CN202849877U CN 201220546612 CN201220546612U CN202849877U CN 202849877 U CN202849877 U CN 202849877U CN 201220546612 CN201220546612 CN 201220546612 CN 201220546612 U CN201220546612 U CN 201220546612U CN 202849877 U CN202849877 U CN 202849877U
Authority
CN
China
Prior art keywords
split type
roadbed
road structure
type road
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220546612
Other languages
Chinese (zh)
Inventor
刘坡拉
李小和
赵勇
韦随庆
廖进星
姚建伟
陈德平
刘庆辉
詹志雄
周飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN 201220546612 priority Critical patent/CN202849877U/en
Application granted granted Critical
Publication of CN202849877U publication Critical patent/CN202849877U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a split type roadbed structure. The split type roadbed structure comprises a plurality of sections of roadbed units, each section of roadbed unit comprises a pile plank foundation, a roadbed wall and a tray, the roadbed wall is fixed on the pile plank foundation, the tray is fixed on the roadbed wall, and a slag stopping groove is arranged at the top of the tray. The split type roadbed structure has the advantages that the load bearing capacity is high, the occupied space is small, and safe operation of a newly built line and existing structures can be guaranteed.

Description

Split type road structure
Technical field
The utility model relates to the railway bed building field, relates in particular to a kind of split type road structure.
Background technology
Roadbed is the banded structure thing as track or road bed of building according to technical requirements.It also will bear train or vehicular load, thereby it is the important component part of whole railway except bearing itself ground deadweight and track or road surface gravity.When the construction of highway or railway is subject to other condition restriction, when the works such as the existing bridge of necessary next-door neighbour pass through, if adopt common soil subgrade, can produce lateral earth pressure to works such as existing bridges, and the bridge foundation cushion cap produced vertical pressure, thereby affect the safety of existing bridge.
In order to address the above problem, two kinds of methods are arranged usually.First method is to adopt the retaining structure closing slopes such as barricade, U-shaped groove.Second method is to adopt bridge to cross over.Yet, when adopting first method, because the size of described retaining structure itself takies certain space and described retaining structure can with stressed biography to shallow layer foundation, affect the basic safety of the works such as existing bridge.When adopting second method, because the bridge pier of described bridge, key dimension etc. are larger, and the construction technology relative complex, be close to existing bridge construction, can bring construction hidden danger.
Therefore, be necessary to provide a kind of split type road structure to overcome defects.
The utility model content
The purpose of this utility model provides a kind of split type road structure, takes up room little and can guarantee the safe operation of newly-built circuit and existing structure thing.
To achieve these goals, the utility model provides a kind of split type road structure, comprises more piece roadbed unit, every joint roadbed unit comprises pile plate foundation, roadbed wall and pallet, the roadbed wall is fixed on the pile plate foundation, and pallet is fixed on the roadbed wall, and the top of pallet is provided with gear tiny fragments of stone, coal, etc. groove.
Particularly, the bottom surface of gear tiny fragments of stone, coal, etc. groove is arranged with weathering.
Particularly, the gradient of weathering is 4%.
Particularly, the pallet both sides are provided with the spilled water hole of a plurality of lateral direction penetratings, are provided with gutter in the spilled water hole.
Particularly, the distance between adjacent two spilled water holes is 5 ~ 10m.
Particularly, be provided with successively waterproofing course, topping and railway ballast layer in the gear tiny fragments of stone, coal, etc. groove.
Particularly, the pallet both sides also are fixed with the sidewalk.
Particularly, pile plate foundation comprises loaded plate and the stake of many foundation, loaded plate be located at many foundation stake top and with the stake of many foundation be the integral type structure, the bottom surface of loaded plate is positioned at underground.
Particularly, the spacing of adjacent two pile bases is greater than 3m.
Particularly, be provided with the shrinkage joint between the adjacent two joint roadbed unit, the seam at shrinkage joint is wide to be 2 ~ 5cm, is provided with pitch hemp cut layer or waterproofing course in the shrinkage joint.
Compared with prior art, the split type road structure of the utility model is pile plate foundation, the combining form of roadbed wall and pallet, thereby, this combining form takes up room little, and during construction, road structure of the present utility model can unsettled leap contiguous structure with it, track or road surface load both can have been born, load is effectively transmitted to the ground deep, thereby, reasonably avoiding the phase mutual interference of construction period and later stage operation between the adjacent structure, and then, not only guaranteed construction and the operation security problem of newly built railway roadbed, and, existing buildings and basic safety thereof guaranteed.
By following description also by reference to the accompanying drawings, it is more clear that the utility model will become, and these accompanying drawings are used for explaining embodiment of the present utility model.
Description of drawings
Fig. 1 is the structural representation of the split type road structure of the utility model.
Fig. 2 is the position view of the split type road structure of the utility model and existing bridge pier.
The specific embodiment
With reference now to accompanying drawing, describe embodiment of the present utility model, similar element numbers represents similar element in the accompanying drawing.
As shown in Figure 1, the split type road structure of the present embodiment comprises more piece roadbed unit, and the length of every joint roadbed unit is 10 ~ 20m, is provided with the shrinkage joint between the adjacent two joint roadbed unit, the seam at shrinkage joint is wide to be 5cm, also is provided with pitch hemp cut layer or waterproofing course in the shrinkage joint 14.
Every joint roadbed unit comprises pile plate foundation 10, roadbed wall 13, pallet 14 and sidewalk 19.Pile plate foundation 10 specifically comprises loaded plate 12 and many foundation stake 11, and loaded plate 12 is located at many foundation stake 11 tops and is the integral type structure with many foundation stake 11, and the bottom surface of loaded plate 12 generally is positioned at below the Z-Z of ground.Particularly, foundation pile 11 adopts the above deposited reinforced concrete pile of C30, and the diameter of foundation pile 11 is more than or equal to 1m, and the spacing L of adjacent two pile bases 11 is generally greater than 3m, and the length that the top of foundation pile 11 is stretched in the loaded plate 12 is 0.5 ~ 1m.Loaded plate 12 adopts the above steel concrete of C30 to build.
Roadbed wall 13 is fixed on the loaded plate 12, and pallet 14 is fixed on the roadbed wall 13, and the end face of pallet 14 is provided with gear tiny fragments of stone, coal, etc. groove 15.The bottom surface of gear tiny fragments of stone, coal, etc. groove 15 is arranged with weathering 16, and the gradient of weathering 16 is 4%.Pallet 14 both sides are provided with the spilled water hole 17 of a plurality of lateral direction penetratings, and the distance between adjacent two spilled water holes 17 is 5 ~ 10m, and are provided with the PVC gutter in the spilled water hole 17.In addition, be provided with successively waterproofing course (not shown), topping (not shown) and railway ballast layer 18 in the gear tiny fragments of stone, coal, etc. groove 15.Particularly, roadbed wall 13 adopts the above plain concrete of C30 or slabstone concreting.Pallet 14 adopts the above steel concrete of C30 to build, and base plate thickness is 0.3 ~ 0.6m, highly exceeds tiny fragments of stone, coal, etc. pin 0.3m.
Sidewalk 19 is fixed on the both sides of pallet 14.The material of humanoid guidance tape, support and railing is consistent with common bridge with job practices.
With reference to figure 2, foundation platform 21 and the pile plate foundation 22 of existing bridge pier 20 are embedded in below ground, and the foundation pile 11 of the split type road structure of the present embodiment is embedded in underground, and the bottom of loaded plate 12 also is embedded in below ground.Loaded plate 12 is positioned at the top of foundation platform 21 and the pile plate foundation 22 of existing highway bridge pier 20, the foundation platform 21 of foundation pile 11 and existing highway bridge pier 20 and pile plate foundation 22 segment distance of being separated by, thereby, reasonably avoiding the phase mutual interference of construction period and later stage operation between the adjacent structure, construction and the operation security problem of newly built railway roadbed have not only been guaranteed, and, guaranteed existing buildings and basic safety thereof.
Abovely in conjunction with most preferred embodiment the utility model is described, but the utility model is not limited to the embodiment of above announcement, should contain various modification, equivalent combinations of carrying out according to essence of the present utility model.

Claims (10)

1. a split type road structure comprises more piece roadbed unit, it is characterized in that, every joint roadbed unit comprises pile plate foundation, roadbed wall and pallet, and the roadbed wall is fixed on the pile plate foundation, and pallet is fixed on the roadbed wall, and the top of pallet is provided with gear tiny fragments of stone, coal, etc. groove.
2. split type road structure as claimed in claim 1 is characterized in that, the bottom surface of gear tiny fragments of stone, coal, etc. groove is arranged with weathering.
3. split type road structure as claimed in claim 2 is characterized in that, the gradient of weathering is 4%.
4. split type road structure as claimed in claim 2 is characterized in that, the pallet both sides are provided with the spilled water hole of a plurality of lateral direction penetratings, is provided with gutter in the spilled water hole.
5. split type road structure as claimed in claim 4 is characterized in that, the distance between adjacent two spilled water holes is 5 ~ 10m.
6. split type road structure as claimed in claim 2 is characterized in that, is provided with successively waterproofing course, topping and railway ballast layer in the gear tiny fragments of stone, coal, etc. groove.
7. split type road structure as claimed in claim 1 is characterized in that, the pallet both sides also are fixed with the sidewalk.
8. split type road structure as claimed in claim 1 is characterized in that, pile plate foundation comprises loaded plate and the stake of many foundation, loaded plate be located at many foundation stake top and with the stake of many foundation be the integral type structure.
9. split type road structure as claimed in claim 8 is characterized in that, the spacing of adjacent two pile bases is greater than 3m.
10. split type road structure as claimed in claim 1 is characterized in that, is provided with the shrinkage joint between the adjacent two joint roadbed unit, and the seam at shrinkage joint is wide to be 2 ~ 5cm, is provided with pitch hemp cut layer or waterproofing course in the shrinkage joint.
CN 201220546612 2012-10-23 2012-10-23 Split type roadbed structure Expired - Lifetime CN202849877U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220546612 CN202849877U (en) 2012-10-23 2012-10-23 Split type roadbed structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220546612 CN202849877U (en) 2012-10-23 2012-10-23 Split type roadbed structure

Publications (1)

Publication Number Publication Date
CN202849877U true CN202849877U (en) 2013-04-03

Family

ID=47981094

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220546612 Expired - Lifetime CN202849877U (en) 2012-10-23 2012-10-23 Split type roadbed structure

Country Status (1)

Country Link
CN (1) CN202849877U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108103853A (en) * 2017-12-20 2018-06-01 芜湖润蓝生物科技有限公司 A kind of track traffic road structure
CN108222060A (en) * 2018-02-12 2018-06-29 中铁二院工程集团有限责任公司 High-speed railway, highway pile foundation joist buttress type pallet subgrade support retainer structure
CN109235155A (en) * 2018-09-17 2019-01-18 中铁二院工程集团有限责任公司 Railway high-filled embankment ancient cooking vessel formula structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108103853A (en) * 2017-12-20 2018-06-01 芜湖润蓝生物科技有限公司 A kind of track traffic road structure
CN108222060A (en) * 2018-02-12 2018-06-29 中铁二院工程集团有限责任公司 High-speed railway, highway pile foundation joist buttress type pallet subgrade support retainer structure
CN109235155A (en) * 2018-09-17 2019-01-18 中铁二院工程集团有限责任公司 Railway high-filled embankment ancient cooking vessel formula structure
CN109235155B (en) * 2018-09-17 2024-01-05 中铁二院工程集团有限责任公司 Tripod structure of railway high-filling embankment

Similar Documents

Publication Publication Date Title
CN201962558U (en) High-steepness side slope subgrade structure for mountainous area
Marshall et al. Understanding housing defects
CN101736692A (en) Construction technology for passenger railway line spanning existing railway cast-in-place box beam bracket
CN202543953U (en) Supporting structure for shallow tunnel in overpass operation
CN203452092U (en) T-shaped pile retaining wall
CN202849877U (en) Split type roadbed structure
CN102146676A (en) High-steep side slope subgrade structure for mountain area
CN103343532B (en) Pre-stressed anchor cable pile-slab wall
CN1580402A (en) Method for broadening mountainous road using overhanging tye structure
CN108222060A (en) High-speed railway, highway pile foundation joist buttress type pallet subgrade support retainer structure
CN105256682B (en) The buried lattice frame of pile and construction method for protecting elevated formation level
CN206828906U (en) A kind of temporary pavement bedding structure for Metro Deep Excavation
CN106498976A (en) A kind of inter-city passenger rail underpass of freeways open-cut group pushes up support and change method
CN205443976U (en) Prevent wind and hinder husky fence
CN108166395A (en) A kind of construction method that beam bridge is built across Business Line
CN202369930U (en) Door opening type bearing framed bent device for multiplayer concrete box girder
CN104652299B (en) Construction method is shifted out in the whole hole of a kind of existing bridges and culverts of electric railway
CN111395065A (en) Pile plate roadbed structure and railway roadbed
CN202482727U (en) Temporary road surface pavement structure for ultra-shallow burying excavation underground project
RU2453650C1 (en) Complex for construction of motor road on piles
CN1277998C (en) Anti-large deformation reinforcement method for railway and highway bridge in subsidence area
CN203729327U (en) Balance weight type reinforced soil composite structure retaining wall
CN202706039U (en) Foundation pit supporting structure for reforming tunnel in old urban area
Thomson et al. Jacked installation of underbridges
CN211815239U (en) Combined construction structure of underground road and ground bridge

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130403