JP2000053375A - Vertical carrier system corresponding to slewing overhead crane - Google Patents

Vertical carrier system corresponding to slewing overhead crane

Info

Publication number
JP2000053375A
JP2000053375A JP10230584A JP23058498A JP2000053375A JP 2000053375 A JP2000053375 A JP 2000053375A JP 10230584 A JP10230584 A JP 10230584A JP 23058498 A JP23058498 A JP 23058498A JP 2000053375 A JP2000053375 A JP 2000053375A
Authority
JP
Japan
Prior art keywords
rail
lift
lifting
load
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10230584A
Other languages
Japanese (ja)
Inventor
Yutaro Omote
佑太郎 表
Yuichi Ikeda
雄一 池田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP10230584A priority Critical patent/JP2000053375A/en
Publication of JP2000053375A publication Critical patent/JP2000053375A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Leg Units, Guards, And Driving Tracks Of Cranes (AREA)
  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a vertical carrier system corresponding to a slewing over head crane capable of improving carrier efficiency of a lift by making a task of a slewing overhead crane and a lifting work of this lift independent. SOLUTION: A rail for load delivery 24 arranged in parallel to a crane rail 16 is mounted on a temporarily provided roof frame 14. A lift 22 is provided with a rail for lifting 26 which is arranged along an extending direction of the rail for load delivery 24 and is linearly butted against an end of the rail for load delivery 24 at a lifting location. The rail for lifting 26 is provided with a lift hoist 28 so as to be freely travelable. The lift hoist 28 is made freely transferable between both of these rails 24, 26 in a state that the rail for lifting 26 is butted against the rail for load delivery 24. The lift hoist 28 travels on the rail for load delivery 24, temporarily places a slung load on a work floor 12a and receives this load by a slewing overhead crane 10.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、多層階建物を構築
するにあたって、その施工階に設けた旋回式天井クレー
ンに、資材などの吊り荷をリフトによって揚重するよう
になった垂直搬送システムに関し、とりわけ、リフトに
よる吊り荷の搬送効率を向上するようにした旋回式天井
クレーンに対応した垂直搬送システムに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a vertical transport system in which a suspended load such as materials is lifted by a lift on a revolving overhead crane provided on a construction floor when a multi-story building is constructed. In particular, the present invention relates to a vertical transfer system for a swiveling overhead crane that improves the transfer efficiency of a suspended load by a lift.

【0002】[0002]

【従来の技術】従来ではRC構造の高層ビルの建設用仮
設設備として、全天候型の仮設架構が提案されている。
この仮設架構は、構築予定建物の形状に合わせてその周
囲に複数本の仮設支柱を立設すると共に、各仮設支柱間
の上部に屋根架構を支持して、建物の高さ増加に伴って
仮設支柱を上方に継足しつつ該屋根架構を持上げること
により、天候に影響されることなく工事を遂行できるよ
うになっている。また、前記屋根架構の下面には天井ク
レーンを配置して、リフトにより揚重された吊り荷を、
この天井クレーンを通じて施工階の各部に搬送して組立
てるようになっている。また、近年では上記天井クレー
ンに旋回式のものが用いられ、リフトによって揚重され
た吊り荷を施工階の任意場所に効率良く搬送できるよう
になっている。
2. Description of the Related Art Conventionally, all-weather temporary frames have been proposed as temporary facilities for the construction of high-rise buildings having an RC structure.
This temporary frame is constructed by erecting a plurality of temporary columns around the building to be constructed and supporting a roof frame on the upper part between the temporary columns. By lifting the roof frame while supporting the pillars upward, construction can be performed without being affected by the weather. Also, an overhead crane is arranged on the lower surface of the roof frame, and the suspended load lifted by the lift is
It is designed to be transported to each part of the construction floor through this overhead crane and assembled. In recent years, a revolving type overhead crane has been used, and a suspended load lifted by a lift can be efficiently transported to an arbitrary place on a construction floor.

【0003】図5は旋回式天井クレーン2を用いた従来
の垂直搬送システム1を示す平面図で、該旋回式天井ク
レーン2は水平方向の旋回を可能とする荷吊りブーム3
を備え、この荷吊りブーム3は仮設屋根架構4に設けた
レール5を移動自在となり、かつ、この荷吊りブーム3
の先端部で吊荷を昇降するようになっている。即ち、こ
の場合は、上記レール5にこれと直角方向を指向するガ
ーダ6が走行自在に取り付けられるとともに、このガー
ダ6に走行自在にホイスト7が取り付けられており、こ
のホイスト7に上記荷吊りブーム3が旋回自在に取り付
けられる。従って、上記旋回式天井クレーン2は、荷吊
りブーム3がホイスト7を介して上記レール5および上
記ガーダ6に沿った2次元移動が可能となり、かつ、該
荷吊りブーム3自体の旋回機能により、吊り荷を施工階
の隅々まで搬送できるようになっている。
FIG. 5 is a plan view showing a conventional vertical transfer system 1 using a swiveling overhead crane 2. The swiveling overhead crane 2 is a load-bearing boom 3 that can swing horizontally.
The load-bearing boom 3 is movable on a rail 5 provided on a temporary roof frame 4, and the load-bearing boom 3
The lifting load is raised and lowered at the tip of the. That is, in this case, a girder 6 oriented in a direction perpendicular to the rail 5 is attached to the rail 5 so as to run freely, and a hoist 7 is attached to the girder 6 so as to run freely. 3 is attached so as to be free to turn. Accordingly, the swing type overhead traveling crane 2 allows the load hanging boom 3 to move two-dimensionally along the rails 5 and the girder 6 via the hoist 7, and the swing function of the load hanging boom 3 itself. The suspended load can be transported to every corner of the construction floor.

【0004】一方、上記旋回式天井クレーン2が設けら
れる構築予定建物の側面には、地上から吊り荷を施工階
まで揚重するリフト8が設けられる。このリフト8は地
上で荷台8aに載置した吊り荷を施工階まで揚重する一
方、上記旋回式天井クレーン2は、ガーダ6をレール5
に走行させてリフト8方向に移動するとともに、ホイス
ト7をガーダ6に走行させて同様にリフト方向に移動
し、荷吊りブーム3で上記リフト8の吊り荷を吊り込む
ようになっている。
On the other hand, a lift 8 for lifting suspended loads from the ground to a construction floor is provided on the side of the building to be constructed in which the revolving overhead crane 2 is provided. The lift 8 lifts the suspended load placed on the bed 8a on the ground to the construction floor, while the swing type overhead crane 2 moves the girder 6 to the rail 5
And the hoist 7 is moved to the girder 6 in the same direction as the lift, and the load of the lift 8 is suspended by the load suspending boom 3.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、かかる
従来の旋回式天井クレーンに対応した垂直搬送システム
にあっては、リフト8で揚重した吊り荷を旋回式天井ク
レーン2に受け渡すにあたって、上述したように吊り荷
を載置したリフト8を施工階まで揚重し、この吊り荷を
旋回式天井クレーン2の荷吊りブーム3がリフト8まで
移動して受け取りに行くようになっている。このため、
旋回式天井クレーン2が吊り荷の建込みなどで他の仕事
を行っている場合は、この仕事を終えるまでリフト8は
揚重位置で待機することになる。このため、リフト8は
この待機時間によって搬送効率が大幅に低下し、延いて
は、全体工期に遅れが生じてしまうという課題があっ
た。
However, in such a vertical transport system corresponding to the conventional swiveling overhead crane, when the suspended load lifted by the lift 8 is transferred to the swiveling overhead crane 2, the above-described operation is performed. The lift 8 on which the suspended load is placed is lifted to the construction floor, and the suspended boom 3 of the revolving overhead crane 2 moves to the lift 8 to receive the suspended load. For this reason,
When the revolving overhead crane 2 is performing other work such as erection of a suspended load, the lift 8 waits at the lifting position until the work is completed. For this reason, there has been a problem that the transport efficiency of the lift 8 is significantly reduced due to the standby time, and a delay is caused in the overall construction period.

【0006】そこで、本発明はかかる従来の課題に鑑み
て成されたもので、リフトで施工階まで揚重した吊り荷
を、この施工階の内方まで搬送して作業床に載置してお
く一方、旋回式天井クレーンは吊り荷をこの作業床から
受け取ることにより、旋回式天井クレーンの仕事とリフ
トの揚重作業とを独立させて、該リフトの搬送効率を向
上するようにした旋回式天井クレーンに対応した垂直搬
送システムを提供することを目的とする。
Accordingly, the present invention has been made in view of such conventional problems, and a suspended load lifted to a construction floor by a lift is conveyed to the inside of the construction floor and placed on a work floor. On the other hand, the swiveling overhead crane receives the suspended load from this work floor, so that the work of the swiveling overhead crane and the lifting operation of the lift are independent, and the transport efficiency of the lift is improved. An object is to provide a vertical transfer system corresponding to an overhead crane.

【0007】[0007]

【課題を解決するための手段】かかる目的を達成するた
めに本発明の請求項1に示す旋回式天井クレーンに対応
した垂直搬送システムは、施工階の天井部分に設けたク
レーンレールに移動自在に取り付けられたクレーンホイ
ストと、このクレーンホイストに設けた水平方向に旋回
自在な旋回式天井クレーンと、地上などの荷吊り位置か
ら上記施工階の揚重位置に吊り荷を揚重するリフトと、
を備えた旋回式天井クレーンに対応した垂直搬送システ
ムにおいて、上記天井部分に取り付けられ、上記旋回式
天井クレーンの荷受け可能な範囲内に配置された荷送用
レールと、上記リフトに設けられ、上記揚重位置で該荷
送用レールと接続される揚重用レールと、該揚重用レー
ルと上記荷送用レールとの間で走行自在なリフトホイス
トとを備える。
In order to achieve the above object, a vertical transportation system corresponding to a swing type overhead traveling crane according to the present invention is provided so as to be movable on a crane rail provided on a ceiling portion of a construction floor. An attached crane hoist, a horizontally movable swiveling overhead crane provided on the crane hoist, and a lift that lifts a suspended load from a suspended position on the ground or the like to a lifting position on the construction floor,
In a vertical transfer system corresponding to a swiveling overhead crane provided with, a loading rail attached to the ceiling portion and arranged within a loadable range of the swiveling overhead crane, provided on the lift, A lifting rail connected to the loading rail at a lifting position; and a lift hoist that can travel between the lifting rail and the loading rail.

【0008】また、本発明の請求項2に示す旋回式天井
クレーンに対応した垂直搬送システムは、上記リフト
は、上記荷吊り位置と上記揚重位置との間に垂直に設け
られて、上記揚重用レールを昇降案内するガイド部材を
備え、このガイド部材は、上記揚重用レールの長さ方向
両端部に該揚重用レールをその幅方向に挟むように間隔
を隔てて配設する。
According to a second aspect of the present invention, there is provided a vertical transport system corresponding to a swing type overhead traveling crane, wherein the lift is provided vertically between the load hanging position and the lifting position, and A guide member is provided for guiding the heavy rail up and down. The guide member is disposed at both ends in the length direction of the lifting rail with a space therebetween so as to sandwich the lifting rail in the width direction.

【0009】以上の構成により本発明の旋回式天井クレ
ーンに対応した垂直搬送システムの作用は、請求項1で
はリフトの揚重用レールに、荷吊りしたリフトホイスト
が走行自在となっており、このリフトホイストは、リフ
トの揚重位置で該揚重用レールが荷送用レールと接続さ
れることにより乗り移り、そして、該荷送用レールを走
行することができる。従って、上記リフトホイストは荷
吊りした状態でリフトから荷送用レールを介して施工階
まで搬送することができるため、この施工階に吊り荷を
荷下ろしして仮置きすることができる。そして、旋回式
天井クレーンはリフトまで吊り荷を取りに行くことな
く、施工階に仮置きされた吊り荷を吊り上げて目的の場
所まで搬送することになる。
With the above construction, the operation of the vertical transport system corresponding to the swiveling overhead crane of the present invention is as follows. In the first aspect, the lift hoist suspended from the load can travel on the lift rail of the lift. The hoist can move by the lifting rail being connected to the loading rail at the lift position of the lift, and can travel on the loading rail. Therefore, the lift hoist can be transported from the lift to the construction floor via the loading rail in a suspended state, so that the suspended load can be unloaded and temporarily stored on this construction floor. Then, the revolving overhead crane lifts the suspended load temporarily placed on the construction floor and conveys it to the destination without going to the lift to retrieve the suspended load.

【0010】一方、上記施工階に吊り荷を仮置きしたリ
フトホイストは、空状態で上記荷送用レールを逆に走行
して上記揚重用レールまで戻ることができる。このた
め、この揚重用レールまで戻った時点でリフトを下降し
て、次の吊り荷を積み込む態勢を取ることができるよう
になり、このリフトによる揚重作業と上記旋回式天井ク
レーンによる搬送作業とが独立されることになる。従っ
て、リフトは旋回式天井クレーンの仕事が終わるのを待
つことなく、次の作業へと進めることができるため、該
リフトの搬送効率を向上することができる。
[0010] On the other hand, the lift hoist in which the suspended load is temporarily placed on the construction floor can travel in reverse on the loading rail and return to the lifting rail. For this reason, when returning to the lifting rail, the lift can be lowered to prepare for the loading of the next suspended load, and the lifting work by this lift and the transfer work by the above-mentioned revolving overhead crane can be performed. Will be independent. Therefore, the lift can proceed to the next operation without waiting for the work of the swiveling overhead crane to be completed, so that the transport efficiency of the lift can be improved.

【0011】また、請求項2ではリフトで揚重される吊
り荷は、該揚重用レールの長さ方向両端部にこのレール
をその幅方向に挟むように間隔を隔てて配設されたガイ
ド部材間に挟まれた状態でリフトホイストに吊り下げら
れる。従って、上記吊り荷が揚重用レールの昇降を案内
するガイド部材と干渉することがなく、揚重用レールの
長さを超える長尺の吊り荷であっても揚重および施工階
への搬送が可能となる。
According to a second aspect of the present invention, a lifted load lifted by a lift is provided at both ends in the length direction of the lifting rail with a guide member disposed at a distance so as to sandwich the rail in the width direction thereof. It is hung by a lift hoist while being sandwiched between. Therefore, the above-mentioned suspended load does not interfere with the guide member for guiding the lifting rail up and down, and even a long suspended load exceeding the length of the lifting rail can be lifted and transported to the construction floor. Becomes

【0012】[0012]

【発明の実施の形態】以下、本発明の実施形態を添付図
面を参照して詳細に説明する。図1から図4は本発明に
かかる旋回式天井クレーンに対応した垂直搬送システム
の一実施形態を示し、図1は旋回式天井クレーンを配置
した施工階の平面図、図2は旋回式天井クレーンを用い
て構築しようとする建物架構の正面図、図3は旋回式天
井クレーンを用いて構築しようとする建物架構の側面
図、図4はリフトの全体構成を示す斜視図である。
Embodiments of the present invention will be described below in detail with reference to the accompanying drawings. 1 to 4 show an embodiment of a vertical transfer system corresponding to a swiveling overhead crane according to the present invention. FIG. 1 is a plan view of a construction floor where a swiveling overhead crane is arranged, and FIG. 2 is a swiveling overhead crane. FIG. 3 is a side view of a building frame to be constructed by using a revolving overhead crane, and FIG. 4 is a perspective view showing the entire configuration of a lift.

【0013】即ち、本発明の旋回式天井クレーンに対応
した垂直搬送システムの基本構成は、施工階12の天井
部分14に設けたクレーンレール16に移動自在に取り
付けられたクレーンホイスト18と、このクレーンホイ
スト18に水平方向の旋回を自在に設けた荷吊りブーム
20の先端部で吊荷を昇降するようになった旋回式天井
クレーン10と、この旋回式天井クレーン10に荷渡し
するために、地上Gなどの荷吊り位置から上記施工階1
2の揚重位置に吊り荷を揚重するリフト22と、を備え
る。
That is, the vertical transport system corresponding to the swing type overhead traveling crane of the present invention comprises a crane hoist 18 movably attached to a crane rail 16 provided on a ceiling portion 14 of a construction floor 12, and a crane hoist 18. A swiveling overhead crane 10 that lifts and lowers a suspended load at the tip of a load hoisting boom 20 that freely swings horizontally in a hoist 18. Construction floor 1 from the position where the load is suspended such as G
And a lift 22 for lifting the suspended load at the second lifting position.

【0014】そして、上記天井部分14に取り付けられ
るとともに、上記クレーンレール16に平行配置される
荷送用レール24と、上記リフト22に設けられ、上記
荷送用レール24の延設方向に沿って配置されるととも
に、揚重位置で該荷送用レール24端に一直線状に突き
合わされる揚重用レール26と、該揚重用レール26に
走行自在に設けられて荷吊りし、この揚重用レール26
が上記荷送用レール24に突き合わされた状態で、これ
ら両レール24,26間で乗り移り自在となり、かつ、
該荷送用レール24を走行自在なリフトホイスト28と
を備える。
A loading rail 24 attached to the ceiling portion 14 and arranged in parallel with the crane rail 16 is provided on the lift 22 along a direction in which the loading rail 24 extends. A lifting rail 26 which is arranged and is linearly abutted against the end of the loading rail 24 at the lifting position, and is provided movably on the lifting rail 26 for hanging a load.
Can be freely moved between these rails 24 and 26 in a state where the rails abut against the above-mentioned loading rail 24, and
A lift hoist 28 that can run on the rails 24 for transport is provided.

【0015】本実施形態の垂直搬送システムに用いられ
る旋回式天井クレーン10は、図1から図3に示すよう
に自動化工法によって構築される多層階の建物架構30
に適用される。この建物架構30は、仮設支柱となる4
本のポスト32で囲まれる内方に下層から上層に向かっ
て構築される。上記ポスト32には、クライミング装置
34を介して上方への盛り替えが可能となった天井部分
としての仮設屋根架構14が設けられ、この仮設屋根架
構14の下方を施工階12として建物架構30が構築さ
れる。
The swiveling overhead crane 10 used in the vertical transport system of the present embodiment is a multi-story building frame 30 constructed by an automated construction method as shown in FIGS.
Applied to This building frame 30 is used as a temporary support 4
It is constructed from the lower layer to the upper layer inwardly surrounded by the book posts 32. The post 32 is provided with a temporary roof frame 14 as a ceiling portion which can be rearranged upward through a climbing device 34, and a building frame 30 is provided below the temporary roof frame 14 as a construction floor 12. Be built.

【0016】そして、上記仮設屋根架構14の下面に上
記旋回式天井クレーン10が左右2基設けられ、これら
旋回式天井クレーン10によって施工階12の全域に亘
って吊り荷の搬送が行われる。該旋回式天井クレーン1
0のクレーンレール16はそれぞれの天井クレーン10
に対して3本づつが1組となって設けられる。該クレー
ンレール16はH型鋼を用いて形成され、上記仮設屋根
架構14の下面に取り付けられる。
On the lower surface of the temporary roof frame 14, two swing overhead cranes 10 are provided on the left and right sides. The swing overhead cranes 10 carry the suspended load over the entire construction floor 12. The swing type overhead traveling crane 1
0 crane rails 16 are each overhead crane 10
Are provided as one set for each of the three sets. The crane rail 16 is formed using H-shaped steel, and is attached to the lower surface of the temporary roof frame 14.

【0017】上記1組となった3本のクレーンレール1
6には、それぞれのクレーンレール16に跨がるように
直角方向にガーダ36が取付けられ、このガーダ36は
クレーンレール16に対して走行自在となっている。こ
のガーダ36はレールとしての機能を備え、このガーダ
36にクレーンホイスト18が走行自在に取り付けられ
る。このクレーンホイスト18には荷吊りブーム20が
水平方向の旋回を自在に取り付けられ、これの先端部に
吊り荷を玉掛けするためのフック38が昇降自在に設け
られる。
The above three crane rails 1
A girder 36 is attached to the crane rail 6 in a direction perpendicular to the crane rail 16 so as to straddle the crane rail 16. The girder 36 has a function as a rail, and the crane hoist 18 is attached to the girder 36 so as to run freely. The load hoisting boom 20 is attached to the crane hoist 18 so as to freely swing in the horizontal direction, and a hook 38 for hanging a hanging load is provided at the tip of the load hoisting boom 20 so as to be movable up and down.

【0018】上記建物架構30の上記クレーンレール1
6が指向する方向の一側中央部には、吊り荷を、荷吊り
位置としての地上Gから上記施工階12まで揚重するた
めのリフト22が設けられる。このリフト22は図4に
示すように矩形状に組み立てられた搬器22aを備え、
この搬器22aの下面には上記荷送用レール24の延設
方向に沿って配置される揚重用レール26が取り付けら
れる。この揚重用レール26はH型鋼などにより下端部
にフランジを設けてあり、この揚重用レール26にリフ
トホイスト28が走行自在に取り付けられる。このリフ
トホイスト28には、吊り荷を昇降自在に玉掛けするフ
ック39が設けられる。
The crane rail 1 of the building frame 30
A lift 22 for lifting a suspended load from the ground G as a load suspension position to the construction floor 12 is provided at a central portion on one side in a direction in which the 6 is directed. The lift 22 includes a transporter 22a assembled in a rectangular shape as shown in FIG.
A lifting rail 26 arranged along the extending direction of the loading rail 24 is attached to the lower surface of the transporter 22a. The lifting rail 26 has a flange at the lower end made of H-shaped steel or the like, and a lift hoist 28 is attached to the lifting rail 26 so as to be able to travel. The lift hoist 28 is provided with a hook 39 for hanging a suspended load up and down.

【0019】上記搬器22aは、地上Gと上記仮設屋根
架構14との間に垂直に張架されるガイド部材としての
ワイヤーロープ40,41によって昇降される。ワイヤ
ーロープ40,41は、搬器22aの揚重用レール26
が延設される方向の両端部に対応して地上Gに設けられ
る一対のウインチ38,38aから繰り出される。各ワ
イヤーロープ40,41は、各ウインチ38,38aか
ら上方に立ち上げて、仮設屋根架構14の下面にそれぞ
れ設けたシーブ群42,44を周回させた後、地上Gに
垂下して固定部46,46aに取り付けてある。そし
て、これら一対のワイヤーロープ40,41は、地上G
と仮設屋根架構14との間の垂直配索部分40a,41
aは平行に緊張配置され、この垂直配索部分40a,4
1aに上記搬器22aの両端部両側に設けたガイド穴2
2bが挿通されて、該搬器22aの昇降時の揺れを防止
するようになっている。
The transporter 22a is raised and lowered by wire ropes 40 and 41 as guide members which are vertically stretched between the ground G and the temporary roof frame 14. The wire ropes 40 and 41 are connected to the lifting rail 26 of the transporter 22a.
Are fed out from a pair of winches 38, 38a provided on the ground G corresponding to both ends in the direction in which they are extended. The respective wire ropes 40, 41 are raised upward from the respective winches 38, 38a, and circulate around sheave groups 42, 44 provided on the lower surface of the temporary roof frame 14, respectively. , 46a. The pair of wire ropes 40 and 41 are connected to the ground G
Vertical laying portions 40a and 41 between the temporary roof frame 14 and
a are tensioned in parallel, and the vertical routing portions 40a, 4a
1a, guide holes 2 provided on both sides of both ends of the transporter 22a.
2b is inserted so as to prevent the carrier 22a from swaying when it is moved up and down.

【0020】また、上記シーブ群42,44は、それぞ
れ一直線状に配置される4個のシーブ42a,42b,
42c,42dおよび44a,44b,44c,44d
からなり、中央部の2個のシーブ42b,42cおよび
44b,44cの間から下方に垂下したワイヤーロープ
40を、搬器22aの両端部上面に設けたシーブ46,
48に周回させて、該搬器22aを懸垂させてある。従
って、上記ウインチ38,38aを巻取りまたは巻戻し
することにより、搬器22aはウインチ38,38aの
巻取り量または巻戻し量の半分の移動量をもって昇降さ
れる。
Each of the sheave groups 42 and 44 has four sheaves 42a, 42b,
42c, 42d and 44a, 44b, 44c, 44d
And a wire rope 40 hanging downward from between the two sheaves 42b, 42c and 44b, 44c at the center, and a sheave 46 provided on the upper surface of both ends of the transporter 22a.
The transporter 22a is suspended by being rotated around 48. Therefore, by winding or rewinding the winches 38, 38a, the transporter 22a is moved up and down with a moving amount of half the amount of winding or rewinding of the winches 38, 38a.

【0021】そして、上記リフト22は搬器22aが最
上方位置となる揚重位置で、上記揚重用レール26は上
記荷送用レール24端に一直線状に突き合わされる。こ
のように一直線状に突き合わされた状態で、リフトホイ
スト28はこれら揚重用レール26と荷送用レール24
との間で乗り移りが可能となる。
The lift 22 is at the lifting position where the transporter 22a is at the uppermost position, and the lifting rail 26 is linearly butted against the end of the loading rail 24. In such a state that the lift hoists 28 are aligned in a straight line, the lift hoists 28 and the load rails 24
It is possible to transfer between and.

【0022】以上の構成により本実施形態の旋回式天井
クレーンに対応した垂直搬送システムにあっては、吊り
荷を施工階12まで搬送するにあたって、まず、地上G
でリフト22のフック39に吊り荷を玉掛けした後、ウ
インチ38,38aを同期して巻き取ることにより搬器
22aが上昇し、これによって吊り荷を揚重することが
できる。そして、搬器22aが最上方位置まで達する揚
重位置で、揚重用レール26が仮設屋根架構14に設け
た荷送用レール24と一直線状に突き合わされ、この状
態で揚重用レール26に位置するリフトホイスト28を
移動して荷送用レール24に乗り移す。そして、該荷送
用レール24に移動したリフトホイスト28を、施工階
12の適宜位置まで走行させて吊り荷を作業床12aに
荷下ろしして仮置きし、その後、空になったリフトホイ
スト28を逆に走行させて上記揚重用レール26まで戻
す。
In the vertical transport system of the present embodiment corresponding to the swiveling overhead crane according to the present invention, when transporting the suspended load to the construction floor 12, first, the ground G
After hanging the suspended load on the hook 39 of the lift 22, the winch 38, 38a is wound up in synchronism to raise the transporter 22a, thereby lifting the suspended load. Then, at the lifting position where the transporter 22a reaches the uppermost position, the lifting rail 26 is linearly butted against the loading rail 24 provided on the temporary roof frame 14, and the lift located on the lifting rail 26 in this state. The hoist 28 is moved to the rail 24 for transport. Then, the lift hoist 28 moved to the loading rail 24 is moved to an appropriate position on the construction floor 12, and the suspended load is unloaded on the work floor 12a and temporarily placed, and then the empty lift hoist 28 is emptied. In the opposite direction to return to the lifting rail 26.

【0023】そして、上記作業床12aに仮置きされた
吊り荷は、旋回式天井クレーン10のガーダ36をクレ
ーンレール16に沿って走行させるとともに、該ガーダ
36に沿ってクレーンホイスト18を走行させて、荷吊
りブーム20を仮置きされた上記吊り荷近傍まで移動す
ることにより、該荷吊りブーム20のフック38に玉掛
けして吊上げ、この状態で吊り荷を目的の場所まで搬送
することになる。
The suspended load temporarily placed on the work floor 12a causes the girder 36 of the revolving overhead crane 10 to travel along the crane rail 16 and the crane hoist 18 to travel along the girder 36. By moving the load boom 20 to the vicinity of the temporarily placed suspended load, the load boom 20 is slung on the hook 38 of the load suspended boom 20 and lifted, and in this state, the suspended load is transported to a target place.

【0024】従って、上記リフトホイスト28は、吊り
荷を作業床12aに仮置きした後に直ちに揚重用レール
26まで戻り、該リフトホイスト28が揚重用レール2
6まで戻った時点で搬器22aを下降して、次の吊り荷
を積み込む態勢を取ることができる。このため、リフト
22による吊り荷の揚重作業と、上記旋回式天井クレー
ン10による搬送作業とを独立して行うことができるよ
うになり、リフト22は旋回式天井クレーン10の仕事
が終わるのを待つことなく、次の作業へと進めることが
できるため、該リフト22の搬送効率を大幅に向上する
ことができる。
Therefore, the lift hoist 28 returns to the lifting rail 26 immediately after the suspended load is temporarily placed on the work floor 12a, and the lift hoist 28
When returning to 6, the transporter 22a can be lowered to be ready to load the next suspended load. For this reason, the lifting work of the suspended load by the lift 22 and the transfer operation by the revolving overhead crane 10 can be performed independently, and the lift 22 stops the work of the revolving overhead crane 10 from being completed. Since the next operation can be performed without waiting, the transfer efficiency of the lift 22 can be greatly improved.

【0025】このとき、上記旋回式天井クレーン10の
荷吊りブーム20は、所定のスパンをもって水平方向に
旋回できるため、作業床12a上の吊り点がクレーンの
走行エリア外にあっても、多少の距離ならばこれを許容
することができるため、作業床12aに吊り荷を仮置き
する位置が少々ずれたとしても、これを容易に玉掛けす
ることができる。
At this time, the lifting boom 20 of the revolving overhead crane 10 can be revolved in a horizontal direction with a predetermined span. Since this can be tolerated if the distance is long, even if the position where the suspended load is temporarily placed on the work floor 12a is slightly shifted, it can be easily slung.

【0026】また、リフトホイスト28は荷送用レール
24を走行して作業床12aの任意の場所に吊り荷を仮
置きすることができるため、時間に余裕のある場合は吊
り荷を建て込もうとする位置の近傍まで搬送して荷下ろ
しする一方、時間に余裕の無い場合は荷送用レール24
を長い距離走行させることなく、リフト22近傍の作業
床12a上に荷下ろしすることによって、搬送に柔軟性
を持たせて全体の搬送効率をより向上することができ
る。更に、現場によっては揚重班によって吊り荷をある
程度先行揚重することによって、高層階施工時の揚重の
遅れを吸収することが可能となる。
Since the lift hoist 28 can travel on the loading rail 24 and temporarily store the suspended load at any place on the work floor 12a, if there is sufficient time, the lift hoist 28 should be built up. To the vicinity of the position to be unloaded, and if there is not enough time, the loading rail 24
Without traveling over a long distance on the work floor 12a in the vicinity of the lift 22, it is possible to impart flexibility to the transport and to further improve the overall transport efficiency. In addition, depending on the site, the lifting load may be lifted to some extent by the lifting team to absorb a delay in lifting during construction of a high floor.

【0027】また、本実施形態では上記リフト22の搬
器22aは、ワイヤーロープ40,41の垂直配索部分
40a,41aによって昇降案内されるが、この垂直配
索部分40a,41aは、揚重用レール26の長さ方向
両端部に揚重用レール26をその幅方向に挟むように間
隔を隔てて配設されるので、吊り荷は、垂直配索部分4
0a,41a間に挟まれた状態でリフトホイスト28に
吊り下げられることになる。従って、吊り荷が揚重用レ
ール26の昇降を案内するワイヤーロープ40,41と
干渉することがなく、揚重用レール26の長さを超える
長尺の吊り荷であっても揚重および施工階12への搬送
が可能となる。
In this embodiment, the transporter 22a of the lift 22 is guided vertically by the vertical routing portions 40a, 41a of the wire ropes 40, 41. The vertical routing portions 40a, 41a are connected to the lifting rails. Since the lifting rails 26 are arranged at both ends in the length direction of the rails 26 at intervals so as to sandwich the lifting rails 26 in the width direction, the suspended load can be moved vertically.
It will be suspended by the lift hoist 28 while being sandwiched between 0a and 41a. Therefore, the suspended load does not interfere with the wire ropes 40 and 41 that guide the lifting and lowering of the lifting rail 26, and even if the suspended load is longer than the length of the lifting rail 26, the lifting and construction floor 12 can be used. Can be transported.

【0028】本実施形態ではリフト22の搬器22aを
昇降するワイヤーロープ40,40aをガイド部材とし
て用いた場合を開示したが、これに限ることなくガイド
部材としては搬器22aを昇降案内する機能を備えてお
れば良く、例えば、剛体の棒状体を地上Gと仮設屋根架
構14との間に対を成して垂直に設け、これをガイド部
材とすることもできる。また、本実施形態では旋回式天
井クレーン10を左右対称として2基設けたが、この旋
回式天井クレーン10は片側1基のみを設けることもで
きる。また、旋回式天井クレーン10を3基以上設けた
場合は、それぞれの間に対応するように複数のリフト2
2が設けられることになる。
In this embodiment, the case where the wire ropes 40, 40a for raising and lowering the transporter 22a of the lift 22 are used as guide members is disclosed. However, the present invention is not limited to this. For example, a rigid rod-shaped body may be provided vertically as a pair between the ground G and the temporary roof frame 14, and this may be used as a guide member. Further, in the present embodiment, two slewing overhead cranes 10 are provided symmetrically, but this slewing overhead crane 10 may be provided with only one slewing overhead crane. When three or more swiveling overhead cranes 10 are provided, a plurality of lifts 2 are provided so as to correspond to each other.
2 will be provided.

【0029】[0029]

【発明の効果】以上説明したように本発明の請求項1に
示す旋回式天井クレーンに対応した垂直搬送システムに
あっては、旋回式天井クレーンの荷受け可能な範囲内
で、荷送用レールを天井部分に設ける一方、リフトに揚
重位置で該荷送用レールと接続される揚重用レールを設
け、該揚重用レールを吊り荷の揚重位置で上記荷送用レ
ールと接続し、揚重用レールに走行自在に設けられて荷
吊りするリフトホイストを、相互に接続した揚重用レー
ルと荷送用レールとの間で走行自在としたので、該リフ
トホイストを荷吊りした状態でリフトから荷送用レール
を介して施工階まで搬送し、施工階に吊り荷を仮置きす
ることができる。従って、旋回式天井クレーンはリフト
まで吊り荷を取りに行くことなく、施工階に仮置きされ
た吊り荷を吊り上げて目的の場所まで搬送できるように
なり、一方、吊り荷を仮置きして空状態となったリフト
ホイストは、直ちに上記揚重用レールまで戻って次の吊
り荷を積み込む態勢を取ることができる。このため、リ
フトによる揚重作業と旋回式天井クレーンによる搬送作
業とを独立させることができるようになり、リフトは旋
回式天井クレーンの仕事が終わるのを待つことなく、次
の作業へと進めることができるため、該リフトの搬送効
率を大幅に向上することができ、延いては、建物の工期
の短縮化を図ることができる。
As described above, in the vertical transport system corresponding to the swiveling overhead crane according to the first aspect of the present invention, the loading rail is set within the range in which the swiveling overhead crane can receive the load. A lift rail is provided on the lift, which is connected to the loading rail at the lifting position, and the lifting rail is connected to the loading rail at the lifting position of the suspended load. The lift hoist, which is mounted on the rails to be able to travel freely and hangs, can be moved between the lifting rail and the loading rail connected to each other. Can be transported to the construction floor via the work rail, and suspended loads can be temporarily placed on the construction floor. Therefore, the swivel overhead crane can lift the suspended load temporarily placed on the construction floor and transport it to the target location without going to the lift to pick up the suspended load. The lift hoist in the state can immediately return to the lifting rail and be ready to load the next suspended load. For this reason, lifting work by the lift and transfer work by the swing overhead crane can be made independent, and the lift can proceed to the next work without waiting for the work of the swing overhead crane to end. Therefore, the transport efficiency of the lift can be greatly improved, and the construction period of the building can be shortened.

【0030】また、本発明の請求項2に示す旋回式天井
クレーンに対応した垂直搬送システムにあっては、リフ
トで揚重される吊り荷を、揚重用レールの長さ方向両端
部にこのレールをその幅方向に挟むように間隔を隔てて
配設されたガイド部材間に挟んだ状態でリフトホイスト
に吊り下げることができるので、上記吊り荷が揚重用レ
ールの昇降を案内するガイド部材と干渉することがな
く、揚重用レールの長さを超える長尺の吊り荷であって
も揚重および施工階への搬送を可能にすることができ
る。
Further, in the vertical transport system corresponding to the swing type overhead traveling crane according to the second aspect of the present invention, the suspended load lifted by the lift is placed on both ends of the lifting rail in the longitudinal direction. Can be hung on the lift hoist in a state of being sandwiched between the guide members disposed at intervals so as to sandwich the same in the width direction, so that the suspended load interferes with the guide member for guiding the lifting / lowering of the lifting rail. This makes it possible to carry out lifting and transporting to a construction floor even for a long suspended load exceeding the length of the lifting rail.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施形態を示す旋回式天井クレーン
を配置した施工階の平面図である。
FIG. 1 is a plan view of a construction floor on which a swiveling overhead crane according to an embodiment of the present invention is arranged.

【図2】本発明の一実施形態を示す旋回式天井クレーン
を用いて構築しようとする建物架構の正面図である。
FIG. 2 is a front view of a building frame to be constructed using a swiveling overhead crane according to an embodiment of the present invention.

【図3】本発明の一実施形態を示す旋回式天井クレーン
を用いて構築しようとする建物架構の側面図である。
FIG. 3 is a side view of a building frame to be constructed using a swiveling overhead crane according to an embodiment of the present invention.

【図4】本発明の一実施形態を示すリフトの全体構成を
示す斜視図である。
FIG. 4 is a perspective view showing the overall configuration of a lift showing one embodiment of the present invention.

【図5】従来の垂直搬送システムを示す施工階の平面図
である。
FIG. 5 is a plan view of a construction floor showing a conventional vertical transport system.

【符号の説明】[Explanation of symbols]

10 旋回式天井クレーン 12 施工階 12a 作業床 14 仮設屋根架構 16 クレーンレール 18 クレーンホイスト 20 荷吊りブーム 22 リフト 24 荷送用レール 26 揚重用レール 28 リフトホイスト 40,41 ワイヤーロープ G 地上 DESCRIPTION OF SYMBOLS 10 Rotating overhead crane 12 Construction floor 12a Work floor 14 Temporary roof frame 16 Crane rail 18 Crane hoist 20 Loading boom 22 Lift 24 Loading rail 26 Lifting rail 28 Lift hoist 40,41 Wire rope G Ground

───────────────────────────────────────────────────── フロントページの続き Fターム(参考) 2E174 CA03 CA04 CA09 CA14 CA16 CA17 CA30 DA02 DA18 DA32 3F202 AA01 BA01 BA10 3F203 AA10 BA01 CA02 CC03 DA01 FA01  ────────────────────────────────────────────────── ─── Continued on the front page F term (reference) 2E174 CA03 CA04 CA09 CA14 CA16 CA17 CA30 DA02 DA18 DA32 3F202 AA01 BA01 BA10 3F203 AA10 BA01 CA02 CC03 DA01 FA01

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 施工階の天井部分に設けたクレーンレー
ルに移動自在に取り付けられたクレーンホイストと、こ
のクレーンホイストに設けた水平方向に旋回自在な旋回
式天井クレーンと、地上などの荷吊り位置から上記施工
階の揚重位置に吊り荷を揚重するリフトと、を備えた旋
回式天井クレーンに対応した垂直搬送システムにおい
て、 上記天井部分に取り付けられ、上記旋回式天井クレーン
の荷受け可能な範囲内に配置された荷送用レールと、 上記リフトに設けられ、上記揚重位置で該荷送用レール
と接続される揚重用レールと、 該揚重用レールと上記荷送用レールとの間で走行自在な
リフトホイストと、を備えたことを特徴とする旋回式天
井クレーンに対応した垂直搬送システム。
1. A crane hoist movably attached to a crane rail provided on a ceiling portion of a construction floor, a horizontally movable swiveling overhead crane provided on the crane hoist, and a load hanging position on the ground or the like. And a lift for lifting the suspended load to the lifting position of the construction floor from above, in a vertical transfer system corresponding to a swiveling overhead crane, comprising: A loading rail provided in the lift; a lifting rail connected to the loading rail at the lifting position and connected to the loading rail; and between the lifting rail and the loading rail. A vertical transport system compatible with swiveling overhead cranes, comprising a movable lift hoist.
【請求項2】 上記リフトは、上記荷吊り位置と上記揚
重位置との間に垂直に設けられて、上記揚重用レールを
昇降案内するガイド部材を備え、このガイド部材は、上
記揚重用レールの長さ方向両端部に該揚重用レールをそ
の幅方向に挟むように間隔を隔てて配設したことを特徴
とする請求項1に記載の旋回式天井クレーンに対応した
垂直搬送システム。
2. The lift includes a guide member vertically provided between the load suspending position and the lifting position to guide the lifting rail up and down, and the guide member includes the lifting rail. 2. The vertical transport system according to claim 1, wherein the lifting rails are arranged at both ends in the length direction at intervals so as to sandwich the lifting rail in the width direction.
JP10230584A 1998-08-17 1998-08-17 Vertical carrier system corresponding to slewing overhead crane Pending JP2000053375A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10230584A JP2000053375A (en) 1998-08-17 1998-08-17 Vertical carrier system corresponding to slewing overhead crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10230584A JP2000053375A (en) 1998-08-17 1998-08-17 Vertical carrier system corresponding to slewing overhead crane

Publications (1)

Publication Number Publication Date
JP2000053375A true JP2000053375A (en) 2000-02-22

Family

ID=16910041

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10230584A Pending JP2000053375A (en) 1998-08-17 1998-08-17 Vertical carrier system corresponding to slewing overhead crane

Country Status (1)

Country Link
JP (1) JP2000053375A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107686056A (en) * 2017-10-17 2018-02-13 中国建筑第七工程局有限公司 Special lifting platform and application method are installed in the lifting of assembly concrete building element
CN110356968A (en) * 2019-08-23 2019-10-22 江阴帕沃特起重机械有限公司 A kind of KBK conveying track for warping creel
CN111439673A (en) * 2020-04-26 2020-07-24 中国建筑第七工程局有限公司 Building handling system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107686056A (en) * 2017-10-17 2018-02-13 中国建筑第七工程局有限公司 Special lifting platform and application method are installed in the lifting of assembly concrete building element
CN107686056B (en) * 2017-10-17 2023-12-19 中国建筑第七工程局有限公司 Special lifting platform for lifting and installing assembled concrete building components and application method
CN110356968A (en) * 2019-08-23 2019-10-22 江阴帕沃特起重机械有限公司 A kind of KBK conveying track for warping creel
CN111439673A (en) * 2020-04-26 2020-07-24 中国建筑第七工程局有限公司 Building handling system
CN111439673B (en) * 2020-04-26 2022-03-11 中国建筑第七工程局有限公司 Building handling system

Similar Documents

Publication Publication Date Title
JP6193170B2 (en) Crane manufacturing method and crane overhead structure system
JPH11159128A (en) Multi-purpose stage for construction of building frame body
JP2819990B2 (en) Hoist type tower crane
JP2000053375A (en) Vertical carrier system corresponding to slewing overhead crane
JP2551161Y2 (en) Overhead traveling crane equipment
JP6393954B2 (en) Crane overhead structure system and crane manufacturing method
JP3994458B2 (en) Operation method of vertical and horizontal transfer device
JP3073384B2 (en) Exterior wall unit mounting device
JP2007261795A (en) Lift mechanism for building
JPH05113026A (en) Temporary scaffold structure
JPH10182066A (en) Vertical conveying device
JPH09328289A (en) Vertical heavy-load lift of overhead crane and conveying method using it
KR0139129B1 (en) Lifting device and method in carrage
JPH1087268A (en) Hoist load turn preventing device for vertical raising device
JP2000240287A (en) Carrier system for automated construction method
JP2002037585A (en) Portal crane and bridge crane
JPH09125578A (en) Fitting device and fitting method for floor member
JP2022081892A (en) Hanging jig, hanging jig set, lifting device, and lifting method
JP2775206B2 (en) Material transport equipment for building construction
JPH08338136A (en) Elevator device for construction
JPH04153460A (en) Constructing method for building, and its equipment
JPH08312146A (en) Temporary frame device for construction
JP3103715B2 (en) Lifting transfer device and lifting transfer method
JPH0797182A (en) Hoist type tower crane
JPH10176420A (en) Conveying method and device for material in underground work

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20040330