JP2004075294A - Jib strut self-assembling method for tower crane - Google Patents

Jib strut self-assembling method for tower crane Download PDF

Info

Publication number
JP2004075294A
JP2004075294A JP2002238543A JP2002238543A JP2004075294A JP 2004075294 A JP2004075294 A JP 2004075294A JP 2002238543 A JP2002238543 A JP 2002238543A JP 2002238543 A JP2002238543 A JP 2002238543A JP 2004075294 A JP2004075294 A JP 2004075294A
Authority
JP
Japan
Prior art keywords
strut
jib
rope
tower
tip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2002238543A
Other languages
Japanese (ja)
Inventor
Eiji Miya
宮 英司
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobelco Construction Machinery Co Ltd
Original Assignee
Kobelco Construction Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobelco Construction Machinery Co Ltd filed Critical Kobelco Construction Machinery Co Ltd
Priority to JP2002238543A priority Critical patent/JP2004075294A/en
Publication of JP2004075294A publication Critical patent/JP2004075294A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a jib strut self-assembling method for a crane enabling assembly of a strut by itself without necessitating an auxiliary crane. <P>SOLUTION: In this tower crane provided with a tower boom 3, a luffing jib 5, and front and rear struts 6, 7 for raising the jib as front attachment in a front part of a machine body 2, one end of a rope 14 is connected with a tip of the rear strut 7, the other end of it is extended through a sheave 8b arranged at a position higher than the rear strut which is at a horizontal attitude to form an angle θ between the rear strut 7 and the rope 14, and the other end of the rope 14 is wound by a winch 12 provided in the machine body 2 to raise the rear strut 7. <P>COPYRIGHT: (C)2004,JPO

Description

【0001】
【発明の属する技術分野】
本発明は、ラフィングジブまたは固定ジブを装備したタワークレーンのジブストラット自力組立方法に関するものである。
【0002】
【従来の技術】
タワークレーンは、フロントアタッチメントと機体を分解して別々に輸送し、現場に搬入された後、組み立てられる。
【0003】
図6は組立前のラフィングジブ付きクレーンを示したものであり、フロントアタッチメントは水平に倒伏された状態にある。
【0004】
機体50の前部にはタワーブーム51が取り付られ、このタワーブーム51の先端部にタワーヘッド52が備えられ、このタワーヘッド52の先端にジブ53が枢着される。
【0005】
このジブ53の後部にはジブストラットとしてフロントストラット(フロントポストと呼ぶ場合がある)54とリヤストラット(リヤポストと呼ぶ場合がある)55がそれぞれ枢着されており、ジブ53の先端部とフロントストラット54の先端部は図示しないジブ支持ロープで連結され、また、フロントストラット54の先端部とリヤストラット55の先端部に設けられた各シーブ間にはジブ起伏ロープ56が架け渡されるようになっている。
【0006】
なお、図中、57はマスト、58はガントリであり、それぞれの先端部に備えられたシーブ間にブーム起伏ロープが掛け渡されるようになっている。また、59はウインチドラムである。
【0007】
【発明が解決しようとする課題】
しかしながら、従来のタワークレーンにおいてジブストラットを組み立てる場合、リヤストラット55を引き起こすのにタワークレーンと別に補助クレーンを用意し、ウインチドラム59からのウインチロープで巻き上げることができる角度までそのリヤストラット55を立てる必要があった。
【0008】
なぜなら、フロントアタッチメントを地上に倒した状態ではリヤストラット55が水平姿勢であるためウインチドラム59によって直接、リヤストラット55を引き起こすことができないからである。
【0009】
また、ジブストラットを分解する場合においてもリヤストラット55をウインチドラム59からのロープで直接支える方法では、リヤストラット55を倒し過ぎてリヤストラット55とロープが平行になった時点でリヤストラット55が反転し、その下方のフロントストラット54に衝突して破損する虞れがある。
【0010】
このように、従来のタワークレーンではジブストラットを組み立てる場合、または分解するときに常に補助クレーンが必要になるという不都合があった。
【0011】
本発明は以上のような従来のタワークレーンにおける課題を考慮してなされたものであり、補助クレーンを必要とせずにジブストラットを自力で組み立てることができるクレーンのジブストラット自力組立方法を提供するものである。
【0012】
【課題を解決するための手段】
本発明は、機体の前部にフロントアタッチメントとして、タワーブームと、ジブと、このジブを支持するジブストラットとを備えたタワークレーンにおいて、フロントアタッチメントを地上に倒した状態で、ジブストラットの先端部に接続したロープをそのジブストラット先端部よりも高い位置で機体側に配置されたガイド手段を介し巻取装置で巻き取ることにより、ジブストラットを自力で引き起こすタワークレーンのジブストラット自力組立方法である。
【0013】
本発明において、上記機体にタワーブームを起伏させるための起伏支柱を備え、その起伏支柱に設けられたガイド手段を介してロープを巻き取ることができる。
【0014】
上記起伏支柱の具体例としては、ガントリやマストが示される。
【0015】
本発明は、機体の前部にフロントアタッチメントとして、タワーブームと、ジブと、このジブを支持するジブストラットとを備えたタワークレーンにおいて、上端部にガイド手段を備えた支持部材を、フロントアタッチメントを地上に倒した状態でそのガイド手段がジブストラットの先端部よりも高い位置となるようにタワーブームに突設し、ジブストラットの先端部に接続したロープをそのガイド手段を介し巻取装置で巻き取ることにより、ジブストラットを自力で引き起こすタワークレーンのジブストラット自力組立方法である。
【0016】
本発明において、ジブストラットを組み立てるとは、フロントアタッチメントが地上に倒された状態でジブ後部に連結されているジブストラットを所定の姿勢に立てることを意味する。
【0017】
【発明の実施の形態】
以下、図面に示した実施形態に基づいて本発明を詳細に説明する。
【0018】
図1および図2は、本発明に係るジブストラット自立組立方法の各工程を示したものであり、フロントアタッチメントを地上に倒した状態を示している。
【0019】
まず、図1(a)において、タワークレーンの全体構成について説明する。
【0020】
1は下部走行体、2は機体としての上部旋回体であり、この上部旋回体2の前部にタワーブーム3が取り付られている。タワーブーム3の先端部にタワーヘッド4が備えられ、このタワーヘッド4の先端にジブ5が枢着される。
【0021】
ジブ5の後部にはジブストラットとしてのフロントストラット6とリヤストラット7がそれぞれ枢着されている。また、上部旋回体2の後部には起伏支柱としてのガントリ8が配置されており、このガントリ8の前側支柱8aの略中間位置に補助ガイドシーブ8bが設けられている。この補助ガイドシーブ8bは、ジブストラット先端部よりも高い位置に配置されガイド手段として機能する。
【0022】
この補助ガイドシーブ8bは、第3ウインチに巻かれたロープをガイドするものであり、ジブの起伏時の他、例えば掘削装置等のオプション機器の吊上げ、吊下げ時にも使用されるものであり、作業時には補助ガイドシーブ8bに掛けられたロープの先端に掘削装置が吊持されるようになっている。
【0023】
タワーブーム3は、ブーム起伏ウインチ9からのブーム起伏ロープ10aにブームガイライン10bを介して接続されており、そのロープ10aを巻上げまたは巻下げることによって起伏するようになっている。
【0024】
一方、ジブ5は、図示しないジブ起伏ウインチによって巻取駆動されるジブ起伏ロープ、ジブストラット6,7、及びジブガイラインを介して連結され、そのジブ起伏ロープを巻上げまたは巻下げることによって起伏するようになっている。
【0025】
なお、図中11は主巻ウインチ、12は補巻ウインチであり、それぞれ吊荷の巻上げ、巻下げ作業に使用される。また、補巻ウインチ12はリヤストラット7の引き起こしにも使用される。13はジブ用に使用される補助ウインチである。
【0026】
また、16は一端がリヤストラット7の先端側に取り付けられたストラット側ガイケーブルであり、17は、一端がブームの基端側背面のブラケットに取り付けられたブーム側ストラットガイケーブルである。後述する自力組立工程で、上記ストラット側ガイケーブル16およびブーム側ストラットガイケーブル17が連結されることで、ストラット先端とブーム基端とを連結支持する連結手段としてのストラットガイケーブルが構成される。
【0027】
上記構成を有するタワークレーンのジブストラット自立組立方法を以下に説明する。
【0028】
図1(a)において、補巻ウインチ12から引き出されたロープ14を、ガントリ8の補助ガイドシーブ8bに通し、ジブ5側に引き出してリヤストラット7の先端部に接続する。
【0029】
図1(b)において、補巻ウインチ12を巻上駆動することによってロープ14を巻き取ると、リヤストラット7とロープ14との間に所定の角度θが確保されることによってリヤストラット7を直接引き起こすことができる。なお、上記所定の角度θとは3°以上であることが好ましい。角度θは力学的に引き起こしができる角度であれば十分であるが、約3°以上設けることが好ましい。
【0030】
図1(c)において、リヤストラット7を矢印A方向に引き起こす際、リヤストラット7とフロントストラット6とに架け渡されているロープ15を繰り出しながらロープ14を巻き上げる。これにより、ロープ14の巻上時にフロントストラット6の負荷が補巻ウインチ12に加わらないようにする。
【0031】
図1(d)において、リヤストラット7がほぼ90°に起立した時点で、リヤストラット7が自重で矢印A′方向に反転しないようにロープ15を張る。
【0032】
図2(e)において、ジブストラット間のロープ15を繰り出しながらストラットガイケーブル16をブーム側ストラットガイケーブル17に接続し、ストラットバックストップ18を取り付ける。
【0033】
図2(f)において、ジブストラット間のロープ15を巻き取り、ストラットガイケーブル16を図に示す状態に張る。
【0034】
なお、ジブストラットの分解時においても、ガントリ8のシーブ8bを通したロープ14をリヤストラット7の先端部に接続し、ロープ14を繰り出すことによってリヤストラット7を安全に水平位置まで倒伏させることができる。このとき、リヤストラット7が水平姿勢になるまでは、ロープ14とリヤストラット7との間に角度θが確保されているため(図1(b)参照)、リヤストラット7がジブ5側に反転してフロントストラット6と衝突するというトラブルを解消することができる。
【0035】
図3および4は、本発明の第二の実施形態を示したものであり、起伏支柱としてのマストのシーブを通してリヤストラット7を自力で組み立てる方法を示したものである。
【0036】
なお、以下の図面において図1と同じ構成要素については同一符号を付してその説明を省略する。
【0037】
図3(a)に示すように、補巻ウインチ12から繰り出されたロープ20を、マスト21の上端に備えられているガイド手段としてのシーブ21aを通して垂下させる。
【0038】
図3(b)に示すように、ロープ20をさらに繰り出してリヤストラット7の先端部に接続する。
【0039】
図3(c)に示すように、ロープ20を弛ませたまま、マスト21をほぼ90°まで起こす。
【0040】
図3(d)に示すように、補巻ウインチ12によってロープ20を巻き上げ、リヤストラット7を矢印A方向に引き起こす。この時、フロントストラット6が起きないようにリヤストラット7とフロントストラット6との間のロープ22を緩める。リヤストラット7を引き起こす場合、リヤストラット7とロープ20との間には所定の角度θ′が確保されているため(図3(c)参照)、リヤストラット7をロープ20で直接、引き起こすことができる。
【0041】
図4(e)に示すように、リヤストラット7をさらに倒した状態でストラットガイライン22をブーム側ストラットガイライン22aに接続する。
【0042】
図4(f)に示すように、リヤストラット7を起こし、ストラットバックストップ23を固定する。
【0043】
図4(g)に示すように、ブームガイライン24、ジブガイライン25をそれぞれ取り付ける。
【0044】
なお、ジブストラットの分解時においても、マスト21先端部のシーブ21aを通したロープ20をリヤストラット7の先端部に接続し、ロープ20を繰り出すことによってリヤストラット7を安全に水平位置まで倒伏させることができる。このとき、リヤストラット7が水平になるまでは、ロープ20とリヤストラット7との間に角度θが確保されているため(図3(c)参照)、リヤストラット7がジブ5側に反転してフロントストラット6と衝突するというトラブルを解消することができる。
【0045】
図5は、本発明の第三の実施形態を示したものであり、タワーブーム3の先端部に支持部材30を突設し、その支持部材30の上端に設けたシーブ30aにロープ31を通し、リヤストラット7を自力で組み立てる方法を示したものである。
【0046】
この自力組立方法では、同図(a)に示すように、支持部材30を設けることにより、リヤストラット7の引き起こし時にのみ、リヤストラット7とロープ31との間に所定の角度θ″を確保することができるようにしている。
【0047】
リヤストラット7がある程度引き起こされると、同図(b)に示すように、ロープ31はシーブ30aから離れて直接、ウインチによって巻き上げられる。
【0048】
上記支持部材30のシーブ30aはガイド手段として機能する。
【0049】
なお、上記実施形態ではラフィングジブを装備したタワークレーンを例に取り説明したが、これに限らず、固定ジブを装備したタワークレーンにも本発明を適用することができる。
【0050】
また、上述の実施形態では、ブーム基端部とジブストラット先端部とを結ぶものは、両端に連結プラグを備えたロッド状のガイケーブルを用いたが、これに限らず、リンクやワイヤロープであってもよい。
【0051】
また、上記実施形態ではガイド手段をシーブで構成したが、これに限らず、ローラ、半割シーブ等で構成することもできる。
【0052】
さらにまた、上述したシーブの位置に、着脱自在な滑車具を連結して自力組立作業を行うようにしてもよい。着脱自在な滑車具を使用すると、組立後にロープを外す作業が容易になるという利点がある。
【0053】
【発明の効果】
以上説明したことから明らかなように、請求項1の本発明によれば、フロントアタッチメントを地上に倒した状態で、ジブストラットの先端部に接続したロープをそのジブストラット先端部よりも高い位置で機体側に配置されたガイド手段を介し巻取装置で巻き取るようにしたため、補助クレーンを必要とせずにジブストラットを自力で引き起こすことが可能になる。
【0054】
請求項2の本発明によれば、機体に備えられた、タワーブームを起伏させるための起伏支柱のガイド手段を介してロープを巻き取るため、既存のガントリやマストに備えられたガイド手段を利用してジブストラットを引き起こすことができる。
【0055】
請求項3の本発明によれば、ジブストラットの先端部よりも高い位置となるようにタワーブームに突設された支持部材のガイド手段を介し、ジブストラットの先端部に接続したロープを巻き取るようにしたため、ジブストラットを自力で引き起こすことができる。
【図面の簡単な説明】
【図1】(a)〜(d)は、本発明に係るジブストラット自力組立方法の第一実施形態についてその手順を示した工程図である。
【図2】(e)および(f)は、図1に続く手順を示した工程図である。
【図3】(a)〜(d)は、本発明に係るジブストラット自力組立方法の第二実施形態についてその手順を示した工程図である。
【図4】(e)〜(g)は、図3に続く手順を示した工程図である。
【図5】(a)および(b)は、本発明に係るジブストラット自力組立方法の第三実施形態を示した説明図である。
【図6】従来のジブストラット組立方法を示す説明図である。
【符号の説明】
1 下部走行体
2 上部旋回体
3 タワーブーム
4 タワーヘッド
5 ジブ
6 フロントストラット
7 リヤストラット
8 ガントリ
8a 前側支柱
8b 補助ガイドシーブ
9 ブーム起伏ウインチ
10a ブーム起伏ロープ
10b ブームガイライン
11 主巻ウインチ
12 補巻ウインチ
13 補助ウインチ
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a jib strut self-assembly method for a tower crane equipped with a luffing jib or a fixed jib.
[0002]
[Prior art]
The tower crane is assembled by disassembling the front attachment and the fuselage and transporting them separately.
[0003]
FIG. 6 shows a crane with a luffing jib before assembly, in which the front attachment is horizontally laid down.
[0004]
A tower boom 51 is attached to a front portion of the body 50, and a tower head 52 is provided at a tip of the tower boom 51. A jib 53 is pivotally attached to a tip of the tower head 52.
[0005]
A front strut (sometimes called a front post) 54 and a rear strut (sometimes called a rear post) 55 are pivotally connected to the rear part of the jib 53 as jib struts, respectively. The distal end of the strut 54 is connected by a jib support rope (not shown), and a jib hoisting rope 56 is bridged between sheaves provided at the distal end of the front strut 54 and the distal end of the rear strut 55. I have.
[0006]
In the drawing, reference numeral 57 denotes a mast, and 58 denotes a gantry, and a boom hoisting rope is stretched between sheaves provided at respective end portions. Reference numeral 59 denotes a winch drum.
[0007]
[Problems to be solved by the invention]
However, when assembling the jib strut in the conventional tower crane, an auxiliary crane is prepared separately from the tower crane to raise the rear strut 55, and the rear strut 55 is raised to an angle that can be hoisted by the winch rope from the winch drum 59. Needed.
[0008]
This is because the rear strut 55 cannot be directly caused by the winch drum 59 because the rear strut 55 is in a horizontal posture when the front attachment is lowered on the ground.
[0009]
Also, in the method of directly supporting the rear strut 55 with the rope from the winch drum 59 even when disassembling the jib strut, the rear strut 55 is turned over when the rear strut 55 is overturned and the rear strut 55 and the rope become parallel. However, there is a possibility that the front strut 54 may be damaged by colliding with the lower strut 54.
[0010]
As described above, the conventional tower crane has a disadvantage that an auxiliary crane is always required when assembling or disassembling the jib strut.
[0011]
The present invention has been made in consideration of the problems of the conventional tower crane as described above, and provides a crane jib strut self-assembly method capable of assembling a jib strut by itself without requiring an auxiliary crane. It is.
[0012]
[Means for Solving the Problems]
The present invention relates to a tower crane including a tower boom, a jib, and a jib strut for supporting the jib as a front attachment at a front portion of the fuselage. A jib strut self-assembly method for a tower crane that causes a jib strut by itself by winding up a rope connected to a jig at a position higher than the end of the jib strut by a winding device via guide means arranged on the fuselage side. .
[0013]
In the present invention, the above-mentioned airframe is provided with an up-and-down support for raising and lowering the tower boom, and the rope can be wound up through guide means provided on the up-and-down support.
[0014]
A gantry and a mast are shown as specific examples of the undulating support.
[0015]
The present invention provides a tower crane including a tower boom, a jib, and a jib strut for supporting the jib as a front attachment to a front portion of the fuselage. In the state that the guide means is placed on the ground, the guide means protrudes from the tower boom so as to be higher than the tip of the jib strut, and a rope connected to the tip of the jib strut is wound by a winding device via the guide means. This is a jib strut self-assembly method of a tower crane which causes a jib strut by itself when taken.
[0016]
In the present invention, assembling the jib strut means that the jib strut connected to the rear part of the jib is set in a predetermined posture in a state where the front attachment is fallen to the ground.
[0017]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, the present invention will be described in detail based on embodiments shown in the drawings.
[0018]
FIGS. 1 and 2 show the individual steps of the jib strut self-standing assembly method according to the present invention, and show a state where the front attachment is lowered to the ground.
[0019]
First, the overall configuration of the tower crane will be described with reference to FIG.
[0020]
Reference numeral 1 denotes a lower traveling body, and 2 denotes an upper revolving body as an airframe. A tower head 4 is provided at the tip of the tower boom 3, and a jib 5 is pivotally attached to the tip of the tower head 4.
[0021]
At the rear of the jib 5, a front strut 6 and a rear strut 7 as jib struts are respectively pivoted. A gantry 8 as an undulating support is disposed at a rear portion of the upper revolving unit 2, and an auxiliary guide sheave 8 b is provided at a substantially middle position of a front support 8 a of the gantry 8. The auxiliary guide sheave 8b is arranged at a position higher than the tip of the jib strut and functions as guide means.
[0022]
The auxiliary guide sheave 8b guides the rope wound around the third winch, and is used not only at the time of raising and lowering the jib, but also at the time of lifting and hanging optional equipment such as an excavator, for example. At the time of work, the excavator is hung on the tip of a rope hung on the auxiliary guide sheave 8b.
[0023]
The tower boom 3 is connected to a boom hoisting rope 10a from a boom hoisting winch 9 via a boom guy line 10b, and rises and lowers by winding or lowering the rope 10a.
[0024]
On the other hand, the jib 5 is connected via a jib hoisting rope wound up by a jib hoisting winch (not shown), jib struts 6, 7 and a jib guy line, and is raised and lowered by winding or lowering the jib hoisting rope. Has become.
[0025]
In the figure, reference numeral 11 denotes a main winding winch and 12 denotes an auxiliary winding winch, which are used for hoisting and lowering a suspended load, respectively. The auxiliary winch 12 is also used to raise the rear strut 7. 13 is an auxiliary winch used for the jib.
[0026]
Reference numeral 16 denotes a strut-side guy cable whose one end is attached to the distal end side of the rear strut 7, and reference numeral 17 denotes a boom-side strut guy cable whose one end is attached to a bracket on the rear side of the base end of the boom. By connecting the strut-side guy cable 16 and the boom-side strut guy cable 17 in a self-assembly process to be described later, a strut guy cable as a connecting means for connecting and supporting the strut tip and the boom base end is formed.
[0027]
The jib strut self-standing assembly method of the tower crane having the above configuration will be described below.
[0028]
In FIG. 1A, a rope 14 pulled out from the auxiliary winch 12 is passed through the auxiliary guide sheave 8 b of the gantry 8, pulled out to the jib 5 side, and connected to the tip of the rear strut 7.
[0029]
In FIG. 1B, when the auxiliary winding winch 12 is driven to hoist and the rope 14 is wound, a predetermined angle θ is secured between the rear strut 7 and the rope 14 to directly connect the rear strut 7 to the rope. Can cause. Note that the predetermined angle θ is preferably 3 ° or more. It is sufficient that the angle θ be an angle that can be caused mechanically, but it is preferable that the angle θ be about 3 ° or more.
[0030]
In FIG. 1 (c), when the rear strut 7 is raised in the direction of arrow A, the rope 14 is wound up while unwinding the rope 15 bridged between the rear strut 7 and the front strut 6. This prevents the load of the front strut 6 from being applied to the auxiliary winch 12 when the rope 14 is hoisted.
[0031]
In FIG. 1 (d), when the rear strut 7 stands at approximately 90 °, the rope 15 is stretched so that the rear strut 7 does not reverse in the direction of the arrow A ′ by its own weight.
[0032]
In FIG. 2E, the strut guy cable 16 is connected to the boom-side strut guy cable 17 while the rope 15 between the jib struts is being extended, and the strut backstop 18 is attached.
[0033]
In FIG. 2F, the rope 15 between the jib struts is wound up, and the strut guy cable 16 is stretched as shown in the figure.
[0034]
Even when the jib strut is disassembled, the rope 14 passing through the sheave 8b of the gantry 8 is connected to the tip of the rear strut 7, and the rope 14 is extended so that the rear strut 7 can safely fall down to the horizontal position. it can. At this time, since the angle θ is secured between the rope 14 and the rear strut 7 until the rear strut 7 assumes the horizontal posture (see FIG. 1B), the rear strut 7 is turned to the jib 5 side. Thus, the trouble of colliding with the front strut 6 can be solved.
[0035]
FIGS. 3 and 4 show a second embodiment of the present invention, and show a method of assembling the rear strut 7 by itself through a sheave of a mast as an undulating support.
[0036]
In the following drawings, the same components as those in FIG. 1 are denoted by the same reference numerals, and description thereof will be omitted.
[0037]
As shown in FIG. 3A, the rope 20 drawn out from the auxiliary winch 12 is suspended through a sheave 21a as a guide means provided at the upper end of the mast 21.
[0038]
As shown in FIG. 3B, the rope 20 is further extended and connected to the tip of the rear strut 7.
[0039]
As shown in FIG. 3C, the mast 21 is raised to approximately 90 ° while the rope 20 is loosened.
[0040]
As shown in FIG. 3D, the rope 20 is wound up by the auxiliary winch 12, and the rear strut 7 is raised in the arrow A direction. At this time, the rope 22 between the rear strut 7 and the front strut 6 is loosened so that the front strut 6 does not rise. When the rear strut 7 is caused to occur, the rear strut 7 may be directly caused by the rope 20 because a predetermined angle θ ′ is secured between the rear strut 7 and the rope 20 (see FIG. 3C). it can.
[0041]
As shown in FIG. 4E, the strut guy line 22 is connected to the boom-side strut guy line 22a with the rear strut 7 further lowered.
[0042]
As shown in FIG. 4F, the rear strut 7 is raised, and the strut backstop 23 is fixed.
[0043]
As shown in FIG. 4G, a boom guy line 24 and a jib guy line 25 are attached.
[0044]
Even when the jib strut is disassembled, the rope 20 passing through the sheave 21a at the tip of the mast 21 is connected to the tip of the rear strut 7, and the rope 20 is extended so that the rear strut 7 safely falls down to the horizontal position. be able to. At this time, since the angle θ is secured between the rope 20 and the rear strut 7 until the rear strut 7 becomes horizontal (see FIG. 3C), the rear strut 7 is turned to the jib 5 side. Therefore, the trouble of colliding with the front strut 6 can be solved.
[0045]
FIG. 5 shows a third embodiment of the present invention, in which a support member 30 is protruded from the tip of a tower boom 3, and a rope 31 is passed through a sheave 30 a provided at the upper end of the support member 30. And how to assemble the rear strut 7 by itself.
[0046]
In this self-assembly method, a predetermined angle θ ″ is secured between the rear strut 7 and the rope 31 only when the rear strut 7 is raised by providing the support member 30 as shown in FIG. Have to be able to.
[0047]
When the rear strut 7 is raised to some extent, the rope 31 is wound up by the winch directly away from the sheave 30a as shown in FIG.
[0048]
The sheave 30a of the support member 30 functions as guide means.
[0049]
In the above embodiment, a tower crane equipped with a luffing jib has been described as an example. However, the present invention is not limited to this, and the present invention can be applied to a tower crane equipped with a fixed jib.
[0050]
In the above-described embodiment, the rod-shaped guy cable having the connection plugs at both ends is used for connecting the boom base end and the jib strut tip, but the present invention is not limited to this. There may be.
[0051]
Further, in the above embodiment, the guide means is constituted by a sheave, but is not limited thereto, and may be constituted by a roller, a half sheave, or the like.
[0052]
Furthermore, a detachable pulley may be connected to the above-mentioned sheave position to perform the self-assembly work. The use of a detachable pulley has an advantage that the operation of removing the rope after assembly is facilitated.
[0053]
【The invention's effect】
As is apparent from the above description, according to the first aspect of the present invention, the rope connected to the tip of the jib strut is placed at a position higher than the tip of the jib strut in a state where the front attachment is tilted to the ground. The jib strut can be raised by itself without the need for an auxiliary crane, since the winding device is used to take up the film via the guide means disposed on the side of the fuselage.
[0054]
According to the second aspect of the present invention, the rope is wound through the guide means of the upright support column for raising and lowering the tower boom provided on the body, so that the guide means provided on the existing gantry and mast is used. And can cause jib strut.
[0055]
According to the third aspect of the present invention, the rope connected to the tip of the jib strut is wound through the guide means of the support member protruding from the tower boom so as to be higher than the tip of the jib strut. As a result, the jib strut can be triggered on its own.
[Brief description of the drawings]
1 (a) to 1 (d) are process diagrams showing the procedure of a first embodiment of a jib strut self-assembly method according to the present invention.
FIGS. 2 (e) and 2 (f) are process diagrams showing a procedure following FIG.
FIGS. 3 (a) to 3 (d) are process diagrams showing the procedure of a second embodiment of the jib strut self-assembly method according to the present invention.
4 (e) to 4 (g) are process diagrams showing a procedure following FIG.
FIGS. 5A and 5B are explanatory views showing a third embodiment of the jib strut self-assembly method according to the present invention.
FIG. 6 is an explanatory view showing a conventional jib strut assembling method.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Lower traveling body 2 Upper revolving structure 3 Tower boom 4 Tower head 5 Jib 6 Front strut 7 Rear strut 8 Gantry 8a Front support column 8b Auxiliary guide sheave 9 Boom hoisting winch 10a Boom hoisting rope 10b Boom guy line 11 Main winding winch 12 Hoisting winch 13 Auxiliary winch

Claims (3)

機体の前部にフロントアタッチメントとして、タワーブームと、ジブと、このジブを支持するジブストラットとを備えたタワークレーンにおいて、
上記フロントアタッチメントを地上に倒した状態で、上記ジブストラットの先端部に接続したロープをそのジブストラット先端部よりも高い位置で上記機体側に配置されたガイド手段を介し巻取装置で巻き取ることにより、上記ジブストラットを自力で引き起こすことを特徴とするタワークレーンのジブストラット自力組立方法。
In a tower crane having a tower boom, a jib, and a jib strut that supports the jib as a front attachment at the front of the fuselage,
Winding the rope connected to the tip of the jib strut at a position higher than the tip of the jib strut by a winding device via a guide means arranged on the fuselage side in a state where the front attachment is lowered to the ground. And causing the jib strut to cause the jib strut by itself.
上記機体にタワーブームを起伏させるための起伏支柱を備え、その起伏支柱に設けられたガイド手段を介して上記ロープを巻き取る請求項1記載のタワークレーンのジブストラット自力組立方法。2. The jib strut self-assembly method for a tower crane according to claim 1, further comprising: an up-and-down support for raising and lowering the tower boom, and winding the rope through guide means provided on the up-and-down support. 機体の前部にフロントアタッチメントとして、タワーブームと、ジブと、このジブを支持するジブストラットとを備えたタワークレーンにおいて、
上端部にガイド手段を備えた支持部材を、上記フロントアタッチメントを地上に倒した状態でそのガイド手段が上記ジブストラットの先端部よりも高い位置となるように上記タワーブームに突設し、上記ジブストラットの先端部に接続したロープをそのガイド手段を介し巻取装置で巻き取ることにより、上記ジブストラットを自力で引き起こすことを特徴とするタワークレーンのジブストラット自力組立方法。
In a tower crane having a tower boom, a jib, and a jib strut that supports the jib as a front attachment at the front of the fuselage,
A support member provided with a guide means at an upper end thereof is protruded from the tower boom so that the guide means is located at a position higher than a tip end of the jib strut in a state where the front attachment is lowered to the ground, and A method for self-assembly of a jib strut for a tower crane, wherein the jib strut is caused to rise by itself by winding a rope connected to a tip portion of the strut by a winding device through a guide means.
JP2002238543A 2002-08-19 2002-08-19 Jib strut self-assembling method for tower crane Pending JP2004075294A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002238543A JP2004075294A (en) 2002-08-19 2002-08-19 Jib strut self-assembling method for tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002238543A JP2004075294A (en) 2002-08-19 2002-08-19 Jib strut self-assembling method for tower crane

Publications (1)

Publication Number Publication Date
JP2004075294A true JP2004075294A (en) 2004-03-11

Family

ID=32021935

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002238543A Pending JP2004075294A (en) 2002-08-19 2002-08-19 Jib strut self-assembling method for tower crane

Country Status (1)

Country Link
JP (1) JP2004075294A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102013219115A1 (en) 2012-09-26 2014-03-27 Kobelco Cranes Co., Ltd. Crane and crane assembly process
JP2014065573A (en) * 2012-09-26 2014-04-17 Kobelco Cranes Co Ltd Lower gib
JP2017007787A (en) * 2015-06-19 2017-01-12 コベルコ建機株式会社 Raising-up method of strut and crane
JP2017105559A (en) * 2015-12-07 2017-06-15 コベルコクレーン株式会社 Strut assembly auxiliary device and strut assembly method
JP2018048015A (en) * 2016-09-23 2018-03-29 コベルコ建機株式会社 Method for assembling mobile crane
JP2018048014A (en) * 2016-09-23 2018-03-29 コベルコ建機株式会社 Method for assembling mobile crane
JP2018167973A (en) * 2017-03-30 2018-11-01 コベルコ建機株式会社 Uprising method of derricking member and crane
JP2018203457A (en) * 2017-06-05 2018-12-27 コベルコ建機株式会社 Raising-up method of strut and crane
JP2019043750A (en) * 2017-09-06 2019-03-22 コベルコ建機株式会社 Crane and method for raising strut of crane
CN112408216A (en) * 2020-10-29 2021-02-26 中联重科股份有限公司 Steel wire rope connecting structure, steel wire rope threading device, threading system and threading method
JP2021050063A (en) * 2019-09-25 2021-04-01 コベルコ建機株式会社 Crane assembling method and crane
WO2024018911A1 (en) * 2022-07-21 2024-01-25 コベルコ建機株式会社 Crane and method for assembling and disassembling crane
WO2024018913A1 (en) * 2022-07-21 2024-01-25 コベルコ建機株式会社 Crane and crane assembly method

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102013219115B4 (en) * 2012-09-26 2021-05-06 Kobelco Cranes Co., Ltd. Crane and crane assembly procedures
JP2014065573A (en) * 2012-09-26 2014-04-17 Kobelco Cranes Co Ltd Lower gib
US9206021B2 (en) 2012-09-26 2015-12-08 Kobelco Cranes Co., Ltd. Crane and crane assembling method
DE102013219115A1 (en) 2012-09-26 2014-03-27 Kobelco Cranes Co., Ltd. Crane and crane assembly process
JP2017007787A (en) * 2015-06-19 2017-01-12 コベルコ建機株式会社 Raising-up method of strut and crane
JP2017105559A (en) * 2015-12-07 2017-06-15 コベルコクレーン株式会社 Strut assembly auxiliary device and strut assembly method
JP2018048014A (en) * 2016-09-23 2018-03-29 コベルコ建機株式会社 Method for assembling mobile crane
JP2018048015A (en) * 2016-09-23 2018-03-29 コベルコ建機株式会社 Method for assembling mobile crane
JP2018167973A (en) * 2017-03-30 2018-11-01 コベルコ建機株式会社 Uprising method of derricking member and crane
DE102018107565B4 (en) 2017-03-30 2022-01-20 Kobelco Construction Machinery Co. Ltd. METHOD OF LIFTING A RAISABLE AND LOWERABLE ELEMENT AND CRANE
JP2018203457A (en) * 2017-06-05 2018-12-27 コベルコ建機株式会社 Raising-up method of strut and crane
JP2019043750A (en) * 2017-09-06 2019-03-22 コベルコ建機株式会社 Crane and method for raising strut of crane
JP2021050063A (en) * 2019-09-25 2021-04-01 コベルコ建機株式会社 Crane assembling method and crane
JP7298419B2 (en) 2019-09-25 2023-06-27 コベルコ建機株式会社 Crane assembly method and crane
CN112408216A (en) * 2020-10-29 2021-02-26 中联重科股份有限公司 Steel wire rope connecting structure, steel wire rope threading device, threading system and threading method
WO2024018911A1 (en) * 2022-07-21 2024-01-25 コベルコ建機株式会社 Crane and method for assembling and disassembling crane
WO2024018913A1 (en) * 2022-07-21 2024-01-25 コベルコ建機株式会社 Crane and crane assembly method

Similar Documents

Publication Publication Date Title
JP5693031B2 (en) Assembly method of mobile lift crane
JP2010241604A5 (en)
JP2007302352A (en) Crane, and crane boom derricking device
JP2008127150A (en) Crane
JP2004075294A (en) Jib strut self-assembling method for tower crane
JP4857880B2 (en) Mobile crane boom mounting method and boom mounting tool
JP6645222B2 (en) How to attach a crane jib
JP4415643B2 (en) crane
JP2010018355A (en) Boom derricking device
JP4011659B2 (en) How to hang back tension wire rope in luffing jib back tension device
JP6683086B2 (en) Mobile crane assembly method
JP6638434B2 (en) Crane boom mounting method
JP7298419B2 (en) Crane assembly method and crane
JP7306080B2 (en) Crane and crane assembly method
JP3571424B2 (en) Luffing jib back tension device
JP6984395B2 (en) Crane and crane assembly method
JP2547044B2 (en) Jib loading and unloading method and device in crane
JP6658020B2 (en) Crane and crane assembling method
JP7234811B2 (en) A crane strut, a method for folding a crane strut, and a method for assembling a crane strut
JPH11292472A (en) Crane
JP4245361B2 (en) Self-propelled tower crane
WO2024018911A1 (en) Crane and method for assembling and disassembling crane
WO2024018913A1 (en) Crane and crane assembly method
JP6579172B2 (en) Crane and crane strut raising method
JP2019199310A (en) Specification changing method of crane and specification-changeable crane

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040921

A711 Notification of change in applicant

Effective date: 20040918

Free format text: JAPANESE INTERMEDIATE CODE: A712

RD03 Notification of appointment of power of attorney

Effective date: 20041215

Free format text: JAPANESE INTERMEDIATE CODE: A7423

A977 Report on retrieval

Effective date: 20070125

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070130

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02