CN202369930U - Door opening type bearing framed bent device for multiplayer concrete box girder - Google Patents

Door opening type bearing framed bent device for multiplayer concrete box girder Download PDF

Info

Publication number
CN202369930U
CN202369930U CN2011205603789U CN201120560378U CN202369930U CN 202369930 U CN202369930 U CN 202369930U CN 2011205603789 U CN2011205603789 U CN 2011205603789U CN 201120560378 U CN201120560378 U CN 201120560378U CN 202369930 U CN202369930 U CN 202369930U
Authority
CN
China
Prior art keywords
box girder
framed bent
door opening
design surface
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011205603789U
Other languages
Chinese (zh)
Inventor
林济
李冀清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CN2011205603789U priority Critical patent/CN202369930U/en
Application granted granted Critical
Publication of CN202369930U publication Critical patent/CN202369930U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a door opening type bearing framed bent device for design surfaces of a multiplayer concrete box girder. The door opening type bearing framed bent device comprises the design surface of an upper concrete box girder and the design surface of a lower concrete box girder and is characterized in that a cast-in-place beam framed bent is arranged under the design surface of the upper concrete box girder, and a door opening type framed bent is erected above the design surface of the lower concrete box girder, wherein the door opening type framed bent is composed of a row of steel pipes with two vertical ends and joist steel arranged at the top, reinforced concrete strip foundations are laid at the footing of the steel pipes, the joist steel is laid on a steel row formed by the transverse single joist steel along the longitudinal direction, and the distances between the joist steel are the distances of vertical rods of the cast-in-place beam framed bent arranged under the design surface of the upper concrete box girder. The door opening type bearing framed bent device provided by the utility model has the advantage that the upper cast-in-place box girder and the lower cast-in-place box girder can be simultaneously constructed, thereby one half of construction time is saved, and the construction progress of a cast-in-place box girder at an interchange section is greatly accelerated.

Description

The door opening formula bearing bent frame device that is used for multi-layer concrete case beam
Technical field
The utility model relates to a kind of door opening formula bearing bent frame device that is used for multi-layer concrete case beam.
Background technology
Along with the develop rapidly of urban construction, elevated road is as increasing being applied in the urban construction of a kind of mode of alleviating urban highway traffic pressure at present.Along with the development of elevated road, complicated multilayer, also increasing being applied in the urban construction of elevated bridge of multiple structure.In general, multilayer viaduct box girder construction is to construct according to principle from top to bottom, builds cast-in-place beam framed bent at the superiors place exactly; Utilize intensive vertical rod and ground supports below the cast-in-place beam framed bent, on the top of vertical rod, lay the template of concrete casting again, wire-tie and carry out concrete casting; Because the floor height of the overpass bridge the superiors that have is very high, therefore whole workload of building cast-in-place beam framed bent is very big, and the duration is also very long; And sometimes the duration very urgent, so after treating that the upper strata box girder construction finishes, reach the standard value of design after; Carry out the construction of lower floor's case beam again; Can cause the whole construction cycle to prolong greatly, therefore demand urgently existing construction is improved, carry out simultaneously so that the construction of multilayer viaduct case beam can realize levels.
Summary of the invention
The purpose of the utility model is can't carry out the existing problem of lower floor's box girder construction when solving the upper strata box girder construction of multilayer viaduct case beam in the prior art, and a kind of door opening formula bearing bent frame device that is used for multi-layer concrete case beam design surface is provided.The utility model is designed for the door opening formula bearing bent frame device of multi-layer concrete case beam design surface; Be included in upper strata concrete box girder design surface, lower-layer concrete case beam design surface; It is characterized in that: below the concrete box girder design surface of upper strata, be provided with cast-in-place beam framed bent; Above lower-layer concrete case beam design surface, set up door opening formula framed bent; Door opening formula framed bent is upright steel pipe by row two ends, and steel pipe top is provided with single i iron and constitutes, and is equipped with steel bar concrete strip basis at the footing of steel pipe; On the steel row that horizontal single i iron constitutes, longitudinally be equipped with i iron, the spacing of i iron is the vertical pole ' s span of the cast-in-place beam framed bent that is provided with of the below of upper strata concrete box girder design surface.It is characterized in that: arrange double steel bar in the steel bar concrete strip basis, press spacing pre-embedded steel slab below steel pipe of steel pipe.It is characterized in that: the vertical rod in the cast-in-place beam framed bent that the below of upper strata concrete box girder design surface is provided with is connected with joist with horizon bar adopts right-angle coupler; Other vertical rods of top rod member and below of vertical rod are connected adopts rotary buckle, other vertical rod to link to each other employing with vertical rod to clasp; Horizon bar connects employing to clasp; The spreading of bridging and adopt rotary buckle with being connected of vertical rod.The utility model has the advantages that two-layer cast-in-situ box girder can be constructed simultaneously up and down, saved the half the engineering time, thereby accelerated the construction speed of grade separation section cast-in-situ box girder greatly.
Description of drawings
Figure is the structural representation of the utility model.
Below in conjunction with accompanying drawing and construction embodiment the utility model is made detailed operation instruction.
The specific embodiment
Be included in upper strata concrete box girder design surface, lower-layer concrete case beam design surface among the figure; It is characterized in that: below the concrete box girder design surface of upper strata, be provided with cast-in-place beam framed bent; Above lower-layer concrete case beam design surface, set up door opening formula framed bent; Door opening formula framed bent is upright steel pipe by row two ends, and steel pipe top is provided with single i iron and constitutes, and is equipped with steel bar concrete strip basis at the footing of steel pipe; On the steel row that horizontal single i iron constitutes, longitudinally be equipped with i iron, the spacing of i iron is the vertical pole ' s span of the cast-in-place beam framed bent that is provided with of the below of upper strata concrete box girder design surface.It is characterized in that: arrange double steel bar in the steel bar concrete strip basis, press spacing pre-embedded steel slab below steel pipe of steel pipe.It is characterized in that: the vertical rod in the cast-in-place beam framed bent that the below of upper strata concrete box girder design surface is provided with is connected with joist with horizon bar adopts right-angle coupler; Other vertical rods of top rod member and below of vertical rod are connected adopts rotary buckle, other vertical rod to link to each other employing with vertical rod to clasp; Horizon bar connects employing to clasp; The spreading of bridging and adopt rotary buckle with being connected of vertical rod.
When building overpass bridge; When upper and lower layer concrete case beam needs construction synchronously, cast-in-place beam framed bent can below the concrete box girder design surface of upper strata, be built, so that the concrete spouting of upper strata concrete box girder; And below the place that intersects with lower-layer concrete case beam design surface; Can below the concrete box girder design surface above build door opening formula framed bent, support with the cast-in-place beam framed bent that upper strata concrete box girder design surface below is built, after the door opening formula framed bent on the concrete box girder design surface of below is built; Can carry out the construction of the cast-in-place beam framed bent of upper and lower layer concrete case beam simultaneously, shorten the duration of construction greatly.

Claims (3)

1. the door opening formula bearing bent frame device that is used for multi-layer concrete case beam; Be included in upper strata concrete box girder design surface, lower-layer concrete case beam design surface; It is characterized in that: below the concrete box girder design surface of upper strata, be provided with cast-in-place beam framed bent, above lower-layer concrete case beam design surface, set up door opening formula framed bent, door opening formula framed bent is upright steel pipe by row two ends; Steel pipe top is provided with single i iron and constitutes; Be equipped with steel bar concrete strip basis at the footing of steel pipe, on the steel row that horizontal single i iron constitutes, longitudinally be equipped with i iron, the spacing of i iron is the vertical pole ' s span of the cast-in-place beam framed bent that is provided with of the below of upper strata concrete box girder design surface.
2. by the described door opening formula bearing bent frame device that is used for multi-layer concrete case beam of claim 1, it is characterized in that: arrange double steel bar in the steel bar concrete strip basis, press spacing pre-embedded steel slab below steel pipe of steel pipe.
3. by the described door opening formula bearing bent frame device that is used for multi-layer concrete case beam of claim 1, it is characterized in that: the vertical rod in the cast-in-place beam framed bent that the below of upper strata concrete box girder design surface is provided with is connected with joist with horizon bar adopts right-angle coupler; Other vertical rods of top rod member and below of vertical rod are connected adopts rotary buckle, other vertical rod to link to each other employing with vertical rod to clasp; Horizon bar connects employing to clasp; The spreading of bridging and adopt rotary buckle with being connected of vertical rod.
CN2011205603789U 2011-12-29 2011-12-29 Door opening type bearing framed bent device for multiplayer concrete box girder Expired - Fee Related CN202369930U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011205603789U CN202369930U (en) 2011-12-29 2011-12-29 Door opening type bearing framed bent device for multiplayer concrete box girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011205603789U CN202369930U (en) 2011-12-29 2011-12-29 Door opening type bearing framed bent device for multiplayer concrete box girder

Publications (1)

Publication Number Publication Date
CN202369930U true CN202369930U (en) 2012-08-08

Family

ID=46593639

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011205603789U Expired - Fee Related CN202369930U (en) 2011-12-29 2011-12-29 Door opening type bearing framed bent device for multiplayer concrete box girder

Country Status (1)

Country Link
CN (1) CN202369930U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102889426A (en) * 2012-10-16 2013-01-23 中国十七冶集团有限公司 Method of roll line hydraulic pipeline system and rolling mill equipment foundation synchronization construction
CN103437279A (en) * 2013-08-29 2013-12-11 中交二公局第一工程有限公司 Overhead cast-in-place box beam pressure-bearing strut and construction technology thereof
CN109403169A (en) * 2018-10-26 2019-03-01 中国十七冶集团有限公司 A kind of interim door opening of municipal administration bridge construction
CN113585076A (en) * 2021-07-08 2021-11-02 中国建筑第六工程局有限公司 Construction method of overwater large-span double-layer cast-in-place beam

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102889426A (en) * 2012-10-16 2013-01-23 中国十七冶集团有限公司 Method of roll line hydraulic pipeline system and rolling mill equipment foundation synchronization construction
CN103437279A (en) * 2013-08-29 2013-12-11 中交二公局第一工程有限公司 Overhead cast-in-place box beam pressure-bearing strut and construction technology thereof
CN103437279B (en) * 2013-08-29 2015-10-21 中交二公局第一工程有限公司 Overhead cast-in-place box compression struts and construction technology thereof
CN109403169A (en) * 2018-10-26 2019-03-01 中国十七冶集团有限公司 A kind of interim door opening of municipal administration bridge construction
CN113585076A (en) * 2021-07-08 2021-11-02 中国建筑第六工程局有限公司 Construction method of overwater large-span double-layer cast-in-place beam

Similar Documents

Publication Publication Date Title
CN102979041B (en) Soft overhead reinforcing jacking method for construction of span box bridge of jacking block of underpass turnout group of railway
CN204000469U (en) A kind of pile formula box road structure
CN101215819B (en) Separated double-layer bridge-floor cable stayed bridge
CN102392536B (en) Construction method for long-span hanging vestibule type template support system
CN201962558U (en) High-steepness side slope subgrade structure for mountainous area
CN103215894B (en) Portable interim prestressed stretch-draw anchor block
CN107841953B (en) High-altitude oblique crossing Liang Doupo side span cast-in-situ section construction support and construction method
CN205295963U (en) Long span steel case back pushes away construction with bearing structure that transversely rectifies
CN106978777B (en) A kind of make-shift bridge device
CN104088221B (en) A kind of T-shaped plate girder precast segment unit based on steel truss and combined bridge deck
CN202369930U (en) Door opening type bearing framed bent device for multiplayer concrete box girder
CN105133484B (en) A kind of part earth anchor higher-lower tower cable-stayed bridge structure
CN102797223B (en) Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
CN102146676A (en) High-steep side slope subgrade structure for mountain area
CN206090275U (en) Assembled rectangular concrete -filled steel tube makes up truss bridge
CN205242278U (en) A triangle string basket method is hanged and is watered device for deck bridge construction
CN103967332B (en) The construction method of a kind of building site enclosing
CN103578346B (en) A kind of simply supported girder bridge teaching simulation structure
CN102493349B (en) Method for prefabricating and erecting box girders by using bailey beam
CN202509398U (en) Base support frame of simulation steel truss girder for assisting erection of main tower zone steel truss girder of cable stayed bridge
CN102392417B (en) Dual-cantilever bearing support structure for large steel pipe and installation method
CN202530364U (en) Inverted triangle pier simply supported or continuous bridge structure
CN203755171U (en) Bridge back-pulling bearing construction support
CN205115988U (en) Part earth anchor height tower cable -stay bridge structure
CN206034264U (en) Novel steel construction shelter bridge foundation structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SHANGHAI MECHANIZED CONSTRUCTION CO., LTD.

Free format text: FORMER NAME: SHANGHAI CITY MACHINERY CONSTRUCTION CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 201802 Jiading District Shunda Road, Shanghai, No. 615

Patentee after: Shanghai Mechanized Construction Group Co., Ltd.

Address before: 201802 Jiading District Shunda Road, Shanghai, No. 615

Patentee before: Shanghai Mechanized Construction Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120808

Termination date: 20161229

CF01 Termination of patent right due to non-payment of annual fee