CN206173802U - System construction is collected with removing hanging flower basket to highway bridge floor runoff - Google Patents
System construction is collected with removing hanging flower basket to highway bridge floor runoff Download PDFInfo
- Publication number
- CN206173802U CN206173802U CN201621176752.4U CN201621176752U CN206173802U CN 206173802 U CN206173802 U CN 206173802U CN 201621176752 U CN201621176752 U CN 201621176752U CN 206173802 U CN206173802 U CN 206173802U
- Authority
- CN
- China
- Prior art keywords
- hanging basket
- cat ladder
- arm
- bolt hole
- fixed mount
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Handcart (AREA)
Abstract
The utility model belongs to the technical field of device for the system construction is collected to highway bridge floor runoff, the great technical problem of construction cost provides a system construction is collected with removing hanging flower basket to highway bridge floor runoff when solve adopting bridge inspect vehicle to carry out installation and the maintenance of highway bridge floor runoff collecting system, including the travelling car and installing the hanging flower basket on the travelling car, the hanging flower basket includes hangs basket, cat ladder and a hanging flower basket arm, hanging the basket and being the open cuboid structure of an upper surface, hang the left and right sides of basket and distinguish a vertical installation cat ladder, the one end of hanging flower basket arm is connected perpendicularly on the top of cat ladder, install the mount on the travelling car, the other end of hanging flower basket arm is installed respectively on the mount, and one side relative with the hanging flower basket on the travelling car is provided with the balancing weight. The utility model discloses simple structure, easy dismounting, repeatedly usable adopts the utility model discloses the construction is simple, and easy operation has reduced construction cost.
Description
Technical field
This utility model belongs to highway deck runoff collection system construction engineering device technique field, and in particular to a kind of
Highway deck runoff collection system construction moving hanging basket.
Background technology
For the installation and maintenance of the highway bridge floor drain pipe being open to traffic, traditional method is examined using bridge
Measuring car is installed and keeped in repair, though can guarantee that the safety of operating personnel and driving, using bridge inspection vehicle highway is carried out
Construction cost is larger when the installation and maintenance of deck runoff collection system.
The content of the invention
This utility model is installation and the dimension for solving to be carried out using bridge inspection vehicle highway deck runoff collection system
A kind of construction cost larger technical problem when repairing, there is provided highway deck runoff collection system construction moving hanging basket.
The technical solution adopted in the utility model is as follows:
A kind of highway deck runoff collection system construction moving hanging basket, including moving cart and installed in movement it is little
Hanging basket on car, the hanging basket includes Hanging Basket, cat ladder and hanging basket arm, and the Hanging Basket is the rectangular structure of a upper surface open,
The left and right sides of Hanging Basket is vertical respectively to install a cat ladder, and the top of cat ladder vertically connects one end of hanging basket arm;The moving cart
Upper mounting and fixing support, the fixed mount is a cuboid framework structure, and the height of the upper surface of fixed mount away from ground is more than at a high speed
The distance between the height of highway barrier, the length of fixed mount and two hanging basket arms match, the other end difference of the hanging basket arm
On fixed mount, the side relative with hanging basket is provided with balancing weight in moving cart.
One end that the hanging basket arm is connected with cat ladder is arranged at intervals with some bolt hole I, the top welding one of the cat ladder
Connecting plate, the connecting plate is made by channel-section steel, including base plate and biside plate, the base plate and biside plate of connecting plate respectively with climb
The top of ladder and the two sides welding of cat ladder, are arranged and the bolt hole I apertures identical on hanging basket arm on the biside plate of connecting plate
Bolt hole II, is provided with one and the bolt hole I apertures identical bolt hole II on hanging basket arm on the connecting plate, connecting plate passes through
Bolt I is fixedly connected with hanging basket arm.
One end that the hanging basket arm is connected with fixed mount is arranged at intervals with some bolt hole III, with hanging basket arm on fixed mount
Upper bolt hole III corresponding position arranges bolt hole IV, and bolt hole IV is identical with the aperture of bolt hole III, and hanging basket arm passes through
Bolt II is fixedly mounted on fixed mount.
The hanging basket arm and cat ladder are made using channel-section steel or angle steel.
The beneficial effects of the utility model:
(1)It is simple using this utility model construction, it is easy to operate, reduce construction cost.
(2)This utility model simple structure, low manufacture cost, and easy accessibility, can reuse.
(3)This utility model is applied to the construction of all of highway bridge floor draining, and installing in bridge floor pipeline also has
Very big application or reference value, applied range.
Description of the drawings
Fig. 1 is front view of the present utility model;
Fig. 2 is top view of the present utility model;
In figure:1- moving carts, 2- hanging basket arms, 3- cat ladders, 4- Hanging Baskets, 5- bolt I, 6- fixed mounts, 7- bolt II, 8- matches somebody with somebody
Pouring weight, 9- connecting plates.
Specific embodiment
As shown in Figure 1, 2, a kind of highway deck runoff collection system construction moving hanging basket, including moving cart 1
With the hanging basket in the moving cart 1, the hanging basket includes Hanging Basket 4, cat ladder 3 and hanging basket arm 2, and the Hanging Basket 4 is a upper table
The rectangular structure that face opens, the Hanging Basket includes operating platform and the guardrail being arranged on around operating platform, and the operation is put down
Platform includes the rectangular frame structure being welded by spacing of reinforcement and the bamboo slab rubber being laid in rectangular frame structure, described
Reinforcing bar lateral separation 45cm is arranged together.The left and right two ends of the Hanging Basket 4 are vertical respectively to install a cat ladder 3, the cat ladder 3 and extension
The position up and down at the left and right two ends of basket 4 is fixedly connected by U-shaped lock, and the other end of cat ladder 3 is respectively perpendicular one hanging basket arm 2 of installation;
The hanging basket arm 2 is made using channel-section steel or angle steel, and hanging basket arm 2 is arranged at intervals with some bolt hole I with one end that cat ladder 3 is connected,
The cat ladder 3 includes two montants and the cross bar being disposed between two montants, and two montant is made using channel-section steel, two montants
Top weld a connecting plate 9, the connecting plate 9 is made using channel-section steel, including base plate and biside plate, the base plate of connecting plate 9 and
Biside plate is welded respectively with the top of cat ladder 3 and two sides of cat ladder 3, on the biside plate of connecting plate 9 in setting and hanging basket arm 2
Bolt hole I apertures identical bolt hole II, is provided with one and the bolt hole I apertures identical on hanging basket arm 2 on the connecting plate 9
Bolt hole II, bolt I5 sequentially pass through bolt hole I and bolt hole II is fixedly connected connecting plate 9 with hanging basket arm 2.On hanging basket arm 2
Being provided with some bolt hole I can conveniently adjust the distance of Hanging Basket and construction point under cat ladder.
Mounting and fixing support 6 in the moving cart 1, the fixed mount 6 be a cuboid framework structure, fixed mount 6 it is upper
Height of the surface far from ground more than freeway guardrail height, the distance between the length of fixed mount 6 and two hanging basket arms 2 phase
Match somebody with somebody, the other end of the hanging basket arm 2 is separately mounted on fixed mount 6, one end interval that the hanging basket arm 2 is connected with fixed mount 6
Some bolt hole III are provided with, position corresponding with the upper bolt hole III of hanging basket arm 2 on fixed mount 6 arranges bolt hole IV, spiral shell
Keyhole IV is identical with the aperture of bolt hole III, and bolt II7 sequentially passes through bolt hole III and bolt hole IV by fixed mount 6 and hanging basket
Arm 2 is fixedly connected.To prevent moving cart 1 from toppling over to hanging basket side, the side relative with hanging basket is provided with and matches somebody with somebody in moving cart 1
Pouring weight 8.
It is of the present utility model to install and use:
(1)The assembling of hanging basket
Hanging basket arm and cat ladder are bolted, then the position up and down at Hanging Basket or so two ends is locked by U-shaped respectively
It is fixedly connected with the lower end of cat ladder.
(2)The installation of hanging basket and moving cart
Shift moving cart onto outside guard rail position first, hanging basket is steadily sling with crane, move closer to dolly, make hanging basket
Bolt hole on arm aligns with the bolt hole on the fixed mount in moving cart, is connected with immediately after, and tightens.It is mobile
Hanging basket carries out the installation of balancing weight according to design after being completed, then moving cart is checked, confirms each part connection
It is whether solid and reliable, if to be moved easily and operate.
(3)Hanging basket must conscientiously be checked that confirm that each part is solid and reliable, anchor is normal, hangs after installing
In the key portion's protection net firmly without breakage after, workmen enter construction hanging basket in, then by operation instrument(Hand-held impact brill,
Expansion bolt etc.)It is transported to safe operation range, and fixation.
(4)Workman stands in Hanging Basket, and PE feed pipes circuit is carried out into substantially setting-out, ejects circuit with cotton rope or the line of ink marker and walks
To, then bored with hand-held impact and be fixed the perforating of support along pvc pipe line direction, then pacified fixed support with expansion bolt
Dress is firm.
This utility model simple structure, low manufacture cost, and easy accessibility, can reuse.It is new using this practicality
Type construction is simple, easy to operate, reduces construction cost.
Claims (4)
1. a kind of highway deck runoff collection system construction moving hanging basket, it is characterised in that:Including moving cart(1)With
Installed in moving cart(1)On hanging basket, the hanging basket include Hanging Basket(4), cat ladder(3)With hanging basket arm(2), the Hanging Basket(4)
For the rectangular structure of a upper surface open, Hanging Basket(4)The left and right sides respectively vertical a cat ladder is installed(3), cat ladder(3)Top
The vertical connection hanging basket arm in end(2)One end;The moving cart(1)Upper mounting and fixing support(6), the fixed mount(6)For a length
Cube frame structure, fixed mount(6)Height of the upper surface away from ground more than freeway guardrail height, fixed mount(6)'s
Length and two hanging basket arms(2)The distance between match, the hanging basket arm(2)The other end be separately mounted to fixed mount(6)On,
Moving cart(1)The upper side relative with hanging basket is provided with balancing weight(8).
2. a kind of highway deck runoff collection system construction moving hanging basket according to claim 1, its feature exists
In:The hanging basket arm(2)With cat ladder(3)Connected one end is arranged at intervals with some bolt hole I, the cat ladder(3)Top weldering
Connect a connecting plate(9), the connecting plate(9)It is made by channel-section steel, including base plate and biside plate, connecting plate(9)Base plate and
Biside plate respectively with cat ladder(3)Top and cat ladder(3)Two sides welding, connecting plate(9)Biside plate on arrange and hanging basket
Arm(2)On bolt hole I apertures identical bolt hole II, connecting plate(9)By bolt I(5)With hanging basket arm(2)It is fixedly connected.
3. a kind of highway deck runoff collection system construction moving hanging basket according to claim 1 and 2, its feature
It is:The hanging basket arm(2)With fixed mount(6)Connected one end is arranged at intervals with some bolt hole III, fixed mount(6)It is upper with
Hanging basket arm(2)Upper bolt hole III corresponding position arranges bolt hole IV, and bolt hole IV is identical with the aperture of bolt hole III, hangs
Basket arm(2)By bolt II(7)It is fixedly mounted on fixed mount(6)On.
4. a kind of highway deck runoff collection system construction moving hanging basket according to claim 3, its feature exists
In:The hanging basket arm(2)And cat ladder(3)Made using channel-section steel or angle steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621176752.4U CN206173802U (en) | 2016-10-27 | 2016-10-27 | System construction is collected with removing hanging flower basket to highway bridge floor runoff |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621176752.4U CN206173802U (en) | 2016-10-27 | 2016-10-27 | System construction is collected with removing hanging flower basket to highway bridge floor runoff |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206173802U true CN206173802U (en) | 2017-05-17 |
Family
ID=58682755
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621176752.4U Active CN206173802U (en) | 2016-10-27 | 2016-10-27 | System construction is collected with removing hanging flower basket to highway bridge floor runoff |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206173802U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109505309A (en) * | 2019-01-07 | 2019-03-22 | 浙江大学城市学院 | A kind of shift system of piping lane segment and the piping lane installation method of application shift system |
CN109763423A (en) * | 2018-12-24 | 2019-05-17 | 中建三局集团有限公司 | A kind of adjustable split-type movable hanging basket and operating method for bridge maintenance |
CN110847031A (en) * | 2019-11-28 | 2020-02-28 | 北京市政路桥股份有限公司 | Movable hanging basket for bridge construction |
CN113322787A (en) * | 2021-06-22 | 2021-08-31 | 中交二公局东萌工程有限公司 | Construction process of bridge deck runoff collecting device and formwork supporting device thereof |
-
2016
- 2016-10-27 CN CN201621176752.4U patent/CN206173802U/en active Active
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109763423A (en) * | 2018-12-24 | 2019-05-17 | 中建三局集团有限公司 | A kind of adjustable split-type movable hanging basket and operating method for bridge maintenance |
CN109505309A (en) * | 2019-01-07 | 2019-03-22 | 浙江大学城市学院 | A kind of shift system of piping lane segment and the piping lane installation method of application shift system |
CN109505309B (en) * | 2019-01-07 | 2023-09-26 | 浙江大学城市学院 | Pipe gallery segment displacement system and pipe gallery installation method using same |
CN110847031A (en) * | 2019-11-28 | 2020-02-28 | 北京市政路桥股份有限公司 | Movable hanging basket for bridge construction |
CN113322787A (en) * | 2021-06-22 | 2021-08-31 | 中交二公局东萌工程有限公司 | Construction process of bridge deck runoff collecting device and formwork supporting device thereof |
CN113322787B (en) * | 2021-06-22 | 2023-03-03 | 中交二公局东萌工程有限公司 | Construction process of bridge deck runoff collecting device and formwork supporting device thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206173802U (en) | System construction is collected with removing hanging flower basket to highway bridge floor runoff | |
CN201132738Y (en) | Acoustical barrier column tool car | |
CN108316152A (en) | A kind of high pier capping beam construction mobile formwork and its construction technology | |
CN107043070A (en) | A kind of Feeding System of Urban Rail Transit equipment installs special portal frame | |
JP3318549B2 (en) | Working scaffold for existing bridge | |
CN208995936U (en) | S type steel box girder of cable stayed bridge on across ground rail traffic slides mounting bracket | |
CN205529923U (en) | Sliding device of demolising of beiLei beam | |
CN206396643U (en) | A kind of bridge side duct installs removable job platform | |
CN111287498B (en) | Protective shed frame for construction of overhead bridge box girder crossing railway and erection method | |
CN211736310U (en) | Movable hanging basket for bridge | |
CN204212065U (en) | Bridge crossing anticollision barrier punching block erection equipment | |
CN216304427U (en) | Road and bridge construction is with safe construction platform | |
CN113738125B (en) | Construction method for lifting limited-space large-span steel structure of station house under line | |
CN113215978B (en) | Construction method for laying pipeline along with bridge | |
CN212245942U (en) | Special trolley for mounting movable adjustable sliding contact line | |
CN210151602U (en) | Railway operation line-crossing highway beam body dismantling beam bottom protection platform | |
CN204038917U (en) | Dismountable external hanging service platform | |
CN204185146U (en) | Construction of Steel Structure overhang crane between skyscraper two tall buildings | |
CN210049105U (en) | Self-propelled bridge formwork operation trolley | |
CN112726416A (en) | Support structure meeting field construction security and construction method | |
CN219508371U (en) | External embedded part of highway bridge guardrail and pipeline mounting rack | |
CN204959505U (en) | Single line roof beam security platform | |
CN203923917U (en) | Job platform at the bottom of a kind of packaged type bridge | |
CN219951910U (en) | Operation platform suitable for bored concrete pile well head detects operation | |
CN217479995U (en) | Cantilever beam hanging basket construction assembled safety platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |