any of the work to be entered for acceptance as listed. , A step of displaying an acceptance input screen of the designated construction, a step of creating construction acceptance information based on the information input according to the construction acceptance input screen, and a construction corresponding to the created construction acceptance information. By registering in the construction information storage means in addition to the registration information of the above, and by inputting a signal for selecting a construction acceptance input content approval function, all constructions registered from the construction information storage means to construction acceptance information are extracted The process is listed as a work subject to approval for construction acceptance, and a signal is input that specifies one of the works subject to approval for construction acceptance. Executing the step of displaying the inspection input content of the completed construction and the step of registering the content approval information of the construction inspection information in the construction information storage means by inputting a signal for approving the displayed construction inspection input content to the computer. This is a recording medium on which a program to be recorded is recorded.

【0035】請求項13〜15の発明においては、保修
工事の進捗段階に応じて必要な工事情報を順次入力して
登録することができ、保修工事の工事依頼から工事検収
にいたるまでの工事情報を一括して電算管理することが
できる。
In the invention of claims 13 to 15, necessary construction information can be sequentially inputted and registered in accordance with the progress stage of the maintenance work, and the construction information from the maintenance request to the construction acceptance can be entered. Can be collectively managed by computer.

【0036】[0036]

【発明の実施の形態】以下、図面に基づいて本発明の保
修工事管理装置の実施の形態について説明する。なお、
各実施の形態を通して共通する部分には同一符号を付し
て、重複する説明は省略する。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view showing a maintenance work management apparatus according to an embodiment of the present invention. In addition,
The same reference numerals are given to the parts common to the respective embodiments, and the overlapping description will be omitted.

【0037】図1は、本発明の保修工事管理装置のブロ
ック図を示すものであり、一定期間までの工事情報を記
憶する工事情報記憶手段1と、一定期間を過ぎた工事情
報を記憶する工事履歴情報記憶手段3と、工事情報記憶
手段1および工事履歴情報記憶手段3へのデータの保存
処理および工事情報記憶手段1および工事履歴情報記憶
手段3からのデータの検索処理を行う情報入出力手段5
と、情報入出力手段5へ工事情報の登録要求および検索
要求を行う複数の工事情報登録・検索要求手段7とで構
成されている。
FIG. 1 is a block diagram of a maintenance work management apparatus according to the present invention. The work information storage means 1 stores work information up to a certain period, and the work information stores work information after a certain period. A history information storage means 3 and an information input / output means for performing a process of storing data in the construction information storage means 1 and the construction history information storage means 3 and a processing of searching for data from the construction information storage means 1 and the construction history information storage means 3 5
And a plurality of construction information registration / search request means 7 for making a registration request and a search request for construction information to the information input / output means 5.

【0038】工事情報記憶手段1は、保修工事の依頼内
容や工事の指示内容、または工事の実績や検収内容とい
った工事情報を記憶している。
The construction information storage means 1 stores construction information such as maintenance work request contents and construction instruction contents, or construction results and inspection contents.

【0039】工事履歴情報記憶手段3は、工事情報記憶
手段1で一定期間が過ぎた工事情報を工事情報記憶手段
1から移しかえて記憶している。
The construction history information storage means 3 stores construction information for which a certain period has passed in the construction information storage means 1 by changing the construction information from the construction information storage means 1.

【0040】工事情報登録・検索要求手段7は、キーボ
ード、マウス、タッチパネル等の入力装置9と、CR
T、LCD等の表示装置および/または記録紙出力装置
等の出力装置11と、入力装置9で入力された工事情報
の登録要求または検索要求を情報入出力手段5に送信
し、情報入出力手段5からの検索結果を出力装置11に
出力する工事情報検索・登録処理手段13とによって構
成され、複数箇所に設置される。
The construction information registration / search request means 7 includes an input device 9 such as a keyboard, a mouse, and a touch panel,
A display device such as T, LCD and / or an output device 11 such as a recording paper output device, and a construction information registration request or a search request input by the input device 9 are transmitted to the information input / output means 5. 5 and a construction information search / registration processing means 13 for outputting the search result from the output device 11 to the output device 11 and installed at a plurality of locations.

【0041】図2は、これを実際のシステムに適応した
例を示すもので、このシステム構成例では所内各所に保
修工事管理端末21が設置され、所内LAN23の伝送
路によって保修工事サーバー25と接続されている。保
修工事管理端末21は、図1の工事情報登録・検索要求
手段7に相当し、保修工事管理サーバー25が図1の情
報入出力手段5と工事情報記憶手段1と工事履歴情報記
憶手段3を備えたものとなっている。
FIG. 2 shows an example in which this is applied to an actual system. In this system configuration example, maintenance work management terminals 21 are installed at various places in the office, and connected to a maintenance work server 25 via a transmission line of the in-house LAN 23. Have been. The maintenance work management terminal 21 corresponds to the construction information registration / search request means 7 in FIG. 1, and the maintenance work management server 25 uses the information input / output means 5, the construction information storage means 1, and the construction history information storage means 3 in FIG. It is equipped.

【0042】次に、本実施の形態の作用を説明する。ま
ず、図1〜図10に基づいて日常保修工事の依頼から検
収に至るまでの工事情報の登録/更新の流れを説明す
る。なお、図3〜図8は表示画面例を、図9は工事情報
記憶手段1または工事履歴情報記憶手段3に記憶される
工事情報のデータ例を示すものである。
Next, the operation of the present embodiment will be described. First, a flow of registration / update of construction information from a request for daily maintenance work to an inspection will be described with reference to FIGS. 3 to 8 show examples of display screens, and FIG. 9 shows an example of construction information data stored in the construction information storage means 1 or the construction history information storage means 3.

【0043】発電所内に保修工事の必要な箇所があれ
ば、受け持ちの部署例えば発電課の担当者が、保修工事
を依頼するために、図2に示す発電課事務所の保修工事
管理端末21において、図3に示すような機能メニュー
画面を出力装置11に表示する。この機能メニュー画面
において、ア、イ、ウ等は機能コードを表し、その右側
の名称は、その機能コードに対応する機能名称を表す。
If there is a place requiring maintenance work in the power plant, the responsible department, for example, a person in charge of the power generation section requests the maintenance work management terminal 21 of the power generation section office shown in FIG. 2 to request the maintenance work. A function menu screen as shown in FIG. On this function menu screen, a, a, c and the like represent function codes, and the names on the right side thereof represent the function names corresponding to the function codes.

【0044】発電課の担当者が、図3に示す機能メニュ
ー画面において、入力装置9により機能コード「ア」の
「工事依頼入力」を選択すると、出力装置11上に、図
4に示すような工事依頼入力画面が出力される。
When the person in charge of the power generation section selects the “construction request input” of the function code “A” by the input device 9 on the function menu screen shown in FIG. The construction request input screen is output.

【0045】この工事依頼入力画面で、依頼日付、依頼
元課、依頼番号、担当箇所、ユニット、パート、件名、
概要を入力し、登録キーを選択すると、工事情報検索・
登録処理手段13が、情報入出力手段5に対し登録要求
を行い、情報入出力手段5が工事情報記憶手段1に上記
工事情報を登録する。このとき、工事情報記億手段1の
内部には入力装置9から入力された情報の他に機能コー
ド「ア」もあわせて記憶される。ここで、ユニットは工
事対象の場所を、パートは工事対象の設備分類を、担当
箇所は保修担当係をそれぞれ示し、ユニット、パートを
入力すると、依頼日付、依頼元課、依頼番号、担当箇所
は自動的に設定されるようにすることもできる。
On this construction request input screen, the request date, request source section, request number, responsible place, unit, part, subject,
Enter an outline and select a registration key to search for construction information.
The registration processing means 13 issues a registration request to the information input / output means 5, and the information input / output means 5 registers the construction information in the construction information storage means 1. At this time, in addition to the information input from the input device 9, a function code "A" is also stored inside the construction information storage means 1. Here, the unit indicates the location of the construction target, the part indicates the equipment classification of the construction target, and the responsible part indicates the maintenance staff.When the unit and part are entered, the request date, request source section, request number, It can be set automatically.

【0046】次に、工事依頼入力を行った人の上長で承
認権限を持っている人、例えば、ここでは発電課の課長
が、発電課事務所の同じまたは他の保修工事管理端末2
1において、図3に示すメニュー画面から機能コード
「イ」の「工事依頼入力内容承認」を入力装置9上から
選択すると、工事情報検索・登録処理手段13は情報入
出力手段5に対し機能コード「イ」を送り、情報入出力
手段5を介して工事情報記憶手段1より機能コード
「イ」が対象となる工事情報として、機能コード「ア」
のものを全て取り出し、一覧にして図5に示すような対
象工事選択画面を出力装置11に表示する。
Next, a person who has entered the construction request and who has the approval authority, for example, here, the section manager of the power generation section is the same or another maintenance work management terminal 2 in the power generation section office.
In FIG. 1, when “Construction request input contents approval” of the function code “A” is selected from the input device 9 from the menu screen shown in FIG. 3, the construction information search / registration processing means 13 sends the function code The function code "A" is sent from the construction information storage means 1 via the information input / output means 5 as the function code "A" as the target construction information.
The target construction selection screen as shown in FIG. 5 is displayed on the output device 11 as a list.

【0047】発電課の課長は、機能コード「ア」の工事
情報の一覧画面から承認対象の工事を選択し、入力装置
9上より内容確認キーを入力すると、工事情報検索・登
録処理手段13は選択された工事の依頼内容を出力装置
11上に表示する。
The section manager of the power generation section selects the construction to be approved from the construction information list screen of the function code "A" and inputs a content confirmation key on the input device 9, and the construction information search / registration processing means 13 The selected construction request is displayed on the output device 11.

【0048】発電課の課長は、表示された工事依頼内容
に問題がないことを確認した後、入力装置9上より承認
キーを入力すると、工事情報検索・登録処理手段13
が、情報入出力手段5に対し更新要求を行い、情報入出
力手段5が工事情報記憶手段1に記憶されている当該工
事情報の機能コード「ア」を「イ」に更新する。
After confirming that there is no problem in the displayed construction request content, the section manager of the power generation section inputs an approval key from the input device 9 and then enters the construction information search / registration processing means 13.
Sends an update request to the information input / output means 5, and the information input / output means 5 updates the function code "A" of the construction information stored in the construction information storage means 1 to "A".

【0049】次に、図4に示す工事依頼入力画面で入力
された「担当箇所」の保修担当者、ここでは保修課ター
ビン係の担当者が、図2に示す保修課事務所の保修工事
管理端末21において、図3に示すメニュー画面から機
能コード「ウ」の「作業指示入力」を入力装置9により
選択すると、工事情報検索・登録処理手段13は情報入
出力手段5に機能コード「ウ」を送り、情報入出力手段
5を介して工事情報記憶手段1から機能コード「イ」の
工事情報を全て取り出して、一覧にした図5に示すよう
な対象工事選択画面を出力装置11に表示する。
Next, a person in charge of maintenance of the “part in charge” input on the construction request input screen shown in FIG. 4, in this case, a person in charge of the maintenance section turbine section, manages the maintenance work of the maintenance section office shown in FIG. In the terminal 21, when “input work instruction” of the function code “c” is selected by the input device 9 from the menu screen shown in FIG. 3, the construction information search / registration processing means 13 causes the information input / output means 5 to output the function code “c” Is sent out from the construction information storage means 1 via the information input / output means 5, and all the construction information of the function code "A" is taken out, and a list of target construction selection screens as shown in FIG. .

【0050】保修課のタービン担当は、この機能コード
「イ」の工事情報の一覧画面から作業指示対象の工事を
選択し、入力装置9上より選択キーを入力すると、工事
情報検索・登録処理手段13によって出力装置11上
に、図6に示すような作業指示入力画面が表示される。
When the turbine in charge of the maintenance section selects the construction for which the work is to be instructed from the construction information list screen of the function code "a" and inputs a selection key from the input device 9, the construction information search / registration processing means 13 displays a work instruction input screen as shown in FIG.

【0051】この作業指示入力画面において、指示日
付、指示番号、工事仕様、作業箇所を入力装置9により
入力し、登録キーを押し操作すると、工事情報検索・登
録処理手段13が、情報入出力手段5に対し更新要求を
行い、情報入出力手段5が、工事情報記億手段1の対応
する工事情報に指示日付、指示番号、工事仕様といった
工事情報を追加するとともに、機能コードを「イ」から
「ウ」へ更新する。
In this work instruction input screen, an instruction date, an instruction number, a construction specification, and a work location are input by the input device 9 and the registration key is pressed. 5, the information input / output means 5 adds construction information such as an instruction date, an instruction number, and a construction specification to the construction information corresponding to the construction information storage means 1, and changes the function code from "A" to "I". Update to "U".

【0052】次に、作業指示入力を行った人の上長で承
認権限を持っている人、例えば、ここでは保修課の課長
が、図3に示すメニュー画面から機能コード「エ」の
「作業指示入力内容承認」を入力装置9を介して選択す
ると、工事情報検索・登録処理手段13は情報入出力手
段5に対し機能コード「エ」を送り、情報入出力手段5
を介して工事情報記憶手段1より機能コード「エ」が対
象となる工事情報として機能コード「ウ」のものを全て
取り出し、工事一覧の対象工事選択画面を出力装置11
に表示する。
Next, the person who has input the work instruction and has the approval authority, for example, here, the manager of the maintenance section, inputs the "work" of the function code "d" from the menu screen shown in FIG. When "instruction input content approval" is selected via the input device 9, the construction information search / registration processing means 13 sends the function code "d" to the information input / output means 5, and the information input / output means 5
All of the function code "C" as the target construction information for the function code "D" from the construction information storage means 1 via the interface, and displays the target construction selection screen of the construction list on the output device 11
To be displayed.

【0053】保修課の課長は、この機能コード「ウ」の
工事情報の一覧画面から承認対象の工事を選択し、入力
装置9上より内容確認キーを入力すると、工事情報検索
・登録処理手段13によって該当する工事の作業指示情
報が出力装置11上に表示される。保修課の課長が、出
力装置11上で内容に問題がないことを確認した後、入
力装置9上より承認キーを入力すると、工事情報検索・
登録処理手段13が情報入出力手段5に対して更新要求
を行い、情報入出力手段5が工事情報記憶手段1に記憶
されている当該工事情報の機能コード「ウ」を「エ」に
更新する。
The section manager of the maintenance section selects the construction to be approved from the construction information list screen of the function code "C" and inputs a content confirmation key on the input device 9, and the construction information search / registration processing means 13 Accordingly, the work instruction information of the corresponding construction is displayed on the output device 11. After the manager of the maintenance section confirms that there is no problem in the content on the output device 11 and inputs an approval key from the input device 9, the construction information search /
The registration processing means 13 issues an update request to the information input / output means 5, and the information input / output means 5 updates the function code "c" of the construction information stored in the construction information storage means 1 to "d". .

【0054】次に、保修課のタービン係によって作業指
示入力画面で入力された「作業箇所」、ここではA工業
(株)が、保修課からの上記作業指示により保修工事を
実施した後、A工業(株)の担当者が図2に示す工事請
負業者事務所の保修工事管理端末21において、図3に
示すメニュー画面から機能コード「オ」の「工事実績入
力」を入力装置9により選択すると、工事情報検索・登
録処理手段13は情報入出力手段5に対し機能コード
「オ」を送り、情報入出力手段5を介して工事情報記憶
手段1より機能コード「オ」が対象となる工事情報とし
て機能コード「エ」のものを全て検索し、検索結果を一
覧にした対象工事選択画面を出力装置11に表示する。
Next, after the "work site" input here by the turbine section of the maintenance section on the work instruction input screen, here A Industry Co., Ltd., carries out the maintenance work according to the work instruction from the maintenance section. When the person in charge of the industrial company selects the “construction result input” of the function code “o” from the menu screen shown in FIG. 3 using the input device 9 in the maintenance work management terminal 21 of the construction contractor office shown in FIG. The construction information search / registration processing means 13 sends the function code “o” to the information input / output means 5, and the construction information for the function code “o” from the construction information storage means 1 via the information input / output means 5. And retrieves all of the function codes “d”, and displays a target construction selection screen listing the search results on the output device 11.

【0055】A工業(株)の担当者が、この機能コード
「エ」の工事情報の一覧画面から作業指示対象の工事を
選択し入力装置9上より選択キーを入力すると、工事情
報検索・登録処理手段13は図7に示すような該当する
工事の実績入力画面を出力装置11上に表示する。
When a person in charge of A Kogyo Co., Ltd. selects the work to be instructed from the work information list screen of the function code "d" and inputs a selection key on the input device 9, the work information is searched and registered. The processing means 13 displays on the output device 11 a result input screen of the corresponding construction as shown in FIG.

【0056】この工事実績入力画面において、工事期
間、処置内容、作業実績等を入力し、登録キーを入力す
ると、工事情報検索・登録処理手段13が情報入出力手
段5に対し更新要求を行い、情報入出力手段5が、工事
情報記憶手段1の当該工事情報に工事期間、処置内容、
作業実績といった工事情報を追加し、さらに機能コード
を「エ」から「オ」へ更新する。
On this construction result input screen, the construction period, the treatment content, the work result, etc. are entered and the registration key is entered, and the construction information search / registration processing means 13 issues an update request to the information input / output means 5, The information input / output means 5 stores the construction period, the treatment content,
Add construction information such as work results, and update the function code from “D” to “O”.

【0057】次に、工事実績入力を行った人の上長で承
認権限を持っている人、例えば、ここでは「A工業
(株)」の課長が、図3に示すメニュー画面から機能コ
ード「カ」の「工事実績入力内容承認」を入力装置9に
より選択すると、工事情報検索・登録処理手段13が情
報入出力手段5に対し機能コード「カ」を送り、情報入
出力手段5が工事情報記憶手段1より機能コード「カ」
が対象となる工事情報として機能コード「オ」のものを
全て検索して検索結果を工事情報検索・登録処理手段1
3に送ることによって、機能コード「オ」の工事情報を
一覧にした対象工事選択画面が出力装置11に表示され
る。
Next, a person who has entered the construction results and who has the approval authority, for example, a section manager of "A Kogyo Co., Ltd." When the user selects “Approval of construction result input contents” of “F” using the input device 9, the construction information search / registration processing means 13 sends the function code “F” to the information input / output means 5, and the information input / output means 5 Function code "f" from storage means 1
Searches for all of the target construction information with the function code "o" and retrieves the search result as construction information search / registration processing means 1.
3, a target work selection screen listing the work information of the function code “o” is displayed on the output device 11.

【0058】A工業(株)の課長は、この機能コード
「オ」の工事情報の一覧画面から承認対象の工事を選択
して入力装置9上より内容確認キーを入力し、折り返し
出力装置11に表示された工事実績の入力内容に問題が
ないことを確認した後、入力装置9上より承認キーを入
力すると、工事情報検索・登録処理手段13が情報入出
力手段5に対し更新要求を行い、情報入出力手段5が工
事情報記憶手段1に記憶されている当該工事情報の機能
コード「オ」を「カ」に更新する。
The section manager of A Kogyo Co., Ltd. selects the construction to be approved from the construction information list screen of the function code “o”, inputs a content confirmation key from the input device 9, and sends it to the return output device 11. After confirming that there is no problem with the input contents of the displayed construction results, when the approval key is input from the input device 9, the construction information search / registration processing means 13 issues an update request to the information input / output means 5, The information input / output unit 5 updates the function code “o” of the construction information stored in the construction information storage unit 1 to “f”.

【0059】次に、作業指示入力を行った担当者、ここ
では保修課タービン係の担当者が図3に示すメニュー画
面から機能コード「キ」の「工事検収入力」を入力装置
9により選択すると、工事情報検索・登録処理手段13
が情報入出力手段5に対し機能コード「キ」を送り、情
報入出力手段5が工事情報記憶手段1より機能コード
「キ」が対象となる工事情報として機能コード「カ」の
ものを全て検索して検索結果を工事情報検索・登録処理
手段13に送り返すことによって、機能コード「カ」の
工事情報を一覧にした対象工事選択画面が出力装置11
に表示される。
Next, when the person in charge of the work instruction input, in this case, the person in charge of the maintenance section turbine, selects the "construction acceptance input" of the function code "g" from the menu screen shown in FIG. , Construction information search and registration processing means 13
Sends the function code “K” to the information input / output means 5, and the information input / output means 5 searches the construction information storage means 1 for all pieces of the function code “F” as the construction information for the function code “K”. By sending the search result back to the construction information search / registration processing means 13, a target construction selection screen listing the construction information of the function code “f” is displayed on the output device 11.
Will be displayed.

【0060】保修課のタービン担当は、この機能コード
「カ」の工事情報の一覧画面から工事検収対象の工事を
選択し、入力装置9上より選択キーを入力すると、出力
装置11上に図8に示すような工事検収入力画面が表示
される。
The maintenance section of the turbine selects the construction to be accepted for construction from the construction information list screen of the function code “f” and inputs a selection key from the input device 9. A construction acceptance input screen as shown in (1) is displayed.

【0061】この工事検収入力画面で作業査定を入力
し、登録キーを入力すると、工事情報検索・登録処理手
段13が情報入出力手段5に対し更新要求を行い、情報
入出力手段5が工事情報記憶手段1の当該工事情報に作
業査定を工事情報として追加し、さらに機能コードを
「カ」から「キ」へ更新する。
When a work assessment is entered on this construction acceptance input screen and a registration key is entered, the construction information search / registration processing means 13 issues an update request to the information input / output means 5, and the information input / output means 5 The work assessment is added to the construction information in the storage means 1 as construction information, and the function code is updated from "f" to "g".

【0062】次に、工事検収入力を行った人の上長で承
認権限を持っている人、例えば、ここでは保修課の課長
が、図3に示すメニュー画面から機能コード「ク」の
「工事検収入力内容承認」を入力装置9により選択する
と、工事情報検索・登録処理手段13が情報入出力手段
5に対し機能コード「ク」を送り、情報入出力手段5が
工事情報記憶手段1より機能コード「ク」が対象となる
工事情報として機能コード「キ」のものを全て検索して
検索結果を工事情報検索・登録処理手段13に送り返す
ことによって、検索結果を一覧にした対象工事選択画面
が出力装置11に表示される。
Next, a person who has performed the construction acceptance input and who has the approval authority, for example, the section manager of the maintenance section in this case, selects the "construction" of the function code "C" from the menu screen shown in FIG. When “acceptance input contents approval” is selected by the input device 9, the construction information search / registration processing means 13 sends a function code “h” to the information input / output means 5, and the information input / output means 5 functions from the construction information storage means 1. By searching for all of the function code “G” as the target construction information for the code “C” and sending the search results back to the construction information search / registration processing means 13, the target construction selection screen listing the search results is displayed. Displayed on the output device 11.

【0063】保修課の課長は、この機能コード「キ」の
工事情報の一覧画面から承認対象の工事を選択し、入力
装置9上より内容確認キーを入力し、折り返し表示され
た工事検収内容に問題がないことを確認した後、入力装
置9上より承認キーを入力すると、工事情報検索・登録
処理手段13が情報入出力手段5に対し更新要求を行
い、情報入出力手段5が工事情報記憶手段1に記憶され
ている当該工事情報の機能コード「キ」を「ク」に更新
する。図9に、工事情報記憶手段1に記憶されている機
能コード「ク」の工事情報のデータ例を示す。以上で、
一通り検収までの流れが終了する。
The section manager of the maintenance section selects the construction to be approved from the construction information list screen of the function code "K", inputs a content confirmation key on the input device 9, and returns to the returned construction inspection content. After confirming that there is no problem, when the approval key is input from the input device 9, the construction information search / registration processing means 13 issues an update request to the information input / output means 5, and the information input / output means 5 stores the construction information. The function code “g” of the construction information stored in the means 1 is updated to “g”. FIG. 9 shows a data example of the construction information of the function code “C” stored in the construction information storage unit 1. Above,
The flow up to acceptance ends.

【0064】このように用いられる保修工事管理装置で
は、工事情報記憶手段1の情報がどんどん蓄積され、検
索処理が遅くなるため、工事検収入力内容承認が完了
し、一定期間たった工事情報は、情報入出力手段5によ
って定期的に工事情報記憶手段1から工事履歴情報記憶
手段3に移動される。これにより、過去の工事と最近の
工事とを分けて管理することができる。この工事履歴情
報記憶手段3に記憶されるデータは、図9に示すとお
り、工事情報記憶手段1内のデータと基本的に同じ構成
である。
In the maintenance work management apparatus used in this way, since the information in the work information storage means 1 is accumulated steadily and the search processing is delayed, the work acceptance input contents approval is completed, and the work information after a certain period The work is periodically moved from the construction information storage means 1 to the construction history information storage means 3 by the input / output means 5. Thereby, past construction and recent construction can be managed separately. The data stored in the construction history information storage means 3 has basically the same configuration as the data in the construction information storage means 1, as shown in FIG.

【0065】次に、図10および図11に基づいて工事
進捗状況検索の流れを説明する。図3に示すメニュー画
面から工事進捗状況検索を入力装置9により選択する
と、出力装置11上に図10に示すような検索条件入力
画面が表示される。この検索条件入力画面において、入
力装置9により検索条件を入力し、検索実行キーを選択
操作すると、工事情報検索・登録処理手段13が情報入
出力手段5に対し検索要求をかけ、情報入出力手段5が
入力された検索条件に基づいて工事情報記憶手段1から
該当する工事情報を検索する。
Next, the flow of the construction progress status search will be described with reference to FIGS. 10 and 11. When the construction progress search is selected from the menu screen shown in FIG. 3 by the input device 9, a search condition input screen as shown in FIG. 10 is displayed on the output device 11. In this search condition input screen, when a search condition is input by the input device 9 and a search execution key is selected, the construction information search / registration processing means 13 issues a search request to the information input / output means 5, and the information input / output means 5 retrieves the corresponding construction information from the construction information storage means 1 based on the inputted search condition.

【0066】この検索結果は情報入出力手段5から工事
情報検索・登録処理手段13に送られ、工事情報検索・
登録処理手段13によって図11に示すような工事進捗
状況一覧にして出力装置11に表示される。
The search result is sent from the information input / output means 5 to the construction information search / registration processing means 13, and the construction information search / registration processing means 13 is provided.
The registration processing means 13 displays the construction progress list as shown in FIG. 11 on the output device 11.

【0067】これは、検索対象が工事情報記憶手段1で
あるが、工事履歴情報記憶手段3の場合も基本的な流れ
は同じであり、過去の工事についても検索可能である。
この場合には、図3に示すメニュー画面から工事履歴情
報検索が選択される。
In this case, the search target is the construction information storage means 1, but the basic flow is the same in the case of the construction history information storage means 3, and the past construction can be searched.
In this case, the construction history information search is selected from the menu screen shown in FIG.

【0068】以上の説明から明らかなように、本実施の
形態によれば、−人だけでなく複数の人が別々の入力手
段や出力手段を用いて、登録要求、検索要求、およびそ
の結果の確認を実施することができるようになる。
As is apparent from the above description, according to the present embodiment, not only a person but also a plurality of persons use different input means and output means to make a registration request, a search request, and a result Confirmation can be performed.

【0069】なお、他の実施の形態として、工事情報記
憶手段1から工事履歴情報記憶手段3に情報を移動する
際に、工事検収入力内容承認が完了し、−定期間がすぎ
たものではなく、費用集計処理が完了したものとするこ
ともできる。これにより、工事情報記憶手段1の内容と
工事履歴情報記憶手段3の内容は、未集計工事と集計済
工事に分かれるため、経理上管理しやすくなる。
As another embodiment, when information is transferred from the construction information storage means 1 to the construction history information storage means 3, the work acceptance input contents approval has been completed, and-the fixed period has not passed. Alternatively, it may be determined that the cost totaling process has been completed. Thereby, the contents of the construction information storage means 1 and the contents of the construction history information storage means 3 are divided into uncounted works and counted works, so that they can be easily managed in accounting.

【0070】図12は、本発明の保修工事管理装置の第
2の実施の形態を示すもので、図1に示す第1の実施の
形態と比較して、イメージ情報を記憶するイメージ情報
記憶手段31が付加され、情報入出力手段5にイメージ
情報の保存処理と呼び出しを行う機能が付加されてい
る。
FIG. 12 shows a second embodiment of the maintenance work management system according to the present invention. Compared with the first embodiment shown in FIG. 1, an image information storage means for storing image information is provided. 31 is added to the information input / output means 5 to store and call image information.

【0071】次に、本実施の形態の作用を説明する。Next, the operation of the present embodiment will be described.

【0072】工事依頼の際に、担当者が保修工事管理端
末(工事情報登録・検索要求手段7)の入力装置9から
依頼日付、依頼元課、依頼番号、担当箇所、ユニット、
パート、件名、概要等の工事情報を入力するのと併せ、
不具合箇所のポンチ絵をイメージ情報として入力し、登
録キーを入力すると、工事情報検索・登録処理手段13
が情報入出力手段5に対し登録要求し、これによって情
報入出力手段5がイメージ情報記憶手段31にイメージ
情報を登録するとともに、工事情報記憶手段1に上記工
事情報を登録する。このとき、工事情報記憶手段1には
イメージ情報記憶手段31に登録したイメージ情報と連
携させるための識別子であるイメージ情報連携キーをあ
わせて登録する。
At the time of the construction request, the person in charge makes a request from the input device 9 of the maintenance work management terminal (construction information registration / search request means 7), the request date, the request source section, the request number, the place in charge, the unit,
Along with entering construction information such as part, subject, and summary,
When a punch picture of a defective part is input as image information and a registration key is input, construction information search / registration processing means 13
Makes a registration request to the information input / output means 5, whereby the information input / output means 5 registers the image information in the image information storage means 31 and registers the construction information in the construction information storage means 1. At this time, an image information link key, which is an identifier for linking with the image information registered in the image information storage unit 31, is also registered in the construction information storage unit 1.

【0073】図13は、工事情報記憶手段1に登録され
る最終段階の工事情報のデータ構成例を示すもので、図
9に示すデータ構成例と比較して、登録項目としてイメ
ージ情報連携キーの項目が追加されている。なお、この
データ構成は工事履歴情報記憶手段3においても同様で
ある。
FIG. 13 shows an example of the data structure of the construction information at the final stage registered in the construction information storage means 1. Compared to the data structure example shown in FIG. Items have been added. This data configuration is the same in the construction history information storage means 3.

【0074】検索の際は、情報入出力手段5は、工事情
報検索・登録処理手段13からの検索要求により工事情
報記憶手段1または工事履歴情報記憶手段3を検索し、
検索された工事情報内のイメージ情報連携キーをもと
に、イメージ情報記憶手段31からイメージ情報を検索
し、工事情報とイメージ情報を組み合わせた検索結果を
工事情報検索・登録処理手段13に送信する。
At the time of the search, the information input / output means 5 searches the construction information storage means 1 or the construction history information storage means 3 according to a search request from the construction information search / registration processing means 13,
Image information is retrieved from the image information storage unit 31 based on the image information link key in the retrieved construction information, and a search result combining the construction information and the image information is transmitted to the construction information search / registration processing unit 13. .

【0075】工事情報検索・登録処理手段13は、情報
入出力手段5からの検索結果に基づいて、出力装置11
に検索結果一覧を表示し、この検索結果一覧から選択さ
れた工事について、工事情報とこれに対応するイメージ
情報を表示する。
The construction information search / registration processing means 13 outputs the output device 11 based on the search result from the information input / output means 5.
A search result list is displayed, and the construction information and the corresponding image information are displayed for the construction selected from the search result list.

【0076】上記の説明からも明らかなように、本実施
の形態によれば、工事情報を入力する際にイメージ情報
もあわせて入力し、そのイメージ情報を工事情報と連携
させて管理することにより、イメージ情報を工事情報の
補足情報として表示することができる。これにより、作
業指示を入力する際や、作業指示によって作業を請負う
際に、保修の必要な不具合箇所を文字だけで判断するこ
となく、イメージとして捉えることができ、不具合箇所
の把握がしやすくなる。
As is clear from the above description, according to this embodiment, when the construction information is inputted, the image information is also inputted, and the image information is managed in cooperation with the construction information. The image information can be displayed as supplementary information of the construction information. Thus, when inputting a work instruction or contracting a work according to the work instruction, it is possible to grasp the defective part requiring maintenance as an image without judging only by characters, and it is easy to grasp the defective part. .

【0077】図14は、本発明の保修工事管理装置の第
3の実施の形態を示すもので、図1に示す第1の実施の
形態と比較して、作業実施に制限があってすぐに作業実
施をすることができない工事に関する工事情報を記憶す
る保留工事情報記憶手段41と、情報入出力手段5に対
し工事情報記憶手段1から保留工事情報記憶手段41に
工事情報を移動させたり、保留工事情報記憶手段41か
ら工事情報を読み込んで来るように要求する工事情報保
留登録・再発行処理手段43とが付加されている。ま
た、出力装置11は、図15に示すようなメニュー画面
を表示する。この画面のメニューには、図3に示すメニ
ュー画面と比較して、機能コード「J」の「保留工事再
発行」の項目が追加されている。
FIG. 14 shows a third embodiment of the maintenance work management system according to the present invention. Compared to the first embodiment shown in FIG. A suspended construction information storage means 41 for storing construction information relating to constructions for which work cannot be performed; and a construction information storage means 41 for moving the construction information from the construction information storage means 1 to the reserved construction information storage means 41 for the information input / output means 5. A construction information hold registration / reissue processing means 43 for requesting that construction information be read from the construction information storage means 41 is added. The output device 11 displays a menu screen as shown in FIG. Compared to the menu screen shown in FIG. 3, the menu of this screen has an additional item of “reissue pending work” of the function code “J”.

【0078】次に、本実施の形態の作用を説明する。保
修課の担当者が、図15に示すメニュー画面から機能コ
ード「ウ」の「作業指示入力」を入力装置9により選択
すると、第1の実施の形態と同様に工事情報検索・登録
処理手段13と情報入出力手段5の処理によって、機能
コード「イ」の工事情報を一覧にした図5に示すような
対象工事選択画面が表示される。ここまでの工事情報登
録にかかる手順は、第1の実施の形態と同じである。
Next, the operation of the present embodiment will be described. When the person in charge of the maintenance section selects the "work instruction input" of the function code "c" from the menu screen shown in FIG. 15 by using the input device 9, the construction information search / registration processing means 13 as in the first embodiment. By the processing of the information input / output means 5, a target construction selection screen as shown in FIG. 5 listing construction information of the function code "a" is displayed. The procedure related to the construction information registration so far is the same as in the first embodiment.

【0079】保修課の担当者は、この機能コード「イ」
の工事情報を一覧にした対象工事選択画面から、いつで
も作業することができる工事と、プラントを停止してい
る時にしか作業することがきない保留対象工事とを判別
する。この判別を容易にするために、対象工事選択画面
から指示された対象工事の詳細情報(例えば作業指示入
力画面のイメージ)を表示するための詳細内容参照ボタ
ンまたは参照キーを設けるようにすることもできる。こ
れによって、保留対象工事と判別された工事について
は、この一覧画面から選択して入力装置9上より保留キ
ーを入力することにより、工事情報保留登録・再発行処
理手段43から情報入出力手段5に保留工事登録要求が
出され、情報入出力手段5によって工事情報記憶手段1
から保留工事情報記憶手段41に該当する工事情報が移
動される。これにより、一覧画面から選択された対象工
事は、通常の工事依頼状態から外されて保留状態とな
る。
The person in charge of the maintenance section can use the function code "A"
From the target construction selection screen listing the construction information of the above, the construction that can be performed at any time and the suspended construction that can be performed only when the plant is stopped are determined. In order to facilitate this determination, a detailed content reference button or a reference key for displaying detailed information (for example, an image of a work instruction input screen) of the target construction instructed from the target construction selection screen may be provided. it can. As a result, the construction discriminated as the construction to be held is selected from the list screen and the holding key is inputted from the input device 9 so that the construction information holding registration / reissue processing means 43 sends the information input / output means 5 A request for registration of the pending construction is issued to the construction information storage means 1 by the information input / output means 5.
, The corresponding construction information is transferred to the reserved construction information storage means 41. As a result, the target construction selected from the list screen is removed from the normal construction request state and is put on hold.

【0080】また、その保留された工事依頼を再度発行
するには、保修課担当が図15に示すメニュー画面から
機能コード「J」の「保留工事再発行」を入力装置9上
より選択すると、工事情報保留登録・再発行処理手段4
3が情報入出力手段5に対し保留工事検索要求をかけ、
情報入出力手段5が保留工事情報記憶手段41より保留
している工事情報を検索し、検索結果を工事情報保留登
録・再発行処理手段43に送信することによって、出力
装置11に保留工事一覧が表示される。
In order to issue the suspended construction request again, the maintenance section staff selects "Reissue pending construction" of the function code "J" from the menu screen shown in FIG. Construction information hold registration / reissue processing means 4
3 makes a request for a pending construction search to the information input / output means 5,
The information input / output unit 5 searches the pending construction information storage unit 41 for the pending construction information, and transmits the search result to the construction information suspension registration / reissue processing unit 43. Is displayed.

【0081】保修課担当は、この保留工事一覧画面から
対象の工事を選択し、入力装置9上より再発行キーを入
力すると、工事情報保留登録・再発行処理手段43が情
報入出力手段5に対し更新要求を行い、情報入出力手段
5が保留工事情報記憶手段41から工事情報記憶手段1
に該当する工事情報を移動する。これにより、選択され
た工事は、通常の工事依頼状態に戻り、図15に示すメ
ニュー画面から作業指示入力画面を呼び出すことができ
る。
The maintenance section staff selects a target construction from the pending construction list screen and inputs a reissue key from the input device 9. The construction information suspension registration / reissue processing means 43 sends the information to the information input / output means 5. An update request is issued to the construction information storage means 41 from the suspended construction information storage means 41.
Move the construction information corresponding to. As a result, the selected work returns to the normal work request state, and the work instruction input screen can be called from the menu screen shown in FIG.

【0082】上記の説明からも明らかなように、本実施
の形態によれば、プラント停止時にしか作業できない工
事についても管理できるようにしたことにより、プラン
ト停止時にしか行えない作業と通常の工事とを区分けす
ることができ、管理する上で混乱を避けることができ
る。
As is apparent from the above description, according to the present embodiment, work that can be performed only when the plant is stopped can be managed, so that work that can be performed only when the plant is stopped and normal work can be performed. Can be divided, and confusion in management can be avoided.

【0083】なお、他の実施の形態として、この再発行
を保留工事情報記憶手段41だけでなく、工事履歴情報
記憶手段3からも行うことができる。この場合には、依
頼入力する際に、以前実施した工事から同じ内容の工事
を検索し、この工事の依頼情報を図4に示すような工事
依頼入力画面に再現する。このように構成することによ
り、以前実施した工事の依頼情報を再現した工事依頼入
力画面から依頼日付と依頼番号を変更するだけで、同じ
内容の工事依頼を発行することができ、省力化となる。
As another embodiment, the reissue can be performed not only from the suspended construction information storage means 41 but also from the construction history information storage means 3. In this case, when a request is input, a construction having the same contents is searched from the constructions performed previously, and the construction request information is reproduced on a construction request input screen as shown in FIG. With this configuration, it is possible to issue a construction request having the same contents by simply changing the request date and the request number from the construction request input screen that reproduces the request information of the previously performed construction, thereby saving labor. .

【0084】図16は、本発明の保修工事管理装置の第
4の実施の形態を示すもので、図1に示す第1の実施の
形態と比較して、入力装置からの差し戻し要求により、
情報入出力手段5を介して工事情報記憶手段1に記憶さ
れている工事情報を更新する差し戻し登録処理手段51
が付加されている。また、出力装置11は、図17に示
すようなメニュー画面を表示する。この画面のメニュー
には、図3に示すメニュー画面と比較して、機能コード
「K」の「差し戻し対応修正」の項目が追加されてい
る。
FIG. 16 shows a fourth embodiment of the maintenance work management system according to the present invention. Compared with the first embodiment shown in FIG.
Return registration processing means 51 for updating the construction information stored in construction information storage means 1 via information input / output means 5
Is added. Further, the output device 11 displays a menu screen as shown in FIG. In the menu of this screen, an item of “Correction corresponding to return” of the function code “K” is added as compared with the menu screen shown in FIG.

【0085】次に、本実施の形態の作用を、例えば作業
指示入力をする際等に、対象工事の工事依頼内容に不備
があることを発見した場合について説明する。
Next, the operation of the present embodiment will be described for the case where it is found that there is an insufficiency in the construction request content of the target construction when, for example, inputting a work instruction.

【0086】保修課担当が、図17に示すメニュー画面
から機能コード「ウ」の「作業指示入力」を入力装置9
により選択すると、第1の実施の形態で説明したように
出力装置11に機能コード「イ」の工事情報一覧からな
る対象工事選択画面(図5参照)が表示される。つい
で、この一覧画面から作業指示対象の工事を選択し、入
力装置9上より選択キーを入力すると、出力装置11上
に図4に示すような作業指示入力画面が表示される。こ
こまでの流れは、第1の実施の形態と同じである。
The maintenance section staff inputs “work instruction input” of the function code “c” from the menu screen shown in FIG.
Is selected, a target construction selection screen (see FIG. 5) including a construction information list of the function code “A” is displayed on the output device 11 as described in the first embodiment. Next, when the construction of the work instruction target is selected from this list screen and a selection key is input from the input device 9, a work instruction input screen as shown in FIG. 4 is displayed on the output device 11. The flow up to this point is the same as in the first embodiment.

【0087】ここで、例えば、作業依頼入力時に入力さ
れたユニットやパートなどに誤りがあった場合、入力装
置9上より差し戻しキーを入力すると、図18に示すよ
うな、差し戻し元(ここでは、作業指示を担当する部
署)から差し戻し先(ここでは、工事依頼を行った部
署)へ工事情報を差し戻すための差し戻し画面が表示さ
れる。
Here, if, for example, there is an error in the unit or part input at the time of inputting the work request, when a return key is input from the input device 9, the return source as shown in FIG. A return screen for returning the construction information from the department in charge of the work instruction to the return destination (in this case, the department that requested the construction) is displayed.

【0088】この差し戻し画面において、入力装置9に
より差し戻し理由を入力し確定キーを押すと、差し戻し
登録処理手段51を介して差し戻し要求が情報入出力手
段5に送信され、情報入出力手段5によって工事情報記
憶手段1の該当する工事情報に差し戻し理由が追加され
るとともに、機能コードが「イ」から「ア」に変更され
る。差し戻しされた工事情報の工事情報記憶手段1内の
データ構成例を図19に示す。
In this return screen, when the reason for return is input by the input device 9 and the enter key is pressed, a return request is transmitted to the information input / output means 5 via the return registration processing means 51. The reason for return is added to the applicable construction information in the information storage means 1, and the function code is changed from "A" to "A". FIG. 19 shows an example of the data configuration of the returned construction information in the construction information storage means 1.

【0089】差し戻された工事情報については、この工
事情報を入力した担当者が不備を修正するために、図1
7に示すメニュー画面から入力装置9により機能コード
「K」の「差し戻し対応修正」を選択する。この差し戻
し対応修正の選択により、工事情報検索・登録処理手段
13から情報入出力手段5に対し検索要求がかけられ、
情報入出力手段5によって工事情報記憶手段1から差し
戻し理由がある工事情報が取り出されて、工事情報検索
・登録処理手段13を介して出力装置11に一覧表示さ
れる。
Regarding the returned construction information, the person who entered this construction information corrects the deficiencies in FIG.
7, the function code “K” and “Resendment Correction” are selected by the input device 9 from the menu screen. By the selection of the return correction, a search request is issued from the construction information search / registration processing means 13 to the information input / output means 5,
The information input / output means 5 retrieves the construction information having a reason for return from the construction information storage means 1 and displays a list on the output device 11 via the construction information search / registration processing means 13.

【0090】担当者がこの一覧画面から該当する工事を
選択すると、図20に示すような差し戻し画面が表示さ
れ、さらにこの差し戻し画面で差し戻し理由を確認した
後に確認ボタンを選択すると、修正対象の入力済み工事
依頼入力画面が出力装置11に表示される。この工事依
頼入力画面上で入力装置9により不備を修正し、更新キ
ーを入力すると、工事情報検索・登録処理手段13が情
報入出力手段5に対し更新要求を行い、情報入出力手段
5によって工事情報記憶手段1の該当する工事情報が更
新され、差し戻し理由も消去される。
When the person in charge selects the applicable construction from this list screen, a restitution screen as shown in FIG. 20 is displayed. Further, after confirming the reason for the reconstitution on this reversion screen and selecting the confirm button, the input of the correction target is made. A completed construction request input screen is displayed on the output device 11. When the defect is corrected by the input device 9 on the construction request input screen and the update key is input, the construction information search / registration processing means 13 issues an update request to the information input / output means 5, and the information input / output means 5 The corresponding construction information in the information storage means 1 is updated, and the reason for return is also deleted.

【0091】ここでは、作業依頼入力時に不備があった
例について説明したが、工事実績入力時に不備があった
場合も、工事検収入力時に差し戻し要求が出され機能コ
ードが「カ」から「オ」に更新される点を除けば、基本
的に同じである。
Here, an example was described in which there was a defect at the time of inputting a work request. However, if there is a defect at the time of input of construction results, a return request is issued at the time of input of construction inspection and the function code is changed from "f" to "o". Is basically the same, except that it is updated to

【0092】上記の説明からも明らかなように、本実施
の形態によれば、工事依頼の入力内容や工事実績の入力
内容に関し不備が見つかった場合には、不備な工事情報
を入力した部署へ工事情報を差し戻して、工事情報を修
正することができる。
As is clear from the above description, according to the present embodiment, if any deficiencies are found in the input contents of the construction request and the input contents of the construction results, the section to which the deficient construction information was input is sent to The construction information can be returned to correct the construction information.

【0093】なお、他の実施の形態として、担当者が本
装置を使用する際に、情報入出力手段5が工事情報記憶
手段1から該当する差し戻し工事がないか判断し、あれ
ば、出力装置11にその旨を表示するようにすることも
できる。この場合には、差し戻しの工事情報があれば、
確実に担当者に通知されるため、差し戻し後の対応修正
が遅延なく行われる。
As another embodiment, when a person in charge uses the present apparatus, the information input / output means 5 judges whether there is a corresponding return work from the work information storage means 1, and if so, outputs 11 may be displayed to that effect. In this case, if there is construction information of return,
Since the person in charge is notified without fail, the correction after the return is made without delay.

【0094】図21は、本発明の保修工事管理装置の第
5の実施の形態を示すもので、図1に示す第1の実施の
形態と比較して、工費の勘定科目コードとその名称を記
憶している勘定科目コード記憶手段61が付加されてい
る。また、工事情報記憶手段1に記憶される工事検収入
力後の工事情報および工事履歴情報記憶手段3に記憶さ
れる工事情報には、図22に示すように、勘定科目コー
ドの欄が付加される。
FIG. 21 shows a fifth embodiment of the maintenance work management system according to the present invention. Compared with the first embodiment shown in FIG. A stored account code storage unit 61 is added. In addition, as shown in FIG. 22, an account code column is added to the construction information after the construction acceptance input stored in the construction information storage means 1 and the construction information stored in the construction history information storage means 3 as shown in FIG. .

【0095】なお、勘定科目は、例えば燃料タンク一括
機械装置修繕、構修一括構築物修繕、雑修一括雑修繕、
通信一括雑修繕等、保修対象や保修内容によって分類さ
れる。
The account items include, for example, fuel tank batch machine repair, construction repair batch structure repair, miscellaneous batch repair,
It is classified according to the maintenance target and maintenance content, such as communication batch repair.

【0096】次に、本実施の形態の作用を説明する。工
事実績入力内容承認までの流れは第1の実施の形態と同
様である。
Next, the operation of the present embodiment will be described. The flow up to the approval of the construction result input contents is the same as in the first embodiment.

【0097】工事検収入力の段階で、図3に示すメニュ
ー画面から機能コード「キ」の「工事検収入力」を選択
し、ついで表示された対象工事選択画面から対象工事を
選択することによって、図23に示すような工事検収入
力画面が出力装置11に表示される。この工事検収入力
画面には、図8に示す工事検収入力画面例と比較して、
勘定科目コードを入力する欄が付加されている。
At the stage of construction acceptance input, by selecting “construction acceptance input” of the function code “G” from the menu screen shown in FIG. 3, and then selecting the target construction from the displayed target construction selection screen, A construction acceptance input screen as shown at 23 is displayed on the output device 11. The construction acceptance input screen is different from the construction acceptance input screen shown in FIG.
A field for inputting an account code is added.

【0098】図23に示す検収項目入力画面において、
入力装置9より作業査定とともに勘定科目コードを入力
する。この勘定科目コードと名称のー覧は勘定科目コー
ド記憶手段に記憶されており、コードが正しいかを、情
報入出力手段5がチェックし、正しければ工事情報記憶
手段1の当該工事情報に作業査定と勘定科目コードを追
加し、さらに機能コードを「カ」から「キ」へ更新す
る。
In the inspection item input screen shown in FIG.
The account code is input from the input device 9 together with the work assessment. The list of account code and name is stored in the account code storage means, and the information input / output means 5 checks whether the code is correct. If the code is correct, the work information is stored in the work information in the work information storage means 1. And the account code are added, and the function code is further updated from "f" to "g".

【0099】検索時には、出力装置11上に図24に示
すような検索条件入力画面を表示して、この検索条件入
力画面から入力装置9により勘定科目コード等の検索条
件を入力し、検索実行キーを入力すると、工事情報検索
・登録処理手段13は情報入出力手段5に対し検索要求
をかけ、情報入出力手段5は勘定科目コードを含む検索
条件に基づいて工事情報記憶手段1または工事履歴情報
記憶手段3から該当する工事情報を検索する。その検索
結果は工事情報検索・登録処理手段13に送られ、工事
情報検索・登録処理手段13によって図25に示すよう
な勘定科目別工事件名一覧画面が出力装置11に表示さ
れる。この勘定科目別工事件名一覧画面では、勘定科目
ごとに、工事の件数と工事費の合計を出力することがで
きる。
At the time of search, a search condition input screen as shown in FIG. 24 is displayed on the output device 11, and search conditions such as an account code are input from the search condition input screen with the input device 9, and a search execution key is displayed. Is input, the construction information search / registration processing means 13 issues a search request to the information input / output means 5, and the information input / output means 5 outputs the construction information storage means 1 or the construction history information based on the search condition including the account code. The corresponding construction information is retrieved from the storage means 3. The search result is sent to the construction information search / registration processing means 13, and the construction information search / registration processing means 13 displays an account item-specific construction subject list screen as shown in FIG. On this account subject-specific construction subject list screen, the total number of constructions and the total construction cost can be output for each account.

【0100】上記の説明からも明らかなように、本実施
の形態によれば、勘定科目コードを工事の検収時に工事
情報とともに登録し、また、その勘定科目コードをキー
にして検索することにより、指定した期間の勘定科目別
の件数・金額の工事実績一覧を出力することができる。
As is clear from the above description, according to the present embodiment, the account code is registered together with the construction information at the time of the work acceptance, and the account code is searched for by using the account code as a key. It is possible to output a list of the construction results of the number and amount of money for each account during the specified period.

【0101】なお、他の実施の形態として、検索の際に
単に期間指定ではなく、年度ごと、期ごと、月度ごとの
ように、経理上の会計期間とあわて指定することによ
り、より会計業務に密着した勘定科目別の件数・金額の
工事実績の把握が可能となる。
As another embodiment, instead of simply specifying a period when searching, instead of specifying a period, an accounting period such as a year, a period, or a month may be specified in a short time, thereby further improving the accounting work. It becomes possible to grasp the number of cases and the amount of money for each account item.

【0102】さらに他の実施の形態として、「入力補
助」機能を用い勘定科目コード記憶手段61に記憶され
ている勘定科目コードの一覧を出力装置11に表示し、
勘定科目コード一覧から選択することによって勘定科目
コード入力を行うようにすることもできる。これによ
り、勘定科目コードの入力ミスを低減することができ
る。
As still another embodiment, a list of account code stored in the account code storage means 61 is displayed on the output device 11 by using the "input assist" function.
The account code can be input by selecting from the account code list. Thereby, it is possible to reduce an input error of the account code.

【0103】図26は、本発明の保修工事管理装置の第
6の実施の形態を示すもので、図1に示す第1の実施の
形態と比較して、工事対象設備の現象・原因・処置・機
器名等の各コードとその名称を記憶している統計コード
記憶手段71と、統計コード記憶手段71に記憶されて
いる統計用コードをキーとして検索統計処理を行う工事
統計手段73が付加されている。
FIG. 26 shows a sixth embodiment of the maintenance work management apparatus of the present invention. Compared with the first embodiment shown in FIG. A statistical code storage unit 71 that stores codes such as device names and their names, and a construction statistical unit 73 that performs search statistical processing using the statistical code stored in the statistical code storage unit 71 as a key are added. ing.

【0104】また、工事情報記憶手段1の工事実績入力
後の工事情報および工事履歴情報記憶手段3の工事情報
には、図27に示すように、「現象コード」、「原因コ
ード」等の統計用コードの欄が付加される。図27に示
す例では、統計用コードとして「現象コード」と「原因
コード」のみ例示しているが、処置内容に処置コードを
記録すれば、統計用コードとして利用することができ
る。
Further, as shown in FIG. 27, the construction information after the construction results have been input in the construction information storage means 1 and the construction information in the construction history information storage means 3 include statistics such as "phenomenon code" and "cause code". A code field is added. In the example shown in FIG. 27, only the “phenomenon code” and the “cause code” are illustrated as statistical codes, but if a treatment code is recorded in the treatment content, it can be used as a statistical code.

【0105】ここで、現象としては、例えば漏洩、亀裂
・破損、汚れ・詰り、動作・指示異常、摩耗・変形、腐
食等の項目に分けられる。また、原因の項目としては、
自然・劣化、設計・製作不完全、施行不完全、保守不完
全、過失、波及事故、災害等が例として挙げられる。ま
た、処置の項目としては、調整・校正、手直し、部品取
替、機器清掃、補給、増締、点検・分解手入等がある。
Here, the phenomena are classified into, for example, items such as leakage, crack / breakage, dirt / clogging, abnormal operation / instruction, wear / deformation, and corrosion. Also, as items of the cause,
Examples include nature / deterioration, incomplete design / manufacturing, incomplete enforcement, incomplete maintenance, negligence, spillover accidents, and disasters. In addition, the items of the treatment include adjustment / calibration, rework, replacement of parts, equipment cleaning, replenishment, tightening, inspection / disassembly, and the like.

【0106】次に、本実施の形態の作用を説明する。作
業指示入力内容承認までの流れは第1の実施の形態と同
様である。工事の作業を行った作業担当者が工事実績入
力を行う際に、図28に示すような工事実績入力画面が
出力装置11に表示される。
Next, the operation of the present embodiment will be described. The flow up to work instruction input content approval is the same as in the first embodiment. When the worker in charge of the work performs the work result input, a work result input screen as shown in FIG. 28 is displayed on the output device 11.

【0107】このような工事実績入力画面において、工
事期間、処置内容(処置コードを含む。)、作業実績と
ともに、統計用として機器名コード、原因コード、現象
コードを入力すると、工事情報検索・登録処理手段13
によって情報入出力手段5に送られる。
On the construction result input screen, when the equipment name code, the cause code, and the phenomenon code are input for statistics together with the construction period, the treatment content (including the treatment code) and the work result, the construction information is searched and registered. Processing means 13
Is sent to the information input / output means 5.

【0108】情報入出力手段5は、送られた統計用コー
ドが正しいかどうかを、統計コード記憶手段71に記憶
されている統計用コードとその名称に基づいてチェック
し、正しければ工事情報記憶手段1の当該工事情報に処
置内容、作業実績とともに統計用コードを追加し、さら
に機能コードを「エ」から「オ」へ更新する。
The information input / output means 5 checks whether or not the sent statistical code is correct based on the statistical code stored in the statistical code storage means 71 and its name. In step 1, a statistical code is added to the construction information together with the treatment content and the work result, and the function code is further updated from "d" to "o".

【0109】検索時には、出力装置11上に図29に示
すような検索条件入力画面を表示して、この検索条件入
力画面から入力装置9により検索条件を入力し、対象統
計項目を選択して、検索実行キーを入力すると、工事情
報検索・登録処理手段13は工事統計手段73に対して
検索要求をかける。
At the time of a search, a search condition input screen as shown in FIG. 29 is displayed on the output device 11, a search condition is input from the search condition input screen by the input device 9, and a target statistical item is selected. When the search execution key is input, the construction information search / registration processing means 13 issues a search request to the construction statistical means 73.

【0110】工事統計手段73は、工事情報検索・登録
処理手段13から検索要求とともに送信された検索条件
に基づいて工事情報記憶手段1または工事履歴情報記憶
手段3から該当する工事件名を検索し、検索条件ととも
に送信された対象統計項目に基づいて検索結果を統計処
理する。
The construction statistics means 73 searches the construction information storage means 1 or the construction history information storage means 3 for a corresponding construction subject based on the search condition transmitted from the construction information search / registration processing means 13 together with the search request. Statistical processing is performed on the search results based on the target statistical items transmitted together with the search conditions.

【0111】工事情報検索・登録処理手段13は、工事
統計手段73からの統計結果を図30に示すような統計
結果画面にして出力装置11に表示する。図30の統計
結果画面では、原因別の件数を表とグラフの形式で出力
している。これは、原因コードだけでなく、現象コード
や処置コードや機器名コードでも同様である。
The construction information search / registration processing means 13 displays the statistical result from the construction statistical means 73 on the output device 11 as a statistical result screen as shown in FIG. In the statistical result screen of FIG. 30, the number of cases for each cause is output in the form of a table and a graph. This applies not only to the cause code, but also to the phenomenon code, the treatment code, and the device name code.

【0112】上記の説明からも明らかなように、本実施
の形態によれば、統計用コードを工事の完了時(工事実
績入力時)や検収時(工事検収入力時)に、工事情報と
あわせて登録することにより、そのコード別の統計一覧
を出力可能となり、設備劣化の傾向管理やプラントの設
備実態管理に役立てることができる。
As is clear from the above description, according to the present embodiment, the statistical code is combined with the construction information when the construction is completed (when the construction result is input) or when the construction is accepted (when the construction acceptance is input). By registering the codes, a statistical list for each code can be output, which can be used for management of equipment deterioration tendency and management of plant equipment actual conditions.

【0113】なお、他の実施の形態として、「入力補
助」機能を用い統計コード記憶手段71に記憶されてい
る統計用コードの一覧を出力装置11に表示し、そこか
ら選択方式にて入力をさせることも可能である。このよ
うな選択方式を採用することにより、各種統計コードの
入力ミスを低減することができる。
As another embodiment, a list of statistical codes stored in the statistical code storage means 71 is displayed on the output device 11 by using the "input assisting" function, and an input is made by a selection method therefrom. It is also possible to make it. By employing such a selection method, it is possible to reduce input errors of various statistical codes.

【0114】図31は、本発明の保修工事管理装置の第
7の実施の形態を示すもので、図1に示す第1の実施の
形態と比較して、単価、係数、税率等の工事実績の計算
に必要なシステム管理定数をその有効日とともに記憶し
ているシステム管理定数記憶手段81と、情報入出力手
段5に対してシステム管理定数記憶手段81の登録・検
索を要求するシステム管理定数検索・登録処理手段83
が付加されている。
FIG. 31 shows a seventh embodiment of the maintenance work management system according to the present invention. Compared with the first embodiment shown in FIG. System management constant storage means 81 which stores the system management constants necessary for the calculation of the information together with the effective date, and a system management constant search requesting the information input / output means 5 to register and search the system management constant storage means 81.・ Registration processing means 83
Is added.

【0115】システム管理情報記憶手段81には、工事
実績を計算する際に必要なシステム管理定数、例えば一
人当たりの作業単価、管理費の係数、税率等がその切替
日(有効開始日)とともに保存される。
The system management information storage means 81 stores system management constants required for calculating construction results, for example, a work unit price per person, a management cost coefficient, a tax rate, and the like along with the switching date (effective start date). Is done.

【0116】また、出力装置11は、図32に示すよう
なメニュー画面を表示する。この画面のメニューには、
図3に示すメニュー画面と比較して、機能コード「L」
の「システム管理定数設定」の項目が追加されている。
The output device 11 displays a menu screen as shown in FIG. The menus on this screen include:
Compared with the menu screen shown in FIG. 3, the function code "L"
"System Management Constant Setting" item has been added.

【0117】次に、本実施の形態の作用を説明する。シ
ステム管理者が、図32に示すメニュー画面から機能コ
ード「L」の「システム管理定数設定」を入力装置9上
から選択すると、図33に示すようなシステム管理定数
設定画面が出力装置11に表示される。
Next, the operation of the present embodiment will be described. When the system administrator selects “system management constant setting” of the function code “L” from the input device 9 from the menu screen shown in FIG. 32, a system management constant setting screen as shown in FIG. Is done.

【0118】このシステム管理定数設定画面において、
作業単価(作業員一人当たりの日当)や、工具損料、安
全管理費、現場管理費、一般管理費等の管理係数や、消
費税率等をその切替日(有効開始日)とともに入力し、
登録キーを入力手段1より入力すると、システム管理定
数検索・登録処理手段83は情報入出力手段5を介して
システム管理定数記憶手段81に入力情報を追加登録す
る。図34に、システム管理定数記憶手段81内の登録
データ例を示す。
In the system management constant setting screen,
Enter the work unit price (per day per worker), tool loss, safety management costs, site management costs, management costs such as general management costs, consumption tax rates, etc., along with the switching date (effective start date),
When a registration key is input from the input unit 1, the system management constant search / registration processing unit 83 additionally registers input information in the system management constant storage unit 81 via the information input / output unit 5. FIG. 34 shows an example of registered data in the system management constant storage unit 81.

【0119】工事実績入力時は、出力装置11に図35
に示すような工事実績入力画面が表示される。この工事
実績入力画面において、工事期間、処置内容、作業実績
を入力すると、入力された工事期間に有効なシステム管
理定数がシステム管理定数記憶手段81から情報入出力
手段5によって取り出され、システム管理定数検索・登
録処理手段83を介して工事実績入力画面上に表示され
るとともに、呼び出されたシステム管理定数と入力され
た工事期間および作業実績から工費、工具損料、安全管
理費、現場管理費、一般管理費および総額等が計算され
て工事実績入力画面上に表示される。
At the time of input of construction results, the output device 11
The construction result input screen shown in Fig. 7 is displayed. When a construction period, a treatment content, and a work result are input on the construction result input screen, a system management constant valid for the input construction period is retrieved from the system management constant storage means 81 by the information input / output means 5, and the system management constant is input. It is displayed on the construction results input screen via the search / registration processing means 83, and is based on the called system management constants and the inputted construction period and work results, and includes construction costs, tool losses, safety management costs, site management costs, general The management cost and total amount are calculated and displayed on the construction result input screen.

【0120】この工事実績入力画面上から登録キーを入
力すると、工事情報検索・登録処理手段13を介して情
報入出力手段5により工事情報記憶手段1内の該当する
工事情報に工事期間、処置内容、作業実績および算出さ
れた各種工事費が追加され、機能コードが「エ」から
「オ」に更新される。
When a registration key is input on the construction result input screen, the information input / output means 5 via the construction information search / registration processing means 13 stores the construction period and the treatment contents in the corresponding construction information in the construction information storage means 1. , The work result and the calculated various construction costs are added, and the function code is updated from “D” to “O”.

【0121】なお、切替日をまたがって長期間工事が行
われる場合に、どの管理定数を適用するかはいくつかの
方法が考えられる。
When construction is performed for a long period of time over the switching date, there are several methods for determining which management constant is to be applied.

【0122】ひとつの方法は、工事期間に対して工事の
開始日もしくは完了日等のある基準日を取り決め、その
日が切替日より前にあるか後ろにあるかによって適用す
る管理定数を決定するものである。
One method is to determine a reference date such as a construction start date or a completion date for the construction period, and to determine a management constant to be applied depending on whether the date is before or after the switching date. It is.

【0123】他のひとつの方法は、実際に作業した日を
より詳細に指定して切替日前後の管理定数をそれぞれ適
用する方法である。図36に、実際に作業した日をより
詳細に指定するための作業実績詳細入力画面例を示す。
このように、日ごとの作業実績をまとめることにより、
切替日の前と後でそれぞれ計算し、より厳密に工事費を
算出することができる。
Another method is a method in which the actual work date is specified in more detail, and the management constants before and after the switching date are applied. FIG. 36 shows an example of a work result details input screen for specifying the actual work day in more detail.
In this way, by summarizing daily work results,
Calculation can be performed before and after the switching date, respectively, to more accurately calculate the construction cost.

【0124】上記の説明からも明らかなように、本実施
の形態によれば、切替更新されるシステム管理定数をそ
の切替日とともにあらかじめ設定しておくことにより、
工事情報記憶手段に記憶されている工事情報に、そのシ
ステム管理情報を反映させ、切替日を判断して自動的に
最適な単価や管理費係数、税率等を用いて工費の自動計
算を行うことができる。
As is clear from the above description, according to the present embodiment, the system management constant to be switched and updated is set in advance together with the switching date, so that
The system management information is reflected in the construction information stored in the construction information storage means, the switching date is determined, and the construction cost is automatically calculated using the optimal unit price, management cost coefficient, tax rate, etc. Can be.

【0125】図37は、本発明の保修工事管理装置の第
8の実施の形態を示すもので、図1に示す第1の実施の
形態と比較して、ΙDごとに機能制約情報をあらかじめ
記憶している機能制約情報記憶手段91と、工事情報検
索・登録処理手段13から送信されたIDにより機能制
約情報記憶手段91から対応する機能制約情報を取り出
し工事情報検索・登録処理手段13に通知するΙD照合
手段93が付加されている。
FIG. 37 shows an eighth embodiment of the maintenance work management system of the present invention. Compared with the first embodiment shown in FIG. 1, function restriction information is stored in advance for each $ D. The corresponding function restriction information is extracted from the function restriction information storage unit 91 based on the ID transmitted from the function restriction information storage unit 91 and the construction information search / registration processing unit 13, and is notified to the construction information search / registration processing unit 13. ΙD collating means 93 is added.

【0126】IDは、入力される担当グループ・役職ご
とに設定されるもので、機能制約情報記憶手段91は、
IDごとに使用(処理)可能な機能や権限を示す機能制
約情報をあらかじめ記憶している。
The ID is set for each charge group / post to be input.
Function restriction information indicating a function or authority that can be used (processed) for each ID is stored in advance.

【0127】次に、本実施の形態の作用を説明する。図
3に示すようなメニュー画面に先立って、図38に示す
ようなΙDの入力を促すΙD入力画面が出力装置11に
表示される。オペレータは、このΙD入力画面におい
て、入力装置9よりΙDを入力すると、工事情報検索・
登録処理手段13を介してΙD照合手段91にΙDが送
られ、ΙD照合手段91は機能制約情報記憶手段91に
記憶されているIDと照合する。
Next, the operation of the present embodiment will be described. Prior to the menu screen as shown in FIG. 3, a ΙD input screen for prompting the user to enter ΙD as shown in FIG. 38 is displayed on the output device 11. When the operator inputs $ D from the input device 9 on this $ D input screen, the construction information search /
The $ D is sent to the $ D matching means 91 via the registration processing means 13, and the $ D matching means 91 checks the ID against the ID stored in the function restriction information storage means 91.

【0128】図39は、機能制約情報記憶手段91に記
憶されるデータ構成例を示すもので、例えば、IDが
「ΑAAAΑ」の場合は、機能コード「ア」は「○」で
あるので、操作可能であるが、機能コード「イ」は
「×」なので、操作禁止の機能であることがわかる。な
お、図39における機能コードは、図3、15、17、
32に示すメニュー画面の機能コードに対応する。
FIG. 39 shows an example of the data structure stored in the function restriction information storage means 91. For example, when the ID is “{AAA}”, the function code “A” is “O”. Although it is possible, since the function code "i" is "x", it is understood that the function is a function for which operation is prohibited. The function codes in FIG. 39 are shown in FIGS.
32 corresponds to the function code on the menu screen.

【0129】このように照合された結果は、ΙD照合手
段91から工事情報検索・登録処理手段13に送信さ
れ、工事情報検索・登録処理手段13は出力装置11に
メニュー画面を表示する際に、例えば操作可能な機能の
メニューのみ表示する、操作禁止の機能のメニューを薄
くあるいは色替して表示するなど、操作可能な機能と操
作不可能な機能を識別可能に表示する。
The result of such collation is transmitted from the ΙD collating means 91 to the construction information search / registration processing means 13, and the construction information search / registration processing means 13 displays a menu screen on the output device 11. For example, an operable function and an inoperable function are distinguishably displayed, such as displaying only a menu of operable functions or displaying a menu of operation-prohibited functions lightly or by changing colors.

【0130】これによって、オペレータは、メニュー画
面において操作可能である機能と、不可能である機能を
区別することができる。
Thus, the operator can distinguish between a function that can be operated on the menu screen and a function that cannot be operated on the menu screen.

【0131】なお、図39に示す例では、ΙDが「ΒB
ΒΒΒ」の場合をみてみると、職位が「課長」となって
いることから、承認行為を許すという判断も可能とな
る。すなわち、ΙD照合手段91が入力IDを役職者Ι
Dと判断した場合に、工事情報検索・登録処理手段13
はその判断結果からオペレータが承認権限を有するもの
と判定して、この場合のみ入力装置9からの承認情報を
工事情報に付加するようにすることもできる。
In the example shown in FIG. 39, ΙD is changed to “ΒB
Looking at the case of “ΒΒΒ”, since the job title is “Manager”, it is possible to determine that approval is permitted. In other words, {the D matching means 91 changes the input ID to the official}
D, the construction information search / registration processing means 13
May determine that the operator has the approval authority from the determination result, and only in this case, the approval information from the input device 9 may be added to the construction information.

【0132】さらに、図39に示すように、IDを箇所
(所属組織)と職位に対応させて管理することにより、
組織と職位の組み合わせによって機能制限や承認権限を
判断するようにすることも可能となる。
Further, as shown in FIG. 39, by managing the ID in association with the place (affiliated organization) and the position,
It is also possible to determine the function restriction and approval authority based on the combination of the organization and the position.

【0133】上記の説明からも明らかなように、本実施
の形態によれば、入力IDにより使用可能な機能をあら
かじめ設定することにより、承認権限を有するIDが入
力されたときのみ承認情報を工事情報に付加するように
することができ、データのセキュリティーを向上させ、
情報の信頼性を高めることができる。
As is clear from the above description, according to the present embodiment, by setting the functions that can be used by the input ID in advance, the approval information is only constructed when the ID having the approval authority is input. Can be added to information, improve data security,
The reliability of information can be improved.

【0134】なお、他の実施の形態として、IDごとに
パスワードをあわせて管理することもできる。これによ
り、ΙDとパスワードの両方が正しくないと本装置が機
能しなくなるため、データのセキュリティーはより高く
なる。
In another embodiment, a password can be managed for each ID. As a result, if both the $ D and the password are incorrect, the present device will not function, and the data security will be higher.

【0135】[0135]

【発明の効果】上記したように、本発明によれば、工事
情報記憶手段および情報入出力手段に対して伝送路を介
して工事情報登録・検索要求手段を増設可能に接続する
ことにより、保修工事にかかわる複数の人が容易に管理
操作することができる。
As described above, according to the present invention, maintenance information is connected to the construction information storage means and the information input / output means via a transmission line so that the construction information registration / search request means can be added. Multiple persons involved in the construction can easily manage and operate.

【0136】また本発明によれば、工事情報として、イ
メージ情報も併せて管理することにより、より的確に情
報の把握や伝達を行うことができる。
According to the present invention, by managing image information as construction information, information can be grasped and transmitted more accurately.

【0137】また本発明によれば、実施時期の制限のあ
る保修工事を通常の工事情報と区別して管理することに
より、工事の際の混乱や不手際を避けることができる。
Further, according to the present invention, the maintenance work whose execution time is restricted is managed separately from ordinary construction information, so that confusion and inaccuracies at the time of construction can be avoided.

【0138】また本発明によれば、入力された工事情報
に誤りがあった場合、誤りを入力した段階に差し戻すこ
とにより、正しい工事情報のもとに保修工事を管理する
ことができる。
Further, according to the present invention, when there is an error in the input construction information, the maintenance work can be managed based on the correct construction information by returning to the stage where the error was input.

【0139】また本発明によれば、工事情報に勘定科目
情報を付加することにより、勘定科目毎の工事件数や工
事金額を集計することができる。
Further, according to the present invention, by adding account item information to the construction information, the number of works and the amount of construction for each account item can be totaled.

【0140】また本発明によれば、工事情報に各種統計
項目情報を付加することにより、項目をもとに統計管理
を行うことができ、不具合の傾向把握が容易となる。
Further, according to the present invention, by adding various kinds of statistical item information to the construction information, statistical management can be performed based on the items, and the tendency of troubles can be easily grasped.

【0141】また本発明によれば、工費の計算に必要な
システム管理定数をその有効開始日とともに管理するこ
とにより、保修工事の作業日に応じて、適切なシステム
管理定数を自動的に適用することができる。
Further, according to the present invention, by managing the system management constants required for calculating the construction cost together with the effective start date, an appropriate system management constant is automatically applied according to the work day of the maintenance work. be able to.

【0142】また本発明によれば、入力ΙDに応じて使
用可能な機能を制限することにより、工事情報のセキュ
リティーを保つことができる。
Further, according to the present invention, the security of construction information can be maintained by limiting the functions that can be used according to the input $ D.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の保修工事管理装置の第1実施の形態を
示すブロック図である。
FIG. 1 is a block diagram illustrating a first embodiment of a maintenance work management device according to the present invention.

【図2】本発明の保修工事管理装置のシステム適用例を
示す図である。
FIG. 2 is a diagram showing a system application example of the maintenance work management device of the present invention.

【図3】図1に示す出力装置に表示されるメニュー画面
例を示す図である。
FIG. 3 is a diagram showing an example of a menu screen displayed on the output device shown in FIG. 1;

【図4】図1に示す出力装置に表示される工事依頼入力
画面例を示す図である。
FIG. 4 is a diagram showing an example of a construction request input screen displayed on the output device shown in FIG. 1;

【図5】図1に示す出力装置に表示される対象工事選択
画面例を示す図である。
FIG. 5 is a diagram showing an example of a target construction selection screen displayed on the output device shown in FIG. 1;

【図6】図1に示す出力装置に表示される作業指示入力
画面例を示す図である。
6 is a diagram showing an example of a work instruction input screen displayed on the output device shown in FIG.

【図7】図1に示す出力装置に表示される工事実績入力
画面例を示す図である。
FIG. 7 is a diagram showing an example of a construction result input screen displayed on the output device shown in FIG. 1;

【図8】図1に示す出力装置に表示される工事検収入力
画面例を示す図である。
8 is a diagram showing an example of a construction acceptance input screen displayed on the output device shown in FIG. 1;

【図9】図1に示す工事情報記憶手段のデータ構成例を
示す図である。
FIG. 9 is a diagram showing a data configuration example of a construction information storage unit shown in FIG. 1;

【図10】図1に示す出力装置に表示される検索条件入
力画面例を示す図である。
10 is a diagram showing an example of a search condition input screen displayed on the output device shown in FIG.

【図11】図1に示す出力装置に表示される工事進捗状
況一覧画面例を示す図である。
11 is a diagram showing an example of a construction progress status list screen displayed on the output device shown in FIG. 1;

【図12】本発明の保修工事管理装置の第2の実施の形
態を示すブロック図である。
FIG. 12 is a block diagram illustrating a maintenance work management device according to a second embodiment of the present invention.

【図13】図12に示す工事情報記憶手段のデータ構成
例を示す図である。
FIG. 13 is a diagram showing a data configuration example of a construction information storage unit shown in FIG.

【図14】本発明の保修工事管理装置の第3の実施の形
態を示すブロック図である。
FIG. 14 is a block diagram illustrating a maintenance work management device according to a third embodiment of the present invention.

【図15】図14に示す出力装置に表示されるメニュー
画面例を示す図である。
15 is a diagram showing an example of a menu screen displayed on the output device shown in FIG.

【図16】本発明の保修工事管理装置の第4の実施の形
態を示すブロック図である。
FIG. 16 is a block diagram illustrating a maintenance work management device according to a fourth embodiment of the present invention.

【図17】図16に示す出力装置に表示されるメニュー
画面例を示す図である。
17 is a diagram showing an example of a menu screen displayed on the output device shown in FIG.

【図18】図16に示す出力装置に表示される差し戻し
画面例を示す図である。
FIG. 18 is a diagram showing an example of a return screen displayed on the output device shown in FIG. 16;

【図19】図16に示す工事情報記憶手段のデータ構成
例を示す図である。
19 is a diagram showing a data configuration example of a construction information storage unit shown in FIG.

【図20】図16に示す出力装置に表示される差し戻し
画面例を示す図である。
20 is a diagram showing an example of a return screen displayed on the output device shown in FIG. 16;

【図21】本発明の保修工事管理装置の第5の実施の形
態を示すブロック図である。
FIG. 21 is a block diagram illustrating a maintenance work management device according to a fifth embodiment of the present invention.

【図22】図21に示す工事情報記憶手段のデータ構成
例を示す図である。
FIG. 22 is a diagram showing a data configuration example of a construction information storage means shown in FIG. 21.

【図23】図21に示す出力装置に表示される工事検収
入力画面例を示す図である。
FIG. 23 is a diagram showing an example of a construction acceptance input screen displayed on the output device shown in FIG. 21;

【図24】図21に示す出力装置に表示される検索条件
入力画面例を示す図である。
24 is a diagram showing an example of a search condition input screen displayed on the output device shown in FIG. 21.

【図25】図21に示す出力装置に表示される勘定科目
別工事件名一覧画面例を示す図である。
FIG. 25 is a diagram showing an example of a construction subject list screen by account item displayed on the output device shown in FIG. 21;

【図26】本発明の保修工事管理装置の第6の実施の形
態を示すブロック図である。
FIG. 26 is a block diagram illustrating a maintenance work management device according to a sixth embodiment of the present invention.

【図27】図26に示す工事情報記憶手段のデータ構成
例を示す図である。
FIG. 27 is a diagram illustrating an example of a data configuration of a construction information storage unit illustrated in FIG. 26;

【図28】図26に示す出力装置に表示される工事実績
入力画面例を示す図である。
FIG. 28 is a diagram showing an example of a construction result input screen displayed on the output device shown in FIG. 26;

【図29】図26に示す出力装置に表示される検索条件
入力画面例を示す図である。
FIG. 29 is a diagram showing an example of a search condition input screen displayed on the output device shown in FIG. 26;

【図30】図26に示す出力装置に表示される統計結果
画面例を示す図である。
30 is a diagram showing an example of a statistical result screen displayed on the output device shown in FIG. 26.

【図31】本発明の保修工事管理装置の第7の実施の形
態を示すブロック図である。
FIG. 31 is a block diagram illustrating a maintenance work management device according to a seventh embodiment of the present invention.

【図32】図31に示す出力装置に表示されるメニュー
画面例を示す図である。
32 is a diagram showing an example of a menu screen displayed on the output device shown in FIG. 31.

【図33】図31に示す出力装置に表示されるシステム
管理定数設定画面例を示す図である。
FIG. 33 is a diagram showing an example of a system management constant setting screen displayed on the output device shown in FIG. 31.

【図34】図31に示すシステム管理定数記憶手段のデ
ータ構成例を示す図である。
34 is a diagram showing a data configuration example of a system management constant storage unit shown in FIG. 31.

【図35】図31に示す出力装置に表示される工事実績
入力画面例を示す図である。
FIG. 35 is a diagram showing an example of a construction result input screen displayed on the output device shown in FIG. 31.

【図36】図31に示す出力装置に表示される作業実績
詳細入力画面例を示す図である。
36 is a diagram showing an example of a work result details input screen displayed on the output device shown in FIG. 31.

【図37】本発明の保修工事管理装置の第8の実施の形
態を示すブロック図である。
FIG. 37 is a block diagram showing an eighth embodiment of the maintenance work management device of the present invention.

【図38】図37に示す出力装置に表示されるΙD入力
画面例を示す図である。
38 is a diagram showing an example of a $ D input screen displayed on the output device shown in FIG. 37.

【図39】図37に示す機能制約情報記憶手段のデータ
構成例を示す図である。
FIG. 39 is a diagram showing a data configuration example of a function restriction information storage unit shown in FIG. 37.

【符号の説明】[Explanation of symbols]

1………工事情報記憶手段 3………工事履歴情報記憶手段 5………情報入出力手段 7………工事情報登録・検索要求手段 9………入力装置 11………出力装置 13………工事情報検索・登録処理手段 21………保修工事管理端末 23………所内LAN 25………保修工事サーバー 31………イメージ情報記憶手段 41………保留工事情報記憶手段 43………工事情報保留・再発行処理手段 51………差し戻し登録処理手段 61………勘定科目コード記憶手段 71………統計コード記憶手段 73………工事統計手段 81………システム管理定数記憶手段 83………システム管理定数検索・登録処理手段 91………機能制約情報記憶手段 93………ID照合手段 1 construction information storage means 3 construction history information storage means 5 information input / output means 7 construction information registration / search request means 9 input device 11 output device 13 ... construction information search / registration processing means 21 ... maintenance work management terminal 23 ... in-house LAN 25 ... maintenance work server 31 ... image information storage means 41 ... reserved construction information storage means 43 ... … Construction information suspension / reissue processing means 51… Return registration processing means 61… Account code storage means 71… Statistical code storage means 73… Construction statistic means 81… System management constant storage means 83 ... system management constant search / registration processing means 91 ... function restriction information storage means 93 ... ID collation means

Claims (15)

【特許請求の範囲】[Claims] 【請求項1】 プラントの設備機器の保全修理を行う保
修工事を管理する装置において、 保修工事ごとに、保修の依頼内容を示す工事依頼情報、
当該保修の作業を業者に指示する内容の作業指示情報、
当該工事の作業実績を示す工事実績情報、および当該工
事の検収内容を示す工事検収情報の各工事情報を工事の
進捗段階に応じて順次記憶する工事情報記憶手段と、 前記工事情報記憶手段の工事情報の登録および検索を行
う情報入出力手段と、 前記情報入出力手段と伝送路を介して接続され、入力装
置および出力装置を備え、前記入力装置を介して入力さ
れた情報に基づいて前記情報入出力手段に対して工事情
報の登録要求または検索要求を行い、前記情報入出力手
段からの検索結果を前記出力装置へ出力する、少なくと
も1つの工事情報登録・検索要求手段とを具備すること
を特徴とする保修工事管理装置。
An apparatus for managing maintenance work for performing maintenance and repair of plant equipment, comprising: construction request information indicating maintenance request contents for each maintenance work;
Work instruction information that instructs the contractor to perform the maintenance work,
Construction information storage means for sequentially storing construction information indicating construction work information indicating the work performance of the construction, and construction inspection information indicating inspection contents of the construction according to the progress stage of the construction, and construction of the construction information storage means An information input / output means for registering and searching for information; an information input / output means connected to the information input / output means via a transmission line, including an input device and an output device, and the information based on information input through the input device. At least one construction information registration / search request means for making a registration request or a search request for construction information to the input / output means and outputting a search result from the information input / output means to the output device. The maintenance work management device that is the feature.
【請求項2】 前記工事情報登録・検索要求手段が、 前記入力装置からの内容承認要求により、前記情報入出
力手段を介して前記工事情報記憶手段から該当する工事
情報を読み出して前記出力装置に出力し、前記入力装置
を介して入力された内容承認信号により前記情報入出力
手段を介して前記工事情報記憶手段の該当する工事情報
に承認情報を付加する手段を有することを特徴とする請
求項1記載の保修工事管理装置。
2. The construction information registration / retrieval request means reads out the corresponding construction information from the construction information storage means via the information input / output means in response to a content approval request from the input device, and sends the read construction information to the output device. Means for outputting approval information to the corresponding construction information in said construction information storage means via said information input / output means in response to a content approval signal input via said input device. The maintenance work management device according to 1.
【請求項3】 前記工事情報登録・検索要求手段が、 前記入力装置からの工事情報の入力要求により、工事情
報の入力を促す工事情報入力画面を前記出力装置に出力
し、前記工事情報入力画面にしたがって前記入力装置を
介して入力された情報に基づいて工事情報を作成し、前
記情報入出力手段を介して前記工事情報記憶手段に登録
する手段を有することを特徴とする請求項1または2記
載の保修工事管理装置。
3. The construction information registration / search requesting means outputs a construction information input screen for prompting input of construction information to the output device in response to a construction information input request from the input device, and outputs the construction information input screen. And means for creating construction information based on the information input through the input device in accordance with the above, and registering the construction information in the construction information storage means via the information input / output means. Maintenance work management device as described.
【請求項4】 前記工事情報登録・検索要求手段が、 前記入力装置からの工事情報の入力要求により、前段階
の情報まで登録された保修工事を対象工事として前記情
報入出力手段を介して前記工事情報記憶手段から取り出
し、対象工事一覧を前記出力装置に出力する手段と、 前記対象工事一覧から前記入力装置を介して選択された
保修工事について工事情報の入力を促す工事情報入力画
面を前記出力装置に出力する手段と、 前記工事情報入力画面に従って前記入力装置を介して入
力された情報に基づいて工事情報を作成し、前記情報入
出力手段を介して前記工事情報記憶手段の当該保修工事
の登録情報に付加する手段とを有することを特徴とする
請求項1または2記載の保修工事管理装置。
4. The construction information registration / retrieval requesting means, through a request for inputting construction information from the input device, targets maintenance work registered up to information at a previous stage as a target construction through the information input / output means. Means for extracting the target work list from the work information storage means and outputting the target work list to the output device; and outputting the work information input screen for prompting input of the work information for the maintenance work selected from the target work list via the input device. Means for outputting to the device, creating construction information based on the information inputted through the input device according to the construction information input screen, and performing the maintenance work of the construction information storage means via the information input / output means. 3. The maintenance work management device according to claim 1, further comprising means for adding to the registration information.
【請求項5】 保修工事を補足説明するイメージ情報を
記憶するイメージ情報記憶手段を具備し、 前記情報入出力手段が、 前記工事情報登録・検索要求手段からの登録要求によ
り、登録要求とともに送信されたイメージ情報および工
事情報のうちイメージ情報を前記イメージ情報記憶手段
に格納し、前記工事情報に前記イメージ情報との連携情
報を付加して前記工事情報記憶手段に登録する手段と、 前記工事情報登録・検索要求手段からの検索要求によ
り、前記工事情報記憶手段から該当する工事情報を検索
し、当該工事情報に付加された連携情報に基づいて前記
イメージ情報記憶手段から該当するイメージ情報を検索
する手段とを有することを特徴とする請求項1ないし4
のいずれか1項に記載の保修工事管理装置。
5. An image information storage means for storing image information supplementally describing the maintenance work, wherein said information input / output means is transmitted together with a registration request by a registration request from said construction information registration / search request means. Means for storing image information among the image information and the construction information in the image information storage means, adding link information with the image information to the construction information, and registering the construction information in the construction information storage means; Means for searching for the corresponding construction information from the construction information storage means in response to a search request from the search request means, and searching for the relevant image information from the image information storage means based on the link information added to the construction information; 5. The method according to claim 1, wherein
The maintenance work management device according to any one of the above.
【請求項6】 作業保留対象の工事依頼情報を記憶する
保留工事情報記憶手段を具備し、 前記工事情報登録・検索要求手段が、 作業指示の段階で、前記出力装置に出力された対象工事
一覧から前記入力装置を介して作業保留対象として選択
された保修工事について、前記情報入出力手段を介して
前記工事情報記憶手段から該当する工事情報を前記保留
工事情報記憶手段に移動する手段と、 前記入力装置からの要求により、前記情報入出力手段を
介して前記保留工事情報記憶手段に記憶されている作業
保留対象の工事情報を読み出し、保留工事一覧を前記出
力装置に出力する手段と、 前記保留工事一覧から前記入力装置を介して選択された
工事情報を前記保留工事情報記憶手段から前記工事情報
記憶手段に移動する手段とを有することを特徴とする請
求項1ないし5のいずれか1項に記載の保修工事管理装
置。
6. A work information registering / retrieval requesting means for storing work request information of a work pending target, wherein said work information registration / search request means outputs a list of target works output to said output device at a work instruction stage. Means for moving the relevant construction information from the construction information storage means to the reserved construction information storage means via the information input / output means, for the maintenance work selected as a work suspension target via the input device; Means for reading out the work information of the work to be suspended stored in the suspended construction information storage means via the information input / output means, and outputting a pending construction list to the output device in response to a request from the input device; Means for moving the construction information selected from the construction list via the input device from the reserved construction information storage means to the construction information storage means. TamotsuOsamu construction management apparatus according to any one of claims 1 to 5.
【請求項7】 前記工事情報登録・検索要求手段が、 前記工事情報記憶手段から前記出力装置に出力された工
事情報について、前記入力装置からの差し戻し要求によ
り、前記入力装置を介して入力された前記工事情報の不
備を示す差し戻し理由を、前記情報入出力手段を介して
前記工事情報記憶手段の当該工事情報に付加する手段
と、 前記入力装置からの要求により、前記情報入出力手段を
介して前記工事情報記憶手段から前記差し戻し理由を付
加された工事情報を修正対象工事情報として読み出し、
前記出力装置に修正対象工事情報一覧を出力する手段
と、 前記修正対象工事情報一覧から前記入力装置を介して選
択された工事情報について、前記入力装置を介して入力
された情報に基づいて、前記情報入出力手段を介して前
記工事情報記憶手段の当該工事情報の不備を修正しかつ
前記差し戻し理由を削除する手段とを有することを特徴
とする請求項1ないし6のいずれか1項に記載の保修工
事管理装置。
7. The construction information registration / search requesting means, wherein the construction information output from the construction information storage means to the output device is input via the input device in response to a return request from the input device. A means for adding a return reason indicating incompleteness of the construction information to the construction information of the construction information storage means via the information input / output means, and a request from the input device, via the information input / output means Read the construction information to which the reason for return is added from the construction information storage means as the work information to be corrected,
Means for outputting a correction target construction information list to the output device, and for the construction information selected from the correction target construction information list via the input device, based on information input via the input device, 7. The device according to claim 1, further comprising: means for correcting a defect of the construction information in the construction information storage means and deleting the reason for sending back via the information input / output means. Maintenance work management device.
【請求項8】 経理上の工費区分を示す勘定科目ごとに
勘定科目コードを記憶する勘定科目コード記憶手段を具
備し、 前記情報入出力手段が、前記工事情報登録・検索要求手
段から送信された勘定科目コードについて前記勘定科目
コード記憶手段に記憶されているか否かを判定し、記憶
されているとき前記勘定科目コードを前記工事情報記憶
手段の対応する工事情報に付加する手段を有することを
特徴とする請求項1ないし7のいずれか1項に記載の保
修工事管理装置。
8. An account item code storage unit for storing an account item code for each account item indicating an accounting cost category, wherein the information input / output unit is transmitted from the construction information registration / search request unit. Means for determining whether or not the account code is stored in the account code storage means, and adding the account code to the corresponding construction information in the construction information storage means when stored. The maintenance work management device according to any one of claims 1 to 7, wherein
【請求項9】 保修工事を統計処理する観点を示す統計
対象項目別に、それぞれ設定された統計用コードを記憶
する統計コード記憶手段を具備し、 前記情報入出力手段が、 前記工事情報登録・検索要求手段から送信された前記統
計対象項目に対応する各統計用コードについて前記統計
コード記憶手段に記憶されているか否かを判定し、記憶
されているとき前記各統計用コードを前記工事情報記憶
手段の対応する工事情報に付加する手段と、 前記工事情報登録・検索要求手段から送信された統計出
力対象項目を含む検索条件に基づいて前記工事情報記憶
手段を検索し、検索結果を当該統計出力対象項目によっ
て統計処理し前記工事情報登録・検索要求手段に送信す
る手段とを有することを特徴とする請求項1ないし8の
いずれか1項に記載の保修工事管理装置。
9. Statistical code storage means for storing a statistical code set for each statistical object item indicating a viewpoint of performing statistical processing of maintenance work, wherein said information input / output means includes said work information registration / retrieval. It is determined whether each statistic code corresponding to the statistic object item transmitted from the request means is stored in the statistic code storage means, and when stored, the respective statistic codes are stored in the construction information storage means. Means for adding to the corresponding construction information, and searching the construction information storage means based on a search condition including a statistical output target item transmitted from the construction information registration / search requesting means, and sets a search result to the statistical output target. 9. A means according to claim 1, further comprising means for performing statistical processing according to items and transmitting the statistical information to the construction information registration / search request means. Repair work management device.
【請求項10】 工費計算に必要なシステム管理定数を
その有効開始日とともに記憶するシステム管理定数記憶
手段を具備し、 前記情報入出力手段が、前記工事情報登録・検索要求手
段から送信された工事期間を示す情報に基づいて、前記
システム管理定数記憶手段から有効なシステム管理定数
を取り出す手段を有し、 前記工事情報登録・検索要求手段が、前記情報入出力手
段から送信されたシステム管理定数と前記入力装置から
入力された作業実績または作業査定に基づいて工費を算
出する手段を有することを特徴とする請求項1ないし9
のいずれか1項に記載の保修工事管理装置。
10. A system management constant storage means for storing system management constants necessary for calculation of construction cost together with the effective start date thereof, wherein said information input / output means is a construction transmitted from said construction information registration / search request means. Based on information indicating a period, the system management constant storage means has a means for extracting a valid system management constant from the storage means, the construction information registration and search request means, the system management constant transmitted from the information input and output means and 10. A device according to claim 1, further comprising means for calculating a work cost based on a work record or work evaluation input from said input device.
The maintenance work management device according to any one of the above.
【請求項11】 IDごとに使用可能な機能と使用付加
の機能を示す機能制約情報を記憶する機能制約情報記憶
手段と、 前記工事情報登録・検索要求手段から送信されたIDに
より、前記機能制約情報記憶手段から対応する機能制約
情報を読み出し、前記工事情報登録・検索要求手段に送
信するID照合手段とを具備することを特徴とする請求
項1ないし10記載の保修工事管理装置。
11. A function restriction information storage unit for storing function restriction information indicating a function usable for each ID and a function added for use, and the function restriction information stored in the construction information registration / search request unit. 11. The maintenance work management device according to claim 1, further comprising: an ID collating means for reading out the corresponding function restriction information from the information storage means and transmitting the information to the construction information registration / search request means.
【請求項12】 過去に完了した保修工事の工事情報を
記憶する工事履歴情報記憶手段を具備し、 前記情報入出力手段が、前記工事情報記憶手段に工事検
収情報まで登録され工事完了した保修工事のうち所定の
判定基準を満たした保修工事について前記工事情報記憶
手段から前記工事履歴情報記憶手段に工事情報を移動す
る手段を有することを特徴とする請求項1ないし11の
いずれか1項に記載の保修工事管理装置。
12. A maintenance work, comprising construction history information storage means for storing construction information of maintenance work completed in the past, wherein the information input / output means is registered up to construction acceptance information in the construction information storage means and the construction work is completed. 12. A maintenance work which satisfies a predetermined judgment criterion among the above, comprising means for moving construction information from the construction information storage means to the construction history information storage means. Maintenance work management equipment.
【請求項13】 プラントの設備機器の保全修理を行う
保修工事の工事情報をコンピュータを用いて管理する保
修工事管理方法において、 工事依頼入力機能を選択する信号の入力により、保修工
事の依頼を受け付ける工事依頼入力画面を表示する工程
と、 前記工事依頼入力画面に従って入力された情報に基づい
て工事依頼情報を作成する工程と、 作成された工事依頼情報を工事情報記憶手段に登録する
工程と、 工事依頼入力内容承認機能を選択する信号の入力によ
り、前記工事情報記憶手段から工事依頼情報まで登録さ
れたすべての工事を抽出し、工事依頼承認対象工事とし
て一覧表示する工程と、 一覧表示された工事依頼承認対象工事のいずれかを指定
する信号の入力により、指定された工事の依頼入力内容
を表示する工程と、 表示された工事依頼入力内容を承認する信号の入力によ
り、当該工事依頼情報の内容承認情報を前記工事情報記
憶手段に登録する工程と、 作業指示入力機能を選択する信号の入力により、前記工
事情報記憶手段から工事依頼情報の内容承認情報まで登
録されたすべての工事を抽出し、作業指示対象工事とし
て一覧表示する工程と、 一覧表示された作業指示対象工事のいずれかを指定する
信号の入力により、指定された工事の作業指示入力画面
を表示する工程と、 前記作業指示入力画面に従って入力された情報に基づい
て作業指示情報を作成する工程と、 作成された作業指示情報を対応する工事の登録情報に付
加して前記工事情報記憶手段に登録する工程と、 作業指示入力内容承認機能を選択する信号の入力によ
り、前記工事情報記憶手段から作業指示情報まで登録さ
れたすべての工事を抽出し、作業指示承認対象工事とし
て一覧表示する工程と、 一覧表示された作業指示承認対象工事のいずれかを指定
する信号の入力により、指定された工事の作業指示入力
内容を表示する工程と、 表示された作業指示入力内容を承認する信号の入力によ
り、当該作業指示情報の内容承認情報を前記工事情報記
憶手段に登録する工程と、 工事実績入力機能を選択する信号の入力により、前記工
事情報記憶手段から作業指示情報の内容承認情報まで登
録されたすべての工事を抽出し、実績入力対象工事とし
て一覧表示する工程と、 一覧表示された実績入力対象工事のいずれかを指定する
信号の入力により、指定された工事の実績入力画面を表
示する工程と、 前記工事実績入力画面に従って入力された情報に基づい
て工事実績情報を作成する工程と、 作成された工事実績情報を対応する工事の登録情報に付
加して前記工事情報記憶手段に登録する工程と、 工事実績入力内容承認機能を選択する信号の入力によ
り、前記工事情報記憶手段から工事実績情報まで登録さ
れたすべての工事を抽出し、工事実績承認対象工事とし
て一覧表示する工程と、 一覧表示された工事実績承認対象工事のいずれかを指定
する信号の入力により、指定された工事の実績入力内容
を表示する工程と、 表示された工事実績入力内容を承認する信号の入力によ
り、当該工事実績情報の内容承認情報を前記工事情報記
憶手段に登録する工程と、 工事検収入力機能を選択する信号の入力により、前記工
事情報記憶手段から工事実績情報の内容承認情報まで登
録されたすべての工事を抽出し、検収入力対象工事とし
て一覧表示する工程と、 一覧表示された検収入力対象工事のいずれかを指定する
信号の入力により、指定された工事の検収入力画面を表
示する工程と、 前記工事検収入力画面に従って入力された情報に基づい
て工事検収情報を作成する工程と、 作成された工事検収情報を対応する工事の登録情報に付
加して前記工事情報記憶手段に登録する工程と、 工事検収入力内容承認機能を選択する信号の入力によ
り、前記工事情報記憶手段から工事検収情報まで登録さ
れたすべての工事を抽出し、工事検収承認対象工事とし
て一覧表示する工程と、 一覧表示された工事検収承認対象工事のいずれかを指定
する信号の入力により、指定された工事の検収入力内容
を表示する工程と、 表示された工事検収入力内容を承認する信号の入力によ
り、当該工事検収情報の内容承認情報を前記工事情報記
憶手段に登録する工程とを含むことを特徴とする保修工
事管理方法。
13. A maintenance work management method for using a computer to manage construction information of maintenance work for performing maintenance and repair of plant equipment, wherein a maintenance work request is received by inputting a signal for selecting a construction request input function. A step of displaying a construction request input screen; a step of creating construction request information based on the information input in accordance with the construction request input screen; a step of registering the created construction request information in the construction information storage means; By inputting a signal for selecting the request input content approval function, all the works registered from the work information storage means to the work request information are extracted and listed as works to be approved for the work request. The process of displaying the request input contents of the specified construction by inputting a signal designating any of the works subject to the request approval. Registering the content approval information of the work request information in the work information storage means by inputting a signal for approving the work request input content, and inputting a signal for selecting a work instruction input function, the work information storage means From the process of extracting all the registered work from the work request information to the content approval information of the construction request information and displaying it as a work instruction target work list, and inputting a signal specifying one of the work instruction target work listed, input Displaying a work instruction input screen of the completed construction, a step of creating work instruction information based on information input according to the work instruction input screen, and converting the created work instruction information to registration information of the corresponding construction. The step of adding and registering in the construction information storage means, and the input of a signal for selecting the work instruction input content approval function, the operation from the construction information storage means is performed. The process of extracting all works registered up to the indication information and displaying them as a list of works subject to approval of work instructions, and inputting a signal specifying one of the works subject to approval of work instructions, which are listed, A step of displaying the work instruction input content, a step of registering the content approval information of the work instruction information in the construction information storage means by inputting a signal for approving the displayed work instruction input content, and a construction result input function. By inputting a signal to be selected, extracting all the works registered from the work information storage means up to the content approval information of the work instruction information, and listing the work as a result input target work, A step of displaying a result input screen of the designated construction by inputting a signal designating any of the above, and information input according to the work result input screen. A step of creating the construction result information based on: a step of adding the created construction result information to the corresponding construction registration information and registering it in the construction information storage means; By inputting, all constructions registered from the construction information storage means to construction performance information are extracted, and a process for listing and displaying the construction performance approval-targeted works or a list of construction performance approval-targeted works is designated. The process of displaying the actual work input contents of the designated construction by inputting the signal, and registering the contents approval information of the actual work information in the work information storage means by inputting the signal for approving the displayed work actual input contents And the input of a signal for selecting the construction acceptance input function, all of the registered works from the construction information storage means to the content approval information of the construction result information are registered. Extracting the matter and displaying a list as the work to be accepted for acceptance input, and displaying an acceptance input screen for the designated construction by inputting a signal designating any of the work to be entered for acceptance entered in the list, A step of creating construction acceptance information based on the information input in accordance with the construction acceptance input screen, a step of adding the created construction acceptance information to the corresponding construction registration information and registering the information in the construction information storage means, By inputting a signal to select the acceptance input content approval function, all constructions registered from the construction information storage means up to construction acceptance information are extracted, and a list is displayed as construction subject to construction acceptance approval. The process of displaying the input contents of the specified construction by inputting a signal designating any of the construction works subject to acceptance approval, and accepting the displayed contents of the construction acceptance input The input of the signal, TamotsuOsamu construction management method, which comprises a step of registering the content approval information of the construction inspection information to the construction information storage unit.
【請求項14】 工事進捗状況検索機能を選択する信号
の入力により、検索条件入力用の検索画面を表示する工
程と、 前記検索画面に従って入力された検索条件に基づいて前
記工事情報記憶手段から該当する工事の登録情報を検索
する工程と、 検索された工事の登録情報により工事進捗状況一覧を表
示する工程とを含むことを特徴とする請求項13記載の
保修工事管理方法。
14. A step of displaying a search screen for inputting a search condition by inputting a signal for selecting a construction progress status search function, and a step of displaying a search screen for inputting a search condition from the work information storage means based on the search condition input according to the search screen. 14. The maintenance work management method according to claim 13, further comprising a step of searching for registration information of the work to be performed, and a step of displaying a list of the work progress status based on the searched registration information of the work.
【請求項15】 工事依頼入力機能を選択する信号の入
力により、設備機器の保全修理の依頼を受け付ける工事
依頼入力画面を表示する工程と、 前記工事依頼入力画面に従って入力された情報に基づい
て工事依頼情報を作成する工程と、 作成された工事依頼情報を工事情報記憶手段に登録する
工程と、 工事依頼入力内容承認機能を選択する信号の入力によ
り、前記工事情報記憶手段から工事依頼情報まで登録さ
れたすべての工事を抽出し、工事依頼承認対象工事とし
て一覧表示する工程と、 一覧表示された工事依頼承認対象工事のいずれかを指定
する信号の入力により、指定された工事の依頼入力内容
を表示する工程と、 表示された工事依頼入力内容を承認する信号の入力によ
り、当該工事依頼情報の内容承認情報を前記工事情報記
憶手段に登録する工程と、 作業指示入力機能を選択する信号の入力により、前記工
事情報記憶手段から工事依頼情報の内容承認情報まで登
録されたすべての工事を抽出し、作業指示対象工事とし
て一覧表示する工程と、 一覧表示された作業指示対象工事のいずれかを指定する
信号の入力により、指定された工事の作業指示入力画面
を表示する工程と、 前記作業指示入力画面に従って入力された情報に基づい
て作業指示情報を作成する工程と、 作成された作業指示情報を対応する工事の登録情報に付
加して前記工事情報記憶手段に登録する工程と、 作業指示入力内容承認機能を選択する信号の入力によ
り、前記工事情報記憶手段から作業指示情報まで登録さ
れたすべての工事を抽出し、作業指示承認対象工事とし
て一覧表示する工程と、 一覧表示された作業指示承認対象工事のいずれかを指定
する信号の入力により、指定された工事の作業指示入力
内容を表示する工程と、 表示された作業指示入力内容を承認する信号の入力によ
り、当該作業指示情報の内容承認情報を前記工事情報記
憶手段に登録する工程と、 工事実績入力機能を選択する信号の入力により、前記工
事情報記憶手段から作業指示情報の内容承認情報まで登
録されたすべての工事を抽出し、実績入力対象工事とし
て一覧表示する工程と、 一覧表示された実績入力対象工事のいずれかを指定する
信号の入力により、指定された工事の実績入力画面を表
示する工程と、 前記工事実績入力画面に従って入力された情報に基づい
て工事実績情報を作成する工程と、 作成された工事実績情報を対応する工事の登録情報に付
加して前記工事情報記憶手段に登録する工程と、 工事実績入力内容承認機能を選択する信号の入力によ
り、前記工事情報記憶手段から工事実績情報まで登録さ
れたすべての工事を抽出し、工事実績承認対象工事とし
て一覧表示する工程と、 一覧表示された工事実績承認対象工事のいずれかを指定
する信号の入力により、指定された工事の実績入力内容
を表示する工程と、 表示された工事実績入力内容を承認する信号の入力によ
り、当該工事実績情報の内容承認情報を前記工事情報記
憶手段に登録する工程と、 工事検収入力機能を選択する信号の入力により、前記工
事情報記憶手段から工事実績情報の内容承認情報まで登
録されたすべての工事を抽出し、検収入力対象工事とし
て一覧表示する工程と、 一覧表示された検収入力対象工事のいずれかを指定する
信号の入力により、指定された工事の検収入力画面を表
示する工程と、 前記工事検収入力画面に従って入力された情報に基づい
て工事検収情報を作成する工程と、 作成された工事検収情報を対応する工事の登録情報に付
加して前記工事情報記憶手段に登録する工程と、 工事検収入力内容承認機能を選択する信号の入力によ
り、前記工事情報記憶手段から工事検収情報まで登録さ
れたすべての工事を抽出し、工事検収承認対象工事とし
て一覧表示する工程と、 一覧表示された工事検収承認対象工事のいずれかを指定
する信号の入力により、指定された工事の検収入力内容
を表示する工程と、 表示された工事検収入力内容を承認する信号の入力によ
り、当該工事検収情報の内容承認情報を前記工事情報記
憶手段に登録する工程とをコンピュータに実行させるプ
ログラムを記録した記録媒体。
15. A step of displaying a construction request input screen for accepting a request for maintenance and repair of equipment by inputting a signal for selecting a construction request input function, and performing a construction based on the information input according to the construction request input screen. A step of creating request information, a step of registering the created construction request information in the construction information storage means, and a step of inputting a signal for selecting a construction request input content approval function, thereby registering from the construction information storage means to the construction request information. By extracting all the completed works and displaying them as a list of works subject to the approval of the construction request, and by inputting a signal specifying one of the works subject to the approval of the construction request, the input contents of the specified construction The step of displaying, and the input of a signal for approving the displayed construction request input contents, the contents approval information of the construction request information is stored in the construction information storage means. A step of registering and, by inputting a signal for selecting a work instruction input function, extracting all works registered from the work information storage means up to the content approval information of the work request information, and displaying the work as a work instruction target work in a list. A step of displaying a work instruction input screen for the designated construction by inputting a signal designating any of the listed work instruction target constructions; anda work based on the information input according to the work instruction input screen. A step of creating instruction information, a step of adding the created work instruction information to the corresponding construction registration information and registering it in the construction information storage means, and inputting a signal for selecting a work instruction input content approval function, A step of extracting all the works registered from the work information storage means up to the work instruction information and displaying the work as a work instruction approval target work in a list; The process of displaying the input contents of the work instruction of the specified construction by inputting a signal designating any of the construction work subject to approval of the work instruction, and the input of the signal to approve the displayed contents of the work instruction Registering the content approval information of the instruction information in the construction information storage means, and inputting a signal for selecting a construction performance input function, whereby all the works registered from the construction information storage means to the content approval information of the work instruction information are registered. Extracting, and displaying a list as a result input target work, a step of displaying a result input screen of the designated work by inputting a signal designating any of the listed result input target works, The process of creating construction performance information based on the information entered according to the performance input screen, and adding the created construction performance information to the registration information of the corresponding construction before By registering in the construction information storage means and inputting a signal for selecting the construction result input content approval function, all the constructions registered from the construction information storage means to the construction result information are extracted, and the construction results are approved as construction result approval works. By displaying a list of processes and inputting a signal to specify any of the listed construction results approval-targeted works, a process of displaying the results of the specified work, and approving the displayed work results input A step of registering the content approval information of the construction result information in the construction information storage means by inputting a signal; and a content approval information of the construction result information from the construction information storage means by inputting a signal for selecting a construction acceptance input function. Extract all the works registered up to this point and list them as the work to be entered for acceptance. A step of displaying an acceptance input screen of the designated construction by inputting a signal to be set, a step of creating construction acceptance information based on the information input according to the construction acceptance input screen, and a step of: A step of adding the corresponding construction information to the construction information storage means and registering the construction information in the construction information storage means. A process of extracting the work and displaying it as a list of works subject to approval for construction inspection, and a process of displaying the contents of the acceptance input for the designated construction by inputting a signal that specifies one of the works subject to approval for construction acceptance. Registering the content approval information of the construction acceptance information in the construction information storage means by inputting a signal for approving the displayed construction acceptance input content. Recording medium for recording a program to be executed by Yuta.
JP13036398A 1998-05-13 1998-05-13 Repair works management device, repair works management method, and recording medium Pending JPH11324336A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13036398A JPH11324336A (en) 1998-05-13 1998-05-13 Repair works management device, repair works management method, and recording medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13036398A JPH11324336A (en) 1998-05-13 1998-05-13 Repair works management device, repair works management method, and recording medium

Publications (1)

Publication Number Publication Date
JPH11324336A true JPH11324336A (en) 1999-11-26

Family

ID=15032594

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13036398A Pending JPH11324336A (en) 1998-05-13 1998-05-13 Repair works management device, repair works management method, and recording medium

Country Status (1)

Country Link
JP (1) JPH11324336A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001344332A (en) * 2000-06-01 2001-12-14 Masaaki Kanda Work management system
JP2003016266A (en) * 2000-05-17 2003-01-17 Dainippon Printing Co Ltd Procedure system and storage medium therefor
JP2005321882A (en) * 2004-05-06 2005-11-17 Chugoku Electric Power Co Inc:The Maintenance information management method and system
JP2006040157A (en) * 2004-07-29 2006-02-09 Chugoku Electric Power Co Inc:The Repair form management system and method
JP2007011707A (en) * 2005-06-30 2007-01-18 Toyo Eng Corp Plant maintenance support system
JP2007193557A (en) * 2006-01-19 2007-08-02 Tokyo Electric Power Co Inc:The Welding inspection confirmation program, business support program, and recording medium
JP2007323303A (en) * 2006-05-31 2007-12-13 Hitachi Ltd Equipment information management support system
JP2008276452A (en) * 2007-04-27 2008-11-13 Nec Fielding Ltd Work management system, device, method and program
JP2010239731A (en) * 2009-03-31 2010-10-21 Chugoku Electric Power Co Inc:The Generation/transformation unit inspection-power outage planning support system, and planning support method of the same
JP2021026366A (en) * 2019-08-01 2021-02-22 株式会社グローバー Information processing system, information processing device, information processing method and information processing program

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08147356A (en) * 1994-11-21 1996-06-07 Toshiba Corp Maintenance management device
JPH0934946A (en) * 1995-07-18 1997-02-07 Mitsubishi Jisho Kk Facility maintenance management system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08147356A (en) * 1994-11-21 1996-06-07 Toshiba Corp Maintenance management device
JPH0934946A (en) * 1995-07-18 1997-02-07 Mitsubishi Jisho Kk Facility maintenance management system

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003016266A (en) * 2000-05-17 2003-01-17 Dainippon Printing Co Ltd Procedure system and storage medium therefor
JP4668457B2 (en) * 2000-05-17 2011-04-13 大日本印刷株式会社 Terminal device, procedure system, and storage medium therefor
JP2001344332A (en) * 2000-06-01 2001-12-14 Masaaki Kanda Work management system
JP2005321882A (en) * 2004-05-06 2005-11-17 Chugoku Electric Power Co Inc:The Maintenance information management method and system
JP2006040157A (en) * 2004-07-29 2006-02-09 Chugoku Electric Power Co Inc:The Repair form management system and method
JP2007011707A (en) * 2005-06-30 2007-01-18 Toyo Eng Corp Plant maintenance support system
JP2007193557A (en) * 2006-01-19 2007-08-02 Tokyo Electric Power Co Inc:The Welding inspection confirmation program, business support program, and recording medium
JP2007323303A (en) * 2006-05-31 2007-12-13 Hitachi Ltd Equipment information management support system
JP2008276452A (en) * 2007-04-27 2008-11-13 Nec Fielding Ltd Work management system, device, method and program
JP2010239731A (en) * 2009-03-31 2010-10-21 Chugoku Electric Power Co Inc:The Generation/transformation unit inspection-power outage planning support system, and planning support method of the same
JP2021026366A (en) * 2019-08-01 2021-02-22 株式会社グローバー Information processing system, information processing device, information processing method and information processing program

Similar Documents

Publication Publication Date Title
US20060212323A1 (en) Production management system
JP6839521B2 (en) Project progress management system
US20020046072A1 (en) Workflow system
CA2337970A1 (en) Maintenance information management system and method of providing a maintenance plan
JP2008299762A (en) Production management program
AU760109B2 (en) Method and system for efficiently transacting an order and for communicating order information between a construction contractor and a construction material supplier
JPH11324336A (en) Repair works management device, repair works management method, and recording medium
JP5086719B2 (en) Contract creation device and contract creation method
JPH10301987A (en) Building maintenance management support system and program recording medium for building maintenance management
JP5012453B2 (en) Audit system, audit method and program
JP2004054716A (en) Work management method and display method for work
CA2331192A1 (en) Charge information processing apparatus, franchise system provided the charge information processing apparatus, charge calculating method, recording medium, and program
JP2016045819A (en) Business result management system and computer program
EP1229474A2 (en) Method and system for providing information pertaining to secondhand articles and machines via a network
JPH11316783A (en) Estimate sheet generation support system for construction maintenance management
JPH11154011A (en) Plant maintenance planning support system
JPH103499A (en) Building maintenance management support system
JP2006293866A (en) Operation method of environmental management system, and environmental management system
JP2021089497A (en) Defect management method in production field and management device thereof and management program thereof
JP2005293235A (en) Market quality problem processing support system
JP2003187069A (en) Quality problem support method and system
JP4691354B2 (en) Repair work centralized management program and repair work centralized management system
JP2006119917A (en) Process management support system, process management support method, and process management support program
JPH0896045A (en) Sales program support system
JP2001117983A (en) Cost managing device and recording medium

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040610

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060704

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20061107