CN212984578U - Novel high altitude steel construction installation work is supplementary device - Google Patents

Novel high altitude steel construction installation work is supplementary device Download PDF

Info

Publication number
CN212984578U
CN212984578U CN202020934022.6U CN202020934022U CN212984578U CN 212984578 U CN212984578 U CN 212984578U CN 202020934022 U CN202020934022 U CN 202020934022U CN 212984578 U CN212984578 U CN 212984578U
Authority
CN
China
Prior art keywords
supporting rod
rods
rod
supporting rods
hanging beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020934022.6U
Other languages
Chinese (zh)
Inventor
尧棋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020934022.6U priority Critical patent/CN212984578U/en
Application granted granted Critical
Publication of CN212984578U publication Critical patent/CN212984578U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a novel high altitude steel construction installation operation is supplementary device, include: the main body bracket, the diagonal brace and the hanging beam handle; the main body bracket comprises a vertical supporting rod and a transverse supporting rod; the transverse supporting rods are arranged between the vertical supporting rods in parallel to form a rectangular frame structure; the vertical supporting rods comprise front supporting rods and rear supporting rods, and the length of each front supporting rod is smaller than that of each rear supporting rod; one end of the inclined supporting rod is connected with the top end of the front supporting rod, and the other end of the inclined supporting rod is connected with the top end of the rear supporting rod; the hanging beam handle is arranged on the rear supporting rod. The utility model provides a the device processing, transformation are simple, and application method is simple reliable, and operation personnel operational scope is big, need not to set up full hall frame, have guaranteed the construction progress, and extensive applicability can effectively improve work efficiency, compares full hall frame significantly reduced manual work and mechanical cost.

Description

Novel high altitude steel construction installation work is supplementary device
Technical Field
The utility model relates to a building engineering technical field, more specifically the utility model relates to a novel high altitude steel construction installation operation is supplementary device that says so.
Background
In the building construction, steel structure buildings are often adopted, at present, with the rapid development of the economy of China and the long-term planning of China, the construction mileage of a high-speed railway is increased rapidly, and the number of all-steel structure unit projects of an industrial factory building serving a high-speed train is increased rapidly. In the installation process of a steel structure, high-altitude falling is the key point of construction safety management, particularly in large-scale steel structure installation and construction, the height of steel structures of a station room and a storehouse is large, the falling often results in serious consequences, the loss of manpower, financial resources and company credit is caused, and the suspension of a project and the delay of a construction period are caused.
In the traditional construction method, a full hall frame is required to be erected as a support, but the erection difficulty is high, the economy is poor, and certain requirements are met on the conditions of a construction site.
Therefore, how to provide a novel overhead steel structure installation operation auxiliary device which is simple, economical and practical to use is a problem which needs to be solved urgently by technical personnel in the field.
SUMMERY OF THE UTILITY MODEL
In view of this, the utility model provides a novel high altitude steel construction installation operation auxiliary device, its aim at solve the problem that needs to set up full hall frame among the prior art and just can carry out the construction through this simple structure easy dismounting's high altitude steel construction installation operation auxiliary device.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a novel high altitude steel construction installation operation is supplementary device, includes: the main body bracket, the diagonal brace and the hanging beam handle;
the main body bracket comprises a vertical supporting rod and a transverse supporting rod; the transverse supporting rods are arranged between the vertical supporting rods in parallel to form a rectangular frame structure;
the vertical supporting rods comprise front supporting rods and rear supporting rods, and the length of each front supporting rod is smaller than that of each rear supporting rod;
one end of the inclined supporting rod is connected with the top end of the front supporting rod, and the other end of the inclined supporting rod is connected with the top end of the rear supporting rod;
the hanging beam handle is arranged on the rear supporting rod.
Preferably, the front supporting rods and the rear supporting rods at least comprise 2 supporting rods, and the plane where the front supporting rods are located is parallel to the plane where the rear supporting rods are located.
Preferably, the transverse supporting rods comprise bottom supporting rods, and the bottom supporting rods are arranged in parallel in a plane formed by the bottom ends of the front supporting rods and the rear supporting rods.
Preferably, the number of the diagonal support bars is 2, and the diagonal support bars are respectively arranged on the front support bar and the rear support bar on the outermost side.
Preferably, the beam hanging handle is L-shaped, and one end of the beam hanging handle is connected with the top end of the rear supporting rod.
Preferably, the device further comprises a bottom plate, and the bottom plate is arranged on the bottom supporting rod.
According to the technical scheme, compare with prior art, the utility model discloses a novel high altitude steel construction installation operation auxiliary device, the device processing, reform transform simply, can select each bracing piece specification according to on-the-spot actual demand, can process preparation high altitude construction auxiliary device by oneself, and application method is simple reliable, and operation personnel operational scope is big, need not to set up full hall frame, has guaranteed the construction progress, and extensive applicability can effectively improve work efficiency, compares full hall frame and has significantly reduced artifical and mechanical cost.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required to be used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the provided drawings without creative efforts.
FIG. 1 is a schematic structural view provided by the present invention;
1-front supporting rod, 2-rear supporting rod, 3-diagonal supporting rod, 4-hanging beam handle and 5-bottom supporting rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The embodiment of the utility model discloses novel high altitude steel construction installation work is supplementary device, include: the main body support, the diagonal brace 3 and the hanging beam handle 4;
the main body bracket comprises a vertical supporting rod and a transverse supporting rod; the transverse supporting rods are arranged between the vertical supporting rods in parallel to form a rectangular frame structure;
the vertical support rods comprise a front support rod 1 and a rear support rod 2, and the length of the front support rod 1 is smaller than that of the rear support rod 2;
one end of the diagonal brace 3 is connected with the top end of the front brace 1, and the other end is connected with the top end of the rear brace 2;
the hanging beam handle 4 is arranged on the rear support rod 2.
In order to further implement the above scheme, the front support rod 1 and the rear support rod 2 both comprise at least 2 steel pipes, and the plane of the front support rod 1 is parallel to the plane of the rear support rod 2.
In order to further implement the above-mentioned embodiment, the lateral support bar includes a bottom support bar 5, and the bottom support bar 5 is disposed in parallel in a plane formed by the bottom ends of the front support bar 1 and the rear support bar 2.
In order to further implement the above embodiment, the diagonal braces 3 are 2 steel pipes, and are respectively disposed on the front brace 1 and the rear brace 2 at the outermost sides.
In order to further implement the above scheme, the hanging beam handle 4 is L-shaped, and one end of the hanging beam handle 4 is connected with the top end of the rear supporting rod 2.
In order to further implement the above embodiment, a bottom plate is further included, and the bottom plate is disposed on the bottom support bar 5.
In this embodiment, all the support rods are steel pipes, the front support rod 1 is a steel pipe with 2 pieces of length of 0.8m, the rear support rod 2 is a steel pipe with 2 pieces of length of 1.8m, the horizontal support rods include 10 steel pipes with 1m, the horizontal support rods are respectively arranged between the front support rods 1, between the rear support rods 2 and between the front support rod 1 and the rear support rod 2, the bottom support rods 5 include 3 pieces, the bottom support rods are arranged in the plane at the bottom of the device, the interval between every two bottom support rods is 0.25m, the inclined support rods 3 are composed of 2 steel pipes with about 1.41m, the bottom plate is a wood pattern with 4cm, and the specific arrangement is as shown in fig. 1.
During construction, the device is installed on the beam by the aid of the tower crane, and then an operator is hoisted into the device through the tower crane to stand on the bottom plate and is required to take safety belts, safety helmets and the like during hoisting. The special person should be used to direct the construction. After the construction is finished, the personnel firstly hoist, and then the device hoists down.
It should be further noted that the specific size of the support rod can be determined according to actual conditions, the specific size of the handle of the hanging beam is determined according to the size of the beam in construction, the horizontal size and the bending size of the handle of the hanging beam are determined by the size of the beam, and the connection mode among the steel pipes is a welding mode.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other. The device disclosed by the embodiment corresponds to the method disclosed by the embodiment, so that the description is simple, and the relevant points can be referred to the method part for description.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (6)

1. The utility model provides a novel high altitude steel construction installation operation is supplementary device which characterized in that includes: the main body support, the diagonal brace (3) and the hanging beam handle (4);
the main body bracket comprises a vertical supporting rod and a transverse supporting rod; the transverse supporting rods are arranged between the vertical supporting rods in parallel to form a rectangular frame structure;
the vertical supporting rods comprise front supporting rods (1) and rear supporting rods (2), and the length of each front supporting rod (1) is smaller than that of each rear supporting rod (2);
one end of the inclined supporting rod (3) is connected with the top end of the front supporting rod (1), and the other end of the inclined supporting rod is connected with the top end of the rear supporting rod (2);
the hanging beam handle (4) is arranged on the rear supporting rod (2).
2. The novel overhead steel structure installation operation auxiliary device as claimed in claim 1, wherein the front supporting rod (1) and the rear supporting rod (2) comprise at least 2 steel pipes, and the plane of the front supporting rod (1) is parallel to the plane of the rear supporting rod (2).
3. The novel overhead steel structure mounting operation auxiliary device as claimed in claim 1, wherein the transverse support rods comprise bottom support rods (5), and the bottom support rods (5) are arranged in parallel in a plane formed by the bottom ends of the front support rods (1) and the rear support rods (2).
4. The novel overhead steel structure installation operation auxiliary device as claimed in claim 2, wherein the inclined support rods (3) are 2 steel pipes and are respectively arranged on the front support rod (1) and the rear support rod (2) on the outermost side.
5. The novel overhead steel structure installation work auxiliary device as claimed in claim 1, wherein the hanging beam handle (4) is L-shaped, and one end of the hanging beam handle (4) is connected with the top end of the rear supporting rod (2).
6. The novel overhead steel structure installation work auxiliary device as claimed in claim 3, further comprising a bottom plate, wherein the bottom plate is arranged on the bottom support rod (5).
CN202020934022.6U 2020-05-28 2020-05-28 Novel high altitude steel construction installation work is supplementary device Expired - Fee Related CN212984578U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020934022.6U CN212984578U (en) 2020-05-28 2020-05-28 Novel high altitude steel construction installation work is supplementary device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020934022.6U CN212984578U (en) 2020-05-28 2020-05-28 Novel high altitude steel construction installation work is supplementary device

Publications (1)

Publication Number Publication Date
CN212984578U true CN212984578U (en) 2021-04-16

Family

ID=75421402

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020934022.6U Expired - Fee Related CN212984578U (en) 2020-05-28 2020-05-28 Novel high altitude steel construction installation work is supplementary device

Country Status (1)

Country Link
CN (1) CN212984578U (en)

Similar Documents

Publication Publication Date Title
CN202139833U (en) Cantilever scaffold for building construction
CN204040435U (en) High-altitude steel structure welding Hanging Basket
CN206753085U (en) A kind of sliding platform for being used to install high-altitude wire frame steel construction
CN212984578U (en) Novel high altitude steel construction installation work is supplementary device
CN208310204U (en) Base for supporting and arranging elevator shaft coupling beam template
CN204691201U (en) A kind of Liftable hanging formula scaffold system
CN205034948U (en) Rack formula hanging beam device
CN213572927U (en) Movable steel platform with adjustable size and capable of being circulated
CN212249129U (en) Protective net fixing rod for attached lifting scaffold
CN211736308U (en) Self-sliding hanging frame device for mounting steel structure factory building roof inner plate
CN210151938U (en) Column top supporting device for low-position jacking formwork system
CN209874434U (en) Simple and easy scaffold frame of encorbelmenting of building high latitude
CN211714558U (en) Hanging stirrup for nuclear power template
CN203475317U (en) Bracket for high pier collar beam construction
CN207749810U (en) A kind of Novel moveable scaffold
CN203382367U (en) Honeycomb core hoisting device
CN103114712B (en) Buckle steel platform support system and construction method thereof
CN101597956A (en) Suspended scaffold
CN209353741U (en) A kind of rack overhead welding ease of Use platform
CN214995797U (en) Safety hanging basket for pipe truss overhead operation
CN218912192U (en) Clamp type operation platform suitable for box girder
CN215948984U (en) Overhanging protection unit and device
CN218912194U (en) Portable safe operation platform for elevator shaft of high-rise building
CN217264181U (en) Integral hoisting tool for steel reinforcement framework of prefabricated part of assembled station
CN212740395U (en) Hoisting frame for hoisting large-span planar steel bar component

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210416