JP6718391B2 - How to suspend and remove concrete slabs - Google Patents

How to suspend and remove concrete slabs Download PDF

Info

Publication number
JP6718391B2
JP6718391B2 JP2017017575A JP2017017575A JP6718391B2 JP 6718391 B2 JP6718391 B2 JP 6718391B2 JP 2017017575 A JP2017017575 A JP 2017017575A JP 2017017575 A JP2017017575 A JP 2017017575A JP 6718391 B2 JP6718391 B2 JP 6718391B2
Authority
JP
Japan
Prior art keywords
concrete slab
suspending
main body
concrete
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017017575A
Other languages
Japanese (ja)
Other versions
JP2018123606A (en
Inventor
治 山口
治 山口
通男 高島
通男 高島
西山 宏一
宏一 西山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP2017017575A priority Critical patent/JP6718391B2/en
Publication of JP2018123606A publication Critical patent/JP2018123606A/en
Application granted granted Critical
Publication of JP6718391B2 publication Critical patent/JP6718391B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

本発明は、コンクリート版の吊降し撤去方法に関し、特に、連設方向に多数連設して配置されたコンクリート版を、順次吊り降ろして撤去してゆくコンクリート版の吊降し撤去方法に関する。 The present invention relates to a method for suspending and removing concrete slabs, and more particularly to a method for suspending and removing concrete slabs in which a large number of concrete slabs arranged in a row in a continuous direction are sequentially suspended and removed.

予め工場等において製造された、プレキャストコンリート製のコンクリート版を、連設方向に多数連設することによって形成された天井版や床版が、土木建造物等の種々の建造物の構成部分として設けられているが、このようなプレキャストコンリート製のコンクリート版を用いて形成された天井版や床版は、老朽化や、建造物の改築等に伴って、撤去する必要を生じることがある。 Ceiling slabs and floor slabs formed by arranging a large number of precast concrete slabs prefabricated in factories in the arranging direction are provided as constituent parts of various structures such as civil engineering structures. However, the ceiling slab and floor slab formed by using such a concrete slab made of precast concrete may need to be removed due to deterioration and renovation of a building.

これらのプレキャストコンリート製のコンクリート版は、一般に、横長の矩形状の平面形状を備えるように製造されており、長手方向の両端部を支持部材によって下方から支持せた状態で、短手方向に多数連設して配置することにより、これらが一体となって天井版や床版を形成している。このようなことから、天井版や床版を撤去する際に、これらの連設して配置された多数のコンクリート版を、順次効率良く撤去できるようにする技術が種々開発されている(例えば、特許文献1参照)。 These precast concrete slabs are generally manufactured so as to have a horizontally long rectangular planar shape, and in the state where both ends in the longitudinal direction are supported from below by supporting members, a large number in the lateral direction are provided. By arranging them in series, they are integrated to form a ceiling slab or floor slab. Therefore, when removing the ceiling slab or floor slab, various techniques have been developed that enable the sequential removal of a large number of these concrete slabs arranged in series (for example, See Patent Document 1).

特許文献1の天井板の撤去方法では、プレキャストコンリート製のコンクリート版を用いて形成された天井版や床版として、例えば道路用のトンネルの上部を仕切って形成されたトンネル天井版を、例えばジャッキ付き昇降台を備える移動式の特殊車両である多軸運搬車等を用いて、下方から支えながら、連設するコンクリート版を連設方向の先端部に位置するものから順次撤去してゆくようになっている。 In the method of removing a ceiling plate of Patent Document 1, as a ceiling slab or a floor slab formed by using a concrete slab made of precast concrete, for example, a tunnel ceiling slab formed by partitioning an upper part of a road tunnel, for example, a jack is used. Using a multi-axle carrier, which is a mobile special vehicle equipped with an attached lift, supports the concrete slabs from below while sequentially removing the concrete slabs from the one located at the tip in the cascading direction. Has become.

特開2016−142098号公報JP, 2016-142098, A

しかしながら、ジャッキ付き昇降台を備える移動式の特殊車両によって下方から支えながら、連設するコンクリート版を順次撤去してゆく方法では、重量物であるコンクリート版をバランス良く支持しながら昇降させるための制御が難しく、特に特殊車両が移動する路面等に、縦断勾配や横断勾配があると、コンクリート版をバランス良く支持しながら昇降させるための制御がさらに難しくなる。 However, in the method of sequentially removing the concrete slabs that are connected while supporting it from below by a movable special vehicle equipped with a lifting platform with jacks, a control for raising and lowering while supporting a heavy concrete slab in a well-balanced manner. However, if the road surface or the like on which the special vehicle moves has a vertical gradient or a transverse gradient, the control for raising and lowering the concrete slab while supporting it in a balanced manner becomes more difficult.

また、移動式のクレーン等を用いて、コンクリート版を上方から吊り上げながら撤去する方法も考えられるが、天井版よりも上方のスペースの大きさが限られていると、クレーン等のブームをコンクリート版の上方に配置することが難しくなって、十分な吊り代を確保することが困難になると共に、コンクリート版を吊り上げたり吊り降ろしたりする際に、ブームやコンクリート版が既設の構造物等と接触しないようにする操作に多くの手間がかかることになる。 It is also possible to remove the concrete slab while hoisting it from above using a mobile crane, but if the space above the ceiling slab is limited, the boom such as a crane can be removed from the concrete slab. It becomes difficult to place it above the floor, making it difficult to secure a sufficient hanging margin, and the boom and concrete slab do not come into contact with existing structures when hoisting or unloading the concrete slab. It takes a lot of time and effort to do so.

さらに、狭いスペースでも相当の吊り代を確保することが可能な、簡易な吊上げ用の装置として、例えばホイストクレーンを用いることも考えられるが、ホイストクレーンを用いる場合、ホイストクレーンを支持する鋼材を固定するためのアンカー部材を、例えばトンネルの天面部等の、天井版よりも上方の構造物に打ち込む必要を生じて、構造物を損傷することになると共に、アンカー部材を天井版よりも上方の構造物に打ち込むことで鋼材を固定するだけでは、十分な支持力を確保することが難しくなる。 Furthermore, as a simple hoisting device that can secure a considerable hoisting allowance even in a narrow space, for example, a hoist crane can be used, but when using a hoist crane, the steel material that supports the hoist crane is fixed. It is necessary to drive the anchor member to the structure above the ceiling slab, such as the top surface of the tunnel, which damages the structure and the anchor member above the ceiling slab. It is difficult to secure a sufficient supporting force only by fixing the steel material by driving it into an object.

このようなことから、連設して配置されて天井版や床版を形成する多数のコンクリート版を、安定した状態で、順次効率良く撤去してゆくことを可能にする新たな技術の開発が望まれている。 Therefore, the development of a new technology that enables the sequential removal of a large number of concrete slabs that are arranged in a row to form a ceiling slab or floor slab in a stable state Is desired.

本発明は、連設して配置されて天井版や床版を形成する多数のコンクリート版を、安定した状態で、順次効率良く撤去してゆくことのできるコンクリート版の吊降し撤去方法を提供することを目的とする。 The present invention provides a method for suspending and removing concrete slabs that can be sequentially and efficiently removed from a large number of concrete slabs that are continuously arranged to form a ceiling slab or a floor slab in a stable state. The purpose is to do.

本発明は、両端部が下方から支持されて、連設方向に多数連設して配置されたコンクリート版を、連設方向の先端側のコンクリート版から順次吊り降ろして撤去してゆくコンクリート版の吊降し撤去方法であって、昇降装置を取り付けた支持架台を、両端部をコンクリート版の両端部に各々載置して、前記連設方向に移動可能に設置する架台設置工程と、前記連設方向の先端部のコンクリート版を、前記支持架台から前記昇降装置を介して支持させた状態で、前記コンクリート版の両端部分において、前記支持架台が載置された両端部よりも内側に、切断装置により切断線を各々形成して、前記コンクリート版の本体部分を両端部分から切り離すコンクリート版切断工程と、切り離した前記コンクリート版の本体部分を、前記昇降装置により吊り降ろす本体部分吊降し工程と、前記本体部分を吊り降した後に、前記支持架台を前記連設方向の後端側に移動させて、残置した前記コンクリート版の両端部分を撤去する両端部分撤去工程とを含んで構成されるコンクリート版の吊降し撤去方法を提供することにより、上記目的を達成したものである。 The present invention, the both ends are supported from below, a large number of concrete slabs arranged in a row in the continuous direction, a concrete slab that is sequentially suspended and removed from the concrete slab on the tip side in the continuous direction. A method of suspending and removing, in which a support stand to which an elevating device is attached is placed on both ends of a concrete slab, respectively, and the support stand is installed so as to be movable in the connecting direction. The concrete slab at the tip of the installation direction is supported by the support cradle through the elevating device, and at both end portions of the concrete slab, cut inside the both ends where the support cradle is placed. A cutting line is formed by a device, respectively, a concrete plate cutting step of separating the main body portion of the concrete plate from both end portions, and a main body portion of the separated concrete plate is suspended by the elevating device. , After the main body portion is suspended, the support frame is moved to the rear end side in the continuous installation direction to remove both end portions of the remaining concrete slab The above object has been achieved by providing a method for suspending and removing a plate.

そして、本発明のコンクリート版の吊降し撤去方法は、前記コンクリート版切断工程において、前記コンクリート版の両端部分の前記切断線による切断面は、下方に向けて外側に傾斜するように各々形成されることが好ましい。 Then, the method for suspending and removing the concrete slab of the present invention is, in the concrete slab cutting step, cut surfaces by the cutting lines at both end portions of the concrete slab are respectively formed so as to be inclined outward toward the lower side. Preferably.

また、本発明のコンクリート版の吊降し撤去方法は、前記本体部分吊降し工程において、切り離した前記本体部分は、残置された前記両端部分よりも下方の空間領域において、これの長手方向が前記連設方向に沿うように回転移動された後に、さらに下方に吊り降ろされることが好ましい。 Further, the method of suspending and removing the concrete slab of the present invention is, in the suspending step of the main body portion, the separated main body portion is in a space region below the left and right end portions, and the longitudinal direction thereof is After being rotationally moved along the connection direction, it is preferably further hung down.

さらに、本発明のコンクリート版の吊降し撤去方法は、前記コンクリート版が、トンネルの内部の空間を上下に仕切るトンネル天井版を形成するものであることが好ましい。 Further, in the method of suspending and removing a concrete slab of the present invention, it is preferable that the concrete slab forms a tunnel ceiling slab that vertically divides a space inside a tunnel.

さらにまた、本発明のコンクリート版の吊降し撤去方法は、前記トンネルが、円形又は馬蹄形の断面形状を備えていることが好ましい。 Furthermore, in the method of suspending and removing a concrete slab of the present invention, it is preferable that the tunnel has a circular or horseshoe-shaped cross-sectional shape.

また、本発明のコンクリート版の吊降し撤去方法は、前記支持架台が、アーチ形状の支持本体部を備えていることが好ましい。 Further, in the method for suspending and removing a concrete slab of the present invention, it is preferable that the support frame includes an arch-shaped support body.

本発明のコンクリート版の吊降し撤去方法によれば、連設して配置されて天井版や床版を形成する多数のコンクリート版を、安定した状態で、順次効率良く撤去してゆくことができる。 According to the method of suspending and removing concrete slabs of the present invention, a large number of concrete slabs that are arranged in series to form a ceiling slab or a floor slab can be sequentially and efficiently removed in a stable state. it can.

本発明の好ましい一実施形態に係るコンクリート版の吊降し撤去方法により天井版が撤去されるトンネルの、(a)は略示横断面図、(b)は天井版の部分を上方から視た略示平面図である。In a tunnel in which a ceiling slab is removed by a method of suspending and removing a concrete slab according to a preferred embodiment of the present invention, (a) is a schematic cross-sectional view, and (b) is a ceiling slab viewed from above. It is a schematic plan view. 本発明の好ましい一実施形態に係るコンクリート版の吊降し撤去方法の架台設置工程を説明する、(a)は略示横断面図、(b)はトンネル内部の略示縦断面図、(c)はトンネル内部の略示平面図である。A cradle installation step of a method for suspending and removing a concrete slab according to a preferred embodiment of the present invention will be described. (a) is a schematic cross-sectional view, (b) is a schematic vertical cross-sectional view inside a tunnel, (c) ) Is a schematic plan view of the inside of the tunnel. 本発明の好ましい一実施形態に係るコンクリート版の吊降し撤去方法のコンクリート版切断工程を説明する、(a)は略示横断面図、(b)はトンネル内部の略示縦断面図、(c)はトンネル内部の略示平面図である。A concrete slab cutting process of a method for suspending and removing a concrete slab according to a preferred embodiment of the present invention will be described. (a) is a schematic transverse sectional view, (b) is a schematic longitudinal sectional view inside a tunnel, ( c) is a schematic plan view of the inside of the tunnel. 本発明の好ましい一実施形態に係るコンクリート版の吊降し撤去方法のコンクリート版切断工程を説明する、(a)は図3(a)のA部拡大図、(b)は(a)のB部拡大図である。A concrete slab cutting process of a method for suspending and removing a concrete slab according to a preferred embodiment of the present invention will be described. (a) is an enlarged view of part A of FIG. 3(a), (b) is B of (a). FIG. 本発明の好ましい一実施形態に係るコンクリート版の吊降し撤去方法の本体部吊降し工程を説明する、(a)は略示横断面図、(b)はトンネル内部の略示縦断面図、(c)はトンネル内部の略示平面図である。A main part suspending process of a method of suspending and removing a concrete slab according to a preferred embodiment of the present invention will be described. (a) is a schematic transverse sectional view, (b) is a schematic longitudinal sectional view inside a tunnel , (C) are schematic plan views of the inside of the tunnel. 本発明の好ましい一実施形態に係るコンクリート版の吊降し撤去方法の両端部分撤去工程を説明する、(a)は略示横断面図、(b)、(c)はトンネル内部の略示縦断面図である。A method of suspending and removing a concrete slab according to a preferred embodiment of the present invention will be described. Both end portions removing steps will be described. (a) is a schematic cross-sectional view, (b), (c) is a schematic vertical section inside a tunnel It is a side view.

本発明の好ましい一実施形態に係るコンクリート版の吊降し撤去方法は、プレキャストコンリート製のコンクリート版を連設方向に多数連設することによって形成された天井版や床版として、例えば図1(a)及び(b)に示すような、上部に円弧状の断面形状部分を含む馬蹄形の断面形状を備える道路トンネル50における、トンネルの内部の空間を上下に仕切って上部に形成されたトンネル天井版20を、連設された各々のコンクリート版21を順次吊り降ろしゆくことによって撤去するための方法として採用されたものである。すなわち、本実施形態の吊降し撤去方法は、道路トンネル50に設けられたトンネル天井版20が、例えば老朽化や、当該トンネル天井版20よりも上方の空間を利用した換気システムの変更等に伴って、撤去する必要を生じた際に、コンクリート版21を、連設方向Xの先端側に配置されたものから、安定した状態で、順次効率良く撤去してゆくことができるようにするための方法として採用されたものである。 A method of suspending and removing a concrete slab according to a preferred embodiment of the present invention is a ceiling slab or a floor slab formed by arranging a large number of precast concrete slabs in the arranging direction, for example, as shown in FIG. In a road tunnel 50 having a horseshoe-shaped cross-sectional shape including an arcuate cross-sectional shape portion as shown in a) and (b), a tunnel ceiling slab formed at the upper part by vertically partitioning the space inside the tunnel. 20 is adopted as a method for removing each of the concrete slabs 21 that are continuously installed by sequentially hanging it down. That is, the method of suspending and removing according to the present embodiment can be applied to, for example, deterioration of the tunnel ceiling slab 20 provided in the road tunnel 50, change of the ventilation system using a space above the tunnel ceiling slab 20, and the like. Accordingly, when it becomes necessary to remove the concrete slab 21, it is possible to sequentially and efficiently remove the concrete slab 21 from the one arranged on the tip side in the continuous direction X in a stable state. Was adopted as the method of.

そして、本実施形態のコンクリート版の吊降し撤去方法は、両端部21bが下方から支持されて、連設方向Xに多数連設して配置されたコンクリート版21を、連設方向Xの先端側のコンクリート版21から順次吊り降ろして撤去してゆく撤去方法であって、図2〜図6に示すように、ホイストクレーン等の公知の簡易な昇降装置31を取り付けた支持架台30を、両端部30cをコンクリート版21の両端部21bに各々載置して、連設方向Xに移動可能に設置する架台設置工程(図2(a)〜(c)参照)と、連設方向Xの先端部のコンクリート版21を、支持架台30から昇降装置31を介して支持させた状態で、コンクリート版21の両端部分21cにおいて、支持架台30が載置された両端部21bよりも内側に、切断装置35(図4(a)参照)により切断線40を各々形成して、コンクリート版21の本体部分21aを両端部分21cから切り離すコンクリート版切断工程(図3(a)〜(c)参照)と、切り離したコンクリート版21の本体部分21aを、昇降装置31により吊り降ろす本体部分吊降し工程(図5(a)〜(c)参照)と、本体部分21aを吊り降した後に、支持架台30を連設方向Xの後端側に移動させて、残置したコンクリート版の両端部分21cを撤去する両端部分撤去工程(図6(a)〜(c)参照)とを含んで構成されている。 Then, in the method of suspending and removing the concrete slab of the present embodiment, both ends 21b are supported from below, and the concrete slabs 21 arranged in a row in the continuous direction X are arranged at the front end in the continuous direction X. It is a removal method in which the concrete slab 21 on the side is sequentially hung and removed, and as shown in FIGS. 2 to 6, a support platform 30 to which a known simple lifting device 31 such as a hoist crane is attached is A pedestal installation step (see FIGS. 2A to 2C) in which the parts 30c are respectively placed on both ends 21b of the concrete slab 21 and movably installed in the continuous installation direction X, and a tip in the continuous installation direction X. Part of the concrete slab 21 while being supported from the support pedestal 30 via the lifting device 31, inside the both ends 21c of the concrete slab 21 inside the both ends 21b on which the support pedestal 30 is placed, a cutting device A concrete slab cutting step (see FIGS. 3(a) to 3(c)) of forming the cutting lines 40 by 35 (see FIG. 4(a)) to separate the main body portion 21a of the concrete slab 21 from the end portions 21c. The main body portion 21a of the separated concrete slab 21 is suspended by the elevating device 31 to suspend the main body portion 21a (see FIGS. 5A to 5C), and after suspending the main body portion 21a, the support pedestal 30 is attached. Both ends are removed by moving to the rear end side in the continuous direction X and removing both end portions 21c of the remaining concrete slab (see FIGS. 6A to 6C).

また、本実施形態のコンクリート版の吊降し撤去方法では、コンクリート版切断工程において、コンクリート版21の両端部分21cの切断線40による切断面40aは、好ましくは下方に向けて外側に傾斜するように各々形成されている(図4(a)参照)。 Further, in the method of suspending and removing the concrete slab of the present embodiment, in the concrete slab cutting step, the cutting surface 40a by the cutting line 40 of both end portions 21c of the concrete slab 21 is preferably inclined downward toward the outside. Are formed on the respective surfaces (see FIG. 4A).

さらに、本実施形態のコンクリート版の吊降し撤去方法では、本体部吊降し工程において、切り離した本体部分21aは、残置された両端部分21cよりも下方の空間領域において、好ましくはこれの長手方向L(図5(b)、(c)参照)が連設方向Xに沿うように回転移動(図5(a)参照)された後に、さらに下方に吊り降ろされるようになっている。 Further, in the method of suspending and removing a concrete slab of the present embodiment, in the main body suspending step, the separated main body portion 21a is preferably in the space region below the left and right end portions 21c, preferably the length thereof. After the direction L (see FIGS. 5B and 5C) is rotationally moved along the continuous direction X (see FIG. 5A), it is further hung down.

また、本実施形態では、コンクリート版の吊降し撤去方法に用いられる支持架台30は、図2(a)〜(c)及び図3(a)〜(c)に示すように、アーチ形状を備えると共に、両端部30cが、トンネル天井版20を形成する既存のコンクリート版21の両端部21bに配置される、連設方向Xに間隔をおいて設けられた少なくとも一対(本実施形態では、一対)のH形鋼等からなる支持本体部30aと、これらの支持本体部30aの上部に連設方向Xに延設して設けられて、これらの支持本体部30aを連結すると共に、昇降装置31が取り付けられている、I形鋼等からなる連結支持ビーム部30bとを含んで構成されている。 Further, in the present embodiment, the support frame 30 used in the method for suspending and removing the concrete slab has an arch shape as shown in FIGS. 2(a) to (c) and FIGS. 3(a) to (c). Both ends 30c are provided at both ends 21b of the existing concrete slab 21 that forms the tunnel ceiling slab 20 and are provided at least in a pair in the continuous direction X (in the present embodiment, a pair). ) Of the H-shaped steel and the like, and a support main body 30a extending in the continuous direction X above the support main body 30a for connecting the support main body 30a and a lifting device 31. And a connecting support beam portion 30b made of I-shaped steel or the like.

ここで、支持架台30は、好ましくは道路トンネル50のトンネル天井版20を形成する既存のコンクリート版21を、連設方向Xの先端側のコンクリート版21から順次吊り降ろして撤去してゆく際に用いる、トンネル天井部コンクリート版の吊降し撤去機構10を構成する架台となっている。トンネル天井部コンクリート版の吊降し撤去機構10は、連設する既存のコンクリート版21の上に設置されて、連設方向Xに移動可能な支持架台30と、支持架台30に取り付けられ、撤去されるコンクリート版21を吊上げ吊降し可能な昇降装置31と、昇降装置31から吊り下げて設けられ、吊り下げられた撤去されるコンクリート版21を回転可能に支持する回転冶具32とを含んで構成されている(図3(a)〜(c)、図5(a)〜(c)参照)。 Here, the support frame 30 is preferably used when the existing concrete slab 21 forming the tunnel ceiling slab 20 of the road tunnel 50 is sequentially hung from the concrete slab 21 on the tip side in the continuous direction X and removed. It is a pedestal that constitutes a mechanism 10 for suspending and removing the concrete slab from the tunnel ceiling. The hanging and removing mechanism 10 for the tunnel ceiling concrete slab is installed on the existing concrete slab 21 that is continuously installed, and is mounted on the support pedestal 30 and the support pedestal 30 that are movable in the continuous installation direction X, and then removed. And an elevating device 31 capable of hoisting the concrete slab 21 to be suspended, and a rotating jig 32 hung from the elevating device 31 and rotatably supporting the suspended concrete slab 21 to be removed. It is configured (see FIGS. 3A to 3C and FIGS. 5A to 5C).

また、本実施形態では、支持架台30を構成する連結支持ビーム部30bは、支持本体部30aにおける同様の高さ位置に、一対設けられており、各々の連結支持ビーム部30bに、昇降装置31が、当該連結支持ビーム部30bに沿って移動可能に取り付けられている。 In addition, in the present embodiment, a pair of connection support beam portions 30b forming the support pedestal 30 are provided at the same height position in the support body portion 30a, and the lifting device 31 is provided in each connection support beam portion 30b. Is movably attached along the connection support beam portion 30b.

さらに、本実施形態では、吊降し撤去機構10を構成する回転冶具32は、昇降装置31から吊り下げられる上部ビーム部33と、撤去されるコンクリート版21を吊り下げる下部ビーム部34とからなり、下部ビーム部34は、回転連結部34aを介して上部ビーム部33と回転可能に連結していることにより、吊り下げられた撤去されるコンクリート版21を、上部ビーム部33に対して回転させることができるようになっている。 Further, in the present embodiment, the rotary jig 32 that constitutes the suspending and removing mechanism 10 includes an upper beam portion 33 that is suspended from the elevating device 31 and a lower beam portion 34 that suspends the concrete slab 21 to be removed. , The lower beam part 34 is rotatably connected to the upper beam part 33 via the rotary connection part 34a, so that the suspended concrete slab 21 is rotated with respect to the upper beam part 33. You can do it.

本実施形態では、図1(a)、(b)に示すように、コンクリート版の吊降し撤去方法によって撤去されるトンネル天井版20は、予め工場等において製造された、プレキャストコンリート製のコンクリート版21を、道路トンネル50の軸方向に沿った連設方向Xに、多数連設して配置することによって形成されている。コンクリート版21は、各々、例えば1500mm程度の長さの短辺と、トンネル天井版20が設置される位置における道路トンネル50の横幅と同様の長さとして、例えば8000mmの長さの長辺とを備える、横長の矩形状の平面形状を有している。コンクリート版21は、道路トンネル50の側壁部から内側に張り出して設けられた、後述する支持部材22に、長辺方向の両端部を支持させると共に、短辺方向を連設方向Xとして、長辺部分を互いに当接させた状態で、多数連設配置された状態で設けられている。また、これらの連設配置されたコンクリート版21は、例えばPC鋼線、連結鋼棒、連結ボルト等(図示せず)を用いて、公知の方法によって、複数のコンクリート版21が、連設方向Xに適宜一体化された状態で設けられている。 In the present embodiment, as shown in FIGS. 1A and 1B, the tunnel ceiling slab 20 to be removed by the method for suspending and removing the concrete slab is a concrete made of precast concrete which is manufactured in advance in a factory or the like. It is formed by arranging a large number of plates 21 in a continuous direction X along the axial direction of the road tunnel 50. Each concrete slab 21 has, for example, a short side having a length of about 1500 mm and a long side having a length similar to the lateral width of the road tunnel 50 at a position where the tunnel ceiling slab 20 is installed, for example, 8000 mm. It has a horizontally long rectangular planar shape. The concrete slab 21 supports both ends in the long side direction on a support member 22 which will be described below and is provided so as to project inward from the side wall of the road tunnel 50, and the short side is defined as the continuous direction X and the long side. It is provided in a state where a large number of parts are arranged in a row in a state where the parts are in contact with each other. In addition, the concrete slabs 21 arranged in succession are, for example, PC steel wires, connecting steel rods, connecting bolts (not shown) and the like, by a known method. It is provided in a state where it is appropriately integrated with X.

コンクリート版21の長辺方向の両端部を支持する支持部材22は、図4(a)、(b)にも示すように、H形鋼等の各種の鋼材を適宜加工することによって形成された、公知の道路トンネル50用のブラケット部材を用いることができる。ブラケット部材22は、道路トンネル50の側壁部の円弧状の断面形状に沿った、湾曲する外周面形状を備える接合基部22aと、接合基部22aから内側に張り出して設けられた、受台部22bとを含んで形成されている。接合基部22aは、これの外周面を、トンネル天井版20が設置される高さ位置における道路トンネル50の側壁部の内側面に密着させた状態で、例えば接合固定ボルト(図示せず)を、側壁部に向けて締着させることによって、ブラケット部材22を、受台部22bを内側に張り出させた状態で、道路トンネル50の側壁部の所定の位置に、強固に接合固定することができる。 As shown in FIGS. 4(a) and 4(b), the supporting member 22 that supports both ends of the concrete slab 21 in the long side direction is formed by appropriately processing various steel materials such as H-section steel. A known bracket member for the road tunnel 50 can be used. The bracket member 22 includes a joining base portion 22a having a curved outer peripheral surface shape along the arcuate cross-sectional shape of the side wall portion of the road tunnel 50, and a cradle portion 22b provided so as to project inward from the joining base portion 22a. Is formed. The joining base portion 22a is, for example, with a joining fixing bolt (not shown) in a state where the outer peripheral surface of the joining base portion 22a is in close contact with the inner surface of the side wall portion of the road tunnel 50 at the height position where the tunnel ceiling slab 20 is installed. By tightening the bracket member 22 toward the side wall portion, the bracket member 22 can be firmly joined and fixed to a predetermined position of the side wall portion of the road tunnel 50 in a state where the cradle portion 22b is bulged inward. ..

ブラケット部材22は、本実施形態では、図1(a)、(b)に示すように、道路トンネル50の両側の側壁部における所定の高さ位置において、コンクリート版21の連設方向Xである道路トンネル50の軸方向に、コンクリート版21の短辺の長さと同様のピッチで、間隔をおいて複数の箇所に各々取り付けらており、これらの受台部22bに、コンクリート版21の両端部21bを載置させることで、多数のコンクリート版21を、各々下方から支持することができるようになっている。 In the present embodiment, the bracket member 22 is in the continuous installation direction X of the concrete slab 21 at a predetermined height position on the side wall portions on both sides of the road tunnel 50, as shown in FIGS. 1(a) and 1(b). Along the axial direction of the road tunnel 50, the same pitch as the length of the short side of the concrete slab 21 is attached to each of a plurality of locations at intervals. By placing 21b, a large number of concrete slabs 21 can be supported from below.

ブラケット部材22の受台部22bは、コンクリート版21の端部を載置させる平坦な載置面22cを備えており(図4(a)、(b)参照)、載置面22cは、例えば縦横400mm程度の大きさの、矩形状(正方形状)の平面形状を備えている。各々コンクリート版21は、各々のブラケット部材22の受台部22bに、各隣接する一対のコンクリート版21の端部角部分を、載置面22cを2分割した領域にそれぞれ載置することにより取り付けられている。これによって、各々のコンクリート版21は、4箇所の端部角部分を、4箇所のブラケット部材22の受台部22bにそれぞれ載置することで、これらの各4箇所のブラケット部材22によって下方から支持されて、安定した状態で取り付けられている。各々のコンクリート版21は、載置面22cに載置された4箇所の端部角部分において、受台部22bに向けて固定アンカー23を締着することによって、ブラケット部材22に強固に固定されている。 The cradle part 22b of the bracket member 22 includes a flat mounting surface 22c on which the end of the concrete slab 21 is mounted (see FIGS. 4A and 4B), and the mounting surface 22c is, for example, It has a rectangular (square) planar shape with a size of about 400 mm in length and width. Each concrete slab 21 is attached to the pedestal portion 22b of each bracket member 22 by placing the end corners of each pair of adjacent concrete slabs 21 in the two divided regions of the placement surface 22c. Has been. Thereby, each of the concrete slabs 21 is placed from the bottom by the bracket members 22 at each of these four locations by placing the four corners of the corner on the pedestals 22b of the bracket members 22 at the four locations. It is supported and mounted in a stable condition. Each concrete slab 21 is firmly fixed to the bracket member 22 by fastening the fixed anchors 23 toward the pedestal portion 22b at the four corners of the end placed on the placing surface 22c. ing.

そして、本実施形態では、コンクリート版の吊降し撤去方法は、上述のように、架台設置工程(図2(a)〜(c)参照)と、コンクリート版切断工程(図3(a)〜(c)参照)と、本体部吊降し工程(図5(a)〜(c)参照)と、両端部分撤去工程(図6(a)〜(c)参照)とを含んで構成されている。 Then, in the present embodiment, the method for suspending and removing the concrete slab is, as described above, the gantry setting step (see FIGS. 2A to 2C) and the concrete slab cutting step (FIG. 3A to ). (See (c)), a main body suspension step (see FIGS. 5(a) to 5(c)), and both end portion removal steps (see FIGS. 6(a) to 6(c)). There is.

架台設置工程では、昇降装置31を取り付けた支持架台30を、両端部30cをコンクリート版21の両端部21bに各々載置して、連設方向Xに移動可能状態で、撤去すべき既存のトンネル天井版20の上に設置する。すなわち、架台設置工程では、ウィンチ等の簡易な装置を用いて作業員の手作業により組み立て可能な大きさや重量の構成部材に分解した状態で、支持架台30や吊降し撤去機構10を、図2(a)〜(c)に示すように、運搬車両55によって道路トンネル50の施工箇所まで運搬すると共に、運搬されてきた支持架台30や吊降し撤去機構10の構成部材を、例えば小型クレーン56を用いて吊り上げて、撤去すべき既存のトンネル天井版20の上に搬送する。また、後述する切断装置としてのコンクリートカッター装置35やウィンチ等の、その他の必要な装置や機器を、同様に例えば小型クレーン56を用いて吊り上げて、撤去すべき既存のトンネル天井版20の上に搬送する。 In the gantry installation step, the support gantry 30 to which the lifting device 31 is attached is placed at both ends 30c on both ends 21b of the concrete slab 21, respectively, and the existing tunnel to be removed is movable in the continuous direction X. It is installed on the ceiling slab 20. That is, in the gantry installation step, the support gantry 30 and the hanging-up/removing mechanism 10 are disassembled in a state in which they are disassembled into constituent members of a size and weight that can be manually assembled by a worker using a simple device such as a winch. As shown in FIGS. 2(a) to 2(c), while being transported by the transport vehicle 55 to the construction site of the road tunnel 50, the transported support frame 30 and the constituent members of the suspension removal mechanism 10 are transferred to, for example, a small crane. It is lifted using 56 and conveyed on the existing tunnel ceiling slab 20 to be removed. Further, other necessary devices and equipment such as a concrete cutter device 35 as a cutting device and a winch, which will be described later, are similarly lifted by using, for example, a small crane 56 and placed on the existing tunnel ceiling slab 20 to be removed. Transport.

しかる後に、既存のトンネル天井版20の上での作業によって、作業員が、搬送された装置や機器を用いて、分解された支持架台30や吊降し撤去機構10の構成部材から、上述の構成を備える当該支持架台30や吊降し撤去機構10を組み立てる。 After that, by the work on the existing tunnel ceiling slab 20, the worker uses the transported device or equipment to remove the above-mentioned components from the disassembled support platform 30 or the components of the suspension removal mechanism 10. The supporting base 30 and the suspension removing mechanism 10 having the structure are assembled.

組み立てられた支持架台30には、一対のアーチ形状の支持本体部30aの各々の下端部でもある両端部30cに、移動用の車輪部材37として、好ましくは公知のチルタンクを取り付けておくことができる(図4(a)、(b)参照)。これによって、取り付けられた昇降装置31や回転冶具32と共に支持架台30を、例えば作業員の手作業により押し出して、コンクリート版21の連設方向Xにスムーズに移動させることができるようになっている。 In the assembled support base 30, it is possible to attach a well-known chill tank, preferably as a wheel member 37 for movement, to both end portions 30c which are also lower end portions of the pair of arch-shaped support main body portions 30a. (See FIGS. 4A and 4B). As a result, the supporting frame 30 together with the attached lifting device 31 and rotary jig 32 can be extruded by, for example, a manual operation of an operator and smoothly moved in the continuous direction X of the concrete slab 21. ..

また、本実施形態では、連設配置されて既存のトンネル天井版20を形成するコンクリート版21の両端部21bに、コンクリート版21の連設方向に沿って延設させて、例えばL形鋼からなるずれ止めガイド部材36(図4(a)、(b)参照)を、各々取り付けておくこともできる。これによって、アーチ形状の支持本体部30aから撤去すべきコンクリート版21を吊り下げた際に、支持本体部30aの両端部30cが、コンクリート版21の重量により間隔を広げるようにして、外側にずれることになるのを効果的に防止することが可能になると共に、支持架台30の両端部30cを案内して、支持架台30を、コンクリート版21の連設方向Xに、よりスムーズに移動させることが可能になる。 In addition, in the present embodiment, both ends 21b of the concrete slab 21 that are continuously arranged to form the existing tunnel ceiling slab 20 are made to extend along the continuous arranging direction of the concrete slab 21, for example, from an L-shaped steel. The slip prevention guide members 36 (see FIGS. 4A and 4B) may be attached respectively. As a result, when the concrete slab 21 to be removed from the arch-shaped support main body 30a is hung, both end portions 30c of the support main body 30a are displaced outward due to the increased weight of the concrete slab 21. It is possible to effectively prevent this from happening, and to guide the both ends 30c of the support platform 30 to move the support platform 30 more smoothly in the continuous direction X of the concrete slab 21. Will be possible.

さらに、本実施形態では、支持架台30を構成する連結支持ビーム部30bは、上述のように、支持本体部30aにおける同様の高さ位置に、一対設けられており、各々の連結支持ビーム部30bに、昇降装置31が取り付けられている。これによって、撤去すべきコンクリート版21を、回転冶具32を介在させて、一対の昇降装置31によって支持本体部30aから吊り下げることで、より安定した状態で、吊り上げたり吊り降ろしたりすることが可能になる。 Further, in the present embodiment, as described above, the pair of connection support beam portions 30b that configure the support pedestal 30 are provided at the same height position in the support main body portion 30a, and each connection support beam portion 30b. An elevating device 31 is attached to the. Accordingly, the concrete slab 21 to be removed can be lifted or hung in a more stable state by suspending the concrete slab 21 from the support main body portion 30a by the pair of lifting devices 31 with the rotary jig 32 interposed. become.

本実施形態のコンクリート版の吊降し撤去方法におけるコンクリート版切断工程では、図3(a)及び図4(a)、(b)に示すように、連設方向Xの先端部のコンクリート版21を、支持架台30から昇降装置31を介して支持させた状態で、コンクリート版21の両端部分21cにおいて、支持架台30が載置された両端部21bよりも内側に、切断装置35により切断線40を各々形成して、コンクリート版21の本体部分21aを両端部分21cから切り離す。 In the concrete slab cutting step in the method of suspending and removing a concrete slab of the present embodiment, as shown in FIGS. 3(a), 4(a) and 4(b), the concrete slab 21 at the tip portion in the continuous direction X is While being supported from the support cradle 30 via the elevating device 31, the cutting line 40 is cut by the cutting device 35 at both end portions 21c of the concrete slab 21 inside the both end portions 21b on which the support cradle 30 is placed. And the main body portion 21a of the concrete slab 21 is separated from both end portions 21c.

すなわち、コンクリート版切断工程では、連設方向Xの先端部のコンクリート版21の、両端部21bの間の本体部分21aの所定の位置に、アンカー(図示せず)を打ち込み、打ち込んだアンカーに、回転冶具32の下部ビーム部34に取り付けられた吊りワイヤー34bの下端部を係止することによって、支持架台30の支持本体部30aから、昇降装置31及び回転冶具32を介してコンクリート版21を支持した状態とする。この状態で、切断装置として、例えばコンクリート切断用の装置として公知のコンクリートカッター装置35を用いて、先端部のコンクリート版21の両端部分21cにおける両端部21bよりも内側の部分に、連設方向Xに延設させて、コンクリート版21を横断する切断線40を、厚さ方向に貫通させて形成する。これによって、両側の切断線40により挟まれる部分の本体部分21aを、両端部分21cから切り離すことができる。 That is, in the concrete slab cutting step, an anchor (not shown) is driven at a predetermined position of the main body portion 21a between both ends 21b of the concrete slab 21 at the tip in the continuous direction X, and the anchor anchor is driven, By supporting the lower end portion of the hanging wire 34b attached to the lower beam portion 34 of the rotating jig 32, the concrete slab 21 is supported from the supporting main body portion 30a of the support frame 30 via the lifting device 31 and the rotating jig 32. It will be in the state where it did. In this state, as a cutting device, for example, a concrete cutter device 35 known as a device for cutting concrete is used, and the end portion 21c of the concrete slab 21 at the tip portion is located inside the both end portions 21b in the continuous direction X. And a cutting line 40 that extends across the concrete slab 21 and penetrates in the thickness direction. Thereby, the main body portion 21a sandwiched by the cutting lines 40 on both sides can be separated from both end portions 21c.

ここで、コンクリート版切断工程では、コンクリート版21の両端部分21cの切断線40による切断面40aを、下方に向けて外側に傾斜させるように各々形成することが好ましい(図4(a)参照)。これによって、後述する本体部分吊降し工程において、残置される両端部分21cから切断線40により切り離された、切断線40による切断面40aで挟まれるこれらの間の本体部分21aを、残置される両端部分21cからスムーズに離間させて、下方に容易に吊り降してゆくことが可能になる。下方に向けて外側に傾斜する切断面40aは、コンクリート版21の両端部分21cを切断する際に、例えばコンクリート版21の上に傾斜した咬ませ部材41を取り付けることで、コンクリートカッター装置35を傾斜させて設置して、カッターブレード35aを外側に向けて傾けた状態で、コンクリートカッター装置35を移動させることによって、容易に形成することができる。 Here, in the concrete slab cutting step, it is preferable to form the cut surfaces 40a of the both end portions 21c of the concrete slab 21 by the cutting lines 40 so as to be inclined downward toward the outside (see FIG. 4A). .. As a result, in the main body portion suspending step described later, the main body portion 21a between the two end portions 21c to be left, which are separated by the cutting line 40 and sandwiched between the cutting surfaces 40a by the cutting line 40, is left. It becomes possible to smoothly separate it from both end portions 21c and easily hang it downward. The cutting surface 40a which inclines outward toward the lower side, when cutting the both end portions 21c of the concrete slab 21, for example, attaches the inclined bite member 41 on the concrete slab 21 to incline the concrete cutter device 35. It can be easily formed by moving the concrete cutter device 35 with the cutter blade 35a tilted outward.

本実施形態のコンクリート版の吊降し撤去方法における本体部吊降し工程では、図5(a)〜(c)に示すように、両端部分21cから切り離したコンクリート版21の本体部分21aを、両端部分21cを残置させた状態で、昇降装置31により下方に吊り降ろす。 In the main body suspension step in the method of suspending and removing the concrete slab of the present embodiment, as shown in FIGS. 5A to 5C, the main body portion 21a of the concrete slab 21 separated from both end portions 21c is With both end portions 21c left, it is hung down by the lifting device 31.

すなわち、本体部吊降し工程では、上述のコンクリート版切断工程によって、支持架台30の支持本体部30aから吊り下げて支持した状態で、両端部分21cから切り離されたコンクリート版21の本体部分21aを、支持架台30に取り付けられたホイストクレーン等による昇降装置31を作動させることによって、回転冶具32と共に下方に吊り降ろす。 That is, in the main body suspension step, the main body portion 21a of the concrete slab 21 separated from both end portions 21c is suspended from the support main body portion 30a of the support frame 30 and supported by the concrete slab cutting step described above. The hoisting crane 31 or the like attached to the support frame 30 is operated to lower and lower the rotary jig 32 together with the rotary jig 32.

ここで、本体部吊降し工程では、コンクリート版21の両端部分21cを残置させて、本体部分21aのみを下方に吊り降ろしてゆくので、道路トンネル50が馬蹄形の断面形状を備えていて、コンクリート版21が取り付けられていた上部のトンネル幅よりも、これよりも下方部分のトンネル幅の方が狭くなっていても、吊り降ろされる本体部分21aの両端部が、道路トンネル50の側壁部に引っ掛かることになるのを回避して、本体部分21aをスムーズに吊り降ろしてゆくことが可能になる。 Here, in the main body suspension step, since both end portions 21c of the concrete slab 21 are left and only the main body portion 21a is suspended downward, the road tunnel 50 has a horseshoe-shaped cross-sectional shape. Even if the tunnel width of the lower portion is narrower than the tunnel width of the upper portion where the plate 21 is attached, both ends of the main body portion 21a to be hung are caught on the side wall portion of the road tunnel 50. By avoiding this, the main body portion 21a can be smoothly hung down.

また、本体部吊降し工程では、切り離した本体部分21aは、道路トンネル50における残置された両端部分21cよりも下方の空間領域において、回転冶具32の下部ビーム部34を、上部ビーム部33に対して回転させることにより(図5(a)参照)、好ましくはこれの長手方向Lが連設方向Xに沿うようにスムーズに回転移動された後に、さらに下方に吊り降ろされるようになっている。これによって、道路トンネル50の内部において、縦長の荷台部57aを道路トンネル50の軸方向であるコンクリート版21の連設方向Xに延設させて、支持架台30の直下部分に移動させたトレーラ等の搬出車両57の荷台部57aに、吊り降ろされて撤去されるコンクリート版21の本体部分21aを、スムーズに積み込ませて、搬出させることが可能になる。 Further, in the main body suspension process, the separated main body portion 21a moves the lower beam portion 34 of the rotary jig 32 to the upper beam portion 33 in the space region below the left and right end portions 21c of the road tunnel 50. By rotating it (see FIG. 5(a)), preferably, the longitudinal direction L thereof is smoothly rotationally moved along the continuous installation direction X and then further hung down. .. As a result, inside the road tunnel 50, the vertically long cargo bed portion 57a is extended in the continuous direction X of the concrete slab 21 which is the axial direction of the road tunnel 50, and moved to the portion directly below the support frame 30. It becomes possible to smoothly load and carry out the main body portion 21a of the concrete slab 21 to be hung and removed from the loading platform portion 57a of the unloading vehicle 57.

吊り降ろしたコンクリート版21の本体部分21aを、搬出車両57の荷台部57aに積み込んだら、下部ビーム部34を上部ビーム部33に対して回転させて、上部ビーム部33と平行な元の位置に戻すと共に、昇降装置31により回転冶具32を上昇させて、元の位置に戻した状態で、支持架台30を連設方向Xの後方側に移動させる。これによって、次の連設方向Xの先端部のコンクリート版21の本体部分21aを撤去する作業を、引き続き行なうことが可能になる。 After the main body portion 21a of the concrete slab 21 that has been hung down is loaded on the loading platform 57a of the unloading vehicle 57, the lower beam portion 34 is rotated with respect to the upper beam portion 33 to return to the original position parallel to the upper beam portion 33. At the same time as returning, the rotating jig 32 is raised by the elevating device 31 and is moved to the rear side in the continuous installation direction X in the state where it is returned to the original position. This makes it possible to continue the work of removing the main body portion 21a of the concrete slab 21 at the leading end in the continuous installation direction X.

本実施形態では、上述のコンクリート版切断工程と、本体部分吊降し工程とを、支持架台30やコンクリートカッター装置35を連設方向Xの後方側に移動させながら、所定回数繰り返して、連設方向Xの先端側から所定数のコンクリート版21として、例えば5箇所のコンクリート版21の本体部分21aを吊り降ろして撤去したら、図6(a)〜(c)に示すように、支持架台30を連設方向Xの後端側にさらに移動させた後に、両端部分撤去工程によって、残置したコンクリート版21の両端部分21cを先端側から順次撤去する作業を行なう。両端部分撤去工程は、先端部のコンクリート版21の本体部分21aを撤去して、支持架台30を連設方向Xの後端側に移動させた直後に、その都度行っても良く、6箇所以上のコンクリート版21の本体部分21aを撤去してから、残置した複数個所のコンクリート版21の両端部分21cを、まとめて撤去することもできる。 In the present embodiment, the concrete slab cutting process and the main body part suspending process described above are repeated a predetermined number of times while moving the support platform 30 and the concrete cutter device 35 to the rear side in the continuous installation direction X. As a predetermined number of concrete slabs 21 from the tip side in the direction X, for example, when the main body portions 21a of the concrete slabs 21 are hung down and removed, as shown in FIGS. After further moving to the rear end side in the continuous installation direction X, a work of sequentially removing both end portions 21c of the remaining concrete slab 21 from the front end side is performed in the both end portion removing step. The step of removing both end portions may be performed each time immediately after the main body portion 21a of the concrete slab 21 at the tip portion is removed and the support base 30 is moved to the rear end side in the continuous installation direction X, at six or more locations. After removing the main body portion 21a of the concrete slab 21, the two end portions 21c of the remaining concrete slabs 21 can be collectively removed.

本実施形態のコンクリート版の吊降し撤去方法における両端部分撤去工程では、例えば高所作業車58の作業床部58aに乗り込んだ作業員による作業によって、残置したコンクリート版21の両端部分21cから、ずれ止めガイド部材36や固定アンカー23等を取り外すと共に、例えばクラッシャ重機59の先端アタッチメント部59aによって挟み込んで持ち上げることにより、残置したコンクリート版21の両端部分21cを、容易に撤去することできる。 In the step of removing both end portions in the method of suspending and removing the concrete slab of the present embodiment, for example, by the work by the worker who got on the work floor portion 58a of the aerial work vehicle 58, from both end portions 21c of the remaining concrete slab 21, Both end portions 21c of the remaining concrete slab 21 can be easily removed by removing the slip prevention guide member 36, the fixed anchor 23, and the like, and sandwiching and lifting them by, for example, the tip attachment portion 59a of the crusher heavy machine 59.

両端部分撤去工程で残置したコンクリート版21の両端部分21cを撤去して、予定していた全てのコンクリート版21を撤去したら、連設方向Xの後方側に移動させた支持架台30やコンクリートカッター装置35等を、高所作業車58の作業床部58aに乗り込んだ作業員による作業や、小型クレーン56を用いた作業によって、解体、撤去して、例えば老朽化や換気システムの変更等に伴って撤去する必要を生じたトンネル天井版20を撤去する工事が終了する。 After removing both end portions 21c of the concrete slab 21 left in the both end portion removing step and removing all the planned concrete slabs 21, the support frame 30 and the concrete cutter device moved to the rear side in the continuous installation direction X 35, etc. are dismantled and removed by work by a worker who has boarded the work floor 58a of the aerial work vehicle 58, or work by using the small crane 56. For example, due to deterioration and change of ventilation system. The construction for removing the tunnel ceiling slab 20 that needs to be removed is completed.

そして、上述の構成を備える本実施形態のコンクリート版の吊降し撤去方法によれば、連設して配置されてトンネル天井版20を形成する多数のコンクリート版21を、安定した状態で、順次効率良く撤去してゆくことが可能になる。 Then, according to the method of suspending and removing concrete slabs of the present embodiment having the above-described configuration, a large number of concrete slabs 21 that are arranged in a row and form the tunnel ceiling slab 20 are sequentially placed in a stable state. It will be possible to remove them efficiently.

すなわち、本実施形態のコンクリート版の吊降し撤去方法は、昇降装置31を取り付けた支持架台30を、両端部30cをコンクリート版21の両端部21bに各々載置して、連設方向Xに移動可能に設置する架台設置工程と、連設方向Xの先端部のコンクリート版21を、支持架台30から支持させた状態で、コンクリート版21の両端部21bよりも内側に切断線40を各々形成して、コンクリート版21の本体部分21aを両端部分21cから切り離すコンクリート版切断工程と、切り離したコンクリート版21の本体部分21aを、昇降装置31により吊り降ろす本体部分吊降し工程と、本体部分21aを吊り降した後に、残置したコンクリート版の両端部分21cを撤去する両端部分撤去工程とを含んで構成されている。 That is, in the method of suspending and removing a concrete slab of the present embodiment, the support pedestals 30 to which the elevating device 31 is attached are placed with their both ends 30c on both ends 21b of the concrete slab 21, respectively, and in the continuous direction X. In a state where the pedestal installation step of movably installing and the concrete slab 21 at the tip portion in the continuous installation direction X are supported from the support pedestal 30, the cutting lines 40 are formed inside the both ends 21b of the concrete slab 21. Then, a concrete plate cutting step of separating the main body portion 21a of the concrete plate 21 from both end portions 21c, a main body portion hanging step of hanging the separated main body portion 21a of the concrete plate 21 by the elevating device 31, and a main body portion 21a. And the both end portions removing step of removing the both end portions 21c of the remaining concrete slab after being suspended.

したがって、本実施形態によれば、撤去するコンクリート版21の本体部分21aを、既存の支持部材によって両端部が支持された支持架台30により上方から吊り下げて、安定した状態で吊り降ろすことが可能になると共に、支持架台30に取り付けた昇降装置から、撤去するコンクリート版21の本体部分21aを吊り下げることで、トンネル天井版20よりも上方のスペースの大きさが限られていても、構造物を損傷することなく、十分な吊り代及び支持力を確保しながら撤去することが可能になり、これによって連設して配置されてトンネル天井版20を形成する多数のコンクリート版21を、安定した状態で、順次効率良く撤去してゆくことが可能になる。 Therefore, according to this embodiment, the main body portion 21a of the concrete slab 21 to be removed can be hung in a stable state by being hung from above by the support frame 30 whose both ends are supported by the existing support members. In addition, by suspending the main body portion 21a of the concrete slab 21 to be removed from the lifting device attached to the support base 30, even if the size of the space above the tunnel ceiling slab 20 is limited, It is possible to remove them while securing a sufficient hanging allowance and a supporting force without damaging the slab and thereby stabilizing a large number of concrete slabs 21 that are arranged in series and form the tunnel ceiling slab 20. It becomes possible to remove them efficiently in this state.

なお、本発明は上記実施形態に限定されることなく種々の変更が可能である。例えば、本発明の吊降し撤去方法によって撤去される、両端部が下方から支持されて、連設方向に多数連設して配置されるコンクリート版は、道路トンネルのトンネル天井版を形成するものである必要は必ずしも無く、その他のトンネル天井版や、トンネル以外の建造物を構成する天井版を形成するものであっても良い。両端部が下方から支持されて、連設方向に多数連設して配置されるコンクリート版は、天井版の他、床版を形成するものであっても良く、例えば高架橋等に設けられて床版を形成する、両端部が下方から支持されて、連設方向に多数連設して配置されるコンクリート版であっても良い。 It should be noted that the present invention is not limited to the above embodiment, and various modifications can be made. For example, a concrete slab that is removed by the suspending and removing method of the present invention and has both ends supported from below and arranged in a row in the connecting direction forms a tunnel ceiling slab of a road tunnel. It is not always necessary to form the above, and other tunnel ceiling slabs or ceiling slabs constituting a building other than the tunnel may be formed. The concrete slabs, both ends of which are supported from below and arranged in a row in the arranging direction, may form not only ceiling slabs but also floor slabs. It may be a concrete slab that forms a slab and is supported by both ends thereof from below and arranged in a row in the arranging direction.

また、両端部をコンクリート版の両端部に各々載置して、連設方向に移動可能に設置される支持架台の支持本体部は、アーチ形状を備えている必要は必ずしもなく、門形形状等を備えていても良い。 Also, the support main body of the support frame, which is installed so that both ends are respectively placed on both ends of the concrete slab and is movable in the continuous direction, does not necessarily have to have an arch shape, and a gate shape or the like. May be provided.

さらに、コンクリート版切断工程において、コンクリート版の両端部分の切断線による切断面を、下方に向けて外側に傾斜するように各々形成する必要は必ずしも無く、本体部分吊降し工程において、切り離した本体部分は、残置された両端部分よりも下方の空間領域において、これの長手方向が連設方向に沿うように回転移動する必要は必ずしも無い。 Further, in the concrete slab cutting process, it is not always necessary to form the cut surfaces by the cutting lines at both end portions of the concrete slab so as to incline outward toward the lower side, and the main body separated in the suspension process of the main body part is cut off. The part does not necessarily have to rotate and move so that the longitudinal direction of the part is in the space region below the left end parts that are left behind.

10 トンネル天井部コンクリート版の吊降し撤去機構
20 トンネル天井版
21 コンクリート版
21a 本体部分
21b 両端部
21c 両端部分
22 支持部材(ブラケット部材)
22a 接合基部
22b 受台部
22c 載置面
23 固定アンカー
30 支持架台
30a 支持本体部
30b 連結支持ビーム部
30c 両端部
31 昇降装置
32 回転冶具
33 上部ビーム部
34 下部ビーム部
34a 回転連結部
34b 吊りワイヤー
35 切断装置(コンクリートカッター装置)
35a カッターブレード
37 車輪部材
40 切断線
40a 切断面
41 咬ませ部材
50 道路トンネル
55 運搬車両
56 小型クレーン
57 搬出車両
57a 荷台部
58 高所作業車
58a 作業床部
59 クラッシャ重機
59a 先端アタッチメント部
X 連設方向
L コンクリート版の本体部分の長手方向
10 Tunnel Ceiling Concrete Plate Suspension and Removal Mechanism 20 Tunnel Ceiling Slab 21 Concrete Slab 21a Body Part 21b Both Ends 21c Both Ends 22 Support Member (Bracket Member)
22a Joining base 22b Cradle 22c Mounting surface 23 Fixed anchor 30 Supporting cradle 30a Support body 30b Connection support beam 30c Both ends 31 Lifting device 32 Rotating jig 33 Upper beam 34 Lower beam 34a Rotation connection 34b Suspended wire 35 Cutting device (concrete cutter device)
35a Cutter blade 37 Wheel member 40 Cutting line 40a Cutting surface 41 Bite member 50 Road tunnel 55 Transport vehicle 56 Small crane 57 Carry-out vehicle 57a Loading platform 58 High-level work vehicle 58a Working floor 59 Crusher heavy machine 59a Tip attachment part X Direction L Longitudinal direction of the body of the concrete slab

Claims (6)

両端部が下方から支持されて、連設方向に多数連設して配置されたコンクリート版を、連設方向の先端側のコンクリート版から順次吊り降ろして撤去してゆくコンクリート版の吊降し撤去方法であって、
昇降装置を取り付けた支持架台を、両端部をコンクリート版の両端部に各々載置して、前記連設方向に移動可能に設置する架台設置工程と、
前記連設方向の先端部のコンクリート版を、前記支持架台から前記昇降装置を介して支持させた状態で、前記コンクリート版の両端部分において、前記支持架台が載置された両端部よりも内側に、切断装置により切断線を各々形成して、前記コンクリート版の本体部分を両端部分から切り離すコンクリート版切断工程と、
切り離した前記コンクリート版の本体部分を、前記昇降装置により吊り降ろす本体部分吊降し工程と、
前記本体部分を吊り降した後に、前記支持架台を前記連設方向の後端側に移動させて、残置した前記コンクリート版の両端部分を撤去する両端部分撤去工程とを含んで構成されるコンクリート版の吊降し撤去方法。
Concrete slabs with both ends supported from below and arranged in a row in the connecting direction are sequentially hung from the concrete slab on the tip side in the connecting direction and removed. Method,
A support platform with a lifting device attached, with both ends respectively placed on both ends of the concrete slab, and a platform installation step of movably installing in the continuous installation direction,
The concrete slab at the tip end in the continuous direction, in a state of being supported from the support cradle via the elevating device, at both end portions of the concrete slab, inside the both ends where the support cradle is placed. A concrete slab cutting step of forming a cutting line by a cutting device to separate the main body portion of the concrete slab from both end portions,
The main body portion of the separated concrete slab, a main body portion suspending step of suspending by the lifting device,
After suspending the main body portion, the support cradle is moved to the rear end side in the continuous installation direction, and both end portions removing step of removing both end portions of the remaining concrete slab is included. How to suspend and remove.
前記コンクリート版切断工程において、前記コンクリート版の両端部分の前記切断線による切断面は、下方に向けて外側に傾斜するように各々形成される請求項1記載のコンクリート版の吊降し撤去方法。 The method of suspending and removing a concrete slab according to claim 1, wherein, in the concrete slab cutting step, cutting surfaces of both end portions of the concrete slab that are cut by the cutting line are each formed to incline outward toward a lower side. 前記本体部分吊降し工程において、切り離した前記本体部分は、残置された前記両端部分よりも下方の空間領域において、これの長手方向が前記連設方向に沿うように回転移動された後に、さらに下方に吊り降ろされる請求項1又は2記載のコンクリート版の吊降し撤去方法。 In the main body portion suspending step, the separated main body portion is further rotatably moved so that the longitudinal direction thereof is along the continuous installation direction in a space region below the left end portions which are left behind. The method for suspending and removing a concrete slab according to claim 1 or 2, which is suspended downward. 前記コンクリート版は、トンネルの内部の空間を上下に仕切るトンネル天井版を形成するものである請求項1〜3のいずれか1項記載のコンクリート版の吊降し撤去方法。 The method for suspending and removing a concrete slab according to any one of claims 1 to 3, wherein the concrete slab forms a tunnel ceiling slab that divides a space inside a tunnel into upper and lower parts. 前記トンネルは、円形又は馬蹄形の断面形状を備えている請求項4記載のコンクリート版の吊降し撤去方法。 The method for suspending and removing a concrete slab according to claim 4, wherein the tunnel has a circular or horseshoe-shaped cross-sectional shape. 前記支持架台は、アーチ形状の支持本体部を備えている請求項1〜5のいずれか1項記載のコンクリート版の吊降し撤去方法。 The method for suspending and removing a concrete slab according to any one of claims 1 to 5, wherein the support base includes an arch-shaped support main body.
JP2017017575A 2017-02-02 2017-02-02 How to suspend and remove concrete slabs Active JP6718391B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017017575A JP6718391B2 (en) 2017-02-02 2017-02-02 How to suspend and remove concrete slabs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017017575A JP6718391B2 (en) 2017-02-02 2017-02-02 How to suspend and remove concrete slabs

Publications (2)

Publication Number Publication Date
JP2018123606A JP2018123606A (en) 2018-08-09
JP6718391B2 true JP6718391B2 (en) 2020-07-08

Family

ID=63109412

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017017575A Active JP6718391B2 (en) 2017-02-02 2017-02-02 How to suspend and remove concrete slabs

Country Status (1)

Country Link
JP (1) JP6718391B2 (en)

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL9301988A (en) * 1993-11-17 1995-06-16 Int Dome Systems Cyprus Ltd Method for manufacturing a tunnel-shaped hood or screen over a traffic route, such as a motorway or railway.
JP2576950B2 (en) * 1994-09-13 1997-01-29 吉田工業株式会社 Removal method of ceiling plate in tunnel and stage car used for it
JP2001073692A (en) * 1999-09-08 2001-03-21 Taisei Corp Ceiling panel replacing method and device thereof
JP4541953B2 (en) * 2005-03-31 2010-09-08 岐阜工業株式会社 Tunnel ceiling panel demounting vehicle
JP6066063B2 (en) * 2013-02-04 2017-01-25 株式会社大林組 Removal method of tunnel partition
JP6283979B2 (en) * 2013-06-25 2018-02-28 株式会社大林組 Method and system for removing ceiling in tunnel

Also Published As

Publication number Publication date
JP2018123606A (en) 2018-08-09

Similar Documents

Publication Publication Date Title
JP7346246B2 (en) Heavy object moving method using heavy object moving device and heavy object moving device
JP6503716B2 (en) Demolition system and demolition method
JP2014227651A (en) Building demolition system
JP2010242308A (en) Method for demolishing high-rise building of concrete slab structure, and concrete slab demolition equipment
JP5484983B2 (en) Method for assembling and dismantling bridge moving work device
JP6893188B2 (en) Demolition system and demolition method of existing structures
JP6718393B2 (en) Mechanism for suspending and removing concrete slabs from the ceiling of tunnels
JP2008248664A (en) Hoisting method of curtain wall
JP6718391B2 (en) How to suspend and remove concrete slabs
JP2017214738A (en) Demolition system and demolition method for high-rise building
JP2014129697A (en) Lifting device, lifting method, and demolition method for building
JP6718392B2 (en) How to suspend and remove concrete slabs
JP6920118B2 (en) Demolition system for existing structures
JP5356091B2 (en) Crane girder exchanging method and crane girder exchanging apparatus
KR101048036B1 (en) Electric hoist
JP7244119B2 (en) Floor slab installation method
JP5609067B2 (en) Load support frame and load support method
JP5948828B2 (en) Lifting device used for assembling cargo lift for building demolition work, cargo lift for building demolition work, and assembling method thereof
JP6449637B2 (en) Building construction method
JP6391134B2 (en) Dismantling method and dismantling system
JP2014025282A (en) Erection method of beam member
JP7034630B2 (en) Dismantling method
JP7097203B2 (en) Climbing telpher and how to demolish a building
JP6967383B2 (en) How to dismantle an existing structure
JP6368726B2 (en) Belt conveyor lifting device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190731

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20200422

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200526

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200612

R150 Certificate of patent or registration of utility model

Ref document number: 6718391

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250