JP2008231700A - Flat anchorage device for post-tensioned type prestressed concrete floor slab, post-tensioned type prestressed concrete floor slab using the anchorage device, and construction method for the post-tensioned type prestressed concrete floor slab - Google Patents

Flat anchorage device for post-tensioned type prestressed concrete floor slab, post-tensioned type prestressed concrete floor slab using the anchorage device, and construction method for the post-tensioned type prestressed concrete floor slab Download PDF

Info

Publication number
JP2008231700A
JP2008231700A JP2007069501A JP2007069501A JP2008231700A JP 2008231700 A JP2008231700 A JP 2008231700A JP 2007069501 A JP2007069501 A JP 2007069501A JP 2007069501 A JP2007069501 A JP 2007069501A JP 2008231700 A JP2008231700 A JP 2008231700A
Authority
JP
Japan
Prior art keywords
floor slab
post
flat
flat cable
anchor head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007069501A
Other languages
Japanese (ja)
Inventor
Yoshitaka Nishida
吉孝 西田
Masato Ogura
正人 小倉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anderson Technology Corp
Original Assignee
Anderson Technology Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anderson Technology Corp filed Critical Anderson Technology Corp
Priority to JP2007069501A priority Critical patent/JP2008231700A/en
Publication of JP2008231700A publication Critical patent/JP2008231700A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a flat anchorage device for a post-tensioned type prestressed concrete floor slab, which can be easily worked and which enables the collective tensioning and anchoring of a plurality of prestressing steel strands, the post-tensioned type prestressed concrete floor slab using the anchorage device, and a construction method for the post-tensioned type prestressed concrete floor slab. <P>SOLUTION: This flat anchorage device for introducing prestress into a concrete floor slab by a post-tensioning system comprises an anchor head in which a plurality of wedge-mounting tapered holes for tensioning and anchoring the prestressing steel strands are drilled in such a manner that axis lines are orthogonal to a planar surface of the anchor head and parallel to one another, and a bearing plate which has the length of a trumpet-shaped pipe portion adjusted in such a manner as to correspond to the anchor head. In the construction method for the post-tensioned type prestressed concrete floor slab, the plurality of prestressing steel strands, which are pulled out in parallel from the anchor head by using the anchor head, are collectively tensioned and anchored by means of a jack capable of tensioning and anchoring them in the same direction at a time; and juxtaposed cable sheaths are serially connected together by means of a hose, so that grout can be injected. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本願発明は、ポストテンション方式PC床版を構築する際、PC鋼より線を緊張・定着するポストテンション方式PC床版用扁平型定着具のアンカーヘッド及び支圧板の構造、及び前記定着具を使用したポストテンション方式PC床版、並びに同ポストテンション方式PC床版の構築方法に関する。   The present invention uses a structure of an anchor head and a bearing plate of a flat type fixing device for a post tension type PC floor slab that tensions and fixes a strand of PC steel when constructing a post tension type PC floor slab, and the fixing device. The present invention relates to a post-tension type PC floor slab and a method for constructing the post-tension type PC floor slab.

床版等薄肉厚のコンクリート部材にプレストレスを導入する工法としては、扁平形状の定着具と扁平形状のケーブルシースを用い、前記扁平形状のケーブルシース内に挿入した複数本のPC鋼より線を前記扁平形状の定着具のトランペット状管部で扇状に開き、その先端をアンカーヘッドの長辺に沿って一列に穿設されたウエッジ装着用テーパ孔に挿通し、前記PC鋼より線をジャッキ等で緊張しながら前記テーパ孔の内壁とPC鋼より線間にウエッジを嵌入して、PC鋼より線を緊張・定着することにより前記コンクリート部材にプレストレスを導入するもの(図5参照)や、前記トランペット状管部で扇状に開かれた複数本のPC鋼より線を1本ごとに、支圧板上に一列に配設したグリップのウエッジ装着用テーパ孔にウエッジを嵌入して、前記PC鋼より線を1本ごとに緊張・定着して前記コンクリート部材にプレストレスを導入するもの(図6参照)が一般的であった。
そして前記ウエッジ装着用テーパ孔は、その先端部でPC鋼より線が折れ曲がることによってPC鋼より線やウエッジの定着作用が弱まることを考慮して扇形に開いた各PC鋼より線の中心軸からの開き角度と等しくなるような傾きを持って穿設され、また、支圧板とアンカーヘッドとの当接面が各PC鋼より線と直交するように曲面としたり、グリッドとの当接面ごとにその傾斜角が異なる傾斜面としたりすることがなされてきた。したがって、アンカーヘッドや支圧板の加工が容易でなく、コストがかかるばかりでなく、複数のPC鋼より線の緊張方向がそれぞれ異なるので、一本ごとにジャッキで緊張する必要があり、ポストテンション方式PC床版の構築に時間がかかるという問題があった。
As a method of introducing prestress into a thin-walled concrete member such as a floor slab, a flat fixing tool and a flat cable sheath are used, and a plurality of PC steel strands inserted into the flat cable sheath are connected. It opens like a fan in the trumpet-like tube part of the flat-shaped fixing tool, and the tip is inserted into a wedge mounting taper hole drilled in a line along the long side of the anchor head, and the PC steel strand is jacked or the like Inserting a wedge between the inner wall of the taper hole and the PC steel wire while tensioning, and introducing prestress into the concrete member by tensioning and fixing the wire from the PC steel (see FIG. 5), A plurality of PC steel strands opened in a fan shape at the trumpet-like tube section are inserted into the wedge mounting taper holes of the grips arranged in a row on the bearing plate. , Nervous and fixed for each one of the line the PC steel which prestressed in the concrete member (see FIG. 6) were common.
The wedge mounting taper hole is formed from the central axis of each PC steel strand that opens in a fan shape in consideration of the fact that the fixing action of the wire and wedge is weakened from the PC steel by bending the wire from the PC steel at the tip. It is perforated with an inclination equal to the opening angle of the plate, and the contact surface between the bearing plate and the anchor head is curved so that it is perpendicular to each PC steel wire, or each contact surface with the grid In some cases, the inclined surfaces have different inclination angles. Therefore, it is not easy to process the anchor head and bearing plate, and it is not only costly, but also the tension directions of the wires are different from those of multiple PC steels. There was a problem that it took time to construct a PC slab.

本願発明は、上記背景技術に鑑みて、加工が容易で、複数本のPC鋼より線の一括緊張を可能にするポストテンション方式PC床版用扁平型定着具、及び同定着具を用いたポストテンション方式PC床版、並びに同ポストテンション方式PC床版の構築方法を提供するものである。   In view of the above-mentioned background art, the present invention is a post-fixing type flat fixing device for a post-tension PC floor slab, which is easy to process and enables collective tension of a plurality of PC steel strands, and a post using an identification attachment The present invention provides a tension type PC floor slab and a method for constructing the post tension type PC floor slab.

本発明者らは、、上記課題を下記の手段によって解決した。
(1)緊張材のPC鋼より線3を緊張・定着するウエッジ装着用テーパ孔1aが複数穿設されてなる直方体状のアンカーヘッド1を備え、打設されたコンクリート床版にポストテンション方式によってプレストレスが導入されるポストテンション方式PC床版用扁平型定着具において、そのそれぞれのウエッジ装着用のテーパ孔1aが、いずれもその軸線をアンカーヘッド1の平面状の表面に対して直交させ互いに平行になるように穿設されてなることを特徴とするポストテンション方式PC床版用扁平型定着具。
(2)前記アンカーヘッドの複数のウエッジ装着用テーパ孔が、長方形状をなすアンカーヘッド表面の長辺に平行な直線上に等間隔に穿設されてなることを特徴とする前項(1)に記載のポストテンション方式PC床版用扁平型定着具。
(3)前記アンカーヘッド1に穿設されたウエッジ装着用テーパ孔1aの先端部でPC鋼より線3が内側に折り曲げられる角度αが、前記アンカーヘッド1の最外縁部のウエッジ装着用テーパ孔1aにおいても、該PC鋼より線3に許容される折り曲げ角度6°以内となるよう、支圧板2の支圧板部2aからケーブルシース結合部2cまでのトランペット状管部2bの長さが調整されてなることを前項(1)又は(2)に記載のポストテンション方式PC床版用扁平型定着具。
The present inventors have solved the above problems by the following means.
(1) It is provided with a rectangular parallelepiped anchor head 1 in which a plurality of wedge mounting taper holes 1a for tensioning and fixing a strand 3 of a strand of PC steel, which is a tension material, are provided. In the flat type fixing device for post-tension type PC floor slabs to which pre-stress is introduced, the respective taper holes 1a for mounting the wedges have their axes orthogonal to the planar surface of the anchor head 1 and are mutually connected. A flat-type fixing device for a post-tension type PC floor slab characterized by being drilled in parallel.
(2) In the above item (1), the plurality of wedge mounting taper holes of the anchor head are formed at equal intervals on a straight line parallel to the long side of the rectangular anchor head surface. A flat type fixing device for a post-tension type PC floor slab as described.
(3) The angle α at which the PC steel wire 3 is bent inward at the tip of the wedge mounting taper hole 1a formed in the anchor head 1 is the wedge mounting taper hole at the outermost edge of the anchor head 1 Also in 1a, the length of the trumpet tube portion 2b from the bearing plate portion 2a of the bearing plate 2 to the cable sheath coupling portion 2c is adjusted so that the bending angle allowed for the strand 3 of the PC steel is within 6 °. A flat-type fixing device for post-tension type PC floor slabs according to (1) or (2) above.

(4)前項(1)〜(3)のいずれか1項に記載のポストテンション方式PC床版用扁平定着具が、コンクリート床版内に埋設された扁平型ケーブルシースの両端に接続され、前記扁平型ケーブルシースに挿通された複数本のPC鋼より線を緊張・定着して、前記コンクリート床版にプレストレスを導入してなることを特徴とするポストテンション方式PC床版。   (4) The post-tension type PC floor slab flat fixing device according to any one of (1) to (3) is connected to both ends of a flat cable sheath embedded in a concrete floor slab, A post-tension type PC floor slab, wherein a plurality of PC steel strands inserted through a flat cable sheath are tensioned and fixed, and prestress is introduced into the concrete floor slab.

(5)前項(1)〜(3)のいずれか1項に記載のポストテンション方式PC床版用扁平定着具を、コンクリート床版6内に埋設された扁平型ケーブルシース5の両端に接続し、前記扁平型ケーブルシース5に挿通された複数本のPC鋼より線3をそれぞれアンカーヘッド1のウエッジ装着用テーパ孔1aから引き出して、前記アンカーヘッド1のウェッジ装着用テーパ孔1aにウエッジ4を嵌入して緊張した後、定着して前記コンクリート床版6にプレストレスを導入し、支圧板2のトランペット状管部2b及び扁平型ケーブルシース5内にグラウトを注入してコンクリート床版6とPC鋼より線3とを一体化することを特徴とするポストテンション方式PC床版の構築方法。
(6)前記扁平型ケーブルシース5内に挿通され、前記アンカーヘッド1の平面状の表面に対して直交させ互いに平行になるように穿設された複数のウエッジ装着用テーパ孔1aから引き出されて平行状態となっている複数本のPC鋼より線3の端部を、複数本のケーブルを把持して同一方向に同時に引張・緊張できるジャッキによって一度に緊張することを特徴とする前項(5)に記載のポストテンション方式PC床版の構築方法。
(5) Connect the flat tensioner for post-tension type PC floor slabs according to any one of (1) to (3) above to both ends of the flat cable sheath 5 embedded in the concrete floor slab 6 The plurality of PC steel strands 3 inserted through the flat cable sheath 5 are pulled out from the wedge mounting taper holes 1a of the anchor head 1 and the wedges 4 are inserted into the wedge mounting taper holes 1a of the anchor head 1. After inserting and tensioning, it is fixed and prestress is introduced into the concrete floor slab 6, and grout is injected into the trumpet tube portion 2 b and the flat cable sheath 5 of the bearing plate 2, and the concrete floor slab 6 and the PC A method for constructing a post-tension type PC floor slab characterized by integrating a steel stranded wire 3.
(6) It is inserted into the flat cable sheath 5 and pulled out from a plurality of wedge mounting taper holes 1a which are formed so as to be orthogonal to and parallel to the planar surface of the anchor head 1. The preceding item (5) characterized in that the end portions of a plurality of PC steel stranded wires 3 in parallel are tensioned at once by a jack capable of simultaneously gripping and tensioning a plurality of cables in the same direction. A construction method of a post-tension type PC floor slab described in 1.

(7)打設されたコンクリート床版6内に、複数の扁平型ケーブルシース5が並列して配設されたポストテンション方式のPC床版において、前記扁平型ケーブルシース5内に挿通されたPC鋼より線3が緊張・定着された後に行われる支圧板2のトランペット状管部2b内と前記扁平型ケーブルシース5内へのグラウト注入が、
第1の扁平型ケーブルシース5のグラウト注入側に接続された前記ポストテンション方式PC床版用扁平型定着具のグラウト注入口2dに圧送ポンプを接続し、この第1の扁平型ケーブルシースのグラウト排出側に接続された前記ポストテンション方式PC床版用扁平型定着具のグラウト排出口と第1の扁平型ケーブルシースに隣接する第2の扁平型ケーブルシースのグラウト注入側の前記ポストテンション方式PC床版用扁平型定着具のグラウト注入口とをホース7により直列に接続し、
さらに第3、第4……の扁平型ケーブルシース5……が配設される場合には、前記第1と第2の扁平型ケーブルシース5、5間の接続と同様の接続を繰り返すことによって、すべての扁平型ケーブルシース5……を直列に接続し、
そして接続の最後となった扁平型ケーブルシース5のグラウト排出側に接続された前記ポストテンション方式PC床版用扁平型定着具のグラウト排出口2dに真空ポンプを接続した後、前記真空ポンプにより前記複数の扁平型ケーブルシース内を減圧しながら、前記圧送ポンプを連続運転して、前記複数の扁平型ケーブルシース内に一度にグラウトを注入・充填することを特徴とする前項(5)又は(6)に記載のポストテンション方式PC床版の構築方法。
(7) In a post-tension type PC floor slab in which a plurality of flat cable sheaths 5 are arranged in parallel in the placed concrete floor slab 6, the PC inserted through the flat cable sheath 5 Grout injection into the trumpet-like tube portion 2b of the bearing plate 2 and the flat cable sheath 5 performed after the steel strand 3 is tensioned and fixed,
A pressure feed pump is connected to the grout inlet 2d of the flat tensioner for the post tension type PC floor slab connected to the grout injection side of the first flat cable sheath 5, and the grout of this first flat cable sheath is connected. The post tension type PC on the grout injection side of the second flat cable sheath adjacent to the grout discharge port of the flat type fixing device for the post tension type PC floor slab connected to the discharge side and the first flat type cable sheath. Connect the grout inlet of the flat fixing tool for floor slabs in series with the hose 7,
Further, when the third, fourth... Flat cable sheaths 5... Are arranged, the same connection as the connection between the first and second flat cable sheaths 5 and 5 is repeated. , Connect all flat cable sheaths 5 ... in series,
Then, after connecting a vacuum pump to the grout outlet 2d of the flat tension fixture for the post tension type PC floor slab connected to the grout discharge side of the flat cable sheath 5 which is the last connection, the vacuum pump is used to (5) or (6), wherein the pumping pump is continuously operated while the inside of the plurality of flat cable sheaths is decompressed, and grout is injected and filled into the plurality of flat cable sheaths at once. The construction method of the post-tension type PC floor slab described in).

〈1〉緊張材のPC鋼より線を緊張・定着するウエッジ装着用テーパ孔が複数穿設されてなる直方体状のアンカーヘッドを備え、打設されたコンクリート床版にポストテンション方式によってプレストレスが導入されるポストテンション方式PC床版用扁平型定着具において、そのそれぞれのウエッジ装着用のテーパ孔が、いずれもその軸線を、アンカーヘッド1の平面状の表面に対して直交させ互いに平行になるように穿設されているので、アンカーヘッドの加工が容易で、ポストテンション方式PC床版用扁平型定着具のコストダウンが図れる。
〈2〉前記アンカーヘッドの複数のウエッジ装着用テーパ孔が、いずれもその軸線を、アンカーヘッドの平面状の表面に対して直交させ互いに平行になるように穿設されていることから、その先端部でPC鋼より線が内側に折り曲げられるが、その角度αが前記アンカーヘッドの最外縁部のウエッジ装着用テーパ孔においても、該PC鋼より線に許容される折り曲げ角度6°以内となるよう支圧板のアンカーヘッド受け台部からケーブルシース結合部までのトランペット状管部の長さが調整されているので、前記PC鋼より線の引張強度としては、95%以上の定着効率[(定着されたときの緊張材の引張強度/緊張時の引張強度)×100]が保証される。
<1> A rectangular parallelepiped anchor head formed with a plurality of wedge mounting taper holes for tensioning and fixing the strands of PC steel strand of tension material. Prestress is applied to the placed concrete floor slab by the post tension method. In the flat type fixing device for the post tension type PC floor slab to be introduced, the taper holes for mounting the respective wedges are parallel to each other with their axes orthogonal to the planar surface of the anchor head 1. Therefore, the anchor head can be easily processed, and the cost of the flat type fixing device for the post tension type PC floor slab can be reduced.
<2> Since the plurality of wedge mounting taper holes of the anchor head are all drilled so that their axes are perpendicular to and parallel to the planar surface of the anchor head, The PC steel wire is bent inward at the portion, and the angle α is also within the bending angle of 6 ° allowed for the PC steel wire in the wedge mounting taper hole at the outermost edge of the anchor head. Since the length of the trumpet-like tube part from the anchor head cradle part of the bearing plate to the cable sheath connection part is adjusted, the tensile strength of the PC steel strand is 95% or more of fixing efficiency [(fixed Tensile strength of tensile material at the time of tension / tensile strength during tension) × 100] is guaranteed.

〈3〉前記アンカーヘッドに穿設される複数のウエッジ装着用テーパ孔が、いずれもその軸線をアンカーヘッドの平面状の表面に対して直交し互いに平行になるように穿設されているので、前記複数のウエッジ装着用テーパ孔からは複数本のPC鋼より線が平行状態で引き出されることから、複数本のPC鋼より線を把持して、同一方向に同時に緊張・定着できるジャッキを用いて一度に緊張することができ、PC鋼より線緊張時間の短縮と省力化が図れ、ポストテンション方式PC床版用扁平型定着具のコストダウンと相まってPC床版構築経費の低廉化が図れる。
〈4〉打設されたコンクリート床版内に、複数の扁平型ケーブルシースが並列して配設されたポストテンション方式のPC床版において、前記扁平型ケーブルシース内に挿通されたPC鋼より線が緊張・定着された後に行われる支圧板のトランペット状管部内と前記扁平型ケーブルシース内へのグラウト注入が、隣り合うポストテンション方式PC床版用扁平型定着具のグラウト注入口を相互にホースで連結することによって、複数本のケーブルシースを直列に接続するとともに、その先端となるポストテンション方式PC床版用扁平型定着具のグラウト注入口に圧送ポンプを、終端となるポストテンション方式PC床版用扁平型定着具のグラウト排出口に真空ポンプ接続し、前記真空ポンプにより前記複数の扁平型ケーブルシース内を減圧しながら、前記圧送ポンプを連続運転して、前記複数の扁平型ケーブルシース内に一度にグラウトを注入・充填するので、ポストテンション方式PC床版の構築の省力化と工期の大幅な短縮ができ、コストの大幅削減が図れる。
また、低粘性又は超低粘性のグラウトを使用することにより一度に注入できる距離を伸ばすことも可能になる。
<3> Since the plurality of wedge mounting taper holes drilled in the anchor head are drilled so that their axes are perpendicular to and parallel to the planar surface of the anchor head, Since a plurality of PC steel wires are drawn out in parallel from the plurality of wedge mounting taper holes, using a jack that can hold a plurality of PC steel wires and simultaneously tension and fix in the same direction. It can be tensioned at once, and the wire tension time can be shortened and labor-saving can be achieved compared with PC steel, and the cost of building a PC slab can be reduced in combination with the cost reduction of the flat type fixing device for a post-tension PC slab.
<4> In a post-tension type PC floor slab in which a plurality of flat cable sheaths are arranged in parallel in a placed concrete floor slab, a PC steel strand inserted through the flat cable sheath The grout injection into the trumpet tube portion of the bearing plate and the flat cable sheath, which is performed after the tension is fixed and fixed, is hose between the grout injection ports of the adjacent post tension type PC floor slab flat fixing tools By connecting them together, a plurality of cable sheaths are connected in series, and a pressure feed pump is connected to the grout inlet of a flat type fixing device for a post tension type PC floor slab at the tip, and a post tension type PC floor at the end A vacuum pump is connected to the grout outlet of the flat fixing device for printing plates, and the inside of the flat cable sheaths is depressurized by the vacuum pump. However, by continuously operating the pumping pump and injecting and filling grout into the plurality of flat cable sheaths at once, labor saving in construction of a post-tension type PC floor slab and a drastic reduction in construction period can be achieved. Costs can be greatly reduced.
It is also possible to extend the distance that can be injected at one time by using a low-viscosity or ultra-low-viscosity grout.

本願発明のポストテンション方式PC床版用扁平型定着具、及び同定着具を使用したポストテンション方式PC床版、並びに同ポストテンション方式PC床版の構築方法の実施の形態を実施例の図に基づいて説明する。
図1は本願発明のポストテンション方式PC床版用扁平型定着具の使用状態を示す断面図、図2はアンカーヘッドと支圧板の上面図及び断面図、図3は横一列に並ぶ複数本のケーブルを同一方向に同時に引張・緊張できるジャッキの外観斜視図、図4は扁平型ケーブルシースが複数本並列配置されたPC床版へのグラウト注入方法の説明図である。
図において1はアンカーヘッド、1aはウエッジ装着用テーパ孔、2は支圧板、2aは支圧板部、2bはトランペット状管部、2cはケーブルシース結合部、2dはグラウト注入口(又は排出口)、3はPC鋼より線、4はウエッジ、5は扁平型ケーブルシース、6はコンクリート床版、7は連結ホースを示す。
The embodiment of the flat type fixing device for the post tension type PC floor slab of the present invention, the post tension type PC floor slab using the identification attachment, and the construction method of the post tension type PC floor slab are shown in the examples. This will be explained based on.
FIG. 1 is a cross-sectional view showing a use state of a flat type fixing device for a post-tension type PC floor slab according to the present invention, FIG. 2 is a top view and cross-sectional view of an anchor head and a bearing plate, and FIG. FIG. 4 is an explanatory view of a method for injecting grout into a PC floor slab in which a plurality of flat cable sheaths are arranged in parallel.
In the drawing, 1 is an anchor head, 1a is a wedge mounting taper hole, 2 is a pressure plate, 2a is a pressure plate, 2b is a trumpet tube portion, 2c is a cable sheath coupling portion, and 2d is a grout inlet (or outlet). 3 is a PC steel strand, 4 is a wedge, 5 is a flat cable sheath, 6 is a concrete floor slab, and 7 is a connecting hose.

本願発明のポストテンション方式PC床版用扁平型定着具は、図2(a)(b)に示すアンカーヘッド1と、図2(c)(d)に示す支圧板2とで構成される。
前記アンカーヘッド1は、図2(a)(b)に見られるように、直方体又はその各隅角部に丸みを持たせてなる駆体に複数のウエッジ装着用テーパ孔1a……が、いずれもその軸線をアンカーヘッド1の平面状の表面に対して直交させ互いに平行になるように穿設されている。
また、支圧板2は、図2(c)(d)に示すように小判形のPC鋼より線挿通孔を有するトランペット状管部2bの上端部の外周に、幅広の平板の支圧板部2aを一体的に設けてなり、この支圧板部2aを介してPC鋼より線3の緊張をコンクリート床版6にプレストレスとして導入されるように構成されている。そして、前記アンカーヘッド1によってPC鋼より線3が緊張・定着された際、前記アンカーヘッド1に穿設されたウエッジ装着用テーパ孔1a……が、いずれもその軸線をアンカーヘッドの平面状の表面に対して直交させ互いに平行になるよう穿設されていることから、支圧板2のケーブルシース結合部2cからトランペット状管部2b内で扇状に開かれたPC鋼より線3が、前記ウエッジ装着用テーパ孔1aの先端部で内側に折り曲げられるが、その角度αが最も大きくなる前記アンカーヘッド1の最外縁部のウエッジ装着用テーパ孔1aにおいても、該PC鋼より線3に許容される折り曲げ角度が6°以内となるように前記支圧板2の支圧板部2aからケーブルシース結合部2cまでのトランペット状管部2bの長さが調整されている。
A flat type fixing device for a post tension type PC floor slab according to the present invention is composed of an anchor head 1 shown in FIGS. 2 (a) and 2 (b) and a bearing plate 2 shown in FIGS. 2 (c) and 2 (d).
As shown in FIGS. 2 (a) and 2 (b), the anchor head 1 has a rectangular parallelepiped or a plurality of wedge mounting taper holes 1a. Are also drilled so that their axes are perpendicular to the planar surface of the anchor head 1 and are parallel to each other.
Further, as shown in FIGS. 2 (c) and 2 (d), the bearing plate 2 has a wide flat bearing plate 2 a on the outer periphery of the upper end portion of the trumpet-like tube portion 2 b having a wire insertion hole made of oval PC steel. The tension of the PC steel strand 3 is introduced into the concrete floor slab 6 as prestress through the bearing plate 2a. When the anchor steel wire 3 is tensioned and fixed by the anchor head 1, the wedge mounting taper holes 1 a pierced in the anchor head 1 both have their axes aligned with the planar shape of the anchor head. Since the PC steel strand 3 opened in a fan shape in the trumpet-like tube portion 2b from the cable sheath coupling portion 2c of the bearing plate 2 is formed so as to be perpendicular to the surface and parallel to each other, the wedge Although it is bent inward at the tip of the mounting taper hole 1a, the wedge mounting taper hole 1a at the outermost edge of the anchor head 1 where the angle α is the largest is also allowed for the strand 3 of the PC steel. The length of the trumpet-like tube portion 2b from the pressure plate 2a to the cable sheath coupling portion 2c of the pressure plate 2 is adjusted so that the bending angle is within 6 °.

本願発明のポストテンション方式PC床版用扁平定着具は、図1に示すように、支圧板2のケーブルシース結合部2cに扁平型ケーブルシース5を結合・接続してコンクリート床版6内に埋設され、前記扁平型ケーブルシース5に挿通された複数本のPC鋼より線3を、前記支圧板2の支圧板部2aのアンカーヘッド受け台上に配設したアンカーヘッド1の複数のウエッジ装着用テーパ孔1a……にそれぞれ1本ずつ挿通して緊張した後、前記アンカーヘッド1の各ウェッジ装着用テーパ孔1a……にウエッジ4を嵌入して定着するものである。
従来、このPC鋼より線の緊張・定着作業は、支圧板の端面が曲面になっていたために、前記複数本のPC鋼より線の緊張方向が1本ずつ異なる(図5、図6参照)ため、それぞれの方向に1本ずつ緊張して定着せざるを得なかったが、本願発明のアンカーヘッド1は、そののウエッジ装着用テーパ孔1aを、その軸線がアンカーヘッド1の平面状の表面に直交し互いに平行になるよう穿設し、前記ウエッジ挿通孔1aから引き出されるPC鋼より線3が互いに平行状態となり、同一方向に緊張できるので、一括緊張用ジャッキを使用して、複数本のPC鋼より線の緊張・定着が一度に行え、ポストテンション方式床版の両端部で使用され、作業効率のよいポストテンション方式床版の構築に寄与している。
このように両端に配設されたポストテンション方式PC床版用扁平型定着具で緊張・定着されたPC鋼より線3によってプレストレスが導入されたコンクリート床版6は、さらに前記支圧板2のトランペット状管部2b及び扁平型ケーブルシース5内にセメントグラウトが注入されて、前記セメントグラウトが硬化した後は、コンクリート床版6とPC鋼より線3とが一体化され、かつセメントの高アルカリ性によって緊張材が腐食から守られ、前記コンクリート床版6に導入されたプレストレスは安定して保持されることになる。
As shown in FIG. 1, the flat fixing device for a post-tension type PC floor slab of the present invention is embedded in a concrete floor slab by connecting and connecting a flat cable sheath 5 to a cable sheath connecting portion 2c of a bearing plate 2. For mounting a plurality of wedges of the anchor head 1 in which a plurality of PC steel strands 3 inserted through the flat cable sheath 5 are arranged on the anchor head cradle of the bearing plate 2a of the bearing plate 2 One is inserted into each of the taper holes 1a, and is tensioned. Then, the wedge 4 is inserted into each wedge mounting taper hole 1a of the anchor head 1 and fixed.
Conventionally, the tension / fixing operation of the wire from the PC steel is different in the tension direction of the wire from the plurality of PC steels one by one because the end surface of the bearing plate is curved (see FIGS. 5 and 6). For this reason, the anchor head 1 of the present invention has to be fixed by tensioning one by one in each direction. However, the anchor head 1 of the present invention has its wedge mounting taper hole 1a, the axis of which is a planar surface of the anchor head 1. Since the PC steel wires 3 drawn out from the wedge insertion holes 1a are parallel to each other and can be tensioned in the same direction, a plurality of jacks for collective tension can be used. PC steel strands can be tensioned and fixed at a time and used at both ends of post-tension type floor slabs, contributing to the construction of post-tension type floor slabs with high work efficiency.
The concrete floor slab 6 in which prestress is introduced by the PC steel strand 3 that is tensioned and fixed by the flat type fixing device for the post-tension type PC floor slab arranged at both ends in this manner is further provided on the bearing plate 2. After cement grout is injected into the trumpet-like tube portion 2b and the flat cable sheath 5 and the cement grout is hardened, the concrete floor slab 6 and the PC steel wire 3 are integrated, and the high alkalinity of the cement. Thus, the tendon is protected from corrosion, and the prestress introduced into the concrete floor slab 6 is stably held.

本願発明のポストテンション方式PC床版用扁平型定着具を用いたポストテンション方式PC床版の構築方法においては、前記アンカーヘッド1の複数のウエッジ装着用テーパ孔1a……が、いずれもその軸線をアンカーヘッド1の平面状の表面に対して直交させ互いに平行になるように穿設されているので、該ウエッジ装着用テーパ孔1a……からそれぞれ引き出される複数本のPC鋼より線3の先端は平行状態になる。したがって、横一列に並ぶ複数本のケーブルを把持して同一方向に同時に引張・緊張できる図3に示すような外形構造のジャッキを用いれば、複数本のPC鋼より線3を一度に緊張でき、PC鋼より線3の緊張時間の短縮と省力化が図れ、定着具のコストダウンと相まってPC床版構築経費の低廉化が図れる。
なお、図3に示した横一列に並ぶ複数本のケーブルを把持して同一方向に同時に引張・緊張できるジャッキは、本発明のポストテンション方式PC床版の構築方法を実施するに当たってあらたに製作したものである。
In the construction method of the post tension type PC floor slab using the flat type fixing device for the post tension type PC floor slab according to the present invention, the plurality of wedge mounting taper holes 1a... Are formed so as to be orthogonal to and parallel to the planar surface of the anchor head 1, so that the tips of the plurality of PC steel strands 3 drawn from the wedge mounting taper holes 1 a. Become parallel. Therefore, by using a jack having an external structure as shown in FIG. 3 that can grip and hold a plurality of cables arranged in a horizontal row and simultaneously pull and tension in the same direction, a plurality of PC steel strands 3 can be tensioned at once, PC steel strand 3 can be shortened and labor-saving can be achieved, and the cost of building a PC slab can be reduced in combination with the cost reduction of the fixing tool.
Note that the jack shown in FIG. 3 that can hold a plurality of cables arranged in a row and can be pulled and tensioned in the same direction at the same time was newly manufactured to implement the post-tension type PC floor slab construction method of the present invention. Is.

ポストテンション方式PC床版においては、図4に示すように、その両端に前記ポストテンション方式PC床版用扁平型定着具が結合された扁平型ケーブルシース5が複数本コンクリート床版6内に並列して埋設され、そして前記ケーブルシース5内に挿通されたPC鋼より線3が前記ポストテンション方式PC床版用扁平型定着具によって緊張・定着され、その後にコンクリート床版6内に並列して埋設された複数の支圧板2……のトランペット状管部2b及び扁平型ケーブルシース5……内にそれぞれグラウトを注入して、コンクリート床版6とPC鋼より線3とを一体化するが、本願発明ではこのグラウト注入を次の手順によって行うものとしている。
すなわち、
[1]並列配置された複数の扁平型ケーブルシース5……のいずれかを第1の扁平型ケーブルシースとし、この第1の扁平型ケーブルシース5のグラウト注入側に接続されたポストテンション方式PC床版用扁平型定着具のグラウト注入口に圧送ポンプを接続し、
[2]この第1の扁平型ケーブルシースのグラウト排出側に接続されたポストテンション方式PC床版用扁平型定着具のグラウト排出口と第1の扁平型ケーブルシースに隣接する第2の扁平型ケーブルシースのグラウト注入側のポストテンション方式PC床版用扁平型定着具のグラウト注入口ををホース7により直列に接続し、
[3]さらに第3、第4……の扁平型ケーブルシースが配設される場合には、前記第1と第2の扁平型ケーブルシース間の接続と同様の接続を繰り返すことによって、すべての扁平型ケーブルシースを直列に接続し、
[4]そして接続の最後となった扁平型ケーブルシース5のグラウト排出側に接続されたポストテンション方式PC床版用扁平型定着具のグラウト排出口に真空ポンプを接続した後、
[5]前記真空ポンプにより前記複数の扁平型ケーブルシース5……内を減圧しながら、前記圧送ポンプを連続運転して、前記複数本の扁平型ケーブルシース5……内に一度にグラウトを注入・充填する。
このグラウト注入方法の採用により、ポストテンション方式PC床版の構築の省力化と工期の大幅な短縮ができ、コストの大幅削減が図れる。また、低粘性又は超低粘性のグラウトを使用することにより一度に注入できる距離を伸ばすことも可能になる。
なお、我が国では、このグラウト注入の省力化を図るため、あらかじめ遅硬性樹脂のグラウトをPC鋼より線とケーブルシースとの間に充填し、作業現場でのグラウト注入を不要にしたプレグラウトケーブルの使用も行われてきたが、この遅硬性樹脂グラウトの硬化年数が明確でなく懸念がもたれていることを考慮すれば、本願発明のポストテンションPC床版構築方法は、前記プレグラウトケーブルを使用した工法の省力効果を凌駕する技術的、経済的効果が得られる。
In the post-tension type PC floor slab, as shown in FIG. 4, a plurality of flat type cable sheaths 5, in which the flat fixing members for the post-tension type PC floor slab are coupled to both ends, are arranged in parallel in the concrete floor slab 6. The PC steel strand 3 embedded in the cable sheath 5 is tensioned and fixed by the flat type fixing device for the post-tension type PC floor slab, and then placed in parallel in the concrete floor slab 6 A grout is injected into each of the trumpet-like tube portion 2b and the flat cable sheath 5 of the plurality of bearing plates 2 embedded, and the concrete slab 6 and the PC steel wire 3 are integrated. In the present invention, this grout injection is performed by the following procedure.
That is,
[1] A post tension type PC connected to the grout injection side of the first flat cable sheath 5 by using any one of the plurality of flat cable sheaths 5... Arranged in parallel as the first flat cable sheath. Connect the pump to the grout inlet of the flat type fixing device for floor slab,
[2] A second flat type adjacent to the grout discharge port of the flat fixing device for a post-tension type PC floor slab connected to the grout discharge side of the first flat cable sheath and the first flat cable sheath. Connect the grout inlet of the flat type fixing device for post-tension type PC floor slabs on the grout injection side of the cable sheath with the hose 7 in series.
[3] When third, fourth,... Flat cable sheaths are further provided, the same connection as the connection between the first and second flat cable sheaths is repeated, so that all Connect flat cable sheaths in series,
[4] After connecting the vacuum pump to the grout outlet of the flat type fixing device for the post tension type PC floor slab connected to the grout discharge side of the flat cable sheath 5 which is the last connection,
[5] The vacuum pump continuously operates the pressure-feed pump while depressurizing the plurality of flat cable sheaths 5... And the grout is injected into the plurality of flat cable sheaths 5. -Fill.
By adopting this grout injection method, it is possible to save labor for construction of a post-tension type PC floor slab and to drastically reduce the construction period, thereby greatly reducing the cost. It is also possible to extend the distance that can be injected at one time by using a low-viscosity or ultra-low-viscosity grout.
In Japan, in order to save labor for this grout injection, the use of a pre-grout cable in which a grout of slow-hardening resin is filled in advance between the PC steel strand and the cable sheath, eliminating the need for grout injection at the work site. However, in consideration of the fact that the curing time of the slow-hardening resin grout is not clear and has concerns, the post-tension PC floor slab construction method of the present invention is a construction method using the pre-grout cable. The technical and economic effects surpass the labor saving effect.

本願発明のポストテンション方式PC床版用扁平型定着具の使用状態を示す断面図Sectional drawing which shows the use condition of the flat type fixing device for post tension type PC floor slabs of this invention 本願発明のアンカーヘッドと支圧板の上面図及び断面図Top view and sectional view of anchor head and bearing plate of the present invention 横一列に並ぶ複数本のケーブルを同一方向に同時に引張・緊張できるジャッキの外観斜視図External perspective view of a jack that can pull and tension multiple cables arranged in a row in the same direction at the same time 扁平型ケーブルシースが複数本並列配置されたポストテンション方式PC床版へのグラウト注入方法の説明図Explanatory drawing of grout injection method to post tension type PC floor slab in which multiple flat cable sheaths are arranged in parallel 従来のアンカーヘッドを用いた定着具の外観図External view of a fixing device using a conventional anchor head 従来のウエッジ装着用グリップを用いた定着具の外観図External view of a fixing device using a conventional wedge mounting grip

符号の説明Explanation of symbols

1:アンカーヘッド
1a;ウエッジ装着用テーパ孔
2:支圧板
2a:支圧板部
2b;トランペット状管部
2c:ケーブルシース結合部
2d:グラウト注入口(又は排出口)
3:PC鋼より線
4:ウエッジ
5:扁平型ケーブルシース
6:コンクリート床版
7:ホース
1: Anchor head 1a; wedge mounting taper hole 2: bearing plate 2a: bearing plate portion 2b; trumpet-like tube portion 2c: cable sheath coupling portion 2d: grout inlet (or outlet)
3: Stranded PC steel 4: Wedge 5: Flat cable sheath 6: Concrete slab 7: Hose

Claims (7)

緊張材のPC鋼より線3を緊張・定着するウエッジ装着用テーパ孔1aが複数穿設されてなる直方体状のアンカーヘッド1を備え、打設されたコンクリート床版にポストテンション方式によってプレストレスが導入されるポストテンション方式PC床版用扁平型定着具において、そのそれぞれのウエッジ装着用のテーパ孔1aが、いずれもその軸線をアンカーヘッド1の平面状の表面に対して直交させ互いに平行になるように穿設されてなることを特徴とするポストテンション方式PC床版用扁平型定着具。   It is equipped with a rectangular parallelepiped anchor head 1 in which a plurality of wedge mounting taper holes 1a for tensioning and fixing a strand 3 of PC steel, which is a tendon material, are provided, and prestress is applied to the placed concrete floor slab by a post tension method. In the flat fixing device for the post tension type PC floor slab to be introduced, the respective taper holes 1a for mounting the wedges are parallel to each other with their axes orthogonal to the planar surface of the anchor head 1. A flat-type fixing device for a post-tension type PC floor slab characterized by being perforated as described above. 前記アンカーヘッド1の複数のウエッジ装着用テーパ孔1aが、長方形状をなすアンカーヘッド1の表面の長辺に平行な直線上に等間隔で穿設されてなることを特徴とする請求項1に記載のポストテンション方式PC床版用扁平型定着具。   The plurality of wedge mounting taper holes 1a of the anchor head 1 are formed at equal intervals on a straight line parallel to the long side of the surface of the anchor head 1 having a rectangular shape. The flat type fixing device for post-tension type PC floor slabs as described. 前記アンカーヘッド1に穿設されたウエッジ装着用テーパ孔1aの先端部でPC鋼より線3が内側に折り曲げられる角度αが、前記アンカーヘッド1の最外縁部のウエッジ装着用テーパ孔1aにおいても、該PC鋼より線3に許容される折り曲げ角度6°以内となるよう、支圧板2の支圧板部2aからケーブルシース結合部2cまでのトランペット状管部2bの長さが調整されてなることを特徴とする請求項1又は2に記載のポストテンション方式PC床版用扁平型定着具。   The angle α at which the PC steel strand 3 is bent inward at the tip of the wedge mounting taper hole 1a formed in the anchor head 1 is also in the wedge mounting taper hole 1a at the outermost edge of the anchor head 1. The length of the trumpet tube portion 2b from the bearing plate 2a of the bearing plate 2 to the cable sheath coupling portion 2c is adjusted so that the bending angle allowed for the PC steel wire 3 is within 6 °. The flat type fixing device for post tension type PC floor slabs according to claim 1 or 2. 請求項1〜3のいずれか1項に記載のポストテンション方式PC床版用扁平定着具が、コンクリート床版6内に埋設された扁平型ケーブルシース5の両端に接続され、前記扁平型ケーブルシース5に挿通された複数本のPC鋼より線3を緊張・定着して、前記コンクリート床版6にプレストレスを導入してなることを特徴とするポストテンション方式PC床版。   The flat fixing device for a post-tension PC floor slab according to any one of claims 1 to 3 is connected to both ends of a flat cable sheath 5 embedded in a concrete floor slab 6, and the flat cable sheath A post-tension type PC floor slab comprising a plurality of PC steel strands inserted through 5 and tensioned and fixed to introduce a prestress into the concrete floor slab 6. 請求項1〜3のいずれか1項に記載のポストテンション方式PC床版用扁平定着具を、コンクリート床版6内に埋設された扁平型ケーブルシース5の両端に接続し、前記扁平型ケーブルシース5に挿通された複数本のPC鋼より線3をそれぞれアンカーヘッド1のウエッジ装着用テーパ孔1aから引き出して、前記アンカーヘッド1のウェッジ装着用テーパ孔1aにウエッジ4を嵌入して緊張した後、定着して前記コンクリート床版6にプレストレスを導入し、支圧板2のトランペット状管部2b及び扁平型ケーブルシース5内にグラウトを注入してコンクリート床版6とPC鋼より線3とを一体化することを特徴とするポストテンション方式PC床版の構築方法。   A flat fixing device for a post-tension type PC floor slab according to any one of claims 1 to 3 is connected to both ends of a flat cable sheath 5 embedded in a concrete floor slab 6, and the flat cable sheath A plurality of PC steel strands 3 inserted through 5 are respectively pulled out from the wedge mounting taper holes 1a of the anchor head 1, and the wedges 4 are inserted into the wedge mounting taper holes 1a of the anchor head 1 to be tensioned. Then, prestress is introduced into the concrete floor slab 6 after fixing, and grout is injected into the trumpet-like tube portion 2b of the bearing plate 2 and the flat cable sheath 5 so that the concrete floor slab 6 and the PC steel strand 3 are connected. A construction method of a post-tension type PC floor slab characterized by integration. 前記扁平型ケーブルシース5内に挿通され、前記アンカーヘッド1の平面状の表面に対して直交させ互いに平行になるように穿設された複数のウエッジ装着用テーパ孔1aから引き出されて平行状態となっている複数本のPC鋼より線3の端部を、複数本のケーブルを把持して同一方向に同時に引張・緊張できるジャッキによって一度に緊張することを特徴とする請求項5に記載のポストテンション方式PC床版の構築方法。   Inserted into the flat cable sheath 5 and drawn out from a plurality of wedge mounting taper holes 1a that are perpendicular to the planar surface of the anchor head 1 and parallel to each other. 6. The post according to claim 5, wherein the ends of the plurality of PC steel stranded wires 3 are tensioned at once by a jack capable of simultaneously grasping the plurality of cables and pulling and tensioning them simultaneously in the same direction. Construction method of tension type PC floor slab. 打設されたコンクリート床版6内に、複数の扁平型ケーブルシース5が並列して配設されたポストテンション方式のPC床版において、前記扁平型ケーブルシース5内に挿通されたPC鋼より線3が緊張・定着された後に行われる支圧板2のトランペット状管部2b内と前記扁平型ケーブルシース5内へのグラウト注入が、
第1の扁平型ケーブルシース5のグラウト注入側に接続された前記ポストテンション方式PC床版用扁平型定着具のグラウト注入口2dに圧送ポンプを接続し、この第1の扁平型ケーブルシースのグラウト排出側に接続された前記ポストテンション方式PC床版用扁平型定着具のグラウト排出口と第1の扁平型ケーブルシースに隣接する第2の扁平型ケーブルシースのグラウト注入側の前記ポストテンション方式PC床版用扁平型定着具のグラウト注入口とをホース7により直列に接続し、
さらに第3、第4……の扁平型ケーブルシース5……が配設される場合には、前記第1と第2の扁平型ケーブルシース5、5間の接続と同様の接続を繰り返すことによって、すべての扁平型ケーブルシース5……を直列に接続し、
そして接続の最後となった扁平型ケーブルシース5のグラウト排出側に接続された前記ポストテンション方式PC床版用扁平型定着具のグラウト排出口2dに真空ポンプを接続した後、前記真空ポンプにより前記複数の扁平型ケーブルシース内を減圧しながら、前記圧送ポンプを連続運転して、前記複数の扁平型ケーブルシース内に一度にグラウトを注入・充填することを特徴とする請求項5又は6に記載のポストテンション方式PC床版の構築方法。
In a post-tension type PC floor slab in which a plurality of flat cable sheaths 5 are arranged in parallel in a cast concrete floor slab 6, a PC steel stranded wire inserted into the flat cable sheath 5 is used. Grout injection into the trumpet-like tube portion 2b of the bearing plate 2 and the flat cable sheath 5 performed after the tension 3 is tensioned and fixed,
A pressure feed pump is connected to the grout inlet 2d of the flat tensioner for the post tension type PC floor slab connected to the grout injection side of the first flat cable sheath 5, and the grout of this first flat cable sheath is connected. The post tension type PC on the grout injection side of the second flat cable sheath adjacent to the grout discharge port of the flat type fixing device for the post tension type PC floor slab connected to the discharge side and the first flat type cable sheath. Connect the grout inlet of the flat fixing tool for floor slabs in series with the hose 7,
Further, when the third, fourth... Flat cable sheaths 5... Are arranged, the same connection as the connection between the first and second flat cable sheaths 5 and 5 is repeated. , Connect all flat cable sheaths 5 ... in series,
Then, after connecting a vacuum pump to the grout outlet 2d of the flat tension fixture for the post tension type PC floor slab connected to the grout discharge side of the flat cable sheath 5 which is the last connection, the vacuum pump is used to 7. The grout is injected and filled at a time into the plurality of flat cable sheaths by continuously operating the pressure pump while reducing the pressure in the plurality of flat cable sheaths. Post-tension PC floor slab construction method.
JP2007069501A 2007-03-16 2007-03-16 Flat anchorage device for post-tensioned type prestressed concrete floor slab, post-tensioned type prestressed concrete floor slab using the anchorage device, and construction method for the post-tensioned type prestressed concrete floor slab Pending JP2008231700A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007069501A JP2008231700A (en) 2007-03-16 2007-03-16 Flat anchorage device for post-tensioned type prestressed concrete floor slab, post-tensioned type prestressed concrete floor slab using the anchorage device, and construction method for the post-tensioned type prestressed concrete floor slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007069501A JP2008231700A (en) 2007-03-16 2007-03-16 Flat anchorage device for post-tensioned type prestressed concrete floor slab, post-tensioned type prestressed concrete floor slab using the anchorage device, and construction method for the post-tensioned type prestressed concrete floor slab

Publications (1)

Publication Number Publication Date
JP2008231700A true JP2008231700A (en) 2008-10-02

Family

ID=39904837

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007069501A Pending JP2008231700A (en) 2007-03-16 2007-03-16 Flat anchorage device for post-tensioned type prestressed concrete floor slab, post-tensioned type prestressed concrete floor slab using the anchorage device, and construction method for the post-tensioned type prestressed concrete floor slab

Country Status (1)

Country Link
JP (1) JP2008231700A (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725113B (en) * 2009-12-08 2011-02-09 中铁大桥(郑州)缆索有限公司 Two arm-brace stretching method of arc bridge tie bar cable
CN102261041A (en) * 2011-05-24 2011-11-30 中铁三局集团有限公司 End part fixing device of pre-buried rubber tube of post-tensioned prestressed bridge
CN102767287A (en) * 2012-07-05 2012-11-07 北京交通大学 Prestress anchor sealing device
CN103009478A (en) * 2012-12-21 2013-04-03 中铁九局集团有限公司桥梁分公司 Tensioning locking and lossless extending device
CN103225403A (en) * 2013-05-10 2013-07-31 史东生 Method for installing elastic supporting and lifting devices by adopting prestressing technique
CN103410329A (en) * 2013-08-30 2013-11-27 南通八建集团有限公司 Large-span basement concrete roof structure flat tube bonded prestressing force construction method
CN103726447A (en) * 2013-12-20 2014-04-16 中交二航局第四工程有限公司 Method and system for secondary tensioning of low-retraction anchorage system vertical prestressed steel strands
CN104452596A (en) * 2014-11-22 2015-03-25 安徽金星预应力工程技术有限公司 Arc-shaped flat anchorage device for bridge
CN107313556A (en) * 2017-07-31 2017-11-03 中国十七冶集团有限公司 A kind of post-stressed steel strand wires flat anchorage
CN110396927A (en) * 2019-07-08 2019-11-01 中建三局第二建设工程有限责任公司 For bridge tower transverse direction bonded prestress rod iron anchoring assembly and construction method
CN110725547A (en) * 2019-10-17 2020-01-24 柳州欧维姆机械股份有限公司 Compact steel strand inhaul cable and manufacturing method thereof
CN112195782A (en) * 2020-09-09 2021-01-08 马鞍山拓锐金属表面技术有限公司 Anticorrosive melting device of steel strand wires ground tackle
CN112554560A (en) * 2020-11-13 2021-03-26 云南建投第六建设有限公司 Post-tensioning method prestress construction method for flat slab structure
CN113373820A (en) * 2021-07-07 2021-09-10 浙江工业职业技术学院 Bridge prestress tension construction method
CN114717941A (en) * 2022-02-21 2022-07-08 中交路桥建设有限公司 Tensioning method for vertical prestressed steel strand of concrete continuous beam
CN114961273A (en) * 2022-05-14 2022-08-30 中国水利水电第七工程局有限公司 Prestressed steering tensioning construction method in narrow space
JP2022166493A (en) * 2021-04-21 2022-11-02 飛島建設株式会社 Pc steel material ventilation decompression rust prevention method and pc structure construction method using the same

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725113B (en) * 2009-12-08 2011-02-09 中铁大桥(郑州)缆索有限公司 Two arm-brace stretching method of arc bridge tie bar cable
CN102261041A (en) * 2011-05-24 2011-11-30 中铁三局集团有限公司 End part fixing device of pre-buried rubber tube of post-tensioned prestressed bridge
CN102261041B (en) * 2011-05-24 2013-07-17 中铁三局集团有限公司 End part fixing device of pre-buried rubber tube of post-tensioned prestressed bridge
CN102767287A (en) * 2012-07-05 2012-11-07 北京交通大学 Prestress anchor sealing device
CN102767287B (en) * 2012-07-05 2015-08-05 北京交通大学 A kind of prestressing force sealing off and covering anchorage instrument
CN103009478A (en) * 2012-12-21 2013-04-03 中铁九局集团有限公司桥梁分公司 Tensioning locking and lossless extending device
CN103225403A (en) * 2013-05-10 2013-07-31 史东生 Method for installing elastic supporting and lifting devices by adopting prestressing technique
CN103225403B (en) * 2013-05-10 2015-07-15 史东生 Method for installing elastic supporting and lifting devices by adopting prestressing technique
CN103410329A (en) * 2013-08-30 2013-11-27 南通八建集团有限公司 Large-span basement concrete roof structure flat tube bonded prestressing force construction method
CN103726447A (en) * 2013-12-20 2014-04-16 中交二航局第四工程有限公司 Method and system for secondary tensioning of low-retraction anchorage system vertical prestressed steel strands
CN103726447B (en) * 2013-12-20 2016-12-07 中交二航局第四工程有限公司 Two times tensioning low retraction anchoring system vertical prestressing steel strand wires method and system thereof
CN104452596A (en) * 2014-11-22 2015-03-25 安徽金星预应力工程技术有限公司 Arc-shaped flat anchorage device for bridge
CN107313556A (en) * 2017-07-31 2017-11-03 中国十七冶集团有限公司 A kind of post-stressed steel strand wires flat anchorage
CN110396927A (en) * 2019-07-08 2019-11-01 中建三局第二建设工程有限责任公司 For bridge tower transverse direction bonded prestress rod iron anchoring assembly and construction method
CN110725547A (en) * 2019-10-17 2020-01-24 柳州欧维姆机械股份有限公司 Compact steel strand inhaul cable and manufacturing method thereof
CN110725547B (en) * 2019-10-17 2023-08-11 柳州欧维姆机械股份有限公司 Compact steel strand inhaul cable and manufacturing method thereof
CN112195782A (en) * 2020-09-09 2021-01-08 马鞍山拓锐金属表面技术有限公司 Anticorrosive melting device of steel strand wires ground tackle
CN112554560A (en) * 2020-11-13 2021-03-26 云南建投第六建设有限公司 Post-tensioning method prestress construction method for flat slab structure
JP2022166493A (en) * 2021-04-21 2022-11-02 飛島建設株式会社 Pc steel material ventilation decompression rust prevention method and pc structure construction method using the same
JP7312781B2 (en) 2021-04-21 2023-07-21 飛島建設株式会社 PC steel material evacuation decompression rust prevention method and PC structure construction method using the same
CN113373820A (en) * 2021-07-07 2021-09-10 浙江工业职业技术学院 Bridge prestress tension construction method
CN114717941A (en) * 2022-02-21 2022-07-08 中交路桥建设有限公司 Tensioning method for vertical prestressed steel strand of concrete continuous beam
CN114717941B (en) * 2022-02-21 2023-09-05 中交路桥建设有限公司 Tensioning method for vertical prestressed steel strands of concrete continuous beam
CN114961273A (en) * 2022-05-14 2022-08-30 中国水利水电第七工程局有限公司 Prestressed steering tensioning construction method in narrow space

Similar Documents

Publication Publication Date Title
JP2008231700A (en) Flat anchorage device for post-tensioned type prestressed concrete floor slab, post-tensioned type prestressed concrete floor slab using the anchorage device, and construction method for the post-tensioned type prestressed concrete floor slab
US6843031B1 (en) Bonded monostrand post-tension system
US7856774B1 (en) Sheathing-retaining wedge assembly for use with a post-tension anchorage system
JP5405889B2 (en) Tension material tensioning method
KR20110111907A (en) Saddle assembly
CN212376149U (en) Connector for connecting unbonded prestressed steel strands in post-cast strip
JP6442104B1 (en) Continuous fiber reinforced strand fixing tool
JP4029105B2 (en) Connector, PC member manufacturing apparatus and manufacturing method
JP2007211449A (en) Structure and construction method for joining steel-frame beam and concrete body together
CN110184954B (en) Bridge prestressed body outer cable dismantling method
KR102023086B1 (en) End compression and tension type permanent anchor
JP6721940B2 (en) Widening structure of existing PC floor slab
CN210163848U (en) External reinforcing apparatus of reinforced concrete roof beam
KR20080006448U (en) Steel wire for clamping fixing
KR101274988B1 (en) Apparatus for introducing stress
CN110685282B (en) Anchor cable bearing device, anchor cable and tensioning construction method thereof
CN108222376B (en) Steel strand connector of pretensioned beam for constructional engineering and use method thereof
JPH111994A (en) Stranded-wire reinforcing material with opening
KR101185156B1 (en) Ground anchor effedted by multi-load
KR100605287B1 (en) Ground anchor with a grout inductive pipe in the inside
KR102672804B1 (en) Anti-twisting anchorhead jig for tendon and anti-twisting steel wire installing method using the same
KR20200041095A (en) Permanent type anchor
JP2005113539A (en) Bridge segment and its installing method
JP2011058181A (en) Method for manufacturing floor slab bridge using square steel pipe
KR102118792B1 (en) Anchor type and tension type permanent anchor