GB2399320A - Semi-submersible jetty for transferring LNG from a production vessel to a transport vessel - Google Patents

Semi-submersible jetty for transferring LNG from a production vessel to a transport vessel Download PDF

Info

Publication number
GB2399320A
GB2399320A GB0305370A GB0305370A GB2399320A GB 2399320 A GB2399320 A GB 2399320A GB 0305370 A GB0305370 A GB 0305370A GB 0305370 A GB0305370 A GB 0305370A GB 2399320 A GB2399320 A GB 2399320A
Authority
GB
United Kingdom
Prior art keywords
jetty
vessel
lng
barge
offlake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
GB0305370A
Other versions
GB0305370D0 (en
Inventor
Malcolm Newell
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to GB0305370A priority Critical patent/GB2399320A/en
Publication of GB0305370D0 publication Critical patent/GB0305370D0/en
Publication of GB2399320A publication Critical patent/GB2399320A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/30Arrangement of ship-based loading or unloading equipment for transfer at sea between ships or between ships and off-shore structures
    • B63B27/34Arrangement of ship-based loading or unloading equipment for transfer at sea between ships or between ships and off-shore structures using pipe-lines
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/24Arrangement of ship-based loading or unloading equipment for cargo or passengers of pipe-lines
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B1/00Hydrodynamic or hydrostatic features of hulls or of hydrofoils
    • B63B1/02Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement
    • B63B1/10Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement with multiple hulls
    • B63B1/107Semi-submersibles; Small waterline area multiple hull vessels and the like, e.g. SWATH
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B22/00Buoys
    • B63B22/02Buoys specially adapted for mooring a vessel
    • B63B22/021Buoys specially adapted for mooring a vessel and for transferring fluids, e.g. liquids

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

An 'L' shaped semi-submersible jetty is provided for use in the transfer of LNG from a production vessel to a transport vessel. In use the jetty is connected to the production vessel by means of a ball and hydraulic clamp coupling 3, which allows no relative motion between the jetty and the production vessel in a longitudinal, transverse or vertical direction, but does allow rolling motion of the jetty. Once the jetty is connected to the production vessel the transport vessel is moored alongside the jetty and LNG is transferred through pipes running along the jetty.

Description

Page Nol of 5 2399320 Semi Submersible Floating Jetty for the Safe
Transfer of LNG between a Floating Production, or Storage Barge, to a Transportation Vessel at an Exposed Offshore Location.
Malcolm Newell 146 Nyetimber Lane, Aldwick, West Sussex, P()21 31IX, United Kingdom Contents Page No The design requirements for a Proposed Floating Offshore LNG Jetty I The Floating, Semi Submersible LNG Jelly 2
Conclusions 5
The design requirements for a Proposed Floating Offshore LNG Jetty The jetty described here is to be used in conjunction with a Tandem Mooring arrangement similar to those used on many Offshore Oil l,oilding systems. In this application the 1,NG Shuttle vessel approaches close enough to pick up single Mooring Hawser which is attached to the Barge at one end, and then the outboard end of this hawser is attached to a BOW Chock on the Shuttle. By slowly running astern, the Shuttle is able to take up this mooring and apply a low tension force to the stern of the Barge. This a) keeps the Shuttle at a fixed and well defined distance from the Barge and also, b) slightly dampens any surge or sway motions of the Barge about its Turret Mooring, reducing the footprint swept out by the loading manifold on the Shuttle and simplifyhg the problem of aligning any Offtake system which is linking the two vessels.
The Ship:- relatively low cost solution to the LNG Offtake Shuttle requirement will be to take a standard LNG vessel (probably having a Moss or other self supporting cargo tank arrangement and powered by a highly reliable steam turbine based propulsion plant) and adapt it for Tandem Mooring. This involves fitting a suitable bow fairlead, mooring chock and a winch capable of handling both the mooring hawser itself and its attendant chaffing chain, floatation buoys, messenger rope etc. The Shuttle so produced is already fitted with mid- ships mounted loading and discharge facilities to international standards and is compatible with most anticipated discharge terminals throughout the world. It would benefit from the addition of forward facing berthing radar as well as an automatic relative heading control and hawser tension monitoring equipment linked to systems on the Barge. The cargo manifolds are already mounted at a longitudinal position on the shuttle where heave and pitch motions are at their minimum but, being at the ship side' are subjected to its maximum roll movements.
The Barge:- is fitted with a Tandem Mooring Hawser mounted, along with its stowage winch, on the centre line of its all (Poop) deck. The adoption of Tandem Mooring virtually eliminates any requirement for sophisticated D.P. and associated power control systems on the Shuttle. By using this mooring system it is possible that the LNG Shuttle Tankers can be conventional steam turbine propelled vessels rather than sophisticated Dynamically Positioned units. it_
Page No2 of 5 The Jetty:- With the two vessels tandem moored in line ahead, pointing into the weather and with the hawser tension stable, we are ready to arrange for Cargo Transfer by fitting:- (Refer to Fig 9).
a) A floating platform? carrying a set of loading arms, which is attached (by units powered from the jetty) to the Shuttle side at its mid-ships position and which is clamped to and movhig with the Shuttle as it rolls.
b) A second floating platform attached to the stern of the Barge at the C/L End coupled to the vertical transom and moving with the Barge in heave.
c) Between items a) and b) must be fitted a rigid but resilient pipe-rack structure capable of safely carrying a normal complement of insulated l, NG and vapour pipelines (plus associated valves and fittings) and which holds them in a dry accessible position well above the sea surface.
d) A second set of loading arms is fitted on a small platform rigidly attached to the stern of the Barge and cantilevered out near item h).
These four basic ingredients form the design basis of the proposed Floating Semi Submersible LNG transfer Jetty which is described next. I he forward end of the light weight, low inertia floating structure is directly coupled to the Barge at its C/L, directly below the Tandem Mooring Hawser attachment and carries platform b!. The coupling is resiliently mounted on the Baige from which it is hydraulically operated. It is colmected to the lloathig platform structure by an articulated ball joint which allows the platform to move freely in roll but restrains all relative longitudinal and heave movement between the Barge and Jetty at this point.
The length of jetty / pipe support structure between the Barge and the Shuttle Mid-ships position is supported on small water plane columns tuned in heave to match the Barge motion. The Jetty columns are tied together by a light weight lattice cmsiruction which enables the Boating structure to form a strong, fight beam between the Barge and the Shuttle Mid-ships where it connects to a deep narrow pontoon containing machinery as well as ballast tanks and which supports the mid-ships loading arms as well as the location and clamping devices for attachment to the Shuttle side.
A brief outline of the operation of the floating jetty as well as a tcw more details of some of its features now follows.
The Floating, Semi Submersible LNG Jetty À LNG Transfer is by Stainless Steel Pipes with LNG Loading Arms at the Barge to Jetty & Jetty to Ship connections.
À Pipe-work expansion and flexure is taken up by proven Omega Bends and LNG grade Swivels À All Mooring and Transfer system equipment is based on well proven and readily available Marine products.
À All pipe-work & fittings associated with LNG transfer are located well above sea level and easily maintained.
À All pipe-work utilizes conventional "Dry and Sealed" marine LNG system Insulation.
À Jetty systems arc easily maintained "On Sitc". Production Bargc facilities can be easily utilized in order to perform more stringent Jetty maintenance. Or, jetty can be easily removed to Shore Base or Shipyard for major work.
À When on site, all Jetty systems arc powered and supplied, via umbilical cables, from the Bargc (Fig 9, Item 1).
À System operation, monitoring and control as well as E.S.D and other Emergency functions are easily integrated with the Bargc Systems and D.C. S. so that the Bargc Control Room can operate and Monitor all Jetty functions.
À Jetty has its own independent Emergency and Base l,oad Generator which provides essential safety back-up for Power, Control & Emergency Systems and for periods when Jetty is dc-coupled or when under tow (Fig 9, Item 2) .
À Jetty connection to the Barge is via a "Ball Joint" on the jetty which is connected to the Barge within a hydraulically operated "Tow Coupling" mounted at the Barge C/L and located well above sea level on the Transom of the Barge (Fig 9, Items).
À Direct coupling of the Barge and floating Jetty minimizes the excursion envelope which the Barge end LNG transfer system has to cope with and minimizes the angular motion in both the vertical and horizontal planes.
À The LNC Omake Vessel (LNG.O.V) is independently Tandem Moored from the stern of the Barge with the mooring hawser passing through a Fairlead mounted vertically above the Jetty Ball Joint connection (Fig 9, Item 4).
À Mooring equipment tor the LNC.O.V is mounted on the Barge Stern at the C/L in a safe location at main deck level.
Page No3 of 5 À No mooring loads *tom the LNG.O.V are transferred to the Jetty structure, which is lightweight and low inertia.
À Restraining forces transferred between the Jetty & the Barge (due to relative Heave and Roil motions) are low as a result of the lightweight Jetty construction in vicinity of the Barge.
À Any Jetty (and LNG O.V) Fishtail" motion relative to the stern of the Barge takes place about a vertical axis through the Hall joint and Tandem Mooring Fairlead, which results in very small relative longitudinal movements between the Jetty and the LNG O.V.
À The upper flange ofthe Jetty beam is tommed by the longitudinal walk way and pipe rack support structure.
À Power and Control is transferred between the Barge and the Jetty via Umbilical cables suspended from retractable Umbilical Crane booms on the [large. This allows the l)mbilical cables to be quickly detached (e.g. Or Jetty detachment as part of ESD or for Tow off).
À All Jetty and LNG O.V mooring and un-mooring operations take place in "Safe Zones" on both Barge and Jetty.
À LNG Transfer from the Barge and Vapour return from the Jetty, are via loading arms slightly offset from the CiL moorings with all related power and controls mounted on the Barge.
À Hazardous Areas associated with LNC transfer are minimized in size and number and are clearly definable. They do not encroach on permanently manned areas or on Mooring and Power transfer systems.
À At a position on the Jetty which coincides with the Mid-ship's Loading Manifold on the 1,NG O.V there is a deep, narrow Ballast Tank and Motor Room on which are mounted the LNG Transter Arms and Fire Fighting equipment (Fig 9, Item S).
À Two electric thrusters with variable speed, f xed pitch propellers are fitted in Tunnels through the Ballast Tanks.
À The side of the Ballast Tank, Motor room facing the l.NG O.V is fitted with a pair of fender i attachment units.
À It is intended that "Vacuum Attachment" units are used (hydraulically tensioned mooring lines could also be used).
À Cantilevered out from the bottom of the Ballast Tank structure and under the LNG O.V Hull arc two "Location Arms" each with a pair of fender / vacuum attachment units mounted on their top sides (Fig 9, Item 6).
À In operation, the Jetty Unit can be raised and lowered between LNG O.V Berthing draft and LNG Loading draft by de-ballasting and ballasting the Ballast Tank, Motor room structure.
À Jetty length and Moorings arc arranged so that the de-ballasting of the Ballast Tank, Motor room structure raises the Loading Arms to the ideal height and alignment for connection to the LNG O.V's mid-ship's loading manifold.
À Prior to arrival of the LNG O.V, the Barge end LNG Transfer Arms are disconnected from the Jetty and lifted cicar.
À The Jetty I hrusters swing the Jetty clear (pivoting about the ball connection) of the Barge Tandem Mooring C/L (Figs 4 and 5).
À The Jetty Ballast T ank, Motor room structure is also ballasted down to the Berthing draft.
À Ideally, Thrusters on the stern old the Production Barge are used to hold the Heading of the Barge and Jetty throughout the LNG O.V's Berthing operation. However, the use of such thrusters is not essential.
À The LNG O.V approaches and connects the Tandem-mooring Hawser (Figs 6 to 8).
À Once the Chaffing Chains are secured in the mooring Bits, the LNG O.V drops back to give a tight Mooring line and it takes up and maintains the same heading as the Production Barge.
À The Jetty Thrusters are used to propel the Jetty back to a position alongside and in contact with the LNCi O.V.
À Initially the jetty and LNG O.V are held together by counter thrust (between Jetty and Ship lateral thrusters).
À The Barge LNG Transfer arms are re-connected to the Jetty pipe-work at the forward end.
À The Jetty Baila.st Tank, Motor room structure is de-ballasted to bring the lower locating arms (and Fender Attachment units) into contact with the bottom ofthe LNG O.V's [lull.
À The astern thrust being applied by the l.N(i O.V is adjusted against the Mooring Hawser elasticity to centrc the LNG Loading Arms on to the mid-ships Loading Manifold.
À Vacuum is applied to the Fender Attachment units and the Ballast Tank, Motor room structure is fully de-ballasted to the loading condition. The Jetty end is now locked against the LNG O.V and moves with the Roll of the Ship.
This results in the virtual absence of motion between the Mid-ships Jetty Loading Arms and the LNG O.V.
À Counter thrust between Jetty and Ship lateral thrusters can now be stopped.
À The Loading Arms are connected up using the Jetty's own hydraulic systems and standard cool-down and loading procedures are followed to allow the loading operation to commence (Fig 8.
À the LNG O.V's astern thrust is maintained throughout the Loading operation and the longitudinal alignment of the l.oading Arrns / Manifold positions are monitored throughout.
À T hroughout the loading operation, control, monitoring & alarm functions are directly available in the Barge CCR.
Page No4 of 5 À Back-up and emergency power is available from the Jetty Base Load (Generator and Switchboard.
À T he Fire Fighting systems at the LNG O.V's Manifolds are augmented by the Monitors mounted at the fore and aft extremes of the Jetty Ballast 'l'ank, Motor room structure.
Advantages from the use of the Jetty, TO THE BARGE: À It Minimizes and Simplifies the Mooring and 1,NG Transfer Facilities which must be mounted ON the Barge.
À It minimizes the footprints required on the Barge for Mooring and LNG Transfer.
À It removes the Marine Mooring and LNG transfer equipment from the vicinity of the Barge Production Facilities.
À It provides easily and clearly defined interfaces between the Barge and the Off-take early in the Project schedule.
À Integration ol'the Mooring and Offtake systems is simplified & impact on the Barge layout & construction reduced.
À There are only minor loads transferred into the Barge structure.
À There are no major structures to be mounted on and integrated with the Barge structure.
À On going maintenance of the Mooring and Of Stake systems have little impact on the Production Barge Operation.
À Integration of the required power, control, alarm and monitoring systems is shnplified.
À No new Gas Hazardous Zones are created and those around the Offlake system are minimized.
À There is no requirement for the Offtake LNG Vessel to lie alongside the Production Barge.
À Tandem Berthing is Sai'er, Simpler and a more Standard operation than Alongside Berthing against a moored Barge.
À The Offtake LNG vessel has no need to closely approach the Barge. The possibility of contact is much reduced.
À The Jetty is virtually an independent Project. Once the Barge / Jetty interfaces are defined, changes to the details of the Jetty or Barge have no impact on the design, construction, installation and commissioning schedules.
À Jetty installation and commissioning is very mpid and has virtually no impact on the Barge progress.
À It is possible for the Jetty to be easily removed from site to Shore if major repairs or maintenance become necessary.
À The construction ofthe Jetty is very simple and can be undertaken by most small to medium sized Shipyards.
À It is possible for a complete Back-up Jetty unit to be held in reserve and introduced very rapidly so that Production and Offlake operations are not disrupted in the change over.
À In extreme emergency it is possible to incorporate Barge / Jetty detachment as part of the ESD function.
Advantages from the use of the Jetty, TO THE LNG Omake Vessel: À Tandem Berthing is less Labour intensive and exposes fewer persons to Mooring Hazards.
À Tandem Berthing can be performed in more extreme sea & wind states, with-out Tugs or Line handling vessels.
À There is much less likelihood of Ship 1\ Barge impact due lo the presence of the Floating Jelly structure.
À ESD and un-berthing operations in an emergency are achieved more quickly, more simply and more safely.
À Offlake Vessel & Barge Hazardous Areas i Safety Zones remain independent. There is minimal operational conflict.
À No modifications required to standard cargo tank and accommodation ventilation systems on 1,NG O.V.
À I lazards to LNG O.V from Barge Production Facilities are much reduced.
À Shrapnel & Blast pressure Hazard to Moss type Cargo Tanks on LNG O.V (from Barge explosion) is much reduced.
À Modif cations to LNG O.V are limited to the addition of Bow Mooring equipment located in non hazardous area.
À There are few changes required to Standard Cargo Loading and Discharge connection and Monitoring systems.
À Ships data transfer, monitoring, control, alarm and EST) functions easily integrated with the Barge D.C.S system.
À The Tandem Mooring operation is identical with that of conventional Oil FPSO (Training & Experience available).
À The presence of the Jetty has virtually no impact on the Berthing operation performed by LNG O.V.
À Pitching of Bow of LNG O.V at extreme of weather window has only minimal impact on LNG transfer connections at the Mid-ships manifold. Weather window is improved if Jetty is used rather than a Bow Loading system.
À No Mooring loads are transferred to the LNG O.V's Hull via structures (or near fluids) at cryogenic temperatures.
À Berthing of LNG O.V involves the use of Thruster assisted Joystick control with electronic safety features, rather than fully sophisticated Dynamic Positioning system.
À When Moored to the Production Barge, there is no requirement for the use of D.P system.
À While moored, propulsion loss or black-our on LNG O.V ol'fers no immediate hazard to Production Barge or Ship.
À Machinery system on LNG O.V can be simpler, Cost and Complexity of LNG O.V is much reduced.
7/3/ 3 Page No5 of 5
Conclusions
The l.NC, 1,oading Jerry becomes an irdependeii Project so that its build site can be completely separate from the Barge construction site and Design or Construction delays on Jetty have no impact on Barge or Shipping Schedule (and vice versa). Tow out and I look up of Jetty and LNG transfer system is much reduced in both time and cost to Project and the Jetty can be completely pre-commissioned prior to ISt connection at Production site. The Jetty can be removed and towed to satiety ir; ar ticipation of "Hurricane" or Storm conditions and Jetty modifications, repairs and maintenance can easily be achieved either on or offthe Production site.
The Jetty design is easily scaled up or down to suit any sized Project or LNG Vessel Capacity. It can be built for (Lightweight) Benign conditions or in (Robust) Exposed location versions. It is also suitable for the transfer of Crude Oils and any other fluid Cargo and could be used for the transfer of any Pumped Slurry-on any scale. It can be re- designed to allow the handling of free flowing granular solids, making it suitable for the loading of e.g. Gas Hydrates or Manganese Nodules from a deep sea dredger.
As presented here, the Jetty can handle LNG and Gas flowing in either direction i.e. onto as well as off the Barge. This makes the Jetty suitable for use in LNG import and Re-Gasification Projects e.g. for the import of LNG into an Industrialised Country such as the USA. 11 is suggested that 1,NG from the 1,NG Ol't:take Vessel arriving from the distant Producing Field is transferred (using the Jetty) to a Turret moored LNG reception and storage vessel which itself is equipped to re-gasify the LNG and pass the warm gas into the adjacent shore Gas distribution system via a short sub- sea pipeline. This use is particularly attractive as it allows the simple introduction of new LNG reception facilities in locations where shore reception and storage of LNG and the location of re-gasitication facilities are difficult or prohibitively expensive. The Moored re- gasification Vessel can be located well offshore in a safe and preferably sheltered position allowing the shipping operation to take place in many places where shore facilities would otherwise be banned. This type of application will allow LNG import to take place quickly and cheaply in most parts ofthe World, especially where the Construction of the necessary shore tanks and other facilities would be difficult (or slow) to introduce.

Claims (1)

  1. Semi Submersible Floating Jetty for the Safe Transfer of LNG between a
    Floating Production, or Storage Barge, to a Transportation Vessel at an Exposed Offshore Location.
    Claims: Claim 1) The Jetty is shaped like a capital "L" with the height (corresponding to the length of jetty-see Fig 9) being roughly / the length of the Offlake vessel + 60 meters. The base is roughly equal to the Beam of the Offlake vessel plus 10 meters.
    The Jetty Ball mooring attachment is located on a forward extension to the jetty fitted half way along the base of the "L" and locates with the hydraulically operated Claw type coupling which is mounted on the stern of the Barge at the C/L and at an elevation of at least 10 meters above the loaded waterline. When connected to the Barge, the coupling allows no relative motion in a Longitudinal, Transverse or Vertical direction but offers no restriction to Roil motions. The dimensions and geometry of the Barge to Offlake vessel Tandem mooring and the dimensions and geometry of the Jetty are such as to ensure that longitudinal movement between the Offlake vessel and Jetty Pontoon are minimised.
    Claim 2) concerns the methods of achieving the "Clamping" Forces between the Jetty Pontoon and the Offlake Vessel and is the main claim but is dependent upon the Jetty shape and the use of the forward attachment method described in Claim 1 above. The "L" shaped Jetty is fitted with the narrow machinery and ballast pontoon as described in the main "Description" and located at the top of the "L" which corresponds with the mid-ship loading position of the LNG Offtake vessel. Claim 2 covers the form of the clamping attachment made between the Jetty and the Offtake vessel. These clamping forces will be applied by the following means: a) Initially the Jetty and Ship are forced together by counter running the Tunnel Thrusters fitted to both vessels.
    b) When the Rubber Fenders mounted on the Jetty are in contact with the Offtake vessel and slightly compressed, a low pressure "Plenum Chamber" is formed from which the Jetty Thrusters extract the water and sea water pressure on the two hulls will hold the vessels together.
    c) The Moulded Rubber Vacuum attachment Fenders are pressed firmly into contact with the Offlake vessel Hull and sea water pumps in the Jetty Pontoon evacuate the Attachment units.
    d) Conventional 'Soft Rope Mooring Tails" stored on the Jetty Pontoon are secured to the mooring bits on the Offlake vessel and tensioned by hydraulic Rams located on the Jetty Pontoon.
    e) In Benign weather conditions the Main Thrusters on both the Jetty and Offlake Vessel are shut down following step d).
    fl "Shearing" of the Vacuum attachment is prevented by the application of slight positive buoyancy to the Jetty Pontoon which forces the lower "Location Arms (Fig 9, Item 6) with their additional Vacuum attachment Fenders into contact with the Offlake vessel bottom which also self aligns the LNG Omake loading Arms mounted on the Jetty Pontoon.
    9) The LNG Vessel and Jetty Pontoon remain clamped securely together and move together with virtually no relative motion so that the LNG Transfer Arms can remain connected to the loading manifold throughout the transhipment operation.
    Malcolm Newell pimp,-__ 7/03/2003
GB0305370A 2003-03-10 2003-03-10 Semi-submersible jetty for transferring LNG from a production vessel to a transport vessel Withdrawn GB2399320A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
GB0305370A GB2399320A (en) 2003-03-10 2003-03-10 Semi-submersible jetty for transferring LNG from a production vessel to a transport vessel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB0305370A GB2399320A (en) 2003-03-10 2003-03-10 Semi-submersible jetty for transferring LNG from a production vessel to a transport vessel

Publications (2)

Publication Number Publication Date
GB0305370D0 GB0305370D0 (en) 2003-04-16
GB2399320A true GB2399320A (en) 2004-09-15

Family

ID=9954416

Family Applications (1)

Application Number Title Priority Date Filing Date
GB0305370A Withdrawn GB2399320A (en) 2003-03-10 2003-03-10 Semi-submersible jetty for transferring LNG from a production vessel to a transport vessel

Country Status (1)

Country Link
GB (1) GB2399320A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7448223B2 (en) * 2004-10-01 2008-11-11 Dq Holdings, Llc Method of unloading and vaporizing natural gas
WO2010059052A1 (en) * 2008-11-20 2010-05-27 Single Buoy Moorings Inc. Multi-function unit for the offshore transfer of hydrocarbons
AU2008219347B2 (en) * 2007-09-28 2012-07-12 Woodside Energy Limited Linked LNG production facility
AU2012207059B2 (en) * 2007-09-28 2013-11-14 Woodside Energy Limited Linked LNG production facility
CN104554689A (en) * 2015-02-03 2015-04-29 重庆燃气集团股份有限公司 Method for supplying natural gas to wharf boat
WO2019162626A1 (en) * 2018-02-23 2019-08-29 Gaztransport Et Technigaz Assembly for refueling a ship, comprising a floating cover device
CN110515340A (en) * 2019-07-09 2019-11-29 深圳市中燃科技有限公司 A kind of inspection remote power feeding system and its method cooperateing with protection with fire-fighting system
WO2020212525A1 (en) * 2019-04-17 2020-10-22 Technip France System for loading and unloading fluid, related installation and method
NO20191192A1 (en) * 2019-10-04 2021-04-05 Connect Lng As Fluid transfer structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2219053A1 (en) * 1973-02-23 1974-09-20 Doris Dev Richesse Sous Marine
US4098212A (en) * 1977-02-17 1978-07-04 Shell Oil Company Tanker loading terminal
US4449471A (en) * 1979-12-13 1984-05-22 Roon Johannes Van Steering combination of pusher tug and barges
GB2347386A (en) * 1999-03-04 2000-09-06 David Lindsay Edwards Modular Marine Articulated Transportation Vessel
GB2369607A (en) * 2000-12-01 2002-06-05 Billy Jay Smart Vessel control system for automatic docking

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2219053A1 (en) * 1973-02-23 1974-09-20 Doris Dev Richesse Sous Marine
US4098212A (en) * 1977-02-17 1978-07-04 Shell Oil Company Tanker loading terminal
US4449471A (en) * 1979-12-13 1984-05-22 Roon Johannes Van Steering combination of pusher tug and barges
GB2347386A (en) * 1999-03-04 2000-09-06 David Lindsay Edwards Modular Marine Articulated Transportation Vessel
GB2369607A (en) * 2000-12-01 2002-06-05 Billy Jay Smart Vessel control system for automatic docking

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7448223B2 (en) * 2004-10-01 2008-11-11 Dq Holdings, Llc Method of unloading and vaporizing natural gas
AU2008219347B2 (en) * 2007-09-28 2012-07-12 Woodside Energy Limited Linked LNG production facility
AU2012207059B2 (en) * 2007-09-28 2013-11-14 Woodside Energy Limited Linked LNG production facility
US9404619B2 (en) 2008-11-20 2016-08-02 Single Buoy Moorings Inc. Multi-function unit for the offshore transfer of hydrocarbons
JP2012509224A (en) * 2008-11-20 2012-04-19 シングル・ブイ・ムーリングス・インコーポレイテッド Multifunctional unit for offshore transfer of hydrocarbons
US8622099B2 (en) 2008-11-20 2014-01-07 Single Buoy Moorings Inc. Multi-function unit for the offshore transfer of hydrocarbons
EP2727812A1 (en) * 2008-11-20 2014-05-07 Single Buoy Moorings Inc Multi-function unit for the offshore transfer of hydrocarbons
WO2010059052A1 (en) * 2008-11-20 2010-05-27 Single Buoy Moorings Inc. Multi-function unit for the offshore transfer of hydrocarbons
US9447921B2 (en) 2008-11-20 2016-09-20 Single Buoy Moorings Inc. Multi-function unit for the offshore transfer of hydrocarbons
CN104554689A (en) * 2015-02-03 2015-04-29 重庆燃气集团股份有限公司 Method for supplying natural gas to wharf boat
WO2019162626A1 (en) * 2018-02-23 2019-08-29 Gaztransport Et Technigaz Assembly for refueling a ship, comprising a floating cover device
FR3078327A1 (en) * 2018-02-23 2019-08-30 Gaztransport Et Technigaz ASSEMBLY FOR REFUELING A VESSEL COMPRISING A FLOATING RECOVERY DEVICE
WO2020212525A1 (en) * 2019-04-17 2020-10-22 Technip France System for loading and unloading fluid, related installation and method
FR3095187A1 (en) * 2019-04-17 2020-10-23 Technip France Fluid loading and unloading system, associated installation and method
CN110515340A (en) * 2019-07-09 2019-11-29 深圳市中燃科技有限公司 A kind of inspection remote power feeding system and its method cooperateing with protection with fire-fighting system
CN110515340B (en) * 2019-07-09 2020-12-08 深圳市中燃科技有限公司 Inspection remote control system and method for cooperative protection with fire-fighting system
NO20191192A1 (en) * 2019-10-04 2021-04-05 Connect Lng As Fluid transfer structure
WO2021063857A1 (en) * 2019-10-04 2021-04-08 Connect Lng As Fluid transfer structure for transfer of fluid across a body of water
NO345945B1 (en) * 2019-10-04 2021-11-08 Connect Lng As Fluid transfer structure

Also Published As

Publication number Publication date
GB0305370D0 (en) 2003-04-16

Similar Documents

Publication Publication Date Title
US7299760B2 (en) Floating LNG import terminal and method for docking
US8286678B2 (en) Process, apparatus and vessel for transferring fluids between two structures
US8186170B2 (en) Floating LNG regasification facility with LNG storage vessel
US8398445B2 (en) Automatic ice-vaning ship
US10549820B2 (en) Method and system for heading control during ship-to-ship transfer of LNG
US6336419B1 (en) Floating structure
US7287484B2 (en) Berthing method and system
US6453838B1 (en) Turret-less floating production ship
JP2005512883A (en) Single point mooring regasification tower
EP0739290B1 (en) A vessel for production and/or loading/unloading and transport of hydrocarbons from offshore fields, and/or for carrying out well operations
GB2399320A (en) Semi-submersible jetty for transferring LNG from a production vessel to a transport vessel
CN110352159B (en) Device for coupling two boats
AU2008239946B2 (en) System for loading of hydrocarbons from a floating vessel
US11541973B1 (en) Floating storage vessel with extension sections and offshore terminal
US10960958B2 (en) Device and method for securing a watercraft
US7426897B2 (en) Mooring apparatus
US20050002739A1 (en) Offshore fluid transfer system
AU2018232894B2 (en) A Method for Offshore LNG Transfer from a FLNG Facility to a LNG Carrier
EP1400442A1 (en) Mooring apparatus
CN114954800A (en) LNG switching barge of small waterplane asymmetric double-body type
NO345945B1 (en) Fluid transfer structure
Sterzenbach Operational Problems of Offshore Oil Loading and Possible Solutions To Overcome the Weather Limitations
NO782171L (en) SEAUGHTY VESSEL WITH TWO HULL.

Legal Events

Date Code Title Description
WAP Application withdrawn, taken to be withdrawn or refused ** after publication under section 16(1)