CN221168757U - Civil engineering construction support - Google Patents

Civil engineering construction support Download PDF

Info

Publication number
CN221168757U
CN221168757U CN202323164276.7U CN202323164276U CN221168757U CN 221168757 U CN221168757 U CN 221168757U CN 202323164276 U CN202323164276 U CN 202323164276U CN 221168757 U CN221168757 U CN 221168757U
Authority
CN
China
Prior art keywords
cross base
shaped clamp
civil engineering
groups
construction support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202323164276.7U
Other languages
Chinese (zh)
Inventor
赵伟男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin Deyuan Water Conservancy Engineering Co ltd
Original Assignee
Jilin Deyuan Water Conservancy Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin Deyuan Water Conservancy Engineering Co ltd filed Critical Jilin Deyuan Water Conservancy Engineering Co ltd
Priority to CN202323164276.7U priority Critical patent/CN221168757U/en
Application granted granted Critical
Publication of CN221168757U publication Critical patent/CN221168757U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The utility model relates to a civil engineering building construction support, which belongs to the technical field of material supports, wherein a sleeve is vertically welded above the center of a cross base, the outer side of the sleeve is fixedly connected with the cross base through four groups of mutually crossed supporting columns, the top of the sleeve is provided with a rotating nut with internal threads, the rotating nut is sleeved on the top of the sleeve and can freely rotate, a screw rod is arranged in the rotating nut, the height of the screw rod can be lifted or lowered through the rotating nut, a flange plate is welded at the top of the screw rod, a left V-shaped clamp and a right V-shaped clamp are welded above the flange plate at 120 degrees, and the left V-shaped clamp and the right V-shaped clamp are 120 degrees, and four groups of pulleys are movably arranged in the left V-shaped clamp and the right V-shaped clamp through bolts and are used for intensively placing a plurality of steel pipes or bars and strip-shaped raw materials; four groups of moving wheels are fixedly arranged at the bottom of the cross base through threads; after the movable wheels are disassembled, the movable wheels can be intensively placed in the trolley with the baffle, and a basket is fixedly arranged on the inner side wall of the trolley and used for intensively placing the movable wheels.

Description

Civil engineering construction support
Technical Field
The utility model relates to a civil engineering building construction support, and belongs to the technical field of material supports.
Background
Civil engineering is a generic term for science and technology in building various types of earth engineering facilities. It refers to both the materials and equipment used and the technical activities of surveying, designing, constructing, maintaining, repairing, etc. performed, as well as the objects of engineering construction. I.e., built on the ground or underground, land, various engineering facilities directly or indirectly serving human life, production, military, scientific research, such as houses, roads, railways, pipes, tunnels, bridges, canals, dams, ports, power stations, airports, ocean platforms, water supply and drainage, protection engineering, etc. Civil engineering refers to various technical works such as investigation, planning, design, construction, installation and maintenance and the like and finished engineering entities thereof for building, constructing or expanding various engineering besides house construction.
The purpose of civil engineering is to create well functioning and comfortable and attractive spaces and passages for human production or living. It is both a physical and mental requirement. Along with the development of society, engineering structures are increasingly large and complicated, super high-rise buildings, super large bridges, huge dams and complex subway systems are continuously emerging, so that the living demands of people are met, and meanwhile, the engineering structures are also evolved into the symbolism of social strength.
The fundamental problem that civil engineering needs to solve is engineering safety, enabling the structure to resist various natural or artificial forces. Any engineering structure bears the self weight and the effect of using load and wind force, and the humidity change can exert force on the civil engineering structure. In seismic areas, civil engineering structures should also be considered to resist the effects of earthquakes. In addition, the effects of explosions, vibrations, etc. on civil engineering cannot be neglected.
The Chinese patent discloses a cable construction support, the application publication number CN113839336A, which is structurally described as comprising a cable fixing component, a circumferential supporting component and a middle supporting component; the cable fixing assembly comprises a body, a connecting part arranged on the body and an accommodating through hole penetrating through the body along a first direction; the circumferential support assembly comprises three side support pieces, wherein the first ends of the three side support pieces are connected to the connecting part, the first ends of the three side support pieces are arranged at equal angle intervals along the circumferential direction, the three side support pieces incline in a second direction, the second ends of the three side support pieces, which are far away from the cable fixing assembly, are distributed in a triangular shape and are supported on the support surface, and the second direction is perpendicular to the first direction; the middle support assembly comprises a middle support piece fixed on the connecting part and arranged along the second direction, and the middle support piece is connected with each side support piece through auxiliary support pieces. When slight shaking along the radial direction of the cable occurs in the horizontal plane in the construction process, the support is more reliable.
The cable construction support has the defects that the cable construction support cannot freely and flexibly lift and move the position, the inner diameter structural design of the cable fixing assembly is small, and only a limited number of cables can be restrained; the single bracket is inconvenient to use and can not be used for restraining and placing the strip-shaped raw materials.
Disclosure of Invention
In order to solve the problems existing in the prior art, the utility model aims to provide a civil engineering building construction support, wherein a sleeve is vertically welded above the center of a cross base, the outer side of the sleeve is fixedly connected with the cross base through four groups of mutually crossed support columns, the top of the sleeve is provided with a rotating nut with internal threads, the rotating nut is sleeved on the top of the sleeve and can freely rotate, a screw rod is arranged in the rotating nut, the height of the screw rod can be lifted or lowered through the rotating nut, a flange plate is welded at the top of the screw rod, a left V-shaped clamp and a right V-shaped clamp are welded at 120 degrees above the flange plate, the left V-shaped clamp and the right V-shaped clamp are 120 degrees, and four groups of pulleys are movably arranged in the left V-shaped clamp and the right V-shaped clamp through bolts and are used for intensively placing a plurality of steel pipes or bars and strip-shaped raw materials; the moving position is convenient; four groups of moving wheels are fixedly arranged at the bottom of the cross base through threads; the centralized transportation is convenient; after the movable wheels at the bottom of the cross base are disassembled, the movable wheels can be intensively placed in the trolley with the baffle, and the basket is fixedly arranged on the inner side wall of the trolley and used for intensively placing the movable wheels.
In order to achieve the above purpose, the utility model provides the following technical scheme
The utility model provides a civil engineering building construction support which characterized in that: including cross base 7, cross base 7 center top perpendicular welding have the sleeve pipe, the sheathed tube outside is through four sets of intercrossing's support column 6 and cross base 7 fixed connection, sheathed tube top is equipped with one and takes internal screw thread swivel nut 5, swivel nut 5 cup joints at sheathed tube top can the free rotation, is equipped with screw rod 4 in swivel nut 5, screw rod 4's top welding has the ring flange, the top of ring flange has left V-arrangement clamp 1 and right V-arrangement clamp 3 with 120 degrees welding, left V-arrangement clamp 1 and right V-arrangement clamp 3 are 120 degrees, both are inside to be equipped with four sets of pulleys 2 through the bolt activity.
The left half part of the left V-shaped clamp 1 and the right V-shaped clamp 3 is fixedly provided with two groups of pulleys 2 through bolts, and the right half part is fixedly provided with two groups of pulleys 2 through bolts.
The outer side of the rotary nut 5 is vertically welded with a hand grip.
The support column 6 and the cross base 7 form an included angle of 60 degrees.
The bottom of the cross base 7 is fixedly provided with four groups of moving wheels 8 through threads.
The utility model has the beneficial effects that
1. The height can be flexibly adjusted; the center top perpendicular welding of cross base 7 has the sleeve pipe, the sheathed tube outside is through four sets of intercrossing's support column 6 and cross base 7 fixed connection, sheathed tube top is equipped with one and takes internal screw thread swivel nut 5, swivel nut 5 cup joints at sheathed tube top can free rotation, be equipped with screw rod 4 in swivel nut 5, can promote or descend the height of screw rod 4 through swivel nut 5, the top welding of screw rod 4 has the ring flange, the top of ring flange has left V-arrangement clamp 1 and right V-arrangement clamp 3 with 120 degrees welding, left V-arrangement clamp 1 and right V-arrangement clamp 3 are 120 degrees, both inside is equipped with four sets of pulleys 2 through the bolt activity, be used for concentrating and place many steel pipes or bar and bar raw and material.
2. The moving position is convenient; four groups of moving wheels 8 are fixedly arranged at the bottom of the cross base 7 through threads.
3. The centralized transportation is convenient; after the movable wheels 8 at the bottom of the cross base 7 are disassembled, the movable wheels can be intensively placed in the trolley 9 with the baffle 10, and a basket 11 is fixedly arranged on the inner side wall of the trolley 9 and used for intensively placing the movable wheels 8.
Drawings
Fig. 1 is a front view of the present utility model.
Fig. 2 is a perspective view of the present utility model.
Fig. 3 is a perspective view of the centralized transportation of the present utility model.
In the figure: left V-shaped clamp 1, pulley 2, right V-shaped clamp 3, screw rod 4, swivel nut 5, support column 6, cross base 7, remove round 8, dolly 9, baffle 10, rim 11.
Description of the embodiments
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
As shown in the attached drawings 1-3, the civil engineering construction support comprises a cross base 7, wherein a sleeve is vertically welded above the center of the cross base 7, the outer side of the sleeve is fixedly connected with the cross base 7 through four groups of support columns 6 which are mutually intersected, the top of the sleeve is provided with a rotating nut 5 with internal threads, the rotating nut 5 is sleeved on the top of the sleeve and can freely rotate, a screw 4 is arranged in the rotating nut 5, a flange is welded on the top of the screw 4, a left V-shaped clamp 1 and a right V-shaped clamp 3 are welded above the flange at 120 degrees, and the left V-shaped clamp 1 and the right V-shaped clamp 3 are 120 degrees and are movably provided with four groups of pulleys 2 through bolts.
The left half part of the left V-shaped clamp 1 and the right V-shaped clamp 3 is fixedly provided with two groups of pulleys 2 through bolts, and the right half part is fixedly provided with two groups of pulleys 2 through bolts.
The outer side of the rotary nut 5 is vertically welded with a hand grip.
The support column 6 and the cross base 7 form an included angle of 60 degrees.
The bottom of the cross base 7 is fixedly provided with four groups of moving wheels 8 through threads.
The application method of the civil engineering building construction support comprises the following steps:
The center top perpendicular welding of cross base 7 has the sleeve pipe, the sheathed tube outside is through four sets of intercrossing's support column 6 and cross base 7 fixed connection, sheathed tube top is equipped with one and takes internal screw thread swivel nut 5, swivel nut 5 cup joints at sheathed tube top can free rotation, be equipped with screw rod 4 in swivel nut 5, can promote or descend the height of screw rod 4 through swivel nut 5, the top welding of screw rod 4 has the ring flange, the top of ring flange has left V-arrangement clamp 1 and right V-arrangement clamp 3 with 120 degrees welding, left V-arrangement clamp 1 and right V-arrangement clamp 3 are 120 degrees, both inside is equipped with four sets of pulleys 2 through the bolt activity, be used for placing steel pipe or bar.
The embodiments of the utility model have been presented for purposes of illustration and description, and are not intended to be exhaustive or limited to the utility model in the form disclosed. Many modifications and variations will be apparent to those of ordinary skill in the art. The embodiments were chosen and described in order to best explain the principles of the utility model and the practical application, and to enable others of ordinary skill in the art to understand the utility model for various embodiments with various modifications as are suited to the particular use contemplated.

Claims (5)

1. The utility model provides a civil engineering building construction support which characterized in that: including cross base (7), the center top perpendicular welding of cross base (7) have the sleeve pipe, telescopic outside is through four sets of intercrossing's support column (6) and cross base (7) fixed connection, telescopic top is equipped with one and takes internal screw thread swivel nut (5), swivel nut (5) cup joints at telescopic top can free rotation, be equipped with screw rod (4) in swivel nut (5), the top welding of screw rod (4) has the ring flange, the top of ring flange has left V-arrangement clamp (1) and right V-arrangement clamp (3) with 120 degrees welding, left V-arrangement clamp (1) and right V-arrangement clamp (3) are 120 degrees, both inside are equipped with four sets of pulleys (2) through the bolt activity.
2. A civil engineering building construction support according to claim 1, wherein: the left half part of the left V-shaped clamp (1) and the right V-shaped clamp (3) is fixedly provided with two groups of pulleys (2) through bolts, and the right half part is fixedly provided with two groups of pulleys (2) through bolts.
3. A civil engineering building construction support according to claim 1, wherein: the outer side of the rotary nut (5) is vertically welded with a hand grab handle.
4. A civil engineering building construction support according to claim 1, wherein: the supporting column (6) and the cross base (7) form an included angle of 60 degrees.
5. A civil engineering building construction support according to claim 1, wherein: the bottom of the cross base (7) is fixedly provided with four groups of moving wheels (8) through threads.
CN202323164276.7U 2023-11-23 2023-11-23 Civil engineering construction support Active CN221168757U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202323164276.7U CN221168757U (en) 2023-11-23 2023-11-23 Civil engineering construction support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202323164276.7U CN221168757U (en) 2023-11-23 2023-11-23 Civil engineering construction support

Publications (1)

Publication Number Publication Date
CN221168757U true CN221168757U (en) 2024-06-18

Family

ID=91464250

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202323164276.7U Active CN221168757U (en) 2023-11-23 2023-11-23 Civil engineering construction support

Country Status (1)

Country Link
CN (1) CN221168757U (en)

Similar Documents

Publication Publication Date Title
CN101892671B (en) Pile anchor rod foundation structure
CN102797643B (en) A kind of wind power generation tower device
CN104831939A (en) Bolt ball welding ball mixed node large span cantilever grid structure construction method
CN206513037U (en) A kind of precast concrete wall panel position regulator
CN113494131A (en) Two-type manual butt joint steel framework
US20210172143A1 (en) Portable mechanically assembled ground fixation stake device
CN211873950U (en) Combined supporting pile for civil engineering
CN221168757U (en) Civil engineering construction support
CN213326235U (en) Stable and anti-shaking lifting device for building construction
CN213572924U (en) Novel overhanging bearing scaffold
CN212689511U (en) Civil engineering construction support
CN203403699U (en) High-rise building steel structure wind and light electricity generating tower
CN107476560B (en) Wind power tower construction platform and method
CN107816209A (en) The large-scale Roof Truss construction technology of installation is lifted across outer both sides
CN213828925U (en) Civil engineering pipe fitting rack
CN204385762U (en) A kind of Rock Bolt Foundation structure
CN204551731U (en) A kind of full steel structure building
CN213115585U (en) Stable form bearing structure that building engineering used
CN210454874U (en) Pipe fitting placer is used in civil engineering construction
CN203531413U (en) Auxiliary structure hoisting whole steel structure wire frame
CN211201250U (en) Strutting arrangement for civil engineering
CN209742483U (en) foundation ditch engineering safety device
CN208105828U (en) A kind of civil construction operation frame
CN213449776U (en) Construction engineering construction is with fence pole easy to assemble
CN206320408U (en) A kind of bag pillar suspension centre in nuclear power GB gallery lifting pipelines

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant