CN203870229U - Time-control voltage-regulating light fixture testing apparatus - Google Patents

Time-control voltage-regulating light fixture testing apparatus Download PDF

Info

Publication number
CN203870229U
CN203870229U CN201420155956.4U CN201420155956U CN203870229U CN 203870229 U CN203870229 U CN 203870229U CN 201420155956 U CN201420155956 U CN 201420155956U CN 203870229 U CN203870229 U CN 203870229U
Authority
CN
China
Prior art keywords
power
schedule controller
pressure regulator
time schedule
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420155956.4U
Other languages
Chinese (zh)
Inventor
张为民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Light Industrial Products Arts & Crafts Textiles Import And Export Co Ltd
Original Assignee
Hangzhou Light Industrial Products Arts & Crafts Textiles Import And Export Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Light Industrial Products Arts & Crafts Textiles Import And Export Co Ltd filed Critical Hangzhou Light Industrial Products Arts & Crafts Textiles Import And Export Co Ltd
Priority to CN201420155956.4U priority Critical patent/CN203870229U/en
Application granted granted Critical
Publication of CN203870229U publication Critical patent/CN203870229U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Circuit Arrangement For Electric Light Sources In General (AREA)

Abstract

The utility model relates to a time-control voltage-regulating light fixture testing apparatus. The apparatus comprises a casing and a test circuit arranged in the casing. The casing is provided with a power input socket and a plurality of power output sockets in an embedded mode. The test circuit comprises a voltage regulator, a sequential controller and a power switch. One input end of the voltage regulator is connected with the zero line electrode of the power input socket, the other end of the voltage regulator is connected with the live line electrode of the power input socket through the power switch, two input ends of the sequential controller are respectively connected with two output ends of the voltage regulator, the plurality of power output sockets are connected between the two output ends of the sequential controller in parallel, and the sequential controller, the regulation knob of the voltage regulator and the power switch are respectively embedded in the casing. According to the utility model, a light fixture to be tested can work under different voltages can work automatically according to preset power on-off time, the testing is convenient, the test work modes are flexible and variable, the testing is complete, and the reliability of the light fixture is improved.

Description

Time control regulating lamp proving installation
Technical field
The utility model relates to a kind of checkout equipment, relates in particular to a kind of time control regulating lamp proving installation.
Background technology
Whether also at present, before light fixture dispatches from the factory, test all fairly simplely, be all generally connect civil power and after the work of certain time length, observe its normal work, thereby judge that whether it is qualified.Because test process is fairly simple, therefore be all generally to be completed by manual control, and light fixture can only switch on by fixing duration, the operating voltage of light fixture is also fixed, so test pattern is more single, test sufficiently complete, can not guarantee the q&r of light fixture, and some light fixture to export, only to light fixture, pass to AC220V voltage, can not guarantee that light fixture also can normally work under AC230V voltage abroad, not meet the requirement of external AC230V voltage.
Summary of the invention
The test pattern that the utility model mainly solves original light fixture is more single, tests sufficiently completely, can not guarantee the technical matters of the q&r of light fixture; A kind of time control regulating lamp proving installation is provided, and it can make light fixture be operated in different voltage, and automatically by the power on/off time of setting, carries out work, convenient test, and test job pattern flexibility and changeability, tests completely, improves the reliability of light fixture.
Above-mentioned technical matters of the present utility model is mainly solved by following technical proposals: the utility model comprises casing and is located at the test circuit in casing, on casing, be embedded with a power input socket and several power output sockets, test circuit comprises pressure regulator, time schedule controller and power switch, described power input socket, power switch, pressure regulator, time schedule controller is connected or described power input socket successively with power output socket, power switch, time schedule controller, pressure regulator is connected successively with power output socket, several power output sockets are connected in parallel, the adjusting knob of pressure regulator and described power switch, time schedule controller is inlaid in respectively on described casing.During work, power input socket connects AC220V voltage, light fixture to be measured is connected with power output socket, by the adjusting knob of rotation pressure regulator, can change the output voltage of pressure regulator, this voltage is that AC0~250V is electrodeless adjustable, to light fixture, pass to the power supply of different voltages, thereby while guaranteeing that light fixture is used at home, voltage fluctuates to some extent and also can work, guarantee that light fixture also can normally work under AC230V voltage abroad, and voltage fluctuates to some extent and also can work, test job voltage is adjustable flexibly, test completely, improve the reliability of the light fixture that dispatches from the factory.
As preferably, input end of described pressure regulator is connected with the zero wire electrode N of described power input socket, another input end of pressure regulator is connected through the firewire electrode L of described power switch and power input socket, two input ends of time schedule controller are connected with two output terminals of described pressure regulator respectively, and several described power output sockets are connected in parallel between two output terminals of time schedule controller.From the AC220V civil power of power input socket access, first through pressure regulator, change voltage, then carry out sequence switch control by time schedule controller, finally adjusted voltage is transported to power output socket, supply with light fixture to be measured and carry out timed on-off of power test.The power on/off that can carry out as required various modes by time schedule controller arranges, and makes light fixture automatically by setting, carry out timed on-off of power work, convenient test, and test job pattern flexibility and changeability, tests completely, improves the reliability of light fixture.
As preferably, input end of described time schedule controller is connected with the zero wire electrode of described power input socket, another input end of time schedule controller is connected through the firewire electrode of described power switch and power input socket, two output terminals of time schedule controller are connected with two input ends of described pressure regulator respectively, and several power output sockets are connected in parallel between two output terminals of described pressure regulator.From the AC220V civil power of power input socket access, first through time schedule controller, carry out sequence switch control, then change voltage by pressure regulator, finally adjusted voltage is transported to power output socket, supply with light fixture to be measured and carry out timed on-off of power test.The power on/off that can carry out as required various modes by time schedule controller arranges, and makes light fixture automatically by setting, carry out timed on-off of power work, convenient test, and test job pattern flexibility and changeability, tests completely, improves the reliability of light fixture.
As preferably, described time schedule controller adopts KG316T micro computer sequential control switch, described time schedule controller has a LCDs and seven that button is set, seven keys when button being set being respectively cancellation/resetkey, school, schools divide key, school week key, automatic/hand key, timing key and clock key.Arrange conveniently, mode of operation is various, uses flexibly.
As preferably, on described casing, be embedded with voltage table, two output terminals of voltage table and described pressure regulator are connected in parallel.Voltage table shows the output voltage of pressure regulator, regulates more convenient.
As preferably, on described casing, be embedded with a pilot lamp, pilot lamp and described power switch are connected in series.The switch that switches on power, pilot lamp is bright, indicates this device to switch on power.
As preferably, described power output socket has eight, four one rows form the right side that two rows are arranged on the rear panel of described casing, described power input socket is arranged on the lower left corner of cabinet rear panel, and the adjusting knob of described power switch, time schedule controller and pressure regulator is arranged on the front panel of casing.This device output total load must not be greater than 500 watts, and power output socket is provided with fuse overload is played a protective role.
The beneficial effects of the utility model are: can make light fixture to be measured be operated in different voltage, AC0~250V is electrodeless adjustable, and automatically by the power on/off time of setting, carry out work, convenient test, and test job pattern flexibility and changeability, tests completely, improves the reliability of light fixture.
Accompanying drawing explanation
Fig. 1 is a kind of circuit theory diagrams of test circuit in the utility model.
Fig. 2 is a kind of main TV structure schematic diagram of the present utility model.
Fig. 3 is a kind of backsight structural representation of the present utility model.
Fig. 4 is the another kind of circuit theory diagrams of test circuit in the utility model.
1. power input sockets in figure, 2. power output socket, 3. pressure regulator, 4. power switch, 5. adjusting knob, 6. time schedule controller, 7. voltage table, 8. pilot lamp, 9. rear panel, 10. front panel, 61. LCDs, 62. arrange button.
Embodiment
Below by embodiment, and by reference to the accompanying drawings, the technical solution of the utility model is described in further detail.
Embodiment 1: the time control regulating lamp proving installation of the present embodiment, and comprise casing and be installed on the test circuit in casing, casing is formed by connecting by base, upper cover, front panel 10 and rear panel 9.As shown in Figure 3, the lower left corner of the rear panel 9 of casing is provided with a power input socket 1, and the right side of the rear panel 9 of casing is provided with 2, eight power output sockets of eight power output sockets and is divided into two rows installation by four one rows.As shown in Figure 1, test circuit comprises pressure regulator 3, time schedule controller 6 and power switch 4, pilot lamp 8, an input end of the zero wire electrode N of power input socket 1 and pressure regulator 3 is connected, the firewire electrode L of power input socket 1 is connected with one end of pilot lamp 8 through power switch 4, another input end of the other end of pilot lamp and pressure regulator 3 is connected, two output terminals of pressure regulator 3 are connected with two input ends of time schedule controller 6 respectively, and be connected in parallel to a voltage table 7 between two output terminals of pressure regulator 3, eight power output sockets 2 are connected in parallel between two output terminals of time schedule controller 6.In the present embodiment, time schedule controller 6 adopts KG316T micro computer sequential control switch, as shown in Figure 2, when it has a LCDs 61 and seven that 62, seven of buttons are set button is set is respectively cancellation/resetkey, school key, school divide key, school week key, automatic/hand key, timing key and clock key.The adjusting knob 5 of time schedule controller 6, voltage table 7 and pressure regulator 3 is from left to right inlaid on the front panel 10 of casing successively, and pilot lamp 8 is inlaid in the first from left angle of front panel 10, and power switch 4 is inlaid in the lower right corner of front panel 10.
In the present embodiment, from the AC220V civil power of power input socket access, first through voltage device, change voltage, then carry out sequence switch control by time schedule controller, finally adjusted voltage is transported to power output socket, supplies with light fixture to be measured and carry out timed on-off of power test.
Embodiment 2: the time control regulating lamp proving installation of the present embodiment, as shown in Figure 4, test circuit comprises pressure regulator 3, time schedule controller 6 and power switch 4, pilot lamp 8, an input end of the zero wire electrode N of power input socket 1 and time schedule controller 6 is connected, the firewire electrode L of power input socket 1 is connected with one end of pilot lamp 8 through power switch 4, another input end of the other end of pilot lamp and time schedule controller 6 is connected, two output terminals of time schedule controller 6 are connected with two input ends of pressure regulator 3 respectively, eight power output sockets 2 are connected in parallel between two output terminals of pressure regulator 3, and be connected in parallel to a voltage table 7 between two output terminals of pressure regulator 3.All the other structures are with embodiment 1.
In the present embodiment, from the AC220V civil power of power input socket access, first through time schedule controller, carry out sequence switch control, then change voltage by voltage device, finally adjusted voltage is transported to power output socket, supplies with light fixture to be measured and carry out timed on-off of power test.
During work, power input socket is connected AC220V civil power, and respectively with eight light fixtures to be measured of eight power output sockets are connected.Turn on the power switch, pilot lamp is bright, and the adjusting knob of rotation pressure regulator, makes the test voltage requirement of the indicated voltage conforms light fixture of voltage table, and this voltage is that AC0~250V is electrodeless adjustable.
Whether correctly observe the clock that the LCDs of time schedule controller shows, when pressing clock key, school key, school divide key and school week key clock is transferred to current correct time.Key and well 1 ETAD expected time of arrival and departure regularly of school week key assignments are divided in key, school when pressing timing key, school, while again pressing timing key, school, key and well 1 pass time regularly of key assignments school week are divided in key, school, repeat above-mentioned steps, complete regularly and 2 open, regularly 2 close ... timing 16 is opened, regularly 16 settings of closing.Press clock key, stop timing is set, and gets back to clock running status.Press automatic/hand key, carry out automatic/hand setting, in the time of automatically, by setting timed on-off of power, in the time of manually, realize the hand switch of load is controlled.By cancellation/resetkey, cancel and setting, then by once recovering original setting.
The utility model output total load must not be greater than 500 watts, and power output socket is provided with fuse overload is played a protective role.
Use the utility model, can make light fixture to be measured be operated in different voltage, and automatically by the power on/off time of setting, carry out work, convenient test, test job pattern flexibility and changeability, tests completely, improves the reliability of light fixture.

Claims (7)

1. a time control regulating lamp proving installation, it is characterized in that comprising casing and being located at the test circuit in casing, on casing, be embedded with a power input socket (1) and several power output sockets (2), test circuit comprises pressure regulator (3), time schedule controller (6) and power switch (4), described power input socket (1), power switch (4), pressure regulator (3), time schedule controller (6) is connected successively with power output socket (2) or described power input socket (1), power switch (4), time schedule controller (6), pressure regulator (3) is connected successively with power output socket (2), several power output sockets (2) are connected in parallel, the adjusting knob (5) of pressure regulator (3) and described power switch (4), time schedule controller (6) is inlaid in respectively on described casing.
2. time control regulating lamp proving installation according to claim 1, the input end that it is characterized in that described pressure regulator (3) is connected with the zero wire electrode N of described power input socket (1), another input end of pressure regulator (3) is connected with the firewire electrode L of power input socket (1) through described power switch (4), two input ends of time schedule controller (6) are connected with two output terminals of described pressure regulator (3) respectively, and described several power output sockets (2) are connected in parallel between two output terminals of time schedule controller (6).
3. time control regulating lamp proving installation according to claim 1, the input end that it is characterized in that described time schedule controller (6) is connected with the zero wire electrode N of described power input socket (1), another input end of time schedule controller (6) is connected with the firewire electrode L of power input socket (1) through described power switch (4), two output terminals of time schedule controller (6) are connected with two input ends of described pressure regulator (3) respectively, several power output sockets (2) are connected in parallel between two output terminals of described pressure regulator (3).
4. according to the time control regulating lamp proving installation described in claim 2 or 3, it is characterized in that described time schedule controller (6) adopts KG316T micro computer sequential control switch, described time schedule controller (6) has a LCDs (61) and seven that button (62) is set, seven keys when button being set being respectively cancellation/resetkey, school, schools divide key, school week key, automatic/hand key, timing key and clock key.
5. according to the time control regulating lamp proving installation described in claim 1 or 2 or 3, it is characterized in that being embedded with voltage table (7) on described casing, two output terminals of voltage table (7) and described pressure regulator (3) are connected in parallel.
6. according to the time control regulating lamp proving installation described in claim 1 or 2 or 3, it is characterized in that being embedded with a pilot lamp (8) on described casing, pilot lamp (8) and described power switch (4) are connected in series.
7. according to the time control regulating lamp proving installation described in claim 2 or 3, it is characterized in that described power output socket (2) has eight, four one rows form the right side that two rows are arranged on the rear panel (9) of described casing, described power input socket (1) is arranged on the lower left corner of cabinet rear panel (9), and the adjusting knob (5) of described power switch (4), time schedule controller (6) and pressure regulator (3) is arranged on the front panel (10) of casing.
CN201420155956.4U 2014-04-02 2014-04-02 Time-control voltage-regulating light fixture testing apparatus Expired - Fee Related CN203870229U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420155956.4U CN203870229U (en) 2014-04-02 2014-04-02 Time-control voltage-regulating light fixture testing apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420155956.4U CN203870229U (en) 2014-04-02 2014-04-02 Time-control voltage-regulating light fixture testing apparatus

Publications (1)

Publication Number Publication Date
CN203870229U true CN203870229U (en) 2014-10-08

Family

ID=51651167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420155956.4U Expired - Fee Related CN203870229U (en) 2014-04-02 2014-04-02 Time-control voltage-regulating light fixture testing apparatus

Country Status (1)

Country Link
CN (1) CN203870229U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107449940A (en) * 2016-04-08 2017-12-08 Abb瑞士有限公司 Test block with the input of RJ45 types and accessory power outlet
CN107449941A (en) * 2016-04-08 2017-12-08 Abb瑞士有限公司 Test Block With Faraday Cage
CN112578758A (en) * 2020-12-24 2021-03-30 深圳市得一微电子有限责任公司 Multi-power-supply test control system and device
CN115219741A (en) * 2022-04-18 2022-10-21 浙江双宇电子科技有限公司 A test jig for lamps and lanterns multi-scheme detects

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107449940A (en) * 2016-04-08 2017-12-08 Abb瑞士有限公司 Test block with the input of RJ45 types and accessory power outlet
CN107449941A (en) * 2016-04-08 2017-12-08 Abb瑞士有限公司 Test Block With Faraday Cage
CN107449941B (en) * 2016-04-08 2022-01-25 泰连服务有限公司 Test block with Faraday cage
CN112578758A (en) * 2020-12-24 2021-03-30 深圳市得一微电子有限责任公司 Multi-power-supply test control system and device
CN112578758B (en) * 2020-12-24 2022-05-27 深圳市得一微电子有限责任公司 Multi-power-supply test control system and device
CN115219741A (en) * 2022-04-18 2022-10-21 浙江双宇电子科技有限公司 A test jig for lamps and lanterns multi-scheme detects

Similar Documents

Publication Publication Date Title
CN203870229U (en) Time-control voltage-regulating light fixture testing apparatus
WO2014187133A1 (en) Intelligent checking system for backup power supply automatic switching apparatus
CN104410549B (en) The test system and method for router
CN203396869U (en) Integrated test equipment
CN204348539U (en) A kind of switch with stand-by power supply and illumination
CN107192942B (en) It is a kind of portable to take the external breaker entry detection device of control electric energy meter
CN205140330U (en) Trouble analogue means is observed and controled in power supply
CN112213592A (en) Distributed terminal double-loop network self-healing transfer detection system and method thereof
CN108737005B (en) Multifunctional electronic clock system for digital campus
CN203932533U (en) A kind of Timing switch socket
KR102403333B1 (en) Automatic Supply Apparatus of Simulation DC Power with Variable Control
CN202735807U (en) Central control device of multimedia teaching room equipment
CN204515086U (en) The auto-action proving installation of automatic change over
CN203287718U (en) Product aging controller for LED (light-emitting diode)
CN103488220B (en) A kind of electric supply installation and method of supplying power to
CN102608367B (en) Step signal source
CN202305748U (en) Testing device for remote control motherboard of distribution automation terminal
CN201449545U (en) Equipment for intelligently detecting electronic control system programs
CN202066944U (en) Multi-chip integrated testing device
CN106742050B (en) power supply conversion logic circuit and implementation method thereof
CN104569711A (en) Method and testing device for open-short circuit experiment of electronic component
CN204215263U (en) Double-power controller verifying attachment
CN207424228U (en) Lamps and lanterns lighting testing equipment
KR100873164B1 (en) Analog timer
CN210864375U (en) Power on-off control equipment for laboratory

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141008

Termination date: 20160402