JP7217195B2 - Double floor construction method - Google Patents

Double floor construction method Download PDF

Info

Publication number
JP7217195B2
JP7217195B2 JP2019082540A JP2019082540A JP7217195B2 JP 7217195 B2 JP7217195 B2 JP 7217195B2 JP 2019082540 A JP2019082540 A JP 2019082540A JP 2019082540 A JP2019082540 A JP 2019082540A JP 7217195 B2 JP7217195 B2 JP 7217195B2
Authority
JP
Japan
Prior art keywords
floor
pedestal
frame
columnar member
finished floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019082540A
Other languages
Japanese (ja)
Other versions
JP2020180442A (en
Inventor
秀樹 工藤
隆光 千葉
靖翔 川口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2019082540A priority Critical patent/JP7217195B2/en
Publication of JP2020180442A publication Critical patent/JP2020180442A/en
Application granted granted Critical
Publication of JP7217195B2 publication Critical patent/JP7217195B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Floor Finish (AREA)

Description

本発明は、二重床施工方法に関する。 The present invention relates to a double floor construction method.

各種機器類の配線や配管のスペースを確保すること等を目的として二重床が採用されている。また、音や振動の遮断を目的として、音響ホールなどにおいても二重床が作用される場合がある。
二重床では、上載する荷重、床下空間に必要な大きさ、二重床に求められる機能等に応じて様々な構造や形態が存在する。例えば、特許文献1では、構造床面上に固定された支持脚に床用台座をかけ渡し、床用台座上に床板を敷設している。また、特許文献2では、基礎部材と床用台座とが一体となった一体化ブロックを所定の位置に配設し、基礎部材を巻き込んだ状態で躯体床のコンクリートを打設した後、台座上に仕上げ床を敷設している。
なお、二重床を有する建物では、二重床の構築が終わらないと室内の仕上げ、天井または屋根の構築等の次工程に進むことができない場合がある。例えば、仕上げ床(浮床)に壁や壁の下地材等を上載する場合には、仕上げ床の施工後でないと壁や下地材等の施工を行うことができない。また、壁や下地材等の施工にクレーン等の揚重機を使用する場合には、揚重機が接触するおそれがある天井や屋根等の施工を壁や下地材等の施工が完了してから行うことになる。また、仕上げ床に上載する壁面や天井面等に仕上げを行う際には足場が必要となるが、仕上げ床の施工の妨げにならないように、足場の組み立ても仕上げ床の施工後に行う場合が発生している。
仕上げ床の施工に先立って、あるいは、仕上げ床の施工と並行して壁や壁の下地材の施工、壁面や天井面の仕上げ作業等を実施することができれば、施工期間の短縮が可能となる。
A double floor is used for the purpose of securing space for wiring and piping of various equipment. In addition, double floors are sometimes used in acoustic halls and the like for the purpose of blocking sound and vibration.
There are various structures and forms of double floors depending on the load to be placed, the required size of the underfloor space, and the functions required of the double floor. For example, in Patent Literature 1, a floor pedestal is stretched over supporting legs fixed on a structural floor surface, and a floor board is laid on the floor pedestal. In addition, in Patent Document 2, an integrated block in which a foundation member and a floor pedestal are integrated is arranged at a predetermined position, and after concrete for the building frame floor is placed in a state where the foundation member is involved, it is placed on the pedestal. Laying the finish floor on the
In addition, in a building having a double floor, it may not be possible to proceed to the next process such as interior finishing, construction of a ceiling or roof, etc. until the construction of the double floor is completed. For example, when a wall or base material for a wall is laid on the finished floor (floating floor), the wall or base material cannot be constructed until after the finish floor is constructed. In addition, when using cranes or other lifting equipment to construct walls and base materials, etc., work on ceilings and roofs that may come into contact with the lifting equipment should be completed after the construction of walls and base materials is completed. It will be. In addition, scaffolding is required when finishing the walls and ceilings that will be placed on the finished floor, but in order not to interfere with the construction of the finished floor, there are cases where the scaffolding is assembled after the construction of the finished floor. are doing.
The construction period can be shortened if it is possible to perform the construction of walls and base materials for walls, the finishing work of walls and ceilings, etc. prior to the construction of the finished floor or in parallel with the construction of the finished floor. .

特開2004-019236号公報Japanese Patent Application Laid-Open No. 2004-019236 特開2012-177225号公報JP 2012-177225 A

本発明は、二重床を有する建物の施工について、工期短縮化を図ることを可能とした二重床施工方法を提案することを課題とする。 SUMMARY OF THE INVENTION An object of the present invention is to propose a double floor construction method capable of shortening the construction period for construction of a building having a double floor.

前記課題を解決するために、本発明は、躯体床から離間した位置に仕上げ床を設ける二重床の施工方法であって、前記躯体床または躯体梁に仮設の台座を設置する台座設置工程と、前記台座上に柱状部材を建て込む柱状部材建込工程と、前記躯体床と前記柱状部材の下端との間に前記仕上げ床を形成する仕上げ床構築工程とを備えている。かかる二重床施工方法によれば、仕上げ床の施工前に柱状部材を設置するため、仕上げ床の施工と並行して室内の仕上げ、壁、天井または屋根の構築等の工程を行うことができ、その結果、工期短縮化を図ることができる。また、柱状部材(例えば、壁の鉄骨柱や足場の脚部等)を仕上げ床の上方に設置するため、柱状部材が仕上げ床の施工の妨げにならない。 In order to solve the above problems, the present invention provides a construction method for a double floor in which a finished floor is provided at a position spaced apart from a structural floor, comprising a pedestal installation step of installing a temporary pedestal on the structural floor or structural beam. , a columnar member erecting step of erecting a columnar member on the pedestal; and a finished floor constructing step of forming the finished floor between the frame floor and the lower end of the columnar member. According to this double floor construction method, since the columnar members are installed before the construction of the finished floor, processes such as interior finishing, wall, ceiling or roof construction can be performed in parallel with the construction of the finished floor. As a result, the construction period can be shortened. In addition, since the columnar members (for example, the steel columns of the walls, the legs of the scaffolding, etc.) are installed above the finished floor, the columnar members do not interfere with the construction of the finished floor.

柱状部材が下端にベースプレートが固定された鉄骨柱である場合には、前記柱状部材建込工程において前記ベースプレートにナットで係止されたボルトを前記台座に取り付け、前記台座と前記ベースプレートとの間に隙間をあけた状態で前記鉄骨柱を建て込み、前記仕上げ床構築工程後に前記ベースプレートから前記ボルトを取り外すことにより前記台座と前記鉄骨柱とを分離する。かかる二重床施工方法によれば、仕上げ床の施工後に柱状部材と台座とを簡易に分離することができる。そのため、柱状部材の存在が床下空間の利用の自由度等に影響を与えることがない。
ここで、前記柱状部材建込工程ではさや管が周設された前記ボルトを前記台座に取り付け、前記仕上げ床構築工程では前記さや管の周囲にコンクリートを打設して前記仕上げ床を形成すれば、ボルトが仕上げ床に固定されることがないため、ボルトの撤去が容易である。
When the columnar member is a steel frame column having a base plate fixed to its lower end, a bolt locked to the baseplate with a nut is attached to the pedestal in the columnar member erecting step, and a bolt is installed between the pedestal and the base plate. The pedestal and the steel column are separated by erecting the steel column with a gap, and removing the bolt from the base plate after the finishing floor construction step. According to this double floor construction method, the columnar member and the pedestal can be easily separated after construction of the finished floor. Therefore, the presence of the columnar member does not affect the degree of freedom of utilization of the underfloor space.
Here, in the step of erecting the columnar members, the bolts around which the sheath pipes are installed are attached to the pedestals, and in the step of constructing the finished floor, concrete is cast around the sheath pipes to form the finished floor. , bolts are easy to remove because they are not fixed to the finished floor.

前記柱状部材が下端にジャッキベースを備えた仮設の建枠の側柱(脚柱)である場合には、前記台座設置工程において前記躯体床または前記躯体梁に第一の台座を固定する作業と、前記仕上げ床の計画高さよりも高い位置において前記第一の台座の上に第二の台座を架け渡す作業とを行い、前記柱状部材建込工程において前記第二の台座上に前記ジャッキベースを設置する。かかる二重床施工方法によれば、台座である第二の台座上に足場の側柱等を設置することができる。第二の台座は、仕上げ床よりも高い位置に配設されているため、足場等を設置しても仕上げ床の施工を妨げることがない。 When the columnar member is a side pillar (pedestal) of a temporary construction frame having a jack base at the lower end, a work of fixing the first pedestal to the building frame floor or the building frame beam in the pedestal installation step; , and a second pedestal is bridged over the first pedestal at a position higher than the planned height of the finished floor, and the jack base is placed on the second pedestal in the column member erecting step. Install. According to this double floor construction method, it is possible to install the side pillars of the scaffolding on the second pedestal, which is the pedestal. Since the second pedestal is arranged at a position higher than the finished floor, installation of a scaffold or the like does not interfere with construction of the finished floor.

本発明の二重床施工方法によれば、仕上げ床の施工に先立ってあるいは仕上げ床の施工と並行して壁や壁の鉄骨柱の施工や、壁面や天井面の仕上げ作業等を実施することを可能となり、その結果、二重床を有する建物の施工について工期短縮化を図ることが可能となる。 According to the double floor construction method of the present invention, prior to or in parallel with the construction of the finished floor, the construction of the walls and the steel columns of the walls, the finishing work of the wall surface and the ceiling surface, etc. are carried out. As a result, it is possible to shorten the construction period for the construction of buildings with double floors.

第一実施形態に係る建物の一部を示す断面図である。It is a sectional view showing a part of building concerning a first embodiment. 第一実施形態に係る柱状部材の脚部を示す断面図である。It is a sectional view showing a leg of a columnar member concerning a first embodiment. 図2のA-A断面図である。FIG. 3 is a cross-sectional view taken along the line AA of FIG. 2; 第一実施形態の二重床施工方法を示すフローチャート図である。It is a flowchart figure which shows the double-floor construction method of 1st embodiment. 第一実施形態の台座設置工程を示す断面図である。It is sectional drawing which shows the pedestal installation process of 1st embodiment. (a)は図5に続く台座設置工程を示す断面図、(b)は(a)の平面図である。(a) is a cross-sectional view showing a pedestal installation process following FIG. 5, and (b) is a plan view of (a). 鉄骨柱の脚部を示す斜視図である。It is a perspective view which shows the leg part of a steel-frame column. 第一実施形態の柱状部材建込工程を示す断面図である。It is a sectional view showing a columnar member erection process of a first embodiment. (a)は図8に続く柱状部材建込工程を示す断面図、(b)は(a)の平断面図である。(a) is a cross-sectional view showing a columnar member erecting step following FIG. 8, and (b) is a horizontal cross-sectional view of (a). 第一実施形態の柱状部材上部の支持状況を示す側面図である。It is a side view which shows the support condition of the columnar member upper part of 1st embodiment. 第二実施形態に係る建物の施工状況を示す断面図である。It is sectional drawing which shows the construction condition of the building which concerns on 2nd embodiment. 第二実施形態の台座を示す図であって、(a)は横断図、(b)は縦断図である。It is a figure which shows the base of 2nd embodiment, Comprising: (a) is a cross-sectional view, (b) is a longitudinal cross-sectional view. 第二実施形態の二重床施工方法を示すフローチャート図である。It is a flowchart figure which shows the double-floor construction method of 2nd embodiment. (a)は第二実施形態の台座設置工程を示す断面図、(b)は(a)に続く台座設置工程を示す断面図である。(a) is a cross-sectional view showing a pedestal installation process of the second embodiment, and (b) is a cross-sectional view showing a pedestal installation process following (a). (a)は第二実施形態の分離工程を示す断面図、(b)は(a)に続く分離工程を示す断面図である。(a) is a cross-sectional view showing a separation step of the second embodiment, and (b) is a cross-sectional view showing a separation step following (a).

<第一実施形態>
本実施形態は、躯体床11上に、免震装置21を介して仕上げ床2を設けるものである。このような二重床の仕上げ床構造は、音楽ホール等がある。音楽ホール等では、ホール内の振動が躯体に伝わることがないように遮断構造となっている。そのため、このようなホール内の仕上げ構造は、仕上げ床2上に設ける必要がある。
第一実施形態では、図1に示すように躯体床11、躯体壁12および梁13を備える建物1の施工において、躯体床11の上面に隙間をあけて仕上げ床(浮き床)2を構築する二重床施工方法について説明する。建物1は、多目的ホールとして使用されるものであって、図1に示すように、躯体壁12の内側に、内壁30を有している。内壁30は、所定の間隔をあけて配設された複数のH形鋼からなる鉄骨柱3に、仕上げ材36を横架することにより形成する。本実施形態の内壁30は、上に向かうにしたがって、躯体壁12に近付くように傾斜している。鉄骨柱3は、内壁30の仕上げ材36を支持する柱状部材であり、図2および図3に示すように、H形鋼からなる柱本体37と、柱本体37の下端に固定されたベースプレート31からなる。
仕上げ床2は、免震装置21を介して躯体床11に上載されている。仕上げ床2の施工は、内壁30の施工と並行して行う。仕上げ床2は、捨て型枠としてのデッキプレート23の上面に鉄筋コンクリート層を積層することにより形成する。デッキプレート23には、鉄骨柱3の位置に対応して開口部23aが形成されている。仕上げ床2を施工する際には、開口部23aを塞ぎプレート61により遮蔽した状態で、コンクリートを打設する。開口部23aは、鉄骨柱3の建て込み後にデッキプレート23を敷設することが可能な大きさを有している。
<First Embodiment>
In this embodiment, the finished floor 2 is provided on the frame floor 11 via the seismic isolation device 21 . Music halls and the like have such a double-floor finished floor structure. In music halls, etc., they have a blocking structure so that vibrations in the hall are not transmitted to the frame. Therefore, the finished structure in such a hall must be provided on the finished floor 2 .
In the first embodiment, as shown in FIG. 1, in the construction of a building 1 having a frame floor 11, frame walls 12, and beams 13, a gap is provided on the top surface of the frame floor 11 to construct a finished floor (floating floor) 2. A double floor construction method will be explained. The building 1 is used as a multipurpose hall, and has an inner wall 30 inside the frame wall 12 as shown in FIG. The inner wall 30 is formed by laying a finishing material 36 across a plurality of steel columns 3 made of H-shaped steel arranged at predetermined intervals. The inner wall 30 of this embodiment is inclined so as to approach the building wall 12 as it goes upward. The steel frame column 3 is a columnar member that supports the finishing material 36 of the inner wall 30. As shown in FIGS. consists of
The finished floor 2 is placed on the frame floor 11 via a seismic isolation device 21 . Construction of the finished floor 2 is performed in parallel with construction of the inner wall 30. - 特許庁The finished floor 2 is formed by laminating a reinforced concrete layer on the upper surface of a deck plate 23 as a temporary formwork. Openings 23 a are formed in the deck plate 23 so as to correspond to the positions of the steel columns 3 . When constructing the finished floor 2, concrete is poured while the opening 23a is blocked by the closing plate 61. - 特許庁The opening 23a has a size that allows the deck plate 23 to be laid after the steel column 3 is erected.

以下、本実施形態の二重床施工法について説明する。
二重床施工方法は、図4に示すように、台座設置工程、柱状部材建込工程、床構築工程および分離工程を備えている。
The double floor construction method of this embodiment will be described below.
The double floor construction method, as shown in FIG. 4, includes a pedestal installation process, a columnar member erection process, a floor construction process, and a separation process.

台座設置工程は、図5に示すように、躯体床11上に台座4を設置する工程である。台座4は、鉄骨柱3を仕上げ床2よりも先に設置するために利用する仮設の台座であり、完成後は、鉄骨柱3と切り離される。台座4から切り離された鉄骨柱3は、仕上げ床2に支持されることとなる。台座4は、鉄筋コンクリート製のブロック状部材であって、躯体床11に植設されたアンカー45を巻き込んだ状態で形成する。アンカー45は、躯体床11を施工する際にあらかじめ埋め込んでおくか、あと施工により躯体床11に植設する。台座4の上面中央には、ボルト用穴41として、窪みが形成されている。本実施形態では、ボルト用穴41の深さを50mmとする。また、ボルト用穴41の内径は、内壁30の鉄骨柱3を建て込む際に使用するボルト5(図3参照)の外径に対応する大きさとする。 The pedestal installation step is a step of installing the pedestal 4 on the frame floor 11, as shown in FIG. The pedestal 4 is a temporary pedestal used for installing the steel frame column 3 prior to the finished floor 2, and is separated from the steel frame column 3 after completion. The steel column 3 separated from the pedestal 4 is supported by the finished floor 2. - 特許庁The pedestal 4 is a block-shaped member made of reinforced concrete, and is formed in a state in which an anchor 45 planted in the frame floor 11 is involved. The anchors 45 are embedded in advance when constructing the structural floor 11, or are planted in the structural floor 11 by post-construction. A depression is formed as a bolt hole 41 in the center of the upper surface of the base 4 . In this embodiment, the depth of the bolt hole 41 is set to 50 mm. Further, the inner diameter of the bolt hole 41 is set to a size corresponding to the outer diameter of the bolt 5 (see FIG. 3) used when erecting the steel frame column 3 of the inner wall 30 .

次に、図6に示すように、台座4の上面にさや管6を仮置きする。さや管6は、仕上げ床2に埋設されることで、仕上げ床2に貫通孔を形成し、仕上げ床2が完成する前の鉄骨柱3の下側を支えるボルト5の空間を確保するために設ける。すなわち、さや管6は、ボルト5が仕上げ床2に埋設、固定されることを防止し、仕上げ床2の完成後にボルト5の撤去を可能とするために、ボルト5用の貫通孔を仕上げ床2に形成するものである。さや管6は、ボルト5(図9参照)の外径よりも大きな内径と仕上げ床2の高さ(厚さ)と同等の長さを有した鋼管からなり、開口部23a(図3参照)を遮蔽するための塞ぎプレート61の上面に固定されている。台座4の上方に配設される塞ぎプレート61には、さや管6の位置に対応して貫通孔62が形成されている。当該塞ぎプレート61は、ベースプレート31と同等の形状を有している。なお、鉄骨柱3を構成する材料には溝型鋼やL形鋼等の鋼材も使用できる。塞ぎプレート61の貫通孔62は、図9(b)に示すように、ベースプレート31と重なるように塞ぎプレート61を配置した際に鉄骨柱3のウェブの延長線と貫通孔62とが接触することがないように、塞ぎプレート61の中心から偏心した位置に形成されている。塞ぎプレート61は、台座4の平面形状よりも大きな形状を有していて、台座4の上面に載置すると台座4から張り出す。さや管6を仮置きする際は、塞ぎプレート61を台座4の上面に載置する。このとき、さや管6は、台座4のボルト用穴41と位置が一致するように設置する。すなわち、さや管6、塞ぎプレート61の貫通孔62および台座4のボルト用穴41は、連通している。 Next, as shown in FIG. 6, the sheath tube 6 is temporarily placed on the upper surface of the pedestal 4 . The sheath pipe 6 is embedded in the finished floor 2 to form a through hole in the finished floor 2 and secure a space for the bolt 5 that supports the lower side of the steel column 3 before the finished floor 2 is completed. prepare. That is, the sheath pipe 6 has a through-hole for the bolt 5 to prevent the bolt 5 from being embedded and fixed in the finished floor 2 and to enable removal of the bolt 5 after the finished floor 2 is completed. 2. The sheath pipe 6 is made of a steel pipe having an inner diameter larger than the outer diameter of the bolt 5 (see FIG. 9) and a length equivalent to the height (thickness) of the finished floor 2, and has an opening 23a (see FIG. 3). is fixed to the upper surface of a closing plate 61 for shielding the A through-hole 62 is formed in a closing plate 61 arranged above the pedestal 4 so as to correspond to the position of the sheath tube 6 . The closure plate 61 has the same shape as the base plate 31 . Steel materials such as channel steel and L-shaped steel can also be used for the material constituting the steel frame column 3 . As shown in FIG. 9B, the through hole 62 of the closing plate 61 is arranged so that the extending line of the web of the steel frame column 3 and the through hole 62 contact each other when the closing plate 61 is arranged so as to overlap the base plate 31. It is formed at a position eccentric from the center of the closing plate 61 so that there is no The closing plate 61 has a shape larger than the planar shape of the pedestal 4 , and protrudes from the pedestal 4 when placed on the upper surface of the pedestal 4 . When temporarily placing the sheath tube 6 , the closing plate 61 is placed on the upper surface of the pedestal 4 . At this time, the sheath tube 6 is installed so as to be aligned with the bolt hole 41 of the base 4 . That is, the sheath tube 6, the through hole 62 of the closing plate 61, and the bolt hole 41 of the base 4 communicate with each other.

柱状部材建込工程は、台座4上に鉄骨柱3を建て込む工程である。本実施形態の鉄骨柱3は、図1に示すように、鉛直に対して傾斜した状態で建て込む。図7に示すように、鉄骨柱3のベースプレート31には、ボルト孔32が形成されている。鉄骨柱3を建て込む際には、まず、図8に示すように、ボルト孔32にボルト5を挿通させて、ベースプレート31の下面からボルト5を下向きに突出させる。このとき、ボルト5は、ベースプレート31の上面および下面にそれぞれ配設されたナット51,51で締着することにより、ベースプレート31に固定する。ボルト5は、ナット51,51を介して固定されているため、ベースプレート31からの突出長が調整可能である。鉄骨柱3を建て込む際にボルト5の突出長を調整することで、ベースプレート31の高さ位置を、仕上げ床2の計画高さよりも高い位置に配置する。次に、図9(a)に示すように、ベースプレート31の下面から突出させたボルト5をさや管6に貫通させた状態で台座4のボルト用穴41に挿入するとともに、鉄骨柱3の上部を梁13に取り付けることで、鉄骨柱3を配置する。台座4とベースプレート31との間には、ボルト5により隙間が形成されている。このとき、図9(b)に示すように、ベースプレート31と塞ぎプレート61とを平面視で重ねる。なお、ボルト5は、鉄骨柱3を所定の位置に配置してから、ボルト孔32を挿通せてボルト用穴41に挿入することができる。ボルト5は、ナット51を介してベースプレート31に着脱可能に取り付けられている。仕上げ床2の完成後に、ボルト5を撤去すれば、鉄骨柱3を躯体床11から分離されて鉄骨柱3が仕上げ床2により支持されるため、仕上げ床2の免震性を確保できる。 The columnar member erection process is a process of erecting the steel frame column 3 on the pedestal 4 . As shown in FIG. 1, the steel column 3 of this embodiment is built in a state inclined with respect to the vertical. As shown in FIG. 7 , bolt holes 32 are formed in the base plate 31 of the steel column 3 . When erecting the steel column 3, first, as shown in FIG. At this time, the bolt 5 is fixed to the base plate 31 by fastening with nuts 51, 51 provided on the upper and lower surfaces of the base plate 31, respectively. Since the bolt 5 is fixed via the nuts 51, 51, the projection length from the base plate 31 can be adjusted. The height position of the base plate 31 is arranged at a position higher than the planned height of the finished floor 2 by adjusting the projecting length of the bolt 5 when erecting the steel column 3.例文帳に追加Next, as shown in FIG. 9A, the bolts 5 projecting from the lower surface of the base plate 31 are inserted into the bolt holes 41 of the base 4 while passing through the sheath tube 6, and the upper portion of the steel column 3 is inserted. is attached to the beam 13, the steel frame column 3 is arranged. A gap is formed by the bolt 5 between the base 4 and the base plate 31 . At this time, as shown in FIG. 9B, the base plate 31 and the closing plate 61 are superimposed in plan view. The bolt 5 can be inserted through the bolt hole 32 and into the bolt hole 41 after the steel frame column 3 is placed at a predetermined position. The bolt 5 is detachably attached to the base plate 31 via the nut 51 . When the bolts 5 are removed after the finished floor 2 is completed, the steel columns 3 are separated from the frame floor 11 and the steel columns 3 are supported by the finished floor 2, so that the finished floor 2 can be seismically isolated.

図1に示すように、本実施形態の鉄骨柱3の上部で梁13の位置には、取付部材33が突設されている。取付部材33は、梁13の上面に乗るように延設されている。取付部材33は、図10に示すように、梁13との間に防振ゴム34を介設した状態で、梁13に上載する。すなわち、鉄骨柱3は、台座4と梁13で支えられる。 As shown in FIG. 1, a mounting member 33 protrudes from the upper portion of the steel column 3 of the present embodiment at the position of the beam 13 . The mounting member 33 extends so as to ride on the upper surface of the beam 13 . As shown in FIG. 10, the mounting member 33 is mounted on the beam 13 with the anti-vibration rubber 34 interposed therebetween. That is, the steel column 3 is supported by the pedestal 4 and the beams 13 .

仕上げ床構築工程では、図2および図3に示すように、躯体床11と鉄骨柱3(ベースプレート31)との間に仕上げ床2を形成する。仕上げ床構築工程では、まず、躯体床11の所定の位置に免震装置21(例えば、ゴム支承)を配設する。次に、仕上げ床2に必要な鉄筋22の配筋を行うとともに捨て型枠としてのデッキプレート23を設置する。デッキプレート23を敷設する際には、塞ぎプレート61がデッキプレート23に上載されるように、さや管6および塞ぎプレート61を持ち上げた状態で行う。デッキプレート23を敷設したら、塞ぎプレート61により開口部23aを遮蔽するように、塞ぎプレート61をデッキプレート23の上に載置する。開口部23aが塞ぎプレート61よりも大きい場合には、打設コンクリートが流出することがないように、塞ぎプレート61と開口部23aとの隙間を他の鋼板で塞ぐ。また、波型のデッキプレート23に平板上の塞ぎプレート61を載置することにより形成される隙間は、打設コンクリートが流出することがないように、シール材(図示せず)などにより塞ぐ。本実施形態では、仕上げ床2の配筋とともに、仕上げ床2と鉄骨柱3とを連結するためのアンカー筋35を配筋する。アンカー筋35は、L字状を呈していて、一端がベースプレート31に固定され、他端部が仕上げ床2内に埋設される。なお、仕上げ床2は無筋とすることもできる。また、アンカー筋35も必要に応じて配筋すればよく、仕上げ床2と鉄骨柱3との固定方法は限定されるものではない。 In the finished floor construction step, as shown in FIGS. 2 and 3, the finished floor 2 is formed between the frame floor 11 and the steel columns 3 (base plates 31). In the finishing floor construction process, first, a seismic isolation device 21 (for example, a rubber bearing) is arranged at a predetermined position of the structural floor 11 . Next, the reinforcing bars 22 necessary for the finished floor 2 are arranged, and a deck plate 23 is installed as a discarded formwork. When laying the deck plate 23 , the sheath tube 6 and the closing plate 61 are lifted so that the closing plate 61 is placed on the deck plate 23 . After laying the deck plate 23, the closing plate 61 is placed on the deck plate 23 so that the closing plate 61 blocks the opening 23a. If the opening 23a is larger than the closing plate 61, another steel plate closes the gap between the closing plate 61 and the opening 23a so that the poured concrete does not flow out. A gap formed by placing a flat closing plate 61 on the corrugated deck plate 23 is closed with a sealing material (not shown) or the like so that the poured concrete does not flow out. In this embodiment, along with the reinforcing bars of the finished floor 2, the anchor bars 35 for connecting the finished floor 2 and the steel columns 3 are arranged. The anchor bar 35 has an L shape, one end of which is fixed to the base plate 31 and the other end of which is embedded in the finished floor 2 . Note that the finished floor 2 can also be made plain. Also, the anchor bars 35 may be arranged as necessary, and the method of fixing the finished floor 2 and the steel frame columns 3 is not limited.

デッキプレート23を設置したら、コンクリートを打設する。コンクリートは、さや管6を巻き込んだ状態で打設する。仕上げ床2は、ベースプレート31の下面との間にわずかな(例えば50mm程度)隙間をあけた状態で形成する。 After installing the deck plate 23, concrete is placed. Concrete is placed in a state in which the sheath pipe 6 is involved. The finished floor 2 is formed with a slight (for example, about 50 mm) gap from the lower surface of the base plate 31 .

分離工程では、鉄骨柱3と台座4とを分離する。仕上げ床2のコンクリートに所定に強度が発現したら、ベースプレート31と仕上げ床2との間に間詰め材24を充填するとともにベースプレート31からボルト5を取り外す。間詰め材24には、無収縮モルタルを使用する。また、ボルト5を抜き出した後の仕上げ床2の貫通孔(さや管6内)には、充填材25を充填する。充填材25を構成する材料は限定されるものではないが、間詰め材24と同じ材料を使用することができる。 In the separation step, the steel column 3 and the pedestal 4 are separated. When the concrete of the finished floor 2 develops a predetermined strength, the filling material 24 is filled between the base plate 31 and the finished floor 2 and the bolts 5 are removed from the base plate 31 . Non-shrinkage mortar is used for the filling material 24 . Moreover, the through-hole (inside the sheath tube 6) of the finished floor 2 after the bolt 5 is pulled out is filled with the filler 25. As shown in FIG. The material constituting the filler 25 is not limited, but the same material as that of the filler 24 can be used.

本実施形態の二重床施工方法によれば、仕上げ床2の施工前に鉄骨柱3を設置するため、仕上げ床2の施工と並行して内壁30(仕上げ材36の設置作業等)の施工を行うことができる。また、鉄骨柱3は、仕上げ床2の上方に仮受けるため、鉄骨柱3の存在が仕上げ床2の施工の妨げにならない。その結果、工期短縮化を図ることができる。また、鉄骨柱3が床下空間の利用の自由度等に影響を与えることもない。
また、鉄骨柱3は、ボルト5を介して台座4に建て込むため、仕上げ床2の施工後の鉄骨柱3と台座4とを分離する作業が容易である。ボルト5には、さや管6が周設されているため、ボルト5が仕上げ床2に固定されることがなく、容易に撤去することができる。
ボルト5を撤去することで、仕上げ床2が躯体床11から分離されて、仕上げ床2が免震装置21に支持された状態となるため、ホール内で生じた振動等が、躯体床11等に伝達することを抑制できる。
According to the double floor construction method of the present embodiment, since the steel columns 3 are installed before the construction of the finished floor 2, the construction of the inner wall 30 (installation work of the finishing material 36, etc.) is performed in parallel with the construction of the finished floor 2. It can be performed. In addition, since the steel columns 3 are temporarily supported above the finished floor 2, the existence of the steel columns 3 does not hinder the construction of the finished floor 2.例文帳に追加As a result, the construction period can be shortened. In addition, the steel column 3 does not affect the degree of freedom of utilization of the underfloor space.
In addition, since the steel frame column 3 is built into the pedestal 4 via the bolts 5, the work of separating the steel frame column 3 and the pedestal 4 after construction of the finished floor 2 is easy. Since the sheath tube 6 is provided around the bolt 5, the bolt 5 is not fixed to the finished floor 2 and can be easily removed.
By removing the bolts 5, the finished floor 2 is separated from the frame floor 11, and the finished floor 2 is supported by the seismic isolation device 21. Therefore, the vibrations and the like that occur in the hall are removed from the frame floor 11 and the like. can be suppressed from being transmitted to

<第二実施形態>
第二実施形態では、第一実施形態と同様に、躯体床11の上面に隙間をあけて仕上げ床(浮き床)2を構築する二重床施工方法について説明する。本実施形態は、室内の仕上げ作業用の足場と仮設材(台座4)を用いるものである。仕上げ床2は、免震装置21を介して躯体床11の上面に形成する。仕上げ床2の施工は、図11に示すように、足場7を利用して壁面や天井面の仕上げを行う作業(仕上げ材36を設置する作業)と並行して行う。なお、足場7の使用目的は限定されるものではなく、例えば、内壁30の鉄骨柱3の建て込みに使用してもよい。足場7は、図12(a)および(b)に示すように、台座4の上に組み立てる。台座4は、躯体梁14上に設けられた複数の第一の台座42と、第一の台座42に上載された第二の台座43とからなる。
二重床施工方法は、図13に示すように、台座設置工程、柱状部材建込工程、床構築工程および分離工程を備えている。
<Second embodiment>
In the second embodiment, as in the first embodiment, a double floor construction method will be described in which the finished floor (floating floor) 2 is constructed with a gap in the upper surface of the frame floor 11 . This embodiment uses a scaffold and a temporary material (pedestal 4) for indoor finishing work. The finished floor 2 is formed on the upper surface of the frame floor 11 via the seismic isolation device 21 . As shown in FIG. 11, the finishing floor 2 is constructed in parallel with the work of finishing the wall surface and the ceiling surface using the scaffolding 7 (the work of installing the finishing material 36). The purpose of use of the scaffolding 7 is not limited. The scaffold 7 is assembled on the pedestal 4 as shown in FIGS. 12(a) and (b). The pedestal 4 consists of a plurality of first pedestals 42 provided on the frame beam 14 and second pedestals 43 placed on the first pedestal 42 .
The double floor construction method, as shown in FIG. 13, includes a pedestal installation process, a columnar member erection process, a floor construction process, and a separation process.

台座設置工程は、躯体床11上に台座4を設置する工程である。台座4は、足場7を支持する仮設部材であって、足場7の撤去後に撤去する。第二の台座43は、多数設けられる足場7の建枠71を支持することが可能となるように、連続した支持台を形成している。多数設けられる各建枠71に対して個々に仕上げ床2を貫通する台座4を形成すると、仕上げ床2の配筋が困難になるとともに、撤去作業にも手間がかかる。そのため、仕上げ床2よりも高い位置に、第一の台座42により支持された第二の台座43を配設して平台を形成することにより、より少ない台座4により複数の建枠71を支持する。第一の台座42は、いわゆる支柱を構成している。柱状の第一の台座42を所定の間隔をあけて配設することにより、仕上げ床2を貫通する部材を最小限に抑え、仕上げ床2を形成することを可能にしている。
台座設置工程では、図14(a)に示すように、まず、躯体梁14上に複数の第一の台座42を固定する。第一の台座42は、H形鋼を縦向きに設けることにより構成されている。なお、第一の台座42を構成する材料には、溝型鋼やL形鋼等の鋼材も使用できる。第一の台座42は、躯体梁14の上面から仕上げ床2の上面までの高さよりも大きな高さ(長さ)を有していて、仕上げ床2を形成した段階で、上端部が仕上げ床2の上面から突出するように構成されている。複数の第一の台座42は、所定の間隔をあけて配設する。本実施形態では、第一の台座42の上面に鋼板44が固定されている。
第一の台座42を設置したら、図14(b)に示すように、仕上げ床2の計画高さよりも高い位置において複数の第一の台座42に第二の台座43を架け渡すことにより、台座4を形成する。第二の台座43は、H形鋼を横向きに設けることにより構成されている。なお、第二の台座43を構成する材料には、溝型鋼やL形鋼等の鋼材も使用できる。第二の台座43は、第一の台座42の上端部にボルト接合する。
The pedestal installation process is a process of installing the pedestal 4 on the frame floor 11 . The pedestal 4 is a temporary member that supports the scaffolding 7 and is removed after the scaffolding 7 is removed. The second pedestal 43 forms a continuous support base so as to support the frame 71 of the scaffolding 7 provided in large numbers. If the pedestals 4 penetrating the finished floor 2 are individually formed for each of the many building frames 71, it becomes difficult to arrange the reinforcing bars of the finished floor 2, and the removal work is also troublesome. Therefore, by disposing the second pedestal 43 supported by the first pedestal 42 at a position higher than the finished floor 2 to form a flat base, the plurality of construction frames 71 are supported by fewer pedestals 4. . The first pedestal 42 constitutes a so-called support. By arranging the columnar first pedestals 42 at predetermined intervals, it is possible to minimize the number of members penetrating the finished floor 2 and form the finished floor 2 .
In the pedestal installation step, first, a plurality of first pedestals 42 are fixed on the structural beam 14, as shown in FIG. 14(a). The first pedestal 42 is configured by vertically providing an H-shaped steel. Steel such as channel steel and L-shaped steel can also be used as the material for forming the first pedestal 42 . The first pedestal 42 has a height (length) greater than the height from the upper surface of the structural beam 14 to the upper surface of the finished floor 2, and when the finished floor 2 is formed, the upper end portion is the finished floor. It is configured to protrude from the upper surface of 2 . The plurality of first pedestals 42 are arranged at predetermined intervals. In this embodiment, a steel plate 44 is fixed to the upper surface of the first pedestal 42 .
After installing the first pedestal 42, as shown in FIG. 4 is formed. The second pedestal 43 is configured by horizontally providing an H-shaped steel. Steel such as channel steel and L-shaped steel can also be used as the material for forming the second pedestal 43 . A second pedestal 43 is bolted to the upper end of the first pedestal 42 .

柱状部材建込工程は、図12(a)および(b)に示すように、台座4上に足場7を組み立てる工程である。本実施形態ではいわゆる枠組足場を利用して、仮設足場を形成する。足場7は、複数の建枠71を所定の間隔をあけて第二の台座43上に建て込むとともに、建枠71同士を筋交い72、つなぎ材73や足場板で連結することにより形成する。また、建枠71は、建枠71の側柱と第二の台座43との間にジャッキ74を介設させた状態で建て込む。ここで、建枠71は、左右の側柱(いわゆる脚柱)と両側柱に横架された横架材等を溶接組み立てして門型を呈している。足場7は、第二の台座43の上に組み立てるため、仕上げ床2の計画高さよりも高い位置に形成される。 The columnar member setting process is a process of assembling a scaffolding 7 on the pedestal 4, as shown in FIGS. 12(a) and 12(b). In this embodiment, a so-called framework scaffold is used to form a temporary scaffold. The scaffolding 7 is formed by erecting a plurality of frames 71 on the second pedestal 43 at predetermined intervals and connecting the frames 71 with braces 72, tethers 73 and scaffolding boards. Further, the frame 71 is erected with a jack 74 interposed between the side pillar of the frame 71 and the second pedestal 43 . Here, the frame 71 exhibits a portal shape by welding and assembling left and right side pillars (so-called pedestals) and horizontal members or the like that are horizontally mounted on both side pillars. Since the scaffolding 7 is assembled on the second pedestal 43, it is formed at a position higher than the planned height of the finished floor 2. - 特許庁

仕上げ床構築工程では、仕上げ床2を形成する。仕上げ床2は、図15(a)に示すように、躯体床11(躯体梁14)と第二の台座43(足場7の建枠71)との間に形成する。仕上げ床2の施工は、まず、躯体床11の所定の位置に免震装置21(図11参照)を配設する。次に、仕上げ床2に必要な鉄筋22(図2参照)の配筋を行うとともに型枠を設置する。そして、型枠内にコンクリートを打設する。コンクリートは、第一の台座42を巻き込んだ状態で打設する。 In the finished floor construction step, the finished floor 2 is formed. The finished floor 2 is formed between the frame floor 11 (framework beam 14) and the second pedestal 43 (the frame 71 of the scaffolding 7), as shown in FIG. 15(a). In constructing the finished floor 2, first, a seismic isolation device 21 (see FIG. 11) is installed at a predetermined position on the frame floor 11. As shown in FIG. Next, the reinforcing bars 22 (see FIG. 2) necessary for the finished floor 2 are arranged and the formwork is installed. Concrete is then poured into the formwork. Concrete is cast with the first pedestal 42 involved.

分離工程では、図15(b)に示すように、第一の台座42を切断して、台座4と仕上げ床2とを分離する。第一の台座42は、仕上げ床2のコンクリートに所定に強度が発現した後、仕上げ床2の下面において切断し、第一の台座42の仕上げ床2よりも下側の部分を撤去する。次に、壁および天井の仕上げ作業が完了したら、足場7および第二の台座43を撤去するとともに、第一の台座42の仕上げ床2の上面から突出する部分を仕上げ床2の上面において切断、撤去する。第一の台座42を切断、撤去することで、仕上げ床2が躯体床11から分離されて、仕上げ床2が免震装置21に支持された状態となるため、ホール内で生じた振動等が躯体床11等に伝達することを抑制できる。 In the separation step, as shown in FIG. 15(b), the first pedestal 42 is cut to separate the pedestal 4 and the finished floor 2 from each other. The first pedestal 42 is cut at the lower surface of the finished floor 2 after the concrete of the finished floor 2 develops a predetermined strength, and the portion of the first pedestal 42 below the finished floor 2 is removed. Next, when the wall and ceiling finishing work is completed, the scaffolding 7 and the second pedestal 43 are removed, and the portion of the first pedestal 42 protruding from the upper surface of the finished floor 2 is cut off on the upper surface of the finished floor 2. withdraw. By cutting and removing the first pedestal 42, the finished floor 2 is separated from the structural floor 11, and since the finished floor 2 is supported by the seismic isolation device 21, vibrations and the like generated in the hall are eliminated. It is possible to suppress transmission to the building frame floor 11 and the like.

本実施形態の二重床施工方法によれば、仕上げ床2の施工前に足場7を設置するため、仕上げ床2の施工と並行して壁や天井の仕上げ作業等を行うことができる。また、足場7を設置する台座4の第二の台座43を仕上げ床2の上方に設置するため、足場7が仕上げ床2の施工の妨げにならない。その結果、工期短縮化を図ることができる。 According to the double floor construction method of this embodiment, since the scaffolding 7 is installed before the construction of the finished floor 2, the finishing work of the walls and ceiling can be performed in parallel with the construction of the finished floor 2. Moreover, since the second pedestal 43 of the pedestal 4 for installing the scaffolding 7 is installed above the finished floor 2, the scaffolding 7 does not interfere with the construction of the finished floor 2. - 特許庁As a result, the construction period can be shortened.

以上、本発明の実施形態について説明したが、本発明は、前述の各実施形態に限られず、各構成要素については、本発明の趣旨を逸脱しない範囲で適宜設計変更が可能である。
例えば、台座4に設置する柱状部材は限定されるものではなく、例えば間柱であってもよい。
また、仕上げ床2の施工と並行して行う作業は、前記各実施形態で示した内容(壁の施工または壁や天井の仕上げ作業)に限定されるものではない。
前記実施形態では、柱状部材建込工程後に仕上げ床2の鉄筋22を配筋する場合について説明したが、施工の順序はこれに限定されるものではない。例えば、仕上げ床2の配筋後に、柱状部材を建て込んでもよい。
また、さや管6は、塞ぎプレート61に固定されている必要はない。
足場7として単管足場を使用する場合には、縦向きに立設された単管(柱状部材)を台座4により支持する。
Although the embodiments of the present invention have been described above, the present invention is not limited to the above-described embodiments, and each component can be appropriately modified in design without departing from the gist of the present invention.
For example, the columnar member installed on the pedestal 4 is not limited, and may be, for example, a stud.
In addition, the work performed in parallel with the construction of the finished floor 2 is not limited to the content (construction of walls or finishing work of walls and ceilings) shown in each of the above embodiments.
In the above embodiment, the case where the reinforcing bars 22 of the finished floor 2 are arranged after the columnar member erecting process has been described, but the order of construction is not limited to this. For example, columnar members may be erected after the finishing floor 2 is arranged with reinforcing bars.
Also, the sheath tube 6 need not be fixed to the closing plate 61 .
When a single pipe scaffold is used as the scaffold 7 , the pedestal 4 supports a single pipe (columnar member) erected vertically.

1 建物
11 躯体床
2 仕上げ床
3 鉄骨柱(柱状部材)
4 台座
5 ボルト
6 さや管
7 足場
71 建枠
1 building 11 frame floor 2 finished floor 3 steel column (columnar member)
4 pedestal 5 bolt 6 sheath tube 7 scaffolding 71 frame

Claims (4)

躯体床から離間した位置に仕上げ床を設ける二重床の施工方法であって、
前記躯体床または躯体梁に仮設の台座を設置する台座設置工程と、
前記台座上に柱状部材を建て込む柱状部材建込工程と、
前記躯体床と前記柱状部材の下端との間に前記仕上げ床を形成する仕上げ床構築工程と、を備えることを特徴とする、二重床施工方法。
A double floor construction method for providing a finished floor at a position spaced apart from a frame floor,
A pedestal installation step of installing a temporary pedestal on the building frame floor or building frame beam;
a columnar member erecting step of erecting a columnar member on the pedestal;
and a finishing floor construction step of forming the finishing floor between the frame floor and the lower end of the columnar member.
前記柱状部材は、下端にベースプレートが固定された鉄骨柱であり、
前記柱状部材建込工程では、前記ベースプレートにナットで係止されたボルトを前記台座に取り付け、前記台座と前記ベースプレートとの間に隙間をあけた状態で前記鉄骨柱を建て込み、
前記仕上げ床構築工程後に、前記ベースプレートから前記ボルトを取り外すことにより前記台座と前記鉄骨柱とを分離する分離工程をさらに備えていることを特徴とする、請求項1に記載の二重床施工方法。
The columnar member is a steel column with a base plate fixed to the lower end,
In the step of erecting the columnar member, a bolt locked to the base plate with a nut is attached to the pedestal, and the steel frame pillar is erected with a gap between the pedestal and the base plate,
The double floor construction method according to claim 1, further comprising a separation step of separating the pedestal and the steel frame column by removing the bolt from the base plate after the finished floor construction step. .
前記柱状部材建込工程では、さや管が周設された前記ボルトを前記台座に取り付け、
前記仕上げ床構築工程では、前記さや管の周囲にコンクリートを打設して前記仕上げ床を形成することを特徴とする、請求項2に記載の二重床施工方法。
In the step of erecting the columnar member, attaching the bolt having a sheath pipe around it to the pedestal;
3. The method of constructing a double floor according to claim 2, wherein in said finishing floor constructing step, concrete is placed around said sheath pipe to form said finishing floor.
前記柱状部材は、下端にジャッキベースを備えた仮設の建枠の側柱であり、
前記台座設置工程において、前記躯体床または前記躯体梁に第一の台座を固定する作業と、前記仕上げ床の計画高さよりも高い位置において前記第一の台座の上に第二の台座を架け渡す作業とを行い、
前記柱状部材建込工程において、前記第二の台座上に、前記ジャッキベースを設置することを特徴とする、請求項1に記載の二重床施工方法。
The columnar member is a side pillar of a temporary frame having a jack base at its lower end,
In the pedestal installation step, the first pedestal is fixed to the structural floor or the structural beam, and the second pedestal is bridged over the first pedestal at a position higher than the planned height of the finished floor. work and
2. The double floor construction method according to claim 1, wherein said jack base is installed on said second pedestal in said columnar member erecting step.
JP2019082540A 2019-04-24 2019-04-24 Double floor construction method Active JP7217195B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019082540A JP7217195B2 (en) 2019-04-24 2019-04-24 Double floor construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019082540A JP7217195B2 (en) 2019-04-24 2019-04-24 Double floor construction method

Publications (2)

Publication Number Publication Date
JP2020180442A JP2020180442A (en) 2020-11-05
JP7217195B2 true JP7217195B2 (en) 2023-02-02

Family

ID=73023729

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019082540A Active JP7217195B2 (en) 2019-04-24 2019-04-24 Double floor construction method

Country Status (1)

Country Link
JP (1) JP7217195B2 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002138597A (en) 2000-11-01 2002-05-14 Hayakawa Rubber Co Ltd Structure for partitioning wall
JP2003184293A (en) 2001-12-20 2003-07-03 Shimizu Corp Structure and construction method for floor-preceding double floor
JP2003213824A (en) 2002-01-23 2003-07-30 Yamaha Corp Building structure and construction method of partition wall
JP2003247331A (en) 2002-02-22 2003-09-05 Sanki Eng Co Ltd Floor panel support structure
JP2009007901A (en) 2007-06-29 2009-01-15 Takenaka Komuten Co Ltd Vibration-proofing stud
JP2009013675A (en) 2007-07-05 2009-01-22 Tokyu Construction Co Ltd Lift-up device, lift-up system, and lift-up method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS51719A (en) * 1974-06-21 1976-01-06 Matsushita Electric Works Ltd Kaikobuno yokozai kabepanerunadono toritsukesochi
JPH07292942A (en) * 1994-04-21 1995-11-07 Ahresty Corp Support for double floor

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002138597A (en) 2000-11-01 2002-05-14 Hayakawa Rubber Co Ltd Structure for partitioning wall
JP2003184293A (en) 2001-12-20 2003-07-03 Shimizu Corp Structure and construction method for floor-preceding double floor
JP2003213824A (en) 2002-01-23 2003-07-30 Yamaha Corp Building structure and construction method of partition wall
JP2003247331A (en) 2002-02-22 2003-09-05 Sanki Eng Co Ltd Floor panel support structure
JP2009007901A (en) 2007-06-29 2009-01-15 Takenaka Komuten Co Ltd Vibration-proofing stud
JP2009013675A (en) 2007-07-05 2009-01-22 Tokyu Construction Co Ltd Lift-up device, lift-up system, and lift-up method

Also Published As

Publication number Publication date
JP2020180442A (en) 2020-11-05

Similar Documents

Publication Publication Date Title
JP4658006B2 (en) Seismic isolation method for existing buildings and temporary seismic control panel
JP2005105766A (en) Removable support beam
JP4472726B2 (en) Base-isolated building structure
JP7217195B2 (en) Double floor construction method
KR101908356B1 (en) Aseismatic Reinforcement Double Steel Frame and Aseismatic Reinforcement Method using thereof
KR20190052638A (en) Beam-reinforced deck plate and construction method using the same
JP6404013B2 (en) Construction method of seismic isolation building
KR20180026286A (en) Grid precast concrete structure and constructing method thereof
JP3551816B2 (en) Seismic isolation method for existing buildings
JP6300228B2 (en) Flat slab structure
JP5479213B2 (en) Underfloor inspection structure
JP6504824B2 (en) Construction method of damping structure
JP7492073B1 (en) Equipment stand construction method
JP6114071B2 (en) Seismic isolation method for existing buildings and temporary structure under construction
JP4511080B2 (en) Construction method of underground structure
JP7151961B2 (en) Piping installation structure and piping pit construction method
KR101409249B1 (en) Top Down Construction method Using Method Of Steel Hybrid Girder Construction
JP6359349B2 (en) Mounting structure and mounting method
JPH0270848A (en) Floor slab
KR102425150B1 (en) External insulation construction method in which the gang form is supported by a reinforcing material to improve construction safety
JP3109877U (en) Base isolation structure
JP6630776B2 (en) Construction method of slab structure
JP2009197537A (en) Structure and method for supporting floor slab
JP6358602B2 (en) Reinforcement structure and reinforcement method for existing columns
JP2003035051A (en) Steel plate for earthquake resisting wall and method for building steel-plate earthquake resisting wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220222

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20221221

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230110

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230123

R150 Certificate of patent or registration of utility model

Ref document number: 7217195

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150