CN205917839U - Connected node of wallboard and floor - Google Patents

Connected node of wallboard and floor Download PDF

Info

Publication number
CN205917839U
CN205917839U CN201620779069.3U CN201620779069U CN205917839U CN 205917839 U CN205917839 U CN 205917839U CN 201620779069 U CN201620779069 U CN 201620779069U CN 205917839 U CN205917839 U CN 205917839U
Authority
CN
China
Prior art keywords
floor
side fascia
connecting node
sleeve
wallboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620779069.3U
Other languages
Chinese (zh)
Inventor
陈定球
俞大有
刘斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuyou Zhizao Technology Investment Co., Ltd
Original Assignee
China Mingsheng Drawin Technology Investment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mingsheng Drawin Technology Investment Co Ltd filed Critical China Mingsheng Drawin Technology Investment Co Ltd
Priority to CN201620779069.3U priority Critical patent/CN205917839U/en
Application granted granted Critical
Publication of CN205917839U publication Critical patent/CN205917839U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model belongs to the technical field of building engineering, a connected node of wallboard and floor is disclosed, including the floor of level setting and the side fascia of vertical setting, the floor sets up side fascia upper portion, the one end of floor is encorbelmented to the side fascia outside, side fascia upper portion is provided with the connecting piece, be provided with pre -buried subassembly in the floor, pre -buried subassembly connects into whole with the connecting piece, the floor sets up pre -buried subassembly department and has seted up the operation mouth, and the floor bottom that is located the side fascia outside is provided with the drip. The utility model discloses need not cast in situ concrete in assembling process, the cost saving, construction speed is fast, and floor and side fascia connect into whole through vertical connecting piece and pre -buried subassembly, have increased the taut ability of connection of this node, are favorable to the conduction of doing all can each other, simultaneously, encorbelment the one end of floor to the side fascia outside to the waterproof problem of concatenation seam is solved to the structural waterproof structure on the floor, satisfies the building quality and the specifications of building.

Description

A kind of wallboard and the connecting node of floor
Technical field
This utility model belongs to construction engineering technical field and in particular to the connecting node of a kind of wallboard and floor.
Background technology
Assembled architecture is built with respect to conventional steel bar concrete field cast-in-place formula, a technical beyond doubt much progress, The prefabricated components factorial praluction of assembled architecture, Assembling, thus can factory normalization produce, quality controllable, efficiently soon Victory, material economy no wastes, production scene and job site non-environmental-pollution.But, in prior art, pre- in assembled architecture In the assembling process of product, node is still had to need using cast-in-place, such as the connection of shear wall and floor, for stable connection, building Plate would generally adopt laminated floor slab, pours one layer of in-situ layer again on the top of precast floor slab, in installation process, the overlapping such as need building The installation of next step prefabricated component could be carried out after the in-situ layer solidification of plate on this basis, so have a strong impact on speed of application, fall Low efficiency of construction, cast in situs simultaneously will inevitably carry out the operation such as formwork, concreting, cause job site to complicate, make Construction cost is increased while becoming potential safety hazard.
In sum, thus need that a kind of speed of application of exploitation is fast, the connection of cost savings, the wallboard being connected firmly and floor badly Node.
Utility model content
The purpose of this utility model be provide that a kind of speed of application is fast, cost savings, the wallboard being connected firmly and floor company Connect node.
Above-mentioned purpose is to be achieved through the following technical solutions: the connecting node of a kind of wallboard and floor, including being horizontally disposed with Floor and vertically arranged Side fascia, described floor is arranged on described Side fascia top, one end of described floor encorbelment to Outside Side fascia, described Side fascia top is provided with connector, is provided with fastener inserts in described floor, described fastener inserts with Connector connection is integral, offers gathering hole, the floor slab bottoms outside Side fascia at described floor setting fastener inserts It is provided with drip.It is arranged such, Side fascia and floor pass through connector and fastener inserts form and are reliably connected, and structure is more firm Gu.The setting of gathering hole makes working place bigger, is more beneficial for connector and connects operation construction during fastener inserts.By floor One end encorbelment to Side fascia, be so conducive on floor constructional waterproofing construction, that is, in the building outside Side fascia Plate bottom arranges drip, so, solves the waterproof problem of floor bottom splicing seams.Certainly, after Side fascia and floor dropping place, Last layer marine glue need to be broken in the outside of underfloor splicing seams.This utility model without cast-in-place concrete, becomes in assembling process This saving, speed of application is fast, short construction period, and floor and Side fascia connect integral, increase by connector and fastener inserts The connection tension ability of this node, is conducive to the conduction of power each other, is encorbelmented to outside Side fascia in one end of floor meanwhile Side, and the waterproof problem solving splicing seams is constructed in constructional waterproofing on floor, meet construction quality and the technical performance of building.
Further, described connector includes screw rod and is arranged on anchoring piece on screw rod, and described fastener inserts are to connect Box, described connection box at least one side forms gathering hole with connecting outside floor, and described connection cassette bottom portion is provided with through hole, and described screw rod is worn Cross through hole and stretch in described connection box, described screw rod is with to be connected box with bolts and fixed by nut screwing clamping.Construction In engineering, after Side fascia dropping place, control the position of floor during floor dropping place so that screw rod passes through through hole insertion pre-buried In the connection box in floor, then fixed with nut screwing clamping, realize the connection of three.Connect box pre-buried during, its Simultaneously leaving certain gaps uncovered by the economic plan, and breach connects with outside floor, so, in addition need not arrange gathering hole in the prefabrication process of floor, and After filling paste in breach, the position that setting connects box forms hard point, and the fastener inserts making and screw rod are connected firmly.Screw rod It is provided with anchoring piece, anchor force in lower Side fascia for the screw rod can be effectively increased, improve the knot that screw rod is connected with lower Side fascia Structure intensity, substantially increases the resistance to drawing ability of screw rod, can effectively prevent under external force screw rod in lower Side fascia Axially and radially move, when especially fastener inserts and screw rod are tightened fixing by rotation nut, so, screw rod and fastener inserts Connect is more firm.Connecting cassette bottom portion can be concordant with wallboard bottom surface, or connects box in wallboard, and wallboard is also reserved logical Hole, and fixed by nut screwing clamping.
Further, described connector includes sleeve and is located at fixture on sleeve, and described sleeve is provided with female thread, institute Stating fastener inserts is to connect box, and described connection box at least one side forms gathering hole, described connection box and sleeve with connecting outside floor With bolts.
Further, described connection cassette bottom portion is provided with through hole, and described bolt passes through through hole to insert in described sleeve.Bolt is worn Cross jack hole insert described sleeve, then tighten bolt so that connector be firmly connected.
Further, described fixture is connected with sleeve square crossing.It is arranged such, sleeve can be effectively increased in Side fascia Anchor force, improve the structural strength that sleeve is connected with Side fascia, substantially increase the resistance to drawing ability of sleeve, can be effective Prevent sleeve axially and radially moving in Side fascia under external force, such as sleeve and fastener inserts fastening are connected by swivel bolt When connecing.
Further, it is filled with slurry in described connection box.It is arranged such, on the one hand can solve to lead to because of reservation operations mouth Unsightly problem, on the other hand, after the slurry in gathering hole solidifies, can play the effect of fixing bolt, it is to avoid using year Limit bolt looseness long or under the influence of external force.Now filling paste has no effect on construction speed, carries out without waiting for slurry hardening again The installation of next prefabricated component node.Certainly, while filling paste, the jack hole of floor splice ends is filled in gathering hole, so Node is more firm.
Further, Side fascia and the contact surface of floor are provided with sbs self-adhering type modified bituminous pitch coiled material.It is arranged such, increase Plus the waterproof effect of splicing seams, effectively prevent water along the Mosaic face seepage of Side fascia and floor.
Further, described Side fascia upper outside carries out chamfered.It is arranged such, strengthen the splicing of floor bottom further The waterproof effect of seam, the part rainwater of floor bottom splicing seams can be along the chamfering of lower Side fascia to outdoor outflow, described chamfering Can be fillet or right angle, marine glue is set preferably at chamfering.
Further, described Side fascia and the contact surface of floor are embedded with elastic water-proof body.Prefabricated mistake in wallboard and/or floor Cheng Zhong, elastic water-proof body is embedded in its Mosaic face, and after this utility model completes assembled docking, wallboard and floor are by water-proof elastic Body is tightly squeezed in the Mosaic face of the two, so, can prevent water along the Mosaic face seepage of wallboard and floor.Certainly, can be in its spelling Junction is embedded with multiple elastic water-proof bodies.Preferably, can be embedding in the contact surface setting groove with elastic water-proof body, elastic water-proof body side Enter the Mosaic face of floor or wallboard, opposite side is squeezed in corresponding wallboard or the groove of floor Mosaic face, so both can play Waterproof effect, nor affects on the smooth of the two contact surface.
Further, described Side fascia and the stitching portion of floor are provided with waterproof steel plate, and adjacent waterproof steel plate welding is integral. It is arranged such, waterproof steel plate now plays closing or the effect blocking Mosaic face, can effectively prevent water along Mosaic face seepage.When So, by polisher, welding position can be polished flat so as to more attractive in appearance after waterproof steel plate welding.
Brief description
The accompanying drawing constituting a part of the present utility model is used for providing further understanding to of the present utility model, and this practicality is new The schematic description and description of type is used for explaining this utility model, does not constitute to improper restriction of the present utility model.
Wallboard respectively involved by a kind of embodiment of this utility model for Fig. 1 and Fig. 2 is cutd open with the connecting node of floor View;
Fig. 3 is the top view of involved wallboard in Fig. 1 and the connecting node of floor.
In figure:
1 floor, 2 Side fascia, 3 drip 4 gathering hole
5 screw rod, 6 anchoring piece 7 connects box 8 nut
9 bolt, 10 sleeve, 11 fixture 12 slurry
13 chamferings
Specific embodiment
Below in conjunction with the accompanying drawings this utility model is described in detail, the description of this part is only exemplary and explanatory, Should not there is any restriction effect to protection domain of the present utility model.Additionally, those skilled in the art's retouching according to presents State, respective combination can be carried out to the feature in embodiment in presents and in different embodiment.
This utility model embodiment is as follows, with reference to Fig. 1~3, a kind of wallboard and the connecting node of floor 1, sets including level The floor 1 put and vertically arranged Side fascia 2, described floor 1 is arranged on described Side fascia 2 top, one end of described floor 1 Encorbelment to Side fascia 2, described Side fascia 2 top is provided with connector, is provided with fastener inserts in described floor 1, described Fastener inserts are connected integral with connector, offer gathering hole 4, outside Side fascia 2 at described floor 1 setting fastener inserts Floor 1 bottom of side is provided with drip 3.It is arranged such, Side fascia 2 and floor 1 pass through connector and fastener inserts formation can By connecting, structure is more firm.The setting of gathering hole 4 makes working place bigger, is more beneficial for connector and connects fastener inserts When operation construction.Encorbelmented to Side fascia 2 in one end of floor 1, be so conducive to constructional waterproofing construction on floor 1, I.e. in the floor 1 bottom setting drip 3 positioned at Side fascia 2 outside, so, solve the waterproof problem of floor 1 bottom splicing seams. Certainly, after Side fascia 2 and floor 1 dropping place, last layer marine glue need to be broken in the outside of 1 time splicing seams of floor.This utility model It is mainly used in building top layer, without cast-in-place concrete in assembling process, cost savings, speed of application is fast, short construction period, Floor 1 and Side fascia 2 are integral by vertical connector connection, increased the connection tension ability of this node, are conducive to mutually Between power conduction, encorbelmented to Side fascia 2 in one end of floor 1, and in constructional waterproofing construction solution on floor 1 meanwhile The certainly waterproof problem of splicing seams, meets construction quality and the technical performance of building.
On the basis of above-described embodiment, in another embodiment of this utility model, such as Fig. 2, described connector includes screw rod 5 And it is arranged on anchoring piece 6 on screw rod 5, described fastener inserts are to connect box 7, outside described connection box 7 at least one side and floor 1 Connection forms gathering hole 4, and described connection box 7 bottom is provided with through hole, and described screw rod 5 passes through through hole and stretches in described connection box 7, Described screw rod 5 tightens fixation with being connected box 7 and connecting using bolt 9 and pass through nut 8.In construction work, after Side fascia 2 dropping place, Control the position of floor 1 so that screw rod 5 passes through through hole insertion to be embedded in the connection box in floor 1 during floor 1 dropping place In 7, then tighten fixation with nut 8, realize the connection of three.Connect box 7 pre-buried during, its one side leaving certain gaps uncovered by the economic plan, And breach and floor 1 is outer connect, so, in the prefabrication process of floor 1, need not in addition gathering hole 4 be set, and work as and fill out in breach After filling slurry 12, the position that setting connects box 7 forms hard point, and the fastener inserts making are connected firmly with screw rod 5.Set on screw rod 5 There is anchoring piece 6, anchor force in lower Side fascia 2 for the screw rod 5 can be effectively increased, improve the knot that screw rod 5 is connected with lower Side fascia 2 Structure intensity, substantially increases the resistance to drawing ability of screw rod 5, can effectively prevent under external force screw rod 5 in lower Side fascia 2 Axially and radially move, when especially fastener inserts and screw rod 5 are tightened fixing by rotation nut 8, so, screw rod 5 with pre-buried It is more firm that assembly also connects.Connecting box 7 bottom can be concordant with wallboard bottom surface, or connects box 7 in wallboard, wallboard Reserved through hole, and fixation is tightened by nut 8.
On the basis of above-described embodiment, in another embodiment of this utility model, such as Fig. 1, described connector includes sleeve 10 and be located at fixture 11 on sleeve 10, described sleeve 10 is provided with female thread, and described fastener inserts are to connect box 7, described Connect connect outer with floor 1 of box 7 at least one side and form gathering hole 4, described connection box 7 is connected using bolt 9 with sleeve 10.
On the basis of above-described embodiment, in another embodiment of this utility model, described connection box 7 bottom is provided with through hole, Described bolt 9 passes through through hole to insert in described sleeve 10.Bolt 9 is passed through jack hole to insert described sleeve 10, then tightens spiral shell Bolt 9 so that connector be firmly connected.
On the basis of above-described embodiment, in another embodiment of this utility model, such as Fig. 1, described fixture 11 and sleeve 10 square crossings connect.It is arranged such, anchor force in Side fascia 2 for the sleeve 10 can be effectively increased, improve sleeve 10 with outward The structural strength that wallboard 2 connects, substantially increases the resistance to drawing ability of sleeve 10, can effectively prevent sleeve under external force 10 axially and radially moving in Side fascia 2, when such as sleeve 10 and fastener inserts are fastenedly connected by swivel bolt 9.
On the basis of above-described embodiment, in another embodiment of this utility model, such as Fig. 1~3, fill out in described connection box 7 It is filled with slurry 12.It is arranged such, on the one hand can solve the unsightly problem leading to because of reservation operations mouth 4, on the other hand, work as operation After slurry 12 solidification in mouthfuls 4, the effect of fixing bolt 9 can be played, it is to avoid service life bolt 9 pine long or under the influence of external force Dynamic.Now filling paste 12 has no effect on construction speed, hardens without waiting for slurry 12 and carries out the peace of next prefabricated component node again Dress.Certainly, while filling paste 12, the jack hole of floor 1 splice ends is filled in gathering hole 4, such node is more firm.
On the basis of above-described embodiment, in another embodiment of this utility model, on the contact surface of Side fascia 2 and floor 1 It is provided with sbs self-adhering type modified bituminous pitch coiled material.It is arranged such, increase the waterproof effect of splicing seams, effectively prevent water along Side fascia 2 Mosaic face seepage with floor 1.
On the basis of above-described embodiment, in another embodiment of this utility model, such as Fig. 1 and Fig. 2, on described Side fascia 2 Carry out chamfering 13 outside portion to process.It is arranged such, strengthens the waterproof effect of floor 1 bottom splicing seams further, floor 1 bottom is spelled The part rainwater of seam can along the chamfering 13 of lower Side fascia 2 to outdoor outflow, described chamfering 13 can be fillet or Right angle, arranges marine glue preferably at chamfering 13.
On the basis of above-described embodiment, in another embodiment of this utility model, described Side fascia 2 contact with floor 1 Face is embedded with elastic water-proof body.In the prefabrication process of wallboard and/or floor 1, elastic water-proof body is embedded in its Mosaic face, when this reality Complete after assembled docking with new, water-proof elastomer is tightly squeezed in the Mosaic face of the two by wallboard and floor 1, so, can prevent Sealing is along the Mosaic face seepage of wallboard and floor 1.Certainly, multiple elastic water-proof bodies can be embedded with its Mosaic face.Preferably, can with The contact surface setting groove of elastic water-proof body, elastic water-proof body side embeds the Mosaic face of floor 1 or wallboard, and opposite side is squeezed into In the groove of corresponding wallboard or floor 1 Mosaic face, so both can play waterproof effect, nor affect on the flat of the two contact surface Whole.
On the basis of above-described embodiment, in another embodiment of this utility model, the splicing of described Side fascia 2 and floor 1 Place is provided with waterproof steel plate, and adjacent waterproof steel plate welding is integral.It is arranged such, waterproof steel plate now plays closing or blocks The effect of Mosaic face, can effectively prevent water along Mosaic face seepage.Certainly, can be by polisher by weld part after waterproof steel plate welding Position polishes flat so as to more attractive in appearance.
The above is only preferred implementation of the present utility model it is noted that common skill for the art For art personnel, on the premise of without departing from this utility model principle, some improvements and modifications can also be made, these improve and Retouching also should be regarded as protection domain of the present utility model.

Claims (10)

1. the connecting node of a kind of wallboard and floor, including horizontally disposed floor and vertically arranged Side fascia, described building Plate is arranged on described Side fascia top it is characterised in that encorbelmenting to Side fascia in one end of described floor, on described Side fascia Portion is provided with connector, is provided with fastener inserts in described floor, and described fastener inserts are connected integral, described building with connector Gathering hole is offered, the floor slab bottoms outside Side fascia are provided with drip at plate setting fastener inserts.
2. wallboard according to claim 1 and floor connecting node it is characterised in that described connector include screw rod with And it is arranged on anchoring piece on screw rod, described fastener inserts are to connect box, and described connection box at least one side connects shape with outside floor Become gathering hole, described connection cassette bottom portion is provided with through hole, described screw rod passes through through hole and stretches in described connection box, described screw rod with Connection box is with bolts and is fixed by nut screwing clamping.
3. wallboard according to claim 1 and floor connecting node it is characterised in that described connector include sleeve with And it is located at fixture on sleeve, described sleeve is provided with female thread, and described fastener inserts are to connect box, described connection box at least Face forms gathering hole with connecting outside floor, and described connection box is with bolts with sleeve.
4. wallboard according to claim 3 and floor connecting node it is characterised in that described connection cassette bottom portion be provided with logical Hole, described bolt passes through through hole to insert in described sleeve.
5. the connecting node of the wallboard according to claim 3 or 4 and floor is it is characterised in that described fixture and sleeve Square crossing connects.
6. the connecting node of the wallboard according to claim 2~4 any one and floor is it is characterised in that described connection It is filled with slurry in box.
7. the wallboard according to Claims 1 to 4 any one and floor connecting node it is characterised in that Side fascia with Sbs self-adhering type modified bituminous pitch coiled material is provided with the contact surface of floor.
8. wallboard according to claim 6 and the connecting node of floor are it is characterised in that described Side fascia upper outside is entered Row chamfered.
9. the connecting node of wallboard according to claim 1 and floor is it is characterised in that connecing of described Side fascia and floor Contacting surface is embedded with elastic water-proof body.
10. the connecting node of wallboard according to claim 1 and floor is it is characterised in that described Side fascia and floor Stitching portion is provided with waterproof steel plate, and adjacent waterproof steel plate welding is integral.
CN201620779069.3U 2016-07-22 2016-07-22 Connected node of wallboard and floor Active CN205917839U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620779069.3U CN205917839U (en) 2016-07-22 2016-07-22 Connected node of wallboard and floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620779069.3U CN205917839U (en) 2016-07-22 2016-07-22 Connected node of wallboard and floor

Publications (1)

Publication Number Publication Date
CN205917839U true CN205917839U (en) 2017-02-01

Family

ID=57873777

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620779069.3U Active CN205917839U (en) 2016-07-22 2016-07-22 Connected node of wallboard and floor

Country Status (1)

Country Link
CN (1) CN205917839U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109306758A (en) * 2018-11-01 2019-02-05 沈阳建筑大学 Prefabricated plate superposed type floor connector and preparation method thereof and construction method
CN110289570A (en) * 2019-06-27 2019-09-27 中国二十二冶集团有限公司 Electrical and light current avoids the pre-buried method that misplaces
CN111535447A (en) * 2020-04-02 2020-08-14 哈尔滨工业大学(深圳)(哈尔滨工业大学深圳科技创新研究院) Prefabricated concrete prefabricated house and corner connecting technology
CN118148260A (en) * 2024-05-13 2024-06-07 北京市建筑工程研究院有限责任公司 Dry-type connection structure and connection method for cantilever component and vertical component

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109306758A (en) * 2018-11-01 2019-02-05 沈阳建筑大学 Prefabricated plate superposed type floor connector and preparation method thereof and construction method
CN110289570A (en) * 2019-06-27 2019-09-27 中国二十二冶集团有限公司 Electrical and light current avoids the pre-buried method that misplaces
CN111535447A (en) * 2020-04-02 2020-08-14 哈尔滨工业大学(深圳)(哈尔滨工业大学深圳科技创新研究院) Prefabricated concrete prefabricated house and corner connecting technology
CN118148260A (en) * 2024-05-13 2024-06-07 北京市建筑工程研究院有限责任公司 Dry-type connection structure and connection method for cantilever component and vertical component

Similar Documents

Publication Publication Date Title
CN104563288B (en) Reinforced concrete frame gridding slab prefabricated energy-saving house
CN205917838U (en) Balcony board installation node
CN205917839U (en) Connected node of wallboard and floor
CN104975652B (en) A kind of precast concrete docks attachment structure
CN206034631U (en) Connected node of wallboard and floor
CN205604473U (en) Assembled shear force wall tooth's socket formula connection structure who combines coincide floor
CN107460954A (en) A kind of post-tensioned prestressing assembling concrete frame energy dissipation component system and construction method
CN205917863U (en) Connected node of wallboard and floor
CN108060746A (en) A kind of prefabricated PC concrete large-span frame system and its construction method
CN206189455U (en) Piping lane
CN207003634U (en) A kind of balcony slab installs node
CN107119799A (en) The prestressing force assembling type node construction and its construction method of beam-ends friction energy-dissipating
CN108005304A (en) A kind of prefabricated PC concrete frame frame system and its construction method
CN202611012U (en) Assembly type concrete shear wall edge member connection structure
CN207110083U (en) Assembled architecture system
CN112342911A (en) Tensioning and anchoring device suitable for slow-bonding prestressed steel strand
CN205662838U (en) Prestressing force joint construction of pier is assembled to prefabricated segment
CN206034662U (en) Connected node of wallboard and floor
CN108951847A (en) A kind of Precast Concrete Frame system and its construction method based on UHPC
CN209211748U (en) A kind of structure node of assembled ceiling radiating system
CN206128281U (en) Balcony board installation node
CN207003685U (en) A kind of connecting node of Side fascia and floor
CN205917873U (en) Connected node of prefab
CN206034624U (en) Balcony installation node
CN205444571U (en) Wallboard connected node

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Nanning Zhongmin zhuyou Intelligent Manufacturing Technology Co., Ltd

Assignor: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT CO., LTD.

Contract record no.: X2019430000004

Denomination of utility model: Connected node of wallboard and floor

Granted publication date: 20170201

License type: Common License

Record date: 20191105

EE01 Entry into force of recordation of patent licensing contract

Assignee: Xiangxi Zhongmin zhuyou Technology Co., Ltd

Assignor: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT CO., LTD.

Contract record no.: X2020430000002

Denomination of utility model: Connected node of wallboard and floor

Granted publication date: 20170201

License type: Common License

Record date: 20200305

EE01 Entry into force of recordation of patent licensing contract
CP03 Change of name, title or address

Address after: 5 / F, office building 2, Zhongmin zhuyou Co., Ltd., No. 10, Zhongshi Road, shaping street, Kaifu District, Changsha City, Hunan Province, 410000

Patentee after: Zhuyou Zhizao Technology Investment Co., Ltd

Address before: 410205 comprehensive building in Hunan province Changsha Kaifu District, No. 30 Xingang Road, Changsha Jinxia bonded logistics center room 3005

Patentee before: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT Ltd.

CP03 Change of name, title or address
EE01 Entry into force of recordation of patent licensing contract

Assignee: Nantong Zhongmin zhuyou Zhizao Technology Co., Ltd

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2020980007488

Denomination of utility model: A kind of joint between wall panel and floor

Granted publication date: 20170201

License type: Common License

Record date: 20201105

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hunan Yuanfeng Construction Engineering Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980000884

Denomination of utility model: A kind of joint between wall panel and floor

Granted publication date: 20170201

License type: Common License

Record date: 20210203

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hunan Hailong Construction Engineering Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980001039

Denomination of utility model: A kind of joint between wall panel and floor

Granted publication date: 20170201

License type: Common License

Record date: 20210207

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Henan YingYuan Construction Service Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980001160

Denomination of utility model: A kind of joint between wall panel and floor

Granted publication date: 20170201

License type: Common License

Record date: 20210218

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Henan guochi Construction Service Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980001282

Denomination of utility model: A kind of joint between wall panel and floor

Granted publication date: 20170201

License type: Common License

Record date: 20210225

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Linzhou Hongen Construction Service Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980001340

Denomination of utility model: A connection node between wallboard and floor

Granted publication date: 20170201

License type: Common License

Record date: 20210302