- CN216840205U CN216840205U CN202123123249.6U CN202123123249U CN216840205U CN 216840205 U CN216840205 U CN 216840205U CN 202123123249 U CN202123123249 U CN 202123123249U CN 216840205 U CN216840205 U CN 216840205U
- Authority
- CN
- China
- Prior art keywords
- plate
- metal
- outer frame
- core material
- metal outer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Panels For Use In Building Construction (AREA)
Abstract
The utility model provides a pipeline comprehensive cavity prefabricated slab and a building structure, which comprises a first metal outer frame, a second metal outer frame, a first plate, a second plate and a core material; the first metal outer frame and the second metal outer frame are oppositely arranged; the first plate is connected between the first metal outer frame and the second metal outer frame to form an installation frame body; the front end face and the rear end face of the mounting frame body are provided with second plates so as to seal the mounting frame body into a closed mounting space; the core material is filled in the installation space. In the utility model, the first plate is connected between the first metal frame and the second metal frame to form an installation frame body, and the second plate is arranged on the front end surface and the rear end surface of the installation frame body to seal the installation frame body into a closed installation space; the core material is filled in the installation space to form the prefabricated plate, so that the lightening and functionalization of the prefabricated plate are realized, the prefabricated plate can be applied to the quick construction of building structures in house decoration, and the manpower requirement in house decoration is reduced.
Description
Technical Field
The utility model relates to a prefabricated building specifically relates to a cavity prefabricated plate and building structure are synthesized to pipeline.
Background
After the existing building is finished, the building cannot be used in the building, and the next step of decoration work can be carried out on the surface. Many old houses are built for years, and the decoration is aged, and the house needs to be refitted again for further beautification.
When decorating the large space of floor area such as convenience store, commercial shop space, exhibition room, office space, hotel apartment, medical space, education space, in traditional fitment, the construction operation technology of its wall is: the method comprises the following steps of on-site paying off, wall surface grooving, line pipe pre-embedding, cement mortar leveling, installation of a flame-retardant board base layer and final installation of a veneer. The construction operation process of the partition wall comprises the following steps: building materials such as bricks, cement, sand, wood and the like are utilized, a field construction mode is adopted for building, and then the partition wall is decorated. In the traditional decoration mode, the time consumption is long, and the requirement of enterprises needing to rapidly live after handing over can not be met. And traditional wall body, the function is single, upstairs and downstairs drainage and its inconvenience, has realized different layers from the system of one-tenth, independent drainage, and traditional panel material is big, and carbon emission exceeds standard.
If the pipeline integrated cavity prefabricated slab can be provided, the prefabricated slab can be used as a floor slab, a floor slab and a wall body, the decoration speed is increased, and the parking speed is further increased.
SUMMERY OF THE UTILITY MODEL
To the defect among the prior art, the utility model aims at providing a cavity prefabricated plate and building structure are synthesized to pipeline.
According to the utility model, the pipe comprehensive cavity precast slab comprises a first metal outer frame, a second metal outer frame, a first plate, a second plate and a core material;
the first metal outer frame and the second metal outer frame are arranged oppositely;
the first plate is connected between the first metal outer frame and the second metal outer frame to form an installation frame body; second plates are arranged on the front end face and the rear end face of the mounting frame body so as to seal the mounting frame body into a closed mounting space;
the core material is filled in the installation space.
Preferably, the metal outer frame comprises a plurality of metal pieces connected end to end;
the metal piece comprises a support plate and an outer baffle plate; the supporting plate is vertically connected to the inner side surface of the outer baffle plate; the outer side surface of the outer baffle plate forms a hook groove;
the supporting plates in the metal outer frame are sequentially connected end to form a plate mounting plate; the grooves in the metal outer frame are connected end to form a plate mounting groove;
the first plate is fixed on the plate mounting plate, and the second plate is fixed on the plate mounting groove.
Preferably, the inner side surfaces of the support plates of the two connected metal pieces are fixedly connected through an angle bracket.
Preferably, the installation space is provided with a plurality of core material fixing pieces;
the plurality of core material fixing pieces are sequentially arranged along the height of the metal outer frame; one end of the core material fixing piece is connected with one inner side face of the installation frame body, and the other end of the core material fixing piece is connected with the other inner side face of the installation frame body;
the core fixing piece is provided with a plurality of core fixing holes, and a plurality of core cylinders are arranged on the core fixing holes.
Preferably, a metal mesh is arranged between the second plate and the outer side face of the outer baffle;
concrete is filled in a cavity area between the two opposite metal nets in the installation space.
Preferably, the core material column adopts an inflatable bag body, a metal hollow pipe or a PC plastic pipe.
Preferably, the device further comprises a transverse tube; the metal hollow pipe or the PC plastic pipe is vertically arranged;
the transverse pipe is transversely arranged and is communicated with a plurality of hollow metal pipes or PC plastic pipes which are sequentially arranged along the transverse direction.
Preferably, the core material cylinder is made of a phase change material.
Preferably, the core material fixing member includes a first fixing member and a second fixing member;
the first fixing piece and the second fixing piece are oppositely connected to form an integral structure.
According to the utility model provides a building structure, include pipeline composite chamber prefabricated plate.
Compared with the prior art, the utility model discloses following beneficial effect has:
in the utility model, a first plate is connected between the first metal frame and the second metal frame to form an installation frame body, and the second plate is arranged on the front end surface and the rear end surface of the installation frame body so as to seal the installation frame body into a closed installation space; the core material is filled in the installation space to form the prefabricated slab, so that the lightweight and functionalization of the prefabricated slab are realized, the prefabricated slab can be applied to the rapid construction of part of building structures in house decoration, and the manpower requirement in the house decoration is reduced;
in the utility model, because the width of the first plate is adjustable, the thickness of the precast slab formed by the metal outer frame and the first plate is flexible and adjustable, and is fixed relative to the thickness of the traditional plate, the utility model can be suitable for application scenes of plates with different thicknesses;
the prefabricated plate in the utility model can be prefabricated on site, and can be finished in an industrialized mode, and a pipeline is arranged in advance, so that the multifunctional function is realized, and the characteristics of integration, prefabrication, assembly, industrialization and the like are realized;
the utility model discloses utilize the building body that the prefabricated plate formed, have the fire prevention, keep warm, give sound insulation, functions such as drainage and easy dismounting, but direct replacement after the panel damages, recoverable cyclic utilization of panel is demolishd in the house, has practiced thrift the resource, has reduced building rubbish's formation, has realized green development.
Drawings
Other features, objects and advantages of the invention will become more apparent upon reading of the detailed description of non-limiting embodiments with reference to the following drawings:
fig. 1 is a schematic structural diagram of a pipeline composite cavity prefabricated slab in an embodiment of the present invention;
fig. 2 is a schematic structural view of a metal outer frame according to an embodiment of the present invention;
fig. 3 is a schematic view of a partial structure of a mounting frame according to an embodiment of the present invention;
fig. 4 is a schematic partial cross-sectional view of a mounting frame according to an embodiment of the present invention;
fig. 5 is a schematic cross-sectional view of a metal member according to an embodiment of the present invention;
FIG. 6 is a schematic structural diagram of a pipeline composite cavity prefabricated slab in another embodiment of the present invention;
FIG. 7 is a schematic view of a partial structure of a pipeline composite cavity precast slab according to another embodiment of the present invention;
fig. 8 is a schematic view illustrating a fitting relationship between the core fixing member and the core according to an embodiment of the present invention;
fig. 9 is a schematic structural view of a core fixing member according to an embodiment of the present invention;
FIG. 10 is a schematic structural diagram of a composite hollow cavity prefabricated panel for pipelines according to still another embodiment of the present invention; and
fig. 11 is a schematic structural view of a building structure according to the embodiment of the present invention.
In the figure:
1 is a first metal outer frame; 101 is a metal piece; 1011 is a support plate; 1012 is an outer baffle; 1013 is a hook groove; 2 is a second metal outer frame; 3 is a first plate; 4 is a second plate; 5 is a core material; 6 is an angle bracket; 7 is a core material fixing piece; 701 is a core material fixing hole; 8 is a core material cylinder; 9 is a metal net; 10 is a light heat-insulating inorganic material; 11 is a transverse tube; 100 is a pipeline integrated cavity prefabricated plate.
Detailed Description
The present invention will be described in detail with reference to the following embodiments. The following examples will assist those skilled in the art in further understanding the present invention, but are not intended to limit the invention in any way. It should be noted that various changes and modifications can be made by one skilled in the art without departing from the spirit of the invention. These all belong to the protection scope of the present invention.
Fig. 1 is a schematic structural diagram of a prefabricated panel for a comprehensive cavity of a pipeline according to an embodiment of the present invention, as shown in fig. 1, the prefabricated panel for a comprehensive cavity of a pipeline according to the present invention includes a first metal frame 1, a second metal frame 2, a first plate 3, a second plate 4, and a core material 5;
the first metal outer frame 1 and the second metal outer frame 2 are oppositely arranged;
the first plate 3 is connected between the first metal outer frame 1 and the second metal outer frame 2 to form an installation frame body; the front end face and the rear end face of the mounting frame body are provided with second plates 4 so as to seal the mounting frame body into a closed mounting space;
the core material 5 is filled in the installation space.
The embodiment of the utility model provides an in, core 5 plays heat preservation, the effect that gives sound insulation, and length direction overlength when panel can embed supporting beam and do the support.
Fig. 2 is a schematic structural diagram of a metal outer frame according to an embodiment of the present invention, as shown in fig. 2, the metal outer frame includes a plurality of metal members 101 connected end to end;
fig. 4 is a schematic partial cross-sectional view of a mounting frame according to an embodiment of the present invention, as shown in fig. 5, the metal member 101 includes a support plate 1011 and an outer baffle 1012; the supporting plate 1011 is vertically connected to the inner side surface of the outer baffle 1012; the outer side of the outer baffle 1012 forms a hook slot 1013;
the supporting plates 1011 in the metal outer frame are sequentially connected end to form a plate mounting plate; the grooves in the metal outer frame are connected end to form a plate mounting groove;
the first plate 3 is fixed on the plate mounting plate, and the second plate 4 is fixed on the plate mounting groove.
Fig. 3 is a schematic view of a partial structure of an installation frame according to an embodiment of the present invention, as shown in fig. 3, inner side surfaces of support plates 1011 of two connected metal members 101 are fixedly connected through an angle bracket 6.
Fig. 6 is a schematic structural view of a pipeline integrated cavity prefabricated slab according to another embodiment of the present invention, as shown in fig. 6, the installation space is provided with a plurality of core fixing members 7;
the plurality of core material fixing pieces 7 are sequentially arranged along the height of the metal outer frame; one end of the core material fixing piece 7 is connected with one inner side surface of the mounting frame body, and the other end of the core material fixing piece is connected with the other inner side surface of the mounting frame body;
the core fixing member 7 is provided with a plurality of core fixing holes 701, and a plurality of core columns 8 are arranged on the core fixing holes 701.
In the embodiment of the present invention, the core cylinder 8 is made of a foam material to further reduce the weight.
Fig. 7 is a schematic partial structural view of a pipeline composite cavity prefabricated slab according to another embodiment of the present invention, and as shown in fig. 7, a metal mesh 9 is disposed between the second plate 4 and the outer side surface of the outer baffle;
and a cavity area between two opposite metal nets 9 in the installation space is filled with a light heat-insulating inorganic material 10.
The embodiment of the utility model provides an in, the metalwork outward flange has the difference in height, and after the metal mesh tiling, pour one deck stereoplasm heat preservation inorganic material, stereoplasm heat preservation inorganic material horizontal plane flushes with the metalwork outward flange for metal frame, core, outside stereoplasm heat preservation inorganic material form overall structure, with increase of strength.
In the embodiment of the present invention, the core material column 8 is made of an inflatable bag, a metal hollow tube or a PC plastic tube.
The embodiment of the utility model provides an in, the gas bag body is full of after gaseous, can further realize the lightweight of panel, and low cost is convenient for transport, but on-the-spot prefabrication, after being full of gas, form with the isolated cavity of outside air, further promote the syllable-dividing heat preservation effect of panel.
When the metal hollow pipe is adopted, the strength is further enhanced, and the function of arranging pipelines can be realized.
When PC plastic pipes and the like are adopted, the sewage discharge function can be realized besides the pipeline arrangement function.
Fig. 9 is a schematic structural diagram of a core fixing member according to an embodiment of the present invention, as shown in fig. 9, the core fixing hole 701 may be a circle, an ellipse, a rounded rectangle, a kidney hole, or a hexagon.
Fig. 10 is a schematic structural view of a prefabricated panel for a comprehensive cavity of a pipeline according to still another embodiment of the present invention, as shown in fig. 10, the prefabricated panel for a comprehensive cavity of a pipeline provided by the present invention further includes a horizontal tube 11;
the metal hollow pipe or the PC plastic pipe is vertically arranged;
the transverse pipe 11 is transversely arranged and is communicated with a plurality of metal hollow pipes or PC plastic pipes which are sequentially arranged along the transverse direction.
In the embodiment of the utility model, the transverse coffin is added, so that the pipeline or the drainage can be transversely or longitudinally arranged, and a functional wall is provided for the drainage system on the same floor of the building;
in the embodiment of the present invention, the core cylinder 8 is made of a phase-change material, so as to realize the temperature adjustment function.
Fig. 8 is a schematic view illustrating a fitting relationship between a core fixing member and a core according to an embodiment of the present invention, as shown in fig. 8, the core fixing member includes a first fixing member and a second fixing member;
the first fixing piece and the second fixing piece are oppositely connected to form an integral structure.
The core material fixture may also be provided as a unitary structure.
Fig. 11 is a schematic structural view of a building structure according to an embodiment of the present invention, and as shown in fig. 11, the present invention provides a building structure including the pipeline composite cavity prefabricated panel 100.
In the embodiment of the present invention, a first plate is connected between the first metal frame and the second metal frame to form an installation frame, and a second plate is disposed on the front end surface and the rear end surface of the installation frame to enclose the installation frame into a closed installation space; the core material is filled in the installation space to form the prefabricated slab, so that the lightweight and functionalization of the prefabricated slab are realized, the prefabricated slab can be applied to the rapid construction of part of building structures in house decoration, and the manpower requirement in the house decoration is reduced; the prefabricated plate in the embodiment of the utility model can be prefabricated on site, and is finished by utilizing an industrialized mode, and a pipeline is arranged in advance, so that the multifunctional function is realized, and the characteristics of integration, prefabrication, assembly, industrialization and the like are realized; the embodiment of the utility model provides an in utilize the building body that prefabricated plate formed, have the fire prevention, keep warm, give sound insulation, functions such as drainage and easy dismounting, but direct replacement after the panel damages, but the house is demolishd panel recycle, has practiced thrift the resource, has reduced building rubbish's formation, has realized green development.
The foregoing description of the specific embodiments of the invention has been presented. It is to be understood that the present invention is not limited to the specific embodiments described above, and that various changes and modifications may be made by those skilled in the art within the scope of the appended claims without departing from the spirit of the invention.
Claims (10)
1. The pipeline comprehensive cavity prefabricated slab is characterized by comprising a first metal outer frame, a second metal outer frame, a first plate, a second plate and a core material;
the first metal outer frame and the second metal outer frame are arranged oppositely;
the first plate is connected between the first metal outer frame and the second metal outer frame to form an installation frame body; the front end face and the rear end face of the mounting frame body are provided with second plates so as to seal the mounting frame body into a closed mounting space;
the core material is filled in the installation space.
2. The pipeline synthetic cavity precast slab of claim 1, wherein the metal outer frame comprises a plurality of metal pieces connected end to end;
the metal piece comprises a support plate and an outer baffle plate; the supporting plate is vertically connected to the inner side surface of the outer baffle plate; the outer side surface of the outer baffle plate forms a hook groove;
the supporting plates in the metal outer frame are sequentially connected end to form a plate mounting plate; the grooves in the metal outer frame are connected end to form a plate mounting groove;
the first plate is fixed on the plate mounting plate, and the second plate is fixed on the plate mounting groove.
3. The prefabricated panel for the pipeline comprehensive cavity as claimed in claim 2, wherein the inner side surfaces of the supporting plates of the two connected metal members are fixedly connected through an angle bracket.
4. The pipeline integrated cavity precast slab as recited in claim 2, wherein the installation space is provided with a plurality of core material fixing members;
the plurality of core material fixing pieces are sequentially arranged along the height of the metal outer frame; one end of the core material fixing piece is connected with one inner side face of the installation frame body, and the other end of the core material fixing piece is connected with the other inner side face of the installation frame body;
the core fixing piece is provided with a plurality of core fixing holes, and a plurality of core cylinders are arranged on the core fixing holes.
5. The pipeline composite cavity precast slab as recited in claim 4, wherein a metal mesh is disposed between the second slab and the outer side of the outer barrier;
concrete is filled in a cavity area between the two opposite metal nets in the installation space.
6. The pipeline integrated cavity precast slab as recited in claim 4, wherein the core material column is made of an inflatable bag, a metal hollow pipe or a PC plastic pipe.
7. The pipeline integrated cavity precast slab according to claim 6, further comprising a cross tube; the metal hollow pipe or the PC plastic pipe is vertically arranged;
the transverse pipe is transversely arranged and is communicated with a plurality of hollow metal pipes or PC plastic pipes which are sequentially arranged along the transverse direction.
8. The pipeline integrated cavity precast slab of claim 4, wherein the core material cylinder is made of a phase change material.
9. The pipeline integrated cavity precast slab of claim 4, wherein the core material fixing member comprises a first fixing member and a second fixing member;
the first fixing piece and the second fixing piece are oppositely connected to form an integral structure.
10. A building structure comprising the pipeline integrated cavity precast slab as recited in any one of claims 1 to 9.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202123123249.6U CN216840205U (en) | 2021-12-14 | 2021-12-14 | Pipeline comprehensive cavity prefabricated slab and building structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202123123249.6U CN216840205U (en) | 2021-12-14 | 2021-12-14 | Pipeline comprehensive cavity prefabricated slab and building structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216840205U true CN216840205U (en) | 2022-06-28 |
Family
ID=82107101
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202123123249.6U Active CN216840205U (en) | 2021-12-14 | 2021-12-14 | Pipeline comprehensive cavity prefabricated slab and building structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216840205U (en) |
-
2021
- 2021-12-14 CN CN202123123249.6U patent/CN216840205U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101353929B (en) | Industrialization energy-saving building house | |
CN105908859A (en) | Heat-preservation precast wall body and assembled house | |
CN109322392B (en) | Light steel house and construction method thereof | |
RU2006139806A (en) | MULTI-LAYERED WALL PANEL, METHOD FOR ITS MANUFACTURE AND METHOD FOR BUILDING AN EXTERNAL WALL OF A MONOLITHIC-FRAME BUILDING FROM MULTILAYERED WALL PANELS | |
CN101629440A (en) | Integrally prefabricated composite external wall panel and manufacturing method thereof | |
CN104032888A (en) | Integrally prefabricated multifunctional composite external wall panel and industrial building external wall | |
CN104695662B (en) | Stone facing prefabricated outer wall panel and its production method and external wall system | |
CN205776895U (en) | Heat insulation prefabricated body of wall and prefabricated buildings | |
CN103266686B (en) | Inflatable skeleton filling wall | |
CN102733537A (en) | Sandwich insulating wall body based on ultrahigh-toughness cement-based composite material and wall boards | |
CN206189685U (en) | Integrated floor of modularization and house | |
CN216840205U (en) | Pipeline comprehensive cavity prefabricated slab and building structure | |
CN100427708C (en) | Energy saving composite self heat insulation wall for building | |
CN106368358A (en) | Modular integrated slabs and house | |
CN101260739A (en) | Expansion-proof component for building cast-in-situ light weight composite wall | |
CN114215268A (en) | Pipeline comprehensive cavity prefabricated slab and building structure | |
CN208685809U (en) | A kind of decoration integrated building of lightweight steel construction assembly | |
CN216360836U (en) | Assembled polymerization adjustable wallboard and wall structure | |
CN203947671U (en) | Integral prefabricated multi-functional compound external wall panel and industrialized building exterior wall | |
CN201050192Y (en) | Expansion-proof assembly for building cast-in-situ lightweight composite wall | |
CN209742157U (en) | External thermal insulation wall structure of fabricated building | |
CN114059684A (en) | Construction method of 3D printing building functional cabin | |
CN107965088A (en) | A kind of novel wall structure | |
WO2018107187A1 (en) | Method of erecting a multilayer exterior wall of a building | |
CN206829538U (en) | A kind of wall body construction with double-layer fireproof template |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |