CN206581951U - A kind of tunnel pin-connected panel preliminary bracing lifts chassis - Google Patents

A kind of tunnel pin-connected panel preliminary bracing lifts chassis Download PDF

Info

Publication number
CN206581951U
CN206581951U CN201720107837.5U CN201720107837U CN206581951U CN 206581951 U CN206581951 U CN 206581951U CN 201720107837 U CN201720107837 U CN 201720107837U CN 206581951 U CN206581951 U CN 206581951U
Authority
CN
China
Prior art keywords
tunnel
door frame
arc
bearing platform
preliminary bracing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720107837.5U
Other languages
Chinese (zh)
Inventor
赖建昌
靳炳强
王忠洁
任文祥
王兴藏
马文超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 24th Bureau Group Co Ltd
China Railway 24th Bureau Group Zhejiang Engineering Testing Co Ltd
Original Assignee
China Railway 24th Bureau Group Co Ltd
China Railway 24th Bureau Group Zhejiang Engineering Testing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 24th Bureau Group Co Ltd, China Railway 24th Bureau Group Zhejiang Engineering Testing Co Ltd filed Critical China Railway 24th Bureau Group Co Ltd
Priority to CN201720107837.5U priority Critical patent/CN206581951U/en
Application granted granted Critical
Publication of CN206581951U publication Critical patent/CN206581951U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Chassis is lifted the utility model discloses a kind of tunnel pin-connected panel preliminary bracing, in order to solve quickly and accurately to move problem in place when the lifting of concrete piece is installed in Tunnel Engineering, including door frame, it is characterized in that door frame bottom is provided with chassis running gear, at the top of door frame and both sides are provided with circular arc load bearing system, also include the slidingtype top arc bearing platform coordinated with tunnel top arc at the top of door frame, top arc bearing platform has walking system, the Lift-on/Lift-off System coordinated with top arc bearing platform is provided with the top of door frame;Described top arc bearing platform includes horizontal lifting body and up and down lifting body.Make full use of tunnel limited height space, it is ensured that the multidirectional accuracy of multi-angle of fixing body, the comprehensive effective support in same tunnel section, uniform application, it is safe and reliable, improve construction quality, the present apparatus is simple in construction, mounting arrangements are convenient, support adjusting range is larger, and efficiency of construction is high.

Description

A kind of tunnel pin-connected panel preliminary bracing lifts chassis
Technical field
The utility model is related to engineering machinery technology, especially a kind of tunnel pin-connected panel preliminary bracing lifting chassis.
Background technology
For the construction requirement of Tunnel Engineering, preliminary bracing construction trolley is provided with various structures shape according to different engineering situations Formula and construction method.Such as patent announcement number is CN203487761U, and a kind of big cross section long tunnel preliminary bracing construction is with simply Chassis, including the portal support that is moved forward and backward along the Longitudinal extending direction of Tunnel and directly over portal support Top operation platform, portal support includes left side vertical supports, right side vertical supports and horizontal shore;Left side vertical supports Left side is from top to bottom provided with multiple left side operation platforms, and the right side of right side vertical supports is from top to bottom provided with multiple right sides and applied The width of work platform, multiple left side operation platforms and multiple right side operation platforms from top to bottom gradually increases;Vertically prop up in left side It is provided with frame and/or right side vertical supports for the cat ladder above and below workmen, left side vertical supports bottom is provided with a multiple left sides Road wheel, right side vertical supports bottom is provided with multiple right road wheels.And for example patent publication No. designs for CN106089258A A kind of Tunnel device and construction method, including support chassis, template and air bag component, support chassis include vehicle frame With the running mechanism for being arranged on bottom of frame, vehicle frame include multiple gate supporting supports being arranged side by side along vehicle frame length direction and Connected between tie-beam for connecting gate supporting support, each gate supporting support by tie-beam, running mechanism is arranged on Positioned at the bottom of the gate supporting support at vehicle frame length direction two ends, template is the arch knot being hinged by multiple arcs plate section Some injected holes are distributed with structure, arc section, platen cover is set above support chassis between template and gate supporting support There is hydraulically extensible bar, air bag component includes the air bag I for being arranged on each arc section side and the arc for being arranged in template bottom The air bag II of shape plate section bottom.The problem of these devices can not solve the lifting installation of concrete piece.
The content of the invention
The purpose of this utility model is, in order to solve in Tunnel Engineering, quickly and accurately to be moved just when the lifting of concrete piece is installed There is provided a kind of tunnel pin-connected panel preliminary bracing lifting chassis of reasonable in design for position problem.
Above-mentioned technical problem of the present utility model is mainly what is be addressed by following technical proposals:A kind of tunnel is assembled Formula preliminary bracing lifts chassis, including door frame, it is characterized in that door frame bottom is provided with the top of chassis running gear, door frame and both sides are set There is the slidingtype top arc bearing platform for also including coordinating with tunnel top arc at the top of circular arc load bearing system, door frame, top arc is held Weight platform has walking system, and the Lift-on/Lift-off System coordinated with top arc bearing platform is provided with the top of door frame;Described top arc Bearing platform includes horizontal lifting body and up and down lifting body.The technical program is main to be made up of five major parts, i.e. chassis row Walking system, door frame, circular arc load bearing system, the walking system of top arc bearing platform and Self-carried type Lift-on/Lift-off System.Device is designed Preliminary bracing Prefabricated Concrete bluff piece width 0.5m~1m, length 2m can be met, thickness 0.2m, used in the range of weight 0.6t~1t. Due to tunnel top limited height, general boom hoisting is difficult evolutionary operation, and present apparatus Self-carried type loop wheel machine will pay concrete piece in advance Lifting to left and right laterallys secure bearing platform in advance, and top arc bearing platform is designed as slidingtype, and prefabricated section can be hung in advance On top load-bearing pallet, level and height and position adjustment are then carried out, to reach accurate purpose in place.Due to outage in tunnel Degree is limited, and the Lift-on/Lift-off System height of the present apparatus is close with the height of top arc bearing platform, what Lift-on/Lift-off System need not in height Particular/special requirement, completion is slided by top arc bearing platform during concrete piece top set completely.
Preferably, described top arc bearing platform both sides bottom part is provided with concrete piece supporting table, held in top arc Radially guide rail is slided provided with arc in the arc top surface position of weight platform.It will can be lifted on the load-bearing pallet of top using concrete piece supporting table Concrete piece be supported positioning, it is ensured that slide adjustment during concrete piece it is steady.
Preferably, described horizontal lifting body includes hydraulic cylinder and liquid that is horizontally disposed and being connected with walking system Press pushing ram.Horizontal lifting body is mainly used in adjustment of the top arc bearing platform along tunnel lateral direction position.
Preferably, described Lift-on/Lift-off System includes being provided with telescopic hoist boom at the top of rotary column, column.General rotation Formula column is located at the edge of door frame, can be sent to top arc bearing platform from outside lifting concrete piece to mount point and concrete piece On.
Preferably, provided with lifting cucurbit in described Lift-on/Lift-off System, telescopic hoist boom is driven by hydraulic system.It is telescopic Arm can extend lifting scope.
Preferably, described circular arc load bearing system includes some support bars, all support bars are along institute's support zone tunnel The diametric(al) arrangement of road circular arc.
Preferably, described door frame, which has, has a traveling at the top of the lateral facade that two support bars are installed, door frame System mounting platform.Guide rail is arranged on walking system mounting platform.
Preferably, being provided with work support pin in described chassis running gear.When same engineered locations are installed, utilize Work support pin stablizes the stability of whole chassis.
Preferably, vertically provided with auxiliary walking system on the arc top surface of described top arc bearing platform, auxiliary is walked Row system is provided with some support bars.Aid in walking system can as the present apparatus a kind of embodiment, in tunnel top Concrete piece reaches substantially to carry out refinement adjustment using the system during mount point position.
The beneficial effects of the utility model are:Tunnel limited height space is made full use of, is substituted by Self-carried type Lift-on/Lift-off System Outside suspender, the concrete piece of tunnel top is completed by top arc bearing platform completely, and the position adjusting mechanism of all directions ensure that The multidirectional accuracy of multi-angle of fixing body, the comprehensive effective support in same tunnel section, uniform application is safe and reliable, Construction quality is improved, the present apparatus is simple in construction, mounting arrangements are convenient, support adjusting range is larger, and efficiency of construction is high.
Brief description of the drawings
Fig. 1 is a kind of chassis main structure diagram of the present utility model.
Fig. 2 is the utility model Fig. 1 local right side structural representation.
Fig. 3 is a kind of portal-framed structure schematic diagram of the present utility model.
Fig. 4 is a kind of top arc bearing platform schematic diagram of the present utility model.
Fig. 5 is a kind of example structure schematic diagram of top arc bearing platform of the present utility model.
In figure:1. chassis running gear, 2. door frames, 3. walking systems, 4. Lift-on/Lift-off Systems, 5. circular arc load bearing systems, 6. top arc bearing platform, 7. support bars, 8. horizontal lifting bodies, 9. auxiliary walking systems.
Embodiment
Below by embodiment, and with reference to accompanying drawing, the technical solution of the utility model is described in further detail.
Referring to Fig. 1, Fig. 2, a kind of tunnel pin-connected panel preliminary bracing lifting chassis of the present embodiment is made up of five major parts:I.e. Chassis running gear 1, door frame 2, circular arc load bearing system 5, walking system 3 and Self-carried type Lift-on/Lift-off System 4.
Wherein chassis running gear 1 is arranged in the bottom of door frame 2, and chassis running gear 1 includes the work support of energy load-bearing main body Pin.The top of door frame 2 and Liang Ce Zhuo are provided with circular arc load bearing system 5, and circular arc load bearing system 5 includes 13 support bars 7, by tunnel arch Structure distribution, both sides respectively set 4 support bars 7, and top sets 5 support bars 7;Tunnel of all support bars 7 along institute's support zone Arc diameter direction is arranged.There are door frame 2 two vertical support bars 7 to install lateral facade, as shown in figure 3, top is one The mounting platform of walking system 3, provided with I-steel guide rail.The top of door frame 2 is additionally provided with circle at the top of the slidingtype coordinated with tunnel top arc Arc bearing platform 6, referring to Fig. 4, the bottom of top arc bearing platform 6 is walking system 3, and top arc bearing platform 6 includes horizontal jacking Mechanism 8 and up and down lifting body, horizontal lifting body 8 include hydraulic cylinder and horizontally disposed and be connected with walking system 3 Hydraulic drive bar.Multigroup roller is provided with walking system 3, roller coordinates with I-steel guide rail.
The both sides bottom part of top arc bearing platform 6 is provided with concrete piece supporting table, the pendulum when supporting table is lifted by crane as concrete piece Platform is put, radially guide rail is slided provided with arc at the arc top surface position of top arc bearing platform 6, it is typically built-in that arc slides guide rail Coordinate in bearing platform skeleton, and with concrete piece supporting table needing a concrete piece to be mounted to slide to mount point upwards.
The Lift-on/Lift-off System 4 coordinated with top arc bearing platform 6 is provided with the one end at the top of door frame 2, Lift-on/Lift-off System 4 has one Telescopic hoist boom is provided with the top of the rotary column of branch, column, telescopic hoist boom is driven by hydraulic system, also filled in Lift-on/Lift-off System 4 There is lifting cucurbit.
Fig. 5 is a kind of embodiment of top arc bearing platform 6, vertically provided with auxiliary walking system 9 on its arc top surface, Aid in the structure of walking system 9 identical with the structure of walking system 3, auxiliary walking system 9 is provided with 5 support bars 7.This certain dress Put and slide guide rail with arc and use cooperatively, set position mutually to stagger.
In use, lifted Prefabricated Concrete piece to the lateral fixation bearing platform of tunnel lateral direction or so with Lift-on/Lift-off System 4, and top Circular arc bearing platform is paid concrete piece in advance and is hung on the bearing frame at the position due to being slidingtype.After the lifting in place of Prefabricated Concrete piece, by platform Behind the row of car walking system 1 to Tunnel Engineering jacking position, by lateral concrete piece jacking in place, then by top arc bearing platform 6 by water Same position is arrived on the flat top of lifting body 8, then, to particular location, treats that circular arc preliminary bracing is prefabricated by lifting body jacking up and down After concrete piece is fixed, each oil cylinder is shunk.Repeat this work and complete overall operation.
Above-described embodiment and schema and the new product form of the non-limiting present invention and style, any art Appropriate change or modification that those of ordinary skill is done to it, all should be regarded as not departing from patent category of the present utility model.

Claims (9)

1. a kind of tunnel pin-connected panel preliminary bracing lifts chassis, including door frame(2), it is characterized in that door frame bottom is walked provided with chassis System(1), door frame top and both sides are provided with circular arc load bearing system(5), door frame top also includes the slip coordinated with tunnel top arc Formula top arc bearing platform(6), top arc bearing platform has walking system(3), it is provided with and is held with top arc at the top of door frame The supporting Lift-on/Lift-off System of weight platform(4);Described top arc bearing platform includes horizontal lifting body(8)And jack up and down Structure.
2. a kind of tunnel pin-connected panel preliminary bracing lifting chassis according to claim 1, it is characterized in that described top circle Arc bearing platform(6)Both sides bottom part is provided with concrete piece supporting table, is radially provided with the arc top surface position of top arc bearing platform Arc slides guide rail.
3. a kind of tunnel pin-connected panel preliminary bracing lifting chassis according to claim 1 or 2, it is characterised in that described water Flat lifting body(8)Including hydraulic cylinder and horizontally disposed and and walking system(3)The hydraulic drive bar of connection.
4. a kind of tunnel pin-connected panel preliminary bracing lifting chassis according to claim 1, it is characterised in that described lifting System(4)Including rotary column, telescopic hoist boom is provided with the top of column.
5. a kind of tunnel pin-connected panel preliminary bracing lifting chassis according to claim 4, it is characterised in that described lifting System(4)In provided with lifting cucurbit, telescopic hoist boom drives by hydraulic system.
6. a kind of tunnel pin-connected panel preliminary bracing lifting chassis according to claim 1 or 2 or 4, it is characterised in that described Circular arc load bearing system(5)Including some support bars(7), diametric(al) of all support bars along institute's support zone tunnel circular arc Arrangement.
7. a kind of tunnel pin-connected panel preliminary bracing lifting chassis according to claim 6, it is characterised in that described door frame (2)With two support bars(7)There is a walking system at the top of the lateral facade installed, door frame(3)Mounting platform.
8. a kind of tunnel pin-connected panel preliminary bracing lifting chassis according to claim 1 or 2 or 4 or 5, it is characterised in that institute The chassis running gear stated(1)In be provided with work support pin.
9. a kind of tunnel pin-connected panel preliminary bracing lifting chassis according to claim 1 or 2, it is characterized in that on described top Portion's circular arc bearing platform(6)Arc top surface on vertically provided with auxiliary walking system(9), auxiliary walking system is provided with some branch Strut(7).
CN201720107837.5U 2017-02-04 2017-02-04 A kind of tunnel pin-connected panel preliminary bracing lifts chassis Active CN206581951U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720107837.5U CN206581951U (en) 2017-02-04 2017-02-04 A kind of tunnel pin-connected panel preliminary bracing lifts chassis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720107837.5U CN206581951U (en) 2017-02-04 2017-02-04 A kind of tunnel pin-connected panel preliminary bracing lifts chassis

Publications (1)

Publication Number Publication Date
CN206581951U true CN206581951U (en) 2017-10-24

Family

ID=60111344

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720107837.5U Active CN206581951U (en) 2017-02-04 2017-02-04 A kind of tunnel pin-connected panel preliminary bracing lifts chassis

Country Status (1)

Country Link
CN (1) CN206581951U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035747A (en) * 2017-12-19 2018-05-15 张罗悦 A kind of tunnel steel form lining trolley

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035747A (en) * 2017-12-19 2018-05-15 张罗悦 A kind of tunnel steel form lining trolley
CN108035747B (en) * 2017-12-19 2019-03-12 厦门雅众建设集团有限公司 A kind of tunnel steel form lining trolley

Similar Documents

Publication Publication Date Title
CN109538238B (en) Tunnel arch prefabricated segment construction device and control method
CN201077721Y (en) Gantry crane with falling girder
CN204457802U (en) Formed by integrally casting formula formwork jumbo
CN103016028A (en) Hydraulic self-propelled steel form carrier for tunnel secondary lining operation
CN105293315B (en) A kind of hanging device of assembled architecture prefabricated components
CN207393229U (en) A kind of tunnel waterproof board spreading hanging platform vehicle with transverse movement system
CN101435268B (en) Stretching device of case beam in case
CN111038940A (en) Rail mounted is used for hoist and mount traction system of transportation
CN103194977B (en) Integration of transporting and building formula Bridge Erector sets up first hole case beam front launching nose machine installation method
CN101943004B (en) Hydraulic self-running inclined-hole ordinary-state concrete casting trolley
CN106939554A (en) Expanded letter steel girder erecting machine and its beam erecting method
CN203247031U (en) Hoisting device for curtain board transporting
CN204938060U (en) The heap de-stacking device of conveying sledge
CN206581951U (en) A kind of tunnel pin-connected panel preliminary bracing lifts chassis
CN204492846U (en) Movable type with inverted arch lining device crosses car trestle
CN203684019U (en) Height and span adjustable track laying machine for subway construction
CN204804360U (en) High altitude prefabricated plate mounting plate
CN210049105U (en) Self-propelled bridge formwork operation trolley
CN212801248U (en) Prefabricated segment beam displacement trolley device
CN201802410U (en) Hydraulic self-traveling normal concrete casting trolley for an inclined tunnel
CN205932963U (en) Many landing legs tire formula tracklaying crane
CN201915333U (en) Bridge erecting machine for erecting curved double-line twin girders at tunnel portal in zero-distance manner
CN211711873U (en) Rail mounted is used for hoist and mount traction system of transportation
CN108840234B (en) Hoisting device for prefabricated section and hoisting method thereof
CN202731933U (en) Full-hydraulic self-propelled trestle trolley

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant