CN220539258U - Positioning and reinforcing device for embedded pipeline - Google Patents

Positioning and reinforcing device for embedded pipeline Download PDF

Info

Publication number
CN220539258U
CN220539258U CN202321792323.XU CN202321792323U CN220539258U CN 220539258 U CN220539258 U CN 220539258U CN 202321792323 U CN202321792323 U CN 202321792323U CN 220539258 U CN220539258 U CN 220539258U
Authority
CN
China
Prior art keywords
pipeline
positioning
wall
rod
reinforcing device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321792323.XU
Other languages
Chinese (zh)
Inventor
刘恒志
魏帆帆
张小兵
郑大运
裴浩然
张铖坤
余子伦
刘英豪
尹先鸿
杨峥
张崇晨
周圣轩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
7th Engineering Co Ltd of MBEC
Original Assignee
7th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 7th Engineering Co Ltd of MBEC filed Critical 7th Engineering Co Ltd of MBEC
Priority to CN202321792323.XU priority Critical patent/CN220539258U/en
Application granted granted Critical
Publication of CN220539258U publication Critical patent/CN220539258U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a positioning and reinforcing device for a pre-buried pipeline, and relates to the field of building construction. The positioning and reinforcing device comprises a positioning rod; the adjusting rod is arranged at the top of the positioning rod; a level measurer mounted on the adjustment lever; at least one pipeline inner wall supporting device is movably arranged on the positioning rod. The device can effectively strengthen the pipeline, reduce the influence of external acting force on the position and the perpendicularity of the pipeline in the concrete pouring process, and therefore improve the construction quality of pipeline pre-burying work; meanwhile, the structural concrete does not need to be re-chiseled or secondarily perforated, and the like, so that the construction efficiency of pipeline pre-burying work is improved.

Description

Positioning and reinforcing device for embedded pipeline
Technical Field
The utility model relates to the field of building construction, in particular to a positioning and reinforcing device for a pre-buried pipeline.
Background
The field of building and municipal engineering often has the problem that pipelines for electromechanical installation, line laying and other constructions are required to be pre-buried on cast-in-situ slabs. According to actual construction and field investigation, most of the reinforcement to the embedded pipeline is to adopt to weld the reinforcing bar at the bottom of the pipeline to clamp or tie the iron wire, and from the standpoint of comprehensive practical effect, the reinforcement mode is extremely easy to generate larger deviation on the position, the perpendicularity and the like of the pipeline in the concrete pouring process, cannot meet the later installation requirement, and leads to the need of re-chiseling or secondary perforating and other treatments on the structural concrete, thereby leading to time and labor consumption in construction, and the quality requirement is difficult to guarantee.
Disclosure of Invention
Aiming at the defects in the prior art, the utility model solves the technical problems as follows: how to improve the construction efficiency and the construction quality of the pipeline embedding work.
In order to achieve the above object, the positioning and reinforcing device for embedded pipelines provided by the utility model comprises:
a positioning rod;
the adjusting rod is arranged at the top of the positioning rod;
a level measurer mounted on the adjustment lever;
at least one pipeline inner wall supporting device is movably arranged on the positioning rod.
On the basis of the technology, the positioning rod is a threaded rod, and the lower end of the threaded rod is a conical spiral and is used for drilling into the template.
On the basis of the technology, the movable pipeline outer wall fixing device is arranged on the positioning rod and is positioned on the upper portion of the pipeline inner wall supporting device.
On the basis of the technology, the pipeline outer wall fixing device comprises a central adjusting nut, and the pipeline outer wall fixing device is connected with the positioning rod in a screwing mode through the central adjusting nut.
On the basis of the technology, the outer wall of the central adjusting nut is provided with at least two first connecting rods, one ends of the first connecting rods are connected with the central adjusting nut, and the other ends of the first connecting rods are connected with fixing clamping ends through telescopic springs.
On the basis of the technology, the shape of the fixing clamp end is L-shaped, the fixing clamp end is used for clamping the outer wall of the pipeline, and a rubber pad is arranged on one side of the fixing clamp end, which is in contact with the pipeline.
On the basis of the technology, the pipeline inner wall supporting device comprises an inner support adjusting nut, and the pipeline inner wall supporting device is connected with the positioning rod through screwing of the inner support adjusting nut.
On the basis of the technology, the outer wall of the inner support adjusting nut is provided with at least two second connecting rods, and the second connecting rods are internally inserted with supporting rods which are used for supporting the inner wall of the pipeline.
On the basis of the technology, the supporting rod adopts an adjusting bolt.
On the basis of the technology, the level measurer adopts quasi-bubble.
Compared with the prior art, the utility model has the advantages that:
according to the utility model, the locating rod passes through the pipeline and is inserted into the template at the bottom of the pipeline, the locating rod can be adjusted to be in a basically vertical state through the adjusting rod and the level measurer which are arranged at the top of the locating rod, and the pipeline inner wall supporting device is moved into the pipeline and supports the inner wall of the pipeline. Compared with the prior art that the steel bar is clamped or iron wire tied through welding, the positioning and reinforcing device is fixed with the template, and the pipeline inner wall supporting device on the positioning and reinforcing device is propped against the inner wall of the pipeline, so that the pipeline and the positioning and reinforcing device are fixed, and when in pouring construction, concrete has flowing force on the pipeline, so that the pipeline is displaced or inclined, but the positioning and reinforcing device can exert resistance on the pipeline, thus the pipeline can be effectively reinforced, the influence of external acting force on the position and the perpendicularity of the pipeline in the concrete pouring process is reduced, and the construction quality of the pipeline pre-burying work is improved; meanwhile, the structural concrete does not need to be re-chiseled or secondarily perforated, and the like, so that the construction efficiency of pipeline pre-burying work is improved.
Drawings
FIG. 1 is a schematic structural view of a pre-buried pipeline positioning and reinforcing device according to an embodiment of the present utility model;
FIG. 2 is a schematic view of a positioning rod and an adjusting rod according to an embodiment of the present utility model;
FIG. 3 is a schematic view of a pipe outer wall fixing device according to an embodiment of the present utility model;
fig. 4 is a schematic structural view of a supporting device for an inner wall of a pipeline according to an embodiment of the utility model.
In the figure: the device comprises a 1-positioning rod, a 101-threaded rod, a 102-conical screw, a 2-adjusting rod, a 3-level measurer, a 4-pipeline outer wall fixing device, a 401-center adjusting nut, a 402-first connecting rod, a 403-telescopic spring, a 404-fixing clamp end, a 5-pipeline inner wall supporting device, a 501-inner supporting adjusting nut, a 502-second connecting rod, a 503-supporting rod, a 6-pipeline and a 7-template.
Detailed Description
Embodiments of the present utility model are described in further detail below with reference to the accompanying drawings.
The pre-buried pipeline positioning and reinforcing device in the embodiment of the utility model, as shown in fig. 1, comprises:
a positioning rod 1;
an adjusting lever 2 provided on the top of the positioning lever 1;
a level measurer 3 mounted on the adjustment lever 2;
at least one pipe inner wall supporting means 5, which is movably arranged on the positioning rod 1.
It can be seen that the present utility model can adjust the positioning rod 1 to a substantially vertical state by inserting the positioning rod 1 through the pipe 6 and into the form 7 at the bottom of the pipe, adjusting the rod 2 and the level gauge 3 installed at the top of the positioning rod 1, moving the pipe inner wall supporting means 5 to the inside of the pipe 6, and supporting the inner wall of the pipe 6. Compared with the prior art that the steel bars are clamped or tied through welding, the positioning and reinforcing device is fixed with the template, and the pipeline inner wall supporting device 5 on the positioning and reinforcing device is propped against the inner wall of the pipeline 6, so that the pipeline 6 and the positioning and reinforcing device are fixed, and when in pouring construction, the concrete has flowing force on the pipeline 6, so that the pipeline 6 is displaced or inclined, but the positioning and reinforcing device can exert a resistance force on the pipeline, thus the pipeline can be effectively reinforced, the influence of external acting force on the position and the perpendicularity of the pipeline in the concrete pouring process is reduced, and the construction quality of the pipeline pre-burying work is improved; meanwhile, the structural concrete does not need to be re-chiseled or secondarily perforated, and the like, so that the construction efficiency of pipeline pre-burying work is improved.
Preferably, as seen in fig. 2, the positioning rod 1 is a threaded rod 101, and the lower end of the threaded rod 101 is a conical screw 102 for drilling into the form 7.
The design has the advantages that: the locating rod 1 of the design can directly drill into the template 7 through rotation, and the construction efficiency of pipeline fixation can be improved.
Preferably, as shown in fig. 1, the positioning rod 1 is provided with a movable pipe outer wall fixing device 4, and the pipe outer wall fixing device 4 is located at the upper part of the pipe inner wall supporting device 5.
The design has the advantages that: the pipe outer wall fixing device 4 can be moved on the positioning rod 1 until the outer wall of the pipe 6 is clamped, so that the pipe 6 is limited to displace in the vertical direction, and the use of the pipe inner wall supporting device 5 is not affected by the design.
Preferably, referring to fig. 3, the pipe outer wall fixing device 4 includes a center adjustment nut 401, and the pipe outer wall fixing device 4 is screwed with the positioning rod 1 through the center adjustment nut 401.
The design has the advantages that: the pipeline outer wall fixing device 4 can be moved on the positioning rod 1 by rotating the pipeline outer wall fixing device 4, the structure is simple to operate, other tools are not needed, and the pipeline outer wall fixing device 4 is in a static state on the positioning rod 1 under the condition that the pipeline outer wall fixing device 4 is not touched.
Preferably, referring to fig. 3, at least two first connecting rods 402 are provided on the outer wall of the central adjusting nut 401, one end of each first connecting rod 402 is connected with the central adjusting nut 401, and the other end is connected with a fixing clip end 404 through a telescopic spring 403.
The design has the advantages that: the size of the pre-buried pipeline 6 may be various, so that the pipeline outer wall fixing device 4 designed for meeting most construction requirements has a telescopic function, and thus the outer wall of the pipeline 6 is effectively fixed.
Preferably, the fixing clip end 404 is L-shaped and is used for clamping the outer wall of the pipeline 6, and a rubber pad is arranged on the side of the fixing clip end 404 contacted with the pipeline.
The design has the advantages that: the shape can enable the fixing clip end 404 to hook the outer wall, so that falling is avoided, and the rubber pad arranged between the fixing clip end 404 and the pipeline 6 can increase the friction force between the fixing clip end 404 and the pipeline 6, and damage to the pipeline 6 caused by overlarge force applied by the fixing clip end 404 can be avoided.
Preferably, referring to fig. 4, the pipe inner wall supporting device 5 includes an inner support adjusting nut 501, and the pipe inner wall supporting device 5 is screwed with the positioning rod 1 through the inner support adjusting nut 501.
The design has the advantages that: the pipeline inner wall fixing device 5 can be moved on the positioning rod 1 by rotating the pipeline inner wall fixing device 5, the structure is simple to operate, other tools are not needed, and the inner wall fixing device 5 is in a static state on the positioning rod 1 under the condition that the pipeline inner wall fixing device 5 is not touched.
Preferably, as shown in fig. 4, at least two second connection rods 502 are provided on the outer wall of the inner support adjusting nut 501, and a support rod 503 for supporting the inner wall of the pipe 6 is inserted into the second connection rods 502.
The design has the advantages that: because the inner support adjusting nut 501 supports the inner wall of the pipeline 6, at least two second connecting rods 502 are provided to ensure the uniformity and effectiveness of the inner wall supporting force.
Preferably, the support rod 503 is an adjusting bolt.
The design has the advantages that: in the installation process of the positioning and reinforcing device, the supporting rod 503 needs to be adjusted to be propped against the inner wall of the pipeline 6, the supporting rod 503 is an adjusting bolt, and a constructor can directly screw the adjusting bolt by hand, so that the supporting rod 503 and the pipeline 6 prop against each other.
Preferably, the level gauge 3 is a level bubble.
The design has the advantages that: the positioning and reinforcing device is in a vertical state or not, and the position of the positioning and reinforcing device can be adjusted while observing the level bubble.
The utility model is not limited to the above-mentioned best mode, any person can obtain other various products under the teaching of the utility model, but any change in shape or structure is within the scope of protection of the utility model, and all the technical schemes are the same or similar to the utility model.

Claims (10)

1. The utility model provides a pre-buried pipeline location reinforcing apparatus which characterized in that, it includes:
a positioning rod (1);
the adjusting rod (2) is arranged at the top of the positioning rod (1);
a level measuring device (3) mounted on the adjusting lever (2);
at least one pipe inner wall supporting device (5) which is movably arranged on the positioning rod (1).
2. The pre-buried pipeline positioning and reinforcing device according to claim 1, wherein: the locating rod (1) is a threaded rod (101), and the lower end of the threaded rod (101) is a conical screw (102) which is used for drilling into the template (7).
3. The pre-buried pipeline positioning and reinforcing device according to claim 1, wherein: the movable pipeline outer wall fixing device (4) is arranged on the positioning rod (1), and the pipeline outer wall fixing device (4) is located on the upper portion of the pipeline inner wall supporting device (5).
4. A pre-buried pipeline positioning and reinforcing device as claimed in claim 3, wherein: the pipeline outer wall fixing device (4) comprises a central adjusting nut (401), and the pipeline outer wall fixing device (4) is connected with the positioning rod (1) in a screwing mode through the central adjusting nut (401).
5. The embedded pipeline positioning and reinforcing device as set forth in claim 4, wherein: the outer wall of the center adjusting nut (401) is provided with at least two first connecting rods (402), one ends of the first connecting rods (402) are connected with the center adjusting nut (401), and the other ends of the first connecting rods are connected with fixing clamping ends (404) through telescopic springs (403).
6. The embedded pipeline positioning and reinforcing device as set forth in claim 5, wherein: the shape of the fixing clamp end (404) is L-shaped, the fixing clamp end is used for clamping the outer wall of the pipeline (6), and a rubber pad is arranged on one side of the fixing clamp end (404) contacted with the pipeline.
7. The pre-buried pipeline positioning and reinforcing device according to claim 2, wherein: the pipeline inner wall supporting device (5) comprises an inner support adjusting nut (501), and the pipeline inner wall supporting device (5) is connected with the positioning rod (1) in a screwing mode through the inner support adjusting nut (501).
8. The embedded pipeline positioning and reinforcing device as set forth in claim 7, wherein: the outer wall of the inner support adjusting nut (501) is provided with at least two second connecting rods (502), and supporting rods (503) are inserted into the second connecting rods (502) and used for supporting the inner wall of the pipeline (6).
9. The pre-buried pipeline positioning and reinforcing device according to claim 8, wherein: the supporting rod (503) is an adjusting bolt.
10. The pre-buried pipeline positioning and reinforcing device according to claim 1, wherein: the level measurer (3) adopts quasi-horizontal bubbles.
CN202321792323.XU 2023-07-07 2023-07-07 Positioning and reinforcing device for embedded pipeline Active CN220539258U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321792323.XU CN220539258U (en) 2023-07-07 2023-07-07 Positioning and reinforcing device for embedded pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321792323.XU CN220539258U (en) 2023-07-07 2023-07-07 Positioning and reinforcing device for embedded pipeline

Publications (1)

Publication Number Publication Date
CN220539258U true CN220539258U (en) 2024-02-27

Family

ID=89973134

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321792323.XU Active CN220539258U (en) 2023-07-07 2023-07-07 Positioning and reinforcing device for embedded pipeline

Country Status (1)

Country Link
CN (1) CN220539258U (en)

Similar Documents

Publication Publication Date Title
CN210216479U (en) Positioning device for pre-embedding large foundation bolt group
CN220539258U (en) Positioning and reinforcing device for embedded pipeline
CN204201279U (en) Pipeline suspension rod between a kind of rack and steel grating
CN211344229U (en) Sliding support bottom plate structure with freely adjustable height
CN112816205A (en) Pipeline gallows detection device
CN215985497U (en) Anchor rod tensile property detection device
CN214995260U (en) Positioning steel bar position controller
CN214615043U (en) Prefabricated component reserved steel bar positioning and correcting device
CN205343431U (en) Prefabricated wall body grout sleeve strip solid matter exposes accurate positioning die of reinforcing bar
CN210289693U (en) Open flow pipeline support frame
CN202769052U (en) Pipeline movable cradle
CN210239143U (en) Reserved hole sleeve fixing part for laminated floor slab
CN216690102U (en) Construction steel bar location structure
CN208073012U (en) A kind of foundation bolt location centralizing device
CN219159729U (en) Height-adjustable assembled support and hanger embedded with fixing device
CN113385795B (en) Positioning device for cutting elliptical groove of cable guide pipe
CN211231869U (en) Water supply and drainage pipeline fixing device
CN211949680U (en) Auxiliary device for ensuring accurate pre-embedding of beam-penetrating sleeve
CN219864360U (en) Temporary supporting device for non-embedded large-scale landscape steel structural column
CN221219839U (en) PC wallboard supports fixing device
CN214613643U (en) Device for positioning and adjusting prefabricated pier stud of bridge
CN215253986U (en) Concrete pouring construction appurtenance
CN219547587U (en) Prestress steel bundle pipeline positioning device
CN219606247U (en) Adjustable stand pipe verticality support
CN218493144U (en) Steel construction stand pre-buried clamping screw positioner

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant