CN219851971U - Be used for refrigerated blast apparatus of steel forging - Google Patents

Be used for refrigerated blast apparatus of steel forging Download PDF

Info

Publication number
CN219851971U
CN219851971U CN202321351044.XU CN202321351044U CN219851971U CN 219851971 U CN219851971 U CN 219851971U CN 202321351044 U CN202321351044 U CN 202321351044U CN 219851971 U CN219851971 U CN 219851971U
Authority
CN
China
Prior art keywords
cooling
cooling frame
frame
fixed
clamping plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321351044.XU
Other languages
Chinese (zh)
Inventor
熊巧云
曹小曼
张星玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daye Ziqian Metal Products Co ltd
Original Assignee
Daye Ziqian Metal Products Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daye Ziqian Metal Products Co ltd filed Critical Daye Ziqian Metal Products Co ltd
Priority to CN202321351044.XU priority Critical patent/CN219851971U/en
Application granted granted Critical
Publication of CN219851971U publication Critical patent/CN219851971U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/10Greenhouse gas [GHG] capture, material saving, heat recovery or other energy efficient measures, e.g. motor control, characterised by manufacturing processes, e.g. for rolling metal or metal working

Landscapes

  • Forging (AREA)

Abstract

The utility model provides a blowing device for cooling steel forgings, which comprises a water tank, wherein a cooling table is fixed on the upper side of the water tank, a fan, a first cooling frame and a second cooling frame are fixed on the upper side of the cooling table, first water pipes are fixed on the upper side and the lower side in the first cooling frame, second water pipes are fixed on the bottom in the second cooling frame, the first water pipes and the second water pipes are communicated with the water tank, a first clamping plate and a second clamping plate are rotationally matched with the second cooling frame, a first dust screen is slidingly matched with the upper side of the second cooling frame, and second dust screens are fixed on the two sides of the second cooling frame. According to the utility model, the first water pipe is arranged in the first cooling frame, the second water pipe is arranged in the second cooling frame, the fan is arranged on the cooling table, and the cooling is carried out in an air cooling and water cooling mode, so that the cooling speed is increased, and the first clamping plate and the second clamping plate are arranged in the second cooling frame, so that the steel forging can be clamped, and the steel forging is suspended, so that the cooling speed on the surface of the steel forging is increased.

Description

Be used for refrigerated blast apparatus of steel forging
Technical Field
The utility model relates to the technical field of steel forging processing, in particular to a blowing device for cooling a steel forging.
Background
After the steel forging is processed, the temperature of the steel forging can reach more than eight hundred degrees centigrade, therefore, cooling treatment is needed to be carried out on the steel forging, as in the patent with the publication number of CN212857583U, a stainless steel forging rapid cooling die is disclosed, ice cubes are filled in the inside of a workbench, a shaft of a motor rotates to drive a poking plate and a blade on a rotating shaft to rotate, the poking plate drives air in the workbench to flow, ice cubes are filled in the workbench, cold air is generated in the workbench, the die box is wrapped by the cold air from the lower side, the die is cooled from the lower side, the blade on the upper side rotates to drive air on the upper side of the workbench to flow, and the die is cooled from the upper side.
The device can accelerate the cooling speed of the steel forging, but the ice blocks belong to consumable products, so frequent replacement of the ice blocks is needed, the temperature of the ice blocks is quite troublesome, and the temperature of the ice blocks is generally lower, so that the difference between the heat taken away by melting ice blocks on the lower side of the steel forging and the heat taken away by blowing on the upper side of the steel forging is larger, and huge temperature difference is generated between the upper side and the lower side of the steel forging, so that the steel forging just produced deforms, and the production of the steel forging is unqualified
To this end, the utility model provides a blowing device for cooling steel forgings.
Disclosure of Invention
Aiming at the defects existing in the prior art, the utility model aims to provide a blowing device for cooling a steel forging piece, so as to solve the problems in the prior art, and the utility model radiates heat together in an air cooling and water cooling mode to accelerate the heat radiation speed; the steel forging can be clamped, so that the steel forging is suspended, the heat dissipation speed of the surface of the steel forging is increased, the steel forging is rotated, and the heat dissipation speed is increased; and the dust can be prevented from contacting with the steel forging at a higher temperature, so that the surface of the steel forging is prevented from burning.
In order to achieve the above object, the present utility model is realized by the following technical scheme: a blowing device for cooling steel forgings comprises a water tank, the water tank upside is fixed with the cooling platform, and the cooling platform upside is fixed with fan, first cooling frame and second cooling frame, and the upper and lower both sides in the first cooling frame all are fixed with first water pipe, and the bottom in the second cooling frame is fixed with the second water pipe, and first water pipe and second water pipe all are linked together with the water tank, and second cooling frame internal rotation cooperation has first splint and second splint, and second cooling frame upside sliding fit has first dust screen, and second cooling frame both sides all are fixed with the second dust screen.
Further, the fan is located at one side of the first cooling rack away from the second cooling rack.
Further, the second cooling frame is rotatably matched with a rotating shaft, and one end of the rotating shaft is fixedly connected with the first clamping plate.
Further, the second cooling frame is rotatably matched with an electric push rod, and the output end of the electric push rod is fixedly connected with the second clamping plate.
Further, the second cooling frame is rotatably matched with a rotary table, one side of the rotary table is fixedly connected with the electric push rod, and the other side of the rotary table is fixedly provided with a rotary handle.
Further, a sliding groove is formed in the upper side of the second cooling frame, and the sliding groove corresponds to the first dustproof net.
Further, a spray head is fixed on the upper side of the second cooling frame, and the spray head is communicated with the water tank.
The utility model has the beneficial effects that: the utility model relates to a blowing device for cooling a steel forging, which comprises a first cooling frame; a first water pipe; a second cooling rack; a second water pipe; a cooling table; a fan; a first clamping plate; a second clamping plate; a first dust screen; and a second dust screen.
Install first water pipe in first cooling frame, install the second water pipe in the second cooling frame, install the fan on the cooling bench, dispel the heat together through forced air cooling and water-cooling's mode, thereby accelerate heat dissipation rate, install first splint and second splint in the second cooling frame, can press from both sides the steel forging, make the steel forging unsettled, thereby accelerate the heat dissipation rate on steel forging surface, and can rotate the steel forging, accelerate heat dissipation rate, install first dust screen in the second cooling frame upside, install the second dust screen in second cooling frame both sides, prevent that the dust from contacting with the steel forging of higher temperature, thereby prevent steel forging surface combustion.
Drawings
FIG. 1 is a schematic view of the assembled perspective view of the whole blower for cooling steel forgings according to the present utility model;
FIG. 2 is a schematic diagram of an assembled perspective view of a water tank, a cooling table and a second cooling rack in a blower for cooling steel forgings according to the present utility model;
FIG. 3 is a schematic diagram of an assembled perspective view of a water tank, a cooling table and a first cooling rack in a blower for cooling steel forgings according to the present utility model;
FIG. 4 is a schematic diagram showing an assembled perspective structure of a second cooling rack and a turntable in a blowing device for cooling steel forgings;
in the figure: 1. a water tank; 2. a cooling table; 3. a fan; 4. a first water pipe; 5. a second water pipe; 6. a first cooling rack; 7. a second cooling rack; 8. a turntable; 9. a rotating handle; 10. a rotating shaft; 11. a first clamping plate; 12. a second clamping plate; 13. an electric push rod; 14. a chute; 15. a first dust screen; 16. a second dust screen; 17. a spray head.
Detailed Description
The utility model is further described in connection with the following detailed description, in order to make the technical means, the creation characteristics, the achievement of the purpose and the effect of the utility model easy to understand.
Referring to fig. 1 to 4, the present utility model provides a technical solution: the utility model provides a blast apparatus for steel forging cooling, includes water tank 1, water tank 1 upside is fixed with cooling platform 2, and cooling platform 2 upside is fixed with fan 3, first cooling frame 6 and second cooling frame 7, and the upper and lower both sides in the first cooling frame 6 all are fixed with first water pipe 4, and the bottom in the second cooling frame 7 is fixed with second water pipe 5, and first water pipe 4 and second water pipe 5 all are linked together with water tank 1, and the rotatory cooperation of second cooling frame 7 has first splint 11 and second splint 12, and the sideslip cooperation of second cooling frame 7 upside has first dust screen 15, and second cooling frame 7 both sides all are fixed with second dust screen 16.
In this embodiment, the fan 3 is located on one side of the first cooling rack 6 far away from the second cooling rack 7, and the fan 3 is used for blowing air, so that the air passes through the first cooling rack 6 and enters the second cooling rack 7, and at this time, the first water pipe 4 in the first cooling rack 6 can cool the air, so that the speed of blowing air to the steel forging can be increased.
The second cooling frame 7 is rotatably matched with a rotating shaft 10, and one end of the rotating shaft 10 is fixedly connected with a first clamping plate 11. The second cooling frame 7 is rotationally matched with the electric push rod 13, the output end of the electric push rod 13 is fixedly connected with the second clamping plate 12, the second cooling frame 7 is rotationally matched with the rotary table 8, one side of the rotary table 8 is fixedly connected with the electric push rod 13, the rotary table 8 is fixedly provided with the rotating handle 9 on the other side, when the steel forging is required to be cooled, the steel forging is placed between the first clamping plate 11 and the second clamping plate 12, then the electric push rod 13 is started, the electric push rod 13 drives the second clamping plate 12 to move, the second clamping plate 12 and the first clamping plate 11 clamp the steel forging, then the rotating handle 9 is rotated, the rotary table 8 can be rotated through the rotating handle 9, and accordingly the electric push rod 13, the rotary shaft 10 and the steel forging are driven to rotate, and accordingly the surface of the steel forging can be cooled more uniformly.
The chute 14 is arranged on the upper side of the second cooling frame 7, the chute 14 corresponds to the first dust screen 15, when the steel forgings need to be clamped, the first dust screen 15 can be scratched off, and after the steel forgings are clamped, the first dust screen 15 slides onto the second cooling frame 7 through the chute 14.
The spray head 17 is fixed on the upper side of the second cooling frame 7, the spray head 17 is communicated with the water tank 1, and for some steel forgings capable of spraying water, a switch of the spray head 17 can be turned on, so that the spray head 17 sprays water, and the cooling speed of the steel forgings is increased.
A water pump is installed in the water tank 1, and water is supplied to the first water pipe 4, the second water pipe 5 and the shower nozzle 17 by the water pump.
Specifically, when the steel forging needs to be cooled, the first dust screen 15 is taken down, then the steel forging is clamped through the first clamping plate 11 and the second clamping plate 12, the first dust screen 15 is installed, then the fan 3 and the water pump are started, so that water is supplied to the first water pipe 4 and the second water pipe 5, the first water pipe 4 cools air blown by the fan 3, the second water pipe 5 cools the air on the lower side of the steel forging, then the rotating handle 9 is rotated, so that the surface of the steel forging can be contacted with cold air, and the cooling speed is accelerated until the cooling is completed.
Furthermore, it should be understood that although the present disclosure describes embodiments, not every embodiment is provided with a separate embodiment, and that this description is provided for clarity only, and that the disclosure is not limited to the embodiments described in detail below, and that the embodiments described in the examples may be combined as appropriate to form other embodiments that will be apparent to those skilled in the art.

Claims (7)

1. A blowing device for cooling steel forgings comprises a water tank (1), and is characterized in that a cooling table (2) is fixed on the upper side of the water tank (1), a fan (3), a first cooling frame (6) and a second cooling frame (7) are fixed on the upper side and the lower side in the first cooling frame (6), a first water pipe (4) is fixed on the upper side and the lower side in the second cooling frame (7), a second water pipe (5) is fixed on the bottom in the second cooling frame (7), the first water pipe (4) and the second water pipe (5) are communicated with the water tank (1), a first clamping plate (11) and a second clamping plate (12) are rotationally matched in the second cooling frame (7), a first dust screen (15) is slidingly matched on the upper side of the second cooling frame (7), and a second dust screen (16) is fixed on the two sides of the second cooling frame (7).
2. A blowing device for cooling steel forgings according to claim 1, characterized in that: the fan (3) is positioned on one side of the first cooling frame (6) away from the second cooling frame (7).
3. A blowing device for cooling steel forgings according to claim 1, characterized in that: the second cooling frame (7) is rotatably matched with a rotating shaft (10), and one end of the rotating shaft (10) is fixedly connected with the first clamping plate (11).
4. A blowing device for cooling steel forgings according to claim 1, characterized in that: the second cooling frame (7) is rotatably matched with an electric push rod (13), and the output end of the electric push rod (13) is fixedly connected with the second clamping plate (12).
5. A blowing device for cooling steel forgings according to claim 4, characterized in that: the second cooling frame (7) is rotationally matched with the rotary table (8), one side of the rotary table (8) is fixedly connected with the electric push rod (13), and the rotary handle (9) is fixed on the other side of the rotary table (8).
6. A blowing device for cooling steel forgings according to claim 1, characterized in that: a sliding groove (14) is formed in the upper side of the second cooling frame (7), and the sliding groove (14) corresponds to the first dustproof net (15).
7. A blowing device for cooling steel forgings according to claim 1, characterized in that: and a spray head (17) is fixed on the upper side of the second cooling frame (7), and the spray head (17) is communicated with the water tank (1).
CN202321351044.XU 2023-05-31 2023-05-31 Be used for refrigerated blast apparatus of steel forging Active CN219851971U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321351044.XU CN219851971U (en) 2023-05-31 2023-05-31 Be used for refrigerated blast apparatus of steel forging

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321351044.XU CN219851971U (en) 2023-05-31 2023-05-31 Be used for refrigerated blast apparatus of steel forging

Publications (1)

Publication Number Publication Date
CN219851971U true CN219851971U (en) 2023-10-20

Family

ID=88333645

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321351044.XU Active CN219851971U (en) 2023-05-31 2023-05-31 Be used for refrigerated blast apparatus of steel forging

Country Status (1)

Country Link
CN (1) CN219851971U (en)

Similar Documents

Publication Publication Date Title
CN106166605B (en) Die casting automated production equipment
CN111230362B (en) Lithium battery pole plate welding mould
CN113334078A (en) Welding production line capable of achieving uniform heat dissipation
CN219851971U (en) Be used for refrigerated blast apparatus of steel forging
CN216445408U (en) Even heat sink is used in metal material thermal treatment
CN212094298U (en) Cooling device for decarbonization of high-carbon ferrochrome
CN205732923U (en) A kind of ferrous metal forming machine
CN209994499U (en) Distributed base station with heat dissipation mechanism
CN218232511U (en) Wheel hub quenching equipment
CN208644048U (en) A kind of brake pump cast casting cooling device
CN209157472U (en) A kind of canister diffuser welding tooling
CN215668128U (en) Heat treatment device for gear production
CN112410528B (en) Quenching device for saw blade machining
CN209292411U (en) Quick cooling equipment is used in a kind of production of mould steel
CN210703250U (en) Welding automatic cooling line
CN211147009U (en) Circulation type cooling device is used in production of radiator hydroecium
CN207787655U (en) A kind of compression mod synergy cooling system
CN208055407U (en) High-chromium abrasion-proof cast iron part rotating spraying quenching unit
CN220464469U (en) Work piece forced air cooling workstation in industrial workshop
CN219724542U (en) Die-casting cooling device for aluminum castings
CN209777760U (en) conveying device for metal die castings
CN216987033U (en) But height-adjusting's industrial equipment of selling of taking off
CN208995531U (en) A kind of quenched air cooler
CN212945389U (en) Casting cooling device
CN219951113U (en) Air-cooled quenching equipment for aluminum castings

Legal Events

Date Code Title Description
GR01 Patent grant