JPH0765455B2 - Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint - Google Patents

Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint

Info

Publication number
JPH0765455B2
JPH0765455B2 JP1138368A JP13836889A JPH0765455B2 JP H0765455 B2 JPH0765455 B2 JP H0765455B2 JP 1138368 A JP1138368 A JP 1138368A JP 13836889 A JP13836889 A JP 13836889A JP H0765455 B2 JPH0765455 B2 JP H0765455B2
Authority
JP
Japan
Prior art keywords
tunnel
shield
trailing
branch
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1138368A
Other languages
Japanese (ja)
Other versions
JPH035600A (en
Inventor
義雄 足立
敏則 水谷
英人 真下
俊夫 鈴木
宗男 吉村
修二 倉木
英樹 荻原
稔 中村
徹 渡辺
寿夫 林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Nippon Steel Corp
Nishimatsu Construction Co Ltd
Sato Kogyo Co Ltd
Shimizu Corp
Original Assignee
Kajima Corp
Nippon Steel Corp
Nishimatsu Construction Co Ltd
Sato Kogyo Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Nippon Steel Corp, Nishimatsu Construction Co Ltd, Sato Kogyo Co Ltd, Shimizu Corp filed Critical Kajima Corp
Priority to JP1138368A priority Critical patent/JPH0765455B2/en
Publication of JPH035600A publication Critical patent/JPH035600A/en
Publication of JPH0765455B2 publication Critical patent/JPH0765455B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、シールド工法によって地下道路のインター
チェンジの分岐・合流部、地下水路の合流部、或いは地
下鉄の分岐部分等を構築する際に、行われるシールドト
ンネルの分岐・接合部の施工方法及びその施工法におい
て使用される分岐・接合部の仮設隔壁施工装置に関す
る。
DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention is applied to the construction of a junction / junction of an underground road interchange, a junction of an underground waterway, a junction of a subway, etc. by a shield construction method. The present invention relates to a method for constructing a branch / joint of a shield tunnel and a temporary partition construction device for the branch / joint used in the method.

〔従来の技術及び発明が解決しようとする課題〕[Problems to be Solved by Prior Art and Invention]

従来シールドトンネルの分岐・接合部の施工は、いわゆ
るオープンカット工法によって行われている。
Conventionally, the branch / joint construction of shield tunnels has been performed by the so-called open cut method.

この種の施工方法は、トンネルの形状に合わせて土留め
を行い、この土留めの内側を地上から掘削した後、地下
構造物を構築後埋め戻すもので、浅い場合には経済的な
方法であるが、深くなるに伴って施工が困難になる等の
課題があった。
This type of construction method is to earth retaining according to the shape of the tunnel, excavating the inside of this earth retaining from the ground, and then backfilling the underground structure, and if it is shallow, it is an economical method. However, there was a problem that construction became difficult as the depth increased.

このため、地下構造物が深い場合は、立て坑とトンネル
とを組み合わせて行われるが、トンネルが序々に分岐す
るようなインタージェンジ等では立坑が大きくなり不経
済施工を強いられる等の課題がある。
For this reason, when the underground structure is deep, it is carried out by combining the vertical shaft and the tunnel, but there is a problem that the vertical shaft becomes large and uneconomical construction is forced in the Intergenge where the tunnel gradually branches. is there.

また、地盤改良などを併用し、NATM工法で処理する方法
もあるが、施工域が相当深くなると、信頼性の面で地盤
が余程安定していないと採用できない等の課題があっ
た。
There is also a method of using the NATM method in combination with ground improvement, but when the construction area becomes considerably deep, there was a problem that it could not be adopted if the ground was not very stable in terms of reliability.

さらに、2本のトンネルを分岐・接合部において、可能
な限り近接させて構築し、その後で分岐・接合部のセグ
メントの一部を取り外すことにより、分岐・接合部を構
築する方法も行われているが、セグメントの一部を取り
外したときに地山が大きく露出し、この露出部の地山を
自立させるために、大規模な凍結工法や薬液注入工法等
の地盤改良を行う必要があり、工費が大幅に嵩む等の課
題があった。
Furthermore, there is also a method of constructing a branch / junction by constructing two tunnels at a branch / junction as close as possible, and then removing a part of the segment of the branch / junction. However, the ground is greatly exposed when a part of the segment is removed, and in order to make this exposed ground self-sustaining, it is necessary to carry out ground improvement such as large-scale freezing construction method and chemical injection method. There was a problem that the construction cost increased significantly.

この発明は、以上の課題を解決するためになされたもの
で、地盤改良の施工範囲が低減でき、補助工法を必要と
せず、施工性、経済性、さらに、施工時の安全性の向上
を可能にしたシールドトンネルの分岐・接合部の施工方
法及び分岐・接合部の仮設隔壁施工装置を提供すること
を目的とするものである。
The present invention has been made to solve the above problems, can reduce the construction range of ground improvement, does not require an auxiliary construction method, it is possible to improve workability, economic efficiency, and safety during construction. It is an object of the present invention to provide a method for constructing a branch / joint part of a shield tunnel and a temporary bulkhead construction device for a branch / joint part.

〔課題を解決するための手段〕[Means for Solving the Problems]

この発明に係る請求項第1項記載のシールドトンネルの
分岐・接合部の施工方法は、先行トンネルの覆工体を設
置するに際して前記先行トンネルと後行トンネルとの分
岐・接合部分に前記先行トンネルと前記後行トンネルと
を仕切る仮設隔壁を構築し、次に、前記後行トンネルを
前記仮設隔壁に向かって斜め方向から掘進しつつ、前記
後行トンネルの覆工体を設置して前記先行トンネルと後
行トンネルとを前記仮設隔壁部で合致させ、次に、前記
先行トンネルと後行トンネルとの分岐・接合部の周辺地
盤の地盤改良を行い、次に、前記仮設隔壁を撤去して前
記先行トンネルと前記後行トンネルとを接合し、次に、
前記先行トンネルと後行トンネルとの分岐・接合部に柱
又は桁梁を設置することを特徴とする。
According to a first aspect of the present invention, there is provided a method for constructing a branch / joint portion of a shield tunnel, wherein the leading tunnel is provided at a branch / joint portion between the leading tunnel and a trailing tunnel when a lining body of the leading tunnel is installed. And constructing a temporary bulkhead that separates the trailing tunnel from the trailing tunnel, and then digging the trailing tunnel from the diagonal direction toward the temporary bulkhead while installing the lining body of the trailing tunnel to install the leading tunnel. And a trailing tunnel at the temporary bulkhead, and then ground improvement of the ground around the junction / junction between the preceding tunnel and the trailing tunnel, and then removing the temporary bulkhead Join the leading tunnel and the trailing tunnel, and then
It is characterized in that columns or girders are installed at a branching / joining portion between the preceding tunnel and the following tunnel.

この発明に係る請求項第2項記載のシールドトンネルの
分岐・接合部の仮設隔壁施工装置は、先行トンネルを掘
進するシールド掘進機のシールドフレーム本体に取り付
けられ、前記シールドトンネルの円周方向に旋回する旋
回フレームと、この旋回フレームに取り付けられ、前記
シールドトンネルの直径方向に摺動する一次伸縮ガイド
ロッドと、この一次伸縮ガイドロッドの先端部に支持ア
ームを介して取り付けられ、前記シールドトンネルの直
径方向に摺動する二次伸縮ガイドロッドと、この二次伸
縮ガイドロッドの先端部に取り付けられ、仮設隔壁を保
持する吊りビームとを備えてなることを特徴とする。
A temporary bulkhead construction device for branching / joining a shield tunnel according to claim 2 of the present invention is attached to a shield frame body of a shield machine for excavating a preceding tunnel, and turns in a circumferential direction of the shield tunnel. Swivel frame, a primary telescopic guide rod that is attached to the swivel frame and slides in the diametrical direction of the shield tunnel, and a tip of the primary telescopic guide rod that is attached via a support arm to the diameter of the shield tunnel. It is characterized by comprising a secondary telescopic guide rod that slides in a direction, and a suspension beam that is attached to a tip end portion of the secondary telescopic guide rod and holds a temporary partition wall.

この発明に係る請求項第3項記載のシールドトンネルの
分岐・接合部の施工方法は、先行トンネルの分岐・接合
部を、円周の一部に前記後行トンネルのシールド掘進機
が通過可能な凹部と、前記先行トンネルと後行トンネル
とを仕切る仮設隔壁とを有する欠円断形面状のセグメン
トによってトンネルの1次覆工を行ない、次に、前記シ
ールド掘進機によって前記セグメントの凹部を通過する
ように掘進して後行トンネルを構築し、次に、前記分岐
・接合部の周辺地盤の地盤改良を行い、次に、前記仮設
隔壁を除去して前記先行トンネルと後行トンネルとを接
合し、次に、前記分岐・接合部に柱又は桁梁を設置する
ことを特徴とする。
In the method for constructing the branch / joint portion of the shield tunnel according to the third aspect of the present invention, the shield machine of the trailing tunnel can pass through a part of the circumference of the branch / joint portion of the preceding tunnel. The primary lining of the tunnel is performed by a segmented segmental segment having a recess and a temporary partition that separates the leading tunnel and the trailing tunnel, and then passes through the recess of the segment by the shield machine. To build a trailing tunnel, and then improve the ground around the branch / joint, and then remove the temporary bulkhead to join the leading tunnel and trailing tunnel. Next, columns or girders are installed at the branch / joint portions.

〔実施例〕〔Example〕

この発明に係る請求項第1項記載のシールドトンネルの
分岐・接合部の施工方法を図示する一実施例に基づいて
説明する(第1図〜第7図参照)。
A method for constructing a branching / joining portion of a shield tunnel according to claim 1 of the present invention will be described based on an embodiment illustrating the embodiment (see FIGS. 1 to 7).

最初に、先行トンネルAを掘進しつつ、その内周にセグ
メントを組み立てて覆工体1を構築する。
First, while excavating the preceding tunnel A, the segments are assembled on the inner periphery of the preceding tunnel A to construct the lining body 1.

この場合、先行トンネルAと後述する後行トンネルBと
の接合部には平板状セグメント組み立てて仮設隔壁2を
構築する。
In this case, the temporary partition walls 2 are constructed by assembling flat plate-shaped segments at the junction between the leading tunnel A and the trailing tunnel B described later.

また、仮設隔壁2の裏側には低強度モルタル、発泡スチ
ロール等の裏込め材3を施し、さらに、その外側に裏込
め材4を注入する。
Further, a backfilling material 3 such as low-strength mortar or styrofoam is applied to the backside of the temporary partition 2, and the backfilling material 4 is poured outside the backfilling material 3.

次に、仮設隔壁2に向かって斜め方向から後行トンネル
Bを掘進し、かつ、先行トンネルAと後行トンネルBと
の接合部に周辺地盤に注入管及び凍結管5を挿入して周
辺地盤の地盤改良を行う。
Next, the trailing tunnel B is excavated obliquely toward the temporary partition wall 2, and the injection pipe and the freezing pipe 5 are inserted into the surrounding ground at the junction between the leading tunnel A and the trailing tunnel B to insert the surrounding pipe into the surrounding ground. To improve the ground.

次に、仮設隔壁2を撤去することによって先行トンネル
Aと後述トンネルBとを接合し、必要により先行トンネ
ルAと後行トンネルBとの間に中柱6を建て付け(第4
図参照)、或いは、先行トンネルAと後行トンネルBと
の間に覆工体1を補強するための柱6又は桁梁7を設置
する(第4図、第5図参照)。
Next, by removing the temporary bulkhead 2, the preceding tunnel A and the below-mentioned tunnel B are joined, and if necessary, the middle pillar 6 is built between the preceding tunnel A and the following tunnel B (fourth
(See the figure), or a column 6 or a girder 7 for reinforcing the lining 1 is installed between the leading tunnel A and the trailing tunnel B (see FIGS. 4 and 5).

第6図及び第7は、この発明に係る請求項第2項記載の
仮設隔壁施工装置を示し、この装置によってシールドト
ンネルの分岐・接合部の仮設隔壁2が構築される。
6 and 7 show a temporary bulkhead construction device according to the second aspect of the present invention, and the temporary bulkhead 2 at the branch / joint portion of the shield tunnel is constructed by this device.

図において、シールド掘進機のシールドフレーム本体8
に、旋回フレーム9がトンネルの円周方向に旋回できる
ように取り付けられている。この旋回フレーム9はシー
ルドフレーム本体8に取り付けられた旋回モーター10に
よって自由に旋回されるようになっている。
In the figure, the shield frame body 8 of the shield machine
In addition, a swivel frame 9 is mounted so as to swivel in the circumferential direction of the tunnel. The swivel frame 9 is swung freely by a swivel motor 10 attached to the shield frame body 8.

旋回フレーム9の後面には左右2本の支持アーム11が平
行に取り付けられ、この左右支持アーム11に1次伸縮ガ
イドロッド12と一次伸縮ジャッキ14とがそれぞれ取り付
けられ、一次伸縮ガイドロッド12は一次伸縮ジャッキ14
によってトンネルの直径方向に摺動自在になっている。
Two left and right support arms 11 are attached in parallel to the rear surface of the revolving frame 9, and a primary telescopic guide rod 12 and a primary telescopic jack 14 are attached to the left and right support arms 11, respectively. Telescopic jack 14
It is slidable in the diameter direction of the tunnel.

一次伸縮ガイドロッド12の先端部には支持アーム13がそ
れぞれ取り付けられ、この支持アーム13は、セグメント
組立位置に張り出した状態に取り付けられ、かつ、仮設
隔壁2の組立時にすでに組み立てられたセグメントと干
渉しないような形状に構成されている(第6図参照)。
A support arm 13 is attached to the tip portion of the primary expansion / contraction guide rod 12, and the support arm 13 is attached to the segment assembling position in a protruding state and interferes with a segment already assembled when the temporary bulkhead 2 is assembled. It is configured in such a shape that it does not (see FIG. 6).

左右支持アーム13の先端部には、二次伸縮ガイドロッド
15と二次伸縮ジャッキ17とがそれぞれ取り付けられ、二
次伸縮ガイドロッド15は二次伸縮ジャッキ17によってト
ンネルの直径方向に摺動自在になっている。
A secondary telescopic guide rod is attached to the tip of the left and right support arms 13.
15 and the secondary telescopic jack 17 are attached respectively, and the secondary telescopic guide rod 15 is slidable in the diameter direction of the tunnel by the secondary telescopic jack 17.

左右二次伸縮ガイドロッド15の下端部には仮設間隔壁2
を保持して組立てるための吊ビーム16が架け渡されてい
る。なお、吊ビーム16と、二次伸縮ガイドロッド15とは
加熱隔壁2の組立時、すでに組み立てられたセグメント
と干渉しないようになっている。
A temporary spacing wall 2 is provided at the lower end of the left and right secondary telescopic guide rods 15.
A suspension beam 16 for holding and assembling is suspended. The suspension beam 16 and the secondary expansion / contraction guide rod 15 do not interfere with the already assembled segments when the heating partition wall 2 is assembled.

次に、この発明に係る請求項第3項記載のシールドトン
ネルの分岐・接合部の施工方法を図示する一実施例に基
づいて説明する(第8図〜第20図参照)。
Next, a method of constructing a branching / joining portion of a shield tunnel according to claim 3 of the present invention will be described based on an embodiment illustrated (see FIGS. 8 to 20).

第8図は、この施工方法によって構築中のシールドトン
ネルの分岐・接合区間を示す平面図、第9図及び第10図
は、第8図におけるII−II線及びIII−III線断面図で、
先行トンネルの分岐・接合区間において、円周部の一部
に後行トンネルBのシールド掘進機Cが通過可能な凹部
18と、先行トンネルAと後行トンネルBとを仕切る仮設
隔壁31とを有する欠円断面形状のコンクリート、又は鋼
製のセグメント19で一次覆行を行い、この凹部18には先
行トンネルAの掘進と同時に、セグメント19に設けた注
入口より埋め戻しを行い、また、後行トンネルBを掘進
するためのシールド掘進機Cは凹部18の埋め戻し部分20
を通過するように掘進して、後行トンネルBを構築す
る。
FIG. 8 is a plan view showing a branching / joining section of a shield tunnel being constructed by this construction method, and FIGS. 9 and 10 are sectional views taken along line II-II and III-III in FIG.
In the branching / joining section of the preceding tunnel, a recess that allows the shield machine C of the following tunnel B to pass through part of the circumference
A segment 19 made of concrete or steel, which has an oval cross-section and has a temporary partition wall 31 for partitioning the leading tunnel A and the trailing tunnel B, is first covered, and the recess 18 is dug into the leading tunnel A. At the same time, the shield machine C for backfilling from the injection port provided in the segment 19 and for excavating the trailing tunnel B is provided with the backfilling portion 20 of the recess 18.
The tunnel B is constructed by digging so as to pass through.

第11図は、後行トンネルBが先行トンネルAに合流した
後、シールド掘進機Cによって後行トンネルBの掘進を
続行して、後行トンネルBが先行トンネルAから徐々に
離れていく場合を示し、この場合にも本施工方法が適用
される。
FIG. 11 shows a case where the trailing tunnel B merges with the leading tunnel A, and then the shield tunneling machine C continues to dig the trailing tunnel B, and the trailing tunnel B gradually separates from the leading tunnel A. The construction method is also applied in this case.

第12図は、前記シールドトンネルの分岐・接合区間に使
用されるセグメント19を示し、後行トンネルBの接合部
分に凹部18が形成されている。
FIG. 12 shows a segment 19 used in the branching / joining section of the shield tunnel, and a recess 18 is formed in the joining portion of the trailing tunnel B.

なお、符号21はセグメントどうしを接合するボルト(図
省略)を通すためのボルト孔である。
Reference numeral 21 is a bolt hole for passing a bolt (not shown) for joining the segments.

第13図は、先行トンネルAにおける円形断面の本体部
と、前記分岐・接合部との間に設置されるセグメント22
を示し、セグメント19の凹部18に対応する部分に妻板部
23が形成されている。
FIG. 13 shows a segment 22 installed between the main body having a circular cross section in the preceding tunnel A and the branching / joining portion.
Shows the end plate of the segment 19 corresponding to the recess 18
23 are formed.

第17図〜第20図は、先行トンネルAの施工工程を示し、
先行トンネルAを掘進するためのシールド掘進機Dによ
って先行トンネルAを掘進し、同時にこのシールド掘進
機Dのエレクター部(後部)において単円断面トンネル
の構築に使用される公知のセグメント24によって先行ト
ンネルAの内周を覆工する(第17図参照)。
17 to 20 show the construction process of the preceding tunnel A,
The shield tunnel machine D for excavating the preceding tunnel A is used to excavate the preceding tunnel A, and at the same time, the known tunnel 24 is used in the erector portion (rear part) of this shield excavator D to construct a single-circle section tunnel. Line the inner circumference of A (see Fig. 17).

なお、図において、符号25はシールド掘進機Dを前進さ
せるためのシールドジャッキ、26はシールド機掘進機D
と組み立てられたセグメント24との間の隙間を塞ぐテー
ルシール、27はシールド掘進機Dの外周を構成するスキ
ンプレートである。
In the figure, reference numeral 25 is a shield jack for advancing the shield machine D, and 26 is a shield machine D.
A tail seal that closes the gap between the assembled segment 24 and 27 is a skin plate that forms the outer periphery of the shield machine D.

シールド掘進機Dがトンネル分岐・接合開始点に到着し
たら、第13図に示すセグメント22を組み立て、同時にシ
ールド掘進機Dに凹部18の地山とトンネル内とを仕切る
ため妻板部28とテールシール29とを新たに取り付ける
(第14図及び第15図参照)。
When the shield machine D arrives at the tunnel branching / joining start point, the segment 22 shown in FIG. 13 is assembled, and at the same time, the shield plate machine D and the tail seal 29 are provided to partition the ground of the recess 18 and the inside of the tunnel. And are newly installed (see Figures 14 and 15).

また、必要に応じてシールド掘進機Dを前進させるため
のシールドジャッキ30を新たに設置する(第14図、第15
図及び第18図参照)。
Further, a shield jack 30 for advancing the shield machine D is newly installed as needed (Figs. 14 and 15).
(See Figure and Figure 18).

この場合、凹部18部分の地山は一時的に露出するので、
必要に応じて凹部18部分の地山の防護工を行う。
In this case, the ground of the recess 18 is temporarily exposed,
If necessary, ground protection work will be carried out on the 18 recesses.

次に、前記のように妻板部28及びテールシール29が設置
されたシールド掘進機Dによって先行トンネルAを掘進
し、同時に第12図に示すセグメント19を組み立てて先行
トンルAの内周を覆工する(第18図参照)。
Next, the preceding tunnel A is excavated by the shield machine D having the end plate 28 and the tail seal 29 installed as described above, and at the same time, the segment 19 shown in FIG. 12 is assembled and the inner circumference of the preceding tunnel A is lined. (See Figure 18).

この場合、凹部18部分の空間部は、セグメント19に予め
設けられた注入口より掘削土やソイルセメント注入する
ことによって埋め戻す(第19図参照)。
In this case, the space of the concave portion 18 is backfilled by injecting excavated soil or soil cement from an injection port previously provided in the segment 19 (see FIG. 19).

このようにして、シールドトンネルの分岐・接合区間の
掘進が終了したら、第18図とは逆の工程でシールド掘進
機Dを改造前の状態に戻し、同時に分岐・接合区間の終
着部分を第13図に示すセグメント22と同じセグメントで
覆工してトンネル断面を単円形に戻す。
In this way, when the excavation of the branching / joining section of the shield tunnel is completed, the shield machine D is returned to the state before remodeling in the process reverse to that of FIG. Line the tunnel cross section back to a single circle by lining it with the same segment 22 as shown.

以下、第17図に示する場合と同じ工程を繰り返して先行
トンネルAの掘進を行う。
Hereinafter, the same steps as those shown in FIG. 17 are repeated to excavate the preceding tunnel A.

前記のように先行トンネルAの分岐・接合区間の構築が
完了したら、後行トンネルBのシールド掘進機Cによっ
て、凹部18の埋め戻し部分20を通過するように後行トン
ネルBの掘進を行う。
When the construction of the branching / joining section of the preceding tunnel A is completed as described above, the shield tunneling machine C of the following tunnel B excavates the following tunnel B so as to pass through the backfilled portion 20 of the recess 18.

先行トンネルAと後行トンネルBとが合流したら、第16
図に示すように先行トンネルAと後行トンネルBとの隔
壁31を撤去し、トンネル接合部の構築を行い、トンネル
の分岐・接合区間の構造体を構築する。
When the preceding tunnel A and the following tunnel B merge, the 16th
As shown in the figure, the partition wall 31 between the leading tunnel A and the trailing tunnel B is removed, the tunnel junction is constructed, and the structure of the branch / junction section of the tunnel is constructed.

なお、実施例では、先行トンネルAと後行トンネルBと
が左右に接合する場合について説明したが、上下に接合
する場合も同様の方法で構築できる(第21図参照)。
In the embodiment, the case where the leading tunnel A and the trailing tunnel B are joined left and right has been described, but a case where they are joined up and down can be constructed by the same method (see FIG. 21).

〔発明の効果〕〔The invention's effect〕

この発明は以上の構成からなるので、以下の効果を有す
る。
Since the present invention is configured as described above, it has the following effects.

先行シールドの覆工体の側部に仮設隔壁を設け、こ
の仮設隔壁部分で後行トンネルを合致させるようにした
ので、仮設隔壁を撤去することにより両トンネルを容易
に接続することができる。またその際、この発明の装置
は仮設隔壁を、覆工体を組立てるセグメントとは別に組
立てることができるので施工が容易である等の効果を有
する。
Since a temporary partition is provided on the side of the lining body of the leading shield and the trailing tunnel is made to coincide with this temporary partition, the two tunnels can be easily connected by removing the temporary partition. In addition, in this case, the device of the present invention has the effect that the temporary partition wall can be assembled separately from the segment for assembling the lining body, so that the construction is easy.

シールドトンネルの分岐・接合部において、先行ト
ンネルの分岐・接合区間に円周部の一部に凹部を有する
次円断面形状のセグメントによってトンネルの一次覆工
を行い、次いで同セグメントの凹部に後行トンネルのシ
ールド掘進機を合流せしめた状態で、掘進して後行トン
ネルを構築しようとしたもので、後行トンネルが先行ト
ンネルに嵌合した状態で接合され、従って分岐接合区間
の地山防護の為の地盤改良の施工範囲が少なくてよく、
露出部分が少なくなり、工費が著しく節減され、また、
前記分岐・接合区間を構築する場合に地山の露出部分が
少なくなるので、施工時の安全性が向上される効果があ
る。
At the branching / joining part of the shield tunnel, the primary lining of the tunnel is performed by the segment with the next circular cross-section that has a concave part in the part of the circumference in the branching / joining section of the preceding tunnel, and then the trailing part of the same segment It is an attempt to construct a trailing tunnel by excavating in a state where the tunnel shield machine is merged.The trailing tunnel is joined in the state of being fitted to the leading tunnel. The construction range for ground improvement is small,
The exposed part is reduced, the construction cost is significantly reduced, and
When the branching / joining section is constructed, the exposed portion of the natural ground is reduced, so that there is an effect that safety during construction is improved.

また、分岐・接合部には覆工体を補強するための柱又は
桁梁を設置するので、強度的にきわめて安定している。
Further, since columns or girders for reinforcing the lining body are installed at the branching / joining portion, the strength is extremely stable.

更に、ルーフシールド工法やパイプルーフ工法、かんざ
し桁圧入工法等の補助工法が不要となり、工費が節減さ
れると共に、工期が短縮される。
Furthermore, auxiliary construction methods such as the roof shield construction method, the pipe roof construction method, and the kanzashi girder press-fitting construction method are not required, so that the construction cost is reduced and the construction period is shortened.

【図面の簡単な説明】[Brief description of drawings]

第1図〜第5図は、この発明に係る請求項第1項記載の
シールドトンネルの分岐・接合部の施工方法の施工工程
を示すトンネルの断面図、第6図と第7図は前記施工方
法に使用される仮設隔壁施工装置の側面図と正面図、第
8図はシールドトンネルの分岐・接合部の施工状況を示
す平面図、第9図、第10図はそれぞれ第8図におけるI
−I線、II−II線断面図、第11はシールドトンネルの分
岐・接合部の施工状況を示す平面図、第12図及び第13図
はそれぞれシールドトンネルの分岐・接合部に使用され
るセグメントの斜視図、第14図はシールド掘進機の一部
横断平面図、第15図は第14図に於けるIII−III線断面
図、第16図はこの発明に係る請求項第3項記載の施工方
法によって構築されたシールドトンネル分岐・接合部の
縦断面図、第17図〜第20図は先行トンネルの施工工程を
示す縦断面図、第21図は先行トンネルと後行トンネルが
上下に接合された状態を示すトンネル分岐部の側面図、
第22図、第23図及び第24図は、第21図におけるIV−IV
線、V−V線及びVI−VI線断面図である。 A……先行トンネル、B……後行トンネル、C、D……
シールド掘進機、1……覆工体、2……仮設隔壁、3、
4……裏込め材、5……注入管及び凍結管、6……柱、
7……桁梁、8……シールドフレーム本体、9……旋回
フレーム、10……旋回モーター、11……支持アーム、12
……一次伸縮ガイドロッド、13……支持アーム、14……
一次伸縮ジャッキ、15……二次伸縮ガイドロッド、16…
…吊ビーム、17……二次伸縮ジャッキ、18……凹部、19
……セグメント、20……埋め戻し部分、21……ボルト
孔、22……セグメント、23……妻部、24……セグメン
ト、25……シールドジャッキ、26……テールシール、27
……スキンプレート、28……妻板部、29……テールシー
ル、30……シールドジャッキ、31……仮設隔壁。
1 to 5 are sectional views of a tunnel showing construction steps of a method for constructing a branch / joint portion of a shield tunnel according to claim 1 of the present invention, and FIGS. 6 and 7 are the construction steps. A side view and a front view of the temporary bulkhead construction device used in the method, FIG. 8 is a plan view showing the construction situation of the branch / joint portion of the shield tunnel, and FIGS. 9 and 10 are respectively I in FIG.
-I line, II-II line sectional view, 11th is a plan view showing the construction situation of the branch / joint of the shield tunnel, and Figures 12 and 13 are the segments used for the branch / joint of the shield tunnel, respectively. FIG. 14 is a partial cross-sectional plan view of the shield machine, FIG. 15 is a sectional view taken along the line III-III in FIG. 14, and FIG. 16 is the claim 3 according to the present invention. Vertical cross-sectional view of the shield tunnel branch / joint constructed by the construction method, Figures 17 to 20 are vertical cross-sectional views showing the construction process of the preceding tunnel, and Figure 21 is the joining of the preceding and succeeding tunnels vertically. Side view of the tunnel branch showing the broken state,
Figures 22, 23 and 24 show IV-IV in Figure 21.
FIG. 6 is a sectional view taken along the line V-V and the line VI-VI. A ... Leading tunnel, B ... Trailing tunnel, C, D ...
Shield machine, 1 ... Lining body, 2 ... Temporary bulkhead, 3,
4 ... backfill material, 5 ... injection tube and freezing tube, 6 ... pillar,
7 ... girder beam, 8 ... shield frame body, 9 ... swivel frame, 10 ... swivel motor, 11 ... support arm, 12
…… Primary telescopic guide rod, 13 …… Support arm, 14 ……
Primary telescopic jack, 15 ... Secondary telescopic guide rod, 16 ...
… Suspended beam, 17 …… Secondary telescopic jack, 18 …… Recessed part, 19
…… Segment, 20 …… Backfill part, 21 …… Bolt hole, 22 …… Segment, 23 …… Tube, 24 …… Segment, 25 …… Shield jack, 26 …… Tail seal, 27
...... Skin plate, 28 ...... Wife plate, 29 ...... Tail seal, 30 …… Shield jack, 31 …… Temporary bulkhead.

───────────────────────────────────────────────────── フロントページの続き (71)出願人 999999999 清水建設株式会社 東京都中央区京橋2丁目16番1号 (71)出願人 999999999 新日本製鐵株式会社 東京都千代田区大手町2丁目6番3号 (71)出願人 999999999 西松建設株式会社 東京都港区虎ノ門1丁目20番10号 (71)出願人 999999999 三井建設株式会社 東京都千代田区岩本町3丁目10番1号 (72)発明者 足立 義雄 茨城県つくば市大字旭1番地 建設省土木 研究所内 (72)発明者 水谷 敏則 茨城県つくば市大字旭1番地 建設省土木 研究所内 (72)発明者 真下 英人 茨城県つくば市大字旭1番地 建設省土木 研究所内 (72)発明者 鈴木 俊夫 東京都千代田区大手町2丁目2番1号 石 川島播磨重工業株式会社内 (72)発明者 吉村 宗男 東京都港区元赤坂1丁目2番7号 鹿島建 設株式会社内 (72)発明者 倉木 修二 東京都中央区日本橋本町4丁目12番20号 佐藤工業株式会社内 (72)発明者 荻原 英樹 東京都中央区京橋2丁目16番1号 清人建 設株式会社内 (72)発明者 中村 稔 東京都千代田区大手町2丁目6番3号 新 日本製鐵株式会社内 (72)発明者 渡辺 徹 東京都港区虎ノ門1丁目20番10号 西松建 設株式会社内 (72)発明者 林 寿夫 東京都千代田区岩本町3丁目10番1号 三 井建設株式会社内 (56)参考文献 特開 平1−192995(JP,A) 特開 昭64−66394(JP,A) ─────────────────────────────────────────────────── ─── Continuation of the front page (71) Applicant 999999999 2-16-1, Kyobashi, Chuo-ku, Tokyo Shimizu Corporation (71) Applicant 999999999 2-6, Otemachi, Chiyoda-ku, Tokyo No. 3 (71) Applicant 999999999 Nishimatsu Construction Co., Ltd. 1-20-10 Toranomon, Minato-ku, Tokyo (71) Applicant 999999999 Mitsui Construction Co., Ltd. 3-10-1 Iwamoto-cho, Chiyoda-ku, Tokyo (72) Inventor Yoshio Adachi 1 Asahi, Tsukuba City, Ibaraki Prefectural Institute of Civil Engineering, Ministry of Construction (72) Inventor Toshinori Mizutani 1st Asahi, Tsukuba City, Ibaraki Prefecture Institute of Civil Engineering, Ministry of Construction (72) Hideto Mashita 1 Asahi, Tsukuba, Ibaraki Prefecture Address Ministry of Construction, Civil Engineering Research Institute (72) Inventor Toshio Suzuki 2-2-1 Otemachi, Chiyoda-ku, Tokyo Ishi Kawashima Harima Heavy Industries Co., Ltd. (72) Akito Yoshimura Muneo Moto-Akasaka 1-2-7, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Shuji Kuraki 4-12-20 Nihonbashihonmachi, Chuo-ku, Tokyo Sato Kogyo Co., Ltd. (72) Invention Author Hideki Ogihara 2-16-1, Kyobashi, Chuo-ku, Tokyo Within Kiyoto Construction Co., Ltd. (72) Inventor Minoru Nakamura 2-3-6 Otemachi, Chiyoda-ku, Tokyo Within Nippon Steel Corporation (72) Inventor Toru Watanabe 1-20-10 Toranomon, Minato-ku, Tokyo Nishimatsu Construction Co., Ltd. (72) Inventor Toshio Hayashi 3-10-1 Iwamotocho, Chiyoda-ku, Tokyo Mitsui Construction Co., Ltd. (56) Reference References JP-A-1-192995 (JP, A) JP-A-64-66394 (JP, A)

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】先行トンネルと、この先行トンネルの構築
後に構築される後行トンネルとからなるシールドトンネ
ルの分岐・接合部の施工方法において、前記先行トンネ
ルの覆工体を設置するに際して前記先行トンネルと前記
後行トンネルとの分岐・接合部分に前記先行トンネルと
前記後行トンネルとを仕切る仮設隔壁を構築し、次に、
前記後行トンネルを前記仮設隔壁に向かって斜め方向か
ら掘進しつつ、前記後行トンネルの覆行体を設置して前
記先行トンネルと後行トンネルとを前記仮設隔壁部で合
致させ、次に、前記分岐・接合部の周辺地盤の地盤改良
を行い、次に、前記仮設隔壁を撤去して前記先行トンネ
ルと前記後行トンネルとを接合し、次に、前記分岐・接
合部に柱又は桁梁を設置すことを特徴とするシールドト
ンネルの分岐・接合部の施工方法。
1. A method of constructing a branch / joint portion of a shield tunnel comprising a preceding tunnel and a trailing tunnel constructed after the preceding tunnel is constructed, wherein the preceding tunnel is used when a lining body of the preceding tunnel is installed. And a temporary partition for partitioning the leading tunnel and the trailing tunnel at the branching / joining portion of the trailing tunnel and
While excavating the trailing tunnel from the oblique direction toward the temporary partition wall, the covering body of the trailing tunnel is installed to match the preceding tunnel and the trailing tunnel at the temporary partition wall portion, and then, Ground improvement of the ground around the branch / joint is performed, then the temporary bulkhead is removed to join the leading tunnel and the trailing tunnel, and then a pillar or girder is added to the branch / joint. A method of constructing a branch / joint part of a shield tunnel, which is characterized by installing
【請求項2】先行トンネルと、この先行トンネルの構築
後に構築される後行トンネルとからなるシールドトンネ
ルの分岐・接合部に、前記先行トンネルと前記後行トン
ネルとを仕切るために設置される仮設隔壁を施工するた
めの分岐・接合部の仮設隔壁施工装置において、前記先
行トンネルを掘進するシールド掘進機のシールドフレー
ム本体に取り付けられ、前記シールドトンネルの円周方
向に旋回する旋回フレームと、この旋回フレームに取り
付けられ、前記シールドトンネルの直径方向に摺動する
一次伸縮ガイドロッドと、この一次伸縮ガイドロッドの
先端部に支持アームを介して取り付けられ、前記シール
ドトンネルの直径方向に摺動する二次伸縮ガイドロッド
と、この二次伸縮ガイドロッドの先端部に取り付けら
れ、前記仮設隔壁を保持する吊りビームとを備えてなる
ことを特徴とするシールドトンネルの分岐・接合部の仮
設隔壁施工装置。
2. A temporary installation installed at a branch / junction of a shield tunnel composed of a leading tunnel and a trailing tunnel constructed after the leading tunnel is constructed so as to partition the leading tunnel and the trailing tunnel. In a temporary bulkhead construction device for branching / joining for constructing a bulkhead, a swivel frame which is attached to a shield frame body of a shield machine for excavating the preceding tunnel and swivels in the circumferential direction of the shield tunnel, and this swivel A primary telescopic guide rod that is attached to a frame and slides in the diametrical direction of the shield tunnel, and a secondary telescopic guide that is attached to the tip end of the primary telescopic guide rod via a support arm and that slides in the diametrical direction of the shield tunnel. The expansion guide rod and the secondary expansion guide rod are attached to the tip end of the temporary expansion partition. Temporary partition wall construction system of branching and joining portion of the shield tunnel, characterized by comprising a hanger beam lifting.
【請求項3】先行トンネルと、この先行トンネルの構築
後に構築される後行トンネルとからなるシールドトンネ
ルの分岐・接合部の施工方法において、前記先行トンネ
ルの分岐・接合部を、円周の一部に前記後行トンネルの
シールド掘進機が通過可能な凹部と、前記先行トンネル
と後行トンネルとを仕切る仮設隔壁とを有する欠円断形
面状のセグメントによってトンネルの1次覆工を行な
い、次に、前記シールド掘進機によって前記セグメント
の凹部を通過するように掘進して後行トンネルを構築
し、次に、前記分岐・接合部の周辺地盤の地盤改良を行
い、次に、前記仮設隔壁を除去して前記先行トンネルと
後行トンネルとを接合し、次に、前記分岐・接合部に柱
又は桁梁を設置することを特徴とするシールドトンネル
の分岐・接合部の施工方法。
3. A method of constructing a branch / junction of a shield tunnel comprising a preceding tunnel and a trailing tunnel constructed after the construction of the preceding tunnel, wherein the branch / join of the preceding tunnel has a circumference of one. The primary lining of the tunnel is performed by a segmented segmental segment having a concave portion through which the shield machine of the trailing tunnel can pass, and a temporary partition wall separating the leading tunnel and the trailing tunnel, Next, the shield tunneling machine excavates so as to pass through the recessed portion of the segment to construct a trailing tunnel, and then the ground around the branch / joint is improved, and then the temporary partition wall. Is removed to join the leading tunnel and the trailing tunnel, and then a pillar or girder beam is installed at the branching / joining portion to construct the branching / jointing portion of the shield tunnel. Law.
JP1138368A 1989-05-31 1989-05-31 Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint Expired - Lifetime JPH0765455B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1138368A JPH0765455B2 (en) 1989-05-31 1989-05-31 Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1138368A JPH0765455B2 (en) 1989-05-31 1989-05-31 Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint

Publications (2)

Publication Number Publication Date
JPH035600A JPH035600A (en) 1991-01-11
JPH0765455B2 true JPH0765455B2 (en) 1995-07-19

Family

ID=15220301

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1138368A Expired - Lifetime JPH0765455B2 (en) 1989-05-31 1989-05-31 Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint

Country Status (1)

Country Link
JP (1) JPH0765455B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009270330A (en) * 2008-05-07 2009-11-19 Nippon Steel Corp Joint structure and joint method of tunnels of different kinds, and composite segment ring structure

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0786314B2 (en) * 1992-05-25 1995-09-20 日本コンクリート工業株式会社 Construction method of side wall used for widening part of tunnel
JP4050882B2 (en) * 2001-07-27 2008-02-20 新日本製鐵株式会社 Segment ring structure
JP4593913B2 (en) * 2003-12-26 2010-12-08 株式会社間組 How to build a branch tunnel
JP4485373B2 (en) * 2005-01-24 2010-06-23 大成建設株式会社 Construction method of tunnel junction
JP4534069B2 (en) * 2005-07-08 2010-09-01 大成建設株式会社 Parallel tunnel joining method
JP4587919B2 (en) * 2005-09-13 2010-11-24 株式会社奥村組 How to construct a junction and junction of shield tunnel
JP4587918B2 (en) * 2005-09-13 2010-11-24 株式会社奥村組 How to construct a junction and junction of shield tunnel
JP4634308B2 (en) * 2006-01-18 2011-02-16 大成建設株式会社 Segment box or propulsion box and air mortar block composite, and construction method for multiple section tunnel
JP4730608B2 (en) * 2006-06-05 2011-07-20 清水建設株式会社 segment
JP4934416B2 (en) * 2006-06-09 2012-05-16 前田建設工業株式会社 How to construct a junction and junction of shield tunnel
JP2008019663A (en) * 2006-07-14 2008-01-31 Maeda Corp Tunnel construction method
JP4598746B2 (en) * 2006-12-11 2010-12-15 新日本製鐵株式会社 Tunnel structure and construction method at branch and junction
JP4824653B2 (en) * 2007-09-04 2011-11-30 鹿島建設株式会社 Tunnel junction and method of constructing tunnel junction
US9617853B2 (en) 2012-07-09 2017-04-11 Komatsu Ltd. Auxiliary tunneling apparatus
JP5513559B2 (en) 2012-07-09 2014-06-04 株式会社小松製作所 Tunnel excavation method
JP6101171B2 (en) * 2013-08-06 2017-03-22 大成建設株式会社 Shield tunnel joining segment, joining structure and joining method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6466394A (en) * 1987-09-07 1989-03-13 Ohbayashi Corp Method of constructing double track type tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009270330A (en) * 2008-05-07 2009-11-19 Nippon Steel Corp Joint structure and joint method of tunnels of different kinds, and composite segment ring structure

Also Published As

Publication number Publication date
JPH035600A (en) 1991-01-11

Similar Documents

Publication Publication Date Title
JP7125550B2 (en) SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH
JPH0765455B2 (en) Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint
JP4958035B2 (en) Shield roof construction method
JP2006348718A (en) Construction method of underground structure and underground structure
JP2007217911A (en) Construction method of underground cavity and tunnel construction method
CN109026026A (en) Under wear existing piping lane the multi-thread more arcading bored tunnel groups of big cross section construction method
JP4132442B2 (en) Tunnel construction method
JP4183470B2 (en) Underground structure and its construction method
JP2017031724A (en) Construction method of large cross section tunnel and large cross section lining body
JP4750568B2 (en) Tunnel junction construction method and tunnel junction structure
JP2002220991A (en) Partition wall installed in main-tunnel shield tunnel and construction method therefor
JP4100231B2 (en) Tunnel branching method using parent-child shield machine
JP2942874B2 (en) How to join tunnels
JPH04357293A (en) Flexible pipe and executing method thereof
JP2009174185A (en) Method of constructing wide section of tunnel
JP3765048B2 (en) How to build a tunnel
JP2893349B2 (en) Large section tunnel structure and its construction method.
JPH05280296A (en) Large scale underground structure and construction method thereof
JP3895881B2 (en) Shield tunnel connection method
JP4780475B2 (en) Tunnel construction method
JP2006152680A (en) Joining construction method for shield tunnel and structure of shield tunnel by its construction method
JP2018178593A (en) Underground wall construction method
JP3162348B2 (en) Steel segment and shield tunnel excavation method for tunnel lining
JPH0462299A (en) Larger section tunnel and construction method thereof
JP2520036B2 (en) Construction method of large section underground cavity and large section tunnel

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080719

Year of fee payment: 13

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080719

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090719

Year of fee payment: 14

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090719

Year of fee payment: 14

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term