EP1058752B1 - Attachment for a finisher - Google Patents

Attachment for a finisher Download PDF

Info

Publication number
EP1058752B1
EP1058752B1 EP99917751A EP99917751A EP1058752B1 EP 1058752 B1 EP1058752 B1 EP 1058752B1 EP 99917751 A EP99917751 A EP 99917751A EP 99917751 A EP99917751 A EP 99917751A EP 1058752 B1 EP1058752 B1 EP 1058752B1
Authority
EP
European Patent Office
Prior art keywords
auxiliary equipment
finisher
additional
material storage
paver
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP99917751A
Other languages
German (de)
French (fr)
Other versions
EP1058752A1 (en
Inventor
Willi Dietrich
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hermann Kirchner GmbH and Co KG
Original Assignee
Hermann Kirchner GmbH and Co KG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hermann Kirchner GmbH and Co KG filed Critical Hermann Kirchner GmbH and Co KG
Publication of EP1058752A1 publication Critical patent/EP1058752A1/en
Application granted granted Critical
Publication of EP1058752B1 publication Critical patent/EP1058752B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C19/00Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
    • E01C19/48Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for laying-down the materials and consolidating them, or finishing the surface, e.g. slip forms therefor, forming kerbs or gutters in a continuous operation in situ

Definitions

  • the invention relates to an additional device for a paver for installing and compacting road surface layers, the paver comprising a chassis with a drive unit, a material reservoir (1), a driver 's cab (9), a distributor (5), a transport device (3) and a compaction screed (7) contains.
  • the additional device can be attached to commercially available pavers and is preferably used to lay two-layer asphalt layers. However, it is also possible to use concrete layers or combined concrete and to install asphalt layers and coverings of all kinds.
  • FR -A 2 697 036 describes a one-paver that has a main ceiling manufactured, e.g. is suitable for a street with car traffic and next to it a secondary ceiling is laid, for example. suitable for bicycle traffic With this paver, paving is hot-on-hot over the entire length Pave width not possible because rolled asphalt is a very tough mass that only by means of screws or other devices with great effort can be distributed or transported on the pad.
  • a paver which allows to use to install and close only one device on a two-layer asphalt layer compacted.
  • This paver is on an enlarged base frame.
  • second transport and distribution system arranged
  • a paver with two screeds is also known from EP-A-0 750 070.
  • each Screeds each include a material storage container, a conveyor line, a cross distributor and one Compaction screed.
  • the screeds are each on a frame with the chassis of the paver connected and can be adjusted in height using a hydraulic cylinder.
  • the invention has for its object to provide a device which, in combination with a commercially available paver, allows the installation of two covering layers of different materials in an economical manner , which can be produced inexpensively and which allows easy conversion of the paver, so that it both can be used for the installation of multi-layer road surfaces as well as for the conventional installation of a single layer surface.
  • a paver equipped with the additional device according to the invention enables the installation of a two-layer asphalt surface, or also the installation of cover layers made of other materials, with a Machine can only be done by retrofitting an existing one Paver can be adapted to the respective task by using a existing paver only attached or removed an additional device becomes.
  • This additional device can be easily removed again that the user only needs one machine that is suitable for both the conventional Installation of only one layer as well as for the installation of a two-layer Rubber can be used.
  • the machine is also Can be manufactured much more cost-effectively than a separate double-finished machine.
  • a paver provided with the additional device according to the invention has two separate compaction screeds, the first one being Standard or high compaction screed is designed and the second screed both as standard screed and as high compaction screed can be.
  • the first screed is used as a paving and pre-compaction screed enables an extremely high pre-compression, which is why one compared to the coverings laid using known methods have a considerably higher flatness of the two-layer covering is reached.
  • the high level of flatness achieved in this way in combination with the high pre-compression it enables if necessary, subsequent densification to a minimum to reduce.
  • An important advantage of the device according to the invention is that standard components that can be used for the usual pavers can be used for the components of the pre-distributor system and compaction screeds of the additional device.
  • the additional device and the material storage container for the base material is attached to the basic unit. For this it is only necessary to push and fasten them on the side of the basic device.
  • Figure 3 illustrates an embodiment for the additional device according to the invention.
  • Figure 4 shows an enlarged material storage container, which instead of Original storage container can be attached.
  • Figure 5 is the unarmed paver with attached additional device and Enlarged material storage container for the base layer material shown.
  • the frame consists of swiveling supports that are connected to the fixed part of the frame at bearings and can be moved with the help of hydraulic cylinders. Also are attached to the frame swivel arms with support wheels that the lateral Make it easier to move the additional device when mounting on the basic device and also to increase the stability of the overall arrangement contribute.
  • the Paver consists of a commercially available paver, in which a layer of material, in the case shown the base layer from the material reservoir via the conveyor belts for the system 1 to the pre-compaction screed 7 be transported, the material beforehand via the distribution screw 5 is distributed.
  • the material for the cover layer is stored and transported in the additional device according to the invention and installed with it.
  • an additional storage container 2 for the cover layer material is arranged on the frame of the additional device in such a way that it is in the assembled state in front of the storage container 1 of the paver.
  • the additional storage container 2 is heated, for which purpose the exhaust gases from the drive motors or additional heating devices operated with gas or electrically can be used.
  • the material to be installed is transported from the storage container 2 via the transport system 4, which is designed here in the form of screws, to the rear compaction screed 8 for the top layer.
  • the additional compaction screed 8 can be attached directly to the compaction screed 7 already present on the paver or separately on the paver
  • the control of the second screed can already be done on the machine existing leveling device or from an additional second leveling device respectively.
  • the second screed can be rigidly attached to the first screed with a height adjustment attached or articulated to the first screed.
  • the attachment to the leveling beam is expediently carried out. It is it is also possible to articulate the second screed on the chassis of the tractor to arrange.
  • FIG. 9 explains an embodiment example for an embodiment in which the Material storage container 2 is arranged behind the cab 9. It is in principle it is also possible to have this storage container above the driver's cab 9 or attached to the side of it.
  • this storage container In the embodiment shown in Figure 3 is a rotatable or above the storage container 2 Slidable version for an additional transport system, which here as Conveyor belt 10 is formed, attached.
  • Conveyor belt 10 can pull the material from the front of the paver, from from which it can be loaded in a simple manner to the storage container 2 can be transported.
  • a storage container is attached to a separately moving device outside the paver. This device can be pushed by the paver or moved self-propelled and / or attached above the paver in a self-supporting manner
  • the paver a transfer device with an intermediate storage container 11 attached are from which with the help of an intermediate storage conveyor belt 12 hot mix is transported via the storage container 1, 2.
  • a changeover flap 13 for reciprocal loading the paver 1 or 2 of the paver is attached.
  • the material receptacle 11 for temporary storage of the hot mix can be provided with a one-part or with a two-part chamber.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Machines (AREA)
  • Road Repair (AREA)
  • Portable Nailing Machines And Staplers (AREA)
  • Output Control And Ontrol Of Special Type Engine (AREA)
  • Bidet-Like Cleaning Device And Other Flush Toilet Accessories (AREA)
  • Optical Fibers, Optical Fiber Cores, And Optical Fiber Bundles (AREA)
  • Steering-Linkage Mechanisms And Four-Wheel Steering (AREA)
  • Pile Receivers (AREA)
  • Diaphragms For Electromechanical Transducers (AREA)
  • Transition And Organic Metals Composition Catalysts For Addition Polymerization (AREA)

Abstract

An attachment device for laying two surface layers which may also consist of different materials in a road way. The device should be economical to produce and suitable for laying multilayer road surfaces or for simply laying a conventional single layer surface. To this end, the inventive attachment contains elements for simultaneously laying two layers, hot on hot. The elements are mounted on a frame to be detachably connected to the finisher, the frame having fixing points for detachably connecting the attachment and the finisher and the attachment and the driver's cab.

Description

Die Erfindung betrifft eine Zusatzeinrichtung für einen Fertiger zum Einbauen und Verdichten von Straßenbelagschichten, wobei der Fertiger ein Fahrwerk mit einem Antriebsaggregat, einen Materialvorratsbehälter (1), ein Fahrerhaus (9), einen Verteiler (5), eine Transporteinrichtung (3) sowie eine Verdichtungsbohle (7) enthält. The invention relates to an additional device for a paver for installing and compacting road surface layers, the paver comprising a chassis with a drive unit, a material reservoir (1), a driver 's cab (9), a distributor (5), a transport device (3) and a compaction screed (7) contains.

Die Zusatzeinrichtung kann an handelsübliche Fertiger angebracht werden und dient vorzugsweise zum Einbau von zweischichtigen Asphaltschichten. Es ist jedoch damit auch möglich, Betonschichten oder kombinierte Beton- und Asphahschichten sowie Belägen jeglicher Art einzubauen.The additional device can be attached to commercially available pavers and is preferably used to lay two-layer asphalt layers. However, it is also possible to use concrete layers or combined concrete and to install asphalt layers and coverings of all kinds.

Im Stand der Technik ist es bekannt, mit Hilfe von Fertigern Belagschichten auf Straßenkonstruktionen aufzubringen. Derzeit dominiert hierfür die Asphaltbauweise da dieser Baustoff eine Reihe von Vorteilen aufweist. Um die Asphaltbauweise besser den Belastungen des Schwerverkehrs anzupassen, wird eine Erhöhung des Verdichtungsgrades und die Reduzierung der Stärke der Deckschichten angestrebt. Zur Erzielung einer wirksamen Abdichtung der Deckschicht sowie zur Minimierung der Alterung der Bindemittel und der Vermeidung von Spurrillen, Deckenschäden, Rissen und Abplatzungen wird in zunehmendem Maße Kompaktasphalt eingesetzt. Der Einbau erfolgt z.B. mit zwei Fertigern, die direkt hintereinander laufen.It is known in the prior art to use covering layers with the help of pavers to apply on road constructions. Currently, the Asphalt construction because this building material has a number of advantages. Around to better adapt the asphalt construction to the loads of heavy traffic, will increase the degree of compaction and reduce the Strength of the top layers sought. To achieve effective Sealing the top layer and to minimize the aging of the Binder and avoiding ruts, ceiling damage, cracks and Flaking is increasingly being used in compact asphalt. The Installation takes place e.g. with two pavers that run directly one behind the other.

In FR -A 2 697 036 ist ein Einzeckfertiger beschrieben, der eine Hauptdecke hergestellt, die z.B. für eine Straße mit Autoverkehr geeignet ist und daneben eine Nebendecke verlegt, die zB. für den Fahrradverkehr geeignet ist Mit diesem Fertiger ist der Einbau heiß- auf-heiß über die gesamte Einbaubreite nicht möglich, da Walzasphalt eine sehr zähe Masse ist, die nur mittels Schnecken oder anderer Vorrichtungen mit großem Kraftaufwand auf der Unterlage verteilt, bzw. transportiert werden kann.FR -A 2 697 036 describes a one-paver that has a main ceiling manufactured, e.g. is suitable for a street with car traffic and next to it a secondary ceiling is laid, for example. suitable for bicycle traffic With this paver, paving is hot-on-hot over the entire length Pave width not possible because rolled asphalt is a very tough mass that only by means of screws or other devices with great effort can be distributed or transported on the pad.

Nach EP 0 730 694 B1 ist ferner ein Fertiger bekannt, der es gestattet, mit nur einem Gerät eine zweischichtige Asphaltscbicht einzubauen und zu verdichten. Bei diesem Fertiger ist auf einem vergrößertem Grundgestell ein. zweites Transport- und Verteilersystem angeordnetAccording to EP 0 730 694 B1, a paver is also known which allows to use to install and close only one device on a two-layer asphalt layer compacted. This paver is on an enlarged base frame. second transport and distribution system arranged

Nachteilig bei dieser Anordnung ist, daß für den Einbau von zwei Asphalt-Schichten ein Spezialfertiger erforderlich ist, der nur für den speziellen Einsatz eines zweischichtigen Asphaltaufbaus verwendet werden kann und der sehr hohe Herstellungskosten erfordert.The disadvantage of this arrangement is that for the installation of two layers of asphalt a special paver is required that is only for the special Use of a two-layer asphalt structure can be used and which requires very high manufacturing costs.

Aus der EP-A-0 750 070 ist des weiteren ein Fertiger mit zwei Einbaubohlen bekannt. Zu jeder dieser Einbaubohlen gehören je ein Materialvorratsbehälter, eine Förderstrecke, ein Querverteiler sowie eine Verdichtungsbohle. Die Einbaubohlen sind jeweils über ein Gestell mit dem Fahrwerk des Fertigers verbunden und können mit Hilfe eines Hydraulikzylinders höhenverstellt werden.A paver with two screeds is also known from EP-A-0 750 070. To each of these Screeds each include a material storage container, a conveyor line, a cross distributor and one Compaction screed. The screeds are each on a frame with the chassis of the paver connected and can be adjusted in height using a hydraulic cylinder.

Der Erfindung liegt die Aufgabe zugrunde, eine Einrichtung zu schaffen, die in Kombination mit einem handelsüblichen Fertiger den Einbau von zwei Belagschichten auch unterschiedlichen Materials in wirtschaftlicher Weise ermöglicht , die kostengünstig hergestellt werden kann und die ein einfaches Umrüsten des Fertiger gestattet, so dass dieser sowohl für den Einbau von mehrschichtigen Straßenbelägen als auch für den herkömmlichen Einbau eines einschichtigen Belages verwendet werden kann.The invention has for its object to provide a device which, in combination with a commercially available paver, allows the installation of two covering layers of different materials in an economical manner , which can be produced inexpensively and which allows easy conversion of the paver, so that it both can be used for the installation of multi-layer road surfaces as well as for the conventional installation of a single layer surface.

Erfindungsgemäß gelingt die Lösung der Aufgabe mit den kennzeichnenden Merkmalen von Patentanspruch 1.According to the invention the problem is solved with the characteristic Features of claim 1.

Vorteilhafte Ausgestaltungen der erfindungsgemäßen Einrichtung sind in den Unteransprüchen angegeben.Advantageous refinements of the device according to the invention are shown in specified in the subclaims.

Ein mit der erfindungsgemäßen Zusatzeinrichtung ausgerüsteter Fertiger ermöglicht es, daß der Einbau einer zweischichtigen Asphaltdecke, bzw. auch der Einbau von Deckschichten aus anderen Materialien, mit einer Maschine erfolgen kann, die lediglich durch Umrüsten eines vorhandenen Fertigers an die jeweilige Aufgabe angepasst werden kann, indem an einem vorhandenem Fertiger nur eine Zusatzeinrichtung angebracht bzw. abmontiert wird. Diese Zusatzeinrichtung kann leicht wieder entfernt werden, so daß der Anwender nur eine Maschine benötigt, die sowohl für den konventionellen Einbau nur einer Schicht als auch für den Einbau eines zweischichtigen Belages verwendet werden kann. Die Maschine ist außerdem wesentlich kostengünstiger herstellbar als ein gesonderter Doppelfertiger.A paver equipped with the additional device according to the invention enables the installation of a two-layer asphalt surface, or also the installation of cover layers made of other materials, with a Machine can only be done by retrofitting an existing one Paver can be adapted to the respective task by using a existing paver only attached or removed an additional device becomes. This additional device can be easily removed again that the user only needs one machine that is suitable for both the conventional Installation of only one layer as well as for the installation of a two-layer Rubber can be used. The machine is also Can be manufactured much more cost-effectively than a separate double-finished machine.

Ein mit der erfindungsgemäßen Zusatzeinrichtung versehener Fertiger verfügt über zwei getrennte Verdichtungsbohlen, wobei die erste Bohle als Standard- oder hochverdichtende Bohle ausgelegt ist und die zweite Bohle sowohl als Standardbohle als auch als Hochverdichtungsbohle ausgerführt sein kann. Die erste Bohle dient als Einbau- und Vorverdichtungsbohle und ermöglicht eine extrem hohe Vorverdichtung, weshalb eine gegenüber den nach bekannten Verfahren verlegten Belägen wesentlich höhere Ebenflächigkeit des zweischichtigen Belages erreicht wird. Die so erzielte hohe Ebenflächigkeit ermöglicht es in Verbindung mit der hohen Vorverdichtung, die gegebenenfalls noch erforderliche Nachverdichtung auf ein Mindestmaß zu reduzieren.A paver provided with the additional device according to the invention has two separate compaction screeds, the first one being Standard or high compaction screed is designed and the second screed both as standard screed and as high compaction screed can be. The first screed is used as a paving and pre-compaction screed enables an extremely high pre-compression, which is why one compared to the coverings laid using known methods have a considerably higher flatness of the two-layer covering is reached. The high level of flatness achieved in this way in combination with the high pre-compression it enables if necessary, subsequent densification to a minimum to reduce.

Ein wichtiger Vorteil der erfindungsgemäßen Einrichtung besteht darin, daß serienmäßige, für die üblichen Fertiger verwendbare Komponenten für die Bauteile Vorverteilersystem und Verdichtungsbohlen der Zusatzeinrichtung verwendet werden können.An important advantage of the device according to the invention is that standard components that can be used for the usual pavers can be used for the components of the pre-distributor system and compaction screeds of the additional device.

Durch die erfindungsgemäße Anordnung der zwei Verdichtungsbohlen besteht ferner die Möglichkeit, getrennte Profile für die beiden Schichten zu erzeugen, z.B. können Regenrinnen eingebracht werden. Ein weiterer wichtiger Vorteil besteht darin, daß in einfacher Weise durch Entfernen der Zusatzeinrichtung ein herkömmlicher Fertiger entsteht, dessen Funktionen voll erhalten bleiben und der ohne ein zusätzliches Übergabegerät arbeiten kann.By arranging the two compaction screeds according to the invention there is also the possibility of creating separate profiles for the two layers generate, e.g. gutters can be installed. Another important advantage is that by simply removing the Additional device creates a conventional paver, whose functions remain fully intact and work without an additional transfer device can.

Es ist möglich, die Steuerung der Schichstärke, die sogenannte Nivellierung gekoppelt mit der ersten Bohle oder unabhängig davon mit einer gesondert arbeitenden Steuerung für die zweite Bohle zu versehen. Als Verdichtungsbohlen können handelsübliche starre Bohlen oder auch ausfahrbare Bohlen eingesetzt werden. It is possible to provide the control of the layer thickness, the so-called leveling coupled with the first screed or independently of it with a separate control for the second screed. Commercially available rigid screeds or extendable screeds can be used as compaction screeds.

Die Erfindung wird im Folgenden anhand eines Ausführungsbeispieles näher erläutert. In der zugehörigen Zeichnung zeigen:

  • Figur 1 einen handelsüblichen Fertiger im Ausgangszustand,
  • Figur 2 den Fertiger nach Abbau von Materialvorratsbehälter und Fahrerhaus,
  • Figur 3 eine erfindungsgemäße Zusatzeinrichtung,
  • Figur 4 einen vergrößerten Materialvorratsbehälter,
  • Figur 5 den Fertiger mit angebauter Zusatzeinrichtung und vergrößertem Materialvorratsbehälter für das Tragschichtmaterial,
  • Figur 6 den Fertiger mit angebauter Zusatzeinrichtung mit hochgeklapptem Teil,
  • Figur 7 eine Ansführungsform für einen mit der erfindungsgemäßen Zusatzeinrichtung versehenen Fertiger und einer zusätzlich am Fertiger angebrachten Übergabeeinrichtung in Seitenansicht,
  • Figur 8 die zugehörige Draufsicht,
  • Figur 9 die Seitensicht einer Ausfuhrungsform mit je einer vorn und hinten an der Zusatzeinrichtung angeordneten Materialvorratsmulde.
  • The invention is explained in more detail below using an exemplary embodiment. In the accompanying drawing:
  • 1 shows a commercially available paver in the initial state,
  • FIG. 2 the paver after dismantling the material storage container and driver's cab,
  • FIG. 3 shows an additional device according to the invention,
  • FIG. 4 shows an enlarged material storage container,
  • 5 shows the paver with attached additional device and enlarged material storage container for the base layer material, FIG.
  • FIG. 6 the paver with attached additional device with part folded up,
  • FIG. 7 shows a side view of an embodiment for a paver provided with the additional device according to the invention and a transfer device additionally attached to the paver,
  • FIG. 8 the associated top view,
  • FIG. 9 shows the side view of an embodiment with a material storage trough arranged at the front and rear of the additional device.
  • In Figur 1 ist ein handelsüblicher Fertiger dargestellt, an den die erfindungsgemäße Zusatzeinrichtung angebracht werden soll,In Figure 1, a commercial paver is shown to which the invention Additional device is to be attached,

    Für das Umrüsten des Fertigers zu einem Einbaugerät, mit dem ein zweischichtiger Asphaltbelag verlegt werden kann, werden zunächst der Materialvorratsbehälter und das Fahrerhaus abgebaut Der Zustand nach dem Abbau dieser Einrichtungen ist in Figur 2 dargestellt An dem verbleibendem Grundgerät befinden sich das Fahrwerk des Fertigers mit dem Antriebsaggregat, die Verteiler- und Transporteinrichtungen sowie die Verdichtungsbohle für das Tragscbichtmaterial.For converting the paver to a built-in device with the two-layer asphalt covering can be laid first Material storage container and the cab dismantled The state after the dismantling of these facilities is shown in Figure 2 on the remaining The chassis of the paver with the basic device Drive unit, the distribution and transport facilities and the Compaction screed for the load-bearing material.

    Danach werden die Zusatzeinrichtung und der Materialvorratsbehälter für das Tragschichtmaterial am Grundgerät angebracht. Hierzu ist es nur erforderlich, diese seitlich auf das Grundgerät zu schieben und zu befestigen.Then the additional device and the material storage container for the base material is attached to the basic unit. For this it is only necessary to push and fasten them on the side of the basic device.

    Figur 3 erläutert eine Ausführungsform für die erfindungsgemäße Zusatzeinrichtung.Figure 3 illustrates an embodiment for the additional device according to the invention.

    Figur 4 zeigt einen vergrößerten Materialvorratsbehälter, der anstelle des Originavorratsbehälters angebracht werden kann.Figure 4 shows an enlarged material storage container, which instead of Original storage container can be attached.

    In Figur 5 ist der ungerüstete Fertiger mit angebauter Zusatzeinrichtung und vergrößertem Materialvorratsbehälter für das Tragschichtmaterial dargestellt.In Figure 5 is the unarmed paver with attached additional device and Enlarged material storage container for the base layer material shown.

    Wie aus Figur 6 ersichtlich ist, ist es möglich einen Teil der angebauten Zusatzeinrichtung nach oben zu schwenken. Dies ist vorteilhaft, um Wartungsarbeiten am Grundgerät durchführen zu können, ohne daß die Zusatzeinrichtung entfernt werden muss. Um das Schwenken der Zusatzeinrichtung zu ermöglichen, besteht das Gestell aus schwenkbaren Trägern, die an Lagerstellen mit dem feststehendem Teil des Gestells verbunden sind und mit Hilfe von Hydraulikzylindern bewegt werden können. Außerdem sind am Gestell Schwenkarme mit Stützrädern angebracht, die das seitliche Heranfahren der Zusatzeinrichtung beim Anbau an das Grundgerät erleichtern und außerdem zur Erhöhung der Standsicherheit der Gesamtanordnung beitragen.As can be seen from Figure 6, it is possible for some of the attached To pivot the additional device upwards. This is beneficial to To be able to carry out maintenance work on the basic device without the Additional device must be removed. To swivel the additional device to enable, the frame consists of swiveling supports that are connected to the fixed part of the frame at bearings and can be moved with the help of hydraulic cylinders. Also are attached to the frame swivel arms with support wheels that the lateral Make it easier to move the additional device when mounting on the basic device and also to increase the stability of the overall arrangement contribute.

    Bei dem in den Figuren 7 und 8 dargestellten Fertiger befinden sich sowohl der Materialvorratsbehälter 1 für die Tragschicht als auch der Materialvorratsbehälter 2 für die Deckschicht an der Vorderseite des Fertigers. Der Fertiger besteht aus einem handelsüblichen Fertiger, bei dem eine Materialschicht, im dargestellten Fall die Tragschicht aus dem Materialvorratsbehälter über die Transportbänder für das System 1 zur Vorverdichtungsbohle 7 transportiert werden, wobei das Material vorher über die Verteilerschnecke 5 verteilt wird.In the paver shown in Figures 7 and 8 there are both the material storage container 1 for the base layer as well as the material storage container 2 for the top layer on the front of the paver. The Paver consists of a commercially available paver, in which a layer of material, in the case shown the base layer from the material reservoir via the conveyor belts for the system 1 to the pre-compaction screed 7 be transported, the material beforehand via the distribution screw 5 is distributed.

    Zum Anbau der Zusatzeinrichtung an einen handelsüblichen Fertiger ist es lediglich erforderlich, das Fahrerhaus 9 von diesem abzubauen, die Zusatzeinrichtung auf das Fahrwerk des Fertigers zu schieben und die Zusatzeinrichtung am Fahrwerk des Fertigers sowie am Fahrerhaus 9 zu befestigen. Zur Befestigung werden vorteilhaft Scaraubverbindungen verwendet, die im dargestellten Beispiel an gabelförmigen Befestigungselementen sowie an entsprechenden Öffnungen der zu verbindenden Baugrupppen angebracht werden. It is for attaching the additional device to a commercially available paver only required to dismantle the driver's cab 9, the additional device to slide on the paver chassis and the additional device to be attached to the paver's chassis and cab 9. Scaraub connections are advantageously used for fastening, which in example shown on fork-shaped fasteners and appropriate openings of the modules to be connected attached become.

    Das Material für die Deckschicht wird in der erfindungsgemäßen Zusatzeinrichtung gelagert und transportiert und mit dieser eingebaut. Hierzu ist ein zusätzlicher Vorratsbehälter 2 für das Deckschichtmaterial so am Gestell der Zusatzeinrichtung angeordnet, daß er sich im montierten Zustand vor dem Vorratsbehälter 1 des Fertigers befindet. Der zusätzliche Vorratsbehälter 2 ist beheizt, wozu die Abgase der Antriebsmotoren oder zusätzliche, mit Gas oder elektrisch betriebene Heizeinrichtungen verwendet werden können. Vom Vorratsbehälter 2 wird das einzubauende Material über das Transportsystem 4, das hier in Form von Schnecken ausgebildet ist, zur hinteren Verdichtungsbohle 8 für die Deckschicht transportiert. Die zusätzliche Verdichtungsbohle 8 kann unmittelbar an der bereits am Fertiger vorhandenen Verdichtungbohle 7 oder separat am Fertiger angebracht seinThe material for the cover layer is stored and transported in the additional device according to the invention and installed with it. For this purpose, an additional storage container 2 for the cover layer material is arranged on the frame of the additional device in such a way that it is in the assembled state in front of the storage container 1 of the paver. The additional storage container 2 is heated, for which purpose the exhaust gases from the drive motors or additional heating devices operated with gas or electrically can be used. The material to be installed is transported from the storage container 2 via the transport system 4, which is designed here in the form of screws, to the rear compaction screed 8 for the top layer. The additional compaction screed 8 can be attached directly to the compaction screed 7 already present on the paver or separately on the paver

    Die Steuerung der zweiten Bohle kann mittels einer an der Maschine bereits vorhandenen Nivelliereinchtung oder von einer zusätzlichen zweiten Nivelliereinrichtung erfolgen.The control of the second screed can already be done on the machine existing leveling device or from an additional second leveling device respectively.

    Die zweite Bohle kann sowohl starr an der ersten Bohle mit einer HöhenverStellung angebracht oder gelenkig mit der ersten Bohle verbunden sein. Zweckmäßigerweise erfolgt dabei die Befestigung am Nivellierholm. Es ist außerdem möglich, die zweite Bohle gelenkig am Chassis der Zugmaschine anzuordnen.The second screed can be rigidly attached to the first screed with a height adjustment attached or articulated to the first screed. The attachment to the leveling beam is expediently carried out. It is it is also possible to articulate the second screed on the chassis of the tractor to arrange.

    Figur 9 erläutert ein Ausführunsbeispiel für eine Ausführung, bei der der Materialvorratsbehälter 2 hinter dem Fahrerhaus 9 angeordnet ist. Es ist prinzipiell auch möglich, diesen Vorratsbehälter oberhalb des Fahrerhauses 9 oder seitlich davon anzubringen. Bei der in Figur 3 dargestellten Ausführungsform ist oberhalb des Vorratsbehälters 2 eine drebbare oder verschiebbare Ausführung für ein zusätzliches Transportsystem, das hier als Transportband 10 ausgebildet ist, angebracht. Mit diesem zusätzlichen Transportband 10 kann das Material von der Vorderseite des Fertigers, von dem aus er in einfacher Weise beschickt werden kann, zum Vorratsbehälter 2 transportiert werden. Um ein ungehindertes Füllen des Vorratsbehälters 1 zu ermöglichen, ist das zusätzliche Transportband 10 in Fahrtrichtung drehbar oder verschiebbar angeordnet, so daß es beim Befüllen des Behälters 1 nach hinten geschoben werden kann und sich zum Befüllen des Behälters 2 in der vorderen Position befindetFIG. 9 explains an embodiment example for an embodiment in which the Material storage container 2 is arranged behind the cab 9. It is in principle it is also possible to have this storage container above the driver's cab 9 or attached to the side of it. In the embodiment shown in Figure 3 is a rotatable or above the storage container 2 Slidable version for an additional transport system, which here as Conveyor belt 10 is formed, attached. With this additional Conveyor belt 10 can pull the material from the front of the paver, from from which it can be loaded in a simple manner to the storage container 2 can be transported. To ensure that the storage container 1 can be filled unhindered To enable the additional conveyor belt 10 in the direction of travel rotatably or slidably arranged so that it is when filling the container 1 can be pushed backwards and used to fill the container 2 is in the front position

    Es ist auch möglich, daß ein Vorratsbehälter an einern separat fahrenden Gerät außerhalb des Fertigers angebracht ist. Dieses Gerät kann vom Fertiger geschoben oder selbstfahrend bewegt werden und/oder selbsttragend oberhalb des Fertigers angebracht seinIt is also possible that a storage container is attached to a separately moving device outside the paver. This device can be pushed by the paver or moved self-propelled and / or attached above the paver in a self-supporting manner

    In den Figuren 7 bis 9 ist eine Ausführung dargestellt, bei der am Fertiger eine Übergabeeinrichtung mit einem Zwischenlagerbehälter 11 angebracht sind, von dem aus mit Hilfe eines Zwischenlagertransportbandes 12 das heiße Mischgut über die Vorratsbehälter 1,2 transportiert wird. Oberhalb der Vorratsbehälter 1,2 ist eine Umstellklappe 13 zur wechselseitigen Beschikkung der Vorratsbehälter 1 oder 2 des Fertigers angebracht Der Materialaufnahmebehälter 11 zur zeitweiligen Aufbewahrung des heißen Mischgutes kann mit einer einteiligen oder mit einer zweiteiligen Kammer versehen sein. In the figures 7 to 9, an embodiment is shown in which the paver a transfer device with an intermediate storage container 11 attached are from which with the help of an intermediate storage conveyor belt 12 hot mix is transported via the storage container 1, 2. Above the Storage container 1, 2 is a changeover flap 13 for reciprocal loading the paver 1 or 2 of the paver is attached. the material receptacle 11 for temporary storage of the hot mix can be provided with a one-part or with a two-part chamber.

    BEZUGSZEICHENLISTELIST OF REFERENCE NUMBERS

    11
    Materialvorratsbehälter für TragschichtMaterial storage container for base course
    22
    Materialvorratsbehälter für DeckschichtMaterial storage container for top layer
    33
    Transportbänder für System 1System 1 conveyor belts
    44
    Transporteinrichtung für System 2Transport device for system 2
    55
    Verteilerschnecke für System 1Distribution screw for system 1
    66
    Verteilerschnecke für System 2Distribution screw for system 2
    77
    Verdichtungsbohle für TragschichtCompaction screed for base course
    88th
    Verdichtungsbohle für DeckschichtCompaction screed for top layer
    99
    Fahrerbausdriver construction
    1010
    zusätzliches Transportbandadditional conveyor belt
    1111
    ZwischenlagerbehälterIntermediate storage container
    1212
    ZwischenlagertransportbandInterim storage conveyor belt
    1313
    UmstellklappeUmstellklappe

    Claims (9)

    1. Auxiliary equipment for a finisher for the placing and compacting of road surfacing layers, with the finisher including a running gear with a drive assembly, a material storage bin (1), a driver's cab (9), a distributor (5), a conveyor unit (3) as well as a compaction board (7), and with the auxiliary equipment including means which allow the hot-to-hot placing of two layers in conjunction with the finisher, with the means consisting of an additional material storage bin (2), an additional distribution facility (6) and an additional compaction board (8), characterized in that the auxiliary equipment is arranged at a mounting which is to be connected to the finisher in a detachable manner, which can be pushed on laterally onto the running gear of the finisher and which contains attachment points for the detachable connection with the auxiliary equipment and with the driver's cab, and in that the mounting presents swivelling supports which can be moved by means of hydraulic cylinders.
    2. Auxiliary equipment as claimed in claim 1, characterized in that both the material storage bin (1) for the base course and the additional material storage bin (2) for the wearing course are located at the front side of the finisher.
    3. Auxiliary equipment as claimed in claim 1 or 2, characterized in that swivelling arms with support wheels are mounted to the mounting, and facilitate the lateral approach movement of the auxiliary equipment during mounting to the basic unit.
    4. Auxiliary equipment as claimed at least in one of the foregoing claims, characterized in that, at the additional compaction board (8), a controlling system is arranged for setting the layer thickness of the second layer and allows the setting of the layer thickness by readjusting the board's inclination, while the controlling system is either coupled to the control for the first compaction board (7), or is designed as an independently working control.
    5. Auxiliary equipment as claimed at least in one of the foregoing claims, characterized in that heating devices are mounted to the conveyor units (3, 4) and/or to the material storage bins (1, 2).
    6. Auxiliary equipment as claimed at least in one of the foregoing claims, characterized in that an additional slidable belt for loading the additional material storage bin (2) is mounted on the finisher.
    7. Auxiliary equipment as claimed at least in one of the foregoing claims, characterized in that the auxiliary equipment is connected to a transfer equipment for the two-way loading of the material storage bins (1, 2) which is mounted to the rear part of the finisher.
    8. Auxiliary equipment as claimed at least in one of the foregoing claims, characterized in that the transfer equipment includes an intermediate storage bin (11) for the temporary storage of the hot mixture with a two-part chamber.
    9. Auxiliary equipment as claimed at least in one of the foregoing claims, characterized in that an automatic distance regulating device is mounted to the auxiliary equipment, and is used to regulate the distance between the finisher and a transfer unit running behind the finisher.
    EP99917751A 1998-02-24 1999-02-20 Attachment for a finisher Expired - Lifetime EP1058752B1 (en)

    Applications Claiming Priority (3)

    Application Number Priority Date Filing Date Title
    DE29803077U 1998-02-24
    DE29803077U DE29803077U1 (en) 1998-02-24 1998-02-24 Additional equipment for a paver
    PCT/DE1999/000479 WO1999042664A1 (en) 1998-02-24 1999-02-20 Attachment for a finisher

    Publications (2)

    Publication Number Publication Date
    EP1058752A1 EP1058752A1 (en) 2000-12-13
    EP1058752B1 true EP1058752B1 (en) 2003-06-04

    Family

    ID=8053047

    Family Applications (1)

    Application Number Title Priority Date Filing Date
    EP99917751A Expired - Lifetime EP1058752B1 (en) 1998-02-24 1999-02-20 Attachment for a finisher

    Country Status (10)

    Country Link
    US (1) US6467992B1 (en)
    EP (1) EP1058752B1 (en)
    JP (1) JP4076118B2 (en)
    AT (1) ATE242359T1 (en)
    DE (2) DE29803077U1 (en)
    DK (1) DK1058752T3 (en)
    ES (1) ES2201704T3 (en)
    PL (1) PL199223B1 (en)
    PT (1) PT1058752E (en)
    WO (1) WO1999042664A1 (en)

    Cited By (2)

    * Cited by examiner, † Cited by third party
    Publication number Priority date Publication date Assignee Title
    DE102006047332A1 (en) * 2006-09-08 2008-03-27 Dynapac Gmbh Making multilayer road surfacer for laying multilayer road surfaces involves conversion whereby an upper road surfacer is arranged above a lower base road surfacer
    DE102007013972A1 (en) * 2007-03-23 2008-10-02 Hermann Kirchner Bauunternehmung Gmbh Work machine unit, in particular for installation and for compacting paving layers, and method for assembling the work machine unit

    Families Citing this family (15)

    * Cited by examiner, † Cited by third party
    Publication number Priority date Publication date Assignee Title
    FR2789705B1 (en) * 1999-02-15 2003-06-20 Colas Sa DRAINING BITUMINOUS LAYER, PAVEMENT COMPRISING SUCH A LAYER AND METHOD FOR OBTAINING SUCH A LAYER
    DE19907213B4 (en) * 1999-02-19 2011-06-22 Dynapac GmbH, 26203 Road paver for simultaneously producing at least two layers of a road surface
    DE20103858U1 (en) 2000-03-07 2001-07-26 Hermann Kirchner GmbH & Co KG, 36251 Bad Hersfeld Additional equipment for a paver
    WO2004074578A1 (en) * 2003-02-19 2004-09-02 Nippo Corporation Asphalt uniformly paving equipment
    US6966725B2 (en) * 2003-10-21 2005-11-22 Cochran Norman L Apparatus for spreading aggregate material on a road berm
    DE102004051748B4 (en) * 2004-10-23 2008-03-06 Baulabor Fienstedt Gmbh Process for producing a multi-layer asphalt pavement with mastic asphalt top layer and paver combination
    EP1897999A2 (en) * 2006-09-08 2008-03-12 Dynapac GmbH Method for creating a multi-layer finisher for applying multi-layer road paving and multi-layer finisher
    US8068962B2 (en) 2007-04-05 2011-11-29 Power Curbers, Inc. 3D control system for construction machines
    DE102010060505A1 (en) * 2010-11-11 2012-05-16 Gottwald Port Technology Gmbh Container transport vehicle
    US8591144B1 (en) 2012-03-23 2013-11-26 Q & D Construction, Inc. Mixer and placer paving systems
    DE102014018533B4 (en) * 2014-12-12 2023-09-28 Bomag Gmbh Method for controlling a work train
    US10407845B1 (en) * 2018-08-22 2019-09-10 Caterpillar Paving Products Inc. Oscillation assembly for a paving machine
    NL2022692B1 (en) * 2019-03-07 2020-09-17 Jansen Infra Verhuur B V Paving assembly and method of providing such an assembly
    BE1028633B1 (en) * 2021-05-18 2022-04-19 Res Inst Highway Mini Transp A two-layer paver for high-level, high-thickness cement concrete pavement
    CN115852781B (en) * 2022-11-29 2023-12-22 河海大学 Screed lifting device of paver

    Family Cites Families (23)

    * Cited by examiner, † Cited by third party
    Publication number Priority date Publication date Assignee Title
    US2891335A (en) * 1955-06-02 1959-06-23 Fred H Linneman Road repair equipment roller attachment for graders
    US3016635A (en) * 1958-11-24 1962-01-16 William W Aston C-bar structure
    CA1014783A (en) * 1974-10-12 1977-08-02 Ernst-August Schrader Device for the adjustment of the working width of road finishers
    US3967913A (en) * 1974-12-16 1976-07-06 Gabriel Jr Gifford W Asphalt roadway patching apparatus
    DE2850344A1 (en) * 1978-11-20 1980-05-22 Reinhard Wirtgen METHOD AND DEVICE FOR REMOVING AND RE-COATING ROAD COVERINGS
    US4272212A (en) * 1979-06-15 1981-06-09 Andrew J. Bauer, Jr. Method and apparatus for rejuvenating and recycling asphalt
    FR2578872B1 (en) * 1985-03-14 1987-04-10 Viafrance Sa TRACT MOLDING TOOL FOR MAKING CONCRETE SLABS ON THE GROUND
    US4702642A (en) * 1986-07-25 1987-10-27 Cedarapids, Inc. Extensible screed assembly for a bituminous paver
    EP0308404B2 (en) * 1987-04-10 1995-02-15 DOMENIGHETTI, Domenico Road paver-finisher with a combination of axles with steering wheels and crawler units
    US4765772A (en) * 1987-05-29 1988-08-23 Angelo Benedetti, Inc. Method and apparatus for filling voids in recycled asphalt
    US4896489A (en) * 1989-03-22 1990-01-30 Deere & Company Implement lift and flotation system with a single transversely adjustable cylinder
    US5000615A (en) * 1990-01-09 1991-03-19 Cmi Corporation System for reclaiming and relaying pavement in place
    US5026206A (en) * 1990-03-30 1991-06-25 Oconnor Patrick L Pavement and base recycle method and apparatus
    US5251999A (en) * 1992-03-25 1993-10-12 Mccracken Hilton G Self-propelled pavement repair apparatus
    FR2697036B1 (en) * 1992-10-16 1995-02-03 Applic Derives Asphalte Device for the implementation of road surfaces.
    DE4237512A1 (en) * 1992-11-08 1994-05-11 Wirtgen Gmbh Method and device for repairing damaged lanes
    CN1052282C (en) * 1993-11-27 2000-05-10 E·里克特 Process for operating a finisher and finisher for laying and compacting asphalt layers
    DE29510058U1 (en) * 1995-06-21 1995-11-02 Joseph Vögele AG, 68163 Mannheim Paver
    DE29603717U1 (en) * 1996-02-29 1996-04-18 Joseph Voegele Ag, 68163 Mannheim Conveyor for paving material and feeder or paver
    DE29617116U1 (en) * 1996-10-01 1996-11-21 Joseph Vögele AG, 68163 Mannheim Built-in train
    DE19647150C2 (en) * 1996-11-14 2001-02-01 Moba Mobile Automation Gmbh Device and method for controlling the installation height of a road finisher
    DE29712038U1 (en) * 1997-07-09 1998-01-02 GVS mbH & Co. KG, 36251 Bad Hersfeld Paving device for paving a two-layer asphalt layer
    US5924819A (en) * 1998-01-23 1999-07-20 Caterpillar Paving Products Linkage mechanism for an extendable asphalt paver screed

    Cited By (2)

    * Cited by examiner, † Cited by third party
    Publication number Priority date Publication date Assignee Title
    DE102006047332A1 (en) * 2006-09-08 2008-03-27 Dynapac Gmbh Making multilayer road surfacer for laying multilayer road surfaces involves conversion whereby an upper road surfacer is arranged above a lower base road surfacer
    DE102007013972A1 (en) * 2007-03-23 2008-10-02 Hermann Kirchner Bauunternehmung Gmbh Work machine unit, in particular for installation and for compacting paving layers, and method for assembling the work machine unit

    Also Published As

    Publication number Publication date
    ATE242359T1 (en) 2003-06-15
    EP1058752A1 (en) 2000-12-13
    PL342494A1 (en) 2001-06-04
    US6467992B1 (en) 2002-10-22
    DE59905833D1 (en) 2003-07-10
    PL199223B1 (en) 2008-08-29
    WO1999042664A1 (en) 1999-08-26
    DK1058752T3 (en) 2003-09-29
    DE29803077U1 (en) 1998-06-25
    ES2201704T3 (en) 2004-03-16
    JP2002504636A (en) 2002-02-12
    PT1058752E (en) 2003-10-31
    JP4076118B2 (en) 2008-04-16

    Similar Documents

    Publication Publication Date Title
    EP1058752B1 (en) Attachment for a finisher
    EP0750070B1 (en) A Road Finisher and a Method of Applying Surface Layers
    DE102015006250B4 (en) Screed unit for a paver finisher and paver with such a screed unit
    DE102017104862A1 (en) ROAD CONSTRUCTION MACHINE
    DE29519719U1 (en) Device for installing covering layers
    WO2018033516A1 (en) Slope finisher
    DE8300083U1 (en) SCREED FOR A PAVER
    EP1261775B1 (en) Accessory for a road finishing machine
    EP1873314B1 (en) Method for producing compact asphalt surfacing
    WO2011042130A1 (en) Method and device for reinforcing a pavement structure
    WO1995014820A1 (en) Process for operating a finisher and finisher for laying and compacting asphalt layers
    DE202005004049U1 (en) Compact asphalt production system, includes machine for laying base layer and machine for laying top layer on top of still hot base layer
    EP3498915B1 (en) Road finisher with raisable chassis
    DE69001973T2 (en) Extendable screed for compacting and manufacturing road surface layers with spraying device for liquid binder.
    DE19652396C1 (en) Ceiling production unit with machine frame and continuous track chassis
    EP1032732A1 (en) Combination of insertion devices for inserting and pre-compressing asphalt layers
    DE19724294C1 (en) Movable tent for providing protection to surfaces exposed to the weather
    EP1972721A2 (en) Work machine unit, in particular for installing and compacting road paving layers and method for installing the work machine unit
    DE20216202U1 (en) Plant for the rehabilitation of a formation
    DE102006047332A1 (en) Making multilayer road surfacer for laying multilayer road surfaces involves conversion whereby an upper road surfacer is arranged above a lower base road surfacer
    DE102020120833B4 (en) Attachment device for a truck for applying a covering layer of pourable building material to a road and/or path substructure
    EP1897999A2 (en) Method for creating a multi-layer finisher for applying multi-layer road paving and multi-layer finisher
    WO1989001077A1 (en) Lateral finisher/distributor
    DE2158818A1 (en) PROCESS FOR MANUFACTURING AND SEALING BOOSTS, FOR EXAMPLE FOR CANALS AND STORAGE BASINS AND DEVICE FOR CARRYING OUT THE PROCESS
    DE29712038U1 (en) Paving device for paving a two-layer asphalt layer

    Legal Events

    Date Code Title Description
    PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

    Free format text: ORIGINAL CODE: 0009012

    17P Request for examination filed

    Effective date: 20000902

    AK Designated contracting states

    Kind code of ref document: A1

    Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE

    RBV Designated contracting states (corrected)

    Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE

    GRAH Despatch of communication of intention to grant a patent

    Free format text: ORIGINAL CODE: EPIDOS IGRA

    GRAH Despatch of communication of intention to grant a patent

    Free format text: ORIGINAL CODE: EPIDOS IGRA

    GRAA (expected) grant

    Free format text: ORIGINAL CODE: 0009210

    AK Designated contracting states

    Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: IE

    Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

    Effective date: 20030604

    REG Reference to a national code

    Ref country code: GB

    Ref legal event code: FG4D

    Free format text: NOT ENGLISH

    REG Reference to a national code

    Ref country code: CH

    Ref legal event code: EP

    REG Reference to a national code

    Ref country code: IE

    Ref legal event code: FG4D

    Free format text: GERMAN

    REF Corresponds to:

    Ref document number: 59905833

    Country of ref document: DE

    Date of ref document: 20030710

    Kind code of ref document: P

    REG Reference to a national code

    Ref country code: SE

    Ref legal event code: TRGR

    REG Reference to a national code

    Ref country code: DK

    Ref legal event code: T3

    REG Reference to a national code

    Ref country code: GR

    Ref legal event code: EP

    Ref document number: 20030403522

    Country of ref document: GR

    GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)

    Effective date: 20031018

    REG Reference to a national code

    Ref country code: IE

    Ref legal event code: FD4D

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: LU

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20040220

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: MC

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20040228

    Ref country code: BE

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20040228

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: DK

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20040301

    REG Reference to a national code

    Ref country code: ES

    Ref legal event code: FG2A

    Ref document number: 2201704

    Country of ref document: ES

    Kind code of ref document: T3

    PLBE No opposition filed within time limit

    Free format text: ORIGINAL CODE: 0009261

    STAA Information on the status of an ep patent application or granted ep patent

    Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

    ET Fr: translation filed
    26N No opposition filed

    Effective date: 20040305

    BERE Be: lapsed

    Owner name: HERMANN *KIRCHNER G.M.B.H. & CO. K.G.

    Effective date: 20040228

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: PT

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20040831

    REG Reference to a national code

    Ref country code: DK

    Ref legal event code: EBP

    REG Reference to a national code

    Ref country code: CH

    Ref legal event code: PL

    REG Reference to a national code

    Ref country code: CH

    Ref legal event code: NV

    Representative=s name: BRAUN & PARTNER PATENT-, MARKEN-, RECHTSANWAELTE

    Ref country code: CH

    Ref legal event code: AEN

    Free format text: DAS PATENT IST AUFGRUND DES WEITERBEHANDLUNGSANTRAGS VOM 04.11.2004 REAKTIVIERT WORDEN.

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: GR

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20030604

    REG Reference to a national code

    Ref country code: FR

    Ref legal event code: PLFP

    Year of fee payment: 18

    REG Reference to a national code

    Ref country code: FR

    Ref legal event code: PLFP

    Year of fee payment: 19

    REG Reference to a national code

    Ref country code: FR

    Ref legal event code: PLFP

    Year of fee payment: 20

    PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

    Ref country code: NL

    Payment date: 20180221

    Year of fee payment: 20

    PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

    Ref country code: GB

    Payment date: 20180221

    Year of fee payment: 20

    Ref country code: DE

    Payment date: 20180221

    Year of fee payment: 20

    Ref country code: ES

    Payment date: 20180322

    Year of fee payment: 20

    Ref country code: CH

    Payment date: 20180221

    Year of fee payment: 20

    Ref country code: FI

    Payment date: 20180216

    Year of fee payment: 20

    REG Reference to a national code

    Ref country code: CH

    Ref legal event code: PCAR

    Free format text: NEW ADDRESS: HOLEESTRASSE 87, 4054 BASEL (CH)

    PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

    Ref country code: FR

    Payment date: 20180226

    Year of fee payment: 20

    Ref country code: SE

    Payment date: 20180222

    Year of fee payment: 20

    Ref country code: IT

    Payment date: 20180221

    Year of fee payment: 20

    Ref country code: AT

    Payment date: 20180220

    Year of fee payment: 20

    REG Reference to a national code

    Ref country code: DE

    Ref legal event code: R071

    Ref document number: 59905833

    Country of ref document: DE

    Ref country code: NL

    Ref legal event code: MK

    Effective date: 20190219

    REG Reference to a national code

    Ref country code: CH

    Ref legal event code: PL

    REG Reference to a national code

    Ref country code: GB

    Ref legal event code: PE20

    Expiry date: 20190219

    REG Reference to a national code

    Ref country code: SE

    Ref legal event code: EUG

    REG Reference to a national code

    Ref country code: AT

    Ref legal event code: MK07

    Ref document number: 242359

    Country of ref document: AT

    Kind code of ref document: T

    Effective date: 20190220

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: GB

    Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION

    Effective date: 20190219

    REG Reference to a national code

    Ref country code: ES

    Ref legal event code: FD2A

    Effective date: 20200723

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: ES

    Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION

    Effective date: 20190221