CN112554560A - Post-tensioning method prestress construction method for flat slab structure - Google Patents

Post-tensioning method prestress construction method for flat slab structure Download PDF

Info

Publication number
CN112554560A
CN112554560A CN202011270092.7A CN202011270092A CN112554560A CN 112554560 A CN112554560 A CN 112554560A CN 202011270092 A CN202011270092 A CN 202011270092A CN 112554560 A CN112554560 A CN 112554560A
Authority
CN
China
Prior art keywords
prestressed
tensioning
grouting
anchor
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011270092.7A
Other languages
Chinese (zh)
Inventor
李海鸿
宋琴
***
张国洋
苏静华
张秀勇
张劲松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ycih No6 Construction Co ltd
Original Assignee
Ycih No6 Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ycih No6 Construction Co ltd filed Critical Ycih No6 Construction Co ltd
Priority to CN202011270092.7A priority Critical patent/CN112554560A/en
Publication of CN112554560A publication Critical patent/CN112554560A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention provides a post-tensioning method prestressed construction method of a flat slab structure, which comprises the steps of prestressed material entering, re-testing → reinforcement cage binding, cushion block in place → prestressed steel strand penetrating → hidden acceptance, cross-over testing, concrete pouring → anchor installation and tensioning equipment → tensioning, locking → pore channel grouting → anchor sealing → project acceptance. According to the post-tensioning prestress construction method for the flat slab structure, the lattice column bearing support is used as a temporary support, a stress system is clear, and compared with a traditional full framing scaffold, a large amount of materials and labor are saved; the prestressed flat slab structure fully meets the design appearance modeling and quality requirements after being molded; the formed prestressed flat slab has smooth surface, easy guarantee of concrete compactness and good surface impression effect.

Description

Post-tensioning method prestress construction method for flat slab structure
Technical Field
The invention relates to the field of building construction methods, in particular to a post-tensioning method prestress construction method for a flat slab structure.
Background
Concrete cooperation reinforcing bar at its top of in-process of current building construction pours and forms, but the unable at utmost of utilization height space between the floor of current structure, it is inconvenient to use, current reinforcing bar in case can't adjust the use after the building is accomplished in addition, cause working error, thereby cause the reduction of quality, it is inconvenient to use, need use a large amount of scaffolds to cooperate the construction when traditional building uses, traditional full hall scaffold wastes a large amount of materials and manual work, current concrete is at the in-process unevenness of pouring, concrete compactness is difficult to guarantee, the surface impression is poor.
Disclosure of Invention
The invention aims to provide a post-tensioning method prestressed construction method of a flat slab structure, aiming at overcoming the defects in the prior art, and solving the problems in the background art.
In order to achieve the purpose, the invention is realized by the following technical scheme: a post-tensioning method prestress construction method for a flat slab structure is characterized in that: the construction method comprises the following steps:
the method comprises the following steps: the prestressed material enters a field and is subjected to rechecking; carrying out template construction according to a design drawing and a lofting sheet; the construction acceptance of the sample plate is qualified, personnel and materials are ready, and the materials are blanked according to a lofting sheet; after the pre-embedding construction of the template, the steel bar and the water and electricity is finished, the acceptance is qualified, and the construction is started after the procedure transfer procedure is handled;
step two: binding a steel bar framework and a cushion block in place; during blanking, the steel strands are numbered one by one according to the principle of firstly arranging long ribs and then arranging short ribs, and the steel strands are numbered uniformly and have the same length; controlling the blanking length: the steel strand is ensured to be straight and not to be overlapped with other steel strands in the paying-off process; the steel wire can penetrate into the steel pipe for blanking; bundling and binding according to the number, binding one wire by each 2m, and buckling a wire binding head into the bundle; when the heights are not uniform, the cushion blocks are used for cushioning, so that the heights are consistent;
step three: penetrating a prestressed steel strand; firstly, manufacturing a prestressed tendon, cutting 4-6 steel strands with the length of 1m in the manufacturing process of the prestressed tendon, carrying out pressure test, and carrying out formal embossing after the pattern is determined to be qualified; the pattern is like a bulb type, and the steel wires are scattered and bent without rib breakage and are qualified;
step four: penetrating a corrugated pipe; the prestressed steel strand pipe is manually penetrated and bundled firstly; the bundling mode is as follows: firstly, threading and then tubing, namely, putting the prestressed tendons into the steel reinforcement framework, and then sleeving the spiral pipe and the connector section by section; collecting the whole bundle of the bundle; during the bundle penetrating construction, workers stand on the scaffold, and penetrate the prestressed tendons into the pore channels one by one; wrapping the front end of the bundle into a bullet shape by using adhesive tapes, manufacturing a traction head for a long (L is more than 60m) curved bundle, and pulling forwards and pushing backwards; measures should be taken after the prestressed tendons penetrate, so that rainwater is prevented from being corroded, and electric damage and mechanical damage are prevented;
step five: concealed acceptance inspection, handover inspection and concrete pouring; inspecting the installation concealment of the prestressed steel strands, and pouring concrete after the inspection is qualified;
step six: mounting an anchorage device and a tensioning device; when the anchorage device is installed, the anchorage device is inspected, equipment is calibrated and pre-inspected; installing a tensioning device at one side of an anchorage device, designing the proportion of grouting material and anchor sealing concrete before tensioning, and checking the quality of member concrete;
step seven: tensioning and locking; the tensioning sequence is according to the design requirement or construction scheme, and the tensioning is performed according to floors, parts and sections; all floors and parts follow the principle of symmetry and uniformity, and equipment is moved as little as possible; adopting graded tensioning and graded anchoring, batch tensioning, stage tensioning and compensation tensioning; the tension anchoring procedure adopts: 0 → 10% σ con → 103% σ con → anchor; measuring the elongation of the prestressed tendon during tensioning: the measuring method can measure the extension of the cylinder body of the jack or the length change of the exposed prestressed tendon; and (3) comparing the actually measured prestressed tendon elongation with the calculated elongation value: if the error is within +/-6 percent, the stretching is normally suspended, the reason is found out, and the stretching can be continued after measures are taken; filling in a prestress tension record;
step eight: grouting a pore passage; before pore grouting, concrete needs to be made into cement blocks, the quality of the concrete is checked, and the specific steps of the pore grouting are as follows: after the prestressed tendons are tensioned and anchored, slurry is timely poured and the plugging work of an anchorage device is well done; the grouting cement is preferably ordinary Portland cement with the grade of not less than 32.5, the water cement ratio is not more than 0.4, and additives for improving the performance of the cement paste can be properly added; the grouting equipment comprises a stirrer, a grouting pump, a slurry storage barrel, a filter, a rubber tube, a connector, a control valve and the like; checking whether the grouting hole and the exhaust hole are communicated with the prestressed tendon pore passage or not, and if not, carrying out pretreatment; preparing grouting material and feeding in sequence: water → admixture (stirring) → cement (stirring); the lower layer and the upper layer are sequentially grouted; each prestressed pipeline is suitable for continuous grouting, and each pore channel needs to be continuously filled with grouting once; if the water cannot be filled continuously at one time, the water is used for flushing, and then the water is poured again; checking the slurry outlet and the exhaust hole one by one from the near to the far of the grouting hole, and sealing one by one after the discharged thick slurry overflows; after the thick slurry overflows from the last slurry outlet hole, sealing the slurry outlet hole, continuously pressurizing (0.4-0.6 Mpa), maintaining the pressure for 2min, and sealing the grouting hole; a group of cubic test pieces with the side length of 70.7mm are kept in each work shift; filling a grouting record;
step nine: sealing the anchorage device; after grouting is finished and the strength meets the design requirement, cutting the steel strand and plugging the anchor head; sealing the anchor according to the design requirement; when no specific requirements are required in design, the design is in accordance with the specifications and related regulations, the anchor sealing concrete is preferably sealed by fine aggregate concrete with the strength higher by one grade than the design strength of the member, and the hidden acceptance inspection is carried out;
step ten: checking and accepting the project; in the prestress construction process, inspection and acceptance of inspection lots are required to be done, and finally, project inspection and acceptance are applied.
In a preferred mode of the present invention, the corrugated pipe is a flat galvanized corrugated pipe, and the length of the corrugated pipe joint is 200mm to 300 mm.
As a preferred mode of the present invention, the grout holes and the vent holes inside the step four and the step eight may be commonly used with each other.
As a preferred mode of the invention, the vertical deviation of the prestressed tendon position in the prestressed tendon installation process in the third step is 10mm, the horizontal deviation is 30mm, and the vertical deviation of the anchor backing plate and the end axis of the prestressed tendon is 10 mm; the beam-shaped beam-direction position deviation qualified rate is more than 92%, and the deviation of more than 15mm is not required; the qualification rate in the horizontal direction is more than 80 percent; when the anchorage device in the step six is installed, the anchorage device adopts a cast iron finished anchorage device matched with the sleeve; the anchorage device finishes the bundle penetrating of the prestressed steel strands, is installed in a tensioning section, is in plug-in connection with the sleeve, and the joint position is sealed by an adhesive tape; a foamed wood plate processing template is adopted between the anchorage device and the template for reinforcement and sealing treatment; the anchorage device is fixed on the steel bar framework and the beam slab template.
As a preferred mode of the invention, in the seventh step, when the tension is used, the tension process should ensure that the stress of each prestressed tendon in the same bundle is uniform; when the prestressed steel strands are tensioned one by one or one by one, the condition that the stress state unfavorable to the structure does not occur in each stage is ensured, and when a stress control tensioning method is adopted, the elongation value of the prestressed tendon is checked; the relative allowable deviation of the actual elongation values from the design calculated theoretical elongation values is ± 6%. The prestressed tendons should be prevented from breaking or slipping during the tensioning process. When the steel wire is broken or slipped, the number of the broken or slipped steel wire is strictly more than 3 percent of the total number of the prestressed tendons with the same section, each steel wire bundle is not more than one steel wire, and the internal shrinkage of the prestressed tendons at the tensioning end in the anchoring stage meets the design requirement; when no specific requirement exists in design, the heading screw anchor is 1mm, the top pressure of the conical anchor and the clamping piece type anchor is not more than 5mm, and the top pressure of the conical anchor and the clamping piece type anchor is 6 mm-8 mm.
As a preferred mode of the invention, the grouting quality control in the step eight is to perform pore grouting as early as possible after the prestressed tendons are tensioned, and cement slurry in the pores is full and compact; the water cement ratio of the cement paste for grouting is not more than 0.4, and the bleeding rate after 3 hours of stirring is not more than 3%. Grouting is carried out according to the design requirement by using the cement paste strength; if no specific requirements are required in design, the slurry strength is not lower than the standard value of the cubic compressive strength of the concrete of the member.
As a preferable mode of the invention, the anchor sealing in the ninth step is implemented by taking effective measures for preventing the anchor from corroding and suffering from mechanical damage; the thickness of the protective layer of the anchor at the convex anchoring end is not less than 50 mm; exposed prestressed tendon protective layer thickness: when the device is in a normal environment, the thickness of the device is not less than 20 mm; when the paint is in an environment which is easy to corrode, the thickness of the paint is not less than 50 mm; cutting the exposed part of the steel strand after anchoring by a mechanical method, wherein the exposed length of the steel strand is not more than 1.5 times of the diameter of the steel strand and is not more than 30 mm; the strength of the anchor sealing concrete is required to be carried out according to the design requirement; when the design has no specific requirements, the fine aggregate concrete with the strength higher than the designed strength of the member by one grade is preferably adopted for plugging.
The invention has the beneficial effects that:
1. according to the post-tensioning prestress construction method for the flat slab structure, the lattice column bearing support is used as a temporary support, a stress system is clear, and compared with a traditional full framing scaffold, a large amount of materials and labor are saved; the prestressed flat slab structure fully meets the design appearance modeling and quality requirements after being molded; the formed prestressed flat slab has smooth surface, easy guarantee of concrete compactness and good surface impression effect.
2. The invention relates to a post-tensioning method prestress construction method of a flat slab structure, wherein the materials of prestressed pipes, prestressed tendons, grouting pipes, exhaust holes and prestressed steel strands of the prestressed flat slab structure are selected, arranged and installed according to a design drawing strictly; the method comprises the steps of prestress tensioning method of the prestress flat slab, tensioning locking value, anchor selection, anchor sealing and waterproofing, grouting mode, grouting pressure measurement, selection and implementation, and ensures the working quality.
3. The post-tensioning prestressed construction method for the flat slab structure reduces concrete cracks, reduces the deflection of concrete members, improves the working quality, ensures the production quality, is convenient to use, has multiple functions, and meets the requirements under different conditions.
Drawings
FIG. 1 is a flow chart of a post-tensioning pre-stressing construction method for a flat slab structure according to the present invention;
Detailed Description
In order to make the technical means, the creation characteristics, the achievement purposes and the effects of the invention easy to understand, the invention is further described with the specific embodiments.
Referring to fig. 1, the present invention provides a technical solution: a post-tensioning method prestress construction method for a flat slab structure is characterized in that: the construction method comprises the following steps:
the method comprises the following steps: the prestressed material enters a field and is subjected to rechecking; carrying out template construction according to a design drawing and a lofting sheet; the construction acceptance of the sample plate is qualified, personnel and materials are ready, and the materials are blanked according to a lofting sheet; after the pre-embedding construction of the template, the steel bar and the water and electricity is finished, the acceptance is qualified, and the construction is started after the procedure transfer procedure is handled;
step two: binding a steel bar framework and a cushion block in place; during blanking, the steel strands are numbered one by one according to the principle of firstly arranging long ribs and then arranging short ribs, and the steel strands are numbered uniformly and have the same length; controlling the blanking length: the steel strand is ensured to be straight and not to be overlapped with other steel strands in the paying-off process; the steel wire can penetrate into the steel pipe for blanking; bundling and binding according to the number, binding one wire by each 2m, and buckling a wire binding head into the bundle; when the heights are not uniform, the cushion blocks are used for cushioning, so that the heights are consistent;
step three: penetrating a prestressed steel strand; firstly, manufacturing a prestressed tendon, cutting 4-6 steel strands with the length of 1m in the manufacturing process of the prestressed tendon, carrying out pressure test, and carrying out formal embossing after the pattern is determined to be qualified; the pattern is like a bulb type, and the steel wires are scattered and bent without rib breakage and are qualified;
step four: penetrating a corrugated pipe; the prestressed steel strand pipe is manually penetrated and bundled firstly; the bundling mode is as follows: firstly, threading and then tubing, namely, putting the prestressed tendons into the steel reinforcement framework, and then sleeving the spiral pipe and the connector section by section; collecting the whole bundle of the bundle; during the bundle penetrating construction, workers stand on the scaffold, and penetrate the prestressed tendons into the pore channels one by one; wrapping the front end of the bundle into a bullet shape by using adhesive tapes, manufacturing a traction head for a long (L is more than 60m) curved bundle, and pulling forwards and pushing backwards; measures should be taken after the prestressed tendons penetrate, so that rainwater is prevented from being corroded, and electric damage and mechanical damage are prevented;
step five: concealed acceptance inspection, handover inspection and concrete pouring; inspecting the installation concealment of the prestressed steel strands, and pouring concrete after the inspection is qualified;
step six: mounting an anchorage device and a tensioning device; when the anchorage device is installed, the anchorage device is inspected, equipment is calibrated and pre-inspected; installing a tensioning device at one side of an anchorage device, designing the proportion of grouting material and anchor sealing concrete before tensioning, and checking the quality of member concrete;
step seven: tensioning and locking; the tensioning sequence is according to the design requirement or construction scheme, and the tensioning is performed according to floors, parts and sections; all floors and parts follow the principle of symmetry and uniformity, and equipment is moved as little as possible; adopting graded tensioning and graded anchoring, batch tensioning, stage tensioning and compensation tensioning; the tension anchoring procedure adopts: 0 → 10% σ con → 103% σ con → anchor; measuring the elongation of the prestressed tendon during tensioning: the measuring method can measure the extension of the cylinder body of the jack or the length change of the exposed prestressed tendon; and (3) comparing the actually measured prestressed tendon elongation with the calculated elongation value: if the error is within +/-6 percent, the stretching is normally suspended, the reason is found out, and the stretching can be continued after measures are taken; filling in a prestress tension record;
step eight: grouting a pore passage; before pore grouting, concrete needs to be made into cement blocks, the quality of the concrete is checked, and the specific steps of the pore grouting are as follows: after the prestressed tendons are tensioned and anchored, slurry is timely poured and the plugging work of an anchorage device is well done; the grouting cement is preferably ordinary Portland cement with the grade of not less than 32.5, the water cement ratio is not more than 0.4, and additives for improving the performance of the cement paste can be properly added; the grouting equipment comprises a stirrer, a grouting pump, a slurry storage barrel, a filter, a rubber tube, a connector, a control valve and the like; checking whether the grouting hole and the exhaust hole are communicated with the prestressed tendon pore passage or not, and if not, carrying out pretreatment; preparing grouting material and feeding in sequence: water → admixture (stirring) → cement (stirring); the lower layer and the upper layer are sequentially grouted; each prestressed pipeline is suitable for continuous grouting, and each pore channel needs to be continuously filled with grouting once; if the water cannot be filled continuously at one time, the water is used for flushing, and then the water is poured again; checking the slurry outlet and the exhaust hole one by one from the near to the far of the grouting hole, and sealing one by one after the discharged thick slurry overflows; after the thick slurry overflows from the last slurry outlet hole, sealing the slurry outlet hole, continuously pressurizing (0.4-0.6 Mpa), maintaining the pressure for 2min, and sealing the grouting hole; a group of cubic test pieces with the side length of 70.7mm are kept in each work shift; filling a grouting record;
step nine: sealing the anchorage device; after grouting is finished and the strength meets the design requirement, cutting the steel strand and plugging the anchor head; sealing the anchor according to the design requirement; when no specific requirements are required in design, the design is in accordance with the specifications and related regulations, the anchor sealing concrete is preferably sealed by fine aggregate concrete with the strength higher by one grade than the design strength of the member, and the hidden acceptance inspection is carried out;
step ten: checking and accepting the project; in the prestress construction process, inspection and acceptance of inspection lots are required to be done, and finally, project inspection and acceptance are applied.
In a preferred mode of the present invention, the corrugated pipe is a flat galvanized corrugated pipe, and the length of the corrugated pipe joint is 200mm to 300 mm.
As a preferred mode of the present invention, the grout holes and the vent holes inside the step four and the step eight may be commonly used with each other.
As a preferred mode of the invention, the vertical deviation of the prestressed tendon position in the prestressed tendon installation process in the third step is 10mm, the horizontal deviation is 30mm, and the vertical deviation of the anchor backing plate and the end axis of the prestressed tendon is 10 mm; the beam-shaped beam-direction position deviation qualified rate is more than 92%, and the deviation of more than 15mm is not required; the qualification rate in the horizontal direction is more than 80 percent; when the anchorage device in the step six is installed, the anchorage device adopts a cast iron finished anchorage device matched with the sleeve; the anchorage device finishes the bundle penetrating of the prestressed steel strands, is installed in a tensioning section, is in plug-in connection with the sleeve, and the joint position is sealed by an adhesive tape; a foamed wood plate processing template is adopted between the anchorage device and the template for reinforcement and sealing treatment; the anchorage device is fixed on the steel bar framework and the beam slab template.
As a preferred mode of the invention, in the seventh step, when the tension is used, the tension process should ensure that the stress of each prestressed tendon in the same bundle is uniform; when the prestressed steel strands are tensioned one by one or one by one, the condition that the stress state unfavorable to the structure does not occur in each stage is ensured, and when a stress control tensioning method is adopted, the elongation value of the prestressed tendon is checked; the relative allowable deviation of the actual elongation values from the design calculated theoretical elongation values is ± 6%. The prestressed tendons should be prevented from breaking or slipping during the tensioning process. When the steel wire is broken or slipped, the number of the broken or slipped steel wire is strictly more than 3 percent of the total number of the prestressed tendons with the same section, each steel wire bundle is not more than one steel wire, and the internal shrinkage of the prestressed tendons at the tensioning end in the anchoring stage meets the design requirement; when no specific requirement exists in design, the heading screw anchor is 1mm, the top pressure of the conical anchor and the clamping piece type anchor is not more than 5mm, and the top pressure of the conical anchor and the clamping piece type anchor is 6 mm-8 mm.
As a preferred mode of the invention, the grouting quality control in the step eight is to perform pore grouting as early as possible after the prestressed tendons are tensioned, and cement slurry in the pores is full and compact; the water cement ratio of the cement paste for grouting is not more than 0.4, and the bleeding rate after 3 hours of stirring is not more than 3%. Grouting is carried out according to the design requirement by using the cement paste strength; if no specific requirements are required in design, the slurry strength is not lower than the standard value of the cubic compressive strength of the concrete of the member.
As a preferable mode of the invention, the anchor sealing in the ninth step is implemented by taking effective measures for preventing the anchor from corroding and suffering from mechanical damage; the thickness of the protective layer of the anchor at the convex anchoring end is not less than 50 mm; exposed prestressed tendon protective layer thickness: when the device is in a normal environment, the thickness of the device is not less than 20 mm; when the paint is in an environment which is easy to corrode, the thickness of the paint is not less than 50 mm; cutting the exposed part of the steel strand after anchoring by a mechanical method, wherein the exposed length of the steel strand is not more than 1.5 times of the diameter of the steel strand and is not more than 30 mm; the strength of the anchor sealing concrete is required to be carried out according to the design requirement; when the design has no specific requirements, the fine aggregate concrete with the strength higher than the designed strength of the member by one grade is preferably adopted for plugging.
While there have been shown and described what are at present considered the fundamental principles and essential features of the invention and its advantages, it will be apparent to those skilled in the art that the invention is not limited to the details of the foregoing exemplary embodiments, but is capable of other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (7)

1. A post-tensioning method prestress construction method for a flat slab structure is characterized in that: the construction method comprises the following steps:
the method comprises the following steps: the prestressed material enters a field and is subjected to rechecking; carrying out template construction according to a design drawing and a lofting sheet; the construction acceptance of the sample plate is qualified, personnel and materials are ready, and the materials are blanked according to a lofting sheet; after the pre-embedding construction of the template, the steel bar and the water and electricity is finished, the acceptance is qualified, and the construction is started after the procedure transfer procedure is handled;
step two: binding a steel bar framework and a cushion block in place; during blanking, the steel strands are numbered one by one according to the principle of firstly arranging long ribs and then arranging short ribs, and the steel strands are numbered uniformly and have the same length; controlling the blanking length: the steel strand is ensured to be straight and not to be overlapped with other steel strands in the paying-off process; the steel wire can penetrate into the steel pipe for blanking; bundling and binding according to the number, binding one wire by each 2m, and buckling a wire binding head into the bundle; when the heights are not uniform, the cushion blocks are used for cushioning, so that the heights are consistent;
step three: penetrating a prestressed steel strand; firstly, manufacturing a prestressed tendon, cutting 4-6 steel strands with the length of 1m in the manufacturing process of the prestressed tendon, carrying out pressure test, and carrying out formal embossing after the pattern is determined to be qualified; the pattern is like a bulb type, and the steel wires are scattered and bent without rib breakage and are qualified;
step four: penetrating a corrugated pipe; the prestressed steel strand pipe is manually penetrated and bundled firstly; the bundling mode is as follows: firstly, threading and then tubing, namely, putting the prestressed tendons into the steel reinforcement framework, and then sleeving the spiral pipe and the connector section by section; collecting the whole bundle of the bundle; during the bundle penetrating construction, workers stand on the scaffold, and penetrate the prestressed tendons into the pore channels one by one; wrapping the front end of the bundle into a bullet shape by using adhesive tapes, manufacturing a traction head for a long (L is more than 60m) curved bundle, and pulling forwards and pushing backwards; measures should be taken after the prestressed tendons penetrate, so that rainwater is prevented from being corroded, and electric damage and mechanical damage are prevented;
step five: concealed acceptance inspection, handover inspection and concrete pouring; inspecting the installation concealment of the prestressed steel strands, and pouring concrete after the inspection is qualified;
step six: mounting an anchorage device and a tensioning device; when the anchorage device is installed, the anchorage device is inspected, equipment is calibrated and pre-inspected; installing a tensioning device at one side of an anchorage device, designing the proportion of grouting material and anchor sealing concrete before tensioning, and checking the quality of member concrete;
step seven: tensioning and locking; the tensioning sequence is according to the design requirement or construction scheme, and the tensioning is performed according to floors, parts and sections; all floors and parts follow the principle of symmetry and uniformity, and equipment is moved as little as possible; adopting graded tensioning and graded anchoring, batch tensioning, stage tensioning and compensation tensioning; the tension anchoring procedure adopts: 0 → 10% σ con → 103% σ con → anchor; measuring the elongation of the prestressed tendon during tensioning: the measuring method can measure the extension of the cylinder body of the jack or the length change of the exposed prestressed tendon; and (3) comparing the actually measured prestressed tendon elongation with the calculated elongation value: if the error is within +/-6 percent, the stretching is normally suspended, the reason is found out, and the stretching can be continued after measures are taken; filling in a prestress tension record;
step eight: grouting a pore passage; before pore grouting, concrete needs to be made into cement blocks, the quality of the concrete is checked, and the specific steps of the pore grouting are as follows: after the prestressed tendons are tensioned and anchored, slurry is timely poured and the plugging work of an anchorage device is well done; the grouting cement is preferably ordinary Portland cement with the grade of not less than 32.5, the water cement ratio is not more than 0.4, and additives for improving the performance of the cement paste can be properly added; the slurry equipment comprises a stirrer, a grouting pump, a slurry storage barrel, a filter, a rubber tube, a connector, a control valve and the like; checking whether the grouting hole and the exhaust hole are communicated with the prestressed tendon pore passage or not, and if not, carrying out pretreatment; preparing grouting material and feeding in sequence: water → admixture (stirring) → cement (stirring); the lower layer and the upper layer are sequentially grouted; each prestressed pipeline is suitable for continuous grouting, and each pore channel needs to be continuously filled with grouting once; if the water cannot be filled continuously at one time, the water is used for flushing, and then the water is poured again; checking the slurry outlet and the exhaust hole one by one from the near to the far of the grouting hole, and sealing one by one after the discharged thick slurry overflows; after the thick slurry overflows from the last slurry outlet hole, sealing the slurry outlet hole, continuously pressurizing (0.4-0.6 Mpa), maintaining the pressure for 2min, and sealing the grouting hole; a group of cubic test pieces with the side length of 70.7mm are kept in each work shift; filling a grouting record;
step nine: sealing the anchorage device; after grouting is finished and the strength meets the design requirement, cutting the steel strand and plugging the anchor head; sealing the anchor according to the design requirement; when no specific requirements are required in design, the design is in accordance with the specifications and related regulations, the anchor sealing concrete is preferably sealed by fine aggregate concrete with the strength higher by one grade than the design strength of the member, and the hidden acceptance inspection is carried out;
step ten: checking and accepting the project; in the prestress construction process, inspection and acceptance of inspection lots are required to be done, and finally, project inspection and acceptance are applied.
2. The post-tensioning prestressed construction method of a flat slab structure according to claim 1, characterized in that: the corrugated pipe is a flat galvanized corrugated pipe, and the length of a corrugated pipe joint is 200mm-300 mm.
3. The post-tensioning prestressed construction method of a flat slab structure according to claim 1, characterized in that: and grouting holes and exhaust holes in the fourth step and the eighth step can be mutually universal.
4. The post-tensioning prestressed construction method of a flat slab structure according to claim 1, characterized in that: the vertical deviation of the prestressed tendon position in the prestressed tendon installation process in the third step is 10mm, the horizontal deviation is 30mm, and the vertical deviation of the anchor backing plate and the axis of the tail end of the prestressed tendon is 10 mm; the beam-shaped beam-direction position deviation qualified rate is more than 92%, and the deviation of more than 15mm is not required; the qualification rate in the horizontal direction is more than 80 percent; when the anchorage device in the step six is installed, the anchorage device adopts a cast iron finished anchorage device matched with the sleeve; the anchorage device finishes the bundle penetrating of the prestressed steel strands, is installed in a tensioning section, is in plug-in connection with the sleeve, and the joint position is sealed by an adhesive tape; a foamed wood plate processing template is adopted between the anchorage device and the template for reinforcement and sealing treatment; the anchorage device is fixed on the steel bar framework and the beam slab template.
5. The post-tensioning prestressed construction method of a flat slab structure according to claim 1, characterized in that: when the step seven is used for tensioning, the tensioning process can ensure that the stress of each prestressed tendon in the same bundle is uniform; when the prestressed steel strands are tensioned one by one or one by one, the condition that the stress state unfavorable to the structure does not occur in each stage is ensured, and when a stress control tensioning method is adopted, the elongation value of the prestressed tendon is checked; the relative allowable deviation of the actual elongation values from the design calculated theoretical elongation values is ± 6%. The prestressed tendons should be prevented from breaking or slipping during the tensioning process. When the steel wire is broken or slipped, the number of the broken or slipped steel wire is strictly more than 3 percent of the total number of the prestressed tendons with the same section, each steel wire bundle is not more than one steel wire, and the internal shrinkage of the prestressed tendons at the tensioning end in the anchoring stage meets the design requirement; when no specific requirement exists in design, the heading screw anchor is 1mm, the top pressure of the conical anchor and the clamping piece type anchor is not more than 5mm, and the top pressure of the conical anchor and the clamping piece type anchor is 6 mm-8 mm.
6. The post-tensioning prestressed construction method of a flat slab structure according to claim 1, characterized in that: the grouting quality control of the step eight is to perform pore grouting as early as possible after the prestressed tendons are tensioned, and cement paste in the pores is full and compact; the water cement ratio of the cement paste for grouting is not more than 0.4, and the bleeding rate after 3 hours of stirring is not more than 3%. Grouting is carried out according to the design requirement by using the cement paste strength; if no specific requirements are required in design, the slurry strength is not lower than the standard value of the cubic compressive strength of the concrete of the member.
7. The post-tensioning prestressed construction method of a flat slab structure according to claim 1, characterized in that: in the step nine, effective measures for preventing the anchorage device from being corroded and damaged by machinery are taken during anchorage sealing; the thickness of the protective layer of the anchor at the convex anchoring end is not less than 50 mm; exposed prestressed tendon protective layer thickness: when the device is in a normal environment, the thickness of the device is not less than 20 mm; when the paint is in an environment which is easy to corrode, the thickness of the paint is not less than 50 mm; cutting the exposed part of the steel strand after anchoring by a mechanical method, wherein the exposed length of the steel strand is not more than 1.5 times of the diameter of the steel strand and is not more than 30 mm; the strength of the anchor sealing concrete is required to be carried out according to the design requirement; when the design has no specific requirements, the fine aggregate concrete with the strength higher than the designed strength of the member by one grade is preferably adopted for plugging.
CN202011270092.7A 2020-11-13 2020-11-13 Post-tensioning method prestress construction method for flat slab structure Pending CN112554560A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011270092.7A CN112554560A (en) 2020-11-13 2020-11-13 Post-tensioning method prestress construction method for flat slab structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011270092.7A CN112554560A (en) 2020-11-13 2020-11-13 Post-tensioning method prestress construction method for flat slab structure

Publications (1)

Publication Number Publication Date
CN112554560A true CN112554560A (en) 2021-03-26

Family

ID=75042199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011270092.7A Pending CN112554560A (en) 2020-11-13 2020-11-13 Post-tensioning method prestress construction method for flat slab structure

Country Status (1)

Country Link
CN (1) CN112554560A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113107129A (en) * 2021-04-20 2021-07-13 中国建筑第七工程局有限公司 Super high-rise post-tensioning method bonded prestressed beamless floor construction method
CN113802770A (en) * 2021-09-24 2021-12-17 中交一航局第四工程有限公司 Processing and laying process of linear member wrapped by bond enhancing knot

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101109227A (en) * 2007-09-05 2008-01-23 中国建筑第七工程局 Construction method of single-stride large cantilever double-pre-stress concrete steel concrete crossbeam
JP2008231700A (en) * 2007-03-16 2008-10-02 Anderson Technology Kk Flat anchorage device for post-tensioned type prestressed concrete floor slab, post-tensioned type prestressed concrete floor slab using the anchorage device, and construction method for the post-tensioned type prestressed concrete floor slab
CN103410329A (en) * 2013-08-30 2013-11-27 南通八建集团有限公司 Large-span basement concrete roof structure flat tube bonded prestressing force construction method
CN109372169A (en) * 2018-11-21 2019-02-22 钱勇 A kind of two dimension prestressing prefabricated reinforced concrete cassette ceiling and preparation method thereof
CN110206143A (en) * 2019-05-10 2019-09-06 中建八局第二建设有限公司 A kind of construction method of post-stressed assembly concrete frame structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008231700A (en) * 2007-03-16 2008-10-02 Anderson Technology Kk Flat anchorage device for post-tensioned type prestressed concrete floor slab, post-tensioned type prestressed concrete floor slab using the anchorage device, and construction method for the post-tensioned type prestressed concrete floor slab
CN101109227A (en) * 2007-09-05 2008-01-23 中国建筑第七工程局 Construction method of single-stride large cantilever double-pre-stress concrete steel concrete crossbeam
CN103410329A (en) * 2013-08-30 2013-11-27 南通八建集团有限公司 Large-span basement concrete roof structure flat tube bonded prestressing force construction method
CN109372169A (en) * 2018-11-21 2019-02-22 钱勇 A kind of two dimension prestressing prefabricated reinforced concrete cassette ceiling and preparation method thereof
CN110206143A (en) * 2019-05-10 2019-09-06 中建八局第二建设有限公司 A kind of construction method of post-stressed assembly concrete frame structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蓝涛, 陈立新: "有粘结预应力在无梁楼盖工程中的应用", 广东土木与建筑, no. 03, 15 March 2005 (2005-03-15), pages 41 - 42 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113107129A (en) * 2021-04-20 2021-07-13 中国建筑第七工程局有限公司 Super high-rise post-tensioning method bonded prestressed beamless floor construction method
CN113802770A (en) * 2021-09-24 2021-12-17 中交一航局第四工程有限公司 Processing and laying process of linear member wrapped by bond enhancing knot

Similar Documents

Publication Publication Date Title
CN111455855B (en) Construction process of main bridge of double-tower single-cable-plane short-tower cable-stayed bridge
CN110206143B (en) Construction method of post-tensioning prestressed assembly concrete frame structure
CN101307595A (en) Large-sized aqueduct prestressing force construction method
CN112554560A (en) Post-tensioning method prestress construction method for flat slab structure
CN115262626B (en) Construction method of underground space prestress steel reinforced concrete top cover under ultra-large span heavy load
CN110939051A (en) Subway hidden cover beam construction method
CN113738119A (en) Large-span prestressed concrete beam roof tooth block tensioning construction method with bonding
CN113459274B (en) Manufacturing method of fiber woven mesh reinforced concrete composite board
CN109653511A (en) Large-span bidirectional mixing prestressing force complete construction method
CN113605771B (en) Prestress assembly type frame structure system
CN110607841A (en) Wind tunnel prestress construction process
CN112502041A (en) Method for crossing karst cavity by cast-in-situ box girder in karst tunnel
CN111663434A (en) Mixed-tension prestress prefabricated cover beam tensioning assembly and method for connecting cover beam and upright column
CN111693226A (en) Efficient leakage detection and anti-blocking construction method for post-tensioned prestressed pipeline of bridge
CN107288024B (en) Assembled beam body and construction method thereof
CN110184948A (en) A kind of Bridge beam construction method
CN116674079A (en) Construction method of prefabricated small box girder
CN113107129A (en) Super high-rise post-tensioning method bonded prestressed beamless floor construction method
CN115256615A (en) Intelligent shower maintenance standard construction system for prefabricated box girder of expressway
CN114059714A (en) Construction process of bonded prestressed beam
CN212404845U (en) Temporary continuous beam pier beam consolidation system and continuous beam bridge
CN112695633A (en) Prefabricated small box girder prestress engineering construction method for intelligent express way
CN113524429A (en) Pre-tensioning method precast slab beam construction process
CN113309229A (en) Grouting reverse-sequence construction method for assembled vertical component
CN111691457A (en) Basement bottom plate construction method and basement bottom plate structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination