CN205743934U - Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis - Google Patents

Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis Download PDF

Info

Publication number
CN205743934U
CN205743934U CN201620760973.XU CN201620760973U CN205743934U CN 205743934 U CN205743934 U CN 205743934U CN 201620760973 U CN201620760973 U CN 201620760973U CN 205743934 U CN205743934 U CN 205743934U
Authority
CN
China
Prior art keywords
inverted arch
reinforcing bar
travelling wheel
bearing frame
self
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620760973.XU
Other languages
Chinese (zh)
Inventor
王悦
王清江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Technology and Business Institute
Original Assignee
Chongqing Technology and Business Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Technology and Business Institute filed Critical Chongqing Technology and Business Institute
Priority to CN201620760973.XU priority Critical patent/CN205743934U/en
Application granted granted Critical
Publication of CN205743934U publication Critical patent/CN205743934U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a kind of self-propelled tunnel inverted arch reinforcing bar spelling and chassis is installed, including rectangle bearing frame, driving, crane beam, travelling wheel and a spike;Rectangle bearing frame is rectangular frame structure, and crane beam is installed between two crossbeams at rectangle bearing frame top and can be along this cross beam movement, and described driving is installed on crane beam and can move along crane beam;Described travelling wheel is located at the lower end of each column of rectangle bearing frame, and a spike is arranged with travelling wheel one_to_one corresponding;This device simple structure, easy to use, during use, first mobile device postpones to specific bit, again a spike is supported on ground, stabilising arrangement, afterwards, transports to installation site by the prefabricated reinforcing bar processed, after being lifted by crane by boom hoisting, installation puts in place, and employing present arrangement avoids existing tunnel inverted arch reinforcement installation and takes manually to install reinforcing bar by root, and operation is inconvenient and affects the problems such as face operation.

Description

Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis
Technical field
This utility model relates to Tunnel Engineering device field, specifically self-propelled tunnel inverted arch reinforcing bar spelling and installs chassis.
Background technology
Present stage, during tunnel construction, inverted arch is constructed forward immediately following face excavation driving, during inverted arch construction, first opens Dig inverted arch foundation ditch, afterwards, manually by root colligation inverted arch reinforcing bar, inverted arch template, concrete construction are installed, treat inverted arch concrete After solidification, form removal pours fill concrete.The many dependence of operation process is artificial, and inverted arch construction exists punching with face tunneling construction Prominent, need reasonable arrangement operation, sometimes, inevasible existence certain work holdup problem, affect Tunnel Construction Schedule.Therefore, need to grind System exploitation is a kind of avoids tunnel inverted arch and face tunneling construction not to affect or the tunnel inverted arch industrialized construction dress of few impact Put and seem the most necessary and urgent.
Utility model content
In view of this, the purpose of this utility model is to provide a kind of self-propelled tunnel inverted arch reinforcing bar spelling and installs chassis, keeps away Having exempted from existing tunnel inverted arch reinforcement installation to take manually to install reinforcing bar by root, operation is inconvenient and affects the problems such as face operation.
Self-propelled tunnel of the present utility model inverted arch reinforcing bar spelling installs chassis, including rectangle bearing frame, drives a vehicle, drives a vehicle Beam, travelling wheel and a spike;Rectangle bearing frame is rectangular frame structure, and crane beam is installed on two horizontal strokes at rectangle bearing frame top Between beam and can be along this cross beam movement, described driving be installed on crane beam and can move along crane beam;Described travelling wheel Being located at the lower end of each column of rectangle bearing frame, a spike is arranged with travelling wheel one_to_one corresponding.
Further, described travelling wheel is rail steel wheel or trackless rubber wheel.
Further, described spike is upper and lower telescopic supporting rod.
Further, described travelling wheel is driven by motor, and every travelling wheel sets a motor.
Further, in the middle part of two crossbeams bottom described rectangle bearing frame, corresponding inverted arch trestle is provided with track travelling wheel and use In the driving motor driving track travelling wheel to rotate.
The beneficial effects of the utility model are: self-propelled tunnel of the present utility model inverted arch reinforcing bar spelling installs chassis, should Device simple structure, easy to use, during use, first mobile device postpones to specific bit, then a spike is supported on ground, stable Device, afterwards, transports to installation site by the prefabricated reinforcing bar processed, boom hoisting after lifting by crane, installation puts in place, uses this device Avoid existing tunnel inverted arch reinforcement installation to take manually by root reinforcing bar to be installed, operation inconvenience and affect face operation etc. and ask Topic.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
Fig. 1 is structural representation of the present utility model, as it can be seen, the self-propelled tunnel inverted arch reinforcing bar spelling of the present embodiment Chassis is installed, including rectangle bearing frame 1, driving 2, crane beam 3, travelling wheel 4 and a spike 5;Rectangle bearing frame 1 is rectangular frame Structure, crane beam 3 is installed between two crossbeams at rectangle bearing frame 1 top and can be along this cross beam movement, and described driving 2 is pacified It is loaded on crane beam 3 and can move along crane beam 3;Described travelling wheel 4 and a spike 5 are located at each of rectangle bearing frame 1 and stand The lower end of post, a spike 5 is arranged with travelling wheel 4 one_to_one corresponding;This device simple structure, easy to use, during use, first mobile dress Put specific bit to postpone, then a spike 5 is supported on ground, stabilising arrangement, afterwards, transport to the prefabricated reinforcing bar processed install Position, boom hoisting after lifting by crane, installation puts in place, use present arrangement avoids existing tunnel inverted arch reinforcement installation take manually by Root installs reinforcing bar, and operation is inconvenient and affects the problems such as face operation;Rectangle bearing frame 1 include four columns, four crossbeams and Four longerons;Two of which crossbeam and two longerons are positioned at the top of rectangle bearing frame 1, another two crossbeam and another two longeron position In the bottom of rectangle bearing frame 1, between two ends and the corresponding column of two crossbeams at top, it is equipped with tilting reinforcement.
In the present embodiment, described travelling wheel 4 is rail steel wheel or trackless rubber wheel;Can traveling on track or ground.
In the present embodiment, described spike 5 is upper and lower telescopic supporting rod, and a spike 5 can be that screw thread stretches or hydraulically extensible Bar, spike 5 bottom is enlarged footing, to reduce the device compressive stress to ground.
In the present embodiment, described travelling wheel 4 is driven by motor 6, and every travelling wheel 4 sets a motor 6, motor 6 Using synchronous motor, to guarantee that device traveling is steady, motor 6 is fixedly installed on the corresponding column of rectangle bearing frame 1.
In the present embodiment, in the middle part of two crossbeams bottom described rectangle bearing frame 1, corresponding inverted arch trestle is provided with track traveling Take turns 7 and for the driving motor 8 driving track travelling wheel 7 to rotate;So that device moves forward and backward along inverted arch trestle;Traveling system System is divided into along ground walking system and along inverted arch trestle walking system two kinds, different according to operating mode during construction, can single selection or It is used in mixed way.
Finally illustrating, above example is only in order to illustrate the technical solution of the utility model and unrestricted, although ginseng According to preferred embodiment, this utility model is described in detail, it will be understood by those within the art that, can be to this The technical scheme of utility model is modified or equivalent, without deviating from objective and the model of technical solutions of the utility model Enclosing, it all should be contained in the middle of right of the present utility model.

Claims (5)

1. a self-propelled tunnel inverted arch reinforcing bar spelling installs chassis, it is characterised in that: include rectangle bearing frame, drive a vehicle, drive a vehicle Beam, travelling wheel and a spike;Rectangle bearing frame is rectangular frame structure, and crane beam is installed on two horizontal strokes at rectangle bearing frame top Between beam and can be along this cross beam movement, described driving be installed on crane beam and can move along crane beam;Described travelling wheel Being located at the lower end of each column of rectangle bearing frame, a spike is arranged with travelling wheel one_to_one corresponding.
Self-propelled tunnel the most according to claim 1 inverted arch reinforcing bar spelling installs chassis, it is characterised in that: described travelling wheel For rail steel wheel or trackless rubber wheel.
Self-propelled tunnel the most according to claim 1 inverted arch reinforcing bar spelling installs chassis, it is characterised in that: described spike For upper and lower telescopic supporting rod.
Self-propelled tunnel the most according to claim 1 inverted arch reinforcing bar spelling installs chassis, it is characterised in that: described travelling wheel Being driven by motor, every travelling wheel sets a motor.
Self-propelled tunnel the most according to claim 1 inverted arch reinforcing bar spelling installs chassis, it is characterised in that: described rectangle holds In the middle part of two crossbeams bottom weight frame, corresponding inverted arch trestle is provided with track travelling wheel and for driving what track travelling wheel rotated to drive Galvanic electricity motivation.
CN201620760973.XU 2016-07-19 2016-07-19 Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis Expired - Fee Related CN205743934U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620760973.XU CN205743934U (en) 2016-07-19 2016-07-19 Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620760973.XU CN205743934U (en) 2016-07-19 2016-07-19 Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis

Publications (1)

Publication Number Publication Date
CN205743934U true CN205743934U (en) 2016-11-30

Family

ID=57375627

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620760973.XU Expired - Fee Related CN205743934U (en) 2016-07-19 2016-07-19 Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis

Country Status (1)

Country Link
CN (1) CN205743934U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110644794A (en) * 2019-10-14 2020-01-03 郑州工程技术学院 Steel frame fixing device for civil engineering
CN111535858A (en) * 2020-04-30 2020-08-14 招商局重庆交通科研设计院有限公司 Complete equipment for quickly replacing inverted arch of tunnel and construction method
CN111550270A (en) * 2020-05-20 2020-08-18 中铁隧道集团一处有限公司 Ultra-large self-propelled tunnel multifunctional operation platform and tunnel steel bar waterproof board construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110644794A (en) * 2019-10-14 2020-01-03 郑州工程技术学院 Steel frame fixing device for civil engineering
CN111535858A (en) * 2020-04-30 2020-08-14 招商局重庆交通科研设计院有限公司 Complete equipment for quickly replacing inverted arch of tunnel and construction method
CN111550270A (en) * 2020-05-20 2020-08-18 中铁隧道集团一处有限公司 Ultra-large self-propelled tunnel multifunctional operation platform and tunnel steel bar waterproof board construction method
CN111550270B (en) * 2020-05-20 2021-07-09 中铁隧道集团一处有限公司 Ultra-large self-propelled tunnel multifunctional operation platform and tunnel steel bar waterproof board construction method

Similar Documents

Publication Publication Date Title
CN105952482B (en) Self-propelled tunnel inverted arch lining trolley
CN201344039Y (en) Anchor rod trolley
CN103016028A (en) Hydraulic self-propelled steel form carrier for tunnel secondary lining operation
CN104879061A (en) Multifunctional self-propelled portal wagon drill
CN205743934U (en) Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis
CN202596743U (en) Formwork trolley for underground tunnel pull-rod-free side wall construction
CN203531925U (en) Self-propelled integral template of tunnel inverted arch
CN204703761U (en) A kind of tunnel construction trolley
CN101943004B (en) Hydraulic self-running inclined-hole ordinary-state concrete casting trolley
CN103072900A (en) Loading frame dual-purpose vehicle under coal mine
CN106013783A (en) Formwork support and erecting method thereof
CN202250105U (en) Integral hydraulic steel formwork trolley
CN201722700U (en) Infrastructure of tower crane
CN206092014U (en) Interim support system transfer table car suitable for multi -pilot is wide open and digs
CN201802410U (en) Hydraulic self-traveling normal concrete casting trolley for an inclined tunnel
CN205296173U (en) Utilize structure of foundation ditch support system bearing tower crane
CN201128882Y (en) Lifting and supporting brackets integrated construction device for bridge arch rib
CN209838445U (en) Tunnel preliminary bracing rapid construction trolley
CN203361170U (en) Supporting upright column pile for building foundation pit support
CN108840234B (en) Hoisting device for prefabricated section and hoisting method thereof
CN206581951U (en) A kind of tunnel pin-connected panel preliminary bracing lifts chassis
CN202300422U (en) Open type tunnel boring machine (TBM) full cross section synchronous lining building trolley for hydraulic tunnel
CN206174964U (en) Template landing stage platform truck
CN101914990B (en) Beam-type transition layer cast-in-situ crossbeam construction formwork supporting system
CN206092006U (en) Self -propelled landing stage

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161130