JP3905021B2 - Construction method of viaduct pier - Google Patents
Construction method of viaduct pier Download PDFInfo
- Publication number
- JP3905021B2 JP3905021B2 JP2002333782A JP2002333782A JP3905021B2 JP 3905021 B2 JP3905021 B2 JP 3905021B2 JP 2002333782 A JP2002333782 A JP 2002333782A JP 2002333782 A JP2002333782 A JP 2002333782A JP 3905021 B2 JP3905021 B2 JP 3905021B2
- Authority
- JP
- Japan
- Prior art keywords
- pier
- column
- pile
- viaduct
- pillar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
- Foundations (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、高架橋橋脚の構築方法に関し、特に、地表付近で橋脚梁を柱に構築するとともに、橋脚梁を所定の高さまでリフトアップして回転させることにより、揚重作業や高所作業を不要とするとともに、橋脚梁構築に必要な道路等の占拠幅を最小限にとどめることができる高架橋橋脚の構築方法に関するものである。
【0002】
【従来の技術】
従来、鉄筋コンクリート造等の現場打ちの高架橋橋脚の施工は、完成時の位置や角度に基づいて、架台や鉄筋、型枠等を組み立て、コンクリートを打設し、硬化後、橋脚梁や上部桁等を設置するという方法が実施されている。
【0003】
【発明が解決しようとする課題】
しかしながら、上記従来の高架橋橋脚の構築方法においては、橋脚梁用の鉄筋及び型枠の設置や、コンクリート打設、吊りによる揚重作業や高所作業に伴う安全面における特別の注意が必要であるとともに、橋脚梁が幅広く土地を占拠することから広い施工用地幅が必要となり、既設道路上に架設する場合は長期間に亘って交通を遮断しなければならない等の問題があった。
【0004】
本発明は、上記従来の高架橋橋脚の構築方法が有する問題点に鑑み、揚重作業や高所作業を不要とするとともに、橋脚梁構築に必要な道路等の占拠幅を最小限にとどめることができる高架橋橋脚の構築方法を提供することを目的とする。
【0005】
【課題を解決するための手段】
上記目的を達成するため、本発明の高架橋橋脚の構築方法は、柱により上部桁が支持される高架橋橋脚の構築方法において、少なくとも略柱の長さを有する断面円形の中空の杭を地盤中に構築して、該杭の中空部にプレキャスト部材からなる柱を挿入し、該挿入した柱の上部に高架橋の橋脚梁を構築した後、ジャッキにより橋脚梁及び柱を持ち上げるとともに、橋脚梁及び柱を、該柱の下端部が杭に挿入された状態で、柱を中心に所定の角度回転させて、所定の位置に支持した後、前記柱と杭の中空部との空隙にコンクリートを充填することにより柱を杭に固定することを特徴とする。
【0006】
この高架橋橋脚の構築方法は、少なくとも略柱の長さを有する断面円形の中空の杭を地盤中に構築して、該杭の中空部にプレキャスト部材からなる柱を挿入し、該挿入した柱の上部に高架橋の橋脚梁を構築した後、ジャッキにより橋脚梁及び柱を持ち上げるとともに、橋脚梁及び柱を、該柱の下端部が杭に挿入された状態で、柱を中心に所定の角度回転させて、所定の位置に支持した後、前記柱と杭の中空部との空隙にコンクリートを充填することにより柱を杭に固定するようにしているので、橋脚梁や橋脚梁と柱との接合部等を地表付近で構築して、従来の橋脚梁用の鉄筋及び型枠の設置や、コンクリート打設、吊りによる揚重作業や高所作業を不要とするとともに、地上での橋脚梁の構築を施工用地幅に適した角度で行っておき、最終的に、橋脚梁を必要な角度に設置し直すことができ、これにより、橋脚梁構築に必要な道路等の占拠幅を最小限にとどめて、長期間に亘る交通遮断等の問題を解消又は著しく軽減軽減することができる。
【0007】
この場合において、杭頭部分にジャッキ反力をとることができる。
【0008】
これにより、十分な支持力が確実に得られるとともに、地盤面に反力をとる場合と比較し、地表面の沈下や地盤の移動などの周辺への影響を小さくすることができる。
【0009】
また、1本の杭あたり少なくとも3台のジャッキを用いることができる。
【0010】
これにより、作業の安定性が得られるとともに、ジャッキのもり換えを容易にすることができる。
【0011】
【発明の実施の形態】
以下、本発明の高架橋橋脚の構築方法の実施の形態を図面に基づいて説明する。
【0012】
図1〜図4に、本発明の高架橋橋脚の構築方法の一実施例を示す。
この高架橋橋脚の構築方法は、例えば、柱1により橋脚梁2が支持される高架橋橋脚を構築するもので、図1(a)に示すように、まず、略柱の長さを有する中空の鋼管杭を地盤中に構築する。
この場合、鋼管杭3は、地盤の性状等に応じて、全長に亘って均一の径、材質のもののほか、本実施例に示すように、上部と下部で異なる径(特に限定されるものではないが、本実施例においては、拡頭タイプの回転貫入鋼管杭としている。)、材質のものを用いることもできる。
【0013】
その後、図1(b)に示すように、杭3の中空部31にプレキャスト部材からなる柱(CFT柱)1を挿入する。
そして、図2(a)〜(b)に示すように、挿入した柱1の上部に高架橋の橋脚梁2を構築し、ジャッキ4により橋脚梁2を持ち上げて所定の高さに支持する。
次に、図3(a)に示すように、この持ち上げた橋脚梁2を所定の角度回転させ、その後、図3(b)に示すように、橋脚梁2とともに回転した柱1を、杭3の中空部31との空隙にコンクリート5を充填することにより杭3に固定する。
【0014】
この場合、リフトアップの際には、橋脚梁2の下部21と杭頭部分32にそれぞれジャッキ反力をとるようにする。
そして、もり換えを行うことができるように、1本の杭あたり少なくとも3台(荷重に応じて、通常、3台乃至4台又はそれ以上の台数)のジャッキ4を組み合わせるとともに、複数の架台6を用いてジャッキストロークのもり換えを行いながら、所定の高さまで持ち上げる。
そして、橋脚梁2を所定の角度回転させる手段としては、特に限定されるものではないが、適宜の高さ位置の架台6と架台6の間に、ガイドレールを有する円環状の2枚の支持板(図示省略)を配設し、支持板同士をガイドレールに沿って相対的に回転させることにより、柱1を中心軸として、橋脚梁2及び柱1を所定の角度回転させるようにする。
【0015】
柱1と杭3との固定が完了した後は、図4(a)に示すように、ジャッキ4と架台6を撤去し、図4(b)に示すように、隣接する柱1の橋脚梁2上に上部桁7を架設する。
この場合、上部桁7の付帯構造としては、高欄、防音壁、軌道等(図示省略)を構築することができる。
【0016】
かくして、本実施例の高架橋橋脚の構築方法は、略柱1の長さを有する中空の杭3を地盤中に構築して、該杭3の中空部31に柱1を挿入するとともに、該挿入した柱1の上部に高架橋の橋脚梁2を構築し、ジャッキ4により橋脚梁2を持ち上げて所定の高さに支持した後、橋脚梁2及び柱1を所定の角度回転させ、橋脚梁2と共に回転した柱1を杭3に固定することから、橋脚梁2や橋脚梁2と柱1との接合部等を地表付近で構築して、従来の橋脚梁2用の鉄筋及び型枠の設置や、コンクリート打設、吊りによる揚重作業や高所作業を不要とするとともに、橋脚梁2を所定の高さに持ち上げてから回転させることから、地上での橋脚梁2の構築を施工用地幅に適した角度で行っておき、最終的に、橋脚梁2を必要な角度に設置し直すことができ、これにより、橋脚梁2構築に必要な道路等の占拠幅を最小限にとどめて、長期間に亘る交通遮断等の問題を解消又は著しく軽減軽減することができる。
そして、杭頭部分32にジャッキ反力をとることにより、十分な支持力が確実に得られるとともに、地盤面に反力をとる場合と比較し、地表面の沈下や地盤の移動などの周辺への影響を小さくすることができる。
また、1本の杭あたり少なくとも3台のジャッキ4を用いることにより、作業の安定性が得られるとともに、ジャッキ4のもり換えを容易にすることができる。
【0017】
ところで、上記実施例においては、ジャッキ4により橋脚梁2及び柱1を持ち上げて所定の高さに支持した後、持ち上げた橋脚梁2及び柱1を所定の角度回転させるようにしたが、このほか、周辺の状況等に応じて、橋脚梁2及び柱1を所定の角度回転させた後、ジャッキ4により橋脚梁2及び柱1を持ち上げて所定の高さに支持するようにしたり、ジャッキ4により橋脚梁2及び柱1を途中まで持ち上げ、持ち上げた橋脚梁2及び柱1を所定の角度回転させた後、さらに、橋脚梁2及び柱1を持ち上げて所定の高さに支持するようにすることにより、橋脚梁2及び柱1の回転を作業のし易い比較的低い位置で行うようにすることもできる。
【0018】
以上、本発明の高架橋橋脚の構築方法について、その実施例を説明したが、本発明の高架橋橋脚の構築方法は、上記実施例の記載に限定されるものではなく、例えば、柱を介して橋脚梁を持ち上げるなど、その趣旨を逸脱しない範囲において適宜に変更することが可能である。
また、図示による高架橋の形状、杭・柱・橋脚梁等の材料や種類及び橋脚梁の持ち上げ方法等はその一例であり、本発明の趣旨はこれらに限定されるものではない。
【0019】
【発明の効果】
本発明の高架橋橋脚の構築方法によれば、少なくとも略柱の長さを有する断面円形の中空の杭を地盤中に構築して、該杭の中空部にプレキャスト部材からなる柱を挿入し、該挿入した柱の上部に高架橋の橋脚梁を構築した後、ジャッキにより橋脚梁及び柱を持ち上げるとともに、橋脚梁及び柱を、該柱の下端部が杭に挿入された状態で、柱を中心に所定の角度回転させて、所定の位置に支持した後、前記柱と杭の中空部との空隙にコンクリートを充填することにより柱を杭に固定するようにしているので、橋脚梁や橋脚梁と柱との接合部等を地表付近で構築して、従来の橋脚梁用の鉄筋及び型枠の設置や、コンクリート打設、吊りによる揚重作業や高所作業を不要とするとともに、地上での橋脚梁の構築を施工用地幅に適した角度で行っておき、最終的に、橋脚梁を必要な角度に設置し直すことができ、これにより、橋脚梁構築に必要な道路等の占拠幅を最小限にとどめて、長期間に亘る交通遮断等の問題を解消又は著しく軽減軽減することができるため、既存の道路に沿って高架橋を構築する場合や狭小な場所に高架橋を構築する場合等でも、用地の買収等を行うことなく高架橋を構築することができる。
【0020】
この場合、杭頭部分にジャッキ反力をとることにより、十分な支持力が確実に得られるとともに、地盤面に反力をとる場合と比較し、地表面の沈下や地盤の移動などの周辺への影響を小さくすることができる。
【0021】
また、1本の杭あたり少なくとも3台のジャッキを用いることにより、作業の安定性が得られるとともに、ジャッキのもり換えを容易にすることができる。
【図面の簡単な説明】
【図1】 本発明の高架橋橋脚の構築方法の一実施例を示し、(a)は鋼管杭の施工を示す工程図、(b)は鋼管杭への柱の挿入を示す工程図である。
【図2】 同実施例の高架橋橋脚の構築方法を示し、(a)は柱への橋脚梁の構築を示す工程図、(b)は橋脚梁と柱の持ち上げを示す工程図である。
【図3】 同実施例の高架橋橋脚の構築方法を示し、(a)は橋脚梁の回転を示す工程図、(b)は柱と鋼管杭の固定を示す工程図である。
【図4】 同実施例の高架橋橋脚の構築方法を示し、(a)は架台とジャッキを撤去した状態を示す工程図、(b)は上部桁を架設した状態を示す工程図である。
【符号の説明】
1 柱
2 橋脚梁
21 下部
3 杭
31 中空部
32 杭頭部分
4 ジャッキ
5 コンクリート
6 架台
7 上部桁[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing a viaduct pier, and in particular, constructs a pier beam in a column near the ground surface, and lifts and rotates the pier beam to a predetermined height, so that lifting work and height work are unnecessary. In addition, the present invention relates to a method for constructing a viaduct pier capable of minimizing the occupation width of roads and the like necessary for pier construction.
[0002]
[Prior art]
Conventionally, construction of on-site viaduct bridge piers such as reinforced concrete structures is based on the position and angle at the time of completion, assembling the gantry, rebar, formwork, etc., placing concrete, hardening, pier beams, upper girders, etc. The method of installing is implemented.
[0003]
[Problems to be solved by the invention]
However, in the conventional method for constructing a viaduct pier, special attention is required in terms of safety associated with installation of reinforcing bars and formwork for pier beams, concrete placement, lifting work by lifting and work at high places. At the same time, since the bridge piers widely occupy the land, a wide construction width is required, and when it is constructed on an existing road, there is a problem that the traffic must be blocked for a long period of time.
[0004]
In view of the problems of the above-mentioned conventional viaduct pier construction method, the present invention eliminates the need for lifting work and height work and minimizes the occupation width of roads and the like necessary for pier beam construction. An object of the present invention is to provide a method for constructing an elevated viaduct.
[0005]
[Means for Solving the Problems]
In order to achieve the above object, a method for constructing a viaduct pier according to the present invention is a method for constructing a viaduct pier in which an upper girder is supported by a column, and a hollow pile having a circular section having at least a substantially column length is provided in the ground. After constructing and inserting a pillar made of a precast member into the hollow portion of the pile and constructing a viaduct bridge on the upper part of the inserted pillar, the pier beam and the column are lifted by a jack, and the pier beam and the column are In a state where the lower end of the column is inserted into the pile, the column is rotated by a predetermined angle around the column and supported at a predetermined position, and then the concrete is filled into the gap between the column and the hollow portion of the pile. characterized in that to secure the posts to the pile by.
[0006]
This viaduct pier construction method is to construct a hollow pile with a circular cross section having at least a substantially column length in the ground, insert a column made of a precast member into the hollow portion of the pile, and After constructing the viaduct bridge on the upper part, lift the bridge pier and column with jacks and rotate the pier beam and column by a predetermined angle around the column with the lower end of the column inserted into the pile. Since the pillar is fixed to the pile by filling the gap between the pillar and the hollow portion of the pile with concrete after being supported at a predetermined position, the bridge pier or the joint between the pier beam and the pillar Etc. are constructed near the surface of the earth, making it unnecessary to install conventional reinforcing bars and formwork for bridge piers, concrete placement, lifting work by lifting and work at high places, and construction of pier bridges on the ground. It is done at an angle suitable for the construction width, and finally The bridge piers can be re-installed at the required angle, thereby minimizing or remarkably reducing problems such as long-term traffic blockage by minimizing the occupation width of roads and the like necessary for pier construction. Can be reduced.
[0007]
In this case, a jack reaction force can be applied to the pile head portion.
[0008]
As a result, a sufficient support force can be obtained reliably, and the influence on the surroundings such as subsidence of the ground surface and movement of the ground can be reduced as compared with a case where a reaction force is applied to the ground surface.
[0009]
Moreover, at least three jacks can be used per pile.
[0010]
Thereby, the stability of the work can be obtained and the replacement of the jack can be facilitated.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of a construction method of a viaduct pier according to the present invention will be described with reference to the drawings.
[0012]
1 to 4 show an embodiment of a method for constructing a viaduct pier according to the present invention.
This viaduct pier construction method is, for example, to construct a viaduct pier in which a
In this case, depending on the properties of the ground, the
[0013]
Thereafter, as shown in FIG. 1B, a column (CFT column) 1 made of a precast member is inserted into the
Then, as shown in FIGS. 2A to 2B, a
Next, as shown in FIG. 3 (a), this lifted
[0014]
In this case, jacking reaction force is applied to the
In addition, at least three jacks (generally three to four or more depending on the load) are combined with each other, and a plurality of
The means for rotating the
[0015]
After the fixation between the
In this case, as an incidental structure of the
[0016]
Thus, in the construction method of the viaduct pier of this embodiment, the
And, by taking jack reaction force on the
Further, by using at least three
[0017]
In the above embodiment, the
[0018]
As mentioned above, although the Example was described about the construction method of the viaduct pier of this invention, the construction method of the viaduct pier of this invention is not limited to description of the said Example, For example, it is a pier via a pillar. It is possible to make appropriate changes within a range that does not depart from the gist, such as lifting a beam.
Further, the shape of the viaduct shown in the figure, materials and types of piles, columns, bridge piers, and the like, and a method for lifting the pier bridges are examples thereof, and the gist of the present invention is not limited thereto.
[0019]
【The invention's effect】
According to the construction method of the viaduct pier of the present invention, a hollow pile having a circular cross section having at least a substantially column length is built in the ground, and a column made of a precast member is inserted into the hollow portion of the pile, After constructing the viaduct bridge on the top of the inserted column, lift the pier beam and the column with a jack , and insert the pier beam and column with the lower end of the column inserted into the pile. Since the pillar is fixed to the pile by filling the space between the pillar and the hollow portion of the pile after the angle is rotated and supported at a predetermined position, the pier beam or the pier beam and the pillar are fixed. The construction of the joints with the ground near the ground surface eliminates the need for conventional reinforcement and formwork for bridge piers, concrete placement, lifting work by lifting, and work at high places. Build the beam at an angle suitable for the construction width. Finally, the bridge piers can be re-installed at the required angle, thereby minimizing the occupational width of roads etc. necessary for the construction of the piers and preventing problems such as long-term traffic blockage. Since it can be eliminated or remarkably reduced, it is possible to construct a viaduct without acquiring a site, etc., even when constructing a viaduct along an existing road or when constructing a viaduct in a narrow place. .
[0020]
In this case, by taking jack reaction force on the pile head part, sufficient support force can be surely obtained, and compared to the case where reaction force is applied to the ground surface, it can move to the surroundings such as subsidence of the ground surface and movement of the ground. The influence of can be reduced.
[0021]
In addition, by using at least three jacks per pile, work stability can be obtained and jack replacement can be facilitated.
[Brief description of the drawings]
FIG. 1 shows an embodiment of a method for constructing a viaduct pier according to the present invention, wherein (a) is a process diagram showing construction of a steel pipe pile, and (b) is a process chart showing insertion of a column into the steel pipe pile.
FIGS. 2A and 2B show a method for constructing a viaduct pier according to the embodiment, wherein FIG. 2A is a process diagram showing construction of a pier beam to a column, and FIG. 2B is a process diagram showing lifting of the pier beam and the column;
3A and 3B show a method for constructing a viaduct pier according to the embodiment, where FIG. 3A is a process diagram showing rotation of the pier beam, and FIG. 3B is a process diagram showing fixation of a column and a steel pipe pile.
4A and 4B show a method for constructing a viaduct pier according to the embodiment, wherein FIG. 4A is a process diagram showing a state in which a gantry and a jack are removed, and FIG. 4B is a process diagram showing a state in which an upper girder is installed.
[Explanation of symbols]
1
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002333782A JP3905021B2 (en) | 2002-11-18 | 2002-11-18 | Construction method of viaduct pier |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002333782A JP3905021B2 (en) | 2002-11-18 | 2002-11-18 | Construction method of viaduct pier |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004169318A JP2004169318A (en) | 2004-06-17 |
JP3905021B2 true JP3905021B2 (en) | 2007-04-18 |
Family
ID=32698399
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002333782A Expired - Lifetime JP3905021B2 (en) | 2002-11-18 | 2002-11-18 | Construction method of viaduct pier |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3905021B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103255721A (en) * | 2013-05-27 | 2013-08-21 | 张云祥 | High-level bridge construction method |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5189431B2 (en) * | 2008-08-05 | 2013-04-24 | 三井住友建設株式会社 | Multi-span continuous concrete bridge |
JP6712201B2 (en) * | 2016-08-31 | 2020-06-17 | 東急建設株式会社 | How to build a pier |
CN107794932B (en) * | 2017-11-06 | 2023-10-03 | 固远晨通科技发展有限公司 | Pier structure is backfilled to foam lightweight concrete |
-
2002
- 2002-11-18 JP JP2002333782A patent/JP3905021B2/en not_active Expired - Lifetime
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103255721A (en) * | 2013-05-27 | 2013-08-21 | 张云祥 | High-level bridge construction method |
Also Published As
Publication number | Publication date |
---|---|
JP2004169318A (en) | 2004-06-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5045214B2 (en) | Column head construction method | |
JP3644605B2 (en) | Reverse driving method of underground structure under road surface. | |
JP4512562B2 (en) | Approach section construction method | |
KR100949601B1 (en) | Method for broadening width of existing bridge without Temporary road | |
CN110117936B (en) | Swivel device for bridge pier and swivel construction method | |
JP3905021B2 (en) | Construction method of viaduct pier | |
JP3850785B2 (en) | Caisson laying method using main foundation pile | |
JP2001059208A (en) | Reinforcing work method by steel arch for existing bridge | |
JP4685341B2 (en) | Viaduct construction method | |
CN116254783A (en) | High-position girder falling construction method suitable for erecting high-speed railway precast box girders | |
JP4477467B2 (en) | Bridge structure and its replacement method | |
JPH11172710A (en) | Method for constructing underground part of steel encased reinforced concrete building | |
KR100496735B1 (en) | Abutment and pier using composite pile and sheet pile of a bridge, and it's construction method | |
CN213571600U (en) | Bridge underpins bearing structure | |
JP3660657B2 (en) | Construction method of viaduct | |
JP4094416B2 (en) | Construction method of multilevel intersection | |
JP3852686B2 (en) | Three-dimensional intersection construction method and three-dimensional intersection | |
JP3690463B2 (en) | Construction method of viaduct | |
JP7350797B2 (en) | How to lift bridge girders | |
JP3779978B2 (en) | Elevated traffic route | |
KR100593203B1 (en) | a deck supportframe and a construction methed | |
KR102671025B1 (en) | Pier and Construction Method using Centrifugal High-Strength PHC Piles | |
KR100949868B1 (en) | The enlargement construction method for base of bridge with guides and molds in the shape of pipes | |
KR100478994B1 (en) | The freeway using a steel pile and sheet pile, and it's construction method | |
JP7269197B2 (en) | ROAD STRUCTURE AND METHOD FOR MANUFACTURING ROAD STRUCTURE |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040708 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060614 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060711 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060911 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070109 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070110 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3905021 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100119 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130119 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140119 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |