JP4136049B2 - Concrete pier construction method - Google Patents

Concrete pier construction method Download PDF

Info

Publication number
JP4136049B2
JP4136049B2 JP04041498A JP4041498A JP4136049B2 JP 4136049 B2 JP4136049 B2 JP 4136049B2 JP 04041498 A JP04041498 A JP 04041498A JP 4041498 A JP4041498 A JP 4041498A JP 4136049 B2 JP4136049 B2 JP 4136049B2
Authority
JP
Japan
Prior art keywords
precast
frame member
reinforcing bar
frame
concrete pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP04041498A
Other languages
Japanese (ja)
Other versions
JPH11241311A (en
Inventor
佳男 篠田
一徳 河野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP04041498A priority Critical patent/JP4136049B2/en
Publication of JPH11241311A publication Critical patent/JPH11241311A/en
Application granted granted Critical
Publication of JP4136049B2 publication Critical patent/JP4136049B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、コンクリート橋脚の施工方法に関する。
【0002】
【従来の技術】
高速道路等の高架橋には、通常、コンクリート橋脚が使用されており、従来は次のような施工方法により構築されていた。即ち、従来は基礎から主鉄筋を多数立設し、この主鉄筋の周囲を取り囲むよう帯鉄筋を固定する。この帯鉄筋を固定するときには、バインド線等を用いて手作業により主鉄筋に固定する。
【0003】
このような、鉄筋の建て込みを完成した後、鉄筋の周囲に支保工を組みコンクリート型枠を設営する。そしてこの型枠の完成後、型枠内部にコンクリートを打設し、養生の後型枠と支保工を解体撤去する。このような工程からなる一連の作業を必要回数繰り返して施工する。
【0004】
【発明が解決しようとする課題】
しかし、上述した従来のコンクリート橋脚の施工方法では次のような問題があった。第一に、鉄筋部分の組み立ては熟練を要する上に多くの手間と労力が必要なので、工期が長期化する。第二に、コンクリート型枠の脱型及び支保工の解体が必要であり、このため多大な労力と型枠等の仮設置場所を要する。第三に、高所作業となるため作業性が低下する。特に、山間地では高い橋脚が必要とされる場合が多く、作業環境の改善が強く望まれる。
【0005】
本発明の目的は、このような問題点を解決することにあり、鉄筋の組立が容易であり、また、脱型を省略して工期を短縮することができ、更に、作業性を向上させることが可能なコンクリート橋脚の施工方法を提供することにある。
【0006】
【課題を解決するための手段】
本発明は、コンクリート橋脚の施工方法であり、前述の技術的課題を解決するために以下のように構成されている。すなわち、本発明のコンクリート橋脚の施工方法は、枠状で所定高さのプレキャスト型枠部材を形成する工程と、
前記プレキャスト型枠部材に鉄筋用フレームを介して鉄筋を取り付ける工程と、
橋脚を構築する所定位置に鉄骨を建て込む工程と、
前記鉄骨の周囲に所定数の前記プレキャスト型枠部材を積み上げる工程と、
前記積み上げられたプレキャス型枠部材の中にコンクリートを打設する工程とを含み、
前記鉄筋用フレームは、前記プレキャスト内枠部材に所定間隔をおいて複数取り付けられ、前記プレキャスト外枠部材及びプレキャスト内枠部材に対して垂直に配され、前記プレキャスト外枠部材及びプレキャスト内枠部材の高さ方向に延び、かつこれらの高さに対応した一対の長辺と、この長辺の両端を連結する一対の短辺とにより形成された枠状部材であり、
前記鉄筋用フレームには、建て込まれた鉄骨とプレキャスト外枠部材との間及び前記鉄骨とプレキャスト内枠部材との間に配筋可能なように、複数の鉄筋を前記一対の長辺上に、当該長辺と交わるように所定間隔で固定することを特徴とする。
【0007】
このコンクリート橋脚の施工方法は、プレキャスト型枠部材を使用するので型枠の解体作業が不要になると共に、プレキャスト型枠部材に予め鉄筋用フレームを介して鉄筋を取り付けてから積み上げるので、プレキャスト型枠部材に鉄筋を容易に取り付けることができると共に、現地における鉄筋の組立作業が不要になる。
【0008】
前記鉄筋は帯鉄筋であり、この帯鉄筋は、前記一対の長辺の両内側又は前記プレキャスト内枠部材側に配されている長辺の内側と前記プレキャスト外枠部材側の長辺の外側とに固定することができる。
また、前記一対の長辺の両内側又は前記プレキャスト内枠部材側に配されている長辺の内側と前記プレキャスト外枠部材側の長辺の外側とに固定されている帯鉄筋を連結している中間帯鉄筋をさらに有するようにしてもよい。
【0009】
前記鉄筋は帯鉄筋であり、この帯鉄筋は、前記一対の長辺の両内側又は前記プレキャスト内枠部材側に配されている長辺の内側と前記プレキャスト外枠部材側の長辺の外側とに固定することができる。また、前記一対の長辺の両内側又は前記プレキャスト内枠部材側に配されている長辺の内側と前記プレキャスト外枠部材側の長辺の外側とに固定されている帯鉄筋を連結している中間帯鉄筋をさらに有するようにしてもよい。
【0010】
【発明の実施の形態】
以下、本発明に係るコンクリート橋脚の施工方法の実施の形態を、図面を参照して詳細に説明する。
【0011】
図1は、本発明に係るコンクリート橋脚の施工方法を示すフローチャートである。このコンクリート橋脚の施工方法においては、まず、例えば組み立てヤードや製造工場などで枠状のプレキャスト型枠部材10(図2参照)を必要な数だけ形成する(ステップ1)。次に、これらのプレキャスト型枠部材10に鉄筋用フレーム14を介して帯鉄筋11を取り付ける(ステップ2)。
【0012】
次に、コンクリート橋脚1の施工現場において、H型鋼などの鉄骨12を建て込み(ステップ3)、この鉄骨12の周囲にプレキャスト型枠部材10を設置する(ステップ4)。この後、支保工(図示せず)を組み立てる(ステップ5)。以下、上述のステップ4のプレキャスト型枠部材10の設置、及びステップ5の志保工の組立を所定回数mだけ繰り返して行うことにより、プレキャスト型枠部材10を順次積み上げて所定の高さにする。次に、積み上げられたプレキャスト型枠部材10内にコンクリート13を打設する(ステップ6)。
【0013】
このようにして、コンクリート橋脚1(図2参照)の一部分を所定の高さまで施工した後、上述のステップ3の鉄骨12の建て込み〜ステップ6のコンクリート打設を所定回数nだけ繰り返して行うことにより、コンクリート橋脚1が完成する。なお、比較的低いコンクリート橋脚1の場合は、鉄骨12を一段とし、この鉄骨12の周囲に所定数のプレキャスト型枠部材10を積み上げてから、コンクリート13を打設することによりコンクリート橋脚1を完成することもできる。これは、上述のm、nを1とした場合である。
【0014】
図2は、上述のコンクリート橋脚の施工方法を適用して製造したコンクリート橋脚1の横断面を示す。このコンクリート橋脚1のプレキャスト型枠部材10は、枠状、本実施の形態では4角形のプレキャスト外枠部材10aと、このプレキャスト外枠部材10aの内側に配置されるプレキャスト内枠部材10bによって構成され、これらのプレキャスト外枠部材10aとプレキャスト内枠部材10bとの間に所定数の鉄骨12が配置されている。
【0015】
プレキャスト外枠部材10a及びプレキャスト内枠部材10bは、コンクリート橋脚1の外壁となるものであり、コンクリート又はモルタルによって4角形に形成されている。このプレキャスト外枠部材10a及びプレキャスト内枠部材10bは、上述のように組み立てヤードや製造工場等において予め複数に分割して製造し、これらの分割片を接続して一体の枠状体として形成することができる。
【0016】
そして、その断面形状は本実施の形態では4角形としたが、円形、楕円形、多角形など任意の形状にすることができる。また、本実施の形態では、プレキャスト内枠部材10bの外周側に鉄筋用フレーム14が適宜な間隔で複数設けられ、これらの鉄筋用フレーム14に帯鉄筋11が取り付けられている。鉄筋用フレーム14及び帯鉄筋11の取り付け方法については後述する。
【0017】
図3〜図12は、上述のコンクリート橋脚1の施工手順を示す。なお、プレキャスト型枠部材10は予め製造されているものとする。ここでは、まず図3に示すように、コンクリート橋脚1の基礎段21にH型鋼などの鉄骨12の定着部分を建て込む。次に、図4に示すように基礎部22のコンクリートを打設する。続いて、図5に示すように基礎部22上に所定数、本実施の形態では2個のプレキャスト外枠部材10aを積み重ねて設置し、次に図6に示すようにこれらのプレキャスト外枠部材10a内にコンクリート13を打設する。これにより、コンクリート橋脚1の中実部分が完成する。
【0018】
次に、図7に示すように鉄骨12上に、次の鉄骨12を載せて例えばボルトで結合する。続いて、図8に示すように設置済みのプレキャスト外枠部材10a上に、所定数のプレキャスト外枠部材10aを上乗せしてから、図9に示すように、鉄骨12の内側にプレキャスト内枠部材10bを所定数だけ積み重ねて配置する。このプレキャスト内枠部材10bには、後述のように帯鉄筋11が取り付けられている。
【0019】
次に、図10に示すようにプレキャスト外枠部材10aとプレキャスト内枠部材10bとを、例えば棒状の連結部材24で連結する。この連結部材24は、棒状部材以外に等辺山型鋼、溝型鋼等の鋼材を使用できる。このように連結部材24で連結することにより、プレキャスト外枠部材10a及びプレキャスト内枠部材10bが、コンクリート13がもたらす側圧で孕むのを防止できる。次に、図11に示すように、プレキャスト外枠部材10aとプレキャスト内枠部材10bとの間に、コンクリート13を打設する。
【0020】
以下同様にして、鉄骨12の建て込み、プレキャスト外枠部材10a及びプレキャスト内枠部材10bの設置及びコンクリート13の打設を繰り返すことにより、図12に示すように、コンクリート橋脚1を完成することができる。
【0021】
図13〜図17は、プレキャスト内枠部材10bに上述の鉄筋用フレーム14及び鉄筋11を取り付ける手順を示す。ここでは、鉄筋用フレーム14を4角形とし、これを縦に2分割した場合について説明する。まず、図13に示すようにプレキャスト内枠部材10bの外周面に、適宜な方法で鉄筋用フレーム14の片方の内側フレーム14aを固定する。内側フレーム14aはコの字状であり、縦辺部分にメッシュ筋25が設けられている。このメッシュ筋25は、帯鉄筋11のピッチを正確に保つと共に、帯鉄筋11の組立を容易にするために取り付けられている。
【0022】
次に、図14に示すようにメッシュ筋25に複数の帯鉄筋11を取り付ける。続いて、図15に示すように内側フレーム14aに他方の外側フレーム14bを取り付ける。この外側フレーム14bにもメッシュ筋26が設けられている。次に、図16に示すように外側フレーム14bのメッシュ筋26に帯鉄筋11を取り付け、更に図17に示すように内側フレーム14aの帯鉄筋11と、外側フレーム14bの帯鉄筋11とを中間帯鉄筋27で連結する。これにより、鉄筋用フレーム14と、帯鉄筋11及び中間帯鉄筋27との取り付けが完了する。
【0023】
このように、本発明に係るコンクリート橋脚の施工方法は、プレキャスト型枠部材10のプレキャスト内枠部材10bに、予め鉄筋用フレーム14を介して鉄筋11を取り付けてから積み上げるので、鉄筋11の取り付けが容易になる。また、現地における鉄筋11の組立作業及び型枠の解体が不要なので、作業工数の低減及び工期の短縮が可能になる。更に、高所における鉄筋組立作業が省略できるので、作業性及び安全性が向上する。
【0024】
また、プレキャスト内枠部材10bに鉄筋用フレーム14を設け、この鉄筋用フレーム14の内側フレーム14aに帯鉄筋11を取り付けたので、帯鉄筋11の取り付けが容易になる。この鉄筋用フレーム14を設けたことにより、プレキャスト型枠10を吊り上げるときに形状が保持される。
【0025】
なお、上述の実施の形態では、コンクリート橋脚1を中空断面とした場合について説明したが、本発明は中実断面のコンクリート橋脚に適用することもできる。また、ここでは鉄筋用フレーム14及び帯鉄筋11をプレキャスト内枠部材10bに取り付けたが、これをプレキャスト外枠部材10aに取り付けることもできる。更に、プレキャスト型枠部材10の設置工程、鉄骨12の建て込み工程は、適宜入れ替えて行うことができる。
【0026】
【発明の効果】
以上説明したように、本発明に係るコンクリート橋脚の施工方法によれば、プレキャスト型枠部材を使用するので、現地における型枠の解体作業が不要になると共に、プレキャスト型枠部材に予め鉄筋用フレームを介して鉄筋を取り付けてから積み上げるので、鉄筋の取り付けが容易になると共に、現地において鉄筋の組立作業が不要になる。したがって、作業工数の低減及び工期の短縮が可能になる。更に高所における鉄筋組立作業が不要になるので、作業性及び安全性が向上する。
【0027】
また、鉄筋を帯鉄筋及び中間帯鉄筋とした場合は、帯鉄筋及び中間帯鉄筋の組立が容易になる。
【図面の簡単な説明】
【図1】本発明に係るコンクリート橋脚の施工方法を説明するフローチャートである。
【図2】本発明に係るコンクリート橋脚を示す断面図である。
【図3】本発明に係るコンクリート橋脚の施工手順を示す図である。
【図4】本発明に係るコンクリート橋脚の施工手順を示す図である。
【図5】本発明に係るコンクリート橋脚の施工手順を示す図である。
【図6】本発明に係るコンクリート橋脚の施工手順を示す図である。
【図7】本発明に係るコンクリート橋脚の施工手順を示す図である。
【図8】本発明に係るコンクリート橋脚の施工手順を示す図である。
【図9】本発明に係るコンクリート橋脚の施工手順を示す図である。
【図10】本発明に係るコンクリート橋脚の施工手順を示す図である。
【図11】本発明に係るコンクリート橋脚の施工手順を示す図である。
【図12】本発明に係るコンクリート橋脚の施工手順を示す図である。
【図13】本発明に係るプレキャスト型枠部材の鉄筋用フレーム及び鉄筋の取り付け手順を示す図である。
【図14】本発明に係るプレキャスト型枠部材の鉄筋用フレーム及び鉄筋の取り付け手順を示す図である。
【図15】本発明に係るプレキャスト型枠部材の鉄筋用フレーム及び鉄筋の取り付け手順を示す図である。
【図16】本発明に係るプレキャスト型枠部材の鉄筋用フレーム及び鉄筋の取り付け手順を示す図である。
【図17】本発明に係るプレキャスト型枠部材の鉄筋用フレーム及び鉄筋の取り付け手順を示す図である。
【符号の説明】
1 コンクリート橋脚
10 プレキャスト型枠部材
10a プレキャスト外枠部材
10b プレキャスト内枠部材
11 帯鉄筋
12 鉄骨
13 コンクリート
14 鉄筋用フレーム
27 中間帯鉄筋
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a concrete pier construction method.
[0002]
[Prior art]
Concrete bridge piers are usually used for viaducts such as expressways, and conventionally constructed by the following construction method. That is, conventionally, a number of main reinforcing bars are erected from the foundation, and the belt reinforcing bars are fixed so as to surround the main reinforcing bars. When fixing the rebar, it is fixed to the main rebar manually by using a bind wire or the like.
[0003]
After completing the building of the reinforcing bar, a support work is built around the reinforcing bar and a concrete formwork is set up. And after completion of this formwork, concrete is cast inside the formwork, and after curing, the formwork and support work are dismantled and removed. A series of operations consisting of these processes are repeated as many times as necessary.
[0004]
[Problems to be solved by the invention]
However, the conventional concrete pier construction method described above has the following problems. First, the assembly of the reinforcing bars requires skill and a lot of labor and labor, so the construction period is prolonged. Secondly, it is necessary to remove the concrete formwork and dismantle the support work, which requires a lot of labor and a temporary installation place for the formwork. Thirdly, workability is reduced due to work at high places. In particular, high piers are often required in mountainous areas, and improvement of the working environment is strongly desired.
[0005]
An object of the present invention is to solve such problems, and it is easy to assemble a reinforcing bar, and it is possible to shorten the work period by omitting demolding, and to further improve workability. It is to provide a concrete pier construction method that can be used.
[0006]
[Means for Solving the Problems]
The present invention is a concrete pier construction method and is configured as follows in order to solve the above-described technical problems. That is, the concrete pier construction method of the present invention is a frame-shaped step of forming a precast formwork member of a predetermined height ,
Attaching a reinforcing bar to the precast formwork member via a reinforcing bar frame;
Building a steel frame at a predetermined position for building a pier;
Stacking a predetermined number of the precast formwork members around the steel frame;
Placing concrete in the stacked precast formwork members,
A plurality of the reinforcing bar frames are attached to the precast inner frame member at a predetermined interval, and are arranged perpendicular to the precast outer frame member and the precast inner frame member, and the precast outer frame member and the precast inner frame member A frame-like member formed by a pair of long sides extending in the height direction and corresponding to these heights, and a pair of short sides connecting both ends of the long sides,
The reinforcing bar frame has a plurality of reinforcing bars on the pair of long sides so that reinforcement can be arranged between the built steel frame and the precast outer frame member and between the steel frame and the precast inner frame member. , And fixed at a predetermined interval so as to cross the long side.
[0007]
Since this concrete pier construction method uses precast formwork members, the work of disassembling the formwork is unnecessary, and the precast formwork members are stacked after the reinforcing bars are attached to the precast formwork members in advance through the rebar frames. Reinforcing bars can be easily attached to the members, and assembly work of the reinforcing bars in the field becomes unnecessary.
[0008]
The reinforcing bars are band reinforcing bars, and the reinforcing bars are arranged on both inner sides of the pair of long sides or on the inner side of the longer side arranged on the precast inner frame member side and on the outer side of the longer side on the precast outer frame member side. Can be fixed to.
In addition, the rebars fixed to both inner sides of the pair of long sides or the inner side of the long side arranged on the precast inner frame member side and the outer side of the long side on the precast outer frame member side are connected. You may make it further have the intermediate strip rebar which is.
[0009]
The reinforcing bars are band reinforcing bars, and the reinforcing bars are arranged on both inner sides of the pair of long sides or on the inner side of the longer side arranged on the precast inner frame member side and on the outer side of the longer side on the precast outer frame member side. Can be fixed to. In addition, the rebars fixed to both inner sides of the pair of long sides or the inner side of the long side arranged on the precast inner frame member side and the outer side of the long side on the precast outer frame member side are connected. You may make it further have the intermediate strip rebar which is.
[0010]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF EMBODIMENTS Hereinafter, embodiments of a concrete pier construction method according to the present invention will be described in detail with reference to the drawings.
[0011]
FIG. 1 is a flowchart showing a concrete pier construction method according to the present invention. In this concrete pier construction method, first, a necessary number of frame-shaped precast mold members 10 (see FIG. 2) are formed in, for example, an assembly yard or a manufacturing factory (step 1). Next, the band reinforcing bar 11 is attached to the precast formwork member 10 through the reinforcing bar frame 14 (step 2).
[0012]
Next, at the construction site of the concrete pier 1, a steel frame 12 such as H-shaped steel is built (step 3), and the precast formwork member 10 is installed around the steel frame 12 (step 4). Thereafter, a support work (not shown) is assembled (step 5). Hereinafter, the precast mold member 10 is repeatedly piled up to a predetermined height by repeating the installation of the precast mold member 10 in Step 4 and the assembly of Shibo in Step 5 a predetermined number of times m. Next, the concrete 13 is placed in the stacked precast formwork member 10 (step 6).
[0013]
In this way, after a part of the concrete pier 1 (see FIG. 2) is constructed to a predetermined height, the above-described construction of the steel frame 12 in step 3 to concrete placement in step 6 are repeated a predetermined number of times n. Thus, the concrete pier 1 is completed. In the case of a relatively low concrete pier 1, the steel pier 12 is arranged in a single stage, a predetermined number of precast formwork members 10 are stacked around the steel skeleton 12, and then concrete 13 is placed to complete the concrete pier 1. You can also This is a case where m and n described above are 1.
[0014]
FIG. 2 shows a cross section of a concrete pier 1 manufactured by applying the concrete pier construction method described above. The precast form member 10 of the concrete bridge pier 1 is composed of a frame-shaped, quadrangular precast outer frame member 10a in the present embodiment, and a precast inner frame member 10b arranged inside the precast outer frame member 10a. A predetermined number of steel frames 12 are arranged between the precast outer frame member 10a and the precast inner frame member 10b.
[0015]
The precast outer frame member 10a and the precast inner frame member 10b serve as the outer wall of the concrete pier 1 and are formed in a quadrangular shape from concrete or mortar. As described above, the precast outer frame member 10a and the precast inner frame member 10b are manufactured by being divided into a plurality of pieces in advance in an assembly yard, a manufacturing factory, or the like, and these divided pieces are connected to form an integral frame-like body. be able to.
[0016]
The cross-sectional shape is a quadrangular shape in the present embodiment, but can be any shape such as a circle, an ellipse, or a polygon. Further, in the present embodiment, a plurality of reinforcing bar frames 14 are provided at appropriate intervals on the outer peripheral side of the precast inner frame member 10 b, and the belt reinforcing bars 11 are attached to these reinforcing bar frames 14. A method for attaching the reinforcing bar frame 14 and the band reinforcing bar 11 will be described later.
[0017]
3-12 shows the construction procedure of the above-mentioned concrete pier 1. In addition, the precast formwork member 10 shall be manufactured previously. Here, first, as shown in FIG. 3, a fixing portion of a steel frame 12 such as H-shaped steel is built in the foundation stage 21 of the concrete pier 1. Next, as shown in FIG. 4, the concrete of the foundation part 22 is laid. Subsequently, as shown in FIG. 5, a predetermined number, in this embodiment, two precast outer frame members 10a are stacked and installed on the base portion 22, and then these precast outer frame members as shown in FIG. Concrete 13 is placed in 10a. Thereby, the solid part of the concrete pier 1 is completed.
[0018]
Next, as shown in FIG. 7, the next steel frame 12 is mounted on the steel frame 12, and it couple | bonds, for example with a volt | bolt. Then, after a predetermined number of precast outer frame members 10a are placed on the precast outer frame member 10a that has been installed as shown in FIG. 8, the precast inner frame member is placed inside the steel frame 12 as shown in FIG. A predetermined number of 10b are stacked and arranged. A band reinforcing bar 11 is attached to the precast inner frame member 10b as described later.
[0019]
Next, as shown in FIG. 10, the precast outer frame member 10 a and the precast inner frame member 10 b are coupled by, for example, a rod-shaped coupling member 24. The connecting member 24 can be made of steel such as equilateral mountain steel and groove steel in addition to the rod-shaped member. By connecting with the connecting member 24 in this way, it is possible to prevent the precast outer frame member 10a and the precast inner frame member 10b from being pinched by the side pressure provided by the concrete 13. Next, as shown in FIG. 11, concrete 13 is placed between the precast outer frame member 10a and the precast inner frame member 10b.
[0020]
In the same manner, the concrete pier 1 can be completed as shown in FIG. 12 by repeating the construction of the steel frame 12, the installation of the precast outer frame member 10a and the precast inner frame member 10b, and the placement of the concrete 13. it can.
[0021]
13 to 17 show a procedure for attaching the above-described reinforcing bar frame 14 and the reinforcing bar 11 to the precast inner frame member 10b. Here, a case will be described in which the reinforcing bar frame 14 has a quadrangular shape and is vertically divided into two. First, as shown in FIG. 13, one inner frame 14a of the reinforcing bar frame 14 is fixed to the outer peripheral surface of the precast inner frame member 10b by an appropriate method. The inner frame 14a is U-shaped, and mesh streaks 25 are provided in the vertical side portion. The mesh bars 25 are attached to keep the pitch of the band reinforcing bars 11 accurate and facilitate the assembly of the band reinforcing bars 11.
[0022]
Next, as shown in FIG. 14, the plurality of rebar bars 11 are attached to the mesh bars 25. Subsequently, as shown in FIG. 15, the other outer frame 14b is attached to the inner frame 14a. Mesh stripes 26 are also provided on the outer frame 14b. Next, as shown in FIG. 16, the rebar 11 is attached to the mesh reinforce 26 of the outer frame 14b, and as shown in FIG. 17, the rebar 11 of the inner frame 14a and the rebar 11 of the outer frame 14b are connected to the intermediate band. It connects with the reinforcing bar 27. Thereby, attachment of the frame 14 for reinforcing bars, the band reinforcing bar 11 and the intermediate band reinforcing bar 27 is completed.
[0023]
Thus, since the construction method of the concrete pier concerning this invention attaches the reinforcing bar 11 after attaching the reinforcing bar 11 to the precast inner frame member 10b of the precast formwork member 10 via the reinforcing bar frame 14 in advance, the reinforcing bar 11 can be attached. It becomes easy. In addition, since it is not necessary to assemble the rebar 11 and dismantle the formwork at the site, it is possible to reduce the work man-hours and the work period. Furthermore, since the rebar assembly work at a high place can be omitted, workability and safety are improved.
[0024]
Further, since the reinforcing bar frame 14 is provided on the precast inner frame member 10b and the band reinforcing bar 11 is attached to the inner frame 14a of the reinforcing bar frame 14, the band reinforcing bar 11 can be easily attached. By providing this rebar frame 14, the shape is maintained when the precast form 10 is lifted.
[0025]
In addition, although the above-mentioned embodiment demonstrated the case where the concrete pier 1 was made into the hollow cross section, this invention can also be applied to the concrete pier of a solid cross section. In addition, here, the reinforcing bar frame 14 and the band reinforcing bar 11 are attached to the precast inner frame member 10b, but this can also be attached to the precast outer frame member 10a. Furthermore, the installation process of the precast formwork member 10 and the erection process of the steel frame 12 can be performed as appropriate.
[0026]
【The invention's effect】
As described above, according to the concrete pier construction method according to the present invention, since the precast formwork member is used, the work of disassembling the formwork in the field is not required, and the precast formwork member is previously provided with the frame for the reinforcing bar. Since the reinforcing bars are piled up after being attached via the brackets, the reinforcing bars can be easily attached and the assembling work of the reinforcing bars becomes unnecessary on site. Therefore, it is possible to reduce the work man-hours and the work period. Furthermore, since the rebar assembly work at a high place becomes unnecessary, workability and safety are improved.
[0027]
Further, when the reinforcing bar is a band reinforcing bar and an intermediate band reinforcing bar, the assembling of the band reinforcing bar and the intermediate band reinforcing bar becomes easy.
[Brief description of the drawings]
FIG. 1 is a flowchart for explaining a concrete pier construction method according to the present invention.
FIG. 2 is a sectional view showing a concrete pier according to the present invention.
FIG. 3 is a diagram showing a construction procedure of a concrete pier according to the present invention.
FIG. 4 is a diagram showing a construction procedure of a concrete pier according to the present invention.
FIG. 5 is a diagram showing a construction procedure of a concrete pier according to the present invention.
FIG. 6 is a diagram showing a construction procedure of a concrete pier according to the present invention.
FIG. 7 is a diagram showing a construction procedure of a concrete pier according to the present invention.
FIG. 8 is a diagram showing a construction procedure of a concrete pier according to the present invention.
FIG. 9 is a diagram showing a construction procedure of a concrete pier according to the present invention.
FIG. 10 is a diagram showing a construction procedure of a concrete pier according to the present invention.
FIG. 11 is a diagram showing a construction procedure of a concrete pier according to the present invention.
FIG. 12 is a diagram showing a construction procedure of a concrete pier according to the present invention.
FIG. 13 is a view showing a reinforcing bar frame and a reinforcing bar attaching procedure of the precast mold member according to the present invention.
FIG. 14 is a view showing a reinforcing bar frame and a reinforcing bar attaching procedure of the precast mold member according to the present invention.
FIG. 15 is a diagram showing a reinforcing bar frame and a reinforcing bar attaching procedure of the precast mold member according to the present invention.
FIG. 16 is a view showing a reinforcing bar frame and a reinforcing bar attaching procedure of the precast mold member according to the present invention.
FIG. 17 is a view showing a reinforcing bar frame and a reinforcing bar attaching procedure of the precast mold member according to the present invention.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Concrete pier 10 Precast formwork member 10a Precast outer frame member 10b Precast inner frame member 11 Band reinforcement 12 Steel frame 13 Concrete 14 Reinforcement frame 27 Intermediate zone reinforcement

Claims (3)

枠状で所定高さのプレキャスト型枠部材を形成する工程と、
前記プレキャスト型枠部材に鉄筋用フレームを介して鉄筋を取り付ける工程と、
橋脚を構築する所定位置に鉄骨を建て込む工程と、
前記鉄骨の周囲に所定数の前記プレキャスト型枠部材を積み上げる工程と、
前記積み上げられたプレキャス型枠部材の中にコンクリートを打設する工程とを含み、
前記鉄筋用フレームは、前記プレキャスト内枠部材に所定間隔をおいて複数取り付けられ、前記プレキャスト外枠部材及びプレキャスト内枠部材に対して垂直に配され、前記プレキャスト外枠部材及びプレキャスト内枠部材の高さ方向に延び、かつこれらの高さに対応した一対の長辺と、この長辺の両端を連結する一対の短辺とにより形成された枠状部材であり、
前記鉄筋用フレームには、建て込まれた鉄骨とプレキャスト外枠部材との間及び前記鉄骨とプレキャスト内枠部材との間に配筋可能なように、複数の鉄筋を前記一対の長辺上に、当該長辺と交わるように所定間隔で固定することを特徴とするコンクリート橋脚の施工方法。
Forming a precast mold member of a predetermined height in a frame shape ;
Attaching a reinforcing bar to the precast formwork member via a reinforcing bar frame;
Building a steel frame at a predetermined position for building a pier;
Stacking a predetermined number of the precast formwork members around the steel frame;
Placing concrete in the stacked precast formwork members,
A plurality of the reinforcing bar frames are attached to the precast inner frame member at a predetermined interval, and are arranged perpendicular to the precast outer frame member and the precast inner frame member, and the precast outer frame member and the precast inner frame member A frame-like member formed by a pair of long sides extending in the height direction and corresponding to these heights, and a pair of short sides connecting both ends of the long sides,
The reinforcing bar frame has a plurality of reinforcing bars on the pair of long sides so as to be arranged between the built steel frame and the precast outer frame member and between the steel frame and the precast inner frame member. A concrete pier construction method characterized by fixing at predetermined intervals so as to cross the long side.
前記鉄筋は帯鉄筋であり、この帯鉄筋は、前記プレキャスト内枠部材側に配されている長辺の内側と、前記プレキャスト外枠部材側の長辺の外側とに固定されることを特徴とする請求項1に記載のコンクリート橋脚の施工方法。The reinforcing bars are band reinforcing bars, and the reinforcing bars are fixed to the inner side of the long side arranged on the precast inner frame member side and the outer side of the long side of the precast outer frame member side. The construction method of the concrete pier of Claim 1 to do. 前記一対の長辺の両内側又は前記プレキャスト内枠部材側に配されている長辺の内側と前記プレキャスト外枠部材側の長辺の外側とに固定されている帯鉄筋を連結している中間帯鉄筋をさらに有していることを特徴とする請求項2に記載のコンクリート橋脚の施工方法。Middle connecting the reinforcing bars fixed to both inner sides of the pair of long sides or the inner side of the longer side arranged on the precast inner frame member side and the outer side of the longer side on the precast outer frame member side The construction method for a concrete pier according to claim 2 , further comprising a belt reinforcing bar.
JP04041498A 1998-02-23 1998-02-23 Concrete pier construction method Expired - Fee Related JP4136049B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP04041498A JP4136049B2 (en) 1998-02-23 1998-02-23 Concrete pier construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP04041498A JP4136049B2 (en) 1998-02-23 1998-02-23 Concrete pier construction method

Publications (2)

Publication Number Publication Date
JPH11241311A JPH11241311A (en) 1999-09-07
JP4136049B2 true JP4136049B2 (en) 2008-08-20

Family

ID=12580014

Family Applications (1)

Application Number Title Priority Date Filing Date
JP04041498A Expired - Fee Related JP4136049B2 (en) 1998-02-23 1998-02-23 Concrete pier construction method

Country Status (1)

Country Link
JP (1) JP4136049B2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001020089A1 (en) * 1999-09-10 2001-03-22 Maeda Corporation Concrete structure and method of constructing the same
JP2003213698A (en) * 2002-01-16 2003-07-30 Maeda Corp Bridge and construction method thereof
JP3906742B2 (en) * 2002-05-23 2007-04-18 Jfeエンジニアリング株式会社 Joint structure and joining method of main girder and reinforced concrete pier
JP4347846B2 (en) * 2005-12-27 2009-10-21 東日本旅客鉄道株式会社 Bridge pier reinforcement method
JP5620344B2 (en) * 2011-06-21 2014-11-05 三井住友建設株式会社 Construction method of pier
CN104120647B (en) * 2014-07-04 2016-09-14 上海应用技术学院 It is suitable for section assembling concrete frame bridge pier system and the construction method of rapid construction
CN111691303A (en) * 2020-06-03 2020-09-22 胡增永 Modular pier base pouring tower for building construction
CN111851300A (en) * 2020-07-09 2020-10-30 中铁六局集团天津铁路建设有限公司 Rectangular frame column construction method adopting template chamfering
CN113699877B (en) * 2021-10-09 2023-03-31 四川省交通勘察设计研究院有限公司 Steel-concrete composite structure pier suitable for high-intensity area and construction method thereof

Also Published As

Publication number Publication date
JPH11241311A (en) 1999-09-07

Similar Documents

Publication Publication Date Title
JP4136049B2 (en) Concrete pier construction method
JPH1030212A (en) Reinforced concrete structure and its construction method
KR101117497B1 (en) Bridge having continuous arch hybrid girders and the bridge construction method using the same
JPH09310405A (en) Reinforced concrete column and precast form
KR100377868B1 (en) pier construction method using Pier scaffolding
JP3841498B2 (en) PCa formwork and pier construction method using this PCa formwork
JPH0978532A (en) Work execution method for concrete bridge pier
KR100456192B1 (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
JP3031530B2 (en) How to build a concrete pier
KR100235117B1 (en) Ready-made steel net for r.c column and the executing method with it
JPH1136229A (en) Construction method for reinforced concrete bridge pier
JP2000129633A (en) Erection method for bridge floor slab
JPH1113017A (en) Construction method of hollow cylindrical skeleton
JP3824242B2 (en) Viaduct-free support construction method
JP2002364072A (en) Beam for hybrid-structure frame
JPH0835210A (en) Tower-like structure and construction method thereof
JPH03279533A (en) Constructing method for rigid-frame type rc super-high building
WO2001020089A1 (en) Concrete structure and method of constructing the same
JP3319709B2 (en) Construction method of prestressed concrete steel beam
JP3388454B2 (en) Bridge pier construction method
JPH05239810A (en) Constructing method for reinforced concrete arch bridge
JP2001207409A (en) Pier structure and its constructing method
JPS61169559A (en) Semi-existing concrete panel using assembled reinforcement
JPS62121251A (en) Building ramen
JP2023175116A (en) Installation method of metal lath

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20041115

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20061031

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061225

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070417

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070614

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20071023

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071221

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080513

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080603

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110613

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120613

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130613

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees