CN202337949U - Bridge jacking device - Google Patents

Bridge jacking device Download PDF

Info

Publication number
CN202337949U
CN202337949U CN201120455140XU CN201120455140U CN202337949U CN 202337949 U CN202337949 U CN 202337949U CN 201120455140X U CN201120455140X U CN 201120455140XU CN 201120455140 U CN201120455140 U CN 201120455140U CN 202337949 U CN202337949 U CN 202337949U
Authority
CN
China
Prior art keywords
jacking
bridge
abutment
counterforce device
control system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201120455140XU
Other languages
Chinese (zh)
Inventor
尹天军
蒋岩峰
郑华奇
袁风翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI XIANWEI CIVIL ENGINEERING Co Ltd
Original Assignee
SHANGHAI XIANWEI CIVIL ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI XIANWEI CIVIL ENGINEERING Co Ltd filed Critical SHANGHAI XIANWEI CIVIL ENGINEERING Co Ltd
Priority to CN201120455140XU priority Critical patent/CN202337949U/en
Application granted granted Critical
Publication of CN202337949U publication Critical patent/CN202337949U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a bridge jacking device, which comprises a programmable logic controller (PLC) hydraulic synchronization jacking control system, a jack deployed by the PLC hydraulic synchronization jacking control system, and a jacking counterforce unit cooperating with the PLC hydraulic synchronization jacking control system to provide support for the jack. The bridge jacking device has the advantages that reliable bearing capacity, synchronism and the whole load bearing capability are provided for bridge jacking; and the jacking counterforce unit can be a metal structure pedant mounted on abutments to bear the jacking counterforce, so that the jacking counterforce unit is convenient to dismount, and is capable of being recycled and effectively saving resource and reducing the construction period.

Description

The bridge jacking device
Technical field
The utility model relates to a kind of building jacking engineering support system, especially a kind of bridge jacking engineering support system.
Background technology
At present, job practices commonly used is to seek utilizable brace foundation in the bridge jacking engineering, adopts the jacking jack to carry out jacking by brace foundation.What generally the most often utilize is exactly the space on original basis or the abutment (abutment or pier stud); But tend to run into the cost that original basis is difficult to utilize or utilize is too high, the duration is long or abutment (abutment or pier stud) on the space too little, can not satisfy the condition that jack is laid.
In the case, a kind of can be imperative for the jacking jack provides the utility model of effective supporting plane and reaction of bearing jacking top bridge.
The utility model content
The technical problem that the utility model will solve is: overcome the deficiency that exists in the prior art; Provide a kind of and when the bridge tale quale can not be utilized, still can the oneself create virtual plane, thereby the bridge jacking apparatus and method of reliable assurance are provided for the bridge jacking engineering with effective support top jacking bridge.
The utility model is realized through following technical scheme:
That is: a kind of bridge jacking device; It comprises PLC Hydraulic Synchronizing jacking control system, the jack under the allotment of aforementioned PLC Hydraulic Synchronizing jacking control system; It is characterized in that it also comprises: matching with PLC Hydraulic Synchronizing jacking control system is combined into the jacking counterforce device that jack provides support.
Said jacking counterforce device is installed in the jacking counterforce device that carries the jacking counter-force on the abutment on original bridge abutment, planting reinforcing bar as jacking counter-force basic jacking counterforce device or metal construction suspension member.
The jacking counterforce device that said metal construction suspension member is installed in carrying jacking counter-force on the abutment is arranged under the plate seam of two adjacent plate-girders, and is connected with abutment through bar planting.Certainly, this bracket is applicable to the jacking of different types of rridges, is not limited to slab and girder, and its position is also not only in the plate seam of adjacent plate-girder.
Said jacking counterforce device can be removed.
A kind of bridge jacking method; It comprises PLC Hydraulic Synchronizing jacking control system, the jack under the allotment of aforementioned PLC Hydraulic Synchronizing jacking control system; Matching with PLC Hydraulic Synchronizing jacking control system is combined into the jacking counterforce device that jack provides support, and wherein its jacking step is following:
On bridge bent cap, pier stud or abutment, implant or install the jacking counterforce device;
The jacking counterforce device directly is installed or is used for fixing the jacking counterforce device at bridge bent cap (abutment or pier stud) end face in bridge bent cap (abutment or pier stud) side bar planting;
According to the jacking stroke jack that is fit to is placed in the jacking counterforce device;
Jacking content through PLC Hydraulic Synchronizing jacking control systematic unity allotment jack.
Said jacking counterforce device is directly to install or pass through at original bridge bent cap, abutment or pier stud end face to fix the metal structural component jacking counterforce device as jacking counter-force basis in bent cap, abutment or the bar planting of pier stud end face.
Said metal construction suspension member is installed on bent cap, abutment or the pier stud plate seam that the jacking counterforce device that carries the jacking counter-force is arranged in two adjacent plate-girders down, and through bar planting be connected.
Said jacking counterforce device can be removed and can reuse.
The utlity model has following beneficial effect:
For bridge jacking provides reliable bearing capacity, synchronism and whole stressed property;
The jacking counterforce device can be that the metal construction suspension member is installed in carrying jacking counter-force on the abutment, and convenient the dismounting and recycling can effectively be saved resource and reduction of erection time;
Description of drawings
Combine the description of its accompanying drawing through following embodiment, can further understand and use novel purpose, specific structural features and advantage in fact the utility model.Wherein, accompanying drawing is:
Fig. 1 be the utility model the jacking counterforce device install and use sketch map;
The specific embodiment
The utility model is jacking, the support system that is applied to building jacking engineering, especially a kind of bridge jacking engineering support system.Be to existing jacking, support system, comprise the significant improvement of making on the basis of shortcoming of bracing or strutting arrangement and method for supporting, have very important practice significance.
Below in conjunction with accompanying drawing and embodiment utility model is further specified:
The utility model provides a kind of bridge jacking device and raising method; Said bridge jacking device mainly comprise with PLC Hydraulic Synchronizing jacking control system, under the allotment of PLC Hydraulic Synchronizing jacking control system jack group and match with PLC Hydraulic Synchronizing jacking control system and to be combined into the jacking counterforce device 10 that jack 20 provides support.
Said jacking counterforce device 10 is for to plant reinforcing bar at original bridge bent cap (pier stud or abutment); Also can make concrete, jacking counterforce device or the metal construction suspension member basic as the jacking counter-force are installed in the jacking counterforce device that bent cap (pier stud or abutment) is gone up carrying jacking counter-force; The jacking counterforce device directly is installed or is used for fixing the jacking counterforce device at bridge bent cap (abutment or pier stud) end face in bridge bent cap (abutment or pier stud) side bar planting.Being installed in the last jacking counterforce device that carries the jacking counter-force of bent cap (pier stud or abutment) with the metal construction suspension member in the present embodiment serves as that the master carries out detailed description to jacking counterforce device 10:
The jacking counterforce device 10 of said metal construction suspension member can be any metal with strong hardness; For example steel, iron etc.; It is example that the utility model adopts the jacking counterforce device 10 of steel work suspension member; It is mounted on the abutment and carries the jacking counter-force, and its plate seam that is arranged in two adjacent plate-girders and is connected with bent cap (pier stud or abutment) through bar planting down.Certainly, this bracket is applicable to the jacking of different types of rridges, is not limited to slab and girder, and its position is also not only in the plate seam of adjacent plate-girder.Wherein, The similar bracket of jacking counterforce device 10 shapes; In the industry cycle also often be called as the jacking of bracket counter-force, be provided with in the middle and lower part of jacking counterforce device 10 one with the load plane 101 of the moulding of jacking counterforce device 10 one, be used for specifically carrying jack 20 and its.
In concrete jacking process, promptly be the raising method of main example with the bridge, wherein its jacking step is following:
According to calculating and design to the engineering bridge material; Be installed on the bent cap (pier stud or abutment) 30 of bridge shifting to an earlier date the ready some jacking counterforce devices 10 in back that machine; After before installation, cap being carried out levelling, the method that is employed in the cladding steel corbel of cap is as the counter-force basis.Steel corbel is connected with bent cap (pier stud or abutment) through bar planting;
Can adopt the jack 20 of different strokes according to the requirement of jacking stroke, promptly according to the jacking stroke jack that is fit to is placed in and rise in the counterforce device 10, jack is installed on the load plane 101.
Effectively provide under the prerequisite of carrying the basis at jacking counterforce device 10, the jacking content through PLC Hydraulic Synchronizing jacking control systematic unity allotment jack comprises the jacking synchronous error, jacking load, jacking displacement etc.
Popular says, the utility model is to adopt PLC Hydraulic Synchronizing jacking control system, in conjunction with multinomial technology such as bracket bar planting technology, spacing technology and jacking monitoring, on original bent cap (pier stud or abutment), plants bracket as the counter-force basis, and superstructure is carried out jacking.
Do the method on bracket counter-force basis after promptly adopting and carry out jacking.The jacking of bracket counter-force mainly comprises two kinds, the one, and on original bridge bent cap (pier stud or abutment), plant reinforcing bar and do concrete bracket carrying jacking counter-force basis; The 2nd, do steel work bracket suspension member and be directly installed on the method that bent cap (pier stud or abutment) is gone up carrying jacking counter-force.
Being employed in existing bent cap (pier stud or abutment) outside bar planting (expansion bolt) makes steel corbel and carries out jacking as the counter-force basis.Jack is arranged under the plate seam of two adjacent plate-girders, and the plate-girder bottom is provided with certain thickness steel plate to disperse concentrated stress.The bracket shearing resistance is mainly born by the anti-shear steel plate on top.Electric hammer punching is adopted in bar planting, not destroy the abutment reinforcing bar.
After jacking finishes steel corbel is removed, the reinforcing bar of implanting is cut, and the abutment surface is repaired.
The description of above-mentioned preferred embodiment makes those skilled in the art can make or use the utility model.The various modifications of these embodiment are conspicuous for a person skilled in the art, and the General Principle of definition can be applied among other embodiment and do not deviate from the spirit or the scope of the utility model here.Therefore, the embodiment that the utility model is not limited to illustrate here, and will meet and the principle and the novel feature the most wide in range consistent scope that disclose here.

Claims (4)

1. bridge jacking device; It comprises PLC Hydraulic Synchronizing jacking control system, the jack under the allotment of aforementioned PLC Hydraulic Synchronizing jacking control system; It is characterized in that it also comprises: matching with PLC Hydraulic Synchronizing jacking control system is combined into the jacking counterforce device that jack provides support.
2. bridge jacking device as claimed in claim 1; It is characterized in that said jacking counterforce device is installed in the jacking counterforce device that carries the jacking counter-force on the abutment on original bridge bent cap, pier stud or abutment, planting reinforcing bar as jacking counter-force basic jacking counterforce device or metal construction suspension member.
3. bridge jacking device as claimed in claim 2 is characterized in that, said metal construction suspension member is installed in the web position that the jacking counterforce device that carries the jacking counter-force on the abutment is arranged in the flank or the T beam of plate-girder, case beam, and is connected with abutment through bar planting.
4. like the arbitrary described bridge jacking device of claim 1-3, it is characterized in that said jacking counterforce device can be removed and use repeatedly.
CN201120455140XU 2011-11-17 2011-11-17 Bridge jacking device Expired - Fee Related CN202337949U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201120455140XU CN202337949U (en) 2011-11-17 2011-11-17 Bridge jacking device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201120455140XU CN202337949U (en) 2011-11-17 2011-11-17 Bridge jacking device

Publications (1)

Publication Number Publication Date
CN202337949U true CN202337949U (en) 2012-07-18

Family

ID=46486647

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201120455140XU Expired - Fee Related CN202337949U (en) 2011-11-17 2011-11-17 Bridge jacking device

Country Status (1)

Country Link
CN (1) CN202337949U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104328743A (en) * 2014-11-24 2015-02-04 上海天演建筑物移位工程股份有限公司 Bridge jacking temporary counter-force support device and counter-force support method
CN110820605A (en) * 2019-11-07 2020-02-21 北京中交桥宇科技有限公司 Airtight nondestructive formula bridge jacking platform of hot melt adhesive

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104328743A (en) * 2014-11-24 2015-02-04 上海天演建筑物移位工程股份有限公司 Bridge jacking temporary counter-force support device and counter-force support method
CN110820605A (en) * 2019-11-07 2020-02-21 北京中交桥宇科技有限公司 Airtight nondestructive formula bridge jacking platform of hot melt adhesive

Similar Documents

Publication Publication Date Title
CN103216114A (en) Translation construction method for building
CN202324606U (en) U-shaped force bearing seat
CN202337949U (en) Bridge jacking device
CN204960289U (en) Builder's jack is encorbelmented whole combination of girder steel and can be had enough to meet need anchor assembly
CN102561392A (en) Structure for supporting construction elevator foundation on basement top plate and construction method thereof
CN206308702U (en) A kind of portable basis of derrick crane
CN203213019U (en) Long cantilever bent cap cast-in-place construction support system
CN101476330B (en) Thick and large-volume concrete elastic base and construction method thereof
CN202596148U (en) Reusable cantilever scaffold anchoring compression ring
CN202298465U (en) Bridge jacking system
CN103552911A (en) Movable hoisting apparatus and construction installation method used by same
CN202416339U (en) Fixed base for tower crane
CN201381517Y (en) Concrete elastic base for supporting large-scale gas turbine generator
CN213710401U (en) Can dismantle bottom plate support of steel bar quilting frame building carrier plate
CN202644407U (en) Demoulding device for bottom plate bracket of capping beam constructed by hoop method
CN204225503U (en) Large span steel truss high altitude bulk conversion beam moulding bed
CN202000266U (en) Supporting structure of bridge coping template
CN204238443U (en) A kind of detachable suspension column fastening devices
CN204199323U (en) For the positioning screw hole mould of pre-embedded bolt quick position
CN105480842A (en) Post-cast equipment supporting beam and construction method thereof
CN104060819A (en) Method for constructing shear wall by using typified forms and used typified forms
CN207209786U (en) The cast-in-place boom support monoblock type automatic disassembling device of falsework
CN114687567A (en) Ultrahigh heavy embedded part hanging construction tool and method
CN203247591U (en) Deep foundation pit steel support
CN201288329Y (en) Precision built-in steel mold of ultralong cluster anchor bolt

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120718

Termination date: 20141117

EXPY Termination of patent right or utility model