CN1920185A - Construction method of green concrete - Google Patents

Construction method of green concrete Download PDF

Info

Publication number
CN1920185A
CN1920185A CN 200510093007 CN200510093007A CN1920185A CN 1920185 A CN1920185 A CN 1920185A CN 200510093007 CN200510093007 CN 200510093007 CN 200510093007 A CN200510093007 A CN 200510093007A CN 1920185 A CN1920185 A CN 1920185A
Authority
CN
China
Prior art keywords
concrete
construction method
stereoscopic graticule
green
green concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200510093007
Other languages
Chinese (zh)
Inventor
沈敏鑫
王振陆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 200510093007 priority Critical patent/CN1920185A/en
Publication of CN1920185A publication Critical patent/CN1920185A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The invention relates to a green concrete construction method, be used in river bank and upland protection, wherein it comprises: finishing slope; laying solid network at the upland; using steel bar and anchor nail to strengthen the solid network; laying concrete at the slope; plating mixed plant base material on the concrete; maintaining the plant. The invention can grow grass on the steel bar concrete protection slope, to hold water and soil.

Description

Construction method of green concrete
Technical field
The present invention relates to a kind of construction method of green concrete, be that stereoscopic graticule is established on the domatic upper berth that is to construct, again with reinforcing bar and the fixing three-dimensional rhombogen net of holdfast, and the concrete that rubble and high molecular polymer mix is layed on the stereoscopic graticule, to plant the spray of living base material and high molecular polymer and grass seeds again and plant on concrete water seasoning.
Background technology
By the bank protection of general hillside, lay cement concrete more than domatic going up greatly, domatic in the hope of strengthening, and prevent rain drop erosion, though these concrete slopes are strengthened domatic and prevented rain drop erosion, domatic is the artificialization face picture of baldness, destroys the ecology of the Nature.For improving above-mentioned shortcoming, known job practices has reserves the hole on concrete revetment, for Turf Culture; Also have on concrete revetment, nail is established the grass planting bag separately, in the hope of the green concrete bank protection.Though on be set forth on the concrete revetment plantation that the practice of reserving the hole can make things convenient for turf, its hole of reserving still can be subjected to rain drop erosion, and then influences the steadiness in concrete lake; And establish the grass planting bag in the concrete revetment nail, though easy construction can cause the damage of concrete revetment, and the intensity of destruction concrete revetment.
The inventor is in view of the disappearance of above-mentioned concrete revetment, is think and the idea of improvement invention, satisfies being engaged in addition improvement design of this skill experience for many years, and then proposes the present invention, and the phase is with usability on the lifting industry.
Summary of the invention
The purpose of this invention is to provide a kind of construction method of green concrete, can not reduce concrete intensity again by the green concrete bank protection.
According to an aspect of the present invention, provide a kind of construction method of green concrete, comprise step:
A) whole slope;
B) establish stereoscopic graticule on sloping upper berth;
C) reinforce stereoscopic graticule with reinforcing bar and holdfast;
D) lay concrete completing on the slope of stereoscopic graticule;
E) spray is planted mixing and is planted living base material on concrete;
F) plant to give birth to and bring up and protect.
The method according to this invention, its beneficial effect are to grow real glossy and green grass seeds on the reinforced concrete revetment of powerful structure having, and make it have greening, beautify the effect of view, and the effect of water and soil conservation is arranged again.
Description of drawings
Fig. 1 is a stereoscopic graticule structural representation of the present invention,
Fig. 2 is that stereoscopic graticule of the present invention sets up the enforcement schematic diagram.
Fig. 3 is that concrete of the present invention is laid schematic diagram.
Fig. 4 of the present inventionly plants living base material and mixes spray and plant schematic diagram.
Fig. 5 is that of the present invention arranging finished schematic diagram.
The critical element symbol description:
10: stereoscopic graticule
20: reinforcing bar
30: holdfast
40: concrete
50: plant living base material
The specific embodiment
About detailed content of the present invention and technological means, enumerate specific embodiment now, and conjunction with figs. is described as follows:
Sincerely see also shown in Fig. 1 and 2
The present invention is a kind of construction method of green concrete, refers to a kind of bank protection construction method of green concrete such as rivers and creeks dyke, hillside that are implemented on especially, and its detailed steps and method are as follows:
One, whole slope
Domatic with desire construction revised smooth-goingly, and the stone, the foreign material that protrude removed, and after the loosening native stone removal, the domatic compacting of watering.
Two, lay stereoscopic graticule 10
Stereoscopic graticule 10 is established on domatic upper berth after compacting.Wherein, stereoscopic graticule can be three-dimensional rhombus net, as shown in Figure 1, also can be other shapes.
Three, reinforcing bar 20 is reinforced with holdfast 30
In the domatic reinforcing bar 20 of binding of the appropriate stereoscopic graticule 10 in shop, in addition type holdfast 30 is reinforced again.
Four, concrete 40 is laid
With the concrete 40 that rubble and high molecular polymer mix, be layed in and complete on stereoscopic graticule 10 domatic, as shown in Figure 3.
Five, planting living base material 50 mixing sprays plants
After concrete is laid one week of maintenance, will plant the living base material 50 of planting that living base material 50 mixes with high molecular polymer and grass seed mix, and spray and plant on concrete 40 surfaces, as shown in Figure 4.
Six, plant to give birth to and bring up and protect
Planting needs wet curing after living base material 50 sprays are planted.
In above-mentioned, it is domatic that desire is constructed, and the slope tiltedly must not be vertical, is 90 degree, or angle is greater than 90 degree, the smooth-going and compacting of watering with domatic correction.
In the domatic thickness of going up the stereoscopic graticule of laying 10 is 2 to 3 millimeters, and the mesh of stereoscopic graticule 10 is 3 to 8 centimetres and takes advantage of 3 to 8 centimetres, take advantage of 5 centimetres to be the best with 5, stereoscopic graticule 10 is bound reinforcing bar 20 supplemental support of 10 millimeters of diameters again and, the spacing in length and breadth of each reinforcing bar 20 respectively is 1.5 to 2.5 meters, circular holdfast 30 with 13 millimeters of diameters hammers in the native wall again, holdfast can be earlier with after the boring, hammer into Tu Bizhong again, and use rock must be admittedly with cemented in native wall, with stereoscopic graticule 10 be fixed in domatic on, this holdfast 30 long 45 to 75 centimetres, it is every square metre average 2 that holdfast 30 is used quantity.
Stereoscopic graticule 10 fixing appropriate after, with rubble and comprise concrete 40 that cement, accelerating admixture, structure-reinforced dose high molecular polymer mix in mixer, fully mix stir after, coagulate machine with concrete conveyer or spray, concrete 40 is layed in completes on stereoscopic graticule 10 domatic, thickness is 8 to 15 centimetres, and one week of water seasoning.
After concrete 40 is laid one week of maintenance, the living base material 50 of planting of organic fiber, wood chip, organic fertilizer be will comprise again and water-loss reducer, glutinous agent, cellulosic organic high molecular polymer and grass seed mix comprised, fully mixing the back spray with mixer plants on the surface of concrete 40,3 to 5 centimetres of thickness, plant living base material 50 sprays and plant back about 1 to 2 months need wet curings, but Yu Shuizhong dissolving fertilizer and glutinous agent during wet curing, grow to Deng grass seeds and can let alone back to nature ecology more than 3 centimetres, as shown in Figure 5.
In sum, construction method of green concrete of the present invention is laid in domatic the going up of construction; Stereoscopic graticule 10, and with the fixing stereoscopic graticule 10 of reinforcing bar 20 and holdfast 30, the concrete 40 that mixes with rubble and high molecular polymer is layed on the stereoscopic graticule 10, to plant living base material 50 sprays with high molecular polymer and grass seeds again and plants on concrete 40, make on the concrete 40 of bank protection and grow grass seeds, and afforest, beautify the natural, ecological view, and take the effect of water and soil conservation, the value of outstanding tool natural, ecological worker method industry.

Claims (10)

1, a kind of construction method of green concrete is characterized in that comprising step:
A) whole slope;
B) establish stereoscopic graticule on sloping upper berth;
C) reinforce stereoscopic graticule with reinforcing bar and holdfast;
D) lay concrete completing on the slope of stereoscopic graticule;
E) spray is planted mixing and is planted living base material on concrete;
F) plant to give birth to and bring up and protect.
2, construction method of green concrete as claimed in claim 1, the mesh that it is characterized in that this stereoscopic graticule are 3 to 8 centimetres and take advantage of 3 to 8 centimetres that the thickness of this stereoscopic graticule is 2 to 3 millimeters.
3, construction method of green concrete as claimed in claim 1, it is characterized in that this stereoscopic graticule binds reinforcing bar with supplemental support, this stereoscopic graticule hammers in the native wall with holdfast, be fixed in domatic on, the diameter of this reinforcing bar is 10 millimeters, and each reinforcing bar spacing in length and breadth respectively is 1.5 to 2.5 meters, this holdfast hammers into Tu Bizhong after can holing earlier again, and use rock must be admittedly with cemented in native wall, it is every square metre average 2 that 45 to 75 centimetres of this holdfasts, holdfast are used quantity.
4, construction method of green concrete as claimed in claim 1, the concrete that it is characterized in that this laying are the concrete that rubble and high molecular polymer mix, in mixer, fully mix stir after, concrete is layed in completes on stereoscopic graticule domatic again.
5, construction method of green concrete as claimed in claim 4 is characterized in that this high molecular polymer comprises mud, accelerating admixture, structure-reinforced dose mixture.
6, construction method of green concrete as claimed in claim 4 is characterized in that this is layed in the concrete of stereoscopic graticule on domatic, thick 8 to 15 centimetres.
7, construction method of green concrete as claimed in claim 1 is characterized in that this plants living base material and further mix organic high molecular polymer and grass seed mix, fully mixes the back spray in mixer and plants on concrete surface.
8, construction method of green concrete as claimed in claim 7 is characterized in that this plants living base material and comprise organic fiber, wood chip, organic fertilizer.
9, construction method of green concrete as claimed in claim 7 is characterized in that this organic high molecular polymer comprises water-loss reducer, glutinous agent, cellulose.
10, construction method of green concrete as claimed in claim 7 is characterized in that this spray plants concrete thick 3 to 5 centimetres of the living base material of planting.
CN 200510093007 2005-08-24 2005-08-24 Construction method of green concrete Pending CN1920185A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200510093007 CN1920185A (en) 2005-08-24 2005-08-24 Construction method of green concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200510093007 CN1920185A (en) 2005-08-24 2005-08-24 Construction method of green concrete

Publications (1)

Publication Number Publication Date
CN1920185A true CN1920185A (en) 2007-02-28

Family

ID=37778015

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200510093007 Pending CN1920185A (en) 2005-08-24 2005-08-24 Construction method of green concrete

Country Status (1)

Country Link
CN (1) CN1920185A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102628261A (en) * 2011-05-27 2012-08-08 上海嘉洁生态型混凝土草坪有限公司 Constructing method of artificial parent ecological layer
CN103321229A (en) * 2013-05-14 2013-09-25 李尚喜 Height increasing measure and construction for mountains
CN103362132A (en) * 2013-07-26 2013-10-23 六蜂王(石狮)环保建材有限公司 Construction method of cast-in-site planting concrete revetment
CN105625443A (en) * 2016-03-06 2016-06-01 广西建工集团第五建筑工程有限责任公司 High-steep soil nail grass planting slope protection structure system and construction method thereof
CN109258322A (en) * 2018-08-20 2019-01-25 中国水利水电第十四工程局有限公司 A kind of interim multiple green construction method of slope plant grass

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102628261A (en) * 2011-05-27 2012-08-08 上海嘉洁生态型混凝土草坪有限公司 Constructing method of artificial parent ecological layer
CN102628261B (en) * 2011-05-27 2014-04-30 上海嘉洁生态科技有限公司 Constructing method of artificial parent ecological layer
CN103321229A (en) * 2013-05-14 2013-09-25 李尚喜 Height increasing measure and construction for mountains
CN103362132A (en) * 2013-07-26 2013-10-23 六蜂王(石狮)环保建材有限公司 Construction method of cast-in-site planting concrete revetment
CN103362132B (en) * 2013-07-26 2016-08-24 六蜂王(石狮)环保建材有限公司 A kind of construction method of cast-in-place greening concrete protective slope
CN105625443A (en) * 2016-03-06 2016-06-01 广西建工集团第五建筑工程有限责任公司 High-steep soil nail grass planting slope protection structure system and construction method thereof
CN109258322A (en) * 2018-08-20 2019-01-25 中国水利水电第十四工程局有限公司 A kind of interim multiple green construction method of slope plant grass

Similar Documents

Publication Publication Date Title
CN107963838B (en) Ecological spray anchor slope protection structure and method
CN104310905B (en) Slope of highway silt firming agent and preparation method thereof
CN102359113A (en) Integrally-cast cement pervious concrete ecological protection slope and construction method thereof
CN111005393B (en) Slope protection structure for repairing landslide body by using live tree piles and construction method
CN101401513A (en) Ecological recovery technique for bamboo splits grid
CN1920185A (en) Construction method of green concrete
CN105297570A (en) Special soil subgrade structure and construction method thereof
CN102677682A (en) Ecological slope protection structure and construction method thereof
CN101089299A (en) Cement slope ecological recovery method
CN101058973A (en) Permeable block, manufacturing method and construction method thereof
CN112544350A (en) Construction method for protecting side slope of ecological grass planting roadbed in geocell
CN111593748A (en) Ecological protection structure of broken rock abrupt slope and construction method thereof
CN108385617B (en) Cotton stalk fiber soil slope reinforcement system and construction method thereof
CN110679226A (en) Construction method combining dredger fill improvement and planting hole improvement
CN1699701A (en) Method for slope reinforcement
CN1540108A (en) Method and equipment for protecting and greening side slope
CN111484278A (en) Ecological concrete, ecological protection slope and construction method of ecological protection slope
KR101035264B1 (en) The method using soil mixture layers reinforced by fibrillated fibers for the creation of shore protection for vegetation
CN114215003B (en) Construction method of water and soil conservation ecological system during construction of landscape topography in sea entrance area
CN110419373B (en) Vegetation recovery method for treating slope by using high-steep rock quality and concrete
KR20110028801A (en) Planting consturuction using the straight bamboo
CN208009448U (en) A kind of mixed bank protection barricade brick of ecology plant
CN113089693A (en) Measure for ecological slope protection of abrupt-slope bermuda grass and preparation method of anti-abrupt plant-growing concrete
CN202214733U (en) Integrally-cast cement water-permeable concrete ecological slope protection
JP2020031595A (en) Slope spraying greening method and vegetation base material

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication