JP2953823B2 - Construction method of offshore substructure - Google Patents

Construction method of offshore substructure

Info

Publication number
JP2953823B2
JP2953823B2 JP18543591A JP18543591A JP2953823B2 JP 2953823 B2 JP2953823 B2 JP 2953823B2 JP 18543591 A JP18543591 A JP 18543591A JP 18543591 A JP18543591 A JP 18543591A JP 2953823 B2 JP2953823 B2 JP 2953823B2
Authority
JP
Japan
Prior art keywords
offshore
frame
pier
substructure
sea
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP18543591A
Other languages
Japanese (ja)
Other versions
JPH059922A (en
Inventor
忠春 井上
知志 森田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP18543591A priority Critical patent/JP2953823B2/en
Publication of JPH059922A publication Critical patent/JPH059922A/en
Application granted granted Critical
Publication of JP2953823B2 publication Critical patent/JP2953823B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、海洋に設置される構造
物、例えば、橋梁やシーバース等の基礎構造物の建造方
法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a structure installed in the ocean, for example, a foundation structure such as a bridge or a sea berth.

【0002】[0002]

【従来の技術】近年、我国では比較的水深の深い海域に
橋梁やシーバースを建設する事例が増えつつある。例え
ば、1988年に開通した本州四国連絡橋備讃瀬戸大橋
は、造船所等において基礎部分となる大型の鋼製ケーソ
ンを製作し、これを浮かべて設置場所まで海上曳航し、
水深50mの支持地盤上に沈設した後、現場で不足分の
上部を継ぎ足していくという建造方法が採用された。
2. Description of the Related Art In recent years, in Japan, bridges and sea berths have been increasingly constructed in relatively deep waters. For example, Bisan Seto Bridge, Honshu-Shikoku Bridge, which was opened in 1988, produced a large steel caisson that was used as a foundation at shipyards, etc.
After submerging on a supporting ground at a depth of 50 m, a construction method was adopted in which the insufficient upper part was added at the site.

【0003】また、シーバースの基礎構造物として、鋼
製のジャケット式構造物が採用されている。この構造物
は工場製作した立体トラスであるジャケット本体を運搬
し、海底に据え付け、ジャケットの支柱内を貫通して地
盤に杭を打設し、杭頭部に上部工を架設固定して施工さ
れる。
[0003] Further, a steel jacket-type structure is employed as a substructure of the sea berth. This structure is constructed by transporting the jacket body, a three-dimensional truss manufactured at the factory, installing it on the sea floor, penetrating through the columns of the jacket, driving the pile into the ground, and installing and fixing the superstructure at the pile head. You.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、前記橋
梁の基礎部分となる大型ケーソンの設置作業では、基礎
の底面が大きいので海底面の掘削・均し作業を広い面積
に対して行う必要があり、また、シーバースにおけるジ
ャケットの設置作業では、杭の打設作業を伴うなど、作
業船および機材に対する費用が高価とならざるを得な
い。更に、上記海洋構造物の現場施工期間が一般に長い
ことから、構造物が不安定な状態で長期間にわたり外力
にさらされるため、防護工として周辺の仮設備が大きく
なるという欠点を有している。
However, in the work of installing a large caisson, which is the foundation of the bridge, it is necessary to perform excavation and leveling of the sea bottom over a large area because the bottom of the foundation is large. In addition, the installation work of the jacket in the sea berth involves the installation work of the pile, and the cost for the work boat and the equipment must be expensive. Furthermore, since the on-site construction period of the above-mentioned offshore structure is generally long, the structure is exposed to external force for a long period of time in an unstable state. .

【0005】本発明は前記課題を解決しようとするもの
であり、その目的は、海洋基礎構造物を構成する支持部
材を簡易な構造とし、これを組み立てて、海洋基礎構造
物を建造する方法を提供することにある。
An object of the present invention is to solve the above-mentioned problems, and an object of the present invention is to provide a method for constructing a marine substructure by assembling the support member constituting the marine substructure with a simple structure. To provide.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するため
に、本発明に係る海洋基礎構造物の建造方法は、海洋構
造物の基礎を構成する複数の支持部材を組立場所以外で
製作し、これを最終設置場所へ洋上曳航し、該支持部材
の下端部を海底地盤に着底させた後、二以上の支持部材
の頂部を連結し、かつ、各支持部材の下端部を海底地盤
に固定することによって課題を解決したものである。
In order to achieve the above object, a method of constructing an offshore substructure according to the present invention comprises manufacturing a plurality of support members constituting a foundation of an offshore structure at a place other than an assembly place. This is towed offshore to the final installation location, the lower end of the support member is landed on the seabed ground, the tops of two or more support members are connected, and the lower end of each support member is fixed to the seabed ground. This solves the problem.

【0007】[0007]

【実施例】以下、海洋基礎構造物として橋梁の橋脚を例
に取り、その建造方法の好適な実施例を、図1に基づい
て説明する。橋脚部材の製作 予め、ドライドックで橋脚を構成するフレーム3を製作
する。フレーム3は、図2(A)に示すような、2本の
脚柱3a間に桁3bを渡した梯子形状をした一対のトラ
ス状フレーム3、3′によって構成する。各フレーム
3、3′の大きさは、設置される海域の水深によって定
まるが、橋脚の高さが数十m〜数百mの範囲内で可能で
ある。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A preferred embodiment of a method for constructing a pier of a bridge will be described below with reference to FIG. Manufacture of Bridge Pier A frame 3 constituting a bridge pier is manufactured in advance by a dry dock. The frame 3 is constituted by a pair of ladder-shaped frames 3, 3 'having a ladder shape in which a spar 3b is provided between two pillars 3a as shown in FIG. The size of each frame 3, 3 'is determined by the water depth of the sea area in which it is installed, but the height of the pier can be within a range of several tens to several hundreds of meters.

【0008】例えば、100mの水深に設置される橋脚
であれば、外径10mのコンクリート管で、高さ120
m、頂部幅50m、脚柱間の開脚幅100mといった寸
法に製作される。また、脚柱3aの内部には、数m間隔
で鋼板製の隔壁を設けて内部を区画し、後記するバラス
ト材が注入される空室と、同バラスト材の給排水を行う
ポンプを設置するポンプ室として利用できるように構成
する。
For example, a pier installed at a depth of 100 m is a concrete pipe having an outer diameter of 10 m and a height of 120 m.
m, the top width is 50 m, and the leg width between the pillars is 100 m. Further, inside the pillar 3a, a partition made of a steel plate is provided at intervals of several meters to partition the inside, and a pump for installing a vacant room into which a ballast material described later is injected and a pump for supplying and discharging the ballast material are provided. It is configured so that it can be used as a room.

【0009】海底地盤の掘削 始めに、フレーム3、3′を着底する部分の海底地盤を
予め掘削し、レベル調整を行う(工程)。また、この
際に、海底地盤の地耐力を調査した上で、必要があれ
ば、掘削孔1内にプレキャスト製コンクリート版等を設
置するか、或いは、水中コンクリートを打設して、海底
基礎2を造成する(工程)。
At the beginning of excavation of the submarine ground, the submarine ground at the portion where the frames 3, 3 'are landed is excavated in advance, and the level is adjusted (process). At this time, after investigating the ground strength of the seabed ground, if necessary, a precast concrete plate or the like is installed in the excavation hole 1 or an underwater concrete is poured into the seabed foundation 2. (Process).

【0010】曳航 フレーム3をドライドックから曳き出して洋上に浮か
べ、設置する海域まで浮上曳航する。なお、小規模なド
ライドックで製作する場合には、フレーム3を複数部分
に分割して製作し、これをドライドックから曳き出して
静穏な洋上で接合した後、最終設置場所へ曳航してもよ
い。
[0010] The tow frame 3 is pulled out of the dry dock, floated on the sea, and levitated and towed to the sea area where it is to be installed. In the case of manufacturing with a small dry dock, the frame 3 is divided into a plurality of parts, manufactured, pulled out of the dry dock, joined on a calm sea, and then towed to the final installation location. Good.

【0011】フレームの着底 先ず、洋上に横たわっているフレーム3の基底部から海
水等のバラスト材を注入していき、フレーム3を洋上で
鉛直に起立させる(工程)。その後、更にバラスト材
を注水して、そのまま前記造成した基礎2上に着底させ
る(工程)。同じ操作をもう一つのフレーム3′につ
いても行う。
[0011] bottom landing of the frame first, we will inject the ballast material such as seawater from the base of the frame 3 lying offshore, is vertically upright frame 3 at sea (step). Thereafter, the ballast material is further injected with water, and the ballast material is directly settled on the formed foundation 2 (step). The same operation is performed for another frame 3 '.

【0012】橋脚の組立 各フレーム3、3′にバラスト材を加え、両者の頂部を
徐々に引き寄せる。引き寄せ作業は、クレーン船、曳
船、ウィンチ等の設備により行う。この際に、注水量と
注水速度を調整することにより、フレーム3、3′の傾
きと橋脚の姿勢を制御することができる。その後、両フ
レーム3、3′の頂部を適当な金具で結合する(工程
)。
Assembling the pier A ballast material is added to each frame 3, 3 ', and the tops of both are gradually drawn. The pulling work is performed by equipment such as a crane ship, tugboat, and winch. At this time, the inclination of the frames 3, 3 'and the attitude of the pier can be controlled by adjusting the water injection amount and the water injection speed. After that, the tops of both frames 3, 3 'are joined with appropriate metal fittings (step).

【0013】橋脚の固定 フレーム3、3′の脚柱3aが着底している掘削孔1内
を、土砂、ソイルセメントまたはコンクリート4等で埋
め戻して、脚柱3aの下端部を海底地盤に固定する(工
程)。
The inside of the excavation hole 1 on which the pillars 3a of the fixed frames 3, 3 'of the piers have landed is backfilled with earth and sand, soil cement, concrete 4, or the like, and the lower end of the pillars 3a is placed on the seabed ground. Fix (process).

【0014】最後に、両フレーム3、3′の洋上に突出
している頂部に所定の大きさの頂版5を載置し、橋脚の
高さ、姿勢を最終的に調整する(工程)。
Finally, a top plate 5 having a predetermined size is placed on the tops of the frames 3, 3 'projecting offshore, and the height and posture of the pier are finally adjusted (step).

【0015】上部工 通常の橋梁施工法と同様にして、主塔等の上部構造物6
を前記頂版5上に設置する(工程)。
[0015] in the same manner as in the superstructure normal bridge construction methods, upper structure of the main tower, etc. 6
Is placed on the top plate 5 (step).

【0016】以上の実施例では、一対のフレーム3、
3′をもって橋脚を構成したが、本発明は、これ以外に
も、図2(B)に示すような中空のコンクリート製また
は鋼製の支柱7を用いて橋脚を構成する支持部材とする
こともできる。即ち、当該支柱7と前記フレーム3との
組合せ、または、複数本の支柱7、7′による組合せが
可能である。更に、フレーム3または支柱7を組み合せ
て、図2(C)に示すような櫓形の基礎構造物8とする
ことも可能である。
In the above embodiment, a pair of frames 3,
Although the bridge pier is constituted by 3 ', the present invention may also be applied to a support member constituting a bridge pier by using a hollow concrete or steel pillar 7 as shown in FIG. 2 (B). it can. That is, a combination of the column 7 and the frame 3 or a combination of a plurality of columns 7, 7 'is possible. Furthermore, it is also possible to combine the frame 3 or the support column 7 to form a tower-shaped substructure 8 as shown in FIG.

【0017】[0017]

【発明の効果】本発明の海洋基礎構造物の建造方法は、
支持部材を簡易な構造の支柱をもって構成したので、構
造物を極めて簡易な方法により建造することができる。
また、支持部材の製作が全てドライドック内で行えるか
ら、洋上作業の多い従来法と比べて、工期を短縮するこ
とができ、品質管理も行き届くという優れた効果を有す
る。
The method for constructing an offshore substructure according to the present invention comprises:
Since the supporting member is constituted by the columns having a simple structure, the structure can be built by an extremely simple method.
In addition, since all of the support members can be manufactured in the dry dock, the construction period can be shortened and quality control can be performed well as compared with the conventional method that involves many offshore operations.

【図面の簡単な説明】[Brief description of the drawings]

【図1】橋脚の組立施工順序を示す説明図である。FIG. 1 is an explanatory diagram showing an assembling / construction order of a pier.

【図2】橋脚を構成する支持部材の変形例を示した図で
ある。
FIG. 2 is a view showing a modified example of a support member constituting a pier.

【符号の説明】[Explanation of symbols]

1 掘削孔 2 海底基礎 3、3′ フレーム 4 埋戻し 5 頂版 6 上部構造物 DESCRIPTION OF SYMBOLS 1 Drilling hole 2 Submarine foundation 3, 3 'frame 4 Backfill 5 Top plate 6 Superstructure

フロントページの続き (58)調査した分野(Int.Cl.6,DB名) E02B 17/02 E01D 19/02 E01D 21/00 E02D 27/32 E02B 17/00 Continuation of the front page (58) Field surveyed (Int. Cl. 6 , DB name) E02B 17/02 E01D 19/02 E01D 21/00 E02D 27/32 E02B 17/00

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 海洋構造物の基礎を構成する複数の支持
部材を組立場所以外で製作し、これを最終設置場所へ洋
上曳航し、該支持部材の下端部を海底地盤に着底させた
後、二以上の支持部材の頂部を連結し、かつ、各支持部
材の下端部を海底地盤に固定することを特徴とする海洋
基礎構造物の建造方法。
1. A plurality of support members constituting a foundation of an offshore structure are manufactured at a place other than an assembly place, and these are towed offshore to a final installation place, and a lower end portion of the support member is landed on the seabed ground. A method of constructing a marine substructure, comprising connecting the tops of two or more support members and fixing the lower end of each support member to the seabed.
JP18543591A 1991-06-29 1991-06-29 Construction method of offshore substructure Expired - Fee Related JP2953823B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18543591A JP2953823B2 (en) 1991-06-29 1991-06-29 Construction method of offshore substructure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18543591A JP2953823B2 (en) 1991-06-29 1991-06-29 Construction method of offshore substructure

Publications (2)

Publication Number Publication Date
JPH059922A JPH059922A (en) 1993-01-19
JP2953823B2 true JP2953823B2 (en) 1999-09-27

Family

ID=16170745

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18543591A Expired - Fee Related JP2953823B2 (en) 1991-06-29 1991-06-29 Construction method of offshore substructure

Country Status (1)

Country Link
JP (1) JP2953823B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4539989B2 (en) * 2006-01-31 2010-09-08 日鉄トピーブリッジ株式会社 Artificial seabed with upwelling flow and its construction method
JP6573277B2 (en) * 2015-11-02 2019-09-11 三井住友建設株式会社 How to build a main tower or pier

Also Published As

Publication number Publication date
JPH059922A (en) 1993-01-19

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
US3528254A (en) Offshore platform structure and construction method
US3987636A (en) Methods and apparatus for anchoring a submerged structure to a waterbed
GB2202494A (en) Deep water support assembly for a jack-up platform structure
KR101211811B1 (en) Cast in concrete pile With precast type Caisson
US3624702A (en) Offshore platform support
CN101392521A (en) Rock-socketed steel dock structure and construction method thereof
JP6105044B2 (en) Partially floating offshore platform for offshore wind power, bridges and offshore structures, and construction method
US4711601A (en) Method of installing offshore constructions
CN109518674B (en) Artificial island segment, assembled artificial island and construction method of assembled artificial island
RU2310721C1 (en) Protection device to protect self-elevating floating drilling installation for exploratory well drilling in ice conditions and method for protection device construction
US3091937A (en) Underwater foundation structure and method therefor
US3115013A (en) Artificial island and method of constructing the same
US4193714A (en) Method for erecting a deck on a marine structure
JPH06146305A (en) Underwater foundation and installation method thereof
JP2953823B2 (en) Construction method of offshore substructure
JP3075179B2 (en) Bridge pier foundation structure and its construction method
JPS58143023A (en) Caisson for pile supporting type breakwater
JP2002364004A (en) Installation method for underwater foundation
US2935854A (en) Offshore drilling platform
JP3463604B2 (en) Dolphin construction method
JP2822873B2 (en) Construction method of deep water foundation structure and its structure
JP2953818B2 (en) Construction method for deep water structures
JP3132846B2 (en) Construction method of pile type offshore structure
JPH0742182A (en) Leg type underwater tunnel and construction method for leg type underwater tunnel

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990622

LAPS Cancellation because of no payment of annual fees