JPH08261616A - Slope preparation and development method and movable slope preparation and development device employed for these methods - Google Patents

Slope preparation and development method and movable slope preparation and development device employed for these methods

Info

Publication number
JPH08261616A
JPH08261616A JP9142395A JP9142395A JPH08261616A JP H08261616 A JPH08261616 A JP H08261616A JP 9142395 A JP9142395 A JP 9142395A JP 9142395 A JP9142395 A JP 9142395A JP H08261616 A JPH08261616 A JP H08261616A
Authority
JP
Japan
Prior art keywords
snow
slope
maintenance
construction
refrigerant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP9142395A
Other languages
Japanese (ja)
Inventor
Sakae Kawahara
栄 河原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KAWAHARA KK
Original Assignee
KAWAHARA KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KAWAHARA KK filed Critical KAWAHARA KK
Priority to JP9142395A priority Critical patent/JPH08261616A/en
Publication of JPH08261616A publication Critical patent/JPH08261616A/en
Pending legal-status Critical Current

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

PURPOSE: To transport smoothly manufactured snow to a development site by storing dispersively snow under each of skiing slope preparation and development devices respectively and conveying the snow separately to a skiing slope and collecting and pressing the snow and accumulating collected or pressed snow with pressure and leveling the snow and forming a skiing slope having a proper thickness. CONSTITUTION: A manufactured amount of snow is computed based on consideration of a skiing slope development scope and weather conditions of a skiing development site (ST1). Based on the computed amount of manufactured snow, the number of skiing slope preparation and development devices to be brought in the skiing slope development site is grasped and each of the skiing slope preparation and development devices is diffusely laid out with a definite spacing beside a skiing slope development scheduled site (ST2a) and (ST2b). Each of the skiing slope preparation and development devices, which are dispersively laid out, are arranged to make snow, thereby storing the snow under each of the skiing slope preparation and development devices (ST3). The snow is separately conveyed on the slope and consolidated and pressed (S4). A proper amount of snow is accumulated dispersively and collected and pressed (ST5). The pressed snow is leveled, thereby forming a slope having a proper thickness.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、ゲレンデの造設地の地
理的、気象条件に柔軟に対応するとともに低コストにて
迅速にゲレンデの造設ないしは整備が可能なゲレンデ整
備・造設方法と、該方法の実施に用いる移設可能なゲレ
ンデ整備・造設装置に関する。
BACKGROUND OF THE INVENTION The present invention relates to a slope maintenance / construction method capable of flexibly responding to geographical and weather conditions of a slope construction site and capable of quickly constructing or maintaining the slope at low cost. , Relates to a relocatable slope maintenance / construction apparatus used for carrying out the method.

【0002】[0002]

【従来の技術】冬季レジャ−の代表であるスキ−を愛好
する人口が急増し、全国各地でスキ−場の新設、拡張が
盛んに行われている。そして、快適且つ安全にスキ−を
するには、スキ−場に一定量の積雪があることが必須要
件であるため、スキ−人口の多い都市部から遠く離れ、
冬季に、雪が多量に降雪する気象条件となる山間地にス
キ−場が設けられている。しかしながら、近年の地球温
暖化等の気象条件の変動により、これら山間地であって
も降雪量、降雪期間の減少、変動が顕著になり、スキ−
場としての機能を発揮できる期間が、年により極端に変
動したり短くなっている。このため、スキ−の愛好家を
失望させるばかりでなく、スキ−場を運営する側も経営
が脅かされる事態となっていた。
2. Description of the Related Art The number of people who love skiing, which is a representative of winter holidays, has increased rapidly, and new ski fields are being established and expanded all over the country. And in order to comfortably and safely ski, it is essential that there is a certain amount of snow in the ski field, so it is far from urban areas with large ski population,
Ski fields are set up in the mountainous areas, where the weather conditions are such that a large amount of snow falls in winter. However, due to recent changes in weather conditions such as global warming, even in these mountainous areas, the amount of snowfall and the amount of snowfall decrease and change become noticeable.
The period during which it can function as a place fluctuates extremely or shortens from year to year. This not only disappointed ski lovers, but also threatened the management of ski fields.

【0003】近年、前記した事態を解決すべく、人工的
に雪を製雪し、製雪した雪を散布等してゲレンデを整備
又は造設する、図27及び図28に示すようなA据え付
け方式のゲレンデ整備・造設装置a1、若しくは、図2
7及び図29に示すような、B据え付け方式のゲレンデ
整備・造設装置a2がスキ−場に導入されはじめてい
る。
In recent years, in order to solve the above-mentioned situation, snow is artificially made and the snow is sprayed to maintain or construct a slope. System slope maintenance / construction equipment a1 or Fig. 2
7 and FIG. 29, a B-installation type slope maintenance / construction apparatus a2 has begun to be introduced into the ski field.

【0004】図28に示すように、(イ)は、雪を人工
的に製雪するユニットであって、製雪装置収容建屋b
と、該製雪装置収容建屋b内に架台c上に横一列に配設
されて収容された複数の製雪装置dと、該複数の製雪装
置dの直下に配設された製雪側搬送コンベアeとから構
成されている。また、同図に示すように、(ロ)は、製
雪した雪を一旦貯蔵するユニットであって、前記製雪手
段収容建屋bの近くに設けられた貯雪用建屋fと、一側
を雪の受渡しが可能な製雪側搬送コンベアeの近傍位置
に他側を貯雪用建屋fの上方位置にそれぞれ配して傾斜
して設けられた貯雪側搬送スクリュウコンベアhと、該
貯雪用建屋f内に上下動可能となして設けられた雪貯蔵
高さ均一化手段iと、該貯雪用建屋fの低位置f1に前
記雪貯蔵高さ均一化手段iとクロスする方向であって一
端を該貯雪用建屋f外に突出なさしめた状態でゲ−トダ
ンパ−iaの近傍位置に設けられた貯雪側搬出スクリュ
ウコンベアjと、から構成されている。尚、前記架台b
の一側寄り下方位置に流通穴c1が設けられている。
As shown in FIG. 28, (a) is a unit for artificially making snow, and is a snowmaking device housing building b.
A plurality of snow-making devices d arranged in a horizontal row on a base c in the snow-making device housing building b, and a snow-making side provided directly below the plurality of snow-making devices d. It is composed of a conveyor e. Further, as shown in the figure, (b) is a unit for temporarily storing the snow-made snow, and is a snow-storing building f provided near the snow-making means accommodating building b and one side of the snow. In the vicinity of the snow-making side transport conveyor e capable of delivering the snow-storage side transport conveyor e, the other side is arranged above the snow-storage building f, respectively, and the snow-storage side transport screw conveyor h is inclined, and the inside of the snow storage building f is provided. And a snow storage height equalizing means i provided so as to be movable up and down, and one end of the snow storage height equalizing means i at a low position f1 of the snow storage building f in a direction crossing the snow storage height equalizing means i. It is composed of a snow storage side carry-out screw conveyor j provided in the vicinity of the gate damper ia in a state where it is not projected outside the building f. Incidentally, the mount b
A circulation hole c1 is provided at a position below one side.

【0005】さらに、図28に示すように、(ハ)は、
貯蔵された雪をスキ−滑降コ−ス側に搬送し散布するA
ユニットであって、前記貯雪用建屋fに隣接して設けら
れたエアブロ−用建屋kと、貯雪側搬出スクリュウコン
ベアjにより搬送された雪を受渡し可能な位置に受入れ
側を配置する一方、エアブロ−用建屋kの上方位置に排
出側を配置するとともに、傾斜してエアブロ−用建屋k
内に設けられたエアブロ−側搬出スクリュウコンベアm
と、該エアブロ−側搬出スクリュウコンベアmの排出側
に近接する位置に設けられた二股振り分け手段m1と、
該二股振り分け手段m1の一方の落下口の下方位置と他
方の落下口の下方位置にそれぞれ設けられた雪流通管連
絡スクリュウコンベアnと、該雪流通管連絡スクリュウ
コンベアnの一側下方位置に設けられたロ−タリバルブ
vと、該ロ−タリバルブvと連通され一側に適宜な風
量、風圧を発するブロア−pが設けられた雪流通管r
と、該雪流通管rの複数位置に適宜間隔にて設けられた
それぞれ雪散布用ホ−スsを付設した複数の分岐弁装置
tと、から構成されている。
Further, as shown in FIG. 28, (c) is
Transfer the stored snow to the ski-descent course side and spray it A
The air blower building k is provided as a unit adjacent to the snow storage building f, and the receiving side is arranged at a position where snow carried by the snow storage side carry-out screw conveyor j can be delivered, while the air blower is arranged. The discharge side is arranged above the building k, and the air blow building k is tilted.
Air blower-side unloading screw conveyor m provided inside
And a forked distribution means m1 provided at a position close to the discharge side of the air blower side discharge screw conveyor m,
A snow distribution pipe connecting screw conveyor n provided at a position below one of the drop openings and a position below the other falling opening of the forked distribution means m1, and provided at a position below one side of the snow distribution pipe connection screw conveyor n. A rotary valve v, and a snow flow pipe r provided with a blower-p communicating with the rotary valve v and having an appropriate air volume and pressure on one side.
And a plurality of branch valve devices t provided with snow-spraying hoses s that are provided at appropriate positions at a plurality of positions on the snow distribution pipe r.

【0006】図28に示すように、前記した雪を人工的
に製雪するユニット(イ)と、製雪した雪を一旦貯蔵す
るユニット(ロ)と、貯蔵された雪をスキ−滑降コ−ス
側に搬送し散布するAユニット(ハ)とからA据え付け
方式のゲレンデ整備・造設装置a1が構成されている。
As shown in FIG. 28, a unit (a) for artificially making the above-mentioned snow, a unit (b) for temporarily storing the snow-made snow, and a ski descent-coil for the stored snow. An A-installation type slope maintenance / construction apparatus a1 is constituted by the A unit (C) which is transported to the spray side and scattered.

【0007】そして、該A据え付け方式のゲレンデ整備
・造営装置a1は、次のように動作するものである。ま
ず、図示しない貯水槽に貯水された水と、フロン等の冷
媒とを複数の製雪装置dにそれぞれ供給して製雪動作な
さしめると、人工的に雪を製雪する製雪工程が実行され
多量の雪が製雪される。つぎに、製雪側搬送コンベアe
と貯雪側搬送スクリュウコンベアhを順次動作させて、
貯雪用建屋f側に製雪された雪を搬送して該貯雪用建屋
f内に連続投入する。そして、多量の雪が山盛で貯雪さ
れぬよう、貯雪高さ均一化手段iを動作なさして、該多
量の雪を、水平状態で貯雪用建屋f内に貯雪させる。
The A-installation type slope maintenance / building apparatus a1 operates as follows. First, when water stored in a water tank (not shown) and a refrigerant such as Freon are supplied to a plurality of snow-making devices d to perform a snow-making operation, a snow-making step of artificially making snow is executed. And a lot of snow is made. Next, the snow making side conveyor e
And the snow storage side transfer screw conveyor h are sequentially operated,
The snow produced is conveyed to the snow storage building f side and continuously put into the snow storage building f. Then, in order to prevent a large amount of snow from being stored in the mountain heap, the snow storage height equalizing means i is operated to store the large amount of snow in the horizontal state in the snow storage building f.

【0008】ついで、図28に示すように、貯雪側排出
スクリュウコンベアjとエアブロ−側搬出スクリュウコ
ンベアmとを順次動作させる。すると、貯雪された人工
雪は貯雪用建屋f外へ搬出される。そして、該搬出され
た人工雪は、エアブロ−側搬出スクリュウコンベアmに
よりエアブロ−建屋k内の上方空間に搬送された後、二
股振り分け手段m1により振り分けられて、一方の雪流
通連絡スクリュウコンベアnと他方の雪流通連絡スクリ
ュウコンベアnに落下する。この後、該雪流通連絡スク
リュウコンベアnを動作させると、搬出された雪は、ロ
−タリバルブv側に搬送される。
Then, as shown in FIG. 28, the snow storage side discharge screw conveyor j and the air blower side discharge screw conveyor m are sequentially operated. Then, the stored artificial snow is carried out of the snow storage building f. Then, the carried-out artificial snow is carried to the upper space in the air blower building k by the air blower-side carry-out screw conveyor m, and then distributed by the forked distribution means m1 to one of the snow distribution communication screw conveyors n. It falls on the other snow distribution contact screw conveyor n. After that, when the snow distribution communication screw conveyor n is operated, the carried-out snow is carried to the rotary valve v side.

【0009】つぎに、図27及び図28に示すように、
ブロア−pを動作させて適宜な風量、風圧を生起なさし
めるとともにロ−タリバルブvを動作させると、人工雪
は、雪流通管r中を搬送されスキ−滑降コ−ス側に移動
する。そして、該雪流通管rと連通する複数の分岐弁装
置tを介して複数の雪散布用ホ−スsからゲレンデ造設
予定地x1又は整備対象ゲレンデx2上に人工雪をそれ
ぞれ散布して複数の人工雪集積小山yを現出なさしめ
る。この後、複数の該人工雪集積小山yそれぞれを突き
崩してならす等して、スロ−プを形成することにより、
ゲレンデを造設、或いは、整備するのである。
Next, as shown in FIGS. 27 and 28,
When the blower-p is operated to generate an appropriate air volume and pressure and the rotary valve v is operated, the artificial snow is conveyed through the snow distribution pipe r and moves to the ski-descent course side. Then, a plurality of snow-spraying hoses s are used to spray artificial snow onto the planned slope construction site x1 or the maintenance target slope x2 through a plurality of branch valve devices t communicating with the snow distribution pipe r. The artificial snow accumulation of Koyama y is revealed. After that, the plurality of the artificial snow accumulation hills y are each broken down and smoothed to form a slop,
Build or maintain the slopes.

【0010】この一方、図29に示すように、B据え付
け方式のゲレンデ整備・造設装置a2は、前記複数の製
雪装置dが直接前記貯雪用建屋f上に設けられた前記し
た製雪した雪を一旦貯蔵するユニット(ロ)と、つぎの
ように構成された、貯蔵された雪をスキ−滑降コ−ス側
に搬送し散布するBユニット(ニ)とから構成されてい
る。
On the other hand, as shown in FIG. 29, in the B installation type slope maintenance / building apparatus a2, the plurality of snow making apparatuses d are directly installed on the snow storage building f to make the snow. It is composed of a unit (b) for temporarily storing snow and a B unit (d) configured as follows for transporting and spraying the stored snow to the ski downhill side.

【0011】図29に示すように、該貯蔵された雪をス
キ−滑降コ−ス側に搬送し散布するBユニット(ニ)
は、前記貯雪用建屋fに隣接して設けられたエアブロ−
用長大建屋k2と、受入れ側を前記したと同様な位置に
配置する一方、排出側をエアブロ−用長大建屋k2内の
上方位置に配置するとともに、傾斜してエアブロ−用長
大建屋k2内に設けられたエアブロ−側搬出スクリュウ
コンベアm2と、該エアブロ−側搬出スクリュウコンベ
アm2の排出側の直下に設けられた排出案内部材m3
と、該排出案内部材m3の直下に設けられた前記したロ
−タリバルブvと、前記したブロア−pと、前記した雪
流通配管rと、複数の前記した分岐弁装置tと、から構
成されている。
As shown in FIG. 29, a B unit (D) for transporting and storing the stored snow to the ski-descent course side.
Is an air blower provided adjacent to the snow storage building f.
The large building for building k2 and the receiving side are arranged at the same positions as described above, while the discharging side is arranged at an upper position in the large building for air blow k2, and is inclined and provided in the large building for air blow k2. The air blower-side unloading screw conveyor m2, and a discharge guide member m3 provided immediately below the discharge side of the airblow-side unloading screw conveyor m2.
A rotary valve v provided directly below the discharge guide member m3, the blower p, the snow distribution pipe r, and a plurality of branch valve devices t. There is.

【0012】該B据え付け方式のゲレンデ整備・造設装
置a2を動作させると、複数の製雪装置dにより製雪さ
れた雪は直接、製雪し雪を一旦貯蔵するユニット(ロ)
に導かれる。つぎに、貯雪側排出スクリュウコンベアj
とエアブロ−側排出スクリュウコンベアm2とを順次動
作させる。すると、貯雪された人工雪は、貯雪用建屋f
外へ排出されてエアブロ−側搬出スクリュウコンベアm
2に受け渡され、エアブロ−用長大建屋k2内の上方空
間に搬送される。そして、該貯雪された人工雪は、排出
案内部材m3を通過してロ−タリバルブvに到達する。
When the B installation type slope maintenance / building device a2 is operated, the snow made by the plurality of snow making devices d is directly snow-made and a unit for temporarily storing the snow (b).
Be led to. Next, the snow storage side discharge screw conveyor j
And the air blower side discharge screw conveyor m2 are sequentially operated. Then, the artificial snow that has been stored will be stored in the snow storage building f.
Screw conveyor that is discharged to the outside and carried out on the air blower side
2 is delivered to the upper space in the air blower long building k2. Then, the stored artificial snow passes through the discharge guide member m3 and reaches the rotary valve v.

【0013】ついで、該ロ−タリバルブvとブロア−p
とを動作させると前記したと同様な経路を順次辿って、
人工雪は、ゲレンデ造設予定地x1又は整備対象ゲレン
デx2上に散布される。
Next, the rotary valve v and the blower p
When and are operated, the same route as described above is sequentially followed,
The artificial snow is sprayed on the planned slope construction site x1 or the maintenance target slope x2.

【0014】[0014]

【発明が解決しようとする課題】上述したように、前記
A据え付け方式のゲレンデ調整・造設装置a1は、貯雪
側搬送スクリュウコンベアh、貯雪側搬出スクリュウコ
ンベアj、エアブロ−側搬出スクリュウコンベアm、ス
クリュウコンベアn等の複数のスクリュウコンベアそれ
ぞれの搬送動作により、製雪された低温の多量の雪は、
前記した各建屋間を順次搬送するものである。この一
方、前記B据え付け方式のゲレンデ整備・造設装置a2
は、一の長大なスクリュウコンベアである貯雪側搬出ス
クリュウコンベアm2の搬送動作により製雪した雪を一
旦貯蔵するユニット(ロ)からエアブロ−用長大建屋k
2に搬送するものである。
As described above, the A-mounting type slope adjusting / constructing apparatus a1 includes a snow storage side transport screw conveyor h, a snow storage side unloading screw conveyor j, an air blower side unloading screw conveyor m, A large amount of low-temperature snow produced by the transport operation of each of the plurality of screw conveyors such as the screw conveyor n
The above-mentioned buildings are sequentially transported. On the other hand, the B installation type slope maintenance / construction device a2
Is a unit (b) for temporarily storing the snow produced by the transport operation of the snow storage side carry-out screw conveyor m2, which is one of the large screw conveyors, from the air blower large building k.
2 is to be transported.

【0015】前記搬送を継続して実行すると、図30に
示すように、搬送動作の際に、これらスクリュウコンベ
アを構成する多数の羽根zの表面z1に、一部の雪sn
が付着し凍結状態となる。しかも、一旦雪が付着しはじ
めると、搬送時間が進行するにつれて付着領域と凍結厚
みが累積的に拡大する。
When the carrying is continuously carried out, as shown in FIG. 30, during the carrying operation, a part of the snow sn is formed on the surface z1 of many blades z constituting the screw conveyor.
Adheres and becomes frozen. Moreover, once snow begins to adhere, the adhesion area and the frozen thickness cumulatively increase as the transport time advances.

【0016】係る事態となると、スクリュウコンベア内
での搬送空間spが極端に狭まったり閉塞してしまい、
羽根zの回転が妨げられ、雪の移動ができなくなり、前
記した各搬送を実行することが不能となる。このため、
ゲレンデの整備作業若しくは造設作業が中断することを
余儀なくされ、前記したA据え付け方式のゲレンデ整備
・造設装置a1、又は、B据え付け方式のゲレンデ整備
・造設装置a2を導入した目的を十分達成することがで
きない事態となった。また、該装置を導入したユ−ザ
−、該装置を納入したメ−カ−は、スクリュウコンベア
の前記した不調を治し、装置全体を再びスム−ズに動作
可能な状態になさしめるメインテナンス作業を、該装置
を設置した後にも度々なさねばならない。
In such a situation, the conveying space sp in the screw conveyor is extremely narrowed or blocked,
The rotation of the blades z is hindered, the snow cannot be moved, and it becomes impossible to perform the above-described respective conveyances. For this reason,
The maintenance work or construction work of the slope is forced to be interrupted, and the purpose of introducing the above-mentioned A installation type slope maintenance / building device a1 or B installation type slope maintenance / building device a2 is sufficiently achieved. It became impossible to do so. Further, the user who has introduced the device and the manufacturer who has delivered the device perform maintenance work for fixing the above-mentioned malfunction of the screw conveyor and putting the entire device in a smooth operable state again. , Often after installing the device.

【0017】また、安全且つ快適なスキ−の滑降を実現
するため、広大なゲレンデ上が常に適宜積雪厚みの積雪
状態となっていることが必須要件である。このため、多
量の雪を製雪し、何時でもゲレンデに散布可能な状態に
せねばならない。しかし、前記したA据え付け方式のゲ
レンデ調整・造営装置a1、B据え付け方式のゲレンデ
整備・造設装置a2は、ともに複数の製雪装置dを一か
所に集中配備して多量の雪を製雪し、製雪された雪を貯
雪用建屋f内に一旦貯蔵し、必要に応じて貯雪用建屋f
から取り出して散布する構成となっている。
Further, in order to realize safe and comfortable skiing, it is essential that the vast slope is always in a snowy state with an appropriate snowfall thickness. For this reason, a large amount of snow must be made so that it can be sprayed on the slopes at any time. However, both the A-installation type slope adjustment / building device a1 and the B-installed slope maintenance / building device a2 described above are provided with a plurality of snow-making devices d concentrated in one place. Then, the snow-made snow is temporarily stored in the snow storage building f, and if necessary, the snow storage building f is stored.
It is designed to be taken out from and sprayed.

【0018】このため、基礎工事を要する製雪装置収容
建屋b、貯雪用建屋f、エアブロ−用建屋k等の建屋の
建設が必要であって、また、これら建屋間を連絡する貯
雪側搬送スクリュアコンベアh等のスクリュウコンベア
の設置も必須となる。係る設置態様から、必然的に装置
設置のコストが嵩むことが避けられず、初期投資が大き
くなり、係る装置普及の妨げとなるものであった。
Therefore, it is necessary to construct a building such as a snow making device housing building b, a snow storage building f, an air blow building k, etc., which requires foundation work, and the snow-storing side transport screw for connecting these buildings to each other. It is also essential to install a screw conveyor such as the conveyor h. Due to such an installation mode, the cost of installing the device is inevitably inevitable, the initial investment becomes large, and the spread of the device is hindered.

【0019】本発明は前記した事情に鑑み、製雪された
雪が常にスム−ズにゲレンデ造設地若しくは整備地に輸
送され、しかも、安価にゲレンデを人工的に整備・造設
可能な方法、及び、該方法の実行に用いる装置を提供す
ることを目的とする。
In view of the above-mentioned circumstances, the present invention is a method in which snow-made snow is always smoothly transported to a slope construction site or a maintenance site, and at the same time, the slope can be artificially maintained / constructed at a low cost. It is also an object of the present invention to provide an apparatus used for carrying out the method.

【0020】[0020]

【課題を解決するための手段】前記目的を達成するた
め、本発明が講じた解決手段は、以下の如くである。請
求項(1)及び請求項(2)の発明にあっては、雪を製
雪する装置を移設可能とし、該装置を必要量の雪を製雪
可能な台数だけ搬送してゲレンデ造設予定地、又は、整
備が必要なゲレンデの脇の複数箇所にそれぞれ分散配置
する。そして、分散配置された各装置を個別に動作させ
製雪とともに直下に分散貯雪した後、分散貯雪された雪
をゲレンデ造設予定地上又は整備が必要なゲレンデ上に
搬送するとともに圧密する工程を反復実行して必要な量
の雪を分散集積圧密し、この後に、ゲレンデを造設又は
整備するようにしたものであって、製雪工程からダイレ
クトに整備・造設工程に移行可能としたものある。
Means for Solving the Problems In order to achieve the above object, the means for solving the problems of the present invention are as follows. According to the inventions of claims (1) and (2), it is possible to relocate a device for making snow, and to carry the required amount of snow by a number capable of making snow to build a slope. Disperse and arrange them on the ground or at multiple places beside the slopes that require maintenance. Then, each distributed device is operated individually to disperse and store snow directly under snow making, and then repeat the process of transporting and consolidating the dispersed and snow-stored snow on the ground where the slope is to be constructed or on the slope where maintenance is required. It is designed to disperse and consolidate the required amount of snow and then build or maintain the slopes, which allows the snowmaking process to be directly transferred to the maintenance / building process. .

【0021】具体的には、請求項(1)の発明は、オフ
シ−ズンにゲレンデの造設を開始する段階でゲレンデ造
設規模とゲレンデ造設地の気象条件を勘案して製雪量を
算出するステップ1と、その算出された製雪量に基づき
ゲレンデ造設地に搬入するゲレンデ整備・造設装置の台
数を把握し、各ゲレンデ整備・造設装置を一定間隔にて
ゲレンデ造設予定地の脇に分散配置するステップ2を予
備的に順次実行し、ついで、分散配置された各ゲレンデ
整備・造設装置を製雪動作なさしめて各ゲレンデ整備・
造設装置それぞれの直下に分散貯雪するステップ3を実
行する。
[0021] Specifically, the invention of claim (1) determines the amount of snow making in consideration of the slope construction scale and the meteorological conditions of the slope construction site at the stage of starting the construction of the slope on the off-season. Calculate the number of slope maintenance / construction equipment to be carried into the slope construction site based on the calculated step 1 and the calculated amount of snow, and plan to construct the slope maintenance / construction equipment at regular intervals. Preliminarily perform step 2 of distributive placement on the side of the ground in advance, and then perform a snow making operation on each decentralized piste maintenance / construction equipment to make each piste maintenance /
Execute step 3 for distributed snow storage directly under each of the building devices.

【0022】つぎに、分散貯雪された雪をゲレンデ造設
予定地上に個別搬送して圧密、又は、整備が必要なゲレ
ンデ上に個別搬送して圧接するステップ4を実行し、つ
いで、そのステップ3とそのステップ4を反復実行して
ゲレンデ造設予定地上に造設に必要な量の雪、又は、整
備が必要なゲレンデ上に整備に必要な量の雪を分散集積
圧密接するステップ5を実行し、しかる後に、分散集積
圧密された雪をならして適宜厚さのスロ−プを形成する
ステップ6を実行する手順からなるゲレンデ整備・造設
方法としたものである。
Next, step 4 is carried out, in which the dispersed and accumulated snow is individually conveyed to the ground on which the slope is to be constructed and compacted, or individually conveyed onto the slope requiring maintenance and pressure contact is performed, and then step 3 is carried out. And the step 4 are repeatedly executed, and step 5 is performed in which the amount of snow required for construction on the ground for which the slope is to be constructed, or the amount of snow required for maintenance on the slope that requires maintenance is dispersed and integrated. After that, the slope maintenance / construction method includes a procedure of performing step 6 of smoothing the distributed and consolidated snow to form a slop having an appropriate thickness.

【0023】一方、請求項(2)の発明は、搭載用部材
と、その搭載用部材の下側に取付けられた複数の脚部材
とから構成された架台と、その搭載用部材の一側上に設
けられた基台と、ストップ弁が付設されている場合があ
る冷媒流入口と冷媒流出口が設けられた外筒とその外筒
の内側に設けられた内筒とその内筒と外筒間に設けられ
た冷媒蒸発室とから構成され前記した基台上に取付けら
れた製雪ドラムと、前記した内筒の中心位置に相当する
前記した基台上に載置された軸受部材と、下端部がその
軸受部材と回動可能に連結されるとともに上端部が若干
前記製雪ドラムから突出なさしめて鉛直に立設された回
動軸と、その回動軸の外周に取付けられた刃物台と、前
記した内筒の内面と若干の隙間をもって対面した状態で
その刃物台の側方に脱着可能に取付けられた削り取り刃
と、その回動軸の上端寄り位置に取付けられ前記した内
筒の内面と対面なさしめた多数の散水ノズルを備えた散
水手段と、その回動軸の上端部と連動連結された駆動手
段と、前記した散水手段と連通され前記した製雪ドラム
外の前記した搭載用部材に配設された給水手段とからな
る製雪装置と、上流側端が前記した冷媒流出口と連通さ
れ配管路にストップ弁が備えられている場合がある気化
低圧冷媒輸送配管と、流入側端がその気化低圧冷媒輸送
配管の下流側端と連通された冷媒圧縮機と、上流側端が
その冷媒圧縮機の流出側端と連通された凝縮手段と、上
流側端がその凝縮手段の流出側端と下流側端が前記した
冷媒流入口とそれぞれ連通され配管路にストップ弁が備
えられている場合がある液化高圧冷媒輸送配管と、その
液化高圧冷媒輸送配管の配管路に設けられた膨張弁とか
ら構成され、前記した搭載用部材の他側上に設けられた
冷凍装置と、から構成されるゲレンデ整備・造設装置を
前提とする。
On the other hand, according to the invention of claim (2), a mount comprising a mounting member and a plurality of leg members attached to the lower side of the mounting member, and an upper side of the mounting member. A base provided on the outer cylinder, an outer cylinder provided with a refrigerant inlet and a refrigerant outlet that may be provided with a stop valve, an inner cylinder provided inside the outer cylinder, and an inner cylinder and an outer cylinder. A snow-making drum, which is composed of a refrigerant evaporation chamber provided between and is mounted on the base, and a bearing member mounted on the base, which corresponds to the center position of the inner cylinder. A rotating shaft having a lower end rotatably connected to the bearing member and an upper end slightly vertically protruding from the snowmaking drum, and a tool rest mounted on the outer periphery of the rotating shaft. And the side of the tool post while facing the inner surface of the inner cylinder with a slight gap. A shaving blade that is detachably attached, a water sprinkling means that is attached to a position near the upper end of the rotating shaft and has a large number of water spray nozzles facing the inner surface of the inner cylinder, and the upper end of the rotating shaft. A snow making device comprising a driving means connected to the water sprinkling means and a water supply means connected to the water sprinkling means and arranged on the mounting member outside the snow making drum; and the refrigerant having the upstream end described above. A vaporized low-pressure refrigerant transport pipe that is in communication with the outlet and may be provided with a stop valve in the pipeline, a refrigerant compressor whose inflow side end communicates with the downstream end of the vaporized low-pressure refrigerant transport pipe, and an upstream side A stop valve is provided in the pipe line, the end of which is connected to the outflow side end of the refrigerant compressor, and the upstream end of which is connected to the outflow side end and the downstream side end of the condensing means and the refrigerant inflow port, respectively. Liquefied high pressure cooling that may have been Slope maintenance / construction consisting of a transport pipe and an expansion valve provided in the pipeline of the liquefied high-pressure refrigerant transport pipe, and a refrigeration device provided on the other side of the mounting member described above. Assuming a device.

【0024】そして、前記した架台と、製雪装置と、冷
凍装置とが相互に連結された際に陸上輸送手段に搭載可
能な大きさと重量に形成され、前記した脚部材が長尺脚
部材であって前記した搭載用部材の冷凍装置が搭載され
ている他側の直下に偏って取付けられ、前記した製雪装
置の直下に製雪された雪の貯雪・搬送空間を現出なさし
めた、移設可能なゲレンデ調整・造設装置としたもので
ある。
Then, when the frame, the snow making device, and the refrigerating device are connected to each other, they are formed to have a size and weight that can be mounted on the land transportation means, and the leg members are long leg members. There is biased directly below the other side where the refrigeration system of the above-mentioned mounting member is mounted, and the snow storage / conveyance space of the snow produced just below the snow production system is revealed. This is a slope adjustment / construction device that can be relocated.

【0025】また、請求項(3)乃至請求項(5)の発
明にあっては、製雪された雪をゲレンデ造設予定地側、
又は、整備が必要なゲレンデ側に搬送するのを省略し、
製雪とともに雪をゲレンデ造設予定地側、又は、整備が
必要なゲレンデ側に直接散布して圧密し、製雪工程から
ダイレクトに散布・圧密工程に移行可能として必要な量
の雪を分散集積圧密するようにし、より一層迅速にゲレ
ンデの整備・造設を可能ならしめるようにしたものであ
る。尚、請求項(5)の発明にあっては、当初は製雪動
作のみとし、製雪された雪をある程度貯雪した後、散布
するようにしたものである。
Further, in the inventions of claims (3) to (5), the produced snow is used for the slope construction site side,
Or, omitting the transportation to the slope side that needs maintenance,
Along with snowmaking, the snow is sprayed directly on the slope construction site or on the slope where maintenance is required to consolidate, and the necessary amount of snow can be dispersed and accumulated as it is possible to move directly from the snowmaking process to the spraying and consolidation process. It is designed to be compacted so that the slopes can be maintained and constructed more quickly. In the invention of claim (5), only the snow making operation is initially performed, and the snow made is stored to some extent and then sprayed.

【0026】具体的には、請求項(3)の発明は、オフ
シ−ズンにゲレンデの造設を開始する場合のみ請求項
(1)記載のステップ1とステップ2を予備的に順次実
行し、つぎに、一定時間継続して各ゲレンデ整備・造設
装置を製雪動作なさしめるとともに製雪された雪をゲレ
ンデ造設予定地側、若しくは、整備が必要なゲレンデ側
に散布して分散貯雪するステップ7を実行し、ついで、
分散貯雪された雪を圧密し分散貯雪圧密するステップ8
を実行し、つぎに、そのステップ7とステップ8を反復
実行してゲレンデ造設予定地上に造設に必要な量の雪を
分散集積圧密し、又は、整備が必要なゲレンデ上に整備
に必要な量の雪を分散集積圧密するステップ9を実行
し、しかる後に、請求項(1)記載のステップ6を実行
する手順からなるゲレンデ整備・造設方法としたもので
ある。
Specifically, in the invention of claim (3), step 1 and step 2 of claim (1) are preliminarily and sequentially executed only when the construction of the slope is started in the off season. Next, for a certain period of time, each snow maintenance / construction device is operated to make snow, and the produced snow is sprayed on the slope construction site or on the slope where maintenance is required to disperse snow. Perform step 7, then
Step 8: Consolidate distributed snow and consolidate distributed snow
And then repeat Step 7 and Step 8 to disperse and consolidate the amount of snow required for construction on the ground where the slope is to be constructed, or for maintenance on the slope where maintenance is required. This is a slope maintenance / construction method including a procedure of performing step 9 of dispersing and consolidating a large amount of snow, and then performing step 6 of claim (1).

【0027】また、請求項(4)の発明は、請求項
(2)記載のゲレンデ整備・造設装置を前提とし、請求
項(2)記載の架台と、製雪装置と、冷媒装置とが相互
に連結された際に陸上輸送手段に搭載可能な大きさと重
量に形成され、また、請求項(2)記載の基台の直下に
シュ−トを設けしめる。さらに、上方側外周に開口部
が、その開口部を起点として一定角度離れた位置に送出
口がそれぞれ設けられ、その開口部が前記したシュ−ト
の下端と対面するようなしてそのシュ−トの下方位置に
配設されたケ−シングと、そのケ−シング内に配設せし
めた複数のブレ−ドがそのケ−シングの回動中心位置に
貫設された回動軸に一定角度間隔にて取付けられた回動
投射体と、内部空間が前記ブレ−ドの回動接線を包含す
るようなして前記した送出口に装着され先端に投射口が
設けられた投雪風胴と、前記した回動軸と連動連結され
た投雪用駆動手段とから構成された雪散布機構を請求項
(2)記載のゲレンデ整備・造設装置に具備せしめたも
のある。
Further, the invention of claim (4) is premised on the slope maintenance / building device of claim (2), and the mount, snow making device and refrigerant device of claim (2) are provided. It is formed to have a size and weight that can be mounted on the land transportation means when connected to each other, and a shoe is provided directly below the base stand according to claim (2). Further, an opening is provided on the outer circumference of the upper side, and a delivery port is provided at a position separated from the opening by a predetermined angle, and the opening faces the lower end of the above-mentioned shoe so that the opening is faced. And a plurality of blades arranged in the casing are disposed at a fixed angular interval on a rotation shaft penetrating at the rotation center position of the casing. A rotary projectile attached to the blade, a snow throwing wind tunnel equipped with a projection opening at the tip thereof, which is attached to the outlet so that the internal space includes the rotary tangent of the blade, and According to another aspect of the present invention, there is provided a snow spraying mechanism including a snow throwing drive unit that is interlocked with the rotating shaft.

【0028】さらに、請求項(5)の発明は、請求項
(2)記載のゲレンデ整備・造設装置を前提とし、請求
項(2)記載の架台と、製雪装置と、冷凍装置とが相互
に連結された際に陸上輸送手段に搭載可能な大きさと重
量に形成され、また、請求項(2)記載の基台の直下に
シュ−トを設けしめる。さらに、一側に受入れ口が他側
に払出口がそれぞれ設けられその受入れ口がそのシュ−
トの下端と対面してそのシュ−トの下方に水平に横設さ
れた中空の一時貯雪兼用送出案内部材と、連結部を除い
てその中空の一時貯雪兼用送出案内部材に貫入され周囲
に複数の送出羽根が一定間隔にて取付けられた送出手段
と、その送出手段の連結部と連動連結された送出用駆動
手段と、から構成された雪一時貯雪兼用送出機構と、請
求項(4)記載の開口部を前記払出口と対面なさしめて
配設された請求項(4)記載の雪散布機構とを請求項
(2)記載のゲレンデ整備・造設装置に具備せしめたも
のである。
Further, the invention of claim (5) is premised on the slope maintenance / construction apparatus of claim (2), and the mount, snow making apparatus and refrigerating apparatus of claim (2) are provided. It is formed to have a size and weight that can be mounted on the land transportation means when connected to each other, and a shoe is provided directly below the base stand according to claim (2). Further, a receiving port is provided on one side and a payout port is provided on the other side, and the receiving port is the shoe.
A hollow temporary snow storage / delivery guide member horizontally provided below the shunt so as to face the lower end of the boot, and a plurality of hollow temporary snow storage / delivery guide members are inserted around the hollow temporary snow storage / delivery guide member except for the connecting portion. 5. The snow temporary snow storage / combining delivery mechanism, comprising: delivery means in which the delivery blades are attached at a constant interval, and delivery drive means interlockingly connected to the connecting portion of the delivery means. The snow-spreading mechanism according to claim (4), which is arranged so that the opening of the device faces the outlet, is provided in the slope maintenance / construction device according to claim (2).

【0029】さらに、請求項(6)の発明にあっては、
ゲレンデ整備・造設装置を、陸上輸送手段による搬送可
能な重量と大きさの全体構成であるとともに、航空輸送
手段でも輸送可能な重量と大きさに分割可能な構成と
し、陸上輸送手段では搬送不能な奥地であっても、ま
た、設置位置を頻繁に変更する要請にも対応可能とし、
より一層機動的に移設可能ならしめたものである。
Further, in the invention of claim (6),
The slope maintenance / construction equipment has an overall structure of weight and size that can be transported by land transportation, and can also be divided into weight and size that can be transported by air transportation, and cannot be transported by land transportation. It is possible to respond to requests to change the installation position frequently, even in a remote area,
This is a move that can be moved more flexibly.

【0030】具体的には、請求項(2)、請求項
(4)、請求項(5)いずれかに記載の発明の移設可能
なゲレンデ整備・造設装置を前提とする。そして、請求
項(2)、請求項(4)、請求項(5)いずれかに記載
の架台を構成する搭載用部材上の冷媒圧縮機及び凝縮手
段配設位置と製雪装置配設位置にそれぞれ複数の水平方
向移動阻止・垂直方向脱着誘導部材が設けられるととも
に複数の吊り上げ平衡位置それぞれに吊りフック取付用
穴若しくは吊りフック取付用螺子が設けられ、請求項
(2)、請求項(4)、請求項(5)いずれかに記載の
凝縮手段と製雪装置それぞれの複数の吊り上げ平衡位置
に吊りフック取付用穴若しくは吊りフック取付用螺子が
設けられ、請求項(2)、請求項(4)、請求項(5)
いずれかに記載の冷媒流入口と冷媒流出口それぞれにス
トップ弁が付設され、請求項(2)、請求項(4)、請
求項(5)いずれかに記載の気化低圧冷媒輸送配管の配
管路にストップ弁が設けられるとともに、その気化低圧
冷媒輸送配管と請求項(2)、請求項(4)、請求項
(5)いずれかに記載の液化高圧冷媒輸送配管それぞれ
の両端に取付フランジが設けられ該取付フランジを介し
て、若しくは、それぞれの両端にクイック脱着流体継手
が設けられ該クイック脱着流体継手を介して前記した製
雪装置側、前記した凝縮手段側とそれぞれ連結され、更
に、前記した気化低圧冷媒輸送配管の配管路にバキュ−
ムポンプと接続可能な弁が、前記した液化高圧冷媒輸送
配管の凝縮手段寄りの配管路に高圧液側弁がそれぞれ設
けられた構造の移設可能なゲレンデ整備・造設装置とし
たものである。
Concretely, it is premised on the slope maintenance / construction apparatus of the invention according to any one of claims (2), (4) and (5). Then, the refrigerant compressor, the condensing means and the snow making device are arranged on the mounting member constituting the mount according to any one of claims (2), (4) and (5). Claims (2), (4), wherein a plurality of horizontal movement prevention / vertical removal guide members are provided respectively, and a plurality of suspension hook equilibrium positions are provided with suspension hook attachment holes or suspension hook attachment screws, respectively. The suspension hook mounting holes or the suspension hook mounting screws are provided at a plurality of suspension equilibrium positions of each of the condensing means and the snow making device according to any one of claims (5), (2), (4). ), Claim (5)
A stop valve is attached to each of the refrigerant inflow port and the refrigerant outflow port according to any one of claims 1 to 5, and a pipeline of the vaporized low-pressure refrigerant transportation pipe according to any one of claims (2), (4), and (5). Is provided with a stop valve, and mounting flanges are provided at both ends of the vaporized low pressure refrigerant transport pipe and the liquefied high pressure refrigerant transport pipe according to any one of claims (2), (4) and (5). The quick desorption fluid couplings are provided through the mounting flanges or at both ends of the mounting flanges, and the quick desorption fluid couplings are connected to the snow making apparatus side and the condensing means side, respectively. Vacuated low pressure refrigerant
The valve connectable to the pump is a transferable slope maintenance / construction device having a structure in which high pressure liquid side valves are respectively provided in the pipe lines near the condensation means of the liquefied high pressure refrigerant transportation pipe.

【0031】さらにまた、請求項(7)の発明にあって
は、水平でない設置位置の状況に柔軟に対応する提案で
あって、製雪装置、冷凍装置を搭載する架台にセルフ水
平誘導機能を備え、水平でない設置地面上であっても整
地工事せずに移設可能なゲレンデ整備・造設装置を迅速
に設置して、製雪動作、散布動作、若しくは、組立動作
を開始できるようにしたものである。
Furthermore, the invention of claim (7) is a proposal for flexibly responding to the situation of an installation position which is not horizontal, and has a self-horizontal guiding function on a mount for mounting a snow making device and a refrigerating device. It is equipped with a slope maintenance / construction device that can be relocated without ground preparation work even on uneven ground so that snowmaking, spraying, or assembly operations can be started. Is.

【0032】具体的には、請求項(2)、請求項
(4)、請求項(5)、請求項(6)いずれかに記載の
移設可能なゲレンデ整備・造設装置を前提とする。そし
て、これらいずれかの架台を構成する複数の長尺脚部材
若しくは中尺脚部材のうちフロント側端とリヤ側端に位
置する脚部材にアウトリガを設けしめたものである。
Specifically, it is premised on the slope maintenance / construction apparatus capable of relocation according to any one of claims (2), (4), (5) and (6). Outriggers are provided on the leg members located at the front side end and the rear side end among a plurality of long leg members or medium length leg members constituting any of these mounts.

【0033】[0033]

【作用】請求項(1)及び請求項(2)の発明の構成に
より、オフシ−ズンにゲレンデの造設を開始する段階
で、製雪された雪が融けないことを前提として、造設す
るゲレンデの規模に基づいて、造設するに要する製雪量
を算出する。つぎに、ゲレンデ造設地の気象条件を考慮
し、融雪量の大小に応じて適宜な融雪係数を採用し、追
加製雪量の大小を追加算出する。そして、先に算出した
製雪量と追加して算出された製雪量により正味製雪量を
算出する。
According to the structures of the inventions of claims (1) and (2), the slopes to be constructed on the premise that the snow made will not melt at the stage of starting the construction of the slopes in the off-season. Calculate the amount of snow making required for construction based on the scale. Next, considering the meteorological conditions of the slope construction site, an appropriate snowmelt coefficient is adopted according to the amount of snowmelt, and the amount of additional snowmaking is additionally calculated. Then, the net snow production amount is calculated from the snow production amount calculated previously and the snow production amount additionally calculated.

【0034】ついで、一つの移設可能なゲレンデ整備・
造設装置の製雪能力と算出された正味製雪量とから、ゲ
レンデの造設に要する移設可能なゲレンデ整備・造設装
置の台数を割り出す。そして、必要な台数の移設可能な
ゲレンデ整備・造設装置それぞれを陸上輸送手段に搭載
し、ゲレンデ造設予定地に輸送し、滑降コ−スから外れ
たゲレンデ造設予定地の脇に一定間隔にて分散配置す
る。
Next, one relocationable slope maintenance /
From the snow making capacity of the construction equipment and the calculated net snow production amount, the number of transferable slope maintenance / construction equipment required for construction of the slope is calculated. Then, the required number of relocating slope maintenance / construction devices were installed on the land transportation means, transported to the planned slope construction site, and at a certain interval beside the planned slope construction site off the downhill course. Distribute and arrange.

【0035】ついで、冷媒を注入して各移設可能なゲレ
ンデ整備・造設装置を製雪動作させると、冷媒圧縮機、
凝縮手段、駆動手段、及び、給水手段は略同時に動作開
始する。そして、冷媒圧縮機の動作により、冷媒は圧縮
されて高圧となり凝縮手段側に圧送される。このため、
該冷媒は放熱しつつ凝縮手段内を移動する。この後、該
冷媒は、凝縮手段側から液化高圧冷媒輸送配管に流入
し、膨張弁を通過する。すると、該冷媒は、低圧、低温
状態となり、該液化高圧冷媒輸送配管側から冷媒流入口
を通って冷媒蒸発室に流入する。この際、該冷媒は、該
冷媒蒸発室内で蒸発して気体状態となり、盛んに蒸発、
潜熱、吸熱する。
Then, by injecting the refrigerant to operate the snow-removing slope maintenance / construction apparatus, the refrigerant compressor,
The condensing means, the driving means, and the water supply means start operating at substantially the same time. Then, due to the operation of the refrigerant compressor, the refrigerant is compressed into a high pressure and is sent under pressure to the condensing means side. For this reason,
The refrigerant moves in the condensing means while radiating heat. After that, the refrigerant flows into the liquefied high-pressure refrigerant transport pipe from the condenser side and passes through the expansion valve. Then, the refrigerant is in a low pressure and low temperature state, and flows into the refrigerant evaporation chamber from the liquefied high pressure refrigerant transport pipe side through the refrigerant inflow port. At this time, the refrigerant is vaporized in the refrigerant evaporation chamber to be in a gas state, and is vigorously evaporated,
Latent heat, endotherm.

【0036】このため、駆動手段及び給水手段の動作に
より回動軸とともに回動する多数の散水用ノズルから内
筒内面に散水された水は膜状に急速凍結する。そして、
冷媒蒸発室で気体状態となった冷媒は、冷媒流出口を通
って再度冷媒圧縮機に移動し、該冷媒圧縮機で圧縮され
て高圧化された後、凝縮手段側に圧送される。
Therefore, the water sprinkled on the inner surface of the inner cylinder from a large number of water sprinkling nozzles that rotate together with the rotating shaft by the operation of the drive means and the water supply means rapidly freezes in the form of a film. And
The refrigerant in the gaseous state in the refrigerant evaporation chamber moves to the refrigerant compressor again through the refrigerant outlet, is compressed by the refrigerant compressor to have a high pressure, and then is sent to the condensing means side.

【0037】つぎに、係る冷媒の気化・液化サイクルを
反復実行しつつ、駆動手段を動作させて回動軸を回動な
さしめると、刃物台の側方に脱着可能となして取付けら
れた削り取り刃は、内筒の内面に薄く結氷した氷を削り
取る。すると、雪に近似した状態で内筒の内面から離脱
して落下する。前記した内筒の内面に対する水の散水か
ら内筒の内面に薄く結氷した氷を削り取る工程を反復実
行すると、各移設可能なゲレンデ整備・造設装置を構成
する各製雪装置直下の地上に、製雪された雪が分散貯雪
される。
Next, while repeatedly carrying out the vaporization / liquefaction cycle of the refrigerant, the driving means is operated to rotate the rotary shaft, so that the scraping tool is detachably attached to the side of the tool post. The blade scrapes off the thinly frozen ice on the inner surface of the inner cylinder. Then, in a state similar to snow, it separates from the inner surface of the inner cylinder and falls. When the step of scraping off the thinly frozen ice from the water sprinkling on the inner surface of the inner cylinder described above is repeatedly performed, on the ground directly below each snow making device constituting each removable slope maintenance / construction device, The snow produced is distributed and stored.

【0038】ついで、分散貯雪された雪を搬送手段にて
個別にゲレンデ造設予定地側、又は、整備が必要なゲレ
ンデ側に搬送した後に圧密すると、ゲレンデ造設予定地
上、又は、整備が必要なゲレンデ上に、一定間隔にて、
融け難く相互密着性能を維持した状態で分散貯雪圧密さ
れる。そして、前記した製雪、貯雪、搬送、圧密を反復
実行すると、ゲレンデ造設予定地上に造設に必要に量の
雪が、又は、整備が必要なゲレンデ上に整備に必要な量
の雪が一定間隔にて分散集積圧密される。この後、搬送
手段により分散集積圧密された雪をならすと、スロ−プ
が形成され、ゲレンデが造設、又は、整備されるのであ
る。
Next, if the distributed snow is transported individually to the slope construction planned site by the transportation means or to the slope side requiring maintenance, and then consolidated, it is necessary to carry out the slope planned construction ground or maintenance. On a slope, at regular intervals,
It is hard to melt and is compacted with distributed snow while maintaining the mutual adhesion performance. When the above-mentioned snow making, snow storage, transportation, and consolidation are repeatedly performed, the amount of snow required for construction on the ground where the slope is to be constructed, or the amount of snow required for maintenance on the slope where maintenance is required is maintained at regular intervals. It is dispersed and consolidated at. After that, when the snow which has been dispersed and integrated by the conveying means is smoothed, a slop is formed and a slope is constructed or maintained.

【0039】また、請求項(3)乃至請求項(5)の発
明の構成により、請求項(1)及び請求項(2)の発明
と同様にして、ゲレンデ造設予定地の脇に分散配置され
た複数の移設可能なゲレンデ整備・造設装置をそれぞれ
製雪動作なさしめる。そして、該移設可能なケレンデ整
備・造設装置が請求項(4)の発明の構成に係る場合に
は、前記したと同様にして製雪された雪は、シュ−ト上
を滑動落下して下端側に滑動移動する。
Further, according to the structures of the inventions of claims (3) to (5), like the inventions of claims (1) and (2), they are dispersed and arranged beside the planned slope construction site. A plurality of removable slope maintenance / construction devices that have been installed are used to perform snowmaking operations. When the transferable skeleton maintenance / construction device has the structure of the invention of claim (4), the snow produced in the same manner as described above slides down on the shoe. It slides to the lower end.

【0040】係る滑動移動と相前後して、投雪用駆動手
段を一側に動作なさしめると、ケ−シング内に内蔵され
ている回動投射体は、複数のブレ−ドが開口部から送出
口側を回動方向とする回動を開始する。この一方、製雪
された雪は、前記シュ−ト、開口部を順次経由してケ−
シング内に流入する。すると、製雪された雪は、複数の
ブレ−ドによりケ−シング内を、遠心力を作用されつつ
前記回動方向に回動搬送される。係る回動搬送により、
製雪された雪は送出口に達っし、ブレ−ドから付与され
た遠心力の作用により、回動接線方向に投射される。す
ると、該製雪された雪は、投雪風胴を通過して投射口か
らゲレンデ造設予定地上、又は、整備が必要なゲレンデ
上に散布される。
Along with the sliding movement, when the snow throwing driving means is moved to one side, the plurality of blades are opened from the opening of the rotary projection body built in the casing. The rotation with the outlet side as the rotation direction is started. On the other hand, the snow made from the snow is passed through the shoot and the opening in this order.
It flows into Sing. Then, the produced snow is rotatably conveyed in the cascading direction in the casing by a plurality of blades while a centrifugal force is applied. Due to such rotation conveyance,
The produced snow reaches the delivery port and is projected in the rotational tangential direction by the action of the centrifugal force applied from the blade. Then, the produced snow passes through the snow throwing wind tunnel and is sprayed from the projection port to the ground on which the slope is to be constructed or on the slope where maintenance is required.

【0041】そして、複数台数の移設可能なゲレンデ整
備・造設装置それぞれを、前記した製雪動作と投雪用駆
動手段の動作を継続なさしめ、前記した製雪された雪が
シュ−ト上を滑動落下する段階からゲレンデ造設予定地
上、又は、整備が必要なゲレンデ上に散布されるに至る
段階を所定時間継続して実行すると、連続して製雪され
た雪が投雪風胴から連続してゲレンデ造設予定地上、又
は、整備が必要なゲレンデ上に連続散布される。この結
果、ゲレンデ造設予定地上、又は、整備が必要なゲレン
デ上に一定間隔にて製雪された人工雪が分散貯雪され
る。つぎに、前記したと同様にして圧密して分散貯雪圧
密する。そして、製雪から分散貯雪圧密に至る動作を反
復実行すると、ゲレンデ造設予定地上、又は、整備が必
要なゲレンデ上に一定間隔にて融け難く相互密着性能を
維持した状態で分散集積圧密される。しかる後に、搬送
手段により分散集積圧密された雪をならすと、スロ−プ
が形成されゲレンデが造設、又は、整備されるのであ
る。
Then, the plurality of relocationable slope maintenance / construction devices are allowed to continue the above-mentioned snow making operation and the operation of the snow throwing driving means, so that the above-mentioned snow-made snow is put on the shoe. If the steps from sliding to falling onto the ground where the slope is to be built or spraying on the slope where maintenance is required are continuously performed for a predetermined time, continuously produced snow will continue from the snow throw wind tunnel. It will be sprayed continuously on the ground where the slopes will be built or on the slopes that need maintenance. As a result, the artificial snow made at regular intervals is distributed and stored on the ground where the slope is to be constructed or on the slope where maintenance is required. Next, in the same manner as described above, the snow is consolidated and the snow is consolidated. When the operations from snow making to distributed snow storage consolidation are repeatedly performed, it is difficult to melt at a fixed interval on the ground where the slope is to be built or on the slope where maintenance is required, and the dispersion is integrated and consolidated while maintaining the mutual adhesion performance. . After that, when the snow which has been dispersed and integrated is smoothed by the conveying means, a slop is formed and a slope is constructed or maintained.

【0042】一方、移設可能なゲレンデ整備・造設装置
が、請求項(5)の発明の構成に係る移設可能なゲレン
デ整備・造設装置である場合には、前記したと同様にし
て製雪された雪は、シュ−ト上を下端側に滑動移動した
後、受入れ口を通って一時貯雪兼用送出案内部材内に流
入する。そして、係る製雪動作のみをしばらく続行する
と、該一時貯雪兼用送出案内部材内と前記シュ−トの下
端側に製雪された雪が貯雪された状態となる。
On the other hand, when the removable slope maintenance / construction device is the removable slope maintenance / construction device according to the invention of claim (5), snow is produced in the same manner as described above. The formed snow slides on the lower end of the shoe and then flows through the receiving port into the temporary snow storage / delivery guide member. Then, if only the snow making operation is continued for a while, the snow produced in the temporary snow storage / delivery guide member and the lower end side of the shunt will be in a state of being stored.

【0043】つぎに、送出用駆動手段を動作させると、
一時貯雪兼用送出案内部材内の雪は、複数の送出羽根に
より攪拌されつつ払出口側に送り出された後、該払出口
から前記開口部を通ってケ−シング内に流入するととも
に、新たに、シュ−トの下端側に貯雪されていた雪が受
入れ口を通って一時貯雪兼用送出案内部材内に流入す
る。そして、前記した送出用駆動手段の動作と相前後し
て投雪用駆動手段を動作させると、ケ−シング内に流入
した製雪された雪は、前記したと同様ようにして、該ケ
−シング内を回動搬送された後、投雪風胴からゲレンデ
造設予定地、又は、整備が必要なゲレンデ側に散布され
る。
Next, when the sending drive means is operated,
The snow in the temporary snow storage / delivery guide member is sent to the outlet side while being agitated by a plurality of delivery blades, then flows from the outlet through the opening into the casing, and is newly replaced. -Snow accumulated on the lower end side of the gutter flows into the temporary snow accumulation and delivery guide member through the receiving port. When the snow throwing driving means is operated before or after the operation of the sending driving means, the snow-made snow that has flowed into the casing is treated in the same manner as described above. After being rotationally conveyed in the single, it is sprayed from the snow throwing wind tunnel to the slope construction site or the slope side requiring maintenance.

【0044】そして、複数台数の移設可能なゲレンデ整
備・造設装置それぞれについて、前記した製雪動作のみ
のしばしの動作、遅れて送出用駆動手段と投雪用駆動手
段を動作なさしめる動作パタ−ンを継続して実行する
と、ゲレンデ造設予定地上、又は、整備が必要なゲレン
デ上に一定間隔にて製雪された人工雪が分散貯雪され
る。つぎに、前記したと同様に圧密して分散貯雪圧密す
る。そして、前記した分散貯雪圧密までの動作を反復実
行すると、ゲレンデ造設予定地上、又は、整備対象ゲレ
ンデ上に多量の製雪された雪が分散集積圧密される。こ
の後、分散集積圧密された雪をならすと、スロ−プが形
成され、ゲレンデが造設、又は、整備されるのである。
With respect to each of the plurality of transferable slope maintenance / construction devices, the above-mentioned snow-making operation for a short time, and the operation pattern for delaying the operation of the sending drive means and the snow throwing drive means. If the operation is continued, artificial snow made at regular intervals will be distributed and stored on the ground where the slope is to be constructed or on the slope where maintenance is required. Next, it is consolidated and dispersed and snow-packed compacted as described above. When the operation up to the above-described distributed snow storage consolidation is repeatedly executed, a large amount of snow-made snow is dispersed and integrated and consolidated on the ground on which the slope is to be constructed or on the slope to be maintained. After that, when the snow that has been dispersed and consolidated is smoothed, a slop is formed, and a slope is constructed or maintained.

【0045】さらに、請求項(6)の発明の構成によ
り、液化高圧冷媒輸送配管の凝縮手段寄りの配管路に設
けられた高圧液側弁を閉じ、冷凍装置を動作させて製雪
装置の冷媒蒸発室内の冷媒を吸入すると、バキュ−ム状
態となる。この後、気化低圧冷媒輸送配管の配管路、及
び、冷媒流入口と冷媒流入口にそれぞれ付設されたスト
ップ弁を閉じる。また、気化低圧冷媒輸送配管と液化高
圧冷媒輸送配管それぞれの一端に設けられた取付フラン
ジ、若しくは、クイック脱着流体継手と冷媒流入口及び
冷媒流出口にそれぞれ付設されたストップ弁との連結を
解除し、且つ、該気化低圧冷媒輸送配管と該液化高圧冷
媒輸送配管それぞれの他端に設けられた取付フランジ、
若しくは、クイック流体脱着流体継手を取り外すと、冷
媒が空中に漏れることなく、製雪装置と冷凍装置との連
結が解除される。
Further, according to the structure of the invention of claim (6), the high pressure liquid side valve provided in the pipe passage near the condensing means of the liquefied high pressure refrigerant transportation pipe is closed, and the refrigerating device is operated to operate the refrigerant of the snow making device. When the refrigerant in the evaporation chamber is sucked, it becomes in a vacuum state. Then, the pipeline of the vaporized low-pressure refrigerant transport pipe, and the refrigerant inlet and the stop valve attached to the refrigerant inlet are closed. Also, the coupling flanges provided at one end of the vaporized low-pressure refrigerant transport pipe and the liquefied high-pressure refrigerant transport pipe, or the quick desorption fluid coupling and the stop valves respectively attached to the refrigerant inlet and the refrigerant outlet are disconnected. And a mounting flange provided at the other end of each of the vaporized low-pressure refrigerant transport pipe and the liquefied high-pressure refrigerant transport pipe,
Alternatively, when the quick fluid desorption fluid coupling is removed, the refrigerant does not leak into the air and the connection between the snow making device and the refrigerating device is released.

【0046】つぎに、吊りフックを凝縮手段上の吊りフ
ック取付用穴に挿入若しくは吊りフック取付用螺子に螺
入して取付け、ワイヤ−を介して該吊りフックを吊り上
げ手段と接続し、該吊り上げ手段を動作させる。また、
同様にして、製雪装置上に吊りフックを取付けて吊り上
げ手段を動作させる。すると、請求項(6)の発明の係
る移設可能なゲレンデ整備・造設装置は、製雪装置と、
冷凍装置を構成する冷媒圧縮機を含む凝縮手段と、冷媒
圧縮機及び凝縮手段を除く冷凍装置を搭載した架台とに
三分割され、航空輸送手段に搭載可能な重量と大きさと
なる。
Next, the hanging hook is inserted into the hanging hook mounting hole on the condensing means or screwed into the hanging hook mounting screw, and the hanging hook is connected to the lifting means through a wire to carry out the lifting. Operate the means. Also,
Similarly, a lifting hook is attached on the snow making device to operate the lifting means. Then, the transferable slope maintenance / construction device according to the invention of claim (6) is a snow-making device,
It is divided into three parts, that is, a condensing means including a refrigerant compressor that constitutes the refrigerating device and a gantry on which the refrigerating device other than the refrigerant compressor and the condensing means is mounted, and has a weight and a size that can be mounted on the air transportation means.

【0047】ついで、まず、前記したと同様にして搭載
用部材上に吊りフックを取付け、該吊りフックを、ワイ
ヤ−を介して航空輸送手段と接続する。この後、該航空
輸送手段を目的地に向けての飛翔動作と下降動作を順次
実行すると、冷媒圧縮機及び凝縮手段を除く冷凍装置を
搭載した架台は、ゲレンデ造設予定地、又は、整備対象
ゲレンデの脇の上空に空輸された後、該ゲレンデ造設予
定地、又は、該整備対象ゲレンデの脇に着地される。
Then, first, a hanging hook is attached on the mounting member in the same manner as described above, and the hanging hook is connected to the air transportation means through the wire. After that, when the flight operation toward the destination and the descending operation of the air transportation means are sequentially executed, the gantry equipped with the refrigerating device excluding the refrigerant compressor and the condensing means becomes the slope construction site or the maintenance target. After being transported by air over the side of the slope, it is landed on the slope construction site or the side of the maintenance target slope.

【0048】この後、同様にして、製雪装置を、航空輸
送手段にて前記架台の製雪装置配設位置直上まで空輸す
る。そして、該航空輸送手段を若干づつ下降動作させる
と、該製雪装置は、水平方向移動阻止・垂直方向脱着誘
導部材と会合した後、所定の配設位置上に搭載される。
また、冷媒圧縮機を含む凝縮手段を同様に航空輸送手段
にて空輸し該航空輸送手段を若干づつ下降動作させる
と、該冷媒圧縮機を含む凝縮手段も架台上の所定の配設
位置に搭載される。尚、冷媒圧縮機を含む凝縮手段を先
に航空輸送手段により空輸した後、若干づつ下降動作な
さしめて、架台上の所定位置に搭載なさしめる場合もあ
る。
Thereafter, in the same manner, the snow-making device is air-transported by the air transporting means to a position right above the snow-making device installation position of the mount. Then, when the air transportation means is moved down a little, the snow making apparatus is mounted on a predetermined arrangement position after meeting with the horizontal movement preventing / vertical detachment guiding member.
Similarly, when the condensing means including the refrigerant compressor is similarly air-transported by the air transporting means and the air transporting means is gradually lowered, the condensing means including the refrigerant compressor is also mounted at a predetermined position on the mount. To be done. In some cases, the condensing means including the refrigerant compressor is first air-transported by the air transportation means and then gradually lowered to be mounted at a predetermined position on the gantry.

【0049】ついでまた、液化高圧冷媒輸送配管と気化
低圧冷媒輸送配管それぞれの一端に設けられた取付フラ
ンジ、若しくは、クイック脱着流体継手を冷媒流入口と
冷媒流出口にそれぞれ付設されたストップ弁と連結なさ
しめて製雪装置側と接続し、且つ、他端に設けられた取
付フランジ、若しくは、クイック脱着流体継手と冷凍装
置を構成する凝縮手段側及び冷媒圧縮機側と接続する
と、三分割された移設可能なゲレンデ整備・造設装置
は、ゲレンデ造設予定地、又は、整備対象ゲレンデの脇
で再組立てされる。
Then, a mounting flange provided at one end of each of the liquefied high-pressure refrigerant transport pipe and the vaporized low-pressure refrigerant transport pipe, or a quick desorption fluid coupling is connected to a stop valve attached to each of the refrigerant inlet and the refrigerant outlet. If it is connected to the snow making device side and is also connected to the mounting flange provided at the other end or the quick desorption fluid coupling and the condensing means side and the refrigerant compressor side that constitute the refrigerating device, the transfer is divided into three parts. Possible slope maintenance / construction equipment is reassembled at the planned slope construction site or at the side of the slope to be maintained.

【0050】つぎに、冷媒流入口と冷媒流出口にそれぞ
れ付設されたストップ弁を開く。この後、気化低圧冷媒
輸送配管の配管路に設けられた弁とバキュ−ムポンプを
接続し、該バキュ−ムポンプを動作させる。すると、気
化低圧冷媒輸送配管の配管路に設けられたストップ弁に
より閉じられた気化低圧冷媒輸送配管の上流側、製雪装
置、高圧液側弁により閉じられた液化高圧冷媒輸送配管
の下流側間がバキュ−ム状態となる。
Next, the stop valves attached to the refrigerant inlet and the refrigerant outlet are opened. Then, the valve provided in the pipe line of the vaporized low-pressure refrigerant transportation pipe is connected to the vacuum pump, and the vacuum pump is operated. Then, between the upstream side of the vaporized low pressure refrigerant transport pipe closed by the stop valve provided in the pipeline of the vaporized low pressure refrigerant transport pipe, the snow making device, and the downstream side of the liquefied high pressure refrigerant transport pipe closed by the high pressure liquid side valve. Becomes a vacuum state.

【0051】ついで、バキュ−ムポンプと接続された弁
を閉じ、高圧液側弁と気化低圧冷媒輸送配管の配管路に
設けられたストップ弁を開くと、冷媒が、凝縮手段、液
化高圧冷媒輸送配管、製雪装置、気化低圧冷媒輸送配
管、冷媒圧縮機、から凝縮手段に至る経路を循環可能な
状態となり、前記した製雪、貯雪若しくは散布の各動作
が実行可能となる。
Then, the valve connected to the vacuum pump is closed, and the high-pressure liquid valve and the stop valve provided in the pipeline of the vaporized low-pressure refrigerant transport pipe are opened. The snow-making device, the vaporized low-pressure refrigerant transport pipe, the refrigerant compressor, and the condensing means can be circulated, and the snow-making, snow-storing, or spraying operations described above can be performed.

【0052】さらにまた、請求項(7)の発明の構成に
より、移設可能なゲレンデ整備・造設装置を、若干傾斜
したゲレンデ造設予定地、又は、整備対象ゲレンデの脇
の地面上に接地させると、傾斜して仮設置される。つぎ
に、フロント側端とリヤ側端の脚部材にそれぞれ設けら
れている複数のアウトリガを個別に動作させると、架台
は傾斜状態から水平状態となる。このため、製雪装置及
び冷凍装置を構成する冷媒圧縮機を含む凝縮手段は、該
架台上の所定位置に水平状態で配設され、又は、配設可
能となり、前記した製雪動作等、又は、装置の再組立を
スム−ズに実行可能となる。
Furthermore, according to the structure of the invention of claim (7), the relocatable slope maintenance / construction device is grounded on a slightly inclined slope construction site or on the ground beside the slope to be maintained. And, it will be installed with a tilt. Next, when the plurality of outriggers provided on the leg members at the front end and the rear end are individually operated, the gantry is changed from the inclined state to the horizontal state. Therefore, the condensing means including the refrigerant compressor constituting the snow making device and the refrigerating device is arranged in a horizontal state at a predetermined position on the frame, or can be arranged, and the snow making operation or the like described above, or Therefore, the reassembly of the device can be smoothly executed.

【0053】[0053]

【実施例】つぎに、本発明の好適な実施例を、図面を参
照しながら説明する。まず、請求項(1)及び請求項
(2)の発明の一実施例を説明する。図1は請求項
(1)の発明のゲレンデ整備・造設方法の一実施例をチ
ャ−ト的に示し、図2は同実施例のうちゲレンデを造設
する段階を上方から模式的に示したものである。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, preferred embodiments of the present invention will be described with reference to the drawings. First, an embodiment of the inventions of claims (1) and (2) will be described. FIG. 1 is a chart showing an embodiment of a slope maintenance / construction method according to the invention of claim (1), and FIG. 2 is a schematic diagram from above showing the step of constructing a slope in the same embodiment. It is a thing.

【0054】また、図5は請求項(2)の発明の一例に
係る移設可能なゲレンデ整備・造設装置を正面からみた
場合を示し、図6は同移設可能なゲレンデ整備・造設装
置を上方からみた場合を示し、図7は同移設可能なゲレ
ンデ整備・造設装置を構成する製雪装置を斜め前方から
みた場合を示し、図8は同製雪装置を構成する散水手段
を斜め前方から一部省略してみた場合を示し、図9は同
製雪装置の内部構造を一部断面して示し、図23は散水
手段を構成する散水皿の構造を一部断面するとともに拡
大して示したものである。
Further, FIG. 5 shows a transferable slope maintenance / construction apparatus according to an example of the invention of claim (2) viewed from the front, and FIG. 6 shows the transferable slope maintenance / construction apparatus. FIG. 7 shows the case seen from above, FIG. 7 shows the snow making apparatus which constitutes the slope maintenance / construction apparatus that can be relocated from diagonally forward, and FIG. 8 shows the water sprinkling means which constitutes the snow making apparatus diagonally forward. FIG. 9 shows a partial cross-section of the internal structure of the snow making device, and FIG. 23 shows a partial cross-section of the structure of the water spray tray constituting the water spraying means and is enlarged. It is shown.

【0055】まず、図2に示すように、ゲレンデ造設予
定地3のスロ−プ5の長さ5A、幅5B、及び、製雪さ
れた雪を堆積させる厚みから、造設規模を把握する。そ
して、製雪された雪が融雪しないことを条件として、該
造設規模を実現するのに必要な製雪量を算出する、図1
に示すST1aを実行する。
First, as shown in FIG. 2, the construction scale is grasped from the length 5A and width 5B of the slop 5 on the slope construction site 3 and the thickness of the deposited snow. . Then, on the condition that the produced snow does not melt, the snow production amount necessary to realize the construction scale is calculated.
ST1a shown in is executed.

【0056】つぎに、ゲレンデ造設予定地3の造設位置
の気象条件(造設時点での気温、風、降水確率等)から
製雪された雪が融雪される度合いを把握する。そして、
融雪される度合いが高い場合には、大きい融雪係数を適
用して、多量の追加製雪量を算出するとともに、該追加
製雪量と前記製雪量と合算して正味製雪量を算出する、
図1に示すST1bを実行する。この一方、融雪される
度合いが低い場合には、小さい融雪係数を適用して、比
較的少量の追加製雪量を算出するとともに、該追加製雪
量と前記製雪量を合算して正味製雪量を算出する、図1
に示すST1cを実行する。
Next, the degree to which the snow produced will be melted is understood from the meteorological conditions (temperature, wind, precipitation probability, etc. at the time of construction) of the construction position of the planned slope construction site 3. And
When the degree of snow melting is high, a large snow melting coefficient is applied to calculate a large amount of additional snow production, and the additional amount of snow production and the snow production amount are added to calculate the net amount of snow production. ,
ST1b shown in FIG. 1 is executed. On the other hand, when the degree of snowmelt is low, a small snowmelt coefficient is applied to calculate a relatively small amount of additional snowmaking, and the additional amount of snowmaking and the amount of snowmaking are summed to produce a net product. Figure 1 to calculate the amount of snow
ST1c shown in is executed.

【0057】前記したST1aを実行した後、ST1
b、若しくは、ST1cを順次実行することにより、請
求項(1)記載の発明のステップ1の一例であるST1
が実行されるのである。
After executing the above-mentioned ST1a, ST1
b or ST1c, which is an example of step 1 of the invention described in claim (1), by sequentially executing ST1c.
Is executed.

【0058】係るST1が実行された後、つぎのように
構成された、請求項(2)の発明の一実施例に係る移設
可能なゲレンデ整備・造設装置1がゲレンデ造設予定地
3に輸送される。すなわち、図5及び図6に示すよう
に、11は、トラック7の荷台7Aに搭載可能な大きさ
の長方形に形成され一側寄り位置に給水手段収容穴13
が穿設された搭載側部材15と、該搭載側部材15と複
数の梁部材17を介して間近に対面配設された脚側部材
19とから構成された搭載用部材である。
After the ST1 is executed, the relocatable slope maintenance / construction apparatus 1 according to one embodiment of the invention of claim (2), which is constructed as follows, is installed at the planned slope construction site 3. Be transported. That is, as shown in FIG. 5 and FIG. 6, 11 is formed in a rectangular shape having a size that can be mounted on the bed 7A of the truck 7, and the water supply means accommodating hole 13 is provided at a position closer to one side.
Is a mounting member composed of a mounting-side member 15 having a hole formed therein, and a leg-side member 19 that is closely faced with the mounting-side member 15 and a plurality of beam members 17.

【0059】図5に示すように、21は、長尺脚部材で
あって、脚側部材19の両端と一側寄りに偏った複数箇
所に、上方を該脚部材19と連結なさしめるとともに補
強部材23を介して相互に支えあって立設されている。
係る連結、立設態様により、脚側部材19の他側下方に
は貯雪・搬送空間25が現出されている。そして、該複
数の長尺脚部材21と、搭載用部材11とから本実施例
に係る架台27が構成されている。
As shown in FIG. 5, reference numeral 21 denotes a long leg member, which is connected to both ends of the leg side member 19 at a plurality of positions which are biased toward one side so that the upper side is connected to the leg member 19 and is reinforced. The members 23 are erected to support each other through the members 23.
Due to this connection and standing manner, the snow storage / transportation space 25 is exposed below the other side of the leg member 19. The plurality of long leg members 21 and the mounting member 11 constitute a pedestal 27 according to this embodiment.

【0060】図5及び図9に示すように、29は、外径
を前記搭載側部材19の幅寸法より若干小さくする一
方、内径を該外径より若干小さくするとともに、高さを
低くして形成され、内壁29a間に交差して一対のクロ
ス部材30が架設された基台である。そして、該基台2
9は、前記貯雪・搬送空間25と上方側から対面する位
置となる前記架台27上の所定位置に設けられている。
As shown in FIGS. 5 and 9, 29 has an outer diameter slightly smaller than the width dimension of the mounting side member 19, while having an inner diameter slightly smaller than the outer diameter and a lower height. It is a base on which a pair of cross members 30 are formed so as to intersect between the inner walls 29a. And the base 2
9 is provided at a predetermined position on the pedestal 27, which is a position facing the snow storage / transportation space 25 from above.

【0061】図9に示すように、31は、前記基台29
の外径より若干小さい外径の薄肉円筒形に形成されると
ともに、下方側に冷媒流入口33が、該冷媒流入口33
の上方側に冷媒流出口35がそれぞれ穿設され、カバ−
体36により覆われた本実施例に係る外筒である。尚、
該冷媒流入口33の流入側隣接位置と該冷媒流出口35
の流出側隣接位置にそれぞれストップ弁74が付設され
ている。また、該カバ−体36により前記冷媒流入口3
3、冷媒流出口35それぞれと対面する位置に装着口3
7が穿設されている。
As shown in FIG. 9, 31 is the base 29
Is formed in a thin-walled cylindrical shape having an outer diameter slightly smaller than the outer diameter of the refrigerant, and the refrigerant inlet 33 is provided on the lower side.
Refrigerant outlets 35 are formed on the upper side of the
The outer cylinder according to the present embodiment is covered with a body 36. still,
The position adjacent to the inlet side of the refrigerant inlet 33 and the refrigerant outlet 35
A stop valve 74 is attached to each of the adjacent positions on the outflow side. In addition, the refrigerant inlet port 3 is provided by the cover body 36.
3, the mounting port 3 at a position facing each of the refrigerant outlet ports 35
7 is drilled.

【0062】また、38は、外径を該外筒31の外径よ
り若干小さくして薄肉円筒形に形成され、該外筒31と
同心位置に配設された内筒である。そして、該内筒38
の係る配設により、該内筒38と前記外筒31間に前記
冷媒流入口33、冷媒流出口35とそれぞれ連通された
冷媒蒸発室39が現出されている。そして、前記した外
筒31と、内筒38と、カバ−体36とから本実施例に
係る製雪ドラム41が構成され、前記基台29上に載置
されている。
Reference numeral 38 is an inner cylinder which is formed in a thin-walled cylindrical shape having an outer diameter slightly smaller than the outer diameter of the outer cylinder 31 and is arranged concentrically with the outer cylinder 31. Then, the inner cylinder 38
With such an arrangement, a refrigerant evaporation chamber 39 communicating with the refrigerant inlet 33 and the refrigerant outlet 35 is exposed between the inner cylinder 38 and the outer cylinder 31. The outer cylinder 31, the inner cylinder 38, and the cover body 36 constitute a snowmaking drum 41 according to the present embodiment, which is placed on the base 29.

【0063】図9に示すように、43は、前記内筒38
の中心位置に相当する前記基台29の内壁29a間に架
設された一対のクロス部材30の交差部位上に設けられ
た軸受部材である。また、45は、上端部から適宜深さ
水供給穴46が設けられ、下端部が該軸受部材43と回
動可能となして連結されている一方、上端部が前記製雪
ドラム41から若干突出なさしめて鉛直に立設された回
動軸である。
As shown in FIG. 9, 43 is the inner cylinder 38.
Is a bearing member provided on an intersecting portion of a pair of cross members 30 provided between the inner walls 29a of the base 29 corresponding to the center position of. Further, 45 has an appropriate depth water supply hole 46 provided from the upper end, and the lower end is rotatably connected to the bearing member 43, while the upper end slightly projects from the snow making drum 41. It is a rotating shaft that is vertically installed.

【0064】図8及び図9に示すように、47は、該回
動軸45の外周に取付けられ、側方先端に多数の削り取
り刃49が脱着可能であるとともに前記内筒38の内壁
38aと若干の隙間(該内壁38aに後述するように氷
が結氷する時、該氷を微細に削り取り可能な隙間)を保
って対面して取付けられた刃物台である。
As shown in FIGS. 8 and 9, 47 is attached to the outer periphery of the rotary shaft 45, and a large number of shaving blades 49 can be attached to and detached from the side tips of the rotary shaft 45 and the inner wall 38a of the inner cylinder 38. It is a tool rest mounted facing each other with a slight gap (a gap that allows fine scraping of ice when ice is frozen on the inner wall 38a as described later).

【0065】図7乃至図9、及び、図23に示すよう
に、51は、短円柱形に形成され内部に放射上に複数の
水流通穴52が設けられた水中継部材であって、複数の
該水流通穴52が前記水供給穴46と連通なさしめて前
記回動軸45の上端側寄りと連結されている。また、5
3は、前記水流通穴52と連通され水中継部材51の側
方に水平に張って取付けられた複数のホ−スである。さ
らに、54は、前記内筒38より若干外径が小さいド−
ナツ状であるとともに断面U字状に形成されて貯水空間
55が現出され、前記水中継部材51の半径方向外方に
配設された散水皿である。そして、該散水皿54の内周
側壁54aに、前記複数のホ−ス53の先端が取付られ
て該貯水空間55と連通されている一方、外周側壁54
bに多数のノズル嵌入穴56が穿設されている。さらに
また、57は、多数の該ノズル嵌入穴56それぞれに嵌
入された散水用ノズルである。そして、これらから本実
施例に係る散水手段58が構成されている。
As shown in FIG. 7 to FIG. 9 and FIG. 23, reference numeral 51 denotes a water relay member formed in a short cylindrical shape and internally provided with a plurality of water circulation holes 52. The water circulation hole 52 is communicated with the water supply hole 46 and is connected to the upper end side of the rotating shaft 45. Also, 5
Reference numeral 3 denotes a plurality of hoses that are connected to the water circulation holes 52 and are horizontally attached to the side of the water relay member 51. Further, 54 is a door having an outer diameter slightly smaller than that of the inner cylinder 38.
It is a sprinkler which is formed in a nut shape and has a U-shaped cross section so that a water storage space 55 is exposed and which is arranged radially outward of the water relay member 51. The tips of the plurality of hoses 53 are attached to the inner peripheral side wall 54a of the water spray tray 54 so as to communicate with the water storage space 55, while the outer peripheral side wall 54 is formed.
A large number of nozzle fitting holes 56 are formed in b. Furthermore, 57 is a sprinkling nozzle fitted in each of the plurality of nozzle fitting holes 56. Then, from these, the water sprinkling means 58 according to the present embodiment is constituted.

【0066】図5、図6、図7及び図9に示すように、
59は、本実施例に係る駆動手段であって、前記回動軸
45の上端側寄りと連動連結されている。また、図5乃
至図7に示すように、61は、前記搭載側部材15に設
けられた前記給水手段収容穴13に設けられた給水タン
ク63と、該給水タンク63に付設された給水用ポンプ
65と、前記回動軸45の上端に設けられた前記水供給
穴46と連通された給水塔67と、一側が該水供給塔6
7と他側が前記給水タンク63と連結された水供給管6
9とから構成された給水手段である。
As shown in FIG. 5, FIG. 6, FIG. 7 and FIG.
Reference numeral 59 denotes a drive unit according to the present embodiment, which is interlocked with the upper end of the rotary shaft 45. Further, as shown in FIG. 5 to FIG. 7, 61 is a water supply tank 63 provided in the water supply means accommodating hole 13 provided in the mounting side member 15, and a water supply pump attached to the water supply tank 63. 65, a water supply tower 67 communicating with the water supply hole 46 provided at the upper end of the rotating shaft 45, and the water supply tower 6 on one side.
7 and a water supply pipe 6 whose other side is connected to the water supply tank 63
9 is a water supply means.

【0067】そして、前記した基台29と、製雪ドラム
41と、軸受部材43と、回動軸45と、削り取り刃4
9を備えた刃物台47と、散水手段58と、駆動手段5
9と、給水手段61とから本実施例に係る製雪装置71
が構成されている。係る構成の該製雪装置71は、図5
に示すように、前記貯雪・搬送空間25と上下に対面す
る前記搭載用部材11上の所定位置に設けられいる。
Then, the base 29, the snow making drum 41, the bearing member 43, the rotating shaft 45, and the scraping blade 4 described above.
A tool rest 47 provided with 9, a sprinkling means 58, and a driving means 5
9 and the water supply means 61, the snow making device 71 according to the present embodiment.
Is configured. The snow making device 71 having such a configuration is shown in FIG.
As shown in FIG. 5, it is provided at a predetermined position on the mounting member 11 which faces the snow storage / transportation space 25 vertically.

【0068】図5及び図6に示すように、73は、配管
中途に気液分離器75が配設され、且つ、該気液分離機
75の近傍位置にストップ弁74が上流側端に取付フラ
ンジ76がそれぞれ配設され、上流端側が該取付フラン
ジ76及び前記冷媒流出口35の流出側隣接位置に付設
されたストップ弁74を介して該冷媒流出口35と連通
された気化低圧冷媒輸送配管である。また、77は、流
入側が該気化低圧冷媒輸送配管73の下流端側と連通さ
れた冷媒圧縮機であって、該気化低圧冷媒輸送配管73
を介して、前記冷媒流出口35と連通されている。
As shown in FIGS. 5 and 6, a gas-liquid separator 75 is disposed in the middle of the pipe 73, and a stop valve 74 is attached to the upstream end at a position near the gas-liquid separator 75. Vaporized low-pressure refrigerant transport pipe in which flanges 76 are respectively arranged and whose upstream ends are communicated with the refrigerant outlet port 35 through a stop valve 74 attached to the attachment flange 76 and a position adjacent to the outlet side of the refrigerant outlet port 35. Is. Reference numeral 77 denotes a refrigerant compressor whose inflow side communicates with the downstream end side of the vaporized low pressure refrigerant transport pipe 73, and the vaporized low pressure refrigerant transport pipe 73
Through the refrigerant outlet port 35.

【0069】図5及び図6に示すように、79は、上流
側が前記冷媒圧縮機77の流出側と連通され周囲をラジ
エ−タ−81により囲まれ、天井部に複数の送風機83
が設けられた凝縮手段である。また、85は、上流端側
が前記凝縮手段79の流出側端と液化高圧冷媒取出手段
87を介して連通されている一方、下流側端位置に取付
フランジ76が配設され、該取付フランジ76及び前記
冷媒流入口33の流入側隣接位置に付設されたストップ
弁74を介して下流側端が該冷媒流入口33と連通され
た液化高圧冷媒輸送配管である。さらに、89は、該液
化高圧冷媒輸送配管85の上流側端間とストップ弁74
が配設された位置間に設けられた膨張弁である。
As shown in FIG. 5 and FIG. 6, the upstream side of 79 communicates with the outflow side of the refrigerant compressor 77 and is surrounded by a radiator 81, and a plurality of blowers 83 are provided on the ceiling.
Is the condensing means. The upstream end of 85 is connected to the outlet end of the condensing means 79 via the liquefied high-pressure refrigerant extracting means 87, while the mounting flange 76 is disposed at the downstream end position. The liquefied high-pressure refrigerant transport pipe has a downstream end connected to the refrigerant inlet 33 through a stop valve 74 attached to the refrigerant inlet 33 adjacent to the inlet. Further, 89 is a portion between the upstream end of the liquefied high pressure refrigerant transport pipe 85 and the stop valve 74.
Is an expansion valve provided between the positions where

【0070】前記した冷媒圧縮機77と、凝縮手段79
と、膨張弁89、及び、これらを連結する気化低圧冷媒
輸送配管73と、液化高圧冷媒輸送配管85とから請求
項(2)の発明の一実施例に係る冷凍装置91が構成さ
れている。そして、以上詳細に説明した架台27と、製
雪装置71と、冷凍装置91とから請求項(2)の発明
の一実施例に係る移設可能なゲレンデ整備・造設装置1
が構成されている。
The above-mentioned refrigerant compressor 77 and condensing means 79
The expansion valve 89, the vaporized low-pressure refrigerant transport pipe 73 connecting these, and the liquefied high-pressure refrigerant transport pipe 85 constitute a refrigeration system 91 according to an embodiment of the invention of claim (2). Then, the pedestal maintenance / construction apparatus 1 which can be relocated from the gantry 27, the snow making apparatus 71, and the refrigeration apparatus 91 described in detail above according to the embodiment of the invention of claim (2).
Is configured.

【0071】つぎに、融雪度合いの高い地にゲレンデを
造設する場合には、このように構成された移設可能なゲ
レンデ整備・造設装置1一台の製雪能力と、前記した正
味製雪量とから、所定期間内にゲレンデを造設可能な多
数の移設可能なゲレンデ整備・造設装置1を準備し、図
2に示すように、陸上輸送手段の一例であるトラック7
にそれぞれ搭載して輸送する。そして、該多数の移設可
能なゲレンデ整備・造設装置1を、造設ゲレンデ3の脇
9に沿って一定間隔にて分散配置する、図1に示す請求
項(1)の発明のステップ2の一例であるST2aを実
行する。
Next, in the case of constructing a slope on a ground with a high degree of snow melting, the snow-making capacity of one transferable slope maintenance / construction apparatus 1 thus constructed and the net snow-making described above. Based on the quantity and quantity, a large number of transferable slope maintenance / construction devices 1 capable of constructing slopes within a predetermined period are prepared, and as shown in FIG. 2, a truck 7 which is an example of land transportation means.
Mounted on each and transported. And, the step 2 of the invention of claim (1) shown in FIG. 1 in which the large number of transferable slope maintenance / construction devices 1 are distributed along the side 9 of the construction slope 3 at regular intervals. ST2a, which is an example, is executed.

【0072】この一方、融雪度合いの低い地にゲレンデ
を造設する場合には、同様にして造設ゲレンデ3の脇9
に沿って一定間隔にて少数の移設可能なゲレンデ整備・
造設装置1を分散配置する、図1に示す請求項(2)の
発明のステップ2の他の例であるST2bを実行する。
On the other hand, in the case of constructing the slope on the ground where the degree of snow melting is low, the side 9 of the slope 3 is similarly constructed.
A small number of slopes that can be relocated at regular intervals along
ST2b which is another example of step 2 of the invention of claim (2) shown in FIG. 1 in which the construction apparatuses 1 are dispersedly arranged is executed.

【0073】ついで、図5に示すように、分散配置され
た各移設可能なゲレンデ整備・造設装置1それぞれを製
雪動作させ、製雪された雪を各貯雪・搬送空間25と対
面する各地上93に落下させる。そして、係る製雪動作
を所定時間実施して、各地上93に分散貯雪して雪の落
下集積山94を現出なさしめる、請求項(1)の発明の
ステップ3の一例である、図1に示すST3を実行す
る。
Then, as shown in FIG. 5, each of the distributable slope maintenance / building devices 1 which are dispersively arranged is operated to make snow, and the snow thus made faces each snow storage / transportation space 25. Drop on top 93. 1 is an example of step 3 of the invention of claim (1) in which the snow making operation is carried out for a predetermined period of time to disperse and store snow on each ground 93 to expose the snow accumulation pile 94. ST3 shown in is executed.

【0074】図1、図2及び図5に示すように、つぎ
に、各地上93に分散貯雪された雪の落下集積山94そ
れぞれをブルド−ザ−95により、ゲレンデ造設予定地
3側方向(図2に示す矢印97方向)に押圧移動なさし
めて、ゲレンデ造設予定地3上に個別搬送した後、該ブ
ルド−ザ−95により圧密する、請求項(1)の発明の
ステップ4の一例である、図1に示すST4を実行す
る。そして、前記したST3とST4を反復実行し、ゲ
レンデ造設予定地3上に一定間隔にて複数の人工雪集積
小山99を現出なさしめ、前記正味製雪量に相当する造
設に必要な量の雪を分散集積圧密する請求項(1)の発
明のステップ5の一例である、図1に示すST5を実行
する。
As shown in FIG. 1, FIG. 2 and FIG. 5, next, the snow accumulation piles 94 of the dispersed snow accumulated on the grounds 93 are respectively moved by the bulldozer 95 toward the slope construction site 3 side. 3. An example of step 4 of the invention of claim (1), which is pressed and moved in the direction of arrow 97 (shown in FIG. 2), individually conveyed onto the slope construction site 3 and then consolidated by the bulldozer-95. ST4 shown in FIG. 1 is executed. Then, ST3 and ST4 described above are repeatedly executed to reveal a plurality of artificial snow accumulation hills 99 on the slope construction site 3 at regular intervals, which is necessary for the construction corresponding to the net snow production amount. The step ST5 shown in FIG. 1, which is an example of step 5 of the invention of claim (1), in which a certain amount of snow is dispersed and integrated is executed.

【0075】しかる後に、図2に示すように、分散集積
圧密された該人工雪集積小山99を、ブルド−ザ−95
により例えば、矢印101乃至105方向に、それぞれ
若干づつ押圧・搬送して雪をならしてスロ−プ5を形成
する、請求項(1)の発明のステップ6の一例である、
図1に示すST6を実行してゲレンデ106を造設する
のである。
Thereafter, as shown in FIG. 2, the artificial snow accumulation hills 99, which have been dispersed and integrated, are mounted on the bulldozer-95.
Is, for example, step S6 of the invention of claim (1), in which the snow is smoothed by pressing and transporting each in the directions of the arrows 101 to 105 little by little.
ST6 shown in FIG. 1 is executed to build the slope 106.

【0076】つぎに、請求項(1)及び請求項(2)の
発明の一実施例の作用について説明する。まず、ゲレン
デ造設予定地3の規模を示すスロ−プ5の長さ5A、幅
5Bをそれぞれ測定する。また、スロ−プ5に等しく製
雪された雪を堆積させることを前提として、スム−ズに
滑降可能な堆積厚みを決定する。そして、これら測定値
と決定値を掛け算すると、製雪された雪が融雪しないこ
とを条件とした、前記規模のゲレンデを造設するに必要
な製雪量が得られ、前記したST1aが実行される。
Next, the operation of one embodiment of the inventions of claims (1) and (2) will be described. First, the length 5A and the width 5B of the slop 5 showing the scale of the slope construction site 3 are measured. In addition, on the assumption that snow produced in the same manner as the slop 5 is deposited, the deposition thickness that allows smooth sliding is determined. Then, when these measured values and the determined values are multiplied, the snow-making amount necessary for constructing a slope of the above scale is obtained on condition that the snow-made snow does not melt, and ST1a described above is executed. .

【0077】つぎに、ゲレンデ造設予定地3の造設位置
が、前記した判断材料から、融雪しやすい気象条件の場
合には、製雪後の融雪量が多いことを考慮して、大きい
融雪係数を適用して、当該融雪量を補う量の追加製雪量
を算出する。この後、該追加製雪量と前記製雪量を合算
すると、融雪しやすい気象条件下での正味製雪量が得ら
れ、前記したST1bが実行される。この一方、融雪し
がたい気象条件の場合には、製雪後の融雪量が少ないこ
とを考慮し、小さい融雪係数を適用して、少ない融雪量
を補う量の追加製雪量を算出した後、該追加製雪量と前
記製雪量を合算すると、融雪しがたい気象条件下での正
味製雪量が得られ、前記したST1cが実行される。
Next, when the construction position of the planned slope construction site 3 is a climatic condition in which snow is easily melted from the above-mentioned judgment material, a large amount of snow melt is taken into consideration in consideration of the large amount of snow melt after snow production. The coefficient is applied to calculate the additional amount of snow making that is an amount that supplements the amount of snow melting. After that, when the additional snow production amount and the snow production amount are summed up, the net snow production amount under the climatic conditions in which snow is easily melted is obtained, and the above-described ST1b is executed. On the other hand, in the case of weather conditions where it is difficult to melt snow, after considering the fact that the amount of snowmelt after snowmaking is small, a small snowmelt coefficient is applied to calculate an additional amount of snowmaking to compensate for the small amount of snowmelt. When the additional snow production amount and the snow production amount are summed up, a net snow production amount under weather conditions where snow is difficult to melt is obtained, and the above-described ST1c is executed.

【0078】前記した正味製雪量を移設可能なゲレンデ
整備・造設装置1一台の製雪能力で割ると、所定期間内
にゲレンデを造設するに必要な移設可能なゲレンデ整備
・造設装置1の台数を得ることができる。そして、造設
位置が融雪しやすい気象条件下にある場合には多数台数
の、融雪しがたい気象条件下である場合には少数台数
の、それぞれ移設可能なゲレンデ整備・造設装置1が必
要となることが判明するのである。
If the above-mentioned net snow-making amount is divided by the snow-making capacity of one transferable ski maintenance / construction apparatus 1, the ski-movable ski maintenance / construction necessary for constructing the ski within a predetermined period is possible. The number of devices 1 can be obtained. A large number of slope maintenance / construction devices 1 that can be relocated are required when the construction position is in a weather condition where snow is easily melted, and a small number when the weather is in a condition where snow is difficult to melt. It turns out that

【0079】該移設可能なゲレンデ整備・造設装置1
は、トラック7に搭載可能な重量であって、前記架台2
7は、該トラック7の荷台7Aに搭載可能な大きさに形
成されていることから、該移設可能なゲレンデ整備・造
設装置1は、トラック7に搭載できる。そして、図2に
示すように、前記した決定により多数台数、若しくは、
少数台数の移設可能なゲレンデ整備・造設装置1を、ト
ラック7に搭載して反復輸送し、ゲレンデ造設予定地3
の脇9に一定間隔にて異なる位置に降ろすと、多数台
数、若しくは、少数台数の移設可能なゲレンデ整備・造
設装置1が一定間隔にて分散配置され、前記したST2
a若しくはST2bが実行される。
The slope maintenance / construction device 1 which can be relocated
Is a weight that can be mounted on the truck 7, and
Since 7 is formed to have a size that can be mounted on the bed 7A of the truck 7, the removable slope maintenance / construction apparatus 1 can be mounted on the truck 7. Then, as shown in FIG. 2, a large number of units, or
A small number of relocating slope maintenance / construction equipment 1 is mounted on a truck 7 and repeatedly transported to the planned slope construction site 3
When the plurality of or a small number of relocating slope maintenance / construction devices 1 are lowered to different positions at regular intervals on the side 9 of the vehicle, the above-mentioned ST2
a or ST2b is executed.

【0080】つぎに、図5に示すように、前記気化低圧
冷媒輸送配管73の配管路の前記した位置に配設された
ストップ弁74と、冷媒流入口33と冷媒流出口35そ
れぞれの前記した位置に付設されたストップ弁74を閉
じ、各移設可能なゲレンデ整備・造設装置1に冷媒の一
例であるフロンを気化低圧冷媒輸送配管73の下流端位
置から注入する。この後、前記した各ストップ弁74を
開状態として、冷媒圧縮機77を圧縮動作なさしめると
とともに、給水用ポンプ65、駆動手段59を略同時に
動作開始なさしめる。
Next, as shown in FIG. 5, the stop valve 74 disposed at the above-mentioned position in the pipeline of the vaporized low-pressure refrigerant transport pipe 73, the refrigerant inlet 33 and the refrigerant outlet 35, respectively. The stop valve 74 attached to the position is closed, and CFC, which is an example of the refrigerant, is injected into each of the transferable slope maintenance / construction apparatuses 1 from the downstream end position of the vaporized low pressure refrigerant transport pipe 73. After that, each of the stop valves 74 described above is opened, and the refrigerant compressor 77 is compressed, and at the same time, the water supply pump 65 and the driving means 59 are started substantially simultaneously.

【0081】冷媒圧縮機77の動作により、注入された
フロンは、加圧されて凝縮手段79に圧送される。する
と、圧送されたフロンは、凝縮手段79内で放熱しつつ
完全に液体状態となる。なお、この際、前記ラジエ−タ
−81と、複数の送風機83冷却動作により冷却効果が
発揮されるため、凝縮手段79は過度に高熱状態となら
ない。
By the operation of the refrigerant compressor 77, the injected CFC is pressurized and sent under pressure to the condensing means 79. Then, the CFC sent under pressure is completely liquefied while radiating heat in the condensing means 79. At this time, since the cooling effect is exhibited by the radiator 81 and the cooling operation of the plurality of blowers 83, the condensing means 79 is not excessively heated.

【0082】凝縮手段79により液化高圧状態となった
フロンは、液化高圧冷媒取出手段87から凝縮手段79
外に取出された後、液化高圧冷媒輸送配管85の下流
側、膨張弁89中を順次移動する。すると、液化高圧状
態のフロンは低圧状態となる。この後、該フロンは、該
液化高圧冷媒輸送配管85の上流側と冷媒流入口33を
順次輸送されて、冷凍装置91側から製雪装置71側に
輸送され、冷媒蒸発室39に流入する。すると、揮発性
の高いフロンは、該冷媒蒸発室39内で急速に気化して
吸熱作用をなす。このため、該冷媒蒸発室39と接する
内筒38は急激に冷却される。
The chlorofluorocarbon brought into the liquefied high-pressure state by the condensing means 79 is condensed from the liquefied high-pressure refrigerant extracting means 87 to the condensing means 79.
After being taken out, it is sequentially moved in the expansion valve 89 on the downstream side of the liquefied high-pressure refrigerant transport pipe 85. Then, the chlorofluorocarbon in the liquefied high pressure state is in the low pressure state. After that, the CFCs are sequentially transported through the upstream side of the liquefied high-pressure refrigerant transportation pipe 85 and the refrigerant inlet 33, are transported from the refrigeration apparatus 91 side to the snow making apparatus 71 side, and flow into the refrigerant evaporation chamber 39. Then, the volatile fluorocarbon rapidly vaporizes in the refrigerant evaporation chamber 39 and has an endothermic effect. Therefore, the inner cylinder 38 in contact with the refrigerant evaporation chamber 39 is rapidly cooled.

【0083】気化して吸熱作用をなしたフロンは、冷媒
流出口35から、気化低圧冷媒輸送配管73の上流側、
気液分離器75、気化低圧冷媒輸送配管73の下流側を
順次輸送された後、冷媒圧縮機77に送られると、フロ
ンは、該冷媒圧縮機77により加圧されて凝縮手段79
に圧送され、一サイクルの気化・液化サイクルが実行さ
れる。そして、該気化・液化サイクルが反復実行される
と、前記内筒38は氷点下まで冷却される。
The chlorofluorocarbon that has been vaporized and exerted an endothermic action flows from the refrigerant outlet port 35 to the upstream side of the vaporized low pressure refrigerant transportation pipe 73.
After being sequentially transported on the downstream side of the gas-liquid separator 75 and the vaporized low-pressure refrigerant transport pipe 73, when sent to the refrigerant compressor 77, the freon is pressurized by the refrigerant compressor 77 and the condensing means 79.
And is pressure-fed, and one cycle of vaporization / liquefaction cycle is executed. Then, when the vaporization / liquefaction cycle is repeatedly executed, the inner cylinder 38 is cooled to below the freezing point.

【0084】また、図7乃至図9、及び、図23に示す
ように、前記駆動手段59の駆動により、回動力が生起
され、該回動力は、回動軸45と散水手段58及び刃物
台47に伝達される。すると、回動軸45は、軸受手段
43により回動支持されながら製雪ドラム41を構成す
る内筒38内を回動する。また、散水用ノズル57が内
筒38の内壁38aと対面しつつ、散水手段57を構成
する散水皿54は、回動軸45とともに回動する。さら
に、刃物台47は、削り取り刃49の刃先が前記内壁3
8aと若干の隙間をもって対面しつつ回動軸45ととも
に回動する。
Further, as shown in FIGS. 7 to 9 and 23, the driving force of the driving means 59 generates a turning force, and the turning force is generated by the rotating shaft 45, the sprinkling means 58 and the tool rest. 47 is transmitted. Then, the rotating shaft 45 rotates in the inner cylinder 38 of the snow making drum 41 while being supported by the bearing means 43. Further, while the water spray nozzle 57 faces the inner wall 38 a of the inner cylinder 38, the water spray tray 54 that constitutes the water spray means 57 rotates together with the rotating shaft 45. Further, in the tool rest 47, the cutting edge of the scraping blade 49 is the inner wall 3
It rotates together with the rotating shaft 45 while facing a small gap with 8a.

【0085】さらに、図5、図6、図8、及び、図9に
示すように、前記給水用ポンプ65の動作により、給水
タンク63内に貯水された水は汲み上げられ、水供給管
69、給水塔67を順次経由して給水手段61側を流通
した後、回動を開始した回動軸45に設けられた水供給
穴46に流入する。この後、該水供給穴46と連通され
た複数の水流通穴52、ホ−ス53を順次経由して、汲
み上げられた水は、散水皿54に設けられた貯水空間5
5に流入する。この後、該水は、散水用ノズル57か
ら、該散水用ノズル57と対面する内筒38の内壁38
aに散水される。そして、散水手段58は回動軸45と
ともに内筒38内を回動しているので、該内筒38の内
壁38a全周にくまなく散水された水が降りかかった
後、下方に伝い移動するので、該内壁38aの全面が濡
れた状態となる。
Further, as shown in FIGS. 5, 6, 8, and 9, the water stored in the water supply tank 63 is pumped up by the operation of the water supply pump 65, and the water supply pipe 69, After flowing through the water supply means 61 side through the water supply tower 67 in sequence, it flows into the water supply hole 46 provided in the rotating shaft 45 that has started to rotate. Thereafter, the water pumped through the plurality of water circulation holes 52 communicating with the water supply hole 46 and the hose 53 in this order is stored in the water storage space 5 provided in the water spray tray 54.
Inflow to 5. After this, the water flows from the water spray nozzle 57 to the inner wall 38 of the inner cylinder 38 facing the water spray nozzle 57.
Water is sprinkled on a. Since the water sprinkling means 58 is rotating inside the inner cylinder 38 together with the rotating shaft 45, the sprinkling water is sprayed all over the inner wall 38a of the inner cylinder 38 and then moved downward. Therefore, the entire surface of the inner wall 38a becomes wet.

【0086】前記したフロンの気化・液化サイクルの反
復実行、回動軸45及び刃物台の回動動作、散水手段5
8の回動動作しながらの散水動作が同時に実行されるの
で、前記内筒38の内壁38a全面に氷101が結氷す
る。すると、回動軸45とともに回動している刃物台4
7に取付けられている削り取り刃49の刃先は、氷10
1と接触する。このため、該削り取り刃49は、若干づ
つ該氷101を削って雪に近似した薄片を削り取る。こ
の後、雪に近似した薄片は、貯雪・搬送空間25と対面
する地上93に落下するといった製雪動作が実行され
る。
Repeated vaporization / liquefaction cycle of CFCs described above, rotational movement of the rotary shaft 45 and the tool rest, and water sprinkling means 5
Since the water sprinkling operation while rotating 8 is simultaneously executed, the ice 101 is frozen on the entire inner wall 38a of the inner cylinder 38. Then, the tool rest 4 rotating together with the rotating shaft 45.
The edge of the shaving blade 49 attached to 7 is ice 10
Contact 1. Therefore, the shaving blade 49 shaves the ice 101 little by little to shave off a thin piece similar to snow. After that, the snow-making operation is performed in which the flakes that are similar to snow fall on the ground 93 facing the snow storage / transportation space 25.

【0087】係る製雪動作を、分散配置された各移設可
能なゲレンデ整備・造設装置1にて、所定時間継続実行
すると、図5に示すように、製雪された雪は、各貯雪・
搬送空間25と対面する地上93に連続して落下する。
このため、該地上93に雪の落下集積小山94が現出さ
れて分散貯雪され、図1に示すST3が実行される。こ
の後、搬送手段の一例であるブルド−ザ−95を、前記
貯雪・搬送空間25に進入させて該雪の落下集積小山9
4を押圧し、前記地上93側がらゲレンデ造設予定地3
側に搬送する。すると、ゲレンデ造設予定地3上に一定
間隔で雪の小山が現出する。この後、前記ブルド−ザ−
95を用いて、該雪の小山に乗り上げる操作を所定時間
実行すると、該雪の小山は圧密され、融雪しがたい状態
となされ、図1に示すST4が実行される。
When the snow-making operation is continuously executed for a predetermined time in each of the relocated movable slope maintenance / building apparatuses 1, as shown in FIG. 5, the snow-made snow is stored in each snow storage area.
It continuously drops on the ground 93 facing the transport space 25.
Therefore, the snow-falling and accumulating hills 94 appear on the ground 93, and the snow is dispersed and stored, and ST3 shown in FIG. 1 is executed. After that, a bulldozer 95, which is an example of a transporting means, is introduced into the snow storage / transportation space 25 to drop and collect the snow.
4 Press to place the slope construction site 3 on the ground 93 side
To the side. Then, snowy mountains appear on the slope construction site 3 at regular intervals. After this, the bulldozer
When the operation of riding on the snowy mound is performed for a predetermined time using 95, the snowy mound is compacted and made difficult to melt, and ST4 shown in FIG. 1 is executed.

【0088】そして、前記した各移設可能なゲレンデ整
備・造設装置1による製雪動作、貯雪動作、と、前記ブ
ルド−ザ−95による搬送動作、圧密動作を順次反復実
行する図1に示すST5を実行する。すると、図2に示
すように、圧密された雪の小山は次第に大きく成長し、
ゲレンデ造設予定地3上に、複数の人工雪集積小山99
が一定間隔にて分散集積圧密され、前記した正味製雪量
が確保されるのである。
Then, the snow-making operation and the snow-storing operation by the above-described transferable slope maintenance / building apparatus 1, the transporting operation by the bulldozer-95, and the consolidation operation are repeatedly executed in order, ST5 shown in FIG. To execute. Then, as shown in Fig. 2, the compacted snow mound gradually grows larger,
On the slope construction site 3, multiple artificial snow piles 99
Are dispersed and consolidated at regular intervals to secure the above-mentioned net snow production amount.

【0089】この後、ブルド−ザ−95により分散集積
圧密された複数の人工雪集積小山99を突き崩して、図
2に示す矢印101乃至105等の方向に押圧・搬送す
ると、複数の人工雪集積小山99が突き崩されるととも
に、圧密された雪が相互に密着されて略均等にならされ
る図1に示すST6が実行され、ゲレンデ造設予定地3
上にスロ−プ5が形成され、ゲレンデ106が造設され
る。
After that, the plurality of artificial snow piles 99, which are distributed and consolidated by the bulldozer-95, are pushed down and pushed and conveyed in the directions of arrows 101 to 105 shown in FIG. ST6 shown in FIG. 1 is executed in which the accumulated hills 99 are pushed down and the compacted snow particles are brought into close contact with each other to be approximately even, and the slope construction site 3
The slope 5 is formed on the top of the slope 5 and the slope 106 is installed.

【0090】つぎに請求項(1)の発明の変形実施例と
作用について説明する。図3は請求項(1)の発明のゲ
レンデ整備・造設方法の変形実施例をチャ−ト的に示
し、図4は同変形実施例のうちゲレンデを造設若しくは
整備する段階を上方から模式的に示したものである。
Next, a modified embodiment of the invention of claim (1) and its operation will be described. FIG. 3 is a chart showing a modified embodiment of the slope maintenance / construction method of the invention of claim (1), and FIG. 4 is a schematic view from above of the step of constructing or maintaining the slope in the variant embodiment. It is shown in the figure.

【0091】図3及び図4に示すように、スキ−シ−ズ
ンに突入し、営業用ゲレンデ108が造設されスキ−場
として営業が開始されている場合には、例えば、一日の
営業が終了した時点で、自然雪が降雪し、該営業用ゲレ
ンデ108上に積雪しているか否かにより、分散配置さ
れた複数の移設可能なゲレンデ整備・造設装置1の稼働
態様を決定する。
As shown in FIG. 3 and FIG. 4, when the ski slope 108 is rushed into and the sales slope 108 is constructed and the business is started as a skiing place, for example, one day business When the operation ends, natural snow has fallen, and the operation mode of the plurality of distributable slope maintenance / construction apparatuses 1 that are distributed is determined depending on whether or not there is snow on the commercial slope 108.

【0092】自然雪が降雪していない場合には、営業用
ゲレンデ108上のスロ−プ109には凸凹等が生じて
滑降コ−スが荒れたままの状態となる。そこで、前記し
た図1に示すST1a、ST1b、及び、ST2aなる
各手順、又は、ST1a、ST1c、及び、ST2bな
る各手順を省略し、図3に示すように、直接複数の移設
可能なゲレンデ整備・造設装置1を前記したと同様にし
て製雪動作、分散貯雪、及び、前記したと同様にして営
業用ゲレンデ108上に搬送して圧密なさしめる請求項
(1)の発明のステップ3の他の例であるST3aとス
テップ4の他の例であるST4aを順次実行する。この
後、該ST3aと該ST4aを反復実行する請求項
(1)の発明のステップ5の他の例であるST5aを実
行する。すると、該スロ−プ109上に一定間隔にて複
数の人工雪集積小丘110が分散集積圧密され、整備に
必要な量の雪が確保される。
When the natural snow is not falling, the slope 109 on the business slope 108 is uneven, and the downhill course remains rough. Therefore, the steps ST1a, ST1b, and ST2a shown in FIG. 1 or the steps ST1a, ST1c, and ST2b shown in FIG. 1 are omitted, and as shown in FIG. The step 3 of the invention of claim (1), wherein the construction apparatus 1 is operated for snow-making, distributed snow is stored in the same manner as described above, and is conveyed and compacted on the business slope 108 in the same manner as described above. ST3a as another example and ST4a as another example of step 4 are sequentially executed. After that, ST5a which is another example of step 5 of the invention of claim (1) for repeatedly executing ST3a and ST4a is executed. Then, a plurality of artificial snow accumulation hills 110 are distributed and consolidated on the slop 109 at regular intervals, and a sufficient amount of snow for maintenance is secured.

【0093】つぎに、請求項(1)記載のステップ6の
他の例であるST6bを実行し、ブルド−ザ−95によ
り、複数の人工雪集積小丘110を突き崩して、図4に
示す矢印111乃至114方向等に押圧・搬送する。す
ると、圧密された雪が相互に密着して再びスロ−プ10
9が形成され、営業用ゲレンデ108の整備が完了す
る。
Next, ST6b, which is another example of step 6 in claim (1), is executed, and the plurality of artificial snow accumulation hills 110 are knocked down by the bulldozer-95, as shown in FIG. It is pressed and conveyed in the directions of arrows 111 to 114. Then, the compacted snows are brought into close contact with each other and the slop 10 is resumed.
9 is formed, and maintenance of the ski slope 108 for business is completed.

【0094】この一方、自然雪が降雪し営業用ゲレンデ
108上に積雪している場合には、荒れた滑降コ−スは
自然雪の降雪により修復されるので、営業用ゲレンデ1
08の整備は不要となる。そこで、複数の移設可能なゲ
レンデ整備・造設装置1の効率的な稼働と、スキ−場の
営業規模の拡大をはかるべく、他の営業用ゲレンデ11
5を新たに造設することとする。
On the other hand, when natural snow is falling and is accumulated on the ski slope 108 for business, the rough downhill course is restored by the snowfall of natural snow.
The maintenance of 08 is unnecessary. Therefore, in order to efficiently operate a plurality of relocatable slope maintenance / construction equipments 1 and to expand the ski area sales scale, other sales slopes 11
5 will be newly built.

【0095】他の営業用ゲレンデ115の造設予定地
が、すでに造設されている営業用ゲレンデ108と隣接
した位置にある場合には、複数の移設可能なゲレンデ整
備・造設装置1は移設する必要はない。この一方、離れ
た位置である場合には、複数の移設可能なゲレンデ整備
・造設装置1の全部又は一部をそれぞれをトラック7に
て当該位置まで輸送した後、前記したと同様に移設す
る、請求項(1)の発明のステップ2のその他の例であ
る図3に示すST2cが実行される。
When the construction site of the other commercial slope 115 is located adjacent to the already-constructed commercial slope 108, a plurality of removable slope maintenance / construction apparatuses 1 are relocated. do not have to. On the other hand, in the case of the distant positions, all or some of the plurality of relocatable slope maintenance / building devices 1 are transported to the respective positions by the truck 7, and then relocated in the same manner as described above. Then, ST2c shown in FIG. 3, which is another example of step 2 of the invention of claim (1), is executed.

【0096】つぎに、複数の移設された、若しくは、隣
接位置であるため移設されなかった移設可能なゲレンデ
整備・造設装置1による前記したと同様の製雪動作、並
びに、貯雪動作と、フルド−ザ−95による前記したと
同様の搬送動作、並びに、圧密動作を順次なさしめる、
図3に示す、ST3b、ST4bを順次実行した後、こ
の手順を反復実行するST5bを実行すると、他の営業
用ゲレンデ115の造設予定地上に一定間隔にて複数の
人工雪集積丘117が分散集積圧密され、造設に必要な
量の雪が確保される。尚、この量は、スキ−シ−ズンに
突入しており低温であって融雪量は少なめであること、
降雪確率が高い気象条件であると考えられることから、
融雪量を補うため追加して製雪する量は少なくてよい。
Next, the same snow-making operation as described above, the snow-storing operation, and the flooding operation by the plurality of relocated or removable slope maintenance / building devices 1 which are not relocated because of the adjacent positions. -Sequentially performing the same conveying operation as described above and the consolidation operation by The-95,
When ST3b and ST4b shown in FIG. 3 are sequentially executed and then ST5b is repeated to repeat this procedure, a plurality of artificial snow accumulation hills 117 are dispersed at regular intervals on the ground on which the other business slope 115 is to be constructed. It will be consolidated and secured, and the amount of snow required for construction will be secured. It should be noted that this amount is low at the low temperature due to rushing into the skies, and the amount of snow melting is small.
Since it is considered that the weather conditions have a high probability of snowfall,
To supplement the amount of snowmelt, the amount of additional snowmaking may be small.

【0097】ついで、図4に示すように、前記したと同
様にして人工雪集積丘117を突き崩し複数方向になら
す、請求項(1)の発明のステップ6のその他の例であ
るST6bを実行すると、他の営業用ゲレンデ115が
造設されるのである。
Then, as shown in FIG. 4, ST6b, which is another example of step 6 of the invention of claim (1), in which the artificial snow accumulation hill 117 is crushed and smoothed in a plurality of directions in the same manner as described above, is executed. Then, another ski slope 115 for business is built.

【0098】尚、前記した製雪装置71は、フロン等の
冷媒を、一の冷媒流入口33からのみ流入させ、冷媒蒸
発室39内を通過させつつ該冷媒蒸発室39と接する前
記内筒38の全体に対し吸熱作用をなさしめた後、一の
冷媒流出口35からのみ流出させる構造となっている。
この構造の他、図24に示すように、冷媒蒸発室を、前
記内筒38の一部の外周を螺旋状に周回させるとともに
お椀状の断面形状に形成された多数の冷媒蒸発小室11
8により区画し、該多数の冷媒蒸発小室118それぞれ
に、冷媒分流流入口119、若しくは、冷媒分流流出口
120を設けしめる構造の製雪装置であってもよい。係
る構造の場合、冷媒分流流入口119から流入し前記内
筒38の一部の外周を螺旋状に周回移動して流通するフ
ロン等の冷媒の吸熱作用により一の冷媒蒸発小室118
と接する該内筒38の一部を冷却し冷媒分流流出口12
0から流出する冷却動作を、多数の冷媒蒸発小室118
それぞれについて実行することにより、該内筒38の全
面を冷却するのである。
In the snow making device 71, the refrigerant such as CFCs is introduced only through the one refrigerant inlet 33, passes through the inside of the refrigerant evaporation chamber 39, and contacts the refrigerant evaporation chamber 39. After the endothermic effect is given to the whole of the above, only one refrigerant outlet 35 is made to flow out.
In addition to this structure, as shown in FIG. 24, a large number of refrigerant evaporation chambers 11 each having a bowl-shaped cross-section formed by spirally encircling a part of the inner cylinder 38 around the outer circumference thereof are formed.
The snow-making apparatus may be structured such that it is divided by 8 and each of the plurality of refrigerant evaporation small chambers 118 is provided with a refrigerant distribution inlet 119 or a refrigerant distribution outlet 120. In the case of such a structure, one refrigerant evaporating small chamber 118 is generated by the endothermic action of the refrigerant such as CFC that flows from the refrigerant distribution inlet 119 and spirally moves around the outer circumference of a part of the inner cylinder 38.
The part of the inner cylinder 38 that is in contact with
The cooling operation flowing out from 0
The entire surface of the inner cylinder 38 is cooled by carrying out the processing for each of them.

【0099】つぎに、請求項(3)乃至請求項(5)の
発明の一実施例を説明する。図10は請求項(3)の発
明のゲレンデ整備・造設方法の一実施例をチャ−ト的に
示し、図11は同一実施例のうちゲレンデが造設される
段階を上方から模式的に示したものである。
Next, one embodiment of the inventions of claims (3) to (5) will be described. FIG. 10 is a chart showing an embodiment of the slope maintenance / construction method according to the invention of claim (3), and FIG. 11 is a schematic diagram showing the slope construction stage from above in the same embodiment. It is shown.

【0100】また、図14は請求項(4)の発明の一例
に係る移設可能なゲレンデ整備・造設装置を正面からみ
た場合を示し、図15は同移設可能なゲレンデ整備・造
設装置を構成する雪散布機構の一例を拡大して側方から
みた場合を示し、図16は同雪散布機構の一例を拡大す
るとともに断面して示したものである。
FIG. 14 shows a transferable slope maintenance / construction apparatus according to an example of the invention of claim (4) as seen from the front, and FIG. 15 shows the transferable slope maintenance / construction apparatus. FIG. 16 is an enlarged and cross-sectional view showing an example of the snow spraying mechanism that is enlarged and seen from the side.

【0101】さらに、図17は請求項(5)の発明の一
例に係る移設可能なゲレンデ整備・造設装置を正面から
みた場合を示し、図18は同移設可能なゲレンデ整備・
造設装置を構成する雪一時貯雪兼用送出機構の一例と該
雪一時貯雪兼用送出機構の払出口と対面して配設された
雪散布機構の一例を拡大して側方からみた場合を示し、
図19は同雪一時貯雪兼用送出機構の一例と同雪散布機
構の一例を拡大するとともに一部断面して示したもので
ある。
Further, FIG. 17 shows a case where the transferable slope maintenance / construction apparatus according to an example of the invention of claim (5) is viewed from the front, and FIG. 18 shows the transferable slope maintenance / installation device.
An example of a temporary snow storage / delivery mechanism that constitutes the construction device and an example of a snow spraying mechanism arranged facing the payout outlet of the temporary snow storage / delivery mechanism of the snow is shown in an enlarged view from the side,
FIG. 19 is an enlarged and partial cross-sectional view of an example of the temporary snow storage / delivery mechanism and the example of the snow spraying mechanism.

【0102】まず、図10に示すように、請求項(1)
の発明の実施例にて説示したと同様にして、請求項
(3)の発明の一例の最初の実行手順である、前記した
ST1aとST1b、若しくは、ST1aとST1cを
順次実行する。この後、つぎのように構成された請求項
(4)の発明の一実施例に係る移設可能なゲレンデ整備
・造設装置121をゲレンデ造設予定地3に輸送する。
First, as shown in FIG.
In the same manner as described in the embodiment of the invention of (3), ST1a and ST1b, or ST1a and ST1c, which are the first execution procedure of the example of the invention of claim (3), are sequentially executed. After that, the removable slope maintenance / construction apparatus 121 according to the embodiment of the invention of claim (4) configured as follows is transported to the slope construction planned site 3.

【0103】図14乃至図16に示すように、123
は、前記基台29の下面に取付けらたド−ナツ状取付板
125と、上方を広口の雪落下口127とする一方、下
方を狭口の雪流通口129とし、該雪落下口127が該
ド−ナツ状取付板125の内側周縁に取付けられたシュ
−トの一例である円錐形シュ−トである。
As shown in FIG. 14 to FIG.
Is a donut-shaped mounting plate 125 mounted on the lower surface of the base 29, and a wide-mouthed snow drop opening 127 on the upper side, and a narrow snow-flow opening 129 on the lower side. It is a conical shoe that is an example of a shoe attached to the inner peripheral edge of the donut-shaped attachment plate 125.

【0104】図16に示すように、133は、鉛直に立
設された直線壁部位であり、135は、略120度に渡
って円弧状に形成され一側弧状端135aが該直線壁部
位133の下端133aと連続的に一体構成された雪導
入側弧状壁部位である。
As shown in FIG. 16, reference numeral 133 denotes a vertical straight wall portion, 135 denotes an arc shape extending over approximately 120 degrees, and one side arcuate end 135a has the straight wall portion 133. Is a snow-introducing-side arcuate wall portion continuously and integrally formed with the lower end 133a.

【0105】また、137は、該雪導入側弧状壁部位1
35と同一の仮想円上に位置し、該雪導入側弧状壁部位
135と相対面して略90度に渡って円弧状に形成され
て回動投射体収容空間139を現出なさしめ、一側弧状
端137aが前記直線壁部位133の上端133bと一
定間隔(前記雪流通口129を通過する雪が溢れること
のない間隔)をあけて相対面して配設されて開口部14
1を現出なさしめ、さらに、他側弧状端137bが前記
雪導入側弧状壁部位135の他側弧状端135bと一定
角度だけ間隔があけられて送出口143を現出なさしめ
た雪迎え側弧状壁部位である。
Reference numeral 137 denotes the snow introduction side arcuate wall portion 1
Positioned on the same imaginary circle as 35 and facing the snow introducing side arcuate wall portion 135 and formed in an arc shape over an angle of about 90 degrees, the rotating projection body accommodation space 139 is exposed. The side arcuate end 137a is disposed so as to face the upper end 133b of the straight wall portion 133 with a constant space (a space where snow passing through the snow circulation port 129 does not overflow) to face each other, and the opening 14 is formed.
1, the other side arcuate end 137b is spaced from the other side arcuate end 135b of the snow introducing side arcuate wall portion 135 by a certain angle, and the sending port 143 is exposed. It is an arcuate wall part.

【0106】さらに、145は、これら各壁部位が前記
した配設により現出される直角三角形近似の突出部を付
設した円形に近似する形状に形成され、中心位置に軸穴
147が穿設された蓋体である。そして、前記直線壁部
位133と、前記雪導入側弧状壁部位135と、前記雪
迎え側弧状壁部位137と、これら壁部位の一側と他側
をそれぞれ覆う一対の蓋体145とから本実施例に係る
ケ−シング131が構成されている。
Further, 145 is formed in a shape close to a circle in which each of these wall portions is provided with a protrusion of a right-angled triangle approximated by the above-mentioned arrangement, and a shaft hole 147 is formed at the center position. It is a lid. Then, the straight wall portion 133, the snow introduction side arcuate wall portion 135, the snow welcoming side arcuate wall portion 137, and a pair of lids 145 that respectively cover one side and the other side of these wall portions are used in the present embodiment. A casing 131 according to an example is configured.

【0107】図16に示すように、149は、回動軸1
51と、該回動軸151に一定角度間隔にて取付けられ
た複数のブレ−ド153とから構成された本実施例に係
る回動投射体である。そして、複数のブレ−ド153が
取付けられた位置と隣接する回動軸151の一方の部位
と他方の部位が前記一対の蓋体145にそれぞれ穿設さ
れた軸穴147に嵌入されて、回動投射体149を構成
する複数のブレ−ド153は、前記回動投射体収容空間
139に配設されている。
As shown in FIG. 16, reference numeral 149 denotes the rotary shaft 1.
The rotary projection body according to the present embodiment is constituted by 51 and a plurality of blades 153 attached to the rotary shaft 151 at a constant angular interval. Then, one part and the other part of the rotary shaft 151 adjacent to the position where the plurality of blades 153 are attached are fitted into the shaft holes 147 formed in the pair of lids 145, respectively, and are rotated. A plurality of blades 153 forming the moving projection body 149 are arranged in the rotating projection body housing space 139.

【0108】図16に示すように、155は、投射口1
57を前記送出口143より小さく絞って長円錐形に形
成された本実施例に係る投雪風胴であって、前記ブレ−
ド153の回動接線153Aが該投雪風胴155の内部
空間155Aに位置するようにして下側端155aが該
送出口143にはめ込まれて、前記回動投射体収容空間
139と連通されている。
As shown in FIG. 16, 155 is the projection opening 1
57 is a snow throwing wind tunnel according to the present embodiment, which is formed in a long conical shape by narrowing 57 smaller than the outlet 143.
The lower end 155a is fitted into the delivery port 143 so that the rotation tangent 153A of the door 153 is located in the internal space 155A of the snow throw wind tunnel 155, and communicates with the rotation projecting body accommodating space 139. There is.

【0109】図14及び図15に示すように、159
は、本実施例に係る投雪用駆動手段であって、前記回動
軸151と連動連結されて前記複数のブレ−ド153が
前記ケ−シング131内で回動可能なよう構成されてい
る。そして、該投雪用駆動手段159は、支持部材16
0により支持されて、ケ−シング131を構成する一方
の蓋体145と対面して配設されている。
As shown in FIGS. 14 and 15, 159
Is a driving means for snow throwing according to the present embodiment, and is configured to be interlocked with the rotating shaft 151 so that the plurality of blades 153 can rotate within the casing 131. . Then, the snow throwing drive means 159 is provided in the support member 16
It is supported by 0 and is arranged so as to face one lid 145 which constitutes the casing 131.

【0110】図14、及び、図16に示すように、前記
したケ−シング131と、回動投射体149と、投雪風
胴155と、投雪用駆動手段159とから本実施例に係
る雪散布機構161が構成されている。
As shown in FIGS. 14 and 16, the casing 131, the rotary projection body 149, the snow throwing wind tunnel 155, and the snow throwing drive means 159 according to the present embodiment are used. A snow spraying mechanism 161 is configured.

【0111】図14に示すように、163は、本実施例
に係る架台であって、前記した搭載用部材11と、該搭
載用部材11と前記したようにして取付けらた複数の中
尺脚部材165とから構成されている。尚、前記した支
持部材160は、図14及び図15に示すように、一対
の中尺脚部材165間に架設された梁部材167に取付
けられている。
As shown in FIG. 14, reference numeral 163 denotes a mount according to the present embodiment, which is the mounting member 11 and a plurality of medium-sized legs attached to the mounting member 11 as described above. And a member 165. The support member 160 is attached to a beam member 167 provided between a pair of medium-sized leg members 165, as shown in FIGS. 14 and 15.

【0112】そして、図14に示すように、請求項
(2)の発明の一実施例に係る移設可能なゲレンデ整備
・造設装置1を構成する前記した製雪装置71と、冷凍
装置91と、本実施例の特徴ある構成要素である前記し
た円錐形シュ−ト123と、雪散布機構161と、架台
163とから請求項(4)の発明の一実施例に係る移設
可能なゲレンデ整備・造設装置121が構成されてい
る。
Then, as shown in FIG. 14, the snow making apparatus 71 and the refrigerating apparatus 91, which constitute the transferable slope maintenance / construction apparatus 1 according to the embodiment of the invention as defined in claim (2), are provided. The transferable slope maintenance according to the one embodiment of the invention of claim (4) from the conical shoe 123, the snow spraying mechanism 161, and the pedestal 163 which are the characteristic components of this embodiment. The building device 121 is configured.

【0113】つぎに、図10及び図11に示すように、
このように構成された移設可能なゲレンデ整備・造設装
置121を、請求項(1)の発明のステップ2の一例に
係るST2a若しくは同ステップの他の例に係るST2
bを実行して、ゲレンデ造設予定地3の脇9に沿って一
定間隔に分散配置する。
Next, as shown in FIG. 10 and FIG.
The transferable slope maintenance / construction apparatus 121 configured as described above is provided with ST2a according to an example of step 2 of the invention of claim (1) or ST2 according to another example of the step.
By executing step b, the parts are arranged at regular intervals along the side 9 of the planned slope construction site 3.

【0114】ついで、分散配置された各移設可能なゲレ
ンデ整備・造設装置121を所定時間連続して製雪動作
なさしめるととともに散布動作なさしめて、製雪された
雪をゲレンデ造設予定地3側に散布し、該ゲレンデ造設
予定地3上に一定量の雪を分散貯雪する請求項(3)の
発明のステップ7の一例である図10に示すST7aを
実行する。この後、分散貯雪された雪をブルド−ザ−9
5により圧密して分散貯雪圧密する、請求項(3)の発
明のステップ8の一例である図10に示すST8aを実
行する。
Then, each of the distributable slope maintenance / building devices 121 which can be relocated is continuously subjected to a snow making operation for a predetermined period of time and a spraying operation is also carried out, so that the snow made snow is made into the slope building planned site 3 The step ST7a shown in FIG. 10, which is an example of step 7 of the invention of claim (3), is carried out, in which a certain amount of snow is dispersed and stored on the planned slope construction site 3. After this, the snow that has been distributed and accumulated is Bulldow-the-9
The step ST8a shown in FIG. 10, which is an example of the step 8 of the invention of claim (3), is performed to perform the consolidation by the step 5 for the distributed snow storage consolidation.

【0115】つぎに、前記したST7aとST8aを反
復して順次実行し、ゲレンデ造設予定地3上に造設に必
要な量の雪を分散集積圧密させる、図10に示す請求項
(3)の発明のステップ9の一例であるST9aを実行
する。しかる後に、前記した請求項(1)の発明の最終
実施工程であるステップ6の一例に係るST6aを実行
すると、ゲレンデ造設予定地3上に計画したゲレンデが
造設されるのである。
Next, the steps ST7a and ST8a described above are repeatedly and sequentially executed to disperse and integrate the amount of snow required for construction on the slope construction site 3 (3) shown in FIG. ST9a, which is an example of step 9 of the present invention, is executed. Then, when ST6a according to an example of step 6 which is the final implementation step of the invention of claim (1) is executed, the planned slope is constructed on the planned slope construction site 3.

【0116】尚、前記した請求項(4)の発明の一実施
例に係る移設可能なゲレンデ整備・造設装置121を構
成する円錐形シュ−ト123の雪流通穴129が狭く、
雪がスム−ズに落流しない恐れがある場合には、該雪流
通穴129を前記雪落下口127より若干小さいだけの
広口とし落下口の断面積を拡張すればよい。この場合、
該雪流通穴129と対面する前記開口部141も広口と
するとともに雪迎え側弧状壁部位137が占める角度範
囲を狭くしたケ−シングとする必要がある。
Incidentally, the snow distribution hole 129 of the conical shoe 123 constituting the transferable slope maintenance / construction apparatus 121 according to the embodiment of the invention described in claim (4) is narrow,
If there is a risk that the snow will not fall into the smooths, the snow circulation hole 129 may be widened to be a little smaller than the snow drop hole 127 to expand the cross-sectional area of the drop hole. in this case,
The opening 141 facing the snow circulation hole 129 is also required to have a wide mouth and a casing in which the angle range occupied by the snow-facing side arcuate wall portion 137 is narrowed.

【0117】ゲレンデを造設するのに用いられる装置
が、請求項(5)の発明の一実施例に係る移設可能なゲ
レンデ整備・造設装置169である場合、該装置はつぎ
のように構成されているので、後述する実行手順がなさ
れる。
When the apparatus used for constructing the slope is the transferable slope maintenance / construction apparatus 169 according to the embodiment of the invention of claim (5), the apparatus is constructed as follows. Therefore, the execution procedure described later is performed.

【0118】図17乃至図19に示すように、前記基台
29の下面に、前記した取付け態様の前記ド−ナツ状取
付板体125と、上端に該ド−ナツ状取付板体125の
内側周縁と連結なさしめて雪落下口127が設けられ、
下端に前後側(図17に示す側を前側とする。)を該雪
落下口127より若干小さく左右側(図18に示す側を
右側とする。)を狭めて形成された断面長方形の長方形
雪流通口172が設けられた滑動落下案内部材173
と、から構成された広口シュ−ト174が設けられてい
る。
As shown in FIGS. 17 to 19, the donut-shaped mounting plate body 125 in the above-described mounting mode is provided on the lower surface of the base 29, and the inside of the donut-shaped mounting plate body 125 is provided at the upper end. A snow fall opening 127 is provided so as not to be connected to the periphery,
A rectangular snow having a rectangular cross section formed by narrowing the front and rear sides (the side shown in FIG. 17 is the front side) at the lower end to be slightly smaller than the snow drop opening 127 and the left and right sides (the side shown in FIG. 18 is the right side). Sliding fall guide member 173 provided with flow port 172
And a wide-mouthed shoe 174 composed of

【0119】また、175は、一側端近くから他側寄り
の上方位置に長方形受入れ口176を他側寄り下方位置
に払出口177をそれぞれ設けしめて断面円形に形成さ
れた胴部位178と、該胴部位178の一側端と他側端
をそれぞれ覆い中心部に軸穴179が穿設された一対の
円形蓋体181とから構成され、該長方形受入れ口17
6が前記長方形雪流通口172と間近に対面なさしめて
前記広口シュ−ト174の下方位置に水平に横設された
一時貯雪兼用送出案内部材の一例である長筒状の一時貯
雪兼用送出案内部材である。尚、前記胴部位178の下
側円弧に一定間隔にて複数の支持片182が取付けられ
ている。
Further, 175 is a trunk portion 178 formed in a circular cross section by providing a rectangular receiving opening 176 at an upper position near one end toward the other side and a payout opening 177 at a lower position near the other side, and The rectangular receiving port 17 is composed of a pair of circular lids 181 each of which covers one end and the other end of the body portion 178 and has a shaft hole 179 formed in the center thereof.
6 is a long tubular temporary snow storage / delivery guide member which is an example of a temporary snow storage / delivery guide member which is horizontally installed below the wide mouth shoe 174 so as to face the rectangular snow circulation port 172 closely. Is. A plurality of support pieces 182 are attached to the lower arc of the body portion 178 at regular intervals.

【0120】図17乃至図19に示すように、183
は、前記軸穴179に嵌合され、軸受側連結部185と
駆動側連結部187を除いて前記胴部位178内に配設
された送出用回動軸189と、軸受側連結部185と駆
動側連結部187を除く該送出用回動軸189の外周に
前記長筒状の一時貯雪兼用送出案内部材171内をスム
−ズに回動可能となして一定ピッチ間隔にて取付けられ
た複数の送出羽根191とから構成された本実施例に係
る送出手段である。
As shown in FIGS. 17 to 19, 183
Is a rotation shaft 189 for delivery which is fitted in the shaft hole 179 and is disposed in the trunk portion 178 except for the bearing side connecting portion 185 and the drive side connecting portion 187, and the bearing side connecting portion 185 and the drive side. A plurality of the plurality of temporary cylinder-shaped temporary snow storage / delivery guide members 171 are mounted on the outer periphery of the delivery rotation shaft 189 excluding the side connecting portion 187 at a constant pitch interval so as to be able to smoothly rotate. The delivery means according to the present embodiment is composed of the delivery vanes 191.

【0121】図17乃至図19に示すように、193
は、適宜な支持部材195により支持されて前記円形蓋
体185と対面なさしめて配設された本実施例に係る送
出用駆動手段であって、前記駆動側連結部187と連動
連結されている。また、196は、軸受部材であって、
前記軸受部材側連結部185を回動可能に支持してい
る。
As shown in FIGS. 17 to 19, 193
Is a driving means for feeding according to the present embodiment, which is supported by an appropriate supporting member 195 and is disposed so as to face the circular lid body 185, and is interlocked with the driving side connecting portion 187. 196 is a bearing member,
The bearing member side connecting portion 185 is rotatably supported.

【0122】前記した長筒状の一時貯雪兼用送出案内部
材175と、送出手段183と、送出用駆動手段193
とから本実施例に係る雪一時貯雪兼用送出機構197が
構成されている。
[0122] The long-cylindrical temporary snow storage / delivery guide member 175, the delivery means 183, and the delivery drive means 193.
Thus, a temporary snow storage / delivery mechanism 197 according to the present embodiment is configured.

【0123】そして、図17に示すように、請求項
(2)の発明の一実施例に係る移設可能なゲレンデ整備
・造設装置1を構成する前記した製雪装置71及び冷凍
装置91と、請求項(4)の発明の一実施例に係る移設
可能なゲレンデ整備・造設装置121を構成する架台1
63と、本実施例の特徴ある構成要素の前記した広口シ
ュ−ト174と、雪一時貯雪兼用送出機構197と、前
記移設可能なゲレンデ整備・造設装置163を構成し開
口部141を払出口177と間近に対面なさしめて雪一
時貯雪兼用送出機構197を構成する長筒状の一時貯雪
兼用送出案内部材171の下方に水平に配設された雪散
布機構161と、から本実施例に係る移設可能なゲレン
デ整備・造設装置169が構成されている。
Then, as shown in FIG. 17, the snow making device 71 and the refrigerating device 91, which constitute the transferable slope maintenance / construction device 1 according to an embodiment of the invention as defined in claim (2), A gantry 1 that constitutes a removable slope maintenance / construction device 121 according to an embodiment of the invention of claim (4).
63, the wide mouth shoe 174 described above, which is a characteristic component of this embodiment, the snow temporary snow storage / delivery mechanism 197, and the transferable slope maintenance / construction apparatus 163, and the opening 141 is discharged. 177 and the snow spraying mechanism 161 horizontally arranged below the long tubular temporary snow storage / delivery guide member 171 forming a temporary snow storage / delivery mechanism 197. A possible slope maintenance / building device 169 is configured.

【0124】このように構成された移設可能なゲレンデ
整備・造設装置169を用いる場合には、一旦、同装置
を製雪動作のみなさしめて製雪された雪を広口シュ−ト
174を経由して雪一時貯雪兼用送出機構197を構成
する長筒状の一時貯雪兼用送出案内部材175側に移動
させ、該長筒状の一時貯雪兼用送出案内部材175の内
部空間175Aに所定量の雪を貯雪する。つぎに、同機
構197を送出動作なさしめて貯雪された雪を雪散布機
構161側に移動なさしめる。この後、該雪散布機構1
61を動作なさしめてゲレンデ造設予定地3側に一時貯
雪された雪を散布してゲレンデ造設予定地3上に分散貯
雪する請求項(3)の発明のステップ7の他の例である
図10に示すST7bが実行されることになる。
In the case of using the removable slope maintenance / construction apparatus 169 having the above-described structure, once the snow is produced by considering the apparatus for snowmaking operation, the snow is made to pass through the wide-mouthed shoe 174. The temporary snow storage / delivery mechanism 197 is moved to the long tubular temporary snow storage / delivery guide member 175 side, and a predetermined amount of snow is stored in the internal space 175A of the long tubular temporary snow storage / delivery guide member 175. To do. Next, the mechanism 197 is not sent out, and the stored snow is moved to the snow spraying mechanism 161 side. After this, the snow spraying mechanism 1
Fig. 6 is another example of step 7 of the invention of claim (3), in which 61 is not operated to disperse the snow temporarily stored on the slope construction site 3 side to disperse and store the snow on the slope construction site 3. ST7b shown in 10 is executed.

【0125】そして、前記したST8aを実行した後、
ST7bとST8aを順次反復実行する請求項(3)の
発明のステップ9の他の例であるST9bを実行する
と、ゲレンデ造設予定地3上に一定間隔にてゲレンデを
造設するに必要な量の雪が分散集積圧密される。しかる
後に、前記したST6bを実行すると、スロ−プ5が形
成され計画したゲレンデが造設される。
Then, after executing the above-mentioned ST8a,
When ST9b, which is another example of step 9 of the invention of claim (3) in which ST7b and ST8a are repeatedly executed, is performed, an amount required to construct slopes on the slope construction site 3 at regular intervals The snow is dispersed and consolidated. Then, when the above-mentioned ST6b is executed, the slope 5 is formed and the planned slope is constructed.

【0126】尚、前記した請求項(5)の発明の一実施
例に係る移設可能なゲレンデ整備・造設装置169を構
成する前記広口シュ−ト174の下端の左右側(図18
に示す側を右側とする。)を、下端の前後側(図17に
示す側を前側とする。)と同一の長さに形成して、下端
に、前記長方形雪流通穴172より雪流通面積を拡張し
た断面正方形の正方形雪流通穴を設けてもよい。この場
合、複数の前記送出羽根191が一定ピッチ間隔にて取
付けられた前記送出用回動軸189を複数本平行であっ
て正方形雪流通穴の下方に水平に配設なさしめる。そし
て、前記長筒状の一時貯雪兼用送出案内部材175を拡
張し、該複数本の送出用回動軸189を収容する構成と
すればよい。
[0126] The left and right sides of the lower end of the wide-mouthed shoe 174 constituting the removable slope maintenance / construction apparatus 169 according to the embodiment of the invention described in claim (5) (Fig. 18).
The side shown in is the right side. ) Is formed to have the same length as the front and rear sides of the lower end (the side shown in FIG. 17 is the front side), and the lower end of the rectangular snow distribution hole 172 has a wider snow distribution area than the rectangular snow distribution area. A circulation hole may be provided. In this case, the plurality of delivery rotating shafts 189 having the plurality of delivery blades 191 attached at a constant pitch are arranged in parallel and horizontally below the square snow circulation hole. Then, the long tubular temporary snow storage / delivery guide member 175 may be expanded to accommodate the plurality of delivery rotating shafts 189.

【0127】つぎに、請求項(3)乃至請求項(5)の
発明の一実施例の作用について説明する。まず、図10
及び図11に示すように、請求項(1)の発明の一実施
例に係る前記したST1a、ST1b及びST2a、若
しくは、ST1a、ST1cおよびST2bを順次実行
すると、ゲレンデを所定時間に造設可能な台数の、請求
項(4)の発明の一実施例に係る移設可能なゲレンデ整
備・造設装置121、若しくは、請求項(5)の発明の
一実施例に係る移設可能なゲレンデ整備・造設装置16
9をゲレンデ造設予定地3の脇9に雪散布機構161を
構成する投雪風胴155をゲレンデ造設予定地3側に向
けた状態で分散配置される。
Next, the operation of the embodiment of the inventions of claims (3) to (5) will be described. First, FIG.
And, as shown in FIG. 11, when the above-mentioned ST1a, ST1b and ST2a or ST1a, ST1c and ST2b according to one embodiment of the invention of claim (1) are sequentially executed, a slope can be built in a predetermined time. Removable slope maintenance / construction device 121 according to one embodiment of the invention of claim (4) or removable slope maintenance / construction according to one embodiment of the invention of claim (5). Device 16
The snow throwing wind tunnels 155 forming the snow spraying mechanism 161 are distributed and arranged on the sides 9 of the planned slope construction site 3 toward the slope planned construction site 3 side.

【0128】ついで、ゲレンデを造設するに用いる装置
が、請求項(4)の発明の一実施例に係る移設可能なゲ
レンデ整備・造設装置121である場合には、図10に
示すように、請求項(3)の発明のステップ7の一例に
係るST7aの実行が開始され、前記したと同様にして
製雪動作が開始される。すると、図14乃至図16に示
すように、前記したと同様のプロセスを経て製雪された
雪は、雪落下口127を通って円錐形シュ−ト123内
を下端に位置する雪流通口129側に滑動移動した後、
該雪流通口129、開口部141を順次通過してケ−シ
ング131内に進入する。
Next, when the apparatus used for constructing the slope is the transferable slope maintenance / construction apparatus 121 according to one embodiment of the invention of claim (4), as shown in FIG. The execution of ST7a according to an example of step 7 of the invention of claim (3) is started, and the snow making operation is started in the same manner as described above. Then, as shown in FIGS. 14 to 16, the snow produced through the same process as described above passes through the snow drop port 127 and the snow flow port 129 located at the lower end in the conical shoe 123. After sliding to the side,
The snow circulation port 129 and the opening 141 are sequentially passed to enter the casing 131.

【0129】係る製雪動作と略同時に投雪用駆動手段1
59を動作させると、図16に示すように、回動軸15
1は一側に回動する一方、複数のブレ−ド153は、ケ
−シング131内を開口部141から送出口143側
(図16中に示す矢印199方向)に回動する。する
と、ケ−シング131内に流入した雪は、該複数のブレ
−ド153に打撃されて回動力とともに遠心力を作用さ
れ、開口部141から送出口143に高速にて回動移動
する。
Almost simultaneously with the snow making operation, the snow throwing drive means 1
When 59 is operated, as shown in FIG.
While 1 is rotated to one side, a plurality of blades 153 are rotated in the casing 131 from the opening 141 toward the delivery port 143 side (direction of arrow 199 shown in FIG. 16). Then, the snow that has flowed into the casing 131 is hit by the plurality of blades 153, exerts a centrifugal force together with a turning force, and rotates at a high speed from the opening 141 to the delivery port 143.

【0130】すると、該雪は、遠心力の作用を受けつつ
送出口143到達した後、該送出口から前記ブレ−ド1
53の回動接線155A上に投げ出される。このため、
該雪は、送出口143から投雪風胴155内に進入した
後、投射口157から空中に投射されて、該投射口15
7の向かいのゲレンデ造設予定地3上に散布される。
Then, the snow reaches the delivery port 143 while receiving the action of centrifugal force, and then the blade 1 is delivered from the delivery port.
It is thrown out on the rotation tangent line 155A of 53. For this reason,
The snow enters the snow blowing wind tunnel 155 through the outlet 143 and is then projected into the air through the projection port 157, so that the projection port 15
It is scattered on the slope construction site 3 opposite to 7.

【0131】前記した雪の製雪と、これと連係する雪の
散布動作を各移設可能なゲレンデ整備・造設装置121
にて所定時間継続して実行すると、図11に示すよう
に、分散配置された各移設可能なゲレンデ整備・造設装
置121それぞれと向かい合うゲレンデ造設予定地3上
のそれぞれの位置に、一定量の雪が降り積もって雪の小
山が現出して分散貯雪される、図10に示すST7aが
実行される。つぎに、前記ブルド−サ−95を用いて、
該雪の小山に乗り上げる操作を所定時間実行すると、該
雪の小山は圧密され融雪しがたい状態で分散貯雪圧密さ
れる、図10に示すST8aが実行される。
[0131] The slope maintenance / construction device 121 capable of relocating the above-described snow making and the snow spraying operation associated therewith.
When it is continuously executed for a predetermined period of time, as shown in FIG. 11, a fixed amount is provided at each position on the planned slope construction site 3 facing each of the distributable slope maintenance / construction devices 121. ST7a shown in FIG. 10 is executed in which the snow is piled up, the small mountains of the snow appear, and the distributed snow is stored. Next, using the Bulldozer-95,
When the operation of riding on the snowy mountain is performed for a predetermined time, the snowy mountain is compacted and distributed snow is compacted in a state where it is difficult to melt snow, and ST8a shown in FIG. 10 is executed.

【0132】そして、請求項(4)の発明の一実施例に
係る各移設可能なゲレンデ整備・造設装置121によ
る、製雪動作、貯雪動作、及び、散布動作と、前記ブル
ド−ザ−95による圧密動作を順次反復実行する図10
に示すST9aを実行する。すると、圧密された雪の小
山は次第に大きく成長し、ゲレンデ造設予定地3上に、
一定間隔にて複数の人工雪集積圧密小山201が現出さ
れ、前記した正味製雪量が確保される。
Then, the snow-making operation, the snow-storing operation, the spraying operation, and the bulldozer-95 by the removable slope maintenance / building apparatus 121 according to the embodiment of the invention of claim (4). 10 for sequentially repeating the consolidation operation by
ST9a shown in is executed. Then, the compact snowy mountain grows gradually and grows on the slope construction site 3,
A plurality of artificial snow accumulation compaction hills 201 appear at regular intervals, and the above-mentioned net snow production amount is secured.

【0133】ついで、図10及び図11に示すように、
前記したST6aを実行すると、ブルド−サ−95は、
複数の人工雪集積圧密小山201を突き崩した後、図1
1に示す矢印203、205、207等の方向に押圧・
搬送する。このため、複数の人工雪集積圧密小山201
は略均等にならされ、ゲレンデ造設予定地3上にスロ−
プ5が形成されてゲレンデが造設される。
Then, as shown in FIG. 10 and FIG.
When ST6a is executed, the bulldozer-95
After crushing a plurality of artificial snow accumulation compaction mountains 201, FIG.
Press in the directions indicated by arrows 203, 205, 207, etc.
Transport. For this reason, a plurality of artificial snow accumulation compaction mountains 201
Are leveled evenly, and the slope is placed on the slope construction site 3.
5 is formed and a slope is constructed.

【0134】一方、ゲレンデを造設するに用いる装置が
請求項(5)の発明の一実施例に係る移設可能なゲレン
デ整備・造設装置169である場合には、請求項(3)
の発明のステップ7の他の例であるST7bの実行が開
始される。すると、前記したと同様にして、まず、製雪
動作のみが開始される。すると、図17乃至図19に示
すように、前記したと同様のプロセスを経て、製雪され
た雪は、前記広口シュ−ト174を通って長方形雪流通
口172、長方形受入口176を順次通過して長筒状の
一時貯雪兼用送出案内部材175内に進入する。そし
て、係る製雪動作のみを一定時間継続実行すると、該一
時貯雪兼用送出案内部材175内と前記広口シュ−ト1
74を構成する雪流通案内部材173内の下方位置に製
雪された雪が貯雪される。
On the other hand, when the apparatus used for constructing the slope is the relocatable slope maintenance / construction apparatus 169 according to the embodiment of the invention of Claim (5), Claim (3)
Execution of ST7b, which is another example of step 7 of the invention described above, is started. Then, similarly to the above, first, only the snow making operation is started. Then, as shown in FIGS. 17 to 19, the snow produced through the same process as described above passes through the wide mouth shoe 174 and sequentially passes through the rectangular snow circulation port 172 and the rectangular receiving port 176. Then, it enters into the long tubular temporary snow storage / delivery guide member 175. When only the snow making operation is continuously executed for a certain period of time, the inside of the temporary snow storage / delivery guide member 175 and the wide mouth shoe 1 are
Snow produced in the snow distribution guide member 173 forming the snow 74 is stored at a lower position.

【0135】つぎに、前記送出用駆動手段193を動作
させると、図19に示すように、送出用回動軸189が
一側に回動するとともに、複数の送出羽根191も一側
に回動を開始する。すると、長筒状の一時貯雪兼用案内
部材173内に貯雪された雪は、該複数の送出羽根18
1により、一時貯雪による雪同士の密着を解きほぐすよ
うに、攪拌作用を受けつつ払出口177側に移動する。
尚、係る移動により、前記雪流通案内部材173内の下
方に貯雪されていた雪は、新たに、長方形雪流通口17
2、受入れ口177を順次通過して、長筒状の一時貯雪
兼用送出案内部材175内に流入する。
Next, when the delivery driving means 193 is operated, as shown in FIG. 19, the delivery rotating shaft 189 rotates to one side and the plurality of delivery blades 191 also rotate to one side. To start. Then, the snow accumulated in the long tubular temporary snow storage / combined guide member 173 is not covered by the plurality of delivery blades 18.
By 1, the movement to the payout exit 177 side is performed while receiving the stirring action so as to loosen the close contact between the snow due to the temporary snow accumulation.
By the movement, the snow accumulated below the snow circulation guide member 173 is newly added to the rectangular snow circulation port 17
2. It sequentially passes through the receiving port 177 and then flows into the long tubular temporary snow storage / delivery guide member 175.

【0136】そして、払出口177に移動した雪は、前
記開口部141を通って前記ケ−シング131内に移動
する。係る送出用駆動手段193の動作と略同時に前記
投雪用駆動手段159を動作させると、前記したと同様
のプロセスを経て、該ケ−シング131内に流入してき
た雪は、前記投雪風胴155からゲレンデ造設予定地3
上に散布される。
Then, the snow that has moved to the payout opening 177 moves into the casing 131 through the opening 141. When the snow throwing drive means 159 is operated at substantially the same time as the operation of the sending drive means 193, the snow that has flowed into the casing 131 through the same process as described above is the snow throwing wind tunnel. Scheduled site 3 from 155
Sprinkled on top.

【0137】前記した製雪動作のみの実行と、所定時間
後の散布動作を反復実行すると、分散配置された各移設
可能なゲレンテイ整備・造設装置169それぞれと向か
い合うゲレンデ造設予定地3のそれぞれの位置に一定量
の雪が降り積もって雪の小山が現出して分散貯雪され
る、図10に示すST7bが実行される。この後、該雪
の小山を前記したと同様にして圧密すると、分散貯雪さ
れていた雪の小山が分散貯雪圧密される、図10に示す
ST8aが実行される。
When only the snow making operation described above and the spraying operation after a predetermined time are repeatedly executed, each of the sloped construction sites 3 facing each of the distributable slope maintenance / construction devices 169. ST7b shown in FIG. 10 is executed, in which a certain amount of snow has accumulated at the position, and a small mountain of snow appears, and distributed snow is stored. After that, when the small mountain of snow is consolidated in the same manner as described above, ST8a shown in FIG. 10 is executed, in which the small mountain of distributed snow is distributed and compacted.

【0138】そして、請求項(5)の発明の一実施例に
係る各移設可能なゲレンデ整備・造設装置169によ
る、製雪動作のみの実行、所定時間後の散布動作、と、
ブルド−ザ−95による圧密動作を順次反復実行する図
10に示すST9bを実行する。すると、圧密された雪
の小山は次第に大きく成長し、ゲレンデ造設予定地3上
に、一定間隔にて分散集積圧密された複数の人工雪集積
圧密小山201が現出され、前記した正味製雪量が確保
される。
Then, only the snow-making operation is executed by the removable slope maintenance / building apparatus 169 according to the embodiment of the invention of claim (5), and the spraying operation after a predetermined time,
ST9b shown in FIG. 10 in which the consolidation operation by the bulldozer-95 is sequentially and repeatedly executed is executed. Then, the compact snow mountain grows gradually and a plurality of artificial snow integrated compact mountains 201 dispersed and integrated at regular intervals appear on the slope construction site 3, and the above-mentioned net snow making is performed. The quantity is secured.

【0139】ついで、図10及び図11に示すように、
前記したST6bを実行すると、ブルド−ザ−95が、
複数の人工雪集積圧密小山201を突き崩した後、図1
1に示す矢印203、205、207等の方向に押圧・
搬送する。このため、複数の人工雪集積圧密小山201
は略均等にならされて、ゲレンデ造設予定地3上にスロ
−プ5が形成されてゲレンデが造設される。
Then, as shown in FIGS. 10 and 11,
When ST6b is executed, Bulldozer-95
After crushing a plurality of artificial snow accumulation compaction mountains 201, FIG.
Press in the directions indicated by arrows 203, 205, 207, etc.
Transport. For this reason, a plurality of artificial snow accumulation compaction mountains 201
Are almost evened, and a slope 5 is formed on the slope construction site 3 to construct a slope.

【0140】つぎに、請求項(3)の発明の変形実施例
及び作用について説明する。図12は請求項(3)の発
明のゲレンデ整備・造設方法の変形実施例をチャ−ト的
に示し、図13は同変形実施例のうちゲレンデが整備若
しくは造設される段階を上方から模式的に示したもので
ある。
Next, a modified embodiment and operation of the invention of claim (3) will be described. FIG. 12 is a chart showing a modified embodiment of the slope maintenance / construction method of the invention of claim (3), and FIG. 13 shows, from above, the step of maintenance or construction of the slope in the modified embodiment. It is shown schematically.

【0141】営業開始後に前記した移設可能なゲレンデ
整備・造設装置121、若しくは、169を用いてゲレ
ンデを整備若しくは造設する場合は、前記した請求項
(1)の発明の変形実施例にて説示したてと同様の手順
を基準とする。そして、前記営業用ゲレンデ108を整
備する必要がある場合には、図12に示すように、前記
したST7aと同様のST7c、若しくは、前記したS
T7bと同様のST7dと前記したST8aを順次実行
した後、これら手順を反復して順次実行するST7cを
実行すると、所定間隔にて複数の人工雪集積圧密小山2
09が営業用ゲレンデ108上に分散集積圧密される。
この後、前記ST6aと同様のST6cを実行すると、
前記したと同様にして営業用ゲレンデ108の整備が完
了する。
In the case where the slope is maintained or constructed by using the above-mentioned transferable slope maintenance / construction device 121 or 169 after the start of business, the modified embodiment of the invention of the above-mentioned claim (1) is used. The procedure is the same as that just described. When it is necessary to maintain the sales slope 108, as shown in FIG. 12, ST7c similar to ST7a described above or S described above is used.
After ST7d similar to T7b and ST8a described above are sequentially executed, ST7c that repeats these procedures and is sequentially executed is executed to perform a plurality of artificial snow accumulation compaction mountain 2 at predetermined intervals.
09 is distributed and integrated on the sales slope 108.
After that, if ST6c similar to ST6a is executed,
The maintenance of the commercial slope 108 is completed in the same manner as described above.

【0142】この一方、前記した基準により、営業用ゲ
レンデ108を整備する必要がなく、他の営業用ゲレン
デ115を造設する余裕と必要がある場合であって、造
設する他の営業用ゲレンデ115の造設予定地が、営業
用ゲレンデ108と隣接する位置であれば、適宜な吊り
上げ装置を用いて、請求項(4)の発明の一実施例に係
る移設可能なゲレンデ整備・造設装置121、若しく
は、請求項(5)の発明の一実施例に係る移設可能なゲ
レンデ整備・造設装置169を旋回移動等なさしるめ
て、これら装置を構成する投雪風胴155を他の営業用
ゲレンデ115の造設予定地側に向かせるようにして分
散配置する。
On the other hand, according to the above-mentioned criteria, there is a case where it is not necessary to maintain the sales slope 108, and there is a margin to construct another sales slope 115, and it is necessary to construct another sales slope 115. If the planned construction site of 115 is a position adjacent to the commercial slope 108, a suitable lifting device can be used to transfer the slope maintenance / construction device according to one embodiment of the invention of claim (4). 121 or the movable slope maintenance / construction device 169 according to the embodiment of the invention of claim (5) is swung or the like, and the snow throwing wind tunnel 155 constituting these devices is replaced by another device. It is distributed and arranged so as to face the construction site of the business slope 115.

【0143】また、他の営業用ゲレンデ115の造設予
定地が営業用ゲレンデ108と離れた位置である場合に
は、前記移設可能なゲレンデ整備・造設装置121、若
しくは、169をトラック7等の陸上輸送手段に搭載し
て間近まで輸送し、つれら装置を構成する投雪風胴15
5を、他の営業用ゲレンデ115の造設予定地側に向か
せるようにして分散配置する、前記したST2cと同様
の図12に示すST2dを実行する。
When the construction site of another business slope 115 is located away from the business slope 108, the transferable slope maintenance / construction device 121 or 169 is used for the truck 7 or the like. Snow wind tunnel 15 which is mounted on the above-mentioned land transportation means and is transported to the vicinity to form a sledding device.
ST2d shown in FIG. 12, which is the same as ST2c described above, in which 5 are distributed and arranged so as to face the other construction slopes 115 for commercial use.

【0144】この後、前記したST7aと同様のST7
e、若しくは、前記したST7bと同様のST7fと前
記したST8aを順次実行した後、これら手順を反復し
て順次実行するST9aを実行すると、図13に示すよ
うに、所定間隔にて複数の人工雪集積圧密小山201が
分散集積圧密され、他の営業用ゲレンデを造設するに必
要な量の雪が確保される。ついで、前記したST6bと
同様のST6dを実行すると、他の営業用ゲレンデ11
5が造設されるのである。
Thereafter, the same ST7 as ST7a described above is used.
e, or ST7f similar to ST7b described above and ST8a described above are sequentially executed, and then ST9a that repeats these procedures and is sequentially executed is executed, as shown in FIG. The integrated compaction hills 201 are dispersed and integrated, and the amount of snow necessary for constructing another commercial slope is secured. Next, when ST6d similar to ST6b described above is executed, the other slope 11 for sales is sold.
5 is built.

【0145】つぎに、請求項(6)の発明の一実施例と
その作用を説明する。図20は、請求項(6)の発明の
一実施例に係る移設可能なゲレンデ整備・造設装置が三
分割されヘリコプタ−に搭載可能となった状態を正面側
から模式的に示し、図21は水平方向移動阻止・垂直方
向脱着誘導部材と吊りフック取付用螺子穴が搭載用部材
上に配設された状態を上方からみた場合を示し、図22
は水平方向移動阻止・垂直方向脱着誘導部材との一例を
拡大するとともに一部断面して示したものである。
Next, one embodiment of the invention of claim (6) and its operation will be described. 21. FIG. 20 schematically shows from the front side a state in which the transferable slope maintenance / construction device according to an embodiment of the invention of claim (6) is divided into three parts and can be mounted on a helicopter. 22 shows a state in which the horizontal movement prevention / vertical attachment / detachment guide member and the hanging hook mounting screw hole are arranged on the mounting member, as viewed from above, and FIG.
Shows an example of the horizontal movement prevention / vertical attachment / detachment guide member while enlarging and showing a partial cross section.

【0146】図20乃至図22に示すように、211
は、円板状に形成され一定間隔にて複数の取付穴213
が設けられた着座部位215と、底面が該着座部位21
5より若干小さくして円錐状に形成され該着座部位21
5の略中央部に一体的に取付けられた脱着誘導部位21
7とから構成された本実施例に係る水平方向移動阻止・
垂直方向脱着誘導部材である。
As shown in FIGS. 20 to 22, 211
Are formed in a disk shape and are provided with a plurality of mounting holes 213 at regular intervals.
And a bottom surface of the seating portion 215.
The seating portion 21 is formed in a conical shape with a size slightly smaller than 5.
Detachment-inducing portion 21 integrally attached to substantially the central portion of 5
Horizontal movement prevention according to the present embodiment, which is composed of 7 and
It is a vertical detachment guide member.

【0147】図22に示すように、該水平方向移動阻止
・垂直方向脱着誘導部材211の配設位置には、前記着
座部位215より直径を大であって適宜深さの円板状に
形成され、該着座部位215を嵌入可能な径であるとと
もに取付穴213と対面する位置に取付螺子穴221が
螺設された支持部位223である。
As shown in FIG. 22, the horizontal movement preventing / vertical detachment guide member 211 is formed in a disc shape having a larger diameter than the seating portion 215 and an appropriate depth. The support portion 223 has a diameter such that the seating portion 215 can be fitted therein, and a mounting screw hole 221 is screwed at a position facing the mounting hole 213.

【0148】図20に示すように、225は、吊り上げ
平衡位置に複数の吊りフック取付用螺子穴227が螺設
されている以外は、前記製雪装置71と同様の構成とし
た本実施例に係る製雪装置である。
As shown in FIG. 20, 225 is the same as the snow making device 71 except that a plurality of hanging hook mounting screw holes 227 are screwed at the hoisting balance position. This is the snow making device.

【0149】図21に示すように、前記水平方向移動阻
止・垂直方向脱着誘導部材211と該支持部位223と
が、本実施例に係る製雪装置225が配設される位置上
であって相対面する二箇所と、本実施例に係る冷凍装置
229が配設される位置上であって相対面する二箇所に
それぞれ設けられ、さらに、四隅にそれぞれ吊りフック
取付用螺子穴227が螺設され、その他の構成を前記搭
載用部材11と同様とした本実施例に係る搭載用部材2
31が構成されている。
As shown in FIG. 21, the horizontal movement prevention / vertical attachment / detachment guide member 211 and the supporting portion 223 are located relative to each other on the position where the snow making device 225 according to the present embodiment is arranged. It is provided at two facing positions and at two facing positions on the position where the refrigerating apparatus 229 according to the present embodiment is disposed, and further, hanging hook mounting screw holes 227 are screwed at four corners, respectively. The mounting member 2 according to the present embodiment having the same other configurations as the mounting member 11 described above.
31 are configured.

【0150】図20に示すように、該搭載用部材231
と複数の前記長尺脚部材21とから本実施例に係る架台
233が構成されている。尚、該搭載用部材231と前
記中尺脚部材であっても勿論適用可能である。
As shown in FIG. 20, the mounting member 231.
The pedestal 233 according to the present embodiment is composed of the plurality of long leg members 21. The mounting member 231 and the medium-sized leg member can of course be applied.

【0151】図20に示すように、気化低圧冷媒輸送配
管73には、気液分離機75寄りの配管路にストップ弁
74が、上流側端であって前記冷媒流出口35と対面す
る側にストップ弁連結用取付フランジ232が、下流側
端であって前記冷媒圧縮機77と対面する側に図示を省
略した取付フランジがそれぞれ設けられている。尚、該
ストップ弁74と該ストップ弁連結用取付フランジ23
2間に図示を省略したパキュ−ウムポンプと接続可能な
弁230が設けられている。この一方、液化高圧冷媒輸
送配管75には、凝縮手段79寄りの膨張弁89と隣接
する配管路に高圧液側弁234が、下流側端であって前
記冷媒流入口33と対面する側にストップ弁連結用取付
フランジ232が、上流側端であって前記凝縮手段79
と対面する側に図示を省略した取付フランジがそれぞれ
設けられている。
As shown in FIG. 20, in the vaporized low-pressure refrigerant transport pipe 73, a stop valve 74 is provided in a pipe passage near the gas-liquid separator 75, at the upstream end which faces the refrigerant outlet 35. The stop valve connecting mounting flange 232 is provided with a mounting flange (not shown) on the downstream side end facing the refrigerant compressor 77. Incidentally, the stop valve 74 and the mounting flange 23 for connecting the stop valve
A valve 230 connectable with a vacuum pump (not shown) is provided between the two. On the other hand, in the liquefied high-pressure refrigerant transport pipe 75, a high-pressure liquid-side valve 234 is provided in a pipe path adjacent to the expansion valve 89 near the condensing means 79, and is stopped at a downstream end facing the refrigerant inlet 33. The valve connecting mounting flange 232 is located at the upstream end and is the condensing means 79.
Mounting flanges (not shown) are respectively provided on the sides facing with.

【0152】尚、気化低圧冷媒輸送配管73の上流側端
と液化高圧冷媒輸送配管の下流側端に設けられたストッ
プ弁連結用取付フランジ232の替わりに後述する図示
を省略したクイック脱着大口径流体継手であってもよ
い。また、気化低圧冷媒輸送配管73の下流側端に設け
られた図示を省略した取付フランジの替わりに該クイッ
ク脱着大口径流体継手を設けてもよく、液化高圧冷媒輸
送配管の上流側端に設けられた取付フランジの替わり
に、後述する図示を省略したクイック脱着小口径流体継
手を設けてもよい。
In place of the stop valve connecting mounting flange 232 provided at the upstream end of the vaporized low-pressure refrigerant transport pipe 73 and the downstream end of the liquefied high-pressure refrigerant transport pipe, a quick detachable large-diameter fluid (not shown) described later is omitted. It may be a joint. Further, the quick desorption large-diameter fluid coupling may be provided in place of the mounting flange (not shown) provided at the downstream side end of the vaporized low pressure refrigerant transport pipe 73, and provided at the upstream side end of the liquefied high pressure refrigerant transport pipe. Instead of the mounting flange, a quick disconnect small diameter fluid coupling (not shown) may be provided, which will be described later.

【0153】尚、図示を省略したが、前記したクイック
脱着小口径流体継手は、複数の小さなボ−ルを押さえる
スリ−ブを引き、この後、プラグをソケットに挿入し、
しかる後に、手を離すとスプリングの弾発力によりスリ
−ブを元の位置に戻らしめて、一方と他方の配管を連結
させる構造のものが考えられる。
Although not shown in the drawings, the quick-disconnect small-diameter fluid coupling described above pulls a sleeve that holds a plurality of small balls, and then inserts a plug into a socket.
After that, when the hand is released, a structure in which the sleeve is returned to its original position by the elastic force of the spring and one pipe and the other pipe are connected to each other can be considered.

【0154】また、図示を省略したが、前記したクイッ
ク脱着大口径流体継手は、内部に連結テ−パ穴が設けら
れた連結座部位と該連結座部位と一体的に構成された中
空鋼製ジャバラ部位とからなる一の継手部材と、連結テ
−パ穴に進入可能に形成されたテ−パ状突起部位と前記
連結座部位の外径と略同一の外径に形成された中空連結
部位を備えた他の継手部材と、該他の継手部材に回動可
能となして取付けられた回動子と、該回動子と足部位を
介して一体構成された連結子からなる連結作用部材とか
ら構成されたものが考えられる。
Although not shown in the drawings, the quick detachable large-diameter fluid coupling described above is made of hollow steel integrally formed with a connecting seat portion provided with a connecting taper hole therein. One joint member composed of a bellows portion, a taper-like projection portion formed so as to be able to enter the connection taper hole, and a hollow connection portion formed to have an outer diameter substantially the same as the outer diameter of the connection seat portion. Coupling member including another joint member including the rotator, a rotator rotatably attached to the other joint member, and a connector integrally configured with the rotator and a foot portion. It is considered that it is composed of and.

【0155】そして、かかる構造のクイック連結大口径
流体継手は、つぎのように各構成部材が動作して迅速に
一方と他方の配管を連結するのである。すなわち、前記
回動子を、一側方向に回動して一の継手部材と他の継手
部材とを対面可能とする。つぎに、該一の継手部材と他
の継手部材とを対面接近させた後、更に接近させ、前記
テ−パ状突起部位を前記連結テ−パ穴に嵌入させる。こ
の後、前記回動子を他側方向に回動させて、前記連結子
を、前記連結座部位の背後と接触させると、該連結座部
位と前記中空連結部位とが強固に当接されることによ
り、前記一の継手部材と他の継手部材254とが連結さ
れて、一方と他方の配管を連結させるのである。
In the quick connection large-diameter fluid coupling having such a structure, each component operates in the following manner to rapidly connect the one and the other pipes. That is, the rotator is rotated in one direction so that one joint member and another joint member can face each other. Next, the one joint member and the other joint member are brought close to each other in face-to-face relation, and then further brought close to each other, and the taper-like projection portion is fitted into the connecting taper hole. Thereafter, when the rotator is rotated in the other direction to bring the connector into contact with the back of the connection seat portion, the connection seat portion and the hollow connection portion are firmly contacted. As a result, the one joint member and the other joint member 254 are connected to each other to connect the one pipe and the other pipe.

【0156】図20に示すように、229は、凝縮手段
79上の吊り上げ平衡位置に複数の吊りフック取付用螺
子穴227が螺設されている点のみが相違し、その他の
構成を前記冷凍装置91と同様とした本実施例に係る冷
凍装置である。
As shown in FIG. 20, 229 is different only in that a plurality of hanging hook mounting screw holes 227 are screwed at the lifting equilibrium position on the condensing means 79. The refrigerating apparatus according to the present embodiment is the same as the refrigerating apparatus 91.

【0157】図20に示すように、前記した製雪装置2
25と、冷凍装置229と、架台233と、とから、請
求項(6)の発明の一実施例に係る移設可能なゲレンデ
整備・造設装置259が構成されている。
As shown in FIG. 20, the snow making device 2 described above is used.
25, the refrigerating apparatus 229, and the pedestal 233 constitute a transferable slope maintenance / construction apparatus 259 according to an embodiment of the invention of claim (6).

【0158】図20に示すように、前記高圧液側弁23
4を閉じた後、冷凍装置229を動作させる。すると、
製雪装置225を構成する冷媒蒸発室39の冷媒は吸入
され、バキュ−ム状態となる。この後、気化低圧冷媒輸
送配管73に設けられたストップ弁74と、冷媒流入口
33の流入端と冷媒流出口35の流出端それぞれに付設
されたストップ弁74を閉じる。
As shown in FIG. 20, the high pressure liquid side valve 23
After closing No. 4, the refrigerating apparatus 229 is operated. Then
The refrigerant in the refrigerant evaporation chamber 39 that constitutes the snow making device 225 is sucked into the vacuum state. Then, the stop valve 74 provided in the vaporized low pressure refrigerant transport pipe 73 and the stop valves 74 attached to the inflow end of the refrigerant inflow port 33 and the outflow end of the refrigerant outflow port 35 are closed.

【0159】また、気化低圧冷媒輸送配管73の上流側
端に設けられたストップ弁連結用取付フランジ232と
冷媒流出口35の流出端に付設されたストップ弁74と
の連結を解除するとともに、液化高圧冷媒輸送配管75
の下流側端に設けられたストップ弁連結用取付フランジ
232と冷媒流入口33の流入端に付設されたストップ
弁74との連結を解除すると、フロン等の冷媒が空中に
漏れることなく、製雪装置225と冷凍装置229との
連結が解除される。尚、前記クイック流体大口径流体継
手が、気化低圧冷媒輸送配管73の上流側端と液化高圧
冷媒輸送配管85の下流側端に設けられた場合であって
も、該クイック脱着大口径流体継手の前記した連結解除
動作により、製雪装置225と冷凍装置229の連結が
迅速に解除される。
Further, the connection between the stop valve connecting mounting flange 232 provided at the upstream end of the vaporized low pressure refrigerant transport pipe 73 and the stop valve 74 attached to the outflow end of the refrigerant outlet 35 is released, and the liquefaction is performed. High pressure refrigerant transport piping 75
When the connection between the stop valve connecting mounting flange 232 provided on the downstream side end of the vehicle and the stop valve 74 attached to the inflow end of the refrigerant inlet 33 is released, the refrigerant such as freon does not leak into the air and snow is produced. The connection between the device 225 and the refrigeration device 229 is released. Even when the quick fluid large-diameter fluid coupling is provided at the upstream end of the vaporized low-pressure refrigerant transportation pipe 73 and the downstream end of the liquefied high-pressure refrigerant transportation pipe 85, the quick desorption large-diameter fluid coupling is By the above-described connection release operation, the connection between the snow making device 225 and the freezing device 229 is quickly released.

【0160】さらに、気化低圧冷媒輸送配管73の下流
端と液化高圧冷媒輸送配管85の上流端に設けられた図
示を省略した取付フランジを取り外すと、フロン等の冷
媒が空中に漏れることなく、冷凍装置229を構成する
冷媒圧縮機77を含む凝縮手段79と、該冷凍装置22
9のその他の構成部材との連結が解除される。尚、クイ
ック脱着大口径流体継手が気化低圧冷媒輸送配管73の
下流側端に、クイック脱着小口径流体継手が液化高圧冷
媒輸送配管85の上流側端にそれぞれ設けられた場合で
あっても、前記した連結解除動作により、同様に連結が
解除される。
Furthermore, by removing the mounting flanges (not shown) provided at the downstream end of the vaporized low pressure refrigerant transport pipe 73 and the upstream end of the liquefied high pressure refrigerant transport pipe 85, refrigerant such as freon will not leak into the air and will be frozen. Condensing means 79 including the refrigerant compressor 77 constituting the device 229, and the refrigerating device 22.
The connection with the other components of 9 is released. Even when the quick desorption large diameter fluid coupling is provided at the downstream end of the vaporized low pressure refrigerant transport pipe 73 and the quick desorption small diameter fluid coupling is provided at the upstream end of the liquefied high pressure refrigerant transport pipe 85, respectively, Similarly, the connection is released by the connection release operation.

【0161】つぎに、例えば、前記製雪装置225側の
前記吊りフック取付螺子穴227に吊りフック261を
螺入し、ワイヤ−263を介して該吊りフック261と
図示を省略した吊り上げ手段とを接続し、該吊り上げ手
段を動作させる。また、同様にして、ワイヤ265を介
して凝縮手段79に取付けた吊りフック261と吊り上
げ手段とを接続し、該吊り上げ手段を動作させる。する
と、本実施例に係る移設可能なゲレンデ整備・造設装置
259は、航空輸送手段の一例であるヘリコプタ−26
5により輸送可能な重量と大きさの、製雪装置225
と、冷凍装置229を構成する冷媒圧縮機77を含む凝
縮手段79と、該冷媒圧縮機77と凝縮手段79を除く
冷凍装置229を構成するその他の構成部材を搭載した
架台233とに三分割される。
Next, for example, a hanging hook 261 is screwed into the hanging hook mounting screw hole 227 on the side of the snow making device 225, and the hanging hook 261 and a lifting means (not shown) are connected via a wire-263. Connect and operate the lifting means. In the same manner, the hanging hook 261 attached to the condensing means 79 is connected to the hoisting means via the wire 265, and the hoisting means is operated. Then, the relocatable slope maintenance / construction apparatus 259 according to the present embodiment is a helicopter-26 which is an example of air transportation means.
5, the snow making device 225 having a weight and a size that can be transported.
And a condensing unit 79 including the refrigerant compressor 77 that constitutes the refrigerating apparatus 229, and a pedestal 233 on which other constituent members that constitute the refrigerating apparatus 229 other than the refrigerant compressor 77 and the condensing unit 79 are mounted. It

【0162】ついで、まず、前記したと同様にして搭載
用部材231上の四箇所に設けられた吊りフック取付用
螺子穴227それぞれ吊りフック261を螺入して取付
け、これら吊りフック261をワイヤ263を介してヘ
リコプタ−265の着陸時支持部材267と接続する。
そして、該ヘリコプタ−265を、上昇動作、ゲレンデ
造設予定地3に向けての一定時間の飛翔動作、この後の
下降動作を順次実行する。すると、冷媒圧縮機77と凝
縮手段79が除外された冷凍装置229を構成するその
他の構成部材を搭載した架台233は、該ヘリコプタ−
265に吊持された状態で空輸された後、ゲレンデ造設
予定地3の脇9に搬送される。
Then, first, in the same manner as described above, the suspension hook mounting screw holes 227 provided at the four positions on the mounting member 231 are respectively attached with the suspension hooks 261 by screwing, and the suspension hooks 261 are attached to the wires 263. And a supporting member 267 for landing of the helicopter-265.
Then, the helicopter-265 sequentially executes the ascending operation, the flying operation toward the planned slope construction site 3 for a fixed time, and the descending operation thereafter. Then, the pedestal 233 having the other components of the refrigeration system 229 excluding the refrigerant compressor 77 and the condenser 79 is mounted on the helicopter.
After being suspended by 265 and transported by air, it is transported to the side 9 of the slope construction site 3.

【0163】ついで、同様にして、製雪装置225を空
輸した後、ヘリコプタ−265を空中停止させると、該
製雪装置225は、該ヘリコプタ−265により吊持さ
れて前記搭載用部材231の製雪装置225の配設位置
直上に仮配設される。つぎに、該ヘリコプタ−265を
若干づつ下降動作させると、該製雪装置225は、ゆっ
くり下降し相対面して配設された一対の水平方向移動阻
止・垂直方向脱着誘導部材211と会合する。そして、
更に一定時間下降動作させると、脱着誘導部位217に
より案内されながら製雪装置225は搭載用部材231
上の所定位置に配設される。
Then, in the same manner, when the helicopter-265 is suspended in the air after the snow-making device 225 is air-transported, the snow-making device 225 is suspended by the helicopter-265 so that the mounting member 231 is manufactured. The snow device 225 is provisionally disposed immediately above the disposition position. Next, when the helicopter-265 is moved down little by little, the snow making device 225 slowly descends and comes into contact with the pair of horizontal movement blocking / vertical removal guide members 211 arranged facing each other. And
When it is further lowered for a certain period of time, the snow-making device 225 is guided by the attachment / detachment guide portion 217 and the snow-making device 225 is mounted on the mounting member 231.
It is arranged at a predetermined position above.

【0164】ついで、凝縮手段79上の前記した吊りフ
ック261を取付け、前記したと同様にしてヘリコプタ
−265にて空輸し、下降動作なさしめると、冷凍装置
229を構成する冷媒圧縮機77を含む凝縮手段79
は、前記したと同様にして前記搭載用部材231上の所
定位置に配置される。
Then, the above-mentioned suspension hook 261 on the condensing means 79 is attached, and the helicopter-265 is air-transported in the same manner as described above, and when the descending operation is performed, the refrigerant compressor 77 constituting the refrigeration system 229 is included. Condensing means 79
Are arranged at predetermined positions on the mounting member 231 in the same manner as described above.

【0165】ついでまた、前記した液化高圧冷媒輸送配
管85の下流側端に設けられたストップ弁連結用取付フ
ランジ232と冷媒流入口33の流入側端に付設された
ストップ弁74とを連結するとともに、気化低圧冷媒輸
送配管73の上流側端に設けられたストップ弁連結用取
付フランジ232と冷媒流出口35の流出側端に付設さ
れたストップ弁74とを連結する。すると、製雪装置2
25と、冷媒圧縮機77と凝縮手段79とが除外された
冷凍装置229とが再度連結される。この後、冷媒流入
口33の流入側端に付設されたストップ弁74と、冷媒
流出口35の流出側端に付設されたストップ弁74を開
状態とする。
Then, the stop valve connecting mounting flange 232 provided at the downstream end of the liquefied high pressure refrigerant transport pipe 85 and the stop valve 74 attached to the inflow end of the refrigerant inlet 33 are connected together. The stop valve connecting mounting flange 232 provided at the upstream end of the vaporized low pressure refrigerant transport pipe 73 is connected to the stop valve 74 provided at the outflow end of the refrigerant outlet port 35. Then, the snow making device 2
25 and the refrigerating apparatus 229 from which the refrigerant compressor 77 and the condensing means 79 are excluded are connected again. Thereafter, the stop valve 74 attached to the inflow side end of the refrigerant inlet 33 and the stop valve 74 attached to the outflow side end of the refrigerant outlet 35 are opened.

【0166】つぎに、気化低圧冷媒輸送配管73の下流
側端に設けられた図示を省略した取付フランジと冷媒圧
縮機77とを連結するとともに、液化高圧冷媒輸送配管
85の上流側端に設けられた図示を省略した取付フラン
ジと液化高圧冷媒取出手段87とを連結すると、冷凍装
置229を構成する冷媒圧縮機77を含む凝縮手段79
と、冷媒圧縮機77と凝縮手段79とが除外された冷凍
装置229とが再度連結される。
Next, an unillustrated mounting flange provided at the downstream end of the vaporized low pressure refrigerant transport pipe 73 is connected to the refrigerant compressor 77, and is provided at the upstream end of the liquefied high pressure refrigerant transport pipe 85. When the mounting flange (not shown) and the liquefied high-pressure refrigerant extracting means 87 are connected, the condensing means 79 including the refrigerant compressor 77 that constitutes the refrigeration system 229.
Then, the refrigerant compressor 77 and the refrigerating apparatus 229 from which the condensing means 79 is excluded are connected again.

【0167】ついで、図示を省略したバキュ−ムポンプ
と弁230とを接続し、該バキュ−ムポンプを所定時間
動作させる。すると、液化高圧冷媒輸送配管85の前記
した位置の配管路に設けられた高圧液側弁234、冷媒
流入口33、製雪装置225内の冷媒蒸発室39、冷媒
流出口35、気化低圧冷媒輸送配管73の配管路の前記
した位置に設けられたストップ弁74間がバキュ−ム状
態となる。
Then, a vacuum pump (not shown) is connected to the valve 230, and the vacuum pump is operated for a predetermined time. Then, the high pressure liquid side valve 234, the refrigerant inflow port 33, the refrigerant evaporation chamber 39 in the snow making device 225, the refrigerant outflow port 35, and the vaporized low pressure refrigerant transportation, which are provided in the pipe line of the above-mentioned position of the liquefied high pressure refrigerant transportation pipe 85, are transported. The space between the stop valves 74 provided at the above-mentioned positions of the pipe path of the pipe 73 is in a vacuum state.

【0168】この後、前記弁230を閉じ、気化低圧冷
媒輸送配管73の配管路に設けられたストップ弁74と
高圧液側弁234を開くと、気化低圧冷媒輸送配管73
と液化高圧冷媒輸送配管85を介して、冷凍装置229
と製雪装置225内の冷媒蒸発室39間をフロン等の冷
媒が循環移動可能な状態となる。かかる状態となると、
請求項(1)、又は、請求項(3)の発明の各実施例に
てい説示した製雪、貯雪、若しくは、散布の各動作が実
行可能となる。
Thereafter, when the valve 230 is closed and the stop valve 74 and the high pressure liquid side valve 234 provided in the pipeline of the vaporized low pressure refrigerant transport pipe 73 are opened, the vaporized low pressure refrigerant transport pipe 73 is opened.
And a refrigerating apparatus 229 through the liquefied high-pressure refrigerant transport pipe 85.
Then, the refrigerant such as CFC can be circulated and moved between the refrigerant evaporation chambers 39 in the snow making device 225. When this happens,
Each of the snow making, snow storing, or spraying operations described in the respective embodiments of the invention of claim (1) or claim (3) can be executed.

【0169】尚、本実施例に係る移設可能なゲレンデ整
備・造設装置269を前記した三分割にする際と、分割
した製雪装置225等の各構成要素を前記した場所に搬
送後の当該場所での再組立をなす際に、前記した位置に
取付られた前記ワンタッチ脱着小口径流体継手とワンタ
ッチ脱着大口径流体継手とをそれぞれ前記した如く脱着
することによっても可能である。
Incidentally, when the transferable slope maintenance / building apparatus 269 according to the present embodiment is divided into three parts as described above, and after the respective constituent elements such as the divided snow making device 225 are transported to the above-mentioned places, It is also possible to detach and attach the one-touch detachable small-diameter fluid joint and the one-touch detachable large-diameter fluid joint, which are attached at the above-mentioned positions, when performing reassembly at a place.

【0170】つぎに、請求項(7)の発明の一実施例と
その作用について説明する。図25は、請求項(7)の
発明の一実施例に係る移設可能なゲレンデ整備・造設装
置を正面からみた場合を示し、図26は同移設可能なゲ
レンデ整備・造設装置に設けられたアウトリガの構成の
一例を一部省略するとともに拡大して斜め正面からみた
場合を示したものである。
Next, one embodiment of the invention of claim (7) and its operation will be described. FIG. 25 shows a transferable slope maintenance / construction apparatus according to an embodiment of the invention of claim (7) when viewed from the front, and FIG. 26 is provided in the transferable slope maintenance / construction apparatus. 2 shows a case in which an example of the configuration of the outrigger is partially omitted and enlarged and seen from an oblique front side.

【0171】図25及び図26に示すように、267
は、断面横長四角形に形成され、正面側と裏面側の一対
のフロント側端長尺脚部材21Aと間近に対面して横設
された断面横長四角形状のアウトリガスライド収容体、
269は、該断面横長四角形状のアウトリガスライド収
容体267内を水平にスライド移動可能な断面横長四角
形に形成され、上面にロックピン穴271が設けられた
アウトリガスライドであり、該アウトリガ収容体267
の両端それぞれにスライド可能となして配設されてい
る。
As shown in FIGS. 25 and 26, 267
Is a laterally elongated quadrangular-shaped outrigger slide accommodating body having a laterally elongated quadrangular shape, which is laterally provided so as to closely face the pair of front side end long leg members 21A on the front side and the back side.
Reference numeral 269 denotes an outrigger slide which is formed in a horizontally long quadrangular cross section that can be slid horizontally in the outrigger slide housing 267 having a horizontally long quadrangular cross section, and has a lock pin hole 271 provided on the upper surface thereof.
Are arranged so as to be slidable on both ends.

【0172】また、273は、断面横長四角形に形成さ
れ、前記アウトリガスライド269に対し若干傾斜して
立設され、取付板体275を介して該アウトリガスライ
ド269の端と連結された断面横長四角形状のアウトリ
ガジャッキ収容体、277は、該アウトリガジャッキ収
容体273内を上下にスライド移動可能に断面横長四角
形に形成されて、該アウトリガジャッキ収容体273の
下方側にスライド可能となして配設され、下端に四角形
の板状に形成されたジャッキフロ−ト279が取付けら
れたアウトリガジャッキである。
Further, 273 is formed in a horizontally long quadrangular cross section, is erected at a slight inclination with respect to the outrigger slide 269, and has a horizontally long quadrangular cross section connected to the end of the outrigger slide 269 through a mounting plate 275. The outrigger jack housing 277 is formed in a horizontally long rectangular cross-section so as to be slidable up and down in the outrigger jack housing 273, and is arranged slidably below the outrigger jack housing 273. This is an outrigger jack to which a jack plate 279 formed in a rectangular plate shape is attached at the lower end.

【0173】図25及び図26に示すように、前記した
アウトリガ収容体267と、一対のアウトリガスライド
269と、一対のアウトリガジャッキ収容体273と、
一対のアウトリガジャッキ277とから本実施例に係る
フロンド側アウトリガ281が構成され、一対のフロン
ト側端長尺脚部材21Aに配設されている。尚、正面側
と裏側の一対のリヤ側端長尺脚部材21Bにも該フロン
ド側アウトリガ281と同様の構成のリヤ側アウトリガ
283が配設されている。
As shown in FIGS. 25 and 26, the above-mentioned outrigger housing 267, a pair of outrigger slides 269, a pair of outrigger jack housings 273,
A front side outrigger 281 according to the present embodiment is constituted by a pair of outrigger jacks 277, and is disposed on the pair of front side end long leg members 21A. A rear outrigger 283 having the same structure as the front outrigger 281 is also arranged on the pair of rear end long leg members 21B on the front and back sides.

【0174】そして、図25に示すように、本実施例に
係る架台285は、前記搭載用部材11と、該搭載用部
材11に請求項(2)の発明の一実施例の説明で説示し
た如く配設された複数の長尺脚部材21と、前記した位
置に配設されたフロント側アウトリガ281と、リヤ側
アウトリガ283とから構成されている。
As shown in FIG. 25, the mount 285 according to this embodiment is explained in the mounting member 11 and the mounting member 11 in the description of the embodiment of the invention of claim (2). The plurality of long leg members 21 arranged as described above, the front side outriggers 281 and the rear side outriggers 283 arranged at the above-described positions.

【0175】尚、図示を省略したが、ヘリコプタ−26
5により吊持して空輸可能な前記架台233に、フロン
ト側アウトリガ281とリヤ側アウトリガ283を同様
に設けて構成した架台287であってもよい。また、図
示を省略したが、前記アウトリガスライド269の水平
方向への移動、前記アウトリガジャッキ277の上下方
向へのスライド移動は油圧シリンダ等の駆動手段により
なされる。
Although not shown, the helicopter 26
A pedestal 287 may be configured by similarly providing a front side outrigger 281 and a rear side outrigger 283 on the pedestal 233 that can be suspended by air and transported by air. Although not shown, the horizontal movement of the outrigger slide 269 and the vertical slide movement of the outrigger jack 277 are performed by a driving means such as a hydraulic cylinder.

【0176】図25に示すように、前記製雪装置71
と、冷凍装置91と、該架台285とから本実施例に係
る移設可能なゲレンデ整備・造設装置288が構成され
ている。係る構成の移設可能なゲレンテ製・造設装置2
88を、組立てた状態でトラック7に搭載して所定時間
陸上輸送すると、ゲレンデ造設予定地3に搬送される。
そして、該ゲレンデ造設予定地3の脇9の地面289が
傾斜等して水平状態でない場合、フロント側アウトリガ
281とリヤ側アウトリガ283とを張出動作させる
と、各アウトリガジャッキ277はアウトリガジャッキ
収容体273の下方からそれぞれ適宜長さ対面する地面
289側にスライド移動する。すると、前記地面289
に各ジャッキフロ−ト279が接地して突っ張るため、
前記架台285は水平状態となり、前記した所定の製雪
動作、散布動作が実行可能となる。
As shown in FIG. 25, the snow making device 71.
The refrigerating apparatus 91 and the gantry 285 constitute a transferable slope maintenance / construction apparatus 288 according to this embodiment. Equipment for erection / construction 2 that can be relocated
When 88 is assembled and mounted on the truck 7 and transported by land for a predetermined time, it is transported to the slope construction planned site 3.
When the ground 289 on the side 9 of the slope construction site 3 is inclined and is not in a horizontal state, when the front outrigger 281 and the rear outrigger 283 are extended, the outrigger jacks 277 are housed in the outrigger jacks. From the bottom of the body 273, it slides to the side of the ground 289 facing each other by an appropriate length. Then, the ground 289
Since each jack float 279 is grounded and stretched,
The gantry 285 is in a horizontal state, and the above-described predetermined snow making operation and spraying operation can be executed.

【0177】一方、前記架台287をヘリコプタ−26
5により吊持して所定時間空輸すると、同様にゲレンデ
造設予定地3に搬送される。そして同様に傾斜等してゲ
レンデ造設予定地3の脇9の地面289が水平状態でな
い場合、前記したと同様にしてフロント側アウトリガ2
81とリヤ側アウトリガ283とを張出動作させると、
前記架台287は水平状態で前記地面289に接地され
る。このため、前記ヘリコプタ−265により吊持して
空輸される後続の前記製雪装置225と、前記冷凍装置
229を構成する冷媒圧縮機77を含む凝縮手段79と
を、前記架台287上の所定位置にスム−ズに搭載して
再組立でき、所定の製雪動作、散布動作等が実行可能と
なる。
Meanwhile, the pedestal 287 is attached to the helicopter 26.
After being suspended by 5 and air-shipped for a predetermined time, it is similarly transported to the planned slope construction site 3. Similarly, when the ground 289 on the side 9 of the planned slope construction site 3 is not horizontal due to a similar inclination or the like, the front side outrigger 2 is processed in the same manner as described above.
81 and the rear outrigger 283 are extended,
The pedestal 287 is horizontally connected to the ground 289. Therefore, the following snow making device 225 suspended by the helicopter-265 and transported by air and the condensing means 79 including the refrigerant compressor 77 constituting the refrigerating device 229 are provided at predetermined positions on the pedestal 287. It can be mounted on a smooth machine and reassembled, and predetermined snow making operation, spraying operation, etc. can be executed.

【0178】本実施例は、請求項(2)記載の発明の一
実施例に係る移設可能なゲレンデ整備・造設装置1を前
提として構成した場合について説明したが、本発明はこ
れに限定されず、請求項(4)記載の発明の一実施例に
係る移設可能なゲレンデ整備・造設装置121、請求項
(5)記載の発明の一実施例に係る移設可能なゲレンデ
整備・造設装置169、請求項(6)記載の発明の一実
施例に係る移設可能なゲレンデ整備・造設装置259を
前提とし、それぞれ前記した位置にフロント側アウトリ
ガ281とリヤ側アウトリガ283を設けて構成する場
合であっても勿論適用可能である。
This embodiment has been described on the premise that the remodelable slope maintenance / construction apparatus 1 according to one embodiment of the invention described in claim (2) is used, but the present invention is not limited to this. First, the transferable slope maintenance / construction apparatus 121 according to the embodiment of the invention described in claim (4) and the transferable slope maintenance / construction apparatus according to the embodiment of the invention described in claim (5). 169, the case where the front side outrigger 281 and the rear side outrigger 283 are provided at the above-mentioned positions on the premise of the removable slope maintenance / construction apparatus 259 according to the embodiment of the invention described in claim (6). However, of course, it is applicable.

【0179】[0179]

【発明の効果】請求項(1)乃至請求項(7)の発明
は、以上詳細に説明した如く構成されているので、次の
ような優れた効果を発揮するものである。請求項(1)
と請求項(3)の発明の構成により、造設、若しくは、
整備するに必要な量の雪を、ゲレンデ造設予定地若しく
は整備対象ゲレンデと間近な位置の複数箇所にそれぞれ
分散製雪するとともに、個別搬送若しくは個別散布と圧
密とを順次反復実行して該ゲレンデ造設予定地又は整備
対象ゲレンデ上に一定間隔にて分散集積圧密し、分散集
積圧密された雪をならしてゲレンデを造設、若しくは、
整備するゲレンデ整備・造設方法としたことから、製雪
された雪を、複数のスクリュウコンベア等の搬送手段に
て受渡しを繰り返しつつ遠距離搬送することに伴う、搬
送途上での圧雪等を起因とする製雪された雪の供給停止
といったことが皆無となった。
Since the inventions of claims (1) to (7) are configured as described in detail above, they exhibit the following excellent effects. Claim (1)
And the construction of the invention of claim (3), or
The amount of snow required for maintenance is distributed to each of the planned construction site or multiple locations close to the maintenance target slope, and individual transportation or individual spraying and consolidation are sequentially repeated, and the skiing is performed. Slopes are constructed on the planned construction site or on the slopes to be maintained at a certain interval by dispersing and consolidating, and then the snow that has been distributed and consolidating is smoothed, or
Due to the slope maintenance / construction method of maintenance, snow-made snow is caused by the pressure snow on the way of transportation, which is caused by the repeated transportation of multiple snow conveyors and other transportation means over long distances. There was no interruption of the snow supply.

【0179】このため、ゲレンデの造設工事、整備工事
が中断することがなく、製雪装置の能力を最大限発揮な
さしめて、計画通りにゲレンデを造設、或いは、整備す
ることができる。そして、係る著効から、スキ−場の安
定経営に多大に寄与するとともに、造設・整備に使用す
る装置のメインテナンス労力を格段に削減することが可
能となった。
Therefore, the slope construction work and maintenance work are not interrupted, and it is possible to construct or maintain the slope according to the plan by maximizing the ability of the snow making device. Due to this remarkable effect, it is possible to greatly contribute to the stable management of ski fields and it is possible to significantly reduce the maintenance labor of the equipment used for the construction and maintenance.

【0180】また、請求項(2)、請求項(4)、及
び、請求項(5)の発明の構成により、ゲレンデ整備・
造設方法の実施に用いられるゲレンデ整備・造設装置
を、トラック等の陸上輸送手段に搭載可能な大きさと重
量に形成して自由に目的地に移設可能としたことから、
必要な台数のゲレンデ整備・造設装置を必要な時だけ、
迅速に造設・整備現場に搬送して分散配置することがで
きるとともに、最小台数のゲレンデ整備・造設装置で最
大数のゲレンデを造設若しくは整備することができる。
[0180] Further, due to the constitution of the inventions of claims (2), (4) and (5), the slope maintenance /
Since the slope maintenance / construction equipment used to carry out the construction method is formed into a size and weight that can be mounted on a land transportation means such as a truck and can be freely relocated to the destination,
Only when you need the necessary number of slope maintenance and construction equipment,
It can be quickly transported to the construction / maintenance site and distributed and arranged, and the maximum number of slopes can be constructed or maintained with the minimum number of slope maintenance / construction equipment.

【0181】さらに、このことから、多数の製雪装置を
収容する製雪装置用大型建屋、大量の雪を貯雪する大容
量の貯雪容器を収容するための貯雪用大型建屋等の建
設、これら大型建屋間を連絡するスクリュウコンベア等
の多数の搬送手段、貯雪用大型建屋とゲレンデ造設予定
地間、若しくは、整備対象ゲレンデ間に雪を遠距離搬送
するための搬送手段や配管等を設ける必要がなく、ゲレ
ンデを造設、整備するコストが格段に低下する。係るコ
ストの低減効果が顕著であるので、人工雪を大量に製
雪、散布等してゲレンデを造設・整備するシステムの普
及を飛躍的に図ることができ、多数のスキ−ファンが手
軽にスキ−を楽しむことが可能となる。
Further, from this, the construction of a large building for a snow making device that accommodates a large number of snow making devices, a large building for a snow storage that accommodates a large capacity snow storage container that stores a large amount of snow, etc. It is necessary to install a large number of transportation means such as screw conveyors that connect the buildings, a transportation means and pipes for long-distance transportation of snow between the large snow storage building and the planned slope construction site, or between the maintenance target slopes. The cost of constructing and maintaining the slopes will be dramatically reduced. Since the cost reduction effect is remarkable, it is possible to dramatically spread the system for constructing and maintaining the slopes by making and spraying a large amount of artificial snow, making it easy for many ski fans. It becomes possible to enjoy skiing.

【0182】さらに、請求項(6)の発明の構成によ
り、ヘリコプタ−等の航空輸送手段でゲレンデ造設予定
地まで空輸可能な構造としたことから、トラック等の陸
上輸送手段が進入不能な奥地であってもゲレンデの造設
が可能となり、また、ゲレンデ整備・造設装置の移設
を、より一層迅速に実行可能となった。
Further, according to the structure of the invention of claim (6), since the structure is such that the air transportation means such as a helicopter can be air-transported to the planned construction site of the slope, the land transportation means such as a truck cannot enter. However, it became possible to construct a slope, and it was possible to move the slope maintenance / construction equipment more quickly.

【0183】さらにまた、請求項(7)の発明の構成に
より、傾斜等して水平状態でない地面であっても、当該
地面を水平に整地することなく、そのままの状態で当該
地面上にゲレンデ整備・造設装置を移設し製雪、散布等
を開始することができる。
Further, according to the structure of the invention of claim (7), even if the ground is not horizontal due to inclination or the like, the ground is not leveled and the slope is maintained on the ground as it is.・ The construction equipment can be relocated to start snow making and spraying.

【図面の簡単な説明】[Brief description of drawings]

【図1】請求項(1)の発明のゲレンデ整備・造設方法
の一実施例を示したフロ−チャ−トである。
FIG. 1 is a flow chart showing an embodiment of a slope maintenance / construction method of the invention of claim (1).

【図2】同実施例のうちゲレンデを造設する段階を模式
的に示した平面図である。
FIG. 2 is a plan view schematically showing a step of constructing a slope in the same example.

【図3】請求項(1)の発明のゲレンデ整備・造設方法
の変形実施例を示したフロ−チャ−トである。
FIG. 3 is a flow chart showing a modified embodiment of the slope maintenance / construction method of the invention of claim (1).

【図4】同変形実施例のうちゲレンデを造設若しくは整
備する段階を模式的に示した平面図である。
FIG. 4 is a plan view schematically showing a step of constructing or maintaining a slope in the modified example.

【図5】請求項(2)の発明の一実施例に係る移設可能
なゲレンデ整備・造設装置を示した正面図である。
FIG. 5 is a front view showing a remountable slope maintenance / construction apparatus according to an embodiment of the invention as set forth in claim (2).

【図6】同移設可能なゲレンデ整備・造設装置を示した
平面図である。
FIG. 6 is a plan view showing the slope maintenance / construction apparatus that can be relocated.

【図7】同移設可能なゲレンデ整備・造設装置を構成す
る製雪装置を示した斜視図である。
FIG. 7 is a perspective view showing a snow making device that constitutes the slope maintenance / building device that can be relocated.

【図8】同製雪装置を構成する散水手段を示した一部省
略斜視図である。
FIG. 8 is a partially omitted perspective view showing water sprinkling means constituting the snow making apparatus.

【図9】同製雪装置の内部構造を示した一部断面正面図
である。
FIG. 9 is a partial cross-sectional front view showing the internal structure of the snow making apparatus.

【図10】請求項(3)の発明のゲレンデ整備・造設方
法の一実施例を示したフロ−チャ−トである。
FIG. 10 is a flow chart showing an embodiment of the slope maintenance / construction method of the invention of claim (3).

【図11】同実施例のうちゲレンデを造設する段階を模
式的に示した平面図である。
FIG. 11 is a plan view schematically showing a step of constructing a slope in the same example.

【図12】請求項(3)の発明のゲレンデ整備・造設方
法の変形実施例を示したフロ−チャ−トである。
FIG. 12 is a flowchart showing a modified embodiment of the slope maintenance / construction method of the invention of claim (3).

【図13】同変形実施例のうちゲレンデを造設若しくは
整備される段階を模式的に示した平面図である。
FIG. 13 is a plan view schematically showing a step of constructing or maintaining a slope in the modified example.

【図14】請求項(4)の発明の一実施例に係る移設可
能なゲレンデ整備・造設装置を示した正面図である。
FIG. 14 is a front view showing a transferable slope maintenance / construction apparatus according to an embodiment of the invention as set forth in claim (4).

【図15】同移設可能なゲレンデ整備・造設装置を構成
する雪散布機構の一例を示した拡大側面図である。
FIG. 15 is an enlarged side view showing an example of a snow spraying mechanism that constitutes the slope maintenance / construction apparatus that can be relocated.

【図16】同雪散布機構の一例を示した拡大断面図であ
る。
FIG. 16 is an enlarged cross-sectional view showing an example of the snow spraying mechanism.

【図17】請求項(5)の発明の一実施例に係る移設可
能なゲレンデ整備・造設装置を示した正面図である。
FIG. 17 is a front view showing a remountable slope maintenance / construction device according to an embodiment of the invention (5).

【図18】同移設可能なゲレンデ整備・造設装置を構成
する雪一時貯雪兼用送出機構の一例と該雪一時貯雪兼用
送出機構の払出口と対面して配設された雪散布機構の一
例を示した拡大側面図である。
FIG. 18 shows an example of a snow temporary snow storage / delivery mechanism that constitutes the slope maintenance / construction device that can be relocated, and an example of a snow spraying mechanism arranged to face a payout opening of the snow temporary snow storage / delivery mechanism. It is the expanded side view shown.

【図19】同雪一時貯雪兼用送出機構の一例と同雪散布
機構の一例を示した一部断面拡大図である。
FIG. 19 is an enlarged partial cross-sectional view showing an example of the snow temporary delivery and snow storage delivery mechanism and an example of the snow spraying mechanism.

【図20】請求項(6)の発明の一実施例に係る移設可
能なゲレンデ整備・造設装置を三分割した状態で示した
正面図である。
FIG. 20 is a front view showing a transferable slope maintenance / construction apparatus according to an embodiment of the invention (6) in a state in which it is divided into three parts.

【図21】水平方向移動阻止・垂直方向脱着誘導部材と
吊りフック取付用螺子案が搭載用部材上に設けられた状
態を示した平面図である。
FIG. 21 is a plan view showing a state in which a horizontal movement blocking / vertical removal guide member and a hanging hook attachment screw plan are provided on the mounting member.

【図22】水平方向移動阻止・垂直方向移動誘導部材の
一例を示した一部切断拡大図である。
FIG. 22 is a partially cutaway enlarged view showing an example of a horizontal movement blocking / vertical movement guiding member.

【図23】散水手段を構成する散水皿の構成を示した一
部断面拡大図である。
FIG. 23 is an enlarged partial cross-sectional view showing the structure of a water spray tray that constitutes water spraying means.

【図24】冷媒蒸発室と、該冷媒蒸発室と連通する冷媒
流入口並びに冷媒流出口の構成の一例を示した一部省略
断面図である。
FIG. 24 is a partially omitted cross-sectional view showing an example of the configurations of a refrigerant evaporation chamber, a refrigerant inlet and a refrigerant outlet communicating with the refrigerant evaporation chamber.

【図25】請求項(7)の発明の一実施例に係る移設可
能なゲレンデ整備・造設装置を示した正面図である。
FIG. 25 is a front view showing a remodelable slope maintenance / construction device according to an embodiment of the invention (7).

【図26】アウトリガの一例を示した一部省略拡大斜視
図である。
FIG. 26 is a partially omitted enlarged perspective view showing an example of an outrigger.

【図27】従来の一般的なゲレンデ整備・造設装置の構
成の概要を模式的に示した斜視図である。
FIG. 27 is a perspective view schematically showing the outline of the configuration of a conventional general slope maintenance / building device.

【図28】従来のゲレンデ整備・造設装置の構成の一例
を示した説明図である。
FIG. 28 is an explanatory diagram showing an example of the configuration of a conventional slope maintenance / construction device.

【図29】従来のゲレンデ整備・造設装置の構成の他の
例を示した説明図である。
FIG. 29 is an explanatory diagram showing another example of the configuration of a conventional slope maintenance / construction device.

【図30】スクリュウコンベア内で雪が搬送不能となる
状態を示した一部省略拡大断面図である。
FIG. 30 is a partially omitted enlarged cross-sectional view showing a state in which snow cannot be conveyed in the screw conveyor.

【符号の説明】[Explanation of symbols]

1 請求項(2)の発明の一実施例に係る移設可能
なゲレンデ整備・造設装置 3 ゲレンデ造設予定地 27 架台 29 基台 39 冷媒蒸発室 41 製雪ドラム 47 刃物台 58 散水手段 61 給水手段 71 製雪装置 74 ストップ弁 89 膨張弁 91 冷凍装置 121 請求項(4)の発明の一実施例に係る移設可能
なゲレンデ整備・造設装置 123 円錐形シュ−ト 131 ケ−シング 149 回動投射体 153 ブレ−ド 161 雪散布機構 169 請求項(5)の発明の一実施例に係る移設可能
なゲレンデ整備・造設装置 171 長筒状の一時貯雪兼用送出案内部材 183 送出部材 193 送出用駆動手段 197 雪一時貯雪兼用送出機構 211 水平方向移動阻止・垂直方向脱着案内部材 225 製雪装置 229 冷凍装置 230 弁 232 ストップ弁連結用フランジ 233 架台 259 請求項(6)の発明の一実施例に係る移設可能
なゲレンデ整備・造設装置 261 吊りフック 265 ヘリコプタ− 281 フロント側アウトリガ 283 リヤ側アウトリガ 288 請求項(7)の発明の一実施例に係る移設可能
なゲレンデ整備・造設装置
1 Removable slope maintenance / construction device according to an embodiment of the invention of claim (2) 3 Scheduled slope construction site 27 Stand 29 Base 39 Refrigerant evaporation chamber 41 Snow making drum 47 Turret 58 Sprinkling means 61 Water supply Means 71 Snow-making device 74 Stop valve 89 Expansion valve 91 Refrigeration device 121 Transferable slope maintenance / construction device 123 according to one embodiment of the invention of claim (4) Cone-shaped shoe 131 Casing 149 Rotation Projector 153 Blade 161 Snow spraying mechanism 169 Transferable slope maintenance / construction device according to one embodiment of the invention of claim (5) 171 Long tubular temporary snow storage / delivery guide member 183 Delivery member 193 For delivery Driving means 197 Temporary snow storage and delivery mechanism 211 Horizontal movement prevention / vertical removal guide member 225 Snow making device 229 Refrigeration device 230 Valve 232 Up valve connection flange 233 Frame 259 Removable slope maintenance / construction device 261 according to one embodiment of the invention of claim (6) 261 Lifting hook 265 Helicopter 281 Front side outrigger 283 Rear side outrigger 288 Claim (7) ) A relocatable slope maintenance / construction device according to an embodiment of the invention

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 オフシ−ズンにゲレンデの造設を開始す
る段階でゲレンデ造設規模とゲレンデ造設地の気象条件
を勘案して製雪量を算出するステップ1と、該算出され
た製雪量に基づきゲレンデ造設地に搬入するゲレンデ整
備・造設装置の台数を把握し、各ゲレンデ整備・造設装
置を一定間隔にてゲレンデ造設予定地の脇に分散配置す
るステップ2を予備的に順次実行し、ついで、分散配置
された各ゲレンデ整備・造設装置を製雪動作なさしめて
各ゲレンデ整備・造設装置それぞれの直下に分散貯雪す
るステップ3を実行し、つぎに、分散貯雪された雪をゲ
レンデ造設予定地上に個別搬送して圧密、又は、整備が
必要なゲレンデ上に個別搬送して圧密するステップ4を
実行し、ついで、該ステップ3と該ステップ4を反復実
行してゲレンデ造設予定地上に造設に必要な量の雪、又
は、整備が必要なゲレンデ上に整備に必要な量の雪を分
散集積圧密するステップ5を実行し、しかる後に、分散
集積圧密された雪をならして適宜厚さのスロ−プを形成
するステップ6を実行する手順からなるゲレンデ整備・
造設方法。
1. A step 1 of calculating a snow production amount in consideration of a slope construction scale and a meteorological condition of the slope construction site at a stage of starting the construction of a slope on an off-season, and the calculated snow production. Preliminary step 2 of grasping the number of slope maintenance / construction equipment to be carried in to the slope construction site based on the amount and disperse each slope maintenance / construction equipment at the side of the planned slope construction site at regular intervals. Then, perform the step 3 in which each of the distributed slope maintenance / building devices is not snow-made and the snow is distributed directly under each of the slope maintenance / building devices, and then the distributed snow is stored. Perform step 4 of individually transporting and consolidating the snow to the ground where the slope is to be constructed or individually transporting it to the slope that requires maintenance, and then repeating step 3 and step 4 Slope construction Execute step 5 to disperse and consolidate the amount of snow required for construction on the planned ground, or the amount of snow required for maintenance on the slope where maintenance is required. Slope maintenance consisting of the procedure to execute step 6 to form a slop of appropriate thickness.
Construction method.
【請求項2】 搭載用部材と、該搭載用部材の下側に取
付けられた複数の脚部材とから構成された架台と、 該搭載用部材の一側上に設けられた基台と、ストップ弁
が付設されている場合がある冷媒流入口と冷媒流出口が
設けられた外筒と該外筒の内側に設けられた内筒と該内
筒と外筒間に設けられた冷媒蒸発室とから構成され前記
基台上に取付けられた製雪ドラムと、前記内筒の中心位
置に相当する前記基台上に載置された軸受部材と、下端
部が該軸受部材と回動可能に連結されるとともに上端部
が若干前記製雪ドラムから突出なさしめて鉛直に立設さ
れた回動軸と、該回動軸の外周に取付けられ刃物台と、
前記内筒の内面と若干の隙間をもって対面した状態で該
刃物台の側方に脱着可能に取付けられた削り取り刃と、
該回動軸の上端部寄り位置に取付けられ前記内筒の内面
と対面なさしめた多数の散水用ノズルを備えた散水手段
と、該回動軸の上端部と連動連結された駆動手段と、前
記散水手段と連通され前記製雪ドラム外の前記搭載用部
材に配設された給水手段とからなる製雪装置と、 上流側端が前記冷媒流出口と連通され配管路にストップ
弁が備えられている場合がある気化低圧冷媒輸送配管
と、流入側端が該気化低圧冷媒輸送配管の下流側端と連
通された冷媒圧縮機と、上流側端が該冷媒圧縮機の流出
側端と連通された凝縮手段と、上流側端が該凝縮手段の
流出側端と下流側端が前記冷媒流入口とそれぞれ連通さ
れ配管路にストップ弁が備えられている場合がある液化
高圧冷媒輸送配管と、該液化高圧冷媒輸送配管の配管路
に設けられた膨張弁とから構成され、前記搭載用部材の
他側上に設けられた冷凍装置と、 から構成されたゲレンデ整備・造設装置において、 前記架台と、製雪装置と、冷凍装置とが相互に連結され
た際に陸上輸送手段に搭載可能な大きさと重量に形成さ
れ、且つ、前記脚部材が長尺脚部材であって前記冷媒装
置が搭載されている前記搭載用部材の他側に偏って取付
けられ、前記製雪装置の直下に製雪された雪の貯雪・搬
送空間が現出されていることを特徴とする移設可能なゲ
レンデ整備・造設装置。
2. A mount comprising a mounting member and a plurality of leg members attached to the lower side of the mounting member, a base provided on one side of the mounting member, and a stop. An outer cylinder provided with a refrigerant inlet and a refrigerant outlet, which may be provided with a valve, an inner cylinder provided inside the outer cylinder, and a refrigerant evaporation chamber provided between the inner cylinder and the outer cylinder. A snow-making drum mounted on the base, a bearing member mounted on the base corresponding to the center position of the inner cylinder, and a lower end rotatably connected to the bearing member. And a vertical rotation shaft whose upper end is slightly protruded from the snow-making drum and is erected vertically, and a tool rest mounted on the outer periphery of the rotation shaft,
A shaving blade detachably attached to the side of the tool rest in a state of facing the inner surface of the inner cylinder with a slight gap,
A sprinkling means attached to a position near the upper end of the rotating shaft and provided with a large number of sprinkling nozzles facing the inner surface of the inner cylinder; and a driving means interlockingly connected to the upper end of the rotating shaft. A snow making device comprising a water supply means connected to the water sprinkling means and arranged on the mounting member outside the snow making drum; and an upstream end connected to the refrigerant outlet and a stop valve provided in a pipeline. In some cases, the vaporized low-pressure refrigerant transport pipe, a refrigerant compressor whose inflow end communicates with the downstream end of the vaporized low-pressure refrigerant transport pipe, and an upstream end communicates with the outflow end of the refrigerant compressor. A condensing means, a liquefied high-pressure refrigerant transport pipe in which an upstream end communicates with an outflow end and a downstream end of the condensing means, respectively, and the refrigerant inflow port may be equipped with a stop valve; From the expansion valve provided in the pipeline of the liquefied high-pressure refrigerant transport pipe A slope maintenance / construction device configured of a refrigeration device provided on the other side of the mounting member, wherein the frame, the snow making device, and the refrigeration device are connected to each other. The leg member is a long leg member, and the leg member is attached to the other side of the mounting member on which the refrigerant device is mounted. Slope storage / construction equipment that can be relocated, characterized in that a snow storage / transportation space for snow produced is exposed immediately below the snow production equipment.
【請求項3】 オフシ−ズンにゲレンデの造設を開始す
る場合のみ請求項(1)記載のステップ1とステップ2
を予備的に順次実行し、つぎに、一定時間継続して各ゲ
レンデ整備・造設装置を製雪動作なさしめるとともに製
雪された雪をゲレンデ造設予定地側、若しくは、整備が
必要なゲレンデ側に散布して分散貯雪するステップ7を
実行し、ついで、分散貯雪された雪を圧密し分散貯雪圧
密するステップ8を実行し、つぎに、該ステップ7とス
テップ8を反復実行してゲレンデ造設予定地上に造設に
必要な量の雪を分散集積圧密し、又は、整備が必要なゲ
レンデ上に整備に必要な量の雪を分散集積圧密するステ
ップ9を実行し、しかる後に、請求項(1)記載のステ
ップ6を実行する手順からなるゲレンデ整備・造設方
法。
3. The step 1 and the step 2 according to claim 1 only when starting the construction of a slope on an off-season.
The preliminary snowboarding is carried out sequentially, and then the snow maintenance operation for each slope is continued for a certain period of time, and the snow-made snow is removed from the slopes where the slopes are to be built or where maintenance is required. Step 7 of spraying to the side to disperse and store the snow is executed, and then step 8 of consolidating the distributed and accumulated snow and consolidating the distributed snow is executed, and then repeating steps 7 and 8 to execute the slope forming. Performing step 9 of dispersing and consolidating the amount of snow required for construction on the planned ground, or consolidating and consolidating the amount of snow required for maintenance on the slope where maintenance is required. (1) A slope maintenance / construction method comprising a procedure of performing step 6 described.
【請求項4】 請求項(2)記載のゲレンデ整備・造設
装置において、請求項(2)記載の架台と、製雪装置
と、冷凍装置とが相互に連結された際に陸上輸送手段に
搭載可能な大きさと重量に形成され、また、請求項
(2)記載の基台の直下にシュ−トを設けしめ、さら
に、 上方側外周に開口部が該開口部を起点として一定角度離
れた位置に送出口がそれぞれ設けられ該開口部が前記シ
ュ−トの下端と対面するようなして該シュ−トの下方位
置に配設されたケ−シングと、該ケ−シング内に配設せ
しめた複数のブレ−ドが該ケ−シングの回動中心位置に
貫設された回動軸に一定角度間隔にて取付けられた回動
投射体と、内部空間が前記ブレ−ドの回動接線を含むよ
うなして前記送出口に装着され先端に投射口が設けられ
た投雪風胴と、前記回動軸と連動連結された投雪用駆動
手段とから構成された雪散布機構が備えられていること
を特徴とする移設可能なゲレンデ整備・造設装置。
4. The slope maintenance / construction apparatus according to claim (2), wherein the land transportation means is used when the gantry according to claim (2), the snow making apparatus, and the refrigeration apparatus are mutually connected. It is formed to have a size and weight that can be mounted, and a skirt is provided immediately below the base according to claim (2), and further, an opening is formed on the outer periphery of the upper side at a certain angle from the opening as a starting point. And a casing arranged at a lower position of the stool so that the opening faces the lower end of the shunt and the casing is disposed in the casing. A plurality of blades mounted on a rotation shaft penetrating the rotation center of the casing at a constant angular interval, and an internal space having a rotation tangent to the blade. A snow throwing wind tunnel equipped with a projection opening at the tip and attached to the delivery port, Relocatable slopes improvement and Zo設 apparatus snow spray mechanism is composed of a shaft and operatively connected to the projecting snow driving means, characterized in that is provided.
【請求項5】 請求項(2)記載のゲレンデ整備・造設
装置において、請求項(2)記載の架台と、製雪装置
と、冷凍装置とが相互に連結された際に陸上輸送手段に
搭載可能な大きさと重量に形成され、また、請求項
(2)記載の基台の直下にシュ−トを設けしめ、さら
に、 一側に受入れ口が他側に払出口がそれぞれ設けられ該受
入れ口が該シュ−トの下端と対面して該シュ−トの下方
に水平に横設された中空の一時貯雪兼用送出案内部材
と、連結部を除いて該中空の一時貯雪兼用送出案内部材
に貫入され周囲に複数の送出羽根が一定間隔にて取付け
られた送出手段と、該送出手段の連結部と連動連結され
た送出用駆動手段と、から構成された雪一時貯雪兼用送
出機構と、 請求項(4)記載の開口部を前記払出口と対面なさしめ
て配設された請求項(4)記載の雪散布機構と、 が備えられていることを特徴とする移設可能なゲレンデ
整備・造設装置。
5. The slope maintenance / construction apparatus according to claim (2), wherein the gantry according to claim (2), the snow making apparatus, and the refrigerating apparatus are connected to each other by land transportation means. It is formed to have a size and weight that can be mounted, and a skirt is provided directly under the base according to claim (2). Further, a receiving port is provided on one side and a payout port is provided on the other side. A hollow temporary snow storage / delivery guide member horizontally installed below the sout facing the lower end of the shunt, and a hollow temporary snow storage / delivery guide member except for the connecting portion. A snow temporary snow storage / delivery mechanism comprising: a delivery means that penetrates and has a plurality of delivery blades attached to the periphery at regular intervals; and a delivery drive means that is interlockingly connected with a connecting portion of the delivery means. The opening according to item (4) is arranged so as not to face the outlet. Motomeko (4) and snow spray mechanism according, relocatable slopes improvement and Zo設 apparatus characterized by is provided.
【請求項6】 請求項(2)、請求項(4)、請求項
(5)いずれかに記載の架台を構成する搭載用部材上の
冷媒圧縮機及び凝縮手段配設位置と製雪装置配設位置に
それぞれ複数の水平方向移動阻止・垂直方向脱着誘導部
材が設けられるとともに複数の吊り上げ平衡位置それぞ
れに吊りフック取付用穴若しくはフック取付用螺子が設
けられ、請求項(2)、請求項(4)、請求項(5)い
ずれかに記載の凝縮手段と製雪装置それぞれの複数の吊
り上げ平衡位置に吊りフック取付用穴若しくは吊りフッ
ク取付用螺子が設けられ、請求項(2)、請求項
(4)、請求項(5)いずれかに記載の冷媒流入口と冷
媒流出口それぞれにストップ弁が付設され、請求項
(2)、請求項(4)、請求項(5)いずれかに記載の
気化低圧冷媒輸送配管の配管路にストップ弁が設けられ
るとともに、該気化低圧冷媒輸送配管と請求項(2)、
請求項(4)、請求項(5)いずれかに記載の液化高圧
冷媒輸送配管それぞれの両端に取付フランジが設けられ
該取付フランジを介して、若しくは、それぞれの両端に
クイック脱着流体継手が設けられ該クイック脱着流体継
手を介して前記製雪装置側と前記凝縮手段側とそれぞれ
連結され、更に、該気化低圧冷媒輸送配管の配管路にバ
キュ−ムポンプと接続可能な弁が、該液化高圧冷媒輸送
配管の凝縮手段寄りの配管路に高圧液側弁がそれぞれ設
けられていることを特徴とする請求項(2)、請求項
(4)、又は、請求項(5)いずれかに記載の移設可能
なゲレンデ整備・造設装置。
6. A refrigerant compressor / condensing means arrangement position and a snow making device arrangement on a mounting member constituting the gantry according to any one of claims (2), (4) and (5). Claims (2) and (), wherein a plurality of horizontal movement prevention / vertical attachment / detachment guide members are provided at the respective installation positions, and a suspension hook mounting hole or a hook mounting screw is provided at each of the plurality of lifting equilibrium positions. 4) The suspension hook mounting holes or the suspension hook mounting screws are provided at a plurality of suspension equilibrium positions of the condensing means and the snow making device according to any one of claims 4 and 5, respectively. A stop valve is attached to each of the refrigerant inflow port and the refrigerant outflow port according to any one of (4) and (5), and any one of claims (2), (4), and (5) is provided. Evaporation of low pressure refrigerant in the pipeline A stop valve is provided, and the vaporized low-pressure refrigerant transport pipe and claim (2) are provided.
A mounting flange is provided at each end of the liquefied high-pressure refrigerant transport pipe according to any one of claims (4) and (5), and a quick desorption fluid coupling is provided through the mounting flange or at each end. A valve that is connected to the snow making device side and the condensing means side via the quick desorption fluid coupling, respectively, and further has a valve connectable to a vacuum pump in a pipeline of the vaporized low pressure refrigerant transport pipe, The high-pressure liquid side valve is provided in each of the pipe passages near the condensing means of the pipe, and the transfer according to any one of claims (2), (4), or (5) is possible. Slope maintenance and construction equipment.
【請求項7】 請求項(2)記載の複数の長尺脚部材で
あってフロント側端とリヤ側端に位置する長尺脚部材、
若しくは、請求項(4)、請求項(5)記載の複数の中
尺脚部材であってフロント側端とリヤ側端に位置する中
尺脚部材にそれぞれフロントアウトリガとリヤアウトリ
ガが設けられていることを特徴とする請求項(2)、請
求項(4)、請求項(5)、又は、請求項(6)いずれ
かに記載の移設可能なゲレンデ整備・造設装置。
7. A plurality of long leg members according to claim 2, wherein the long leg members are located at a front end and a rear end.
Alternatively, in the plurality of medium-sized leg members according to claims (4) and (5), a front outrigger and a rear outrigger are provided on the medium-sized leg members located at the front end and the rear end, respectively. The transferable slope maintenance / construction device according to any one of claims (2), (4), (5), or (6).
JP9142395A 1995-03-25 1995-03-25 Slope preparation and development method and movable slope preparation and development device employed for these methods Pending JPH08261616A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9142395A JPH08261616A (en) 1995-03-25 1995-03-25 Slope preparation and development method and movable slope preparation and development device employed for these methods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9142395A JPH08261616A (en) 1995-03-25 1995-03-25 Slope preparation and development method and movable slope preparation and development device employed for these methods

Publications (1)

Publication Number Publication Date
JPH08261616A true JPH08261616A (en) 1996-10-11

Family

ID=14025974

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9142395A Pending JPH08261616A (en) 1995-03-25 1995-03-25 Slope preparation and development method and movable slope preparation and development device employed for these methods

Country Status (1)

Country Link
JP (1) JPH08261616A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002066747A1 (en) * 2001-02-13 2002-08-29 Kabushiki Kaisha Piste Snow Industries System and method for maintaining ski run in skifield by utilizing artificial snow producing machine
JP2016090207A (en) * 2014-11-11 2016-05-23 アイスマン株式会社 Artificial snowfall device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002066747A1 (en) * 2001-02-13 2002-08-29 Kabushiki Kaisha Piste Snow Industries System and method for maintaining ski run in skifield by utilizing artificial snow producing machine
JP2016090207A (en) * 2014-11-11 2016-05-23 アイスマン株式会社 Artificial snowfall device

Similar Documents

Publication Publication Date Title
EP0378636B1 (en) Snow making equipment and method
US5004151A (en) Method and apparatus for making snow
US9909796B2 (en) Snow making method and apparatus
US2968164A (en) Method of generating snow
US3257815A (en) Method and apparatus for the largescale production of snow fields for sports use
US4836446A (en) Device and method for producing artificial snow
US4914923A (en) Method of covering artificial alpine- or nordic-skiing tracks with snow and means for implementing the method
JP2014506668A (en) The method of holding snow and ice
US11828515B2 (en) Method and apparatus for making falling snow
US20090114735A1 (en) Snowmaking methods
JPH08261616A (en) Slope preparation and development method and movable slope preparation and development device employed for these methods
WO1991010104A1 (en) Snow making apparatus
JPH0730984B2 (en) Snowmaking method at indoor ski resort
US7124521B1 (en) Apparatus for resurfacing an ice surface
US20100202834A1 (en) Snow transportation system
JPH0755307A (en) Method for snow making on indoor artificial skiing ground
JPH01312371A (en) Method for causing fall of artificial snow and ice
JPH09133444A (en) Ice making machine in skiing ground
JPH06300405A (en) Snow-making machine
JPH06180169A (en) Artificial snowmaking machine
JPH08200909A (en) Conveying system for icy snow
JPH02154964A (en) Ice heat storage chamber
CN110799254A (en) Climate strategy for indoor entertainment facilities
JPH04302975A (en) Snow producing machine
JPH0742125A (en) Method and device for conveying and sprinkling snow ice grain