JP3690463B2 - Construction method of viaduct - Google Patents
Construction method of viaduct Download PDFInfo
- Publication number
- JP3690463B2 JP3690463B2 JP13085398A JP13085398A JP3690463B2 JP 3690463 B2 JP3690463 B2 JP 3690463B2 JP 13085398 A JP13085398 A JP 13085398A JP 13085398 A JP13085398 A JP 13085398A JP 3690463 B2 JP3690463 B2 JP 3690463B2
- Authority
- JP
- Japan
- Prior art keywords
- viaduct
- formwork
- column
- floor slab
- temporary
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
- Working Measures On Existing Buildindgs (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は構造物の構築方法に係わり、特に既設軌道の直下に近接せしめて鉄筋コンクリート造の高架橋を構築するに際して適用して好適な高架橋の構築方法に関する。
【0002】
【従来の技術】
建築工事や土木工事の分野においては、既設物の直下に近接せしめて新設構造物を設ける場合が多々ある。たとえば図5に示すような鉄道用の高架橋1を構築するに際しては、(a)に示すように既存の軌道を仮設支柱2および仮設桁3により仮支持して車両を運行しながら、その下方空間に高架橋1を構築する場合がある。そのような場合にはまず高架橋1の柱4を立設し、次いでその上部に床版5を設けることになるが、新設するべき床版5を既設物である仮設桁3に対して十分に近接させて設けることが一般的であり、したがってそれら床版5と仮設桁3との間にはごくわずかな間隙しか確保し得ないことが通常である。
【0003】
【発明が解決しようとする課題】
ところで、上記のように既設物の直下に近接せしめて新設構造物を設ける場合において、新設構造物が鉄筋コンクリート造である場合には、既設物が新設構造物の施工の障害となることがある。たとえば図5に示した場合において新設すべき高架橋1が鉄筋コンクリート造であるときには、床版5を施工するに際してコンクリート打設用の型枠を仮設桁3の直下に設け、その型枠上に鉄筋を組み立てることになるのであるが、床版5を仮設桁3に対して十分に近接させて設ける必要があることから仮設桁3の下方に型枠工事や鉄筋工事を行うためのスペースが殆ど確保し得ず、その作業が極めて困難なものとなる。
【0004】
このため、従来においては型枠工事や鉄筋工事が可能な程度に床版5と仮設桁3との間の間隙を必要以上に大きく確保するか、もしくは型枠工事や鉄筋工事が不要な構造や工法を採用するしかないが、そのようなことは不都合であるので有効な改善策が要望されていた。
【0005】
【課題を解決するための手段】
上記事情に鑑み、本発明は、既設軌道の直下に近接せしめて鉄筋コンクリート造の高架橋を構築するに際し、構築すべき高架橋の柱の柱脚部を先行施工するとともに、前記既設軌道の下方において昇降可能な架台を設置し、該架台を降下せしめた状態で該架台上に前記高架橋の床版を形成するための型枠を支保工により支持して本来の設置位置よりも低い位置に配置するとともに、該型枠上に前記床版の鉄筋を組み立て、しかる後に、前記架台をジャッキにより上昇せしめて前記型枠および前記鉄筋を本来の設置位置に導き、柱脚部の上部に柱筋および柱型枠を組み立て、前記型枠上および前記柱型枠内にコンクリートを打設して前記柱および床版を形成することを特徴とする。
【0006】
【発明の実施の形態】
以下、本発明の実施形態を図1〜図4を参照して説明する。以下で説明する実施形態は、図5に示したように既存の軌道を仮設支柱2および仮設桁3により仮支持しながらその下方空間にラーメン構造の鉄筋コンクリート造の高架橋1を新設する場合に適用したものである。この場合、新設するべき高架橋1の床版5は可及的に仮設桁3に対して近接して設けることが要求され、したがってその床版5と仮設桁3との間には50〜150mm程度の間隙しか確保し得ない状況にある。なお、図1〜図4においていずれも(a)は横断面図、(b)は縦断面図であって、(b)に示されるように本実施形態では高架橋1の施工をその長さ方向に一定長ずつ(図示例のものは3スパンずつ)行うものとしている。また、図1〜図4においては新設すべき高架橋1および既設物である仮設支柱2と仮設桁3はいずれも鎖線で示してある(ただし(b)においては仮設支柱2および仮設桁3の図示は省略している)。
【0007】
本実施形態の構築方法では、まず、図1に示すように高架橋1を支持するための杭6、基礎7を施工するとともに、柱4の下端部すなわち柱脚部4aのみを先行施工し、柱脚部4aの上部には柱筋8を突出せしめておく。これらの施工は仮設桁3と地表との間に十分なスペースが確保されるので通常の工法により支障なく行い得る。
【0008】
次いで、図2に示すように、仮設桁3の下方において昇降可能な架台9を地表部に設置し、その上部に床版5を形成するための型枠10を支保工11により支持して設置する。この際、架台9は地表部に降下させておき、型枠10は本来の設置位置(すなわち実際に床版5を形成するべき位置)よりも低い位置となるように支保工11の高さを設定する。これにより、支保工11および型枠10の組立作業は実質的に地表部で行い得て高所作業とはならず、また、仮設桁3の下方に作業スペースを確保し得るから型枠10の組立作業を容易に行い得る。
【0009】
次に、図3に示すように、上記で組み立てた型枠10の上部に床版5中に埋設するべき鉄筋12を組み立てる。これらの鉄筋12を組み立てる作業も、型枠10が本来の設置位置よりも低い位置に配置されていることから、仮設桁3との間に作業スペースが確保され、支障なく実施することができる。
【0010】
上記の鉄筋12の組立作業が完了したら、図4に示すようにジャッキ13を用いて架台9を徐々に上昇せしめ、鉄筋12および型枠10を本来の設置位置すなわち床版5を形成するべき位置まで上昇させる。そして、鉄筋12および型枠10をその位置に保持したままで、すでに施工が完了している柱脚部4aの上部に継ぎ足す形で柱筋14を組み立て、その周囲に柱型枠(図示せず)を組み立てる。しかる後に、コンクリートを打設して床版5と柱4を一体に形成すれば図5(b)に示したような高架橋1が完成する。なお、ジャッキ13としては汎用の油圧ジャッキやセンターホールジャッキ等を任意に採用可能であるし、架台9を地表より押し上げる形式のもののみならず架台9を上方より吊り上げる形式のものも採用可能である。また、コンクリート打設荷重は型枠10、支保工11、架台9を介してジャッキ13により受けることが可能であるが、必要に応じて架台9と地表との間にコンクリート打設荷重を受けるための他の支保工を適宜設ければ良い。
【0011】
以上のように、型枠10および鉄筋12を架台9上において本来の設置位置よりも下げて低い位置として組み立ててから、架台9を上昇させて本来の位置に配置することにより、型枠10および鉄筋12の組立作業に際して仮設桁3が障害になることがなく、またそれらの作業を高所ではなく地表部において容易に行うことができ、しかも架台9をジャッキ13によりジャッキアップすることのみで鉄筋12および型枠10を本来の設置位置まで速やかにかつ容易に上昇させることが可能であり、仮設桁3により仮支持している鉄道の運行に支障を来すこともない。
【0012】
以上のことから、上記方法によれば、型枠10や鉄筋12を最初から本来の位置に設置する場合に比較すると作業性を格段に改善することができるし、従来のように施工性を考慮して仮設桁3と床版5との間の間隙を必要以上に大きく確保するような必要がなく、また従来においては作業スペースが確保できないために採用することができなかった構造や工法も採用可能となる。
【0014】
【発明の効果】
以上で説明したように、本発明は、既設軌道の下方に高架橋を新設するに際し、新設するべき高架橋の柱の柱脚部を先行施工するとともに、既設軌道の下方に昇降可能な架台を設置し、その架台上において床版施工用の型枠および鉄筋を本来の設置位置よりも低い位置に下げた状態で組み立てた後、架台をジャッキにより上昇せしめてそれら型枠および鉄筋を本来の設置位置に導き、柱脚部の上部に柱筋および柱型枠を組み立て、前記型枠上および前記柱型枠内にコンクリートを打設して柱および床版を形成するようにしたから、型枠および鉄筋の組立作業に際して既設物が障害になることがなく、したがって型枠や鉄筋を最初から本来の位置に設置する場合に比較すると作業性を格段に改善することができ、その結果、従来のように施工性を考慮して既設軌道と新設高架橋との間隙を必要以上に大きく確保するような必要がなく、従来においては作業スペースが確保できないために採用することができなかった構造や工法も採用可能となる。
【図面の簡単な説明】
【図1】 本発明の構築方法により既設物の直下に高架橋を構築する場合の実施形態を示すもので、基礎および柱脚部を先行施工した状態を示す図である。
【図2】 同、架台上に型枠を設置した状態を示す図である。
【図3】 同、型枠上に鉄筋を組み立てた状態を示す図である。
【図4】 同、架台を昇降させて型枠および鉄筋を本来の位置に配置した状態を示す図である。
【図5】 既設物である仮設桁の直下に新設構造物である高架橋を設置する場合の例を示す図である。
【符号の説明】
1 高架橋
2 仮設支柱
3 仮設桁
4 柱
4a 柱脚部
5 床版
9 架台
10 型枠
11 支保工
12 鉄筋
13 ジャッキ
14 柱筋 [0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing a structure, regarding how to build a suitable viaduct applied when particular building a viaduct reinforced concrete are caused to close immediately below the existing track.
[0002]
[Prior art]
In the field of construction work and civil engineering work, there are many cases where new structures are provided in close proximity to existing objects. For example, when the
[0003]
[Problems to be solved by the invention]
By the way, in the case where a new structure is provided close to the existing structure as described above, if the new structure is a reinforced concrete structure, the existing structure may be an obstacle to the construction of the new structure. For example, in the case shown in FIG. 5, when the
[0004]
For this reason, in the prior art, a gap between the
[0005]
[Means for Solving the Problems]
In view of the above circumstances, the present invention can be constructed in advance of the column base of the viaduct column to be constructed, and can be moved up and down below the existing track when building a reinforced concrete viaduct close to the existing track. And placing the support frame on the frame to form the viaduct floor slab in a state where the frame is lowered, and placing it at a position lower than the original installation position. assembling the rebar of the slab to the mold on frame, thereafter,-out guide to the original installation position of the formwork and the reinforcement of the frame and raised by jacking pillars muscle and pillar shape on the top of the column base portion A frame is assembled, and concrete is placed on the mold and in the column mold to form the columns and floor slab .
[0006]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to FIGS. The embodiment described below is applied to the case where a ramen-structured reinforced
[0007]
In the construction method of the present embodiment, first, as shown in FIG. 1, the
[0008]
Next, as shown in FIG. 2, a
[0009]
Next, as shown in FIG. 3, the
[0010]
When the assembly work of the
[0011]
As described above, by assembling the
[0012]
From the above, according to the above method, the workability can be remarkably improved as compared with the case where the
[0014]
【The invention's effect】
As explained above, when the present invention newly installs a viaduct below an existing track , the present invention installs a column base of the pillar of the viaduct to be newly installed, and installs a platform that can be raised and lowered below the existing track. After assembling the floor slab formwork and rebar to a position lower than the original installation position on the base, raise the base with a jack to bring the formwork and rebar to the original installation position. guide-out, assembling the pillar muscle and pillar formwork on top of the column base, it is so arranged to form a column and a floor plate by Da設concrete on the formwork and the column formwork within the mold and There is no obstacle to existing objects during rebar assembly work, so workability can be significantly improved compared to the case where the formwork and rebar are installed in the original position from the beginning. Workability It is not necessary, such as to ensure unnecessarily large gap between the new viaduct with the existing track in consideration, it is possible to adopt the structure and construction methods can not be employed for working space can not be secured in the conventional.
[Brief description of the drawings]
FIG. 1 is a diagram showing an embodiment in the case where a viaduct is constructed directly under an existing object by the construction method of the present invention, and is a diagram showing a state in which a foundation and a column base are pre-constructed.
FIG. 2 is a view showing a state in which a formwork is installed on a gantry.
FIG. 3 is a view showing a state in which the reinforcing bars are assembled on the formwork.
FIG. 4 is a view showing a state in which the frame and the reinforcing bar are arranged in their original positions by raising and lowering the gantry.
FIG. 5 is a diagram showing an example in which a viaduct that is a new structure is installed immediately below a temporary girder that is an existing object.
[Explanation of symbols]
1 Viaduct
2 Temporary struts
3
4a
14 Column reinforcement
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13085398A JP3690463B2 (en) | 1998-05-13 | 1998-05-13 | Construction method of viaduct |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13085398A JP3690463B2 (en) | 1998-05-13 | 1998-05-13 | Construction method of viaduct |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11324345A JPH11324345A (en) | 1999-11-26 |
JP3690463B2 true JP3690463B2 (en) | 2005-08-31 |
Family
ID=15044232
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP13085398A Expired - Fee Related JP3690463B2 (en) | 1998-05-13 | 1998-05-13 | Construction method of viaduct |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3690463B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106555379A (en) * | 2015-09-30 | 2017-04-05 | 中铁十八局集团第四工程有限公司 | Pass through both wired elevated formation level Combined temporary bridge construction methods |
-
1998
- 1998-05-13 JP JP13085398A patent/JP3690463B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH11324345A (en) | 1999-11-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5045214B2 (en) | Column head construction method | |
JP2002256573A (en) | Foundation for existing foundation reinforcing steel tower and construction method for it | |
JP5405337B2 (en) | Construction method of railway RC ramen structure viaduct | |
KR100949601B1 (en) | Method for broadening width of existing bridge without Temporary road | |
JP2790986B2 (en) | Bridge pier construction method and construction method | |
KR101889064B1 (en) | Construction method of a long span bridge main tower | |
KR100580225B1 (en) | Upper structure raising method using bridge upper structure support and lift equipment and this | |
JP2006063718A (en) | Method of constructing overhung bridge using corrugated steel plate web | |
JP3841493B2 (en) | Construction method of viaduct using PCa concrete member | |
JP3690463B2 (en) | Construction method of viaduct | |
JP5003253B2 (en) | RC beam construction method | |
JPH10331272A (en) | Construction method of building frame constituted of reinforced concrete column, core wall, uppermost wall beam, and slab | |
JP2980567B2 (en) | How to replace the bearing device | |
KR100769552B1 (en) | Method of bent construction for temporary bridge | |
JP3644606B2 (en) | Installation method of formwork support in reverse placement method | |
KR20120124129A (en) | Non-supporting rc top down construction method using hybrid formwork beam | |
JP7134133B2 (en) | Bridge railing construction method | |
KR101194866B1 (en) | Rahmen bridge construction method using longitudinal and lateral steel member | |
JP3905021B2 (en) | Construction method of viaduct pier | |
JP3338240B2 (en) | Construction method for reinforced concrete structures | |
JP2961306B2 (en) | Work scaffold | |
JP3660657B2 (en) | Construction method of viaduct | |
KR101531839B1 (en) | Arch-Rahmen type tunnel construction method | |
JP2534009B2 (en) | Form support for overhang | |
JP2731907B2 (en) | Construction work method on sloping land |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040729 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050104 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050228 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050524 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050607 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
LAPS | Cancellation because of no payment of annual fees |