JPH0323689B2 - - Google Patents

Info

Publication number
JPH0323689B2
JPH0323689B2 JP11814782A JP11814782A JPH0323689B2 JP H0323689 B2 JPH0323689 B2 JP H0323689B2 JP 11814782 A JP11814782 A JP 11814782A JP 11814782 A JP11814782 A JP 11814782A JP H0323689 B2 JPH0323689 B2 JP H0323689B2
Authority
JP
Japan
Prior art keywords
steel plate
plate cell
construction
caisson
cell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP11814782A
Other languages
Japanese (ja)
Other versions
JPS598835A (en
Inventor
Akira Sano
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Nippon Steel Corp
Toa Corp
Original Assignee
Shimizu Construction Co Ltd
Sumitomo Metal Industries Ltd
Toa Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Sumitomo Metal Industries Ltd, Toa Corp filed Critical Shimizu Construction Co Ltd
Priority to JP11814782A priority Critical patent/JPS598835A/en
Publication of JPS598835A publication Critical patent/JPS598835A/en
Publication of JPH0323689B2 publication Critical patent/JPH0323689B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Description

【発明の詳細な説明】 本発明は、あらかじめ製作された鋼板セルを用
いて、主として海中にケーソン基礎を築造する根
入れ式鋼板セル・ケーソン工法に係るものであ
る。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an embedded steel plate cell caisson construction method for constructing a caisson foundation mainly underwater using prefabricated steel plate cells.

従来、海中基礎の施工法には種々のものがある
が、海中にケーソン基礎形式のものを施工するに
は、人工の島を構築したうえで行つている。とこ
ろが、大水深の場合には築島が非常に大規模なも
のとなり、海上作業時間が長くかかつて、工事の
効率が低い許りでなく、変りやすい海洋気象状況
に対応して施工上の安全を十分確保できない等の
問題提起がなされている。
Conventionally, there are various methods for constructing underwater foundations, but in order to construct a caisson foundation underwater, an artificial island is first constructed. However, in the case of deep water, the construction island would be very large, and the time required to work at sea would be long, and the efficiency of construction would be low. Problems have been raised such as not being able to secure enough supplies.

本発明は、上記の如き実状に鑑み、たとえ大水
深であり、また水底地盤中の支持層が深い場合で
あつても、簡易迅速にケーソン基礎を築造するこ
とができ、施工効率の大幅な向上と安全性の向上
を図ることができる根入れ式鋼板セル・ケーソン
工法を提供しようとするものである。
In view of the above-mentioned circumstances, the present invention enables the construction of a caisson foundation simply and quickly even in deep water and in cases where the support layer in the underwater ground is deep, thereby significantly improving construction efficiency. The purpose of this project is to provide an embedded steel plate cell caisson construction method that can improve safety.

以下、本発明に係る工法を図面の記載に基いて
説明する。
Hereinafter, the construction method according to the present invention will be explained based on the drawings.

本発明の工法に用いる鋼板セル1は、所要の直
径を有し、かつ打設場所の水深および支持層の深
さに応じた高さを有するものであり、工場や現場
近くの作業ヤードであらかじめ製作されたもので
ある。なお、鋼板セル1の補強リブプレートは外
面に取付けられている。
The steel plate cell 1 used in the construction method of the present invention has a required diameter and a height corresponding to the water depth at the pouring site and the depth of the supporting layer, and is prepared in advance at a factory or work yard near the site. It was manufactured. Note that the reinforcing rib plate of the steel plate cell 1 is attached to the outer surface.

上記鋼板セル1を用いて海中にケーソン基礎を
築造するにあたつては、鋼板セル1をクレーン船
や台船等により打設場所まで運搬し、かつ位置決
めする。次いで、振動打込み方式により急速に海
底地盤a中に打込み、直ちに内側の海水を排除す
ると共に土砂を投入して中詰めを行い、鋼板セル
1が外側からの水圧で破壊されないようにし、か
つ適正な姿勢を保持せしめる。また、中詰め後、
必要に応じて鋼板セル1の根入れ部周囲に水中固
化薬液2を注入し、鋼板セル1の封止を完全にす
る。鋼板セル1を振動打込み方式により打込む装
置としては、所要台数の振動杭打機を連動システ
ムにより同調駆動させて鋼板セル1に均一な振動
エネルギーを伝えるものとする。
When constructing a caisson foundation in the sea using the steel plate cell 1, the steel plate cell 1 is transported to a casting site by a crane ship, barge, etc., and positioned. Next, the steel plate cell 1 is rapidly driven into the seabed ground a using a vibration driving method, and the seawater inside is immediately expelled, and earth and sand are poured in to fill the steel plate cell 1 with water pressure from the outside and to prevent the steel plate cell 1 from being destroyed by water pressure from the outside. Make them maintain their posture. Also, after filling,
If necessary, an underwater solidifying chemical solution 2 is injected around the embedded portion of the steel plate cell 1 to completely seal the steel plate cell 1. The apparatus for driving the steel plate cells 1 by the vibration driving method is one in which a required number of vibrating pile drivers are synchronously driven by an interlocking system to transmit uniform vibration energy to the steel plate cells 1.

叙上のように、鋼板セル1の設置工事が完了し
たならば、鋼板セル1の内面に沿つて地中連続壁
3を施工し、さらにこの地中連続壁3に連接する
クロス状に地中連続壁4を施工して、ケーソン基
礎5を築造する。ケーソン基礎5上には躯体コン
クリート6が施工される。
As mentioned above, once the installation work of the steel plate cell 1 is completed, the underground continuous wall 3 is constructed along the inner surface of the steel plate cell 1, and the underground continuous wall 3 is further connected to the underground continuous wall 3 in a cross shape. A continuous wall 4 is constructed and a caisson foundation 5 is constructed. A concrete frame 6 is constructed on the caisson foundation 5.

なお、鋼板セル1内の泥水圧による泥水の根入
れ部からの漏出は、その周囲に水中固化薬液2を
注入することによつて防止でき、また、鋼板セル
1の上端からの泥水の溢流は、施工基面bを外部
水位cより1〜2m程度下げることによつて防止
することができる。そして、この対策によつて海
水の汚濁を回避することができる。
In addition, leakage of muddy water from the embedded part due to muddy water pressure in the steel plate cell 1 can be prevented by injecting the underwater solidifying chemical solution 2 around it, and the overflow of muddy water from the upper end of the steel plate cell 1 can be prevented. This can be prevented by lowering the construction base b by about 1 to 2 m below the external water level c. By taking this measure, it is possible to avoid seawater pollution.

工場または現場近くの作業ヤードで製作される
鋼板セル1は、打設場所の水深および支持層の深
さに応じた高さのものを製作することができ、ま
た、製作された鋼板セル1はそのままクレーン船
や台船等により打設場所へ運搬することができる
ので、大水深および支持層が深くても施工が可能
である。そして、鋼板セル1の据付け後は、単に
鋼板セル1内の地中連続壁3,4の施工によつ
て、ケーソン基礎5を築造することができるの
で、大がかりな仮設工事を必要とせず、簡易迅速
な施工が可能となる。このため、特に変りやすい
海洋気象状況に対応した安全施工ができ、本発明
による工法は海洋開発の促進に大いに貢献するも
のである。
The steel plate cell 1 manufactured in a factory or a work yard near the site can be manufactured with a height that corresponds to the water depth of the pouring site and the depth of the supporting layer. Since it can be transported as is to the pouring site using a crane boat, barge, etc., construction can be carried out even in deep water and deep supporting layers. After the steel plate cell 1 is installed, the caisson foundation 5 can be constructed by simply constructing the underground continuous walls 3 and 4 within the steel plate cell 1. This enables quick construction. Therefore, safe construction can be carried out especially in response to changeable marine weather conditions, and the construction method according to the present invention greatly contributes to the promotion of marine development.

これを要するに、本発明は、あらかじめ製作さ
れた鋼板セルを打設場所に運搬して位置決めし、
この鋼板セルを振動打込み方式により急速に水底
地盤中に打込み、直ちに土砂を投入して中詰めを
行つた後、上記鋼板セル内に地中連続壁を施工し
てケーソン基礎を築造することを特徴とする根入
れ式鋼板セル・ケーソン工法であるから、たとえ
大水深であり、また水底地盤中の支持層が深い場
合であつても、簡易迅速にケーソン基礎を築造す
ることができ、施工効率の大幅な向上と安全性の
向上を図ることができる効果を奏するものであ
る。
In summary, the present invention transports and positions prefabricated steel plate cells to a pouring site,
This steel plate cell is rapidly driven into the underwater ground using a vibratory driving method, and after immediately filling it with earth and sand, an underground continuous wall is constructed within the steel plate cell to construct a caisson foundation. Because it is an embedded steel plate cell caisson construction method, it is possible to construct a caisson foundation simply and quickly, even in deep water or with a deep support layer in the underwater ground, which improves construction efficiency. This has the effect of significantly improving safety and improving safety.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明に係る根入れ式鋼板セル・ケーソ
ン工法の一実施例を示すものであつて、第1図は
築造されたケーソン基礎の一部を縦断した側面
図、第2図は同上水平断面図、第3図A,B,
C,DおよびEは施工順序を示した縦断側面図で
ある。 1……鋼板セル、3,4……地中連続壁、5…
…ケーソン基礎、6……躯体コンクリート、a…
…海底地盤、b……施工基面、c……外部水面。
The drawings show an embodiment of the embedded steel plate cell caisson construction method according to the present invention, in which Fig. 1 is a longitudinal cross-sectional side view of a part of the constructed caisson foundation, and Fig. 2 is a horizontal cross-section of the same. Figure, Figure 3 A, B,
C, D and E are longitudinal sectional side views showing the construction order. 1... Steel plate cell, 3, 4... Underground continuous wall, 5...
...Caisson foundation, 6...Structure concrete, a...
...Seafloor ground, b...Construction base, c...External water surface.

Claims (1)

【特許請求の範囲】[Claims] 1 あらかじめ製作された鋼板セルを打設場所に
運搬して位置決めし、この鋼板セルを振動打込み
方式により急速に水底地盤中に打込み、直ちに土
砂を投入して中詰めを行つた後、上記鋼板セル内
に地中連続壁を施工してケーソン基礎を築造する
ことを特徴とする根入れ式鋼板セル・ケーソン工
法。
1. Transport the prefabricated steel plate cell to the casting site, position it, rapidly drive the steel plate cell into the underwater ground using the vibration driving method, immediately fill it with earth and sand, and then insert the steel plate cell into the concrete. This is an embedded steel plate cell caisson construction method that is characterized by constructing an underground continuous wall and building a caisson foundation.
JP11814782A 1982-07-06 1982-07-06 Footing type steel plate cell caisson work Granted JPS598835A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11814782A JPS598835A (en) 1982-07-06 1982-07-06 Footing type steel plate cell caisson work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11814782A JPS598835A (en) 1982-07-06 1982-07-06 Footing type steel plate cell caisson work

Publications (2)

Publication Number Publication Date
JPS598835A JPS598835A (en) 1984-01-18
JPH0323689B2 true JPH0323689B2 (en) 1991-03-29

Family

ID=14729239

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11814782A Granted JPS598835A (en) 1982-07-06 1982-07-06 Footing type steel plate cell caisson work

Country Status (1)

Country Link
JP (1) JPS598835A (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60195230A (en) * 1984-03-15 1985-10-03 Toa Harbor Works Co Ltd Foundation forming work of soft ground
DE10257522B4 (en) * 2002-12-10 2013-06-06 Hans Mosbauer Substructure for seepage of rainwater and method for the production of a civil engineering work and apparatus for carrying out the method
CN108999205A (en) * 2018-09-28 2018-12-14 北京首钢建设集团有限公司 A kind of basis fluting retaining wall uses the construction method of rectangular steel plates circle
CN110512637B (en) * 2019-08-30 2021-08-06 东南大学 Novel shock insulation composite foundation and construction method thereof

Also Published As

Publication number Publication date
JPS598835A (en) 1984-01-18

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
CN102561371B (en) Steel caisson enclosure structure at island-tunnel combination part and construction method thereof
US20160376762A1 (en) Construction method for planting hollow columns in a seabed of a marine environment for supporting waterborne structures thereon
CN109113086B (en) A kind of steel reinforced concrete combined cofferdam construction method in deep water exposed bedrock riverbed area
CN109780325A (en) A kind of water factory's water intaking tunnel submarine pipeline installation method
US3618327A (en) Caisson structure and pier construction methods
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
US5024557A (en) Method and apparatus for constructing an offshore hollow column
JPH0323689B2 (en)
JPH06146305A (en) Underwater foundation and installation method thereof
JP2000290936A (en) Method and caisson for constructing bridge pier footing
JP4066340B2 (en) Ground improvement method
JPH09316894A (en) Bridge pier foundation structure, and construction method thereof
JP3209503B2 (en) Water intake / discharge equipment underwater construction method
JP3209502B2 (en) Water intake / discharge equipment underwater construction method
JP4132320B2 (en) Foundation construction method
CN216973476U (en) Gravity type fan foundation that caisson and steel-pipe pile combine
JP2953823B2 (en) Construction method of offshore substructure
JPH11336102A (en) Foundation structure for underwater tunnel and its construction method
JP2512744B2 (en) How to place underwater concrete
JPH0377349B2 (en)
JPH07216915A (en) Construction method of underground type storage tank and bottom mounting float
JP2576902B2 (en) Construction methods and buildings in landfills
JP2001214419A (en) Method for setting up ocean stricture using caisson
CN111827321A (en) Composite cofferdam construction method