CN204999299U - Dry coke quenching no. 1, burnt dust discharging device of secondary dust remover - Google Patents
Dry coke quenching no. 1, burnt dust discharging device of secondary dust remover Download PDFInfo
- Publication number
- CN204999299U CN204999299U CN201520577831.5U CN201520577831U CN204999299U CN 204999299 U CN204999299 U CN 204999299U CN 201520577831 U CN201520577831 U CN 201520577831U CN 204999299 U CN204999299 U CN 204999299U
- Authority
- CN
- China
- Prior art keywords
- ash
- valve
- coke powder
- coke
- discharging device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Coke Industry (AREA)
Abstract
The utility model relates to a dry coke quenching no. 1, burnt dust discharging device of secondary dust remover includes at least: fine coke cooling unit, unload grey push -pull valve, first form unloading valve, fine coke intermediate bin, storehouse pump intake valve, gas -force ash conveying storehouse pump, ash pipeline way, hui cang, add wet mixer, storehouse pump fluidization room, a fine coke cooling unit upper end and dry coke quenching system secondary dust remover link to each other respectively, receive fine coke and the granule of being isolated by the dust remover and cool off, fine coke cooling unit lower extreme the discharge gate with unload grey push -pull valve upper end and link to each other, the lower extreme that unloads grey push -pull valve with the upper end of first form unloading valve link to each other, lower extreme and the fine coke intermediate bin entry of first form unloading valve link to each other, be connected through storehouse pump intake valve between fine coke intermediate bin and the gas -force ash conveying storehouse pump. The utility model provides the automatic operation degree of high system reduces workman's intensity of labour and improves operational environment, improvement work efficiency.
Description
Technical field
The utility model relates to the burnt ash-discharging device of dry quenching field recyclegas system time dust collector, particularly a kind of dry coke quenching first and second dust exhaustor.
Background technology
Dry quenching technology utilizes inertia recyclegas to carry out with red-hot coke the sensible heat that interchange of heat absorbs red-hot coke dry putting out in stove, then by other function devices in system to the process utilized by the recyclegas after heating, thus reach the object of UTILIZATION OF VESIDUAL HEAT IN.
The important function device of dry coke quenching auxiliary comprises and dryly puts out the equipment such as stove, circulating fan, boiler, recycle gas line
The tiny flour particle of cooled coke can absorb in the process of sensible heat and mixes with carrying out at the dry recyclegas put out in stove interchange of heat, then enters recycle gas line, by the equipment such as circulating fan, boiler.
Due to the particularity of circulating fan and boiler plant, strict restriction is had for the dust granules content in recyclegas, must process it by arranging dust exhaustor, to ensure the normal service life of equipment in recycle gas line, so dedusting and unload grey equipment and just seem particularly important.
The equipment that unloads in the past adopts the coke powder cooling intallation arranging meet requirements below dust exhaustor, form unloading valve is set at the cinder-discharging port of coke powder cooling intallation and interlocks to the corresponding level-sensing device arranged on coke powder cooling intallation, the intrasystem DCS control system of access dry coke quenching auxiliary controls automatically to ash-valve, is then carried by the defeated grey equipment of independent operating the coke powder of being discharged by form unloading valve, transports outward.
The defeated grey equipment of independent operating generally has two kinds of modes, and the first is connected with form unloading valve by arranging slat conveyer, mechanically the ashes of discharging is collected, is processed; The second is connected with form unloading valve by arranging pneumatic delivery bin pump, mechanically the ashes of discharging collected, processed; And the first utilizes scrapper conveyor to carry out the defeated grey process of mechanical system and unreliable, there is the situation of the how easy generation reentrainment of dust of leak source, and the second utilizes the mixture of airstream and strength to carry out the mode of defeated ash, due to the structure of equipment itself, and the reason of form valve service conditions can not carry out direct interlocked control, can only by defeated grey equipment separately outside dry coke quenching auxiliary system DCS control system, therefore can not facilitate in center-control indoor, intuitively it controlled and show, thus cause all inconvenience and problem in production run process.
Utility model content
The purpose of this utility model is to provide the burnt ash-discharging device of a kind of dry coke quenching first and second dust exhaustor efficiently, so as to solve the burnt ash-discharging device of dry coke quenching first and second dust exhaustor in the past and coke dry quenching body control system separate, can not control it convenient in Central Control Room, intuitively and show, thus improve the automatic operating degree of system, reduce the labour intensity of workman and improve working environment, increase work efficiency.
To achieve these goals, the utility model by the following technical solutions, the burnt ash-discharging device of a kind of dry coke quenching first and second dust exhaustor, at least comprise: coke powder cooling unit, unload grey push-pull valve, the first form unloading valve, coke powder intermediate bin, storehouse pump intake valve, pneumatic transporting ash silo pump, ash handing pipeline, ash silo, wetting stirrer, Cang Beng fluidising chamber, described coke powder cooling unit upper end is connected respectively with dry quenching system one secondary filter, receives the coke powder and particle separated by dust exhaustor and cools; The discharging opening of described coke powder cooling unit lower end with unload grey push-pull valve upper end and be connected, the described lower end of unloading grey push-pull valve is connected with the upper end of the first described form unloading valve; The lower end of the first described form unloading valve is connected with coke powder intermediate bin entrance; Be connected by storehouse pump intake valve between coke powder intermediate bin with pneumatic transporting ash silo pump.
The upper end of described pneumatic transporting ash silo pump is connected with storehouse pump intake valve, the outlet of Cang Beng fluidising chamber is connected with ash handing pipeline, ash silo is delivered to by ash handing pipeline by after the coke powder fluidisation in the pump of storehouse, the second form unloading valve then by being arranged on ash silo is discharged, after enter wetting stirrer, humidification stir after discharged by exhaust tube.
Described coke powder cooling unit upper end is barreled structure, and lower end is funnel-form.
Described coke powder intermediate bin upper end is barreled structure, and lower end is funnel-form.
Described ash silo upper end is barreled structure, and lower end is funnel-form.
Described wetting stirrer horizontal positioned, lower end connects exhaust tube.
The utility model has the advantages that: because the pressure in the work section below work section more than form unloading valve and storehouse pump intake valve is different, so directly can not connect thus cause the situation of defeated grey equipment independent operating, be therefore provided with coke powder intermediate bin and transition, buffering are carried out to it; In addition, the upper end of pneumatic transporting ash silo pump is connected with storehouse pump intake valve, the outlet of Cang Beng fluidising chamber is connected with ash handing pipeline is then discharged after the coke powder fluidisation in the pump of storehouse by the form unloading valve being arranged on ash silo to ash silo by Pipeline transport, after enter wetting stirrer, humidification stir after discharged by exhaust tube.Thus improve the automatic operating degree of system, reduce the labour intensity of workman and improve working environment, increase work efficiency.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of the burnt ash-discharging device of a kind of dry coke quenching first and second of the utility model embodiment dust exhaustor;
Label declaration, 1, coke powder cooling unit; 2, grey push-pull valve is unloaded; 3, the first form unloading valve; 4, coke powder intermediate bin; 5, storehouse pump intake valve; 6, pneumatic transporting ash silo pump; 7, ash handing pipeline; 8, ash silo; 9, the second form unloading valve; 10, wetting stirrer; 11, Cang Beng fluidising chamber; 12, exhaust tube.
Detailed description of the invention
As shown in Figure 1, the burnt ash-discharging device of a kind of dry coke quenching first and second dust exhaustor, at least comprise: coke powder cooling unit 1, unload grey push-pull valve 2, first form unloading valve 3, coke powder intermediate bin 4, storehouse pump intake valve 5, pneumatic transporting ash silo pump 6, ash handing pipeline 7, ash silo 8, wetting stirrer 10, Cang Beng fluidising chamber 11, described coke powder cooling unit 1 upper end is connected respectively with dry quenching system one secondary filter, receives the coke powder and particle separated by dust exhaustor and cools; The discharging opening of described coke powder cooling unit 1 lower end with unload grey push-pull valve 2 upper end and be connected, the described lower end of unloading grey push-pull valve 2 is connected with the upper end of the first described form unloading valve 3 and isolates when overhauling for equipment; The lower end of the first described form unloading valve 3 is connected with coke powder intermediate bin 4 entrance, operationally, by volume space separate in the first form unloading valve 3, make in the process of continuous ash discharge, can ash discharge can keep again unloading the relatively stable of form ash valve above working space internal pressure smoothly.
Be connected by storehouse pump intake valve 5 between coke powder intermediate bin 4 with pneumatic transporting ash silo pump 6; Because the pressure in the work section of the first form unloading valve more than 3 and the work section of storehouse pump intake valve less than 5 is different, so directly can not connect thus cause the situation of defeated grey equipment independent operating, be therefore provided with coke powder intermediate bin 4 and transition, buffering are carried out to it; The upper end of described pneumatic transporting ash silo pump 6 is connected with storehouse pump intake valve 5, Cang Beng fluidising chamber 11 outlet is connected with ash handing pipeline 7, ash silo 8 is delivered to by ash handing pipeline 7 by after the coke powder fluidisation in the pump of storehouse, the second form unloading valve 9 then by being arranged on ash silo 8 is discharged, after enter wetting stirrer 10, humidification stir after discharged by exhaust tube 12.
Described coke powder cooling unit 1 upper end is barreled structure, and lower end is funnel-form.
Described coke powder intermediate bin 4 upper end is barreled structure, and lower end is funnel-form.
Described ash silo 8 upper end is barreled structure, and lower end is funnel-form.
Described wetting stirrer 10 horizontal positioned, lower end connects exhaust tube 12.
The parts that the present embodiment does not describe in detail and structure belong to the well-known components of the industry and common structure or conventional means, do not describe one by one here.
Claims (6)
1. the burnt ash-discharging device of dry coke quenching first and second dust exhaustor, at least comprise: coke powder cooling unit (1), unload grey push-pull valve (2), the first form unloading valve (3), coke powder intermediate bin (4), storehouse pump intake valve (5), pneumatic transporting ash silo pump (6), ash handing pipeline (7), ash silo (8), wetting stirrer (10), Cang Beng fluidising chamber (11), described coke powder cooling unit (1) upper end is connected respectively with dry quenching system one secondary filter, receives the coke powder and particle separated by dust exhaustor and cools; The discharging opening of described coke powder cooling unit (1) lower end with unload grey push-pull valve (2) upper end and be connected, the described lower end of unloading grey push-pull valve (2) is connected with the upper end of the first described form unloading valve (3); The lower end of the first described form unloading valve (3) is connected with coke powder intermediate bin (4) entrance; Be connected by storehouse pump intake valve (5) between coke powder intermediate bin (4) with pneumatic transporting ash silo pump (6).
2. the burnt ash-discharging device of a kind of dry coke quenching first and second dust exhaustor according to claim 1, it is characterized in that: the upper end of described pneumatic transporting ash silo pump (6) is connected with storehouse pump intake valve (5), Cang Beng fluidising chamber (11) outlet is connected with ash handing pipeline (7), ash silo (8) is delivered to by ash handing pipeline (7) by after the coke powder fluidisation in the pump of storehouse, the second form unloading valve (9) then by being arranged on ash silo (8) is discharged, after enter wetting stirrer (10), humidification stir after by exhaust tube (12) discharge.
3. the burnt ash-discharging device of a kind of dry coke quenching first and second dust exhaustor according to claim 1, is characterized in that: described coke powder cooling unit (1) upper end is barreled structure, and lower end is funnel-form.
4. the burnt ash-discharging device of a kind of dry coke quenching first and second dust exhaustor according to claim 1, is characterized in that: described coke powder intermediate bin (4) upper end is barreled structure, and lower end is funnel-form.
5. the burnt ash-discharging device of a kind of dry coke quenching first and second dust exhaustor according to claim 1, is characterized in that: described ash silo (8) upper end is barreled structure, and lower end is funnel-form.
6. the burnt ash-discharging device of a kind of dry coke quenching first and second dust exhaustor according to claim 1, it is characterized in that: described wetting stirrer (10) horizontal positioned, lower end connects exhaust tube (12).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520577831.5U CN204999299U (en) | 2015-08-04 | 2015-08-04 | Dry coke quenching no. 1, burnt dust discharging device of secondary dust remover |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520577831.5U CN204999299U (en) | 2015-08-04 | 2015-08-04 | Dry coke quenching no. 1, burnt dust discharging device of secondary dust remover |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204999299U true CN204999299U (en) | 2016-01-27 |
Family
ID=55156197
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520577831.5U Expired - Fee Related CN204999299U (en) | 2015-08-04 | 2015-08-04 | Dry coke quenching no. 1, burnt dust discharging device of secondary dust remover |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204999299U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110239960A (en) * | 2019-05-23 | 2019-09-17 | 成都瑞柯林工程技术有限公司 | Unloading valve group unloads grey method and powder fluidization system |
CN113462839A (en) * | 2021-07-06 | 2021-10-01 | 广东韶钢松山股份有限公司 | Blast furnace ash removal system and blast furnace ash removal method |
-
2015
- 2015-08-04 CN CN201520577831.5U patent/CN204999299U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110239960A (en) * | 2019-05-23 | 2019-09-17 | 成都瑞柯林工程技术有限公司 | Unloading valve group unloads grey method and powder fluidization system |
CN113462839A (en) * | 2021-07-06 | 2021-10-01 | 广东韶钢松山股份有限公司 | Blast furnace ash removal system and blast furnace ash removal method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101761933B (en) | Low-temperature furnace smoke sucking exhaust gas and hot air drying composite powder feeding bituminous coal and meagre coal universal type powder preparing system | |
CN101870897B (en) | Process for carrying out strengthening circulation, stage grinding and quality improvement on lignite by utilizing superheated steam and system thereof | |
CN103542407A (en) | Flying ash recirculating device and flying ash recirculating method for circulating fluidized bed boiler | |
CN105066718A (en) | Comprehensive utilization system for sintering waste heat | |
CN204999299U (en) | Dry coke quenching no. 1, burnt dust discharging device of secondary dust remover | |
CN214779271U (en) | High-order feed bin steel scrap adding system | |
CN102633122B (en) | Pneumatic conveying and blast furnace injecting device for coke oven dust-removing ash and using method thereof | |
CN207769504U (en) | A kind of system for improving high basic metal coal and staiing coking | |
CN203333491U (en) | Energy-saving environment-friendly cement clinker preparation system | |
CN204902609U (en) | System is used multipurposely to sintering waste heat | |
CN210399936U (en) | Clean sintering system based on fuel preparation and roasting control | |
CN103351106A (en) | Energy-saving and environment-friendly cement clinker preparation system | |
CN107152677A (en) | A kind of CFBB slag removing system | |
CN103194554B (en) | Simple raw coal drying process for blast furnace coal injection | |
CN207247834U (en) | Semi-coke drying system | |
CN109132344A (en) | A kind of bucket grain elevator with air blast heat exchange function | |
CN205187360U (en) | Material sealing pump | |
CN208332308U (en) | Coal-fired sludge coupled electricity-generation system | |
CN208983330U (en) | Double fuel boiler system | |
CN208979918U (en) | A kind of lock wind unloader | |
CN110526596B (en) | Quick cooling and discharging mixed lime kiln | |
CN207936772U (en) | A kind of hot mine is cooling and residual neat recovering system | |
CN208218699U (en) | A kind of mixing formula limekiln of fast cooling discharging | |
CN219991486U (en) | Dry quenching environment dust removal system | |
CN101738081A (en) | Shaft kiln |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |