CN209262658U - A kind of reinforcement by connection structure when gas chamber piston system hangs are removed - Google Patents

A kind of reinforcement by connection structure when gas chamber piston system hangs are removed Download PDF

Info

Publication number
CN209262658U
CN209262658U CN201821915441.4U CN201821915441U CN209262658U CN 209262658 U CN209262658 U CN 209262658U CN 201821915441 U CN201821915441 U CN 201821915441U CN 209262658 U CN209262658 U CN 209262658U
Authority
CN
China
Prior art keywords
piston
reinforcement
gas chamber
truss
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821915441.4U
Other languages
Chinese (zh)
Inventor
张云鹏
刘群杰
吕中亮
张琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Third Metallurgical Group Co Ltd
Original Assignee
China Third Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Third Metallurgical Group Co Ltd filed Critical China Third Metallurgical Group Co Ltd
Priority to CN201821915441.4U priority Critical patent/CN209262658U/en
Application granted granted Critical
Publication of CN209262658U publication Critical patent/CN209262658U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model relates to reinforcement by connection structures when a kind of dismounting of gas chamber piston system hangs, including vertical plate lifting lug, chain hoist, wind up reinforcement and lower edge reinforcement;The vertical plate lifting lug be it is multiple, be arranged on gas chamber column correspondingly, and corresponding piston winds up the lower section of truss;Vertical plate lifting lug is connected with corresponding piston truss upright-column by chain hoist;Piston winds up and sets the reinforcement that winds up between truss and gas chamber column, sets string reinforcement between the gas chamber column and piston truss upright-column of piston lower edge truss.In the operation process that the utility model is used to remove the piston for being trapped in a certain position because of accident using the method that suspension is removed, structure is simple, highly-safe, advantageously reduces construction cost.

Description

A kind of reinforcement by connection structure when gas chamber piston system hangs are removed
Technical field
When being removed the utility model relates to gas chamber technical field of construction more particularly to a kind of gas chamber piston system hangs Reinforcement by connection structure.
Background technique
In recent years, as China's industry is grown rapidly, industry constantly upgrades, and smelting equipment is in terms of enlargement, environmental protection Development, the projects such as coal gas, steam combined cycle power generating are more and more by major steel mill's exploitation, construction.Gas chamber is as power generation The auxiliary facility of project enters the peak period of a construction, and the gas chamber built in the past, which also enters, to be concentrated the transformation phase and scrap Phase, date of retirement are essentially the gas chamber of construction in one's early years, the case where piston can not vacantly be fallen after rise are frequently occurred after run throughout the year.
Authorization Notice No. is that the Chinese patent of CN101709829B discloses a kind of " dismantling method of coal gas storage cabinet ", will Piston is down to bottom of cabinet bulk and then is removed;For the thin oil sealing-type dry-type gas chamber under accident condition when piston clamping stagnation exists When a certain position, bottom of cabinet bulk can not be down to;Removing piston system in the case is one and compares difficult task, only The method that can be removed using suspension, suspension removes piston system because piston system weight is big, span is big, and piston has shifting at any time Dynamic possibility, therefore lead to that difficulty of construction is big, risk is big.
Summary of the invention
The utility model provides reinforcement by connection structure when a kind of gas chamber piston system hangs are removed, for using outstanding It hangs in the operation process that the method removed removes the piston for being trapped in a certain position because of accident, structure is simple, safety Property it is high, advantageously reduce construction cost.
In order to achieve the above object, the utility model is implemented with the following technical solutions:
A kind of gas chamber piston system hangs remove when reinforcement by connection structure, including vertical plate lifting lug, chain hoist, on String reinforcement and lower edge reinforcement;The vertical plate lifting lug be it is multiple, be arranged on gas chamber column correspondingly, and corresponding piston It winds up the lower section of truss;Vertical plate lifting lug is connected with corresponding piston truss upright-column by chain hoist;Piston wind up truss with The reinforcement that winds up is set between gas chamber column, is set between the gas chamber column and piston truss upright-column of piston lower edge truss String reinforcement.
The reinforcement that winds up, lower edge reinforcement are made of I-steel.
Compared with prior art, the utility model has the beneficial effects that
Reinforcement by connection structure described in the utility model is used for the piston system demolishing process of thin oil sealing-type dry-type gas chamber In, piston removes the method removed using suspension subregion, by reinforcement by connection structure described in the utility model by accident condition Under piston be suspended on gas chamber column, then removed;In addition to needing with crane when the piston under handling disassembly, nothing Other Large-scale Hoisting equipment need to be used, without setting up support scaffolding, realizes and is surpassed using what less tooling, equipment Removal were hung High, large span piston system purpose improves the economic benefit of enterprise to reduce the cost of enterprise.
Detailed description of the invention
Fig. 1 is the signal of reinforcement by connection structure when a kind of gas chamber piston system hangs described in the utility model are removed Figure.
In figure: 1. wind up 4. lower edge reinforcement of reinforcement 2. chain hoist, 3. vertical plate lifting lug, 5. gas chamber column The 9. piston lower edge truss of truss 6. 7. piston of piston truss upright-column, 8. piston winds up
Specific embodiment
Specific embodiment of the present utility model is described further with reference to the accompanying drawing:
As shown in Figure 1, be reinforcement by connection structure when a kind of gas chamber piston system hangs described in the utility model are removed, Including vertical plate lifting lug 3, chain hoist 2, wind up reinforcement 1 and lower edge reinforcement 4;The vertical plate lifting lug 3 is multiple, a pair It is arranged with answering on gas chamber column 5, and corresponding piston winds up the lower section of truss 8;Vertical plate lifting lug 3 and corresponding piston truss upright-column 6 are connected by chain hoist 2;Piston, which winds up, sets the reinforcement 1 that winds up between truss 8 and gas chamber column 5, close to piston lower edge String reinforcement 4 is set between the gas chamber column 5 and piston truss upright-column 6 of truss 9.
The reinforcement 1 that winds up, lower edge reinforcement 4 are made of I-steel.
Gas chamber piston system includes the piston plate of dome shape, the lower edge truss being arranged on piston plate, along piston edges of boards It piston truss upright-column that edge is set side by side, the sub-truss for connecting adjacent pistons truss upright-column and is set on piston truss upright-column Piston side siding, further include be set to the upper end of the column wind up truss and connection is winded up the intermediate supports of truss and lower edge truss Truss.
When thin oil sealing-type dry-type gas chamber piston system hangs are removed under accident condition with the following method:
1) it as shown in Figure 1, accident condition lower piston 7 is trapped in a certain position, removes before piston system first with air by coal Coal gas replacement in gas holder comes out, and carries out dismounting operation after pressure in gas chamber reaches equilibrium valve;
2) vertical plate lifting lug 3 is welded on every gas chamber column 5, vertical plate lifting lug 3 is correspondingly arranged at piston and winds up truss 8 Lower section;Piston truss upright-column 6 is connect with vertical plate lifting lug 3 by chain hoist 2, prevents piston 8 in work progress mobile;
3) piston is winded up and is reinforced between truss 8 and gas chamber column 5 using the reinforcement 1 that winds up, close to piston lower edge It is reinforced between the gas chamber column 5 and piston truss upright-column 6 of truss 9 using lower edge reinforcement 4;
4) crane reaches piston 7 and originates on the outside of the corresponding gas chamber of cutting region, carries out lifting and prepares;
5) by starting cutting region along being removed by several times by cutting region clockwise or counterclockwise when piston 7 is removed, by subregion Piston component after the cutting of domain hangs original position by crane respectively, finishes until piston 7 is all removed.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this Novel technical solution and its design is subject to equivalent substitution or change, should be covered within the scope of the utility model.

Claims (2)

  1. Reinforcement by connection structure when 1. a kind of gas chamber piston system hangs are removed, which is characterized in that including vertical plate lifting lug, chain type Crane, wind up reinforcement and lower edge reinforcement;The vertical plate lifting lug be it is multiple, correspondingly be arranged gas chamber column on, And corresponding piston winds up the lower section of truss;Vertical plate lifting lug is connected with corresponding piston truss upright-column by chain hoist;Piston It winds up and sets the reinforcement that winds up between truss and gas chamber column, the gas chamber column and piston truss close to piston lower edge truss are vertical String reinforcement is set between column.
  2. 2. reinforcement by connection structure when a kind of gas chamber piston system hangs according to claim 1 are removed, feature exist In the reinforcement that winds up, lower edge reinforcement are made of I-steel.
CN201821915441.4U 2018-11-20 2018-11-20 A kind of reinforcement by connection structure when gas chamber piston system hangs are removed Active CN209262658U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821915441.4U CN209262658U (en) 2018-11-20 2018-11-20 A kind of reinforcement by connection structure when gas chamber piston system hangs are removed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821915441.4U CN209262658U (en) 2018-11-20 2018-11-20 A kind of reinforcement by connection structure when gas chamber piston system hangs are removed

Publications (1)

Publication Number Publication Date
CN209262658U true CN209262658U (en) 2019-08-16

Family

ID=67555552

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821915441.4U Active CN209262658U (en) 2018-11-20 2018-11-20 A kind of reinforcement by connection structure when gas chamber piston system hangs are removed

Country Status (1)

Country Link
CN (1) CN209262658U (en)

Similar Documents

Publication Publication Date Title
CN108930228A (en) The construction method of bent cap hoop bracket overall pulling down
CN101832465B (en) Synchronously jacking construction method for side plate and top cover of rubber film sealed gas holder
CN102486051B (en) Manual demolishing method of large-area spherical net rack
CN203372980U (en) Detachable top cover hanger applicable to pressurized water reactor
CN101264845A (en) Crown block high altitude integrated suspension transposition construction method
CN209262658U (en) A kind of reinforcement by connection structure when gas chamber piston system hangs are removed
CN106044580A (en) Whole lifting method of wet electrostatic dust removing device body equipment
CN202017503U (en) Automatic pin puller for hydraulic support
CN207312995U (en) One kind self-control bridge-collision-avoidance wall form hanging device
CN211444835U (en) Tower body tile holding mounting and dismounting device of tower crane
CN202000268U (en) Foldable front outrigger for bridge girder erection machine
CN109538921A (en) Gas chamber piston system hangs method for dismounting under a kind of accident condition
CN106481967B (en) A kind of installation method of rubber diaphragm gas chamber
CN105926455B (en) A kind of bottom die of box-beam overall pulling down method
CN106013819A (en) Hoisting system and method for hoisting prefabricated exterior wall cladding based on overhead hooking exchange
CN204238443U (en) A kind of detachable suspension column fastening devices
CN202644407U (en) Demoulding device for bottom plate bracket of capping beam constructed by hoop method
CN202337949U (en) Bridge jacking device
CN205216819U (en) Petrochemical engineering tower
CN207209786U (en) The cast-in-place boom support monoblock type automatic disassembling device of falsework
CN105060124A (en) Intra-frame portal crane system and hoisting use method thereof
CN204549893U (en) A kind of tackling system of auxiliary hoist jib hinged-support bearing replacing
CN211110624U (en) Lifting appliance capable of rapidly replacing cage ribs of gas dust removal box
CN211310552U (en) Protection device for hoisting large part
CN203961249U (en) Combined type Cantilever Beams

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant